The document provides guidelines for numbering drawings and documents for a construction project. It explains that the numbering can include: 1) A discipline code, system code, year, supplier/contractor name, and contractor project job number for main contractor drawings. 2) For sub-vendor drawings released by the main package supplier/contractor, the numbering includes: a discipline code, vendor identifier, technical specification number, discipline code, document number, drawing/document size, and revision number. 3) An example construction project document number is provided as M26-SE-12-CO-M1, rev01 for a main contractor drawing and M26-SE-V-06-E25-A

Uploaded by

kumar
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
204 views

Document Numbering System

The document provides guidelines for numbering drawings and documents for a construction project. It explains that the numbering can include: 1) A discipline code, system code, year, supplier/contractor name, and contractor project job number for main contractor drawings. 2) For sub-vendor drawings released by the main package supplier/contractor, the numbering includes: a discipline code, vendor identifier, technical specification number, discipline code, document number, drawing/document size, and revision number. 3) An example construction project document number is provided as M26-SE-12-CO-M1, rev01 for a main contractor drawing and M26-SE-V-06-E25-A

Uploaded by

kumar
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

X=0, 1, 2..

XX 123 X 123 X1 REV X

Till Approval

X= 00, 11, 22As built drawings Discipline M or E or I or C (Two Word) System under Discipline (Two Digits)

Year of Document Generation (Two Word) Supplier / Contractor Name (Two Words) Contractors Project Job No. (Three Digits)

XX 123 X 123 X1 REV X

M26 SE 12 CO M1 01

Contractor Mecwel Project job number For e.g. Siemens for turbine and Aux 2012 Control oil system Mechanical first doc. Rev no.01

The document number can be written as M26-SE-12-CO-M1, rev01

SUB VENDORs DRAWINGS released by PACKAGE SUPPILER / CONTRACTOR

XX 123 VX 12 123 X1 REV X

X=0, 1, 2..

Till Approval

X= 00, 11, 22As built drawings Dwg/Doc size-A0 / A1 /A2 /A3 /A4 (Three Digits) Dwg/ Doc No (Three Digits) Tech. Spec. No.=>2 digit No i.e. 0 to99 Vendor Drgs: V (One Word) Discipline M or E or I or C (One Word) VM or VE or VI Supplier / Contractor Name (Two Words) Contractors Project Job No. (Three Digits)

XX 123 VX 12 123 X1 REV X

M26 SE V 06 E25 A3 01

Contractor Mecwel Project job number For e.g. Siemens for turbine and Aux Vendor Drawing shall be marked with symbol V For example out of 12 packages we can assign Tech spec no.06 for Cooling water system Electrical document no.25 A3 size paper Rev no.01

M26-SE-V-06-E25-A3, Rev01 Sub vendor Document number