Installation BubbleDeck
Installation BubbleDeck
Page 1 of 1
August 2006
Version: 1
Content: Site Erection & Installation information Type A Filigree Element Test Report Summary
Technical Papers
Acoustic Performance
Disproportional Collapse
Develop together programme for production / installation drawings, manufacturing and delivery to site Preparation by us of a detailed programme for production / installation drawings, manufacturing and delivery to site. Review by you and issuing to us programme approval. Confirm to us your planned sequence of erecting the BubbleDeck elements on site. Confirm to us your requirements for any phasing, day joints, and service riser holes above 250mm diameter you want pre-forming in the factory. Planning by you of fixed / mobile crane provision and location providing adequate capacity to lift heaviest elements. Advising us of your arrangements for site access and any access restrictions / procedures. Providing our advice on technical and practical construction issues. Selection by you of preferred propping system and arranging propping beam layout to be issued to us for review and comment. Preparation by us of production / installation drawings (projects above 2,000 m2 in phases as programmed) and submission to you for review and formal sign-off approval. Preparation by us of Quality and Delivery Control forms showing planned loading of elements onto our transport trailers, submission to you for review and approval.
Planning erection of Slab Elements Prior to us commencing preparation production / installation drawings (see Stage 7 above) you must confirm to us your planned sequence of erecting the BubbleDeck elements on site during construction. This sequence has to be incorporated on our drawing element numbering at an early stage and passed to our factory in order to ensure a) the correct element edge profiles are manufactured, and b) plan the sequence of manufacturing / transporting elements. a) Element Edge Profiles: Longitudinal edges of elements require different detailing dependant upon their position see drawing below showing slab edge cross-sections element as planned. It is Page 3 of 12
important the large splay shown on the right hand longitudinal edge is present at every junction between two elements to provide adequate concrete cover, for fire resistance and durability performance, to the loose reinforcement splice bars laid across the elements joints on top of the precast concrete layer. Direction of Site Erection
b) Manufacturing and Transporting Sequence: We will programme the order of manufacturing elements and loading of the elements onto our transport to reflect, as closely as practically feasible, your planned erection sequence. However, for transport efficiency and safety, some elements have to be loaded on the transport trailers out of sequence to their erection order (e.g. small elements have to be stacked on top of larger elements), in which case these elements can be temporarily lifted off and stored elsewhere on site while the transport trailer is unloaded. The order of loading elements onto the transport trailers will be shown on our Quality and Delivery Control form. Formal drawing approval prior to manufacture Once we have received your production / installation drawings sign-off we can then implement manufacture of materials and the elements and be ready to commence site deliveries of elements and loose rebar within 4 weeks time. We appreciate progress of construction on site can be affected by many external factors including exceptionally adverse weather and other events beyond your control. If you need to change the programming of BubbleDeck deliveries and/or manufacture in response to such events please immediately inform us so we can then re-programme to your requirements. Once BubbleDeck trailers have left our factory we regret we are unable to defer site delivery without passing on additional transport and storage / trailer hire costs. We have even advanced deliveries to keep up with quicker than expected progress constructing BubbleDeck slabs on site. BubbleDecks Construction Package As part of our service we will supply you with the following construction information, advice, products and assistance:Project Stage BubbleDeck Design Service / Product Engineering Design of BubbleDeck floor slabs & drawings. Submitting design to you for review and sign-off. Liaison with you about any checking engineer / Approved Inspector queries and providing further information as required. Page 4 of 12
Construction Planning
Preparation of manufacturing and construction drawings comprising i) Element layout plan, ii) Loose bottom reinforcement (site installation), iii) Loose top reinforcement (site installation), iv) Bubble pattern v) Pre-cast reinforcement (incorporated into elements at factory). Submitting drawings to you & Consultants for review and sign-off. Preparing programme for manufacture and supply of products to site, agreeing with you and placing orders for materials and manufacturing. Preparation of bar bending schedules for loose reinforcement.
Manufacturing Product Loose Reinforcement Site Delivery Site Support Site Inspections Insurance / Guarantees
Providing site operatives with product induction seminar. Providing our advice on technical and practical construction issues. BubbleDeck Site Erection and Installation Manual. BubbleDeck Health & Safety Policy. Quality and Delivery Control Forms. Manufacture of filigree elements comprising top / bottom mesh reinforcement / additional bar reinforcement / plastic bubble void formers / 60mm pre-cast concrete layer. Manufacturing and supplying all loose reinforcement required to complete BubbleDeck slabs. Monitoring and arranging BubbleDeck Filigree Elements & loose reinforcement delivery, on time, using between 8 metre to 13.6 metre long flatbed trailers. Technical advice and guidance to yourselves and site operatives on site installation & construction works. Site inspections of BubbleDeck installation & loose reinforcement checking prior to casting of in-situ concrete. Following completion of works on site and account settlement entering into suitable Collateral Warranty/s (subject to wording acceptable to our Insurers) as may be required and provision of our Professional Indemnity & Public Liability Insurance cover.
Stage 1 Erect Temporary Propping During erection each slab must be placed on suitable temporary propping beams arranged in parallel rows mounted on props sufficient to adequately support the weight of the pre-cast filigree elements plus the loose reinforcement fixed on site, concrete poured on site and all other site construction loads applied during final pouring of the concrete topping and curing of the slab. The The maximum distance between propping beams must not be greater than 1.8 metres maximum distance of the propping beams from slab edges must be as follows: from an edge where a slab is supported on brick or concrete walls 300mm from an edge next to construction tolerance joints 200mm
Propping beams must be at right angles to the direction of the reinforcement girders pre-cast in the element. Normally the girder reinforcement is placed parallel to the length of each slab but this must always be checked against the manufacturing and installation drawings. The propping beams, and individual props below, must form a stable platform prior to placing filigree elements onto them and maintained stable during casting of the site concrete. Important: Removal of the temporary propping is NOT allowed before each slab is cured sufficient to support its own weight and temporary construction loads. Page 5 of 12
Typical cross-section of temporary propping system Back-Propping When consecutive floor slabs within one block are to be constructed above each other either:- a) the slab below the one being constructed must be back-propped, or alternatively b) each completed slab must be self-supporting within the maximum allowed deflection. Option a) Prior to erecting propping for the next, subsequent, slab above the completed slab remove the propping from below the completed slab and erect back-props at 1.8m intervals (without parallel beams) at either mid-span or third-span, dependant upon length of spans involved. Option b) Prior to erecting propping for the next, subsequent, slab above loosen the props below the completed slab, to allow the floor to reach its maximum deflection, and then tighten the props again. This is to ensure additional loads from the slab being erected above is taken on its own props rather than adding to loads onto the floor directly below, avoiding weight accumulation from consecutive floors placing unnecessary strain on props and other construction elements.
Stage 2 Delivery, Offloading and Lifting Elements Site Delivery We deliver the elements on flatbed trailers typically between 12m to 13.6m long, excluding drivers cab. The filigree elements will be stacked on top of each other up to a maximum 2.1 metres overall height. Page 6 of 12
For example, with BD280 slabs there will be maximum 7 layers of slabs, with a transport height of 250mm each plus wooden packers typically 50mm deep separating each element, making an overall height of 2.1 metres above the trailers bed. Each individual load will be planned so the weight of a load will be a maximum 25.3 Tonnes and you must provide suitably hard and level access for our delivery transport to reach the offloading position you have determined. Important: Upon arrival of the delivery trailers on site it is your responsibility to carefully inspect the filigree elements for quality and to ascertain any damage that has been incurred during transport. Any damage to the filigree elements, or other unacceptable characteristics, must be reported by you to us by entering the details on our Quality and Delivery Control Form and faxing this back to our Head Office within 2 hours of trailer arriving on site. Once the elements have been lifted off the trailer we may be unable to determine when any damage occurred and in this event we cannot accept responsibility. Following your inspection the delivery driver will require you to sign the Quality and Delivery Control Form to confirm you have received the elements, which will be retained by him / her for our records. After removing all the filigree elements from the flatbed trailer the wooden transport packing beams / blocks must be replaced back onto the trailer before it leaves site, for return to our factory and re-use. Any transport materials that are not returned to our transport operator will be contra-charged by us to your account.
Offloading Filigree Elements It is your responsibility to provide attendance and adequate mechanical equipment (fixed or mobile crane with minimum 6 Tonne lifting capacity) for offloading elements from the trailers upon their arrival at site. For optimum working efficiency we recommend you plan site operations to allow the filigree elements to be lifted off the trailers and moved straight into their final position on the temporary propping. However, for transport efficiency and safety some elements are loaded onto the trailer out of sequence to their erection order, in which case or in the event of site circumstances preventing final placing the filigree elements can be temporarily stored elsewhere on site. The elements must be transversely supported on timber packers laid between the bubble rows (sat on the top reinforcement mesh) at maximum 1.8 metres centres resting on flat, level, ground and protected from soiling by mud, dirt, or other materials. Elements can be stacked on top of each other to a maximum 7 layers high. While we will organise and plan deliveries in accordance with your programme as earlier agreed with us (refer to Pre-construction Planning above) we are unable to accept any responsibility for any delays with deliveries or construction progress arising from events outside our control such as unexpected access restrictions or force majeure. Lifting and Placing Filigree Elements The filigree elements must ONLY be lifted by the lattice beam girder reinforcement. Lifting hooks must be attached under the upper angles of the girder reinforcement diagonals. Lifting hooks must NEVER be attached to the upper reinforcement mesh as this would be unsafe.
Page 7 of 12
It is your responsibility to organise and provide suitable lifting equipment All lifting equipment for must be tested and certified capable of lifting a minimum of 6 Tonnes, appropriate for the purpose as described below, and must meet all legal health and safety requirements. Each individual element requires the use of EIGHT lifting hooks, in 2 parallel rows of 4 hooks each attached around the lattice girders positioned approx. 1/5 of the total element length in from each end. The upper part of the hoisting system (4 suited chains) must be at least 6 metres minimum in length. Chain branches to the eight lifting hooks must be equal lengths. When in use, care should be taken that lifting forces are equal at each lifting hook point and the element remains horizontal during lifting. Before lifting attach suitable ropes at two opposite corners of the element for guiding element into position on the propping beams
Positioning of Filigree Elements on Propping It is important the elements are lifted into position in the planned erection system, and care is taken with correct positioning of the elements. Each element must be positioned the correct way round (often obvious from position of column cut outs and building shape, but please refer to element installation drawings) so the top chamfer along the longitudinal edge is butted up to the adjacent elements vertical longitudinal edge. Adjacent elements must NOT have their top chamfers facing together. Important: During final positioning of the elements ensure the bubble pattern between adjacent elements are aligned as shown on the installation drawings, so the spaces between bubble rows on adjacent elements line to facilitate inserting splice reinforcement across the element joints. For quick installation of the bottom splice reinforcement we recommend when the first element is in final position the bottom splice bars are temporarily slid fully in between the bubble rows on top of the precast concrete layer before the adjacent element is placed. At a later stage please remember to slide the bottom splice bars back across the element joint between the bubble rows in the adjacent element, so the bars are finally positioned half in one element and half in the adjacent element prior to concreting. Site Adjustment of Filigree Elements The filigree elements are designed and manufactured to suit the buildings configuration and column / wall layout. They arrive on site with cut-outs / recesses / steps for column or wall positions (including a 100mm shear zone margin between r.c. columns / walls and the pre-cast concrete layer) and larger service holes already formed, therefore they should not require any site adjustment. However it has been known for columns to be erected out of position on site and in this unusual event it is possible to carefully alter the filigree element with a disc cutter to maintain the 100mm shear zone margin between r.c. columns / walls and the elements pre-cast concrete biscuit. Important: The upper and diagonal bars in the lattice beam girder reinforcement must NOT be cut on site as they have an important structural function both during lifting and once in place.
Page 8 of 12
Cut-Outs, Recesses and Service Holes During the manufacturing process polystyrene void formers are fixed in these locations to create areas without any concrete bottom biscuit. During erection of the elements these are quickly broken out with a suitable mallet. Stage 3 - Fixing Loose Reinforcement. We provide site installation drawings for reinforcement fixed at the bottom of the slab (directly on top of the pre-cast concrete biscuit formwork without spacers or on top of site shuttering on spacers) and reinforcement fixed at the top of the slab (directly on top of the top mesh reinforcement), together with accompanying bar bending schedules. These must be studied and closely followed at all times, if you have any question please call our site support officer or Head Office for assistance. The sequence for fixing loose reinforcement is at your discretion, however we recommend the following procedure is adopted:Typical Reinforcement Type 1. Bottom Joint Splice bars Installation / Fixing Procedure Inserted loose between every bubble directly on top of the precast concrete biscuit permanent formwork. If they have been inserted into one element during lifting elements into position, as we recommend, then simply slide the bars across the joint between adjacent elements to sit with equal lengths both sides of the joint between elements. Inserted loose between bubbles in positions shown on drawings across holes, openings and returns in slabs where applicable Where applicable assemble bars into cages and fix between and / or around columns (if shown on drawings) Slide hairpins in between bubble rows and slide in top / middle / bottom edge bars around slabs perimeter, tying to hairpins as shown on drawings Installation / Fixing Procedure (cont.) Insert bottom bars across columns directly on top of the pre-cast concrete bottom formwork. Fix bars over top mesh reinforcement (between the bubbles) across and around column heads as shown on drawings, tying in place to mesh.
2. Bottom Shear bars 3. Beam Strips within slab depth 4. Perimeter Hairpins / Bars Typical Reinforcement Type (cont.) 5. Column Shear Reinforcement
Note: where shear studs or shear rails have been pre-cast into element at factory there may not be any bars to be fixed on site. 6. Top Joint mesh / bar Purpose made mesh sheets are placed with the bars between bubble reinforcement rows and tied in place equally across the joint between adjacent elements. In certain locations, for engineering reasons, splice bars will be placed equally across the element joints between bubble rows and tied to the top mesh reinforcement, as shown on the drawings. Other loose Reinforcement As building configurations vary it is not possible to describe all possible non-typical loose reinforcement configurations (such as cages for steps between main slab and cantilever slab) requiring site fixing. This non-typical reinforcement will be shown and detailed on the site installation drawings. Important: Top joint mesh reinforcement must fit between the bars above columns to avoid excessive layers of steel and difficulty with achieving required concrete cover.
Page 9 of 12
Stage 4 Constructing Shuttering Once the perimeter loose reinforcement has been installed work on erecting perimeter and construction joint shuttering can commence. Temporary works are your responsibility to determine, but our recommendations are:Location Perimeter Shuttering Shuttering Erection Procedure Cut sheet of 18mm ply into strips with width of finished slab depth. Fix 75x50mm battens along back edge at top and bottom. Where BD element is tight to edge of finished slab simply plug and screw through bottom batten & ply shuttering straight into centre of pre-cast concrete permanent formwork adge. Fix top of ply shuttering by wire tying back to top mesh reinforcement from screws fixed into top batten. When an in-situ concrete edge strip has been planned to make up the overall floor-plate width then construct perimeter shuttering with timber gallows brackets & plywood perimeter / soffite shuttering in traditional manner, except bracket bottom batten can be plugged and screwed to underside of pre-cast concrete permanent formwork. Cut sheet of 18mm ply into strips 200mm wide, plug and screw 50x50 battens to face of r.c. columns / walls (top 18mm below slab soffite), slide ply into position. Plug and screw external edge of ply shuttering into underside of pre-cast concrete permanent formwork. Cut sheet of 18mm ply into strips 180mm wide and prop up to underside of pre-cast concrete permanent formwork.
Note: We can manufacture and supply cast into elements a pre-formed BubbleDeck Fast Edge steel permanent formwork, eliminating the need for constructing perimeter shuttering on site enquire for further details at time of placing order. Stage 5 Preparation for Concreting The pre-cast concrete permanent formwork edges are manufactured to a high accuracy and care taken to get a tight joint during laying the elements can render joint filling unnecessary. When joints between slab elements have not been closely butted they must be filled to prevent grout seepage. Should this be required joint filling can be undertaken with either mortar grout or a small bead of silicone sealant inserted at the bottom of the splay joint between elements. This is most easily undertaken prior to installing the loose splice reinforcement. Important expanding foam must NOT be used for joint filling as the uncontrollable thickness can adversely reduce concrete cover to splice reinforcement impairing durability and fire resistance of the finished slab. Prior to pouring topping concrete remove element labels, unused tying wire, unused reinforcement, loose concrete and all other debris or foreign matter. Then immediately before placing in-situ concrete power-wash top of the pre-cast concrete permanent formwork to clean off residual dirt and moisten the pre-cast concrete surface. Important maintain the pre-cast concrete biscuit top surface, particularly during hot weather, in a damp (not wet) condition to ensure a good bond between the pre-cast concrete permanent formwork concrete and the in-situ concrete.
Page 10 of 12
Stage 6 BubbleDeck Site Inspection Once you are able to predict when all loose reinforcement will be fixed please contact our Site Support Adviser, Colin Swinnerton, on mobile: 07703 440180 to notify the date you intend to pour concrete and arrange our site inspection. He will then arrange for our technical representative to visit site and undertake a full inspection of the BubbleDeck element and loose reinforcement installation. Following inspection our technical representative will issue you with an inspection record listing any work that needs to be undertaken prior to site concreting, or confirming the installation is ready for concreting and the work is to our approval. Important - While we always seek to provide a quick and efficient service we do need at least 2 working days notice of any site concrete pour to be able to ensure our inspection team are available to attend site. It is essential we are able to inspect prior to site concreting in order to be able to covert your project with our Professional Indemnity and Product Liability Insurance cover. Stage 7 Pouring Topping Concrete Important When ordering concrete please take into account the volume taken up by the bubble void formers mean the concrete volume is NOT arrived at by taking the pour area x depth from top of shuttering to pre-cast concrete permanent formwork. The concrete volume to order can be estimated, dependant upon BubbleDeck slab depth type, from the following table:BubbleDeck Slab Type BD230 A BD280 A BD340 A BD390 A BD450 A Overall Slab Depth (inc. 60mm pre-cast) 230 mm 280 mm 340 mm 390 mm 450 mm Concrete Volume m3 every m2 pour area 0.11 0.14 0.18 0.21 0.25 Max aggregate size 10mm 10mm 15mm 15mm 15mm
When pouring concrete evenly distribute across the area and avoid placing in heaps. Due to the limited space between the bubbles a thin vibrating poker MUST be used to compact the concrete, remove any entrained air and to ensure a good flow around the bubbles. Avoid separation occurring due to the vibrating of shuttering, reinforcement and/or bubbles that can result in segregation of the concrete mix. Once the concrete has been poured a steel beam or power float is then used to level the top and finish to an even and level surface.
Page 11 of 12
Stage 8 Removing Temporary Propping During construction planning we will confirm to you the minimum period for removal of propping before back-propping. This is usually between 8 to 14 days from pouring of the site concrete as long as the 7 or 14 day concrete test results have confirmed the site concrete has reached at least 60% of its final design strength, but can vary dependant upon our floor slab design, strength of site concrete, and ambient temperatures. Once you have received the 7 day concrete test results please forward them to our Head Office, our technical team will then confirm to you it is acceptable to remove temporary propping. If you are then proceeding to construct another floor immediately above the one just completed please refer to the section about Back Propping on Page 6 of this Manual. Subsequent Site Operations Holes through slabs After casting the slab holes can easily be diamond core drilled through the BubbleDeck slab on site. It is uneconomic to pre-cast holes less than 250mm diameter in the factory and post-drilling ensures accurate vertical alignment. Larger service riser holes / cut-outs, where advised to us during preconstruction planning, are shown on our drawings and pre-formed in our factory. Fixings into slabs There is a minimum of 20mm concrete below the centre of each bubble, but just a short distance away from the bubble centre the concrete depth quickly increases to 70mm plus up the side of each bubble. Therefore most fixings can be made using normal methods (plug & screw / expanding anchors, etc.) to provide adequate fixings for wiring conduits, cable trays, ventilation ducts and the like. Where stronger fixings are required to resist higher pull out (downward) forces from heavy loads to be suspended from the soffite we recommend our Bubble layout drawings (page 4 in all cases) are inspected to determine where fixings will occur directly below or close to the edge of a bubble. Where fixing locations and lengths are likely to project into a bubble void we recommend Hilti HIT HY20 Injection Resin Anchor with HIT sieve, item no. 00068613, are used. Hilti also produce a range of other fixing systems designed for fixing through into voids. BubbleDeck UK UK Office 4 Firs Close, Ellesmere Road, St Martins, Nr Oswestry, Shropshire, SY11 3LT Telephone: +44 (0)1691 774242 Facsimile: +44 (0)1691 774294 E-Mail: [email protected] Site Support / Health & Safety Adviser Colin Swinnerton FCIOB, MRICS, MaPS, Cert. FM Mobile: 07703 440180 Channel Islands, Ireland & Head Office White Lodge, Wellington Road, St. Saviour, JERSEY, C.I., JE2 7TE Telephone: +44 (0)1534 725402 Facsimile: +44 (0)1534 739115 E-Mail: [email protected] www.BubbleDeck-UK.com
BubbleDeck Site Erection & Installation Manual Edition 4A April 2006
Page 12 of 12