Monthly Progress Report January-2013
Monthly Progress Report January-2013
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
INDEX
1.0
Project Background
Third Party Quality Audit Consultant Major Activities and Review Meetings of the Month Status of TPQA Visits Progress of NCRMP works TPQA Status Report for NCRMP Works and NCRs Pending up to end of January-2013
3 3 4 5
6.0 7.0
District wise status of tests conducted by TPQA Details of QC Audit Reports Submitted during this Month Statement Showing the Inspections and Site Visits of Districts during the Month of January-2013 Photographs of Site Visits during the Month of January-2013
28 29
8.0
32 45
Page 1 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
District
RHB
RCS
MPCS
Bridges
Roads (R&B)
Total
Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore
6 8 2 10 5 3 14 17
8 6 8 3 12 7 9
2 7 3 2 -
4 2 2 1 -
1 1 -
21 3 21 13 10 8 17 24 26
6 8 2 10 5 3 14 17
8 6 7 3 12 7 9
2 7 3 2 -
4 2 2 1
1 1 -
0 0 0 1 0 0 0 0 0
Page 2 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2.0
To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd. On 31 st May2011, the Contract for Consultancy Service was signed between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd .
3.0 S.No.
1 2 3
Place
Hyderabad Hyderabad Hyderabad
Date
07.01.2013 08.01.2013 31.01.2013
Activity
Attended Review meeting of TPQA at H Block in AP Secretariat with Commissioner and PD Attended Review meeting of EPTRI at H Block in AP Secretariat with Commissioner and PD Attended Review meeting at H Block in AP Secretariat with Commissioner and PD
Page 3 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
4.0
The following table shows the details of TPQA visits to sites in respective districts.
District Up to Dec.2012 Srikakulam Vizianagaram Vishakhapatnam East Godavari West Godavari Krishna Guntur Prakasam Nellore
452 72 361 612 436 299 373 407 323
Up to January.2013
483 73 414 628 462 304 392 438 341
Page 4 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
5.0
The district wise progress of works is shown below. The works in the West Godavari are not started and the works in Krishna District has just started. At many places the first milestone is completed but works are not started. The line departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the agreement conditions should be imposed.
Third Party Quality Audit by Egis India consulting services Summary of Activities Agreements for Packages Communicated PR
1 2 3 4 5 6 7 8 9 Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore Total 6 13 7 3 4 6 12 16 67
S.No.
District
R&B
5 3 0 0 0 0 2 1 0 11
21 3 21 12 10 8 17 24 26
142
0 0 0 1 0 0 0 0 0
1 79 143
Total Packages for which Agreements are received Total Number of works in the above packages
Page 5 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
TPQA STATUS REPORT FOR NCRMP WORKS TO THE END OF JANUARY 2013
S. No. Packages / Works entrusted PR R&B Status of Works Started Not Started No. of Visits of TPQA Total No. of QC tests done NCRs Issued closed Pending Audit Reports Issued Environmental & Social Reports Issued
District
1 2 3 4 5 6 7 8 9
Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasam Nellore Total
16 21 13 10 8 15 23 26 132
5 3 2 1 11
21 3 21 12 10 8 17 24 26 142
0 0 0 1 0 0 0 0 0 1
54 3 25 28 20 3 14 36 32 215
54 3 25 28 20 3 14 36 32 215
0 0 0 0 0 0 0 0 0 0
57 9 41 31 37 21 32 50 48 326
Page 6 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN SRIKAKULAM DISTRICT UP TO 31.01.2013 Milestone Completion Dates First 31.08.11 31.08.11 Second 31.12.11 31.12.11 Third 30.04.12 30.04.12 Progress w.r.t. milestone up to 31.01.2013 complete Entire work complete Entire work complete Entire work
Categ ory
Names of works under each package Road from DPN R&B road to Uddandapalem
Agreement No. / Date /2010-11, Dt. 30.04.2011 /2010-11, Dt. 30.04.2011 /2010-11, Dt. 30.04.2011
Remarks
completed completed
NCRMP/BW/AP/RHB/PRED/ 01/Santhabommali/0 03
Road from K. Umilada Junction to Koduru (Link Road) Road from Borubhadra, Malagam to Kollipadu via Seepuram, Gantapeta
31.08.11
31.12.11
30.04.12
completed 300 mts CC road completed, GSB laying is in progress, road formation width vary from 6.00mts to 7.50mts completed BT layer completed from Km 5/670 to Km 7/270, and WBM Gr- III metal
30.08.11
31.12.11
30.04.12
First Milestone i.e Earthwork & Cd works &GSB First Milestone i.e Earthwork & Cd works & GSB First Milestone i.e Earthwork & Cd works &GSB
Road from Talasamudram to Dola Regulator NCRMP/BW/AP/RHB/PRED/01/ Polaki/005 Road from R&B road Edulavalasa - Killam to Jonnam via Talasamudram
30.08.11
31.12.11
30.04.12
31.07.11
31.10.11
31.01.12
Page 7 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
17.08.11
17.01.12
17.06.12
collection is in progress from Km 5/000 to Km 5/670 Slab A2-pier completed and Slab A1-pier sis in progress, Approach road e/w, GSB, WMM, SDBC completed. CD, R/W works completed. Completed.
Construction of Minor Bridge at Km 12/2-4 of NH-5 to Surampeta Road via Naruva, mentada Construction of High level bridge across Bendigedda at KM 4/10 of Pundi-Parlakimidi road in Srikakulam Dt, A.P. Improvesments NaupadaVenkatapuram road from 0/0to15/0km Road from NP road to URKpuram Road from Deppuru, Bahadapalli road to onkuluru & to cyclone shelter Road from R&B road to Devunthalada
45/2010-2011, Dt17.12.2010
17.05.11
17.10.11
17.03.12
1/2010, Dt.11.11.2010 43/2010-11, 17.12.2010 G.o rt No 451 dt 06.04.2010 G.o rt No 451 dt 06.04.2011 G.o rt No 451 dt 06.04.2012
11.08.11
11.01.12
11.06.12
Completed.
Roads
Completion of entire work WBM GR-II &III complete WBM GR-II &III complete WBM GR-II &III complete
RCS
NCRMP/BW/AP/RCS/PRED/01/ V.KOTTURU/002
Page 8 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from pollada to Komarthalada & to cyclone shelter Road from Koyyam R&B Road to Moosavanipeta Road from Mentada to Dovupeta Road from Kotcherela road to Kollibhemavaram & cyclone shelter Road from Kotcherla road to Pathasundarapalem Construction of Cyclone shelter at Kollipadu MPCS NCRMP/B_W/AP/MPC S/PRED/01/Santhabo mmalli/005
G.o rt No 451 dt 06.04.2013 G.o rt No 451 dt 06.04.2010 G.o rt No 451 dt 06.04.2010 G.o rt No 451 dt 06.04.2010 G.o rt No 451 dt 06.04.2010 G.o rt No 451 dt 06.04.2010
WBM GR-II &III complete Completion of entire work Completion of entire work Completion of entire work Completion of entire work Completion of stilt floor & first floor Completion of stilt floor & first floor
work completed work completed work completed work completed work completed Silt floor level slab completed. Upto plinth beam completed, and columns above plinth beam is in progress
NCRMP/BW/AP/RCS/PRED/01/ ETCHERLA/005
07.03.12
07.08.12
07.01.13
Page 9 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN VIZIANAGARAM DISTRICT UP TO 31.01.2013 Categor y Packages allotted under Phase - 1 Names of works under each package Construction of Minor Bridge at Km. 7/2 near Puligedda of Konada Ramatheertham R&B Road to Konathalapalem via Yerukonda, Pasupam, Kollayavalsa (Z.P. Road) Construction of Minor Bridge at Km 15/2 near Chakaligadda of Konada Ramatheertham R&B road to Konathalapalem (via) Yerukonda, Pasupam, Kollayavalsa (ZP Road) Improvements to Road from Konada Ramatheertham (R&B) Road to Konathalapalem (Via) Pasupam, Yerukonda, Kollayavalsa from Km 12/0 to 16/5 (Km 0/0 to 4/0 i.e. up to NH-5 crossing) Agreement No./ Date Milestone Completion Dates First Second Third Progress w.r.t. milestone up to 31.01.2013 Remarks
NCRMP/B-W/ AP/ Br/ R&B/ 02/Puligadda/ 007 Bridges NCRMP/B-W/ AP/ Br/ R&B/ 02/ Chakaligadda /008
30.06.11
31.01.12
31.05.12
As against of 100 % in the 3rd Milestone Minor deviation approval is awaited. It takes 15 days time to complete the work after deviation approval
07.07.11
07.02.12
07.06.12
Road
07.06.11
07.12.11
07.03.12
Page 10 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF TOTAL WORKS IN VISAKHAPATNAM DISTRICT UP TO 31.01.2013 Categ ory Packages allotted under Phase - 1 Names of works under each package Agreement No. / Date Milestone Completion Dates First Second Third Progress w.r.t. milestone up to 31.01.2013 Plinth beam & Staircase, Stilt floor slab, First floor slab, ramp slabs are completed. EOAT submitted on 24.08.12 All Slabs are completed. Inside and outside wall plastering work completed. White cement applications, wood joinery and Electrical works are to be progress. Plinth beam & Staircase, Stilt floor slab, First floor slab, ramp slabs are completed. EOAT submitted on 24.08.12 Stilt Slab & stilt floor, First floor and head room slabs are completed. Ceiling plastering work and first floor brick work are in progress.
Remarks
05.06.12
05.10.12
05.02.13
02.02.12
02.06.12
02.10.12
likely to be completed before 15.02.2013 likely to be completed before March.2013 likely to be completed before March.2013
02.03.12
02.08.12
02.01.13
02.03.12
02.08.12
02.01.13
Page 11 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
02.03.12
02.08.12
02.01.13
Stilt floor, First floor, second floor, Head room slabs are completed. Ist floor and second floor brick masonry work is in progress. Plinth beam completed and filling under floor is in progress. EOAT proposals submitted on 29.06.12. Work not started due to site problem
Construction of cyclone shelter at Venkayyapalem Construction of cyclone shelter at Thikkavanipalem Road from NH-5 to Ramarayadupalem Road from R & B road to Rajakoduru
02.01.12
02.04.12
02.07.12
06.01.12
06.04.12
06.07.12
/2011-12, Dt. 15.09.2011 /2011-12, Dt. 15.09.2011 /2011-12, Dt. 15.09.2011 /2011-12, Dt. 15.09.2011 /2011-12, Dt. 15.09.2011
14.12.11
14.03.12
14.06.12
Road Furniture & B.T is completed. CD works are completed & B.T work is Completed CD works are completed & B.T work is Completed CD Work is completed & B.T work is completed B.T & C.C road works are Completed.
completed
RCS
NCRMP/BW/AP/RCS/PRED/ 03/Rambilli/002
Road from R & B road to Kattubolu to Marripalem Road from R & B road to Krishnampalem
NCRMP/BW/AP/RCS/PRED/ 03/Nakkapalli/003
14.12.11
14.03.12
14.06.12
completed
Page 12 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from Upmaka Rajayyapeta R&B road to Janakayyapeta NCRMP/BW/AP/RHB/PRED/ 03/Nakkapalli/001 NCRMP/BW/AP/RHB/PRED/ 03/Anandapuram/ 003 Road from Vempudi to Patimeeda Road from R&B road to Mullaparra up to Beach end Road from R&B B.P Kallalu to Matchvanipalem Road from R & B road to Pothurajanapalem Road from R & B road to Jalaripeta Road from R & B road to Venkayyapalem Road from R&B road to Ava- Somavaram Road from R&B Road to Avarajam
/2011-12, Dt. 15.09.2011 /2010-11, Dt. 11.01.2011 /2010-11, Dt. 27.01.2011 /2010-11, Dt. 10.03.2011 /2010-11, Dt. 28.03.2011 /2010-11, Dt. 28.03.2011 /2010-11, Dt. 11.01.2011 /2011-12, Dt. 27.04.2011 /2011-12, Dt. 27.04.2011
CD works are Completed & B.T work is completed Work is completed Work is completed
completed -
09.06.11
09.09.11
09.12.11
Work is completed
27.06.11
27.09.11
27.12.11
Work is completed
RHB
NCRMP/BW/AP/RHB/PRED/ 03/Paravada/004
27.06.11
27.09.11
27.12.11
Work is completed
10.04.11
10.07.11
10.10.11
Work is completed
26.07.11
26.10.11
26.01.12
Work is completed
26.07.11
26.10.11
26.01.12
Work is completed
Page 13 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF TOTAL WORKS IN EAST GODAVARI DISTRICT UP TO 31.01.2013. Categ ory Packages allotted under Phase - 1 NCRMP/B-W /RCS/PRED/ 04/Karapa/001 NCRMP/B-W/AP/RCS/ PRED/04/Thondangi/004 NCRMP/B-W /AP/RCS/ PRED/04/Thondangi/004 NCRMP/B-W /AP/RCS/ PRED/04/Thondangi/004 NCRMP/B-W/AP/RCS/ PRED/04/Uppalaguptam /003 NCRMP/B-W/AP/RCS/ PRED/04/Thondangi/004 NCRMP/B-W/AP/RCS/ PRED/04/Thondangi/004 NCRMP/B-W/AP/RCS/ PRED/04/Thondangi/004 RHB NCRMP/B-W/AP/RHB/ PRED/04/Karapa/001 Names of works under each package Approach Road to cyclone Shelter at Adivipudi Road from R&B Road to P.Chodipallipeta CS Road from R&B Road to K.Chodipallipeta CS Road from R&B Road to Hukumpeta CS Road from R&B Road to Chinaraghavulapeta Cyclone Shelter Road from R&B Road to Gaddipeta CS Road from R&B Road to Danavaipeta CS Road from R&B Road to G.Musalayyapeta CS Road from Gurjanapalli to Bandulavaripalem Agreement No. / Date Milestone Completion Dates First 32/2011-12 Dt:20.05.2011 73/2011-12 Dt:07.09.2011 73/2011-12 Dt:07.09.2011 73/2011-12 Dt:07.09.2011 74/2011-12 Dt: 23.09.2011 73 /2011-12 Dt:07.09.2011 73 /2011-12 Dt:07.09.2011 73/2011-12 Dt:07.09.2011 24/2011-12 Dt:27.04.2011 30-11-2011 3 months 06.12.2011 3 months 06.12.2011 3 months 06.12.2011 3 months 22.11.2011 3 months 06.12.2011 3 months 06.12.2011 3 months 06.12.2011 30-09-2011 Second 31-10-2011 3 months 06.03.2012 3 months 06.03.2012 3 months 06.03.2012 3 months 22.06.2011 3 months 06.03.2012 3 months 06.03.2012 3 months 06.03.2012 31-10-2011 Third 31-01-2012 3 months 06.06.2012 3 months 06.06.2012 3 months 06.06.2012 ----------3 months 06.06.2012 3 months 06.06.2012 3 months 06.06.2012 31-01-2012 Progress w.r.t. milestone up to 31.01.2013 100%
Remarks
Completed.
Completed. Completed Completed Completed Completed Completed Not yet Started Completed
RCS
Page 14 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/ PRED/04/Katrenikona/0 03 NCRMP/BW/AP/MPCS/PRED/04/ Uppalaguptam/002 NCRMP/B-W /AP/MPCS/PRED/04/ Thondangi/001 NCRMP/B-W /AP/MPCS/PRED/04/Tho ndangi/001
Road from PR roads to Dasarivanipeta and to Cyclone Shelter Construction of Cyclone Shelter at Pedaraghavulapeta of Uppalaguptam Mandal E.G.Dt. Construction of Cyclone Shelter at Lakshmanudipeta in Thondangi Construction of Cyclone Shelter at Avulamanda
18/2011-12 Dt:27.04.2011
30-11-2011
30-11-2011
20-01-2012
100%
Completed. Likely to be completed by June 2013 Likely to be completed by March 2013 Likely to be completed by March 2013
78/2011-12 Dt:17.10.2011
3 months 16.01.2012
3 months 16.04.2012
3 months 16.07.2012
45%
MPCS
77/2011-12 Dt:07.09.2011
4 months 16.02.2012
4 months 16.06.2012
4 months 16.10.2012
80%
77/2011-12 Dt:07.09.2011
4 months 16.02.2012
4 months 16.06.2012
4 months 16.10.2012
80%
Page 15 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN WEST GODAVARI DISTRICT UP TO 31.01.2013 Packages allotted under Phase 1 Agreemen t No. / Date Milestone Completion Dates First Second Third Progress w.r.t. milestone up to 31.01.13 100%
Categ ory
Names of works under each package Road from NH 214 A at Ranga Statue center to Harijanawada of Kalipatnam (E) (Mogalthuru Mandal R&B road at Panchayat Office to Pulaparthivarithota via Badava (Mogalthuru Mandal W.G.Dist.) Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge to Gogulamma Harijanapeta (Mogalthuru Mandal) From Narsapur Mogalthuru R&B road to Dayadaldaspeta via Venkateshwara Swamy temple (Mogalthuru Mandal ) Road from NH 214 A road to Harijanapeta of Kothota R&B road to Indira Nagar (via) Pochamma temple (Narsapur Mandal) Road from R&B road to Pedalanka (Narsapur Mandal W.G.Dist.) Road from LB Cheria CC road to Chillapalem of LB Cheria. From A-U R&B Road to Satyanarayanapuram (Kalla Mandal) From A-U R&B Road to Mekaladibba (Kalla Mandal W.G.Dist.)
Remarks
Completed
NCRMP/BW/AP/RHB/PRED/ 05/Mogaltur/001
16 /201112 Dt.27.04.20 11
27/4/2011 to 22/9/2011
23/9/2011 to 24/2/2012
25/2/2012 to 26/7/2012
100%
Completed
100%
Completed
100% 27/4/2011 to 22/9/2011 21 /201112 Dt.09.05.20 11 09/05/2011 to 04/09/2011 23/9/2011 to 24/2/2012 05/09/2011 to 06/01/2012 25/2/2012 to 26/7/2012 07/01/2011 to 08/5/2012
Completed
RHB
NCRMP/BW/AP/RHB/PRED/ 05/Narsapur/002
NCRMP/BW/AP/RHB/PRED/ 05/Kalla/003
25 /201112 Dt.26.05.20 11
26/5/2011 To 20/8/2011
20/8/2011 to 21/11/2011
22/11/2011 To 23/2/2012
Page 16 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN KRISHNA DISTRICT UP TO 31.01.2013 Cate gory Packages allotted under Phase - 1 NCRMP/B-W/AP/RHB/ PRED/06/Machilipatnam/001 Names of works under each package Road connecting R&B road through Gantlammapalem Road from R & B Road to B.V Thota Road from Potalapalem Z.P road to Chikativanipalem Road from Intheru R&B Road to Rangaraopet Road from R&B road to Cyclone Shelter at Chandala Road from Bhogireddypalli R&B Road to Ramakhandam RCS NCRMP/B-W /AP/RCS/ PRED/06/Machilipatnam/001 Road from R&B Road Chinnapuram to Gundupalem Road from Potlapalem Z.P road to Pothepalli. Agreement No. / Date 8/201112/27.04.2011 7/201112/27.04.2011 7/201112/27.04.2011 9/201112/27.04.2011 9/201112/27.04.2011 32/2011-12/ Dt.02.09.2011 32/201112/27.04.2011 32/2011-12/ Dt.02.09.2011 Milestone Completion Dates First 26.07.2011 Second 26.10.2011 Third 26.01.2012
Remarks
Completed
NCRMP/B-W/AP/RHB/ PRED/06/Kruthivennu/003
26.07.2011
26.10.2011
26.01.2012
Completed
01.12.2011
01.03.2012
01.06.2012
Completed
01.12.2011
01.03.2012
01.06.2012
Completed
01.12.2011
01.03.2012
01.06.2012
Completed
Page 17 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN GUNTUR DISTRICT UP TO 31.01.2013 Agreemen t No./ Date 7/20112012 27.04.2011 8/20112012 27.04.2011 79/20102011 1.12.2010 78/20102011 1.12.2010 2011-2012 1.11.2011 Milestone completion dates First 26.7.2011 26.8.2011 Second 26.10.2011 26.12.2011 Third 26.01.2012 26.4.2012 Progress w.r.t. milestone up to 31.01.2013 31.5.2011 30.11.2011 31.5.2012 31.5.2011 30.11.2011 31.5.2012 90% 31.01.2012 31.01.2012 30.04.2012 30.04.2012 31.07.2012 31.07.2012 45% 2011-2012 1.11.2011 29.02.2012 30.06.2012 31.10.2012 20% Completed Likely to be completed before March 2013 Completed. Likely to be completed before Feb 2013 Likely to be completed before Feb 2013
Categ ory
Names of works under each package R/f Ganapavaram R&B Road to Kesavapuri ST colony R/f R&B Road to Mohammad Alipalem R/f R&B Road to Katurivaripalem. Reconstruction of High-level Bridge @Km5/2 of BapatlaSuryalanka Road across perali drain in Guntur Dt. Reconstruction of High-level Bridge @Km2/4 of BapatlaPandurangapuram Road across perali drain in Guntur Dt. Road from R&B road to Mandevaripalem Road from R&B Road Alluru to Yadavapalem Road from Ganapavaram R&B Road to Pedamarpuvaripalem
Remarks
RHB
NCRMP/B-W/AP/PRED/ 07/Nagaram/002
Bridge s
NCRMP/B-W/AP/Br/R&B/ 07/Bapatla/010
NCRMP/B-W/AP/Br/R&B/ 07/Bapatla/011
RCS
NCRMP/BW/AP/RCS/PRED/ 07/Karlapalem/002
Page 18 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R&B Road to Chinapuluguvaripalem From R&B road to Yaramvaripalem Road from R&B Road to Pedagollapalem Cyclone Shelter Pedagollapalem P.R road to Bonthagoralapalem Road from R&B Road to Gurunadhanagar Road from R & B Road to Adavala H/O Bavaji palem Road from R & B Road to Atlavaripalem Road from R & B Road to Hanumathanagar Road from R & B Road to Adarsh nagar 2011-2012 17.10.2011
29.02.2012
30.06.2012
31.10.2012 25%
Likely to be completed before Feb 2013 Completed. Completed. Shoulders are in progress. Completed. Completed. Completed. Completed. Completed.
29.02.2012 29.02.2012
30.06.2012 30.06.2012
31.10.2012 31.10.2012
NCRMP/BW/AP/RCS/PRED/ 07/Nizampatnam/003
NCRMP/BW/AP/RCS/PRED/ 07/Bapatla/004
Page 19 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN PRAKASAM DISTRICT UP TO 31.01.2013 Names of works under each package Construction of High level Bridge at Km 16/10 of Naguluppapadu Kanaparthy road Road from Pakala ZP Road to Aulavaripalem Cyclone shelter NCRMP/B-W/AP/RHB/ PRED/08/S.Konda/001 Road from R&B Road to Somarajupalli Agreemen t No. / Date Milestone completion dates First 5/31/2011 Completion up to sill level Second 12/31/2011 Completion up to below deck slab Third 5/31/2012 Completion of entire work including approaches Progress of work for the month January 2013
Categ ory
Remarks
BRID GES
completed
Dated 25.04.2011 Dated 25.04.2011 8/24/2011 Earth work, CD work, GSB 12/24/2011 WBM, Grade II & III 4/24/2012 BT, Shoulders & road furniture
CC Road & Shoulders work is Completed. BT, CC road & culverts are completed from KM 0/0 to 2/146. BT, & culverts are Completed from KM 0/0 to 0/900. work is completed WBM-Grade-III Layer Completed. OGPC + Seal Coat To be taken up WBM-Grade-III Layer Completed. OGPC + Seal Coat To be taken up
completed
completed
RHB
Dated 25.04.2011
completed
NCRMP/B-W/AP/RHB/ PRED/08/S.Konda/002
dated 10/02/2011
dated 10/02/2011
Page 20 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/ PRED/08/S.Konda/002
Road from Pakala R&B road to Mosanaladinne Road from R&B road to Binginapalli Harijanawada Cyclone Shelter
dated 10/02/2011
dated 10/02/2011
WBM-Grade-III material laying work is in progress CC road work is completed from KM 0/0 to KM 0/220. Shoulders work is to be taken up. BT, CC road, shoulders & culverts are completed from km 0/0 to km 3/8.work is completed BT completed.CD work completed.CC road work completed from km 0/0 to km 1/430 and CC dip work is completed BT completed.CD work completed.CC road and shoulders work completed from km 0/0 to km 3/900. BT completed.CD work completed and shoulders work completed from km 0/0 to km 3/4. work is completed
98%
98%
Dated 27/04/2011
completed
Road from KEM R&B Road to Sankuvarigunta NCRMP/B-W/AP/RHB/ PRED/08/Kothapatnam/ 004 Road from KEM R & B Road to Pullareddypalem
Dated 27/04/2011 9/26/2011 Earth work, CD work, GSB Dated 27/04/2011 2/26/2012 WBM, Grade II & III
completed
completed
NCRMP/B-W/AP/RHB/ PRED/08/Ulavapadu/07
dated 27/04/2011
completed
Page 21 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/RHB/ PRED/08/Ulavapadu/08
dated 27/04/2011
4/26/2012 BT, Shoulders & road furniture 3/15/2012 BT, Shoulders & road furniture 1/18/2012 BT, Shoulders & road furniture
BT completed.CD work completed.CC road and shoulders work completed from km 0/0 to km 5/086. work is completed BT completed. CD work completed.CC road and shoulders work completed from km 0/0 to km 4/5. work is completed BT completed. CD work completed.CC road and shoulders work completed from km 0/0 to km 2/103. work is completed cc road completed, BT road completed& shoulders completed. Road from km 0/0 to km 0/525. work is completed cc road completed, BT road completed& shoulders completed. Road from km 0/0 to km 1/735. work is completed C.C.road and Shoulders are completed Road from km 0/0 to km 0/500.
completed
NCRMP/B-W/AP/RHB/ PRED/08/Tangutur/09
dated 16/03/2011
7/15/2011 Earth work, CD work, GSB 7/18/2011 Earth work, CD work, GSB
completed
NCRMP/B-W/AP/RHB/ PRED/08/Tangutur/10
dated 19/04/2011
completed
Road from R&B road to Vijayanagar colony cyclone shelter 1/29/2012 Earth work, GSB 5/29/2012 shoulders, Gr-III 9/29/2012 BT, CC pavement and road furniture
completed
RCS
NCRMP/B-W/AP/RCS/ PRED/08/Vetapalem/001
dated 30.09.2011
completed
completed
Page 22 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R&B road to Ramnagar colony cyclone shelter Road from R&B road to cyclone shelter at Mankenavaripalem Road from R&B Road to Keerthivaripalem cyclone shelter Road from R&B Road to Devinuthula cyclone shelter of Chirala Mandal
C.C.completed Road from km 0/0 to km 0/475.Shoulders to be taken up. CC road completed. Shoulders work is to be taken up. C.C road and Shoulders are completed from km 0/0 to km 0/265. work is completed C.C road and Shoulders are completed from km 0/0 to km 0/800. work is completed 24.05.2012 Head room, plastering, flooring, water supply arrangeme nts, sanitary fitting, electrical items, compound wall, cc pavement. Earthen mounds (raised Stilt floor, G.F , & Terrace floor- roof slab completed. Brick work completed, Plastering work completed, Cattle platform completed revetment work completed, flooring work is completed, compound wall 120 meters length completed, Electrical work is completed. work is completed
completed
completed
completed
NCRMP/B-W/AP/RCS/ PRED/08/Chirala/002
dated 27.08.2011
completed
MPCS
NCRMP/B-W/APMPCS/ PRED/08/Ulavapadu/001
24.11.2011 All items up to stilt floor slab including ramp, stair case foundations , columns, beams, pcc flooring etc.,
24.02.2012 All items up to second floor slab including first floor, and in 2nd floor including stair case, columns etc.,
completed
Page 23 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
23.11.2011 All items up to stilt floor slab including ramp, stair case foundations , columns, beams, pcc flooring etc.,
23.02.2012 All items up to first floor slab and head room slb in 2 nd floor including stair case, columns etc.,
portion), water harvesting, septic tank, slump and soak pit. etc., 23.05.2012 plastering, flooring, water supply arrangeme nts, sanitary fitting, electrical items, compound wall, cc pavement. Earthen mounds (raised portion), water harvesting, septic tank, slump and soak pit. etc.,
Internal & External Plastering completed. Flooring Work Completed. Compound Wall Painting Completed. CC Road Completed. Shoulder work in Completed. Painting work in Completed. Electrical Fittings in progress. Tiles in bathrooms work in Completed. Water harvest & Soak pit work in completed.
completed
Page 24 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATUS OF WORKS IN SPSR NELLORE DISTRICT UP TO 31.01.2013 Name of package Name of work 1. Road from NH5 to Sambasiva Puram Road from 9/6 of Juvvaladinne R&B Road to 11/0 of Juvvaladinne R&B Road Via Venkateshpalem Road from 1/6 of Zuvvaladinne R&B Road to Tellagunta KM to 2/720 Road from R&B Road to Muttambeka Via Pittuvanipalla Road from R&B Chittamur to Soma Samudram Road from5/8 of Chennayapalem Road to Gummadi bandla Road from pedattapupalem R&B road to Chennayapalem H.wada Road from K.T R&B Road to Alliguntapalem 1)Road from KT R&B road to Alaganipadu to Vavilla Road from R&B road Kancharapalem HW to Alaganipadu. date of agreement mile stone -I mile stone -II mile stone -III Present Statues of work OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed 26.2.201210 Months: WBM GrII, GrII and Shoulders 26.7.2012 15 Months: BT and Road Furniture OGPC+SC completed WBM Gr-II is in progress & CD Works completed. Remarks completed completed
NCRMP/B-W/AP/ RHB/PRED/09/ BOGOLO/RHB/001 NCRMP/B-W/AP/ RHB/PRED/09/ BOGOLU/002 NCRMP/B-W/AP/ RHB/PRED/09/ CHITTAMURU/003 RHB NCRMP/B-W/AP/ RHB/PRED/09/RHB/ KAVALI/004
1/19/2011
5Months: Earth Work, Pipe Culverts, GSB 6.5,2011 3Months: Earth Work, Pipe Culverts, GSB 17.6.2011 5Months: Earth Work, Pipe Culverts, GSB
10 Months: WBM GrII, GrII and Shoulders 6.8.2011 6 Months: WBM GrII, GrII and Shoulders 17.11.2011 10 Months: WBM GrII, GrII and Shoulders
15 Months: BT and Road Furniture 6.11.20119 Months: BT and Road Furniture 17.4.2012 15 Months: BT and Road Furniture
completed
07.02.2011
18.01.2011
17.01.2011
27.04.2011
98%
Page 25 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
NCRMP/B-W/AP/ PRED/09/ MUTHUKUR/RHB/ 006 NCRMP/B-W/AP/ RHB/PRED/09/ V.CHALEM/RHB/ 007 NCRMP/B-W/AP/ RHB/PRED/09/Allur /009 NCRMP/B-W/AP/ RHB/PRED/009/ T.P.GUDUR/012 NCRMP/B-W/AP/ PRED/09/kota/RCS /001 NCRMP/B-W/AP/ PRED/09/ MUTHUKUR/RCS/ 002 NCRMP/B-W/AP/ PRED/09/Chillakur/ RCS/004
Road from R&B road to Patuvari Kandriga Road from SurvepalliPudiparthi road to Srikanth Colony providing BT Surface to the road from R&B road to Edagali Kandriga Road from R&B road Alluru to Galidibbalu (via) Chukavani dibba Ring Road to TP GudurSalipeta R & B Road via CS Puram and Mandapam Vill. Road from R & B Road C S Puram to Sivaramapuram Road from R&B road to A.S PURAM Road from GD Road to Vavilla Palem Road from R&B Road kappaladoruvu to bandla Palem H.wada
25.4.11
24.7.2011 3Months: Earth Work, Pipe Culverts, GSB 26.8.2011 4Months: Earth Work, Pipe Culverts, GSB 23.6.2011 5Months: Earth Work, Pipe Culverts, GSB 18.8.2011 3Months: Earth Work, Pipe Culverts, GSB 9.8.2011 3Months: Earth Work, Pipe Culverts, GSB 20.7.2011 3Months: Earth Work, Pipe Culverts, GSB 22.8.2011 3Months: Earth Work, CD Works, GSB
24.10.2011 6 Months: WBM GrII, GrII, CC Pavement and Shoulders 26.12.2011 8 Months: WBM GrII, GrII and Shoulders 23.11.2011 10 Months: WBM GrII, GrII and Shoulders 18.11.2011 6 Months: WBM GrII,GrII, CC Pavement and Shoulders 9.11.11 6 Months: WBM GrII,GrII and Shoulders 20.10.2011 6 Months: WBM GrII,GrII,CC Pavement and Shoulders 22.11.2011 6 Months: WBM GrII,GrII and Shoulders
24.1.2012 9 Months: BT and Road Furniture 26.4.2012 12 Months: BT and Road Furniture 23.4.2012 15 Months: BT and Road Furniture 18.2.2012 9 Months: BT and Road Furniture 9.2.2012 9 Months: BT, CC Pavement and Road Furniture 20.1.2012 9 Months: BT CC road and Road Furniture 22.2.2012 9 Months: BT, CC Pavement and Road Furniture
OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed OGPC+ SC completed
completed
completed completed
27.04.2011
24.01.2011
completed
19.05.2011
10.05.2011
RCS
21.04.2011
completed
23.05.2011
OGPC+ SC completed
completed
Page 26 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
17.05.2011
16.11.2011 6 Months: WBM GrII,GrII Shoulders and CC Pavement 20.5.2012 4 Months: WBM GrII,GrII , Shoulders and CC Pavement
16.2.2012 9 Months: BT, CC Pavement and Road Furniture 20.9.2012 4 Months: BT, CC Pavement and Road Furniture
OGPC+ SC completed GSB. From 0.00 to 5.320 (Bits), WBM Gr-II, Gr-III from 0.00 to 5.320 and OGPC+SC 0/6 to 5/1 is completed OGPC+ SC completed
completed
Road Connecting R&B Road through Voturu Village in SPSR Nellore District.
21.09.2011
completed
Road from Kotha satram R&B to Indrsanagar (via) Thumalapenta palam, Patharavadu palam, Ramudu palam, Karaduvari palam & Sreeramapuram Road from R&B road to Sullurpeta Mallam to Berijengalapalli cyclone shelter Providing BT road to Pedapannamgadu in Tada Mandal
29.08.2011
28.12.2011 4Months: Earth Work, Pipe Culverts, GSB 8.8.2011 3Months: Earth Work, Pipe Culverts, GSB 14.02.2013 (5Months) Earth Work, Pipe Culverts, GSB & CC road 14.02.2013 (5Months) Earth Work, Pipe Culverts, GSB & CC road
28.4.2012 4 Months: WBM GrII,GrII , Shoulders and CC Pavement 8.11.2011 6 Months: WBM GrII, GrII Shoulders and CC Pavement 13.06.2013 (4 Months): WBM GrII, GrII Shoulders 13.06.2013 (4 Months): WBM GrII, GrII Shoulders
28.8.2012 4 Months: BT, CC Pavement and Road Furniture 8.2.2012 9 Months: BT, CC Pavement and Road Furniture 13.09.2013 Months) BT and Road Furniture 13.09.2012 Months) BT and Road Furniture
completed
09.05.2011
OGPC+ SC completed
completed
67%
14.09.2012 Road from @ 56/8 to C.K road to Periyavettu kuppam cyclone shelter
9.41%
Page 27 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
6.0 District wise status of tests conducted by TPQA: Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of tests conducted in the field till end of December 2012 are presented.
Summary of QC Tests - Up to 31.01.2013 No. Tests Conducted during the Month 30 0 89 42 0 3 50 50 32 296 Total no. of Tests Passed 30 0 89 42 0 3 50 50 32 296 Failed 0 0 0 0 0 0 0 0 0 0 Total no. of Tests up to 31.01.2013 Passed 1499 461 2280 1170 349 88 645 1951 1185 9628 Failed 6 0 46 0 0 0 11 4 21 88
S.No.
District
1 2 3 4 5 6 7 8 9
Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore Total
Page 28 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
7.0 Details of Quality Control Audit Reports Submitted During this Month:
Package Number NCRMP/BW/AP/RHB/PRED/ 09/vidavalur/005 NCRMP/B-W/AP/RCS/PRED/ 08/VETAPALEM/001 NCRMP/BW/AP/RCS/PRED/ 07/Karlapalem/002. NCRMP/B-W/AP/RCS/PRED/ 07/PV Palem/001 NCRMP/B-W/AP/RCS/PRED/ 09/TADA/009 NCRMP/B-W/AP/RHB/PRED/ 03/Anandapuram/003 NCRMP/B-W/AP/RCS/PRED/ 03/Anandapuram/001
Name of Work Road from R&B road Kancharapalem HW to Alaganipadu of SPSR Nellore Dt. Road from NH to Challareddypalem In Prakasam District Road from Pedagollapalem PR Road to Bonthagorlapalem Road from R&B Road Alluru to Yadavapalem in Guntur DT. Providing BT Road to Peda Pannam Gadu in Tada Mandal of Nellore Dt. Providing Road from R&B B.P Kallalu to Matchvanipalem in Visakhapatnam Dt. Providing B.T to the Road from NH-5 to Ramaraidupalem in Visakhapatnam Dt.
Page 29 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Road from R&B road Kancharapalem HW to Alaganipadu of SPSR Nellore Dt. Construction of cyclone shelter at Kollipadu in Santhabommali Mandal in Srikakulam Dt.
Nellore Srikakulam
Final QCRs submitted in this month NCRMP/B-W/AP/RHB/PRED/ 06/Kruthivennu/003 NCRMP/B-W/AP/RCS/PRED/ 06/Machilipatnam/001 NCRMP/B-W/AP/RCS/PRED/ 06/Machilipatnam/001 NCRMP/B-W/AP/RHB/PRED/ 06/Machilipatnam/002 NCRMP/B-W/AP/RCS/PRED/ 06/Machilipatnam/001 NCRMP/B-W/AP/RHB/PRED/ 06/Machilipatnam/001 NCRMP/B-W/AP/RHB/PRED/ 06/Kruthivennu/003 NCRMP/B-W/AP/RHB/PRED/ 06/Machilipatnam/002 NCRMP/B-W/AP/RHB/PRED/ 05/MOGALTHURU/001 NCRMP/B-W/AP/RHB/PRED/ 05/Narasapur/002 NCRMP/B-W/AP/RHB/ PRED/ 05/Narasapur/002 NCRMP/B-W/AP/RHB/PRED/ 05/MOGALTHURU/001 NCRMP/B-W/AP/RHB/PRED/ 05/MOGALTHURU/001 NCRMP/B-W/AP/RHB/PRED/ 05/Narasapur/002 Road from Interu ZP road to Rangaraopeta in Krishna Dt. Road from Bhogireddypalli R&B road to Ramakhandam in Krishna Dt. Road from Potlapalem ZP road to Potepalli in Krishna Dt. Road from R&B road to B.V.Thota in Krishna Dt. Road from Chinnapuram R&B road to Gundupalem in Krishna Dt. Road connecting R&B road through Gantalammapalem in Krishna Dt. Road from R&B road to Cyclone shelter at Chandala in Krishna Dt. Road from Potlapalem Z.P road to Chikativanipalem in Krishna Dt. R&B Road at Panchayat office to Pulaparthivarithota via Badava of Mogalthuru Mandal in West Godavari Dt. Road from R&B road to Pedalanka of Narsapur Mandal in West Godavari District. R&B road to Indira Nagar (via) Pochamma temple of Narsapur Mandal in West Godavari Dt. Road from NH 214 A road to Harjanawada of kothota of Mogalthuru Mandal in West Godavari Dt. Road from NH 214 A at Ranga statue center to Harijanawada of Kalipatnam (E) of Mogalthuru Mandal Road from LB Cherla CC road to Chillapalem of LB Cherla of Narsapur Mandal in West Godavari Dt. Krishna Krishna Krishna Krishna Krishna Krishna Krishna Krishna West Godavari West Godavari West Godavari
West Godavari
West Godavari
West Godavari
Page 30 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Mogaltur Vempa R&B Road at Uchintha kalava Bridge to Gogulamma Harijanapeta of Mogalthuru Mandal in West Godavari Dt. From Narsapur Mogaltur R&B road to Dayaldaspeta via Venkateshwara Swamy Temple of Mogalthuru Mandal in West Godavari Dt. From A-U R&B Road to Satyanarayanapuram of Kalla Mandal in West Godavari Dt. From A-U R&B Road to Mekaladibba of Kalla Mandal in West Godavari Dt.
West Godavari
West Godavari
Page 31 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
8.0 Statement Showing the Inspections and Site Visits of Districts during the Month of January -2013
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH OF DECEMBER 2012 Sl. No. TPQA INSPECTIONS DURING THIS MONTH PACKAGE NO NAME OF WORK DATES OF VISIT NCRMP/B-W/AP/MPCS/PRED/ 01/Santhabommali/005 NCRMP/B-W/AP/RCS/PRED/ 01/V.Kotturu/002 NCRMP/B-W/AP/RCS/PRED/ 01/V.Kotturu/002 NCRMP/B-W/AP/RCS/PRED/ 01/V.Kotturu/002 NCRMP/B-W/AP/RCS/PRED/ 01/V.Kotturu/002 NCRMP/B-W/AP/MPCS/PRED/ 01/Santhabommali/005 NCRMP/B_W/AP/Br/R&B/ 01/Bendigedda/004 NCRMP/B-W/AP/MPCS/PRED/ 01/Polaki/006 NCRMP/B-W/AP/MPCS/PRED/ 01/Polaki/006 Construction of Cyclone shelter at Runku in Santhabommali Mandal. Road from Deppuru, bhadapalli road to Onkuluru & cyclone shelter. Road from NP Road to URK Puram Road from Pollada to Komrlathada&Cyclonic shelter Road from R&B ROAD TO Devunalthada Construction of Cyclone shelter at Kollipadu in Santhabommali Mandal. Construction of High level Bridge across Bendigedda at km 4/10 of Pundi-Parlkimidi road in Srikakulam Dist. Road from Talasamudram to Dola regulator Road from Mabagam R&B road to Dubbakavanipeta via gajapathinagaram. 19.01.13,26.01.13 8.01.13 8.01.13 8.01.13 8.01.13 3.01.13, 19.01.13, 24.01.13 NO. OF VISITS 2 1 1 1 1 3
1 2 3 4 5 6
7 8 9
1 1 1
Page 32 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
10 11 12 13 14 15 16 17 18 19
NCRMP/BW/AP/MPCS/PRED/01/Polaki/005 NCRMP/BW/AP/RCS/PRED/01/Etcherla/005 NCRMP/BW/AP/RCS/PRED/01/Etcherla/005 NCRMP/BW/AP/RCS/PRED/01/Etcherla/005 NCRMP/BW/AP/RCS/PRED/01/Etcherla/005 NCRMP/B_W/BR/R&B/01/uppigedda/002 NCRMP/BW/AP/Br/AR&B/ 01/Patnavanipeta/001 NCRMP/B-W/AP/RHB/PRED/ 01/Santhabommali/003 NCRMP/B-W/AP/RHB/PRED/ 01/Santhabommali/003 NCRMP/B-W/AP/RHB/PRED/ 01/Santhabommali/003
Road from R&B road Edullavalasa-Killam to jonnam via talasamudram Road from Kotcherla road to Pathasundarapalem Road from Kotcherla road to Kollibhemavaram & to cyclone shelter Road from mentada to Dovupeta Road from Koyyam R&B road to Moosavanipeta Construction of HLB across uppugedda at Km 7/6 of Srikakulam municipal limits to Pukkalapeta Construction of Bridge at km 11/6-8 of NH-5 to Patnavanipeta connecting Sundarapalem. Road from DPN road Uddandapalem Road from K.Umilada to Koduru (Link road) Road from Borubadra, Malagam road to Kollipadu via Seepuram, Ghantapeta
24.01.13 11.01.13 11.01.13 11.01.13 11.01.13 3.01.13, 5.01.13, 10.01.13, 24.01.13 4.01.13, 10.01.13, 18.01.13, 21.01.13, 22.01.13, 26.01.13, 27.01.13 9.01.13 9.01.13 9.01.13 TOTAL
1 1 1 1 1 4 7 1 1 1 31
Page 33 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THE MONTH OF DECEMBER 2012 S NO. TPQA INSPECTIONS DURING THIS MONTH DATES OF VISIT 29.02.2013 Total NO. OF VISITS 1 1
PACKAGE NO
NAME OF WORK Construction of Minor Bridge at Km 15/2 near Chakaligadda of Konada Ramatheertham R&B road to Konatalapalem (via) Yerukonda, Pasupam, Kollayavalasa (ZP Road) in Vizianagaram District.
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISAKHAPATNAM DURING THIS MONTH OF JANUARY - 2013 S NO . TPQA INSPECTIONS DURING THIS MONTH DATES OF VISIT NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004 Construction of cyclone shelter at Venkayyapalem in Rambilli Mandal Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal 03.01.13, 05.01.13 08.01.13, 19.01.13 22.01.13, 30.01.13 03.01.13, 09.01.13 10.01.13, 17.01.13 23.01.13, 30.01.13 03.01.13, 17.01.13 23.01.13, 30.01.13 NO. OF VISITS 6
PACKAGE NO
NAME OF WORK
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002
NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003
Page 34 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
4 5 6 7 8 9 10 11 12 13 14 15 16
NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003 NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/002
Construction of cyclone shelter at Bangarrampeta in Nakkapalli Mandal Construction of cyclone shelter at Ratnayampeta in Payakaraopeta Mandal Construction of cyclone shelter at Gajapathinagaram in Payakaraopeta Mandal Road from R&B road to B.P Kallalu to Matchavanipalem Road from NH-5 to Ramarayyadupalem Road from R&B to road to Rajakoduru Road from R&B to road to Krishnampalem B.T to the road from R & B road to Venkayyapalem Road from R & B road to Pothurajanapalem Road from R&B road to Pedateenarla to Chinateenarla Road from Upamaka Rajayyapeta R&B road to Janakayyapeta Providing B.T to the road from Vempudi to Patimeeda B.T to the road from R&B to Mullaparra up to beach end
03.01.13, 30.01.13 04.01.13, 12.01.13 04.01.13, 09.01.13 12.01.13 18.01.13 19.01.13 19.01.13, 22.01.13 19.01.13 19.01.13, 22.01.13 11.01.13 23.01.13 23.01.13 23.01.13 23.01.13
2 2 3 1 1 2 1 2 1 1 1 1 1
Page 35 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
17 18 19 20 21 22 23 24 25 26 27 28 29
NCRMP/B-W/AP/RCS/PRED/03/S.Rayavaram/006 NCRMP/B-W/AP/MPCS/PRED/03/S.Rayavaram/009 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008 NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/007 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 NCRMP/B-W/AP/MPCS/PRED/03/Atchutapuram/006 NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/009 NCRMP/B-W/AP/RCS/PRED/03/Atchutapuram/007 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005 NCRMP/B-W/AP/MPCS/PRED/03/Paravada/005
Road from R&B Road to Revupolavaram Cyclone shelter . Construction of Cyclone shelter at Bangarampalem I&II H/O Vakadu. Road from R&B road to Gajareddypalem Construction of cyclone shelter at Rajayyapeta Road from ZP Road Palamanpeta to Korlayyapeta Construction of cyclone shelter at Palmanpeta Construction of cyclone shelter at Kadapalem Construction of cyclone shelter at Vadapalem Road from R&B road to Vadapalem Road from R&B road to Kothapatnam Road from Rajala R&B road to Rajarayyudupalem Construction of cyclone shelter at Jalaripeta Construction of cyclone shelter at Mutyalammpalem
31.01.13 31.01.13 08.01.13, 19.01.13 22.01.13 09.01.13, 17.01.13 09.01.13, 17.01.13 09.01.13, 17.01.13 08.01.13 08.01.13 08.01.13 08.01.13 08.01.13 11.01.13 11.01.13 TOTAL
1 1 3 2 2 2 1 1 1 1 1 1 1 53
Page 36 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DURING THIS MONTH OF JANUARY 2013 TPQA INSPECTIONS DURING THIS MONTH DATES OF VISIT NCRMP/B-W/ AP/RCS/ PRED/04/ KARAPA/001 NCRMP/B-W/ AP/RHB/ PRED/04/ KARAPA/001 NCRMP/B-W/AP/RHB/ PRED/04/ Katrenikona/003 Road from approach road to cyclone shelter at adavipudi in e.g.dt. Road from gurajanapalli to bandulavaripalem Road from PR road to Dasarivanipeta and to Cyclone Shelter Road from R&B Road to G.Musalayyapeta CS Road from R&B Road to P.Chodipallipeta CS Road from R&B Road to K.Chodipallipeta CS NCRMP/B-W /AP/RCS/PRED/04/ Thondangi/004 Road from R&B Road to Hukumpeta CS Road from R&B Road to Gaddipeta CS Road from R&B Road to Danavaipeta CS Cyclone Shelter at Avulamanda and of Thondangi Mandal , E.G.Dt. Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal, E.G.Dt. Road from R&B Road to Chinaraghavulapeta Cyclone Shelter Nil Nil 16.012.2013 Nil Nil Nil Nil Nil Nil 03.01.2013, 11.01.2013, 15.01.2013 and 31.01.2013 03.01.2013, 11.01.2013, 15.01.2013 and 31.01.2013 NIL NO. OF VISITS Nil Nil 1 Nil Nil Nil Nil Nil Nil 4 4 NIL
S NO.
PACKAGE NO
NAME OF WORK
1 2 3 4 5 6 7 8 9 10
Page 37 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
13
16
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS OF YEAR-II WORKS DURING THIS MONTH JANUARY 2013 S NO . 1. 2. NCRMP/B-W/AP/RCS/PRED/05/Kalla/003 3. 4. 5. 6. NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/005 7. 8. NCRMP/B-W/AP/RCS/PRED/05/Bhimavaram/004 PACKAGE NO NAME OF WORK Road from R&B road to Ayodya lanka Marrimula cyclone shelter. Road from R&B road to Modi Cyclone Shelter Road from R&B road to S.C Bose Colony Cyclone Shleter Construction of approach road to cyclone shelter in Losari of Bhimavaram Mandal. Road from R&B road to Kothakayalathippa cyclone shelter Road from Narsapur Perupalem R&B road to Mandavarithota Road from Mollaparru R & B road to Mollaparru Patha Colony Road from K.P Palem (N) Panchayat office to Metturevu Palli palem TPQA INSPECTIONS DURING THIS MONTH NO. OF DATES OF VISITS VISITS 19.01.2013 10.01.2013 10.01.2013 02.01.2013 1 1 1 1
NCRMP/B-W/AP/RCS/PRED/05/Achanta/002
Page 38 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
9. 10. 11. 12. 13. NCRMP/B-W/AP/RHB/PRED/05/Bhimavaram/005 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/009 NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/007 NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/006 NCRMP/B-W/AP/RHB/PRED/05/Kalla/004 NCRMP/B-W/AP/RCS/PRED/05/Narsapur/006
R&B road to Chinamynavanilanka P.R road to Ramanujapuram Road from P.R road to Prakasapuram K.G. R&B Road to Mamidipudi of Kalawapudi. Road from Dongapindi R & B Road to Revu (Pallipalem) in Dongapindi of Bhimavaram Mandal. Road from R & B Road to Sarvodhyanagar (Garivelladibba) H/o Losari of Bhimavaram Mandal. Khalipatnam R&B Road to Khalipatnam ferry Road from R & B Road at Metturevu to Parasavari meraka via Kandulapativari meraka Road from Narasapur Perupalem R &B Road to Janakiram Colony in Andevarimeraka of K.P.Palem (S) Road from Narsapur Perupalem R & B road to Dondaparthivari meraka Road from Narsapur Perupalem R & B Road to Melamvaripalem Perupalem(S) Road from Perupalem Mollaparru R & B road via Sattinenivarimeraka to K.D.Pallavapalem Road from Perupalem Dibbalapallipalem R & B road to Mellapallavapalem Road from Perupalem beach R & B Road to Challavarimeraka via Mucherlavarimeraka Road from Perupalem R&B road to Dindla Road from Narsapur Perupalem R & B road to Nellipallipalem via Ambedkar colony Harijanapeta Road from Perupalem R & B Road to Kouruvaripalem Road from SP R&B road to Pasaladeevi
1 1 1 1 1 1 1 1 1
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/008
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010
Page 39 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
27. 28. 29. 30. 31. 32. 33. 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45. 46. NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/001 NCRMP/B-W/AP/MPCS/PRED/05/Narsapur/003 NCRMP/B-W/AP/MPCS/PRED/05/Mogalturu/002 NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014 NCRMP/B-W/AP/RHB/PRED/05/Narsapur/013 NCRMP/B-W/AP/RHB/PRED/05/Narsapur/012
LT R&B road to Modi SP R&B road to Gannabathulavari palem of Chamakuripalem Road from R&B road to SC Colony of Pedalanka R&B road to Rajeev Nagar of Darbharevu SP R&B road to Pedathota of Turputallu R&B road to Peta of Turputallu R&B road to Pedathota of Turputallu R&B road to Guttulavarimeraka Road from R & B Road to Pulaparthivaripalem R&B road to Pedaedigapalem R&B road to Evanivarimeraka Road from PR Road to Prakashpuram SC colony of Vemuladeevi(E) Road from PR road to Vemuladeevi (E) colony (Via) Ralla cheruvu of Vemuladeevi (E) Road from PR road to Addalavarimeraka of Vemuladeevi(E) Sardupalli Palem of Vemuladeevi Pedamynavani lanka Chinamynavani lanka Vemuladeevi East Yetimondi of Perupalem Bellamkondavarimeraka
1 1 1 1 1 1 1 1 1 1 1 1 1 26
Page 40 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING THE MONTH JANUARY 2013 S NO. TPQA INSPECTIONS DURING THIS MONTH DATES OF VISITS Road from China Zinkapalem to Gollamanda via peda Zinkapalem Road from R&B road to Cyclone Shelter at Gollamanda 1 NCRMP/B-W/AP/RCS/PRED/06/Nagayalanka/006 Road from ZP Road to Cyclone shelter at Natchugunta Road from Krishna river to Elechetla Dibba Cyclone shelter 2 NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka/009 Road from R&B Road Dananjaya Colony to Krishnapuram 09.01.13 09.01.13 09.01.13 09.01.13 09.01.13 TOTAL NO. OF VISITS 1 1 1 1 1 5
PACKAGE NO
NAME OF WORK
Page 41 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THIS MONTH OF JANUARY- 2013 TPQA INSPECTIONS DURING THIS MONTH DATES OF VISIT Road from Ganapavaram R&B Road to Pedamarpuvaripalem. NCRMP/B-W/AP/RCS/PRED/07/Karalapalem/002 7.1.2013, 8.1.203, 17.1.2013, 26.1.2013, 27.1.2013, 30.1.2013, 31.1.2013. 5.1.2013, 30.1.2013, 31.1.2013. 5.1.2013 NO. OF VISITS 7
S NO.
PACKAGE NO
NAME OF WORK
Road from R&B road to chinapuluguvaripalem Road from Ganapavaram PR Road to Bonthagorlapalem.
4 5
NCRMP/B-W/AP/Br/R&B/07/Bapatla/010
Reconstruction of HLB @ km 5/2 of Bapatla Suryalanka road across perali drain in Guntur District. Road from R & B Road to Hanumanth Nagar.
2 1 1 4 19
NCRMP/B-W/AP/RCS/PRED/07/Pv palem/001 6 7 NCRMP/B-W/AP/RCS/PRED/07/Pv palem/001 Road from R & B Road to Adarshnagar. Road from R & B Road Allur to Yadavapalem TOTAL
Page 42 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE MONTH OF JANUARY-13 Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 PACKAGE NO NCRMP/B-W/APMPCS/PRED/ 08/NG Padu/003 NCRMP/B-W/AP/Br/R&B/ 08/Kanaparthi/012 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/002 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/002 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/002 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/002 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/001 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/001 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/001 NCRMP/B-W/AP/RHB/PRED/ 08/Ulavapadu/07 NCRMP/B-W/AP/RHB/PRED/ 08/Tangutur/09 NCRMP/B-W/AP/RHB/PRED/ 08/Tangutur/10 NCRMP/B-W/APMPCS/PRED/ 08/Ulavapadu/001 NAME OF WORK Kanaparthy cyclone shelter in Nagulappapadu mandal. Construction of High level Bridge at Km 16/10 of Naguluppalapadu Kanaparthi road in Prakasam District Road from NH5 to Mulaguntapadu Road from Pakala R&B road to Mosanaladinne Road from R&B road to Binginapalli Harijanawada Cyclone Shelter Road from R&B road to Chalivendradibba Road from Pakala ZP Road to Aulavaripalem Cyclone shelter Road from R&B Road to Somarajupalli Road from R&B road to Narravaripalem Road from MC Road to Subbarayudu Satram Road from R&B road Pellur to Vasepallipadu Road from R&B road to Kesupalem Chakicherla cyclone shelter in Ulavapadu mandal prakasam district TPQA INSPECTIONS DURING THIS MONTH NO. OF DATES OF VISIT VISITS 04.01.2013 03.01.2013 05.01.2013, 10.01.2013, 29.01.2013, 30.01.2013, 05.01.2013, 10.01.2013, 26.01.2013, 28.01.2013, 31.01.2013 10.01.2013 10.01.2013, 15.01.2013, 23.01.2013 25.01.2013, 28.01.2013 10.01.2013 10.01.2013 10.01.2013 11.01.2013 10.01.2013, 23.01.2013 24.01.2013, 28.01.2013 10.01.2013 11.01.2013 TOTAL 15.01.2013 31.01.2013 15.01.2013 29.01.2013 1 1 6 7 1 5 1 1 1 1 4 1 1 31
Page 43 of 93
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THE MONTH OF JANUARY 2013 SL NO 1 2 3 4 5 6 7 8 9 10 11 TPQA INSPECTIONS DURING THIS MONTH Package Number NCRMP/B-W/AP/RHB/PRED/ 09/V.CHALEM/RHB/007 NCRMP/B-W/AP/RHB/PRED/ 09/V.CHALEM/RHB/007 NCRMP/B-W/AP/PRED/ 09/MUTHUKUR/RHB/006 NCRMP/B-W/AP/PRED/ 09/MUTHUKUR/RCS/002 NCRMP/B-W/AP/RHB/PRED/ 09/VIDAVALURU/005 NCRMP/B-W/AP/RHB/PRED/ 09/VIDAVALURU/005 NCRMP/B-W/AP/RCS/PRED/ 09/KAVALI/006 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 NCRMP/B-W/AP/RHB/PRED/ 009/T.P.GUDUR/012 NCRMP/B-W/AP/RHB/PRED/ 009/T.P.GUDUR/012 Name of work Providing BT Surface to the road from R&B road to Edagali kandriga Road from Suvepalli-Pudiparthi road to Srikanth Colony Road from R&B road to Patuvarikandriga Road from R&B Road kappaladoruvu to bandla palem H.wada Road from KT R&B road to Allaganipadu to vavilla Road from R&B road Kancharlapalam HW to Alaganipadu. Road Connecting R&B Road through Voturu Village in SPSR Nellore District Providing BT road to Peda Pannam Gadu in Tada Mandal of Nellore Dt. Road from @ km 56/8 to CK Road to Periyavettu Kuppam Cyclone Shelter Ring Road to TP Gudur- Salipeta R & B Road via CS Puram and Mandapam Village Road from R & B Road C S Puram to Sivaramapuram DATES OF VISITS 01.01.2013, 02.01.2013 01.01.2013, 02.01.2013 01.01.2013 01.01.2013 11.01.2013 09.01.2013, 11.01.2013, 21.01.2013, 24.01.2013 21.01.2013 09.01.2013, 31.01.2013 09.01.2013, 31.01.2013 16.01.2013 16.01.2013 Total NO. OF VISITS 2 2 1 1 1 4 1 2 2 1 1 18
Page 44 of 93
Photo Presentation by Third Party Quality Audit Consultant of AP NCRMP Works during January 2013
In Joint Venture
Page 45 of 93
Page 46 of 93
Page 47 of 93
Page 48 of 93
Page 49 of 93
Page 50 of 93
Page 51 of 93
Measurement verification
Measurement verification
Measurement verification
Page 52 of 93
Site View
Site View
Measurement verification
Page 53 of 93
Page 54 of 93
Page 55 of 93
Page 56 of 93
Page 57 of 93
Page 58 of 93
Page 59 of 93
Page 60 of 93
Page 61 of 93
Page 62 of 93
Page 63 of 93
Name Board
Site View
Site View
Measurement verification
Page 64 of 93
Name Board
Measurement verification
Measurement verification
Page 65 of 93
Name Board
Site view
Site view
Site view
Page 66 of 93
Name Board
Site View
Measurement verification
Page 67 of 93
Name Board
Name Board
Site view
Measurement verification
Page 68 of 93
Village board
Name board
Site View
Site View
Page 69 of 93
Name board
Site View
Site View
Site View
Page 70 of 93
Name board
Site View
Page 71 of 93
Page 72 of 93
Page 73 of 93
Page 74 of 93
Page 75 of 93
Page 76 of 93
Page 77 of 93
Page 78 of 93
Page 79 of 93
Page 80 of 93
Page 81 of 93
NCRMP TPQA inspection of Road from R&B road Kancharapalem HW to Alaganipadu of Nellore Dt. On 20.12.12 Collection of WBM Gr-II aggregates
Page 82 of 93
NCRMP TPQA inspection of Road from R&B road Kancharapalem HW to Alaganipadu of Nellore Dt. On 20.12.12 Wearing coat is in progress
Page 83 of 93
NCRMP TPQA inspection of Road from R&B road Kancharapalem HW to Alaganipadu of Nellore Dt. On 29.12.12 Volumetric analysis for WBM Gr-II layer
Page 84 of 93
NCRMP TPQA inspection of Road from R&BroadKancharapalem HW to Alaganipadu of Nellore Dt o29.12.12-Carriage way width checking
Page 85 of 93
NCRMP TPQA inspection of Providing BT road to Peda Pannam Gadu in Tada Mandal of Nellore Dt on 18.12.2012-Collection of WBM Gr-II aggregates
Page 86 of 93
View of CC road
Page 87 of 93
Page 88 of 93
View of CC road
Page 89 of 93
NCRMP TPQA inspection of Road from R&B road Kancharapalem HW to Alaganipadu on 11.01.13-Collection of WBM Gr-III aggregates
Page 90 of 93
NCRMP TPQA inspection of Road from R&B road Kancharapalem HW to Alaganipadu on 21.01.13- WBM Gr-III layer thickness checking
Page 92 of 93
Page 93 of 93