Advantages of HVDC Over Ac Transmission
Advantages of HVDC Over Ac Transmission
. 250 km Baltic Cable between Sweden and Germany ). Endpoint-to-endpoint long-haul bulk power transmission without intermediate 'taps', for example, in remote areas. Increasing the capacity of an existing power grid in situations where additional power wires are difficult or expensive to install. Allowing between transmission AC unsynchronised
The main reason behind the HVDC transmission: A HVDC transmission line costs less than an AC line for the same transmission capacity. However, the terminal stations are more expensive in the HVDC case due to the fact that they must perform the conversion from AC to DC and vice versa. But above a certain distance, the so-called "break-even distance", the HVDC alternative will always give the lowest cost. The break-even-distance is much
smaller for submarine cables (typically about 50 km) than for an overhead line transmission. The distance depends on several factors (both for lines and cables) and an analysis must be made for each individual case. The importance of the break-evendistance concept should not be overstressed, since several other factors, such as controllability, are important in the selection between AC or HVDC.
distribution systems. Reducing the profile of wiring and pylons for a given power transmission capacity. Connection of remote generating plant to the distribution grid. Stabilising a predominantly AC power-grid,without maximum circuit current. increasing short prospective
(Typical
investment
costs
for
an
overhead
line
transmission
with
AC
and
HVDC).
Drawback
of
the
HVDC
Transmission system:
The required static invertors are expensive and cannot be overloaded very much. At smaller transmission distances the losses in the static inverters may be bigger than in an AC powerline, and the cost of the inverters may not be offset by reductions in line construction cost. In contrast to AC systems, realizing multiterminal systems is complex, as is expanding multiterminal existing systems. schemes to Controlling
APPLICATION
first Rihand long
OF
-
HVDC
Delhi and
TRANSMISSION IN INDIA:
Chandrapur - Padghe were the distance HVDC projects in India. The 1500 MW Rihand - Delhi transmission was put into service in 1990. It transmits Rihand power from the Singrauli thermal
power complex with a combined power generation of several thousand MW, over a distance
of 814 km to Dadri station, close to the capital of India. The 1500 was put MW Padghe into
(DOE), national
Govt. HVDC on
of R
India, &D
Chandrapur transmission
service in 1998. It transmits power from the Chandrapur in the eastern part of Maharashtra over a distance of 736 km to the Mumbai area. In 1983-84, HVDC kV, in 100 when India, MW
CONCLUSIONS:
The Project has provided the necessary support to build an infrastructure facilities to carry out research and development activities concerning analysis, operation and control of integrated DC power system. In addition to manpower training the facilities have been extensively used for the following purposes: To develop software for simulation and analysis of HVDC systems. To develop and test new concepts in microprocessor based control and protection of HVDC converter and Static Var System.
decision was being taken to introduce a 100 Government of India supported experimental line HVDC project - called National HVDC project - with the sole objective of developing technology, execution monopole to indigenous entrusted BHEL. project its This
involved
conversion of one circuit of existing double circuit 220 kV AC lines between Lower Sileru (Andhra Pradesh) and Barsoor (Madhya Pradesh) to HVDC transmission on the same tower. Consequently, in 1986,
To carry out research in a) Operation & Control of HVDC links connected to weak
converter control
REFERENCE:
S.RAO EHV AC, HVDC TRANSMISSION AND DISTRIBUTION ENGINEERING. C.L.WADHWA ELECTRICAL POWER SYSTEMS.