Using Primavera P6, the schedule update process lessons learned are organized into four main steps: PLAN, UPDATE, REVIEW / ANALYZE and COMMUNICATE. In this installment we are going to focus on the first step, Plan. If you missed the first part of this series, begin here.
Do your construction projects exist in a vacuum? | Project Planning Construction Document Manager Thats Robust Conceptual Estimating when Planning Construction Projects The Right Way to Pass Through Construction Job Costs for Accounting How to effectively plan schedule using Primavera P6?
Select Month
Select Category
It should be noted that an activity listing grouped by Activity Code (View menu, Group and Sort by) is an option in the Activity window. However, grouping by Resources is not as functional in the Activity window but available in the Assignments window.
Provide training
The Planner / Scheduler should provide training to each responsible party to ensure all parties understand their role in the update process. Training should include details on how to update the schedule, how to review the schedule, and how to add fragnets for change management. The schedule basis should also include a description of how project control performance will be measured and assessed in respect to the schedule including rules for earning progress and the procedures for evaluating progress and forecasting remaining durations. [1] Training should provide an understanding of the update reports (i.e. short interval schedules based on previous update) and what information is required of each individual to complete these reports (i.e. activity remaining duration/percent complete and impacts and mitigation).
Gather data
The first step in the update process, prior to any data input, is to gather the data. The Planner / Scheduler should provide the update report or layout to the team and responsible parties at regularly scheduled intervals based on the frequency of the update process. Suggested information to provide in the update report or layout is: Activity ID, Activity Name, Original Duration, Remaining Duration, Total Float, Start, Finish, Actual Start, Actual Finish, Blank column for remarks. It is also helpful to include columns for Predecessor and Successors. A useful feature in Primavera P6 is the Progress Spotlight Option in the Activities window. By selecting Progress Spotlight, the schedule layout is highlighted to a specific time period (based on the Timescale minimum time increment. For monthly updates, it is useful to highlight two months; for weekly updates, it is useful to highlight two weeks (as shown in Figure 2). This will provide the Planner / Scheduler with data for one time-period of actual dates plus one time-period of forecasted dates / logic.
Each of the responsible parties should fill out their respective scope of work on the update sheet. In the Activities window, the layout can be sorted by responsible party using Group, Sort options (located under the View menu) and selecting the appropriate Responsibility activity code. In the Activity Assignments view, the layout can be sorted by resource using Group, Sort options.
Duration types
Typically, a project can be subdivided into four phases: Initial Phase, Planning Phase, Execution Phase, and Closeout Phase. The level of incorporating estimated work durations based on production factors may change dependent on the phase of the project. As scope of work is being defined, production rates and durations are estimated. Duration can then be based on these estimates. However, once the scope has been clearly defined and the project duration established, production rates are typically monitored in order to maintain successful project completion. Defining the activity Duration type determines the use of production rates and how they affect progressed durations. There are three Duration Types to consider: Fixed Units and Duration established Budgeted Units and Duration calculate the Units/Time production rate. Typically used after contract award and during execution phases. Fixed Units/Time and Duration established Units/Time production rates and Duration calculate the projected Budgeted Units. This Duration Type is used when established Budgeted Quantities are not assigned but are secondary to the Duration and the Production Rate (i.e. Time and Material Schedule). The last two Duration Types are typically used during the Initial Phase or constructability phase to calculate durations based on either Budgeted Units or Units per Time. Fixed Units established Budgeted Units calculate the Duration based on defined Units/Time production rates. Fixed Units/Time established Units/Time production rates calculate Duration based on desired Budgeted Units. These settings are based on resource definition and settings both at the resource and project levels. The last two options, Fixed Units and Fixed Units/Time (typically used to prepare a constructability schedule) calculate Duration based on the settings within the Project Details.
Calculation settings
When calculating actual dates and project progress, P6 applies certain rules which affect the process outcome (Tools menu, Schedule, Options). When external relationships exist to and from other projects, the option to ignore these external relationships will determine whether those relationships affect the currently opened schedule. (Note: If this option is not selected when importing/exporting files from other databases, P6 preserves External dates based on the external relationships.) P6 has an option to apply Expected Finish dates to activities to calculate activity completions. This can be used for long lead procurement items or when a completion date determines the activitys duration. In P6 there are three options available when scheduling progressed activities: retained logic, progress override, and actual dates. Each of these settings affects the way the scheduled dates are calculated in an update and are important for the Scheduler to understand. The Retained Logic setting maintains the as-built sequence of activities regardless of actual work. With the Progress Override setting the activity logic sequence can be overridden based on actual work. The direct predecessor activitys dates (Remaining Early) drive those successor activities which have not started. When the predecessor is assigned an Actual Finish, the activitys dates (Remaining Early) are driven by the Data Date. When the activity has an Actual Start, its Remaining Duration drives the Remaining Early Finish. The Actual Dates setting allows for future actualized activity dates to calculate sequence.
Resource settings
P6 calculates resource actuals (units/cost) based on the settings defined at the Resource level (Resource Details) and Project level (Project Details). That is the first step of the schedule update process. Keep an eye out for the next step which is Review/Analyze. Should you have questions about this article, please feel free to leave an email or contact us at [email protected]. Bibliography No. 1 , AACE International 2006 Chapter 7.2 Schedule Planning and Development Chapter 8.1 Project Control Plan Implementation Chapter 9.2 Progress and Performance Management Chapter 10.1 Project Performance Assessment Chapter 10.2 Forecasting Chapter 10.3 Change Management
This entry was posted in Primavera P6 , Tips and Tricks and tagged Primavera P6 , Project Planning, Project Scheduling by Hill-PCI Group. Bookmark the permalink .
I would like to know the procedure to update a WBS Summary Activity loaded with resources. This is apart from updating individual activities under this WBS Summary Activity.
Reply
Thank you for your inquiry Raymund. I also received your email and have already directed it to appropriate person. We are glad to hear that you find the series helpful. Stay tuned for the reply. Again, thanks! hillpcigroup (^ruby)
Reply
I am much confused now a days with updating a fully resource loaded P6 plan. I update the schedule weekly in terms of Actual units. and when i schedule it, the previous interval values goes on changing (i mean previous weeks actual values changes each time i schedule the plan, that should not be changed of course to analysize the previous achievements) Would really appreciate appropriate answer via email. thanks.
Reply
Pingback: Homepage
hello sir, please suggest me the steps in updating the schedule in terms of resource based. and i dont know how to update in primaverabut i loaded the resource and just doing everything in excel.it ll be helpful for me if u guide me .thank you
Reply
Thanks for your email. I am forwarding your inquiry to the scheduling team to get back to you soon. Happy holidays!~
Reply
Someone from the team will be touching base with you about the matter. Thanks for visiting our website.