Chap 07 Cost-Management
Chap 07 Cost-Management
Practice Exam 1. One way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI B. Multiply by SPI C. Multiply by CPI D. Divide by CPI 2. Estimate at completion (EAC) is a periodic evaluation of: A. Cost of work completed B. Value of work performed C. Anticipated total cost at project completion D. What is will cost to finish the job 3. If earned value (EV) =350, actual cost (AC)=400, planned value (PV) =325. What is cost variance (CV)? A. 350 B. -75 C. 400 D. -50 4. Double declining balance is a form of: A. Decelerated depreciation B. Straight line depreciation C. Accelerated depreciation D. Life cycle costing 5. Analogous estimating: A. Uses bottom-up estimating techniques B. Is used most frequently during the executing processes of the project C. Uses top-down estimating techniques D. Uses actual detailed historical costs 6. The cost of choosing one project and giving up another is called A. Fixed cost B. Sunk Cost C. Net Present value (NPV) D. Opportunity cost 7. The main focus of life cycle costing is to: A. Estimate installation costs B. Estimate the cost of operations and maintenance C. Consider installation costs when planning the project costs D. Consider operations and maintenance costs in making project decisions 8. Cost performance measurement is BEST done through which of the following? A. Asking for a present complete from each team member and reporting that in the monthly progress report B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance.
18. Project setup costs are an example of: A. Variable costs. B. Fixed costs. C. Overhead costs. D. Opportunity costs. 19. Value analysis is performed to get: A. More value from the cost analysis. B. Management to buy into the project. C. The team to bye into the project. D. A less costly way of doing the same work. 20. Who has the cost risk in a fixed price (FP) contract? A. Team. B. Buyer. C. Seller. D. Management. 21. Which of the following represents the estimated value of the work actually accomplished? A. Earned Value (EV). B. Planned value (PV). C. Actual Cost (AC). D. Cost Variance (CV). 22. You have four projects from which to choose one. Project A is being done over a six year period and has a net present value (NVP) of U.S. $70,000. Project B is being done over a three year period and has a NPV of U.S. $30,000. Project C is being done over a five year period and has an NPV of U.S. $40,000. Project D is being down over a one year period and has an NPV of U.S. $60,000. Which Project Would You choose? A. Project A. B. Project B. C. Project C. D. Project D. 23. Project A has an internal rate of return (IRR) of 21 percent. Project N has an IRR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of 19 percent. Which of these would be the BEST project? A. Project A.
25. Your company can accept one of three possible projects. Project A has a net
present value (NPV) of U.S. $30,000 and will take six years to complete. Project B has an NPV of U.S. $60,000 and will take three years to complete. Project C has an NPV of U.S. $90,000 and will take four years to complete. Based on this information, which project would you pick? A. they all have the same value. B. Project A. C. Project B. D. Project C. 26. The seller tells you that your activities have resulted in an increase in their costs. You should: A. Recommend a change to the project cists. B. Have a meeting with management to find out what to do. C. Ask the seller for supporting information. D. Deny any wrongdoing. 27. Your cost forecast shoes that you will have a cost overrun at the end of the project. Which of the following should you do? A. Eliminate risks in estimates and re-estimate. B. Meet with the sponsor to find out what work can be done sooner. C. Cut quality. D. Decrease scope. 28. A new store development project requires the purchase of various equipment, machinery and furniture. The department responsible for the development recently centralized its external purchasing process and standardizes its new order system. In which document can these new procedures be found? A. Project scope statement. B. WBS. C. Staffing management plan. D. Organizational policies. 29. Early in the life of your project. You are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. If would be BNEST to: A. Agree to analogous estimating as it is a form of expert judgment. B. Suggest life cycle costing as a compromise. C. Determine why the sponsor wants such an accurate estimate.
36. You are a project manager for a large consulting firm. Your superior has just
asked for your input on a decision about which project you company should pursue. Project A has an internal rate of return (IRR) of 12 percent. Project B has a predicted benefit cost ratio (BCR) of 1.3 Project C has an opportunity cost of U.S $75,000. Project D has a payback period of six months. If you had to choose based on this data, which project would you select? A. Project A B. Project B C. Project C D. Project C
37. You are about to take over a project from another project manager and find
out the following information about the project. Activity Z has an early start (ES) of performance index (CPI) is 1.1. Schedule performance index (SPI) is 0.8. There are 11 stakeholders on the project. Based on this information, which of the following would you be the MOST concerned about? A. Schedule B. Float C. Cost D. The number of available resources
38. The difference between the cost baseline and the cost budget can be BEST described as? A. The management reserve B. The contingency reserve C. The project cost estimate D. The cost account 39. You provide a project cost estimate to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should you do? A. Start the project and constantly look for cost savings B. Tell all the team members to cut 15 percent from their estimates C. Inform the sponsor of the activities to be cut D. Add additional resources with low hourly rates
Project Cost Management project cost. Choice D is often done by inexperienced project managers who know of nothing else. Now only does it provide little information, but also it cannot be used to predict the future. Choice B is the best answer since it looks at the past and uses this information to estimate future costs. 9. Answer D Explanation The CPI is less than one, so the situation is bed. Choice D is the best answer. 10. Answer C Explanation Earned value questions ask for a calculation or an interpretation of the results. See the tricks under this topic in this book. 11. Answer D Explanation A change control procedure is not required to obtain estimates, but without the other three choices, you cannot develop the estimates. You need the WBS to define the activities, the network diagram to see the dependencies and the risks to determine contingencies. Note: These are high-level risks, not the detailed risks we identify later in the planning process group. 12. Answer A Explanation Parametric estimates use a mathematical model to predict project cost or time. 13. Answer D Explanation This estimate has a wide range. It is done during project initiating, when very little is known about the project. 14. Answer B Explanation This question is designed to determine whether you understand that estimates should be in a range and what are the standard ranges. 15. Answer D Explanation The law of diminishing returns has nothing to do with choosing between projects. Notice that this question requires you to understand that projects should be systematically selected and that the selection should be based on some formal evaluation of all projects available. Many project managers have little experience or knowledge of the activities such as this that go on during project initiation. Though there are not many questions on the exam on project initiation, a little study can help you get many of these questions right, even if you are not currently involved in initiating projects in you company. 16. Answer B Explanation The opportunity cost is the value of the project that was not selected; the lost opportunity.
Project Cost Management 17. Answer A Explanation You are training the team on skills required for the project. The cost is directly related to the project and thus a direct cost. 18. Answer B Explanation Setup costs do not change as production on the project changes. Therefore, they are fixed costs. 19. Answer D Explanation Notice that you need to know the definition of value analysis to answer this question. Also notice that the other choices could be considered correct by someone who does not know the definition. 20. Answer C Explanation If the costs are more than expected under a fixed price contract, the seller mist pay those costs. As explained in the procurement chapter, cost risk refers to the person who will have to pay for the added cost if costs escalate. Because the price is fixed, the seller will have to pay any increased costs out of their profit. Naturally, this does not include increased PRICE due to change orders. A fixed price contract and the PRICE could be changed with changed with change orders. 21. Answer A Explanation It can confusing to differentiate earned value terms from each other. The definition presented here is for EV or earned value, so choice A is the best choice. 22. Answer A Explanation The number of years is already included in the calculation of NPV. You simply pick the project with the highest NPV. 23. Answer C Explanation Remember, the internal rate of return is similar to the interest rate you get from the bank. The higher the rate is, the better the return. 24. Answer B Explanation you should pick the higher number. 25. Answer D Explanation Remember, project length is incorporated when computing NPV. You would choose the project that provides the most value, in this case the project with the highest NPV.
26. Answer C Explanation This is a professional and social responsibility/procurement/cost question. The situation described involves a claim. The best thing to do would be to get supporting information to find out what happened and take corrective action for the future. After choice C and negotiation, Choice A would most likely occur. Choice D is unethical. Choice B is a meeting with your management and should not occur until you have all the information. 27. Answer A Explanation look for the choice which would have the least negative impact in this situation. You would not need to meet with the sponsor to do choice B. choices C and D always have negative effects. The choice with the least negative impact is choice A. 28. Answer D Explanation Procedures for the rental and purchase of supplies and equipment are found in the organizational policies. 29. Answer A Explanation this is a tricky question. In order to pick the best answer, you need to realize that analogous estimating is a form of expert judgment. Notice choice C, determine why, sounds like a good idea, but look at the rest of the sentence. Analogous estimates are not accurate. Reading every word of this choice helps eliminate it. 30. Answer B Explanation The overall project budget (choice A) may be included in the project charter but not the detailed costs. Even small projects (choice C) should have a budget and schedule. It is not impossible to create a project budget before the project management plan is created (choice D). It is just not wise, as the budget will not be accurate. 31. Answer C Explanation Choice A is too general. The estimates are already created created in this example, so the answer is not B. The answer is not D, cost control, because the baseline has not been created. The correct answer is C. 32. Answer B Explanation Sunk costs (choice B) are expended costs. The rule is that they should not be considered when decided whether to continue with a troubled project. 33. Answer A Explanation A project without a charter is a project without support. The information provided for the other projects does not justify selecting them. Even
Project Cost Management the number of resources is not relevant since the number of resources for the new project is not supplied. 34. Answer D Explanation To answer this question, you must look for a choice that would take longer and cost more. If you picked choice A, reread it. It says scope was changed, not necessarily added to. If the change was to reduce the scope, it might also have reduced cost. Though it would take time to handle the event described in choice B, the impacted activity might not be on the critical path, and thus might not affect time. Choice C would definitely add cost, but not necessarily time. Only choice D would negatively affect both time and cost. 35. Answer C Explanation Actual costs are used to measure CPI, and there is no reason to use SPI in this situation, so choices A and B are not correct. Using past history (choice D) is another way of saying analogous. The best way to estimate is bottom-up (choice C). Such estimating would have improved the overall quality of the estimate. 36. Answer A. Explanation This is a question about project selection and could easily be included in other chapters. In order to interpret the information, you need to know what each item is. The benefit cost ratio for choice B is unfavorable. There is not enough information provided to support recommending or not recommending choices C or D. This leaves only choice A with a 12 percent return, as providing a clear benefit. 37. Answer A Explanation This is one of those questions that combines topics from various knowledge areas. Did you fall into the trap of calculating the float for Z? The amount of float for one activity and the number of stakeholders does not tell you anything in this case, so choices B and D cannot be the best answers. The CPI is greater than one and the SPI is less that one. Therefore, the thing to be most worried about would be schedule. 38. Answer A Explanation The cost accounts are included in the project cost estimate and the management reserve is added to that to come up with the cost baseline. Thereafter the management reserve is added to come up with the cost budget. Therefore, only choice A is correct. 39. Answer C Explanation This question is full of choices that are not correct project management actions. If you picked the wrong answer, look again at the choices and try to determine what you are missing. Whatever it is, it will show up more than once on the real exam!
Project Cost Management To answer the question, you must first realize that it is never appropriate for a project manager to just cut estimates across the board (choice B). The project manager should have created an estimate with realistic work package estimates that do not include padding. Then, if cost must be decreased, the project manager can look to cut quality, decrease risk, cut scope or use cheaper resource (and at the same time closely monitoring the impact of change on the project schedule). One of the worst things the project manager can do is to start a project while knowing that the time or cost for the project is unrealistic. Therefore, choice A cannot be best. Notice that choice D suggests adding additional resources. That would cost more. Choice C involves evaluating, looking for alternatives and then going to the sponsor to tell him the impact of the cost cutting.