2013.03.18 Civil Works Daily Progress Report

This daily progress report summarizes infrastructure work on a haul road project. On the date reported, work included measuring individual land boundaries in Block B, fill work in Block B until Station 1+800, and standby of road filling in Block A due to a broken-down dump truck. A welding machine used for container reinforcement broke down and was under repair. The report documents weather conditions, personnel and equipment hours, locations and descriptions of work, progress percentages, and notes difficulties including delays and equipment issues.

Uploaded by

Adited Mln
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
75% found this document useful (4 votes)
3K views2 pages

2013.03.18 Civil Works Daily Progress Report

This daily progress report summarizes infrastructure work on a haul road project. On the date reported, work included measuring individual land boundaries in Block B, fill work in Block B until Station 1+800, and standby of road filling in Block A due to a broken-down dump truck. A welding machine used for container reinforcement broke down and was under repair. The report documents weather conditions, personnel and equipment hours, locations and descriptions of work, progress percentages, and notes difficulties including delays and equipment issues.

Uploaded by

Adited Mln
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Page 1 of 2

DAILY PROGRESS REPORT


PROJECT NAME PROJECT DESCRIPTION WEATHER Clear x TEMP Fair 15 - 20
RAINY

: CIVIL & INFRASTRUCTURE BEP : INFRASTRUCTURE - HAULROAD TIME Rain 30 -35 Med x Med x Heavy R. x 35 -40 High
MANAGER

00

01

02

03

04

05

06

07

08

09

10

11

12

13

14

15

16

17

18

19

20

21

22

23

Cloudy 20 - 25 Still Dry

Shower 25 - 30 x Low Low

SHOWER RAIN HEAVY RAIN


SUPERINTENDENT UNSKILL LABOR. SKILL LABORERS

x x x NUMBER OF PERSONNEL AND MAJOR EQUIPMENT


TRUCK (PICK UP) TRUCK (DUMP) TRUCK DRIVER COMPACTOR COMPRESOR EXCA. H. 450 OPERATOR SURVEYOR

TRUCK (WATER)

MESIN POTONG

CONTRACTOR/SUBCON/SUPPLIER

HOURS 18 0 9 1 1

BEP PT.ARJA WAHANA BAKTI BENGKEL LAS KEMBAR REJEKI LOCATION BLOK A HR BEP/ATP BLOK B HR BEP/ATP HR BEP/ATP HR BEP/ATP

1 1 6

2 5

1 1

LV

HUMIDITY

DOZER

High

1 1 1 1

1 2

AND/OR DESCRIPTION OF WORK Pembangunan HR BEP ATP Cut & Fill Perkuatan gorong-gorong Container Pengukuran batas pembebasan lahan

ESTIMATED QUANTITIES ITEM Pekerjaan Fill Jalan Blok A/LW Fabrikasi Besi UNP Container Pengukuran batas lahan

VOL

SAT

PROGRESS THIS DATE TOTAL 95% 75% 93% 5% 85%

REMARKS: Include condition of traffic control and roadway; important discussions with contractor; rejected work or materials and reasons; delays, difficulties, accidents, utility damage and other unusual conditions and events; arrivals and departures of major equipment, visitors.

Conditions

Difficulty

A: Pengukuran batas lahan perorangan di blok B HR BEP B. Pekerjaan Fill HR Blok B PT.BEP sampai di STA 1+800 C. Kegiatan penimbunan jalan di blok A stand by karena unit DT Breakdown D. Buldozer D85 untuk pekerjaan HR BEP di blok A dibawa menuju tambang SBJ. A: Mesin las Pek. Perkuatan Gorong-gorong kontainer rusak, sedang dalam perbaikan

PREPARED BY: Asdiansyah

CERT. NO. 180313.CIV.DPR.BEP

SIGNATURE:

SHIFT DAY/NIGHT

Su. x

Mo.

Tu.

Wed.

Th.

Fr.

Sa.

WORK DATE: 18-Mar-13

TOTAL STATION

TOWER LAMP

SUPERVISOR

WIND

FUEL TANK

MESIN LAS

FOREMAN

GRADER

LOADER

GENSET

PC 300

PC 200

1 1

Page 2 of 2

DAILY PHOTO PROGRESS REPORT


PROJECT NAME PROJECT DESCRIPTION : CIVIL & INFRASTRUCTURE BEP : INFRASTRUCTURE - HAULROAD WORK DATE: SHIFT: 18-Mar-13 DAY