Extra Work Model
Extra Work Model
( code )
Richiedente
BS - 171
Kharafi National
45283 Non
Date
1-Sep-11 Non
To
Disciplina
Civil (Bldg)
Codice
CA
Backcharge
Assicurazione
Control Building, for foundation F1(16No's), F2 (2No's) & F3(1 No) demolising and casting of foundation as of revision in drawing.
Control Building, for foundation F1(16No's), F2 (2No's) & F3(1 No) demolising and casting of foundation as of revision in drawing. SAIPEM revised the drawing
PREVENTIVO
( ESTIMATION )
MANO D'OPERA ( MANPOWER ) QUALIFICA
( TRADE )
RIF.
( REF )
ORE
( HOURS )
PREZZO
( PRICE )
IMPORTO
( TOTAL )
MATERIALI E MEZZI D'OPERA (MATERIALS AND EQUIPMENT) DESCRIZIONE RIF. ORE PREZZO IMPORTO
( DESCRIPTION ) ( REF ) ( Qty ) ( PRICE ) ( TOTAL )
65 60 60 40 50 64
271.70 Material 238.80 Material uplift 15% 94.20 66.00 94.50 80.64
A3.01 A3.02
5050.00
5050.00 757.50
Subtotal
845.84
Subtotal
5,807.50
Totale KWD
6,653.34
ANNOTAZIONI
( NOTES ) none
( 1 ) Economia ( Time Work ) - Prezzi Unitari ( Unit Prices ) - Forfait ( Lump Sum )
Per Saipem
( Saipem Reps ) . KWD
Importo previsto
( Total estimated ) 6,653.34
L' Impresa
( Subcontractor )
CONSUNTIVO ( JOB CARD DATA ) Control Building, for foundation F1(16No's), F2 (2No's) & F3(1 No) demolising and casting of foundation as of revision in drawing. SAIPEM revised the drawing
MANO D'OPERA ( MANPOWER ) QUALIFICA ( TRADE ) Forman Chargehand Carpenter Mason Concrete finisher Helper/labourer RIF. ( REF ) URP SW 2 9 URP SW 2 10 URP SW 2 13 URP SW 2 14 URP SW 2 15 URP SW 2 16 ORE ( HOURS ) 52 54 60 40 35 64 PREZZO ( PRICE ) 4.18 3.98 1.57 1.65 1.89 1.26 IMPORTO ( TOTAL )
DATE
12-Oct-08
to
25-Oct-08
MATERIALI E MEZZI D'OPERA (MATERIALS AND EQUIPMENT) DESCRIZIONE ( DESCRIPTION ) RIF. ( REF ) A3.01 A3.02 ORE ( Qty ) 1 PREZZO ( PRICE ) 5010.00 IMPORTO ( TOTAL ) 5010.00 751.50
217.36 Material 214.92 Material uplift 15% 94.20 66.00 66.15 80.64
Total KWD
739.27
Total KWD
5,761.50
N ( NO )
Data ( Date )
N ( NO )
Data ( Date )
N ( NO )
Data ( Date )
739.27
5,761.50
6,500.77
L' Impresa
(Subcontractor)
Importo complessivo
(Total amount)
per SAIPEM
(SAIPEM Reps)
KWD 6,500.77