Standard Specifications
Standard Specifications
FOR
CONSTRUCTION AND MAINTENANCE
OF
ROADS AND BRIDGES
Issued Ul)der the AwftOrity of
The General Manager
Road Development Authority
Ministry of Highways
Sri Lanka
1989
i
DRAFTING COMMITTEE
This book of specificationshas been drafted by the following committee:
.. ' ". " ", ...",
Mr Denzil D Senanayake (Convenor)
Mr B M de Soysa .
Mr E F M Perera
Mr H C S Seshachar
Dr Kingsley Goonawardena
Mr G S Hattotuwegama
Mr M B S Fernando
Mr R P Nanayakkara
Mr D P Mallawaratchie
Dr Asoka de Silva
Mr S Palliyaguru
Mr Susil Weeratunga (Secretary)
ACKNOWLEDGEMENT
The drafting committee acknowledges with thanks the financial assistance received from Institute for
Construction Training and Development (leTAD) for the preparation of this book on their behalf, for
the use of the Highways Sector in Sri Lanka.
ii
PREFACE
This book of standard Specifications for construction and maintenance of roads and bridges, is intended
to cover all aspects of road construction and maintenance in Sri Lanka and to establish uniformity and
consistency in the procedures adopted.
In the preparation of each of these specifications, special efforts were made to simplify them suitably
for the easy use of the local contractor whilst at the same time maintaining the necessary standards
from the point of view of a quality job of work. Special emphasis is laid on quality control of works
and a separate chapter which deals with this aspects is incorporated.
A special feature of this book is the incorporation of a comprehensive set of specifications in respect
of road maintenance activities.
It is intended to revise these specifications from time to time and also to incorporate other specifications
as and when they become necessary. For this purpose it is hoped that there will be a feedback on the
application of these specifications.
iii
CONTENTS
No and Title of chapter
No and Title of section Page
100 101 Abbreviations 01
GENERAL 102 Definitions 01
103 Arrangements for 03
Traffic During
Construction
104 Control of Works 05
105 Control of Materials 06
106 General Rules for 06
Measurement and payment
107 Sieve Designations 09
200 201 Clearing and Grubbing 11
SITE CLEARING 202 Removal of Structures 14
and obstructions
300 301 Roadway Excavation 16
EARTHWORKS 302 Excavation and Back 21
fill of Structures
303 Borrow Excavation 24
304 Embankment Construction 25
305 Trench Excavation for 31
Utility Services and Reinstatement
306 . Explosives and Blasting Operations 34
400
401 Soil Subbases 39
SUBBASES, BASES
402 Stabilized Soil 42
AND SHOULDERS Subbases and Bases
403 Single sized Aggregate 46
Bases
404 Water bound and Dry 51
Bound Macadam Bases
405 Dense Graded Aggregate 54
Bases
406 Penetration macadam 56
Bases
407 Bitumen Bound Bases 60
408 Reconstruction of 64
Aggregate Bases
409 Shoulder Construction 67
500
501 Prime Coat 70
SURFACE APPLICATIONS, 502 Tack Coat 73
SURFACE 503 Hot bitumen 75
DRESSING AND Applications
SURFACINGS 504 Sand Sealing 77
iv
No and Title of chapter
No and Title of section Page
600
UNPAVED
ROADS
700
DRAINAGE
CONSTRUCTION
800
INCIDENTAL
CONSTRUCTION
RIGID PAVEMENTS
505
506..
507
601
602
603
701
702
703
704
705
706
707
801
802
803
804
805
806
807
808
809
810
811
901
Seal Coat Treatments
(Surface Dressings)
Asphalt Concrete
Surfacings
Cold Mix surfacings
79
87
101
Gravelling of Earth
Roads and Regravelling of
Gravel Roads
Priming of Gravel Roads
107
110
Maintenance of Earth
and Gravel Roads
113
Roadside and Leadaway
Surface Drains
Sub surface Drains
CUnderdrains)
Manholes, Catchpits
and Inlets
Under Ground Pipe Drains
Drainage Backfill
Behind Earth Retaining Structures
Weepholes for Earth
Retaining Structures
Pipe Culverts
115
118
121
124
128
130
132
Top Soiling
Grassing
Planting Trees, Shrubs, Vines Etc.
Rip Rap Protection
for embankment Slopes
Gabion Walls
Paved Side Walks
Precast Concrete
Kerbs and Channels
Guard Rails and
Walls, Guard Stones and Guide Posts.
Fencing
Road markings
Road Signs
137
139
143
147
150
153
156
160
164
166
171
Cement Concrete Pavements 179
v
900
1000
No and Title of chapter
No and Title of section Page
BRIDGES AND
OTHER
STRUCTURES
1100
MAINTENANCE OF
CARRIAGEWAY
1200
MAINTENANCE OF
SHOULDERS AND
ROADSIDE
1300
MAINTENANCE OF
DRAINAGE SYSTEMS
1001
1002
1003
1004
1005
1006
1007
1008
1009
1010
1101
1102
1103
1104
1201
1202
1203
1204
1205
1301
1302
1303
1304
Concrete for Structures 186
Steel Reinforcement 204
for Concrete Structures
Prestressing for Structures 207
Pile Foundations for 215
Structures
Well Foundations for 229
Structures
Random Rubble Masonry 235
Brick Work and 239
Block Work for Structures
Formwork for Structures 242
Bridge Expansion Joints 246
Bridge Bearings 248
Cold Mix for Patching 250
Patching Potholes 252
Ruts and Depressions
Edge Correction 260
Patch Sealing 264
Repairs and Correction 267
to shoulders and the
Road Side
General Upkeep of Shoulders 270
and the Road Side
Jungle Clearing along
the Road Side 272
Foot Walks 274
Kerbs and Channels 276
Clearing and reshaping of 278
Earth Drains
Clearing and Repairing 280
of Built - Up-Drainage Systems
Clearing, Desilting 282
and repairing of Culverts
Providing Scupper Drains 284
vi
1400
No and Title of chapter
No and Title.of section Page
MAINTENANCE OF
BRIDGES AND
CAUSEWAYS
1500
MAINTENANCE OF
ROAD SIGNS AND
MARKINGS
1600
QUALITY CONTROL
OF WORKS
1700
MATERIAL DETAILS
1800
DESIGNATION OF TESTS
FOR QUALITY CONTROL
OF MATERIAL AND
WORKS
1401
1402
1403
1404
1405
1406
1501
1502
1601
1602
1701
1702
1703
1704
1705
1706
1707
1708
1709
1801
1802
1803
1804
Steel Bridges 286
Timber Decked bridges 292
Prestressed Concrete 295
and Reinforced
Concrete Bridges
Sub Structures of Bridges 298
Cable Supported Foot Bridges 300
(Suspension Bridges)
Causeways 303
Road Signs 306
Road Markings 311
Control of Alignment 313
and Surface Regularity
Quality Control
314
Tests During Construction
Aggregates
329
Binders
336
Cement 338
Concrete Admixtures
340
Concrete Precast 340
Units
Filler for Asphalt Concrete 341
Paints 341
Soils 341
Timber
347
Aggregates .348
Bituminous Binder and Bitumen 349
Aggregate Mixes
Cement and Concrete 353
Soils
354
vii
100 GENERAL
101 ABBREVIATIONS
Wherever the foloowing abbreviations are used in these specifications or on the
plans, they shall be considered as representing the same as the respective expression as
given below:
AC
AIV
ASTM
BS
CBR
CMS
CRS
CSS
CS
DMB
DBST
GI
LAAV
LL
MC
MS
PI
PL
PVC
RCC
ROW
RR
RSJ
SBST
SLS
WBM
Asphaltic Concrete.
Aggregate Impact Value
American Society for Testing Materials
British Standards
California Bearing Ratio
Cationic Medium Setting
Cationic rapid Setting
Cationic Slow Setting
Ceylon Standards
Dry Bound Macadam
Double Bituminous Surface Treatment
Galvanized Iron
Los Angeles abrasion Value
Liquid Limit
Medium Curing
Mild Steel
Plasticity Index
Plastic Limit
Poly Vinyl Chloride
Reinforced Cement Concrete
Right of Way
Random Rubble
Rolled Steel Joist
Single Bituminous Surface Treatment
Sri Lanka standards
Water Bound Macadam.
102 DEFINITIONS
Wherever in these specifications the following terms are used, their meaning shall
be interpreted as follows:
Bridge - A structure including supports, erected normally over a water way, for carrying
traffic, having a clear span between supports of more than 3.0 m measured along the centre
line of the roadway.
Carriageway - The paved or unpaved area of the roadway designated for vehicular travel.
Contract - The written agreement between the employer and the Contractor setting forth
the obligations of the parties there under for the performance of the prescribed work.
Contract Item (Pay Item) - A specific item of work for which a rate per unit is provided in
the contract.
Contractor - Any individual, partenership, firm or corporation, with employer for
performance of prescribed work.
Culvert - Any structure under the roadway with a clear opening of less than 3.0 m measured
along the centre of the roadway.
Drawings - See Plans
Engineer - An Engineer of the employer or any other Engineer delegated with the
responsibility of administering the contract.
Laboratory - Any authorised laboratory approved by the Employer.
Pavement Structure - The combinations of subbase, base and surfacings placed on a sub
grade to support the traffic. .
(i) Subbase - The layer or layers of specificed or selected material of designated
thickness placed on sub grade on which the road base will be constructed.
(ii) Base - The layer or layers of specificed or selected material of designated thickness
placed on a subbase or sub grade on which a surfacing will be constructed.
(iii) Surfacing - the binder application, dressing or surface course constructed on the base
as a protective measure to the pavement structure, against traffic action and the
effects of weather and climate.
Pay Item - See contract item.
Plans - The contract drawings which show the location, characteristic details and dimensions
of the prescribed work, including layouts, profiles, cross sections etc.
(i) Working Drawings - Supplemental drawings, sketch diagrams, etc., supplied by the
Engineer during construction regarding details.
Road bed (road formations) - The prepared surface, formed to line, level and required cross
section, to receive the pavement structure. It is also the top of the sub grade
Right of way (ROW) - Extent of the land legally available for the roadway and the road
side.
Road Side - The area adjoining the cuter edge of the road way including the verges and
embankments.
Roadway - Area covered by the carriageway, shoulder and drains.
l
2
Shoulder - The protion of the roadway contiguous with the carriageway mainly for
emergency use and for lateral support of the pavement structure.
Side Walk - That portion of the roadway primarily constructed for the use of the pedestrians.
Specification - The compilation of provisions and requirements for the performance of
prescribed work.
(i) Standard specifications - This book of specifications approved for general
application and use.
(ii) Supplemental Specification - Approved additions and revisions to the Standard
Specifications.
(iii) Speciall Provisions - Additions and revisions to the Standard and Supplemental
specifications applicable to an individual project.
Structures - Bridges, Culverts, Retaining walls drains and such other constructions which
are not otherwise defined herein.
Sub Grade - The layer of soil immediately beneath the road formation.
Sub Structure - All that part of a bridge or culvert below the bearings.
Super Structure - All that part of a bridge or culvert above the berarings.
103 ARRANGEMENTS FOR TRAFFIC DURING CONSTRUCTION
103.1 Gengeral
Road and bridge works should be carried out causing the least inconvenience to
traffic and in a manner consistant with the satisfactory execution of work. In respect of all
works involving improvement to existing roads, the contractor shall provide and maintain
during the execution of work, a passage for traffic either along a part of the existing pavement
of the road carriageway under improvement or along a temporary diversion constructed close
to the road. This arrangement shall be made keeping in view the intensity of traffic so that
the duration of the hindrance is limited to the minimum. The importance of the road and the
points connected by the road shall also be borne in mind while making arrangements for the
traffic diversion.
Arrangements may be made to close sections of roads where necessary subject to
satisfactory alternative routes being provided. Such closures are to be subject to the approval
of the Engineer and the client organization.
3
103.2 .. Using Part of the Road
Part of carriageway could be kept open to traffic while improvement works such as
widening of the road or strengthening of the existing pavement is being carried out in the
other part, provided the part kept open to traffic is adequate for the purpose, if necessary, by
widening the shoulders. In such cases the shoulders shall be dressed and brought in level
with the existing carriageway and shall be continuously maintained in good condition for
the entire duration of the work. Where imporvement work is in progress in long stretches
along important roads suitable passing bays shall, where possible, be provided with the
apporval of the Engineer. On less important roads, the method of keeping part of the
carriageway to traffic shall, as far as practicable, be adopted even in respect of repairs to or
reconstruction of culverts and minor bridges.
103.3 Temporary Dlverslon _
If, in the opinion of the Engineer, it is not possible to pass the traffic on apart width
of the carriageway, or by any other route a temporary diversion close to the road shall be
constructed as directed. Such a diversion shall be constructed to specifications approved by
the Engineer by using locally available materials as far as practicable. Temporary cross
drainage arrangements shall also be provided as directed wherever necessary. The diversion
shall be maintained in good condition till the original road is opened to traffic.
103.4 Traffic Sattey and Control
All necessary measures for the safety to traffic during construction shall be taken
by providing, erecting and maintaining barricades, road signs, markings, flags, lights etc.,
as required by the Engineer and complying with the requirements of the motor traffic act.
The barricades shall be strong and shall be painted conspicuously. Red lanterns or warning
lights shall be mounted on the barricades at nights and shall be kept lit till sunrise.
At the points where traffic is to deviate from its normal path (whether on temporary
diversion or part of the carriageway) clear directions to the traffic shall be conspicuously
exhibited at both ends with the. aid of appropriate road signs. The portion of road closed for
traffic shall be barricaded with painted drums or other suitable devices. At night these
markings shall be adequately lit so as to be clearly visible. One way traffic arrangements
shall be resorted to, in case the traffic is heavy, in consultation withand assistance of the
Police Authorities. Signs warning the traffic of the hindrance ahead shall also be installed
well beyond the points of diversion. Necessary flag men shall be stationed at both ends to
guide the traffic. .
4
103.5 Measurement and Payment
All arrangements for traffic during construction including maintenance thereof shall
be considered as incidental to the work and no extra payment shall be admissable, unless
otherwise specified.
However, earth work in widening of shoulders, passing places, diversions and
metalling or surface treatment shall be measured and paid for under the relevant pay items
if so specified.
104 CONTROL OF WORKS
104.1 Authority of the Engineer
The Engineer shall decide on all matters which may arise including the following:
(a) The quality and acceptability of materials furnished
(b) Rate of progress of work
(c) Interpretation of,and changes to, plans and specificatios
(d) Acceptable fulfilment of the contract on the part of the contractor.
(e) Type of Machinery and Equipment to be used.
Decisions regarding the above will be based on stipulations given in contract
documents and sound engineering practice taking into consideration all factors bearing on
the issue including all regulations, instructions and guide lines established by the client
organisation for the administration of the contract.
In this regard the Engineer shall be free to exercise such powers as are conferred 011
him by the general conditions of contract.
104.2 Conformity with Plans and Specifications
All work performed shall be in accordance with these specifications and in conformity
with lines, levels, grades, cross sections and dimensions shown on plans and working
drawings. All materials furnished shall also be in conformity with the specifications and in
the event the materials furnished and I or work performed are not totally in conformity with
the plans and specifications but work reasonably acceptable to the Engineer has been
produced, a determination will be made by the Engineer, whether the work will be accepted
and remain in place. Where such work is accepted, an appropriate financial adjustment in
the contract 'price for such work or materials shall be made by the Engineer. In the event the
work performed and I or the materials furnished are not in conformity with the plans and
specifications and have resulted in inferior or unsatisfactory product, such work or material
shall be removed and replaced or otherwise corrected by and at the expense ofthe contractor.
5
Unless otherwise specificed, the contractor shall set such initial construction stakes
and bench marks that will serve as the field controls for the construction work and obtain
the approval of the Engineer for same. No work shall begin till such stakes and bench marks
are certificed as correct by the Engineer or his representative.
105 CONTROL OF MATERIALS
105.1 Source of Supply and Quality Requirements
Unless otherwise provided, all materials used on the work shall be furnished by the
Contractor from sources of his choice.
In order to expedite the inspection and testing of materials, the contractor shall notify
the Engineer of his proposed sources of materials well in advance of procurement for
approval.
If it is found after trial that sources of supply for previously approved material do
not produce uniform or satisfactory products or, if the products form any source proves
unacceptable at any time, the contractor shall furnish materials from other sources.
Possible sources of materials may be shown on plans or described in special
provisions but it shall be the responsibility of the contractor to get the quality of the material
from such sources approved by the Engineer, and also look into the quantities available. The
Engineer may reject certain protions and also accept other protions from the same source.
105.2 Storage of Materials
Materials shall be so stored as to ensure the preservation of their quality and fitness
for the work. Stored materials shall be located so as to facilitate their prompt inspection.
Approved portions of the right -or-way may be used for storage purposes. All storage sites
from which the stored materials have been removed shall be restored to their original
condition by the contractor at his expense.
In case of materials which need piling for storage and measurements, these should
be piled on level areas and to standard shapes so as to facilitate easy measurements and
computations of volumes.
105 (3) Handling of Materials
All materials shall be handled in such a manner as to preserve their quality and
fitness for the work.
106 GENERAL RULES FOR MEASURMENT AND PAYMENT
AU measurements shall be recorded in the metric system unless otherwise specified.
Different items of work shall be measured in accordance with the procedures laid down in
the relevant sections of specifications read in conjunction with the relevant stipulations in
the contract. In respect of lumpsum contracts, however, the procedure specified in the contract
shall be adopted.
6
All measurements, unless otherwise specified, shall be recorded and computed nearest
to the following units:
(i) Length and breadth 10mm
(ii) Areas 0.01 sq. m
(iii) Cubic contents 0.01 cu. m
(iv) Height, depth or thickness of
subbase, bases, surfacings and
structural members 5mm
(v) Height, depth or thickness of
earthwork measured by tape 10mm
(vi) Height, depth or thickness of
earthwork measured with level and staff 5mm
In case of any difference between the above units and those specified under the
relevant items of specifications the latter shall prevail.
The measurement of materials piled shall be recorded for arriving at the cubical
contents by measuring the length, breadth and height of piles. The quantity shall be
caluculated in cubic metres correct to two places of decimals.
106.1 Lead for Materials
Lead or transport distance where applicable shall be measured over the shortest
practicable route and not necessarily the actual route taken for transport. The decision of
the Engineer shall be final in this regard.
(i) Carriage by manual labour shall be measured in units of 30 metres.
(ii) Carriage by animal/mechanical transport shall be reckoned in one km. unit. Distance
of 0.5 km. or more shall be taken as one km. and distance of less than 0.5 km. shall be
ignored. However, when the total lead is less than 0.5 km. it will not be ignored' but
paid for separately in stages of 30 metres subject to the condition that the rate worked
on this basis does not exceed the rate for one km. by mechanical transport.
(iii) The measurements of materials piled and measured as specified at 106 above shall be
the basis of payment for arriving at the transport charges, in respect of materials
transported unless otherwise specified.
7
(iv) The rate for transport is inclusive of all operations including loading, transport,
unloading and piling.
106.2 Measurement of Payement for Area and Volume Based Payment
(a) Area Basis
When measurement of base courses and subbase courses is stipulated to be made on
an area basis, the thickness of the course shall be checked at regular intervals by cutting
holes or by other approved means, as directed by the Engineer.
(b) Volume Basis
The finished thicknesses of subbases, bases and surface courses to be paid on a
volume basis shall be computed in the following manner, unless otherwise specified.
Initial levels shall be recorded before the commencement of the work at a grid of
points normally not exceeding 10 metres, centre to centre, longitudinally and at intervals
normally not exceeding 2 metres transversely. Transverse levels however, shall include the
edges and the centre line. Final levels shall be similaryly recorded at the same grid points
after completion of each item of work listed seperately for payment. The average thickness
of the course in any area shall be the mean of the difference of initial and final levels in that
area but limited to the thickness stipulated in the relevant drawings, designs and
specifications.
Notwithstanding the above, the Engineer shall have the option to cut cores / holes to
check the thickness.
106.3 Scope of Rates for Different Items of Work
In the absence of directions or stipulations to the contrary, the rates are to be
considered as full compensation for all the operations and the rates are to be considered as
the full inclusive rates for finished work covering all labour, materials, wastage, temporary
works overhead charges and the obligations and risks arising out of the conditions of contract.
106.4 Facilities for Verification of Measurements
The contractor shall provide all the necessary facilities for checking and verification
of the measurements at all stages of work, to the officers of the client organization.
106.5 Selection of pay items
Selection of pay items given under each section will depend on the method of
measurement adopted on the contract.
106.6 Sub Divisions Within Pay Items
Where sub divisions within pay items become necessary, due to variations of type
of material, thickness of layer, rate of application etc., letter suffixes in alphabetical order
shall be used to denote the sub divisions within each such pay item. These letter suffixes
shall be incorporated alongside the number given within the bracketed protion of the pay
item number.
8
\
107 SIEVE DESIGNATIONS
The sieve sizes that are generally used in these specifications for grading of soils.
and aggregates are as stipulated in column 1 of Table 107 - 1 which conforms to ASTM E 11
of 1981. It should be noted that sieves given therein are the metric equivalents for the original
sieves in imperial units given in column 2 of Table 107 - 1 which conforms to ASTM Ell of
1961.
The equivalent BS metric sieves that are also in use are given in column 3 of t'his.
table, which conforms to BS 410 of 1976.
Table 107 . 1
Sieve Sizes used in Corresponding Original Equivalent 138
these specifications
. sieves in imperial units metric sieves
mm urn in # mm urn
(1) (2)
(3)
75 3 75
63 2 1/2 63
50 2 50
37.5 1 1/2 37.5/40
25.0 1 28
19 3/4 20
12.5 1/2 14
9.5 3/8 10
6.3 1/4 6.3
4.75 4 5
2.36 8 2
1.18 16 1.18
600 30 600
300 50 300
150 100 150
75 200 75
Even though some of the above sieves are not in the standard ISO series they are
selected for the purposes of these specifications due to their common usage in Sri Lanka.
However, the principal ISO series is given in Table 107-2 for information and
adoption when specified in special provisions of contracts.
9
."'. ,.'., ,
Table 107.2
"mm
Sieve Sizes
urn
~ 1
: .> '
.
90
63
45
31.5
22.4
16.0
11.2
8.0
5.6
4.0
2.8
2.0
1.4
1.0
710
500
355
250.
180
125
90
63
10
200 SITE CLEARING
201 CLEARING AND GRUBBING
201.1 Description
This work shall consist of clearing, grubbing, removing and disposing of everything
on the ground surface of the disignated areas within the right of way, including trees and at
other vegetation and debris, except for the following.
(a) structures and obstructions that shall be removed in accordance with section 202.
(b) All objects, trees and other vegetation that are designated to remain.
The work shall include the preservation from injury or defacement of all those
objects, trees and other vegetation that are designated to remain.
201.2 Work Requirements
(a) General
The contractor shall establish the limits of clearing or clearing and grubbing and
designate all trees, shrubs, plants and other objects that are to remain and obtain the Engineer's
prior approval for same.
In carrying out work care shall be exercised to ensure that existing roadway and
other facilities,utilities and services, trees and plants, designated for preservation and also
the adjoining property are protected from injury or damage which could result from the
contractors operations.
(b) Clearing and Grubbing
All surface objects, all trees, stumps and roots, and all branches of trees not
designated to remain shall be cleared and I or grubbed subject to the following provisions.
(i) Outside the limits of earthwork (cut and fill), stumps and roots shall be allowed to
remain provided that the top of the stumps are not more than 0.30 metres above natural
ground level. However, trees in these areas shall be cut so that the stumps are in line
with the natural ground level as far as practicable.
(ii) In areas of embankment construction undisturbed stumps and roots and non-perishable
solid objects shall be removed to a minimum depth of 0.5 metres below the top of the
sub grade or slopes of embankments.
(iii) Where the embankment fill is less than 3.0 metres all top soil shall be grubbed to an
average depth of 0.15 metres except where directed otherwise.
11
(iv) In cut areas stumps and roots shall be removed to depths not less than 0.5 metres
below the top of the subgrade over which the pavement is to be constructed.
(c) Disposal of Cleared Materials
All saleable timber as designated by the Engineer shall be neatly stored in an approved
accessible place within or near the right of way as directed and shall be trimmed and stacked
in accordance with the requirements of the appropriate Government Agency to which the
-timber belongs or as directed by the Engineer.
Unsaleable timber as designated by the Engineer and all stumps, roots, logs and
other refuse from the clearing and from the grubbing operations shall be disposed of by
burning or other means approved by the Engineer.
Piling of such material for burning shall be carried out, as approved by the Engineer,
either at or near the centre of the cleared area or in adjacent open spaces where no damage
to trees or other vegetation could occur.
All burning shall be done in conformity with the regulations and at such times and
in such manner as to prevent the fire from spreading to areas adjoining the right of way.
Contractor shall be responsible for damage to any property, or injury to persons, res ulting
from such operations. At the end of such operations the roadway and adjacent areas shall be
left with a neat and finished appearance free of accumulations of burnt or half burnt material.
201.3 Measurment & Payment
(a) Measurment
Unless otherwise specified, clearing or clearing and grubbing shall be measured
separately on an area basis in square metres of area cleared or area cleared and grubbed.
Where so specified the total area cleared or cleared and grubbed shall be considered as one
item for lump sum payment.
Removal of trees of girth less than 300 mm shall be considered as incidental to
these operations (see note below).
Removal of trees of girth greater than 300 mm as well as cutting and removal of
branches of trees of girth greater that 300 mm shall be measured in numbers and separately
assessed according to the size categories given below.
(i) girth greater than or equal to 300 mm and less than 600 mm.
(ii) girth greater than or equal to 600 mm and less than 1000 mm.
12
-. ; ~
(iii) girth greater than or equal to 1000 mm and less than 2000 mm.
(iv) girth greater than or equal to 2000 mm and less than 3000 mm.
(v) girth greater than or equal to 3000 mm.
Note
For the above purpose girth shall be a measured at a height of 1 metre above ground level
for trees and at the cut for branches of trees.
(b) Payment
(i) Clearing or Clearing & grubbing
This work measured as provided above will be paid for at the contract unit rates
which shall be full compensation for furnishing all labour, materials, tools, equipment and
incidentals necessary to do the work and for carrying out all the clearing and grubbing in
the designated areas including the removal and disposal of all resulting material.
(ii) Removal of trees
Payment for removal of trees will include payment for removal of their stumps when
cut, and also payment for removal of their roots where necessary, according to these
specifications.
The payment shall include full compensation for all labour materials, tools,
equipment and incidentals necessary for carrying out all work necessary including disposal
of all resulting material.
The Pay Items and Pay Units will be as follows:
Pay Item Pay Unit
201 (1) Clearing Square metres I Lump sum
201 (2) Clearing and Grubbing Square metres I Lump sum
201 (3) Removal of trees
(state girth) Number
201 (4) Removal of branches
(state girth) Number
Note
Refer sub section 106.6 regarding sub divisions of pay items.
13
',--_.
202 REMOVAL OF STRUCTURES AND OBSTRUCTIONS
202.1 Description
This work shall include dismantling, demolishing, removal and disposal, or salvage
wholly or in part, of all existing structures, indluding buildings, bridges, culverts and
obstructions such as abandoned pipe lines, old pavements and kerbs etc.
202.2 Work Requirements
Existing wstructures within the right of way shall be removed by the contractor, as
indicated on the drawings or as required. Where existing bridges and culverts are identified
for use as temporary crossings or detours, no parts of these shall be removed without the
prior approval of the Engineer. Such bridges and culverts shall not be closed to traffic or
obstructed until the new work is opened to traffic.
When the drawings provide for using the existing sub-structures, or parts of same,
as permanent parts of the new structures, only those portions indicated on the drawings to
be removed shall be removed. When no such use is contemplated, all exposed protions of
the existing structures above the stream bed shall be completely removed. When the proposed
structure is a bridge, and it becomes necessary to remove portions of the existing structure
below ground in order to construct the new work, excavation for such removal shall be
carried out as provided for in section 302., and shall be executed with the approval of the
Engineer.
Old pavements, kerbs and such other obstructions shall be removed only to the extents
required in the drawings or directed by the Engineer and their edges shall be cut to a neat
finish. Abandoned pipe lines and ducts shall be removed to joint a where possible.
If the super - structures of bridges are deemed fit for use elsewhere, such useable
protions shall be marked and removed without damage. Also when pipe culverts, box culverts
other structures or parts there of with a salvage value are removed, care shall be exercised
in their removal.
Materials having a salvage value shall be stacked, in neat stacks of like material, in
a manner to facilitate easy loading and removal as directed by the Engineer. All such material
shall become the property of the Ministry unless otherwise provided in the contract.
All material which is not considered of value by the Engineer shall be removed
from the right of way and disposed of so as not to constitute an obstruction or a nuisance.
14
202.3 Measurement & Payment
If the contract contains a separate item for removal of existing structures and
obstructions, the contract lump sum price for that item shall be payment in full for the removal
and disposal of them as specified herein.
If the contract does not contain a separate item for removal of existing structures
and obstructions but it is indicated on the drawings that they are to be removed, such work
shall be considered as incidental to the contract.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
202 (1) Removal of structures and obstructions Lump sum
15
300 EARTHWORKS
301 ROADWAY EXCAVATION
301.1 Description
This work shall consist of all excavation within the limits of the roadway, required
for the purpose of roadway construction except excavation for sturctures (specified separately
in section 302). It shall also consist of excavations directed by the Engineer falling outside
the limits of the roadway, not specified elsewhere in these specifications. The work shall
include hauling and stacking or hauling to sites of embankment construction, of suitable
materials, the disposal of unsuitable materials and the trimming and shaping of exposed
faces of excavation.
301.2 Classification of Materials
(a) Excavated materials
Unless otherwise specified all materials excavated fromthe area designated for the
roadway shall be classified as given below. The decision of the Engineer in this regard shall
be binding on the contractor.
The total volume of roadway excavation shall either be included wholly under items
(i), (ii), (iii) and (viii) or under items (ii), (iii), (iv), (v), (vi), (vii) and (viii) given below.
(i) Unclassified soil
Unclassified soil shall include all soils excavated in accordance with this specification.
(ii) Soft Rock
Soft rock shall comprise weathered rock, sand stone, lime stone, and such layers
which can be excavated by picking, ripping and other similar means without resorting to
blasting and / or sledging.
(iii) Hard rock
Hard rock shall comprise all igneous, metamorphic and sedimentary rock, incl uding
large boulders, which require blasting and / or sledging for removal.
(iv) Loose soils
Loose soils shall comprise all loose sands and silts and other materials, deposited
by earthslips or similar occurrences, that can be excavated using the shovel or similar tools.
For purposes of these specifications loose soils shall be further classified as dry or wet.
(v) Ordinary soils
Ordinary soils shall comprise all naturally occuring sands clays, silts, organic soils,
peat and varying combinations of these, the excavation of which requires tools such as the
mamotty in addition to the shovel.
16
(vi) Medium soils
Medium soils shall comprise gravels sands and clays and varying combinations of
these, the excavation of which requires tools such as the mamotty and the shovel but in the
opinion of the Engineer requires a greater effort per unit volume of excavation than for
ordinary soils.
(vii) Hard soils
Hard soils shall comprise gravels cabooks, stiff clay, and other hardened layers of
soil which require the pickaxe and similar tools to loosen before they could be excavated.
(viii) Marshy material
Marshy material shall comprise materials from swamps and marshes containing
watery peat and other vegetable matter, including logs, often found to exist in combination
with sand, silt and clay which require special methods for excavation such as grabbing and
pumping.
(b) Suitable and Unsuitable Materials
For purposes of re-use and disposal, excavated materials shall be grouped as suitable
and unsuitable, as given below.
(i) Unsuitable Materials
Unsuitable materials shall include highly plastic clays, silt, peat and other organic
soils and soils containing roots grass and other vergetable matter and soils that do not meet
the requirements of sub section 304.2.
(ii) Suitable Materials
Suitable materials shall include all natural soils other than those defined as unsuitable
materials above.
301.3 Construction Requirements
(a) Limits of Excavation
The contractor shall set out the limits of excavation and shall carry out excavation
operations as specified herein and in a manner approved by the Engineer. The excavation
shall conform to the lines, levels grades and side slopes shown on the drawings or as directed
by the Engineer. However, if unsuitable material is encountered outside the specified limits
of excavation such material shall be excavated over areas and to depths as directed by the
Engineer. Any excess excavation of suitable materials, shall be made good with suitable
material at the cost of the contractor.
(b) Removal of Top Soil
Top soil encountered during roadway excavation shall be stockpiled at suitable
locations for use in soiling the side slopes and the verges and any excess top soil shall be
removed from the site to dumping grounds.
17
(c) Re-use of Suitable Material
The contractor shall organise and carry out excavation work in a manner that the
suitable materials are excavated separately for use in works without contamination by the
unsuitable material. Any material that becomes unsuitable by contamination due to the
negligence of the contractor shall be made good by him at his own expense.
All suitable material that is excavated shall be used in the construction of the roadway
except where such material is in excess. Such excess material shall be disposed of otherwise
with the approval-of the Engineer
(d) Removal of Unsuitable Material
Unsuitable material that is excavated shall be removed from the site to dumping
grounds approved by the Engineer. All- dumped material shall be spread as directed by the
Engineer in a manner not to interfere with the drainage pattern of the area.
(e) Excavation in Rock
Rock encountered in roadway excavation shall be removed upto at least 0.15 m
below the finished level of the subgrade or as otherwise indicated in the drawings. A uniform
surface that could be easily drained, shall be obtained by controlled blasting, sledging and
splitting along cleavage planes.
The extra depth excavated shall be backfilled to the level of the top of the subgrade
using suitable material in a manner specified for embankment construction in section 304.
Where blasting is required it shall be carried out according to section 306 and all
necessary precautions given therein carefully observed.
(f) Excavation in Marshy Material
Unless otherwise specified or directed, the method of excavation of marshy material
shall be such that as the marshy material is excavated, the void is filled with an approved
granular material with the least possible delay ensuring thereby, to the extent practicable,
the exclusion of all unsuitable material from within the lateral limits of the roadway.
(g) Excavation for Road Widening
Excavation for widening of existing road formations shall be done according to the
cross sections given in drawings and or as directed by the Engineer.
Care shall be exercised to ensure the stability of the road platform adjacent to sections
excavated and that the existing platform is not loosened beyond what is practically required.
Any overbreak shall be made good at the expense of the contractor.
18
(n) Earth slips
Removal of material in slips in areas beyond the lines and slopes of excavation shall
not be paid for unless such occurrences are shown to have been beyond the control of the
contractor and not preventable by the exercise of due care on his part.
U) De-Watering
If water is met within the cut area due to springs, seepage or rain,it shall be removed
by suitable means as and when required by the Engineer.
Care shall be taken to discharge the drained water so as not to cause damage to the
works, or any adjacent property. .
(k) Finishing Operations
The surfaces resulting from the excavation shall be finished to the levels given in
drawings or as directed by the Engineer. All cut slopes shall be finished neatly to the specified
slopes. Care shall be taken to remove all unstable boulders away from these slopes.
/301.4 Measurement & Payment
(a) Measurement
Roadway excavation shall be. measured in its original positron and the volume
determined in cubic metres by the average end-area method as computed on the original and
final cross sections of required and completed work, unless otherwise specified. Separate
measurements shall be made for each class of material encountered.
Measurements of rock excavated below sub grade level shall be computed on the
basis of excavation to the specified minium depth below subgrade level only and no over
break shall be included.
Interim payment may be made on measured volume of required excavation actually.
excavated, befor final shaping, provided the contractor's intention to complete the work, is
clear.
(b) Payment
The quantities of roadway excavation measured as specified above will be paid for
at the contract unit rate per cubic metre for each class of material encountered. Such rates
shall include full compensation for excavation, removal, haulage for re-use or satisfactory
disposal of all roadway excavation, for shaping, dressing and completion of surface and for
furnishing all labour, material, tools, equipment and incidentals necessary to complete the
work.
Dewatering shall be paid for separately.
Where the loose soil is separately classified as wet and dry, payment shall be on two
separate rates.
19
The Pay Items and Pay Units will be as Follows :
Pay Item Pay Unit
Either
301 (1) Roadway excavation in unclassified soil Cubic metres
or
301 (2) Roadway excavation in classified soil
(state class of soil) Cubic metres
and the following
301 (3) Roadway excavation in classified
rock (state whether soft or hard) Cubic metres
301 (4) Roadway excavation in marshy material Cubic metres
301 (5) Dewatering Item.
Note
Refer sub section 106.6 regarding sub divisions of pay items.
20
302 EXCAVATION AND BACKFILL OF STRUCTURES
302.1 Description
This work shall consist of the necessary excavation for foundation of bridges,
culverts, retaining walls, head walls, wing walls and other structures.
The work shall include the necessary diverting of streams; construction and
subsequent removal of necessary cofferdams and cribs; all necessary sheeting, shoring,
bracing, dewatering and pumping; removal of logs, stumps and other deleterious matter and
obstructions for placing the foundations; trimming of excavation; backfilling, clearing the
site of debris and the disposal of excess excavated material.
302.2 Classification of Materials
The classification of excavated materials and suitable and unsuitable materials for backfilling
shall be as given in sub section 301.2
302.3 Construction Requirements
(a) General
Prior to commencement of excavation operations, the limits of excavation shall be set out as
shown in drawings or as directed by the Engineer.
The depth of excavation shall be as shown in the drawings, unless the foundation strata
encountered is such as to require changes. In the latter case the depth of excavation shall be
as directed by the Engineer. Where blasting is required it shall be carried out according to
section 306 and all ncessary precautions given therein carefully observed.
(b) Excavation for Foundation Above Water Table
Unless otherwise directed excavation for foundations above water table shall be
carried out to the width of the lowest step of the footings and the sides left vertical without
shoring where the nature of the soil and the depth of excavation allows it. Where this is not
possible the contractor shall erect all necessary shoring shuttering, planking for the safety
of personnel and works.
(c) Excavation for Foundations Below Water Table
Where water is met within the excavation due to stream flow, seepage, springs etc.
the contractor shall take adequate measures such as bailing, pumping, construction of
diversion channels and bunds, cofferdamming and any othermeasures to keep the foundation
trenches free from water as necessary.
Where cofferdamming is required, these shall be constructed to adequate depths
and heights with due regard to safety and stability and made as water - tight as necessary to
permit work to be carried out inside them. The interior dimensions of the cofferdams should
be such as to give sufficient clearance for the construction and inspection and to permit
installation of pumping machinery etc., as may be required within the enclosed area
21
(d) Preparation of Foundation
The bottom of the foundation shall be to the lines and levels as given in the drawings
or as reuqired by the Engineer. Where this is in soil and above the water table it shall be
watered where necessary and rammed, and where it is below the water table it shall be
prepared as directed by the Engineer.
Where rock strata is encountered, soft and weathered material shall be removed as
necessary and the surface trimmed and dressed as directed by the Engineer.
If the excavation has been carried out deeper than necessary, as given in the drawings
or as otherwise directed by the Engineer, the extra depth shall be made good with concrete
or masonry of the foundation grade or any other approved material at the cost of the contractor.
(e) Backfilling
Backfilling of the foundation shall be carried out in accordance with sub section
304.3 j (iv). As stated therein it shall be noted that the backfilling shall be done only after
the foundation concrete or masonry has been in position for at least 7 days and in a manner
not to cause undue thrust on any part of the foundation.
(f) Use and Disposal of Surplus Material
All suitable material form the surplus of excavation shall as far as possible be used
in the construction of the roadway.
All excess soil and other material from the excavation, including logs, boulders,
shall be romoved from the site as directed by the Engineer.
302.4 Measureement & Payment
(a) Measurement
All excavation shall be measured according to dimensions as given in the drawings
prepared for purposes of excavation or as directed by the Engineer, in cubic metres for each
class of material encountered. Any excavation in excess of above other than what had been
allowed by the Engineer shall be considered as carried out for the convenience of the
contractor in executing the work and shall not be measured for payment.
(b) Payment
The quantities of excavation for structures as measured above will be paid for at the
contract unit rate per cubic metre for each class of material encountered. Such rates shall
include full compensation for all labour, materials, tools, equipment, safety measures and
incidentals necessary to carry out the work to this specification. This work shall include;
22
\
i
(i) Setting out
(ii) Removal of all logs stumps and other deleterious matter and obstructions for placing
the foundation including trimming bottoms of excavation.
(iii) Backfilling, clearing the site and disposal of all surplus material.
Construction of necessary cofferdams, cribs, sheeting, shoring and bracing and their
subsequent removal and dewatering shall be paid for separately.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
Either
302 (1) Excavation in unclassified soil
and backfill of structures Cubic metres
or
302 (2) Excavation in classified soil
(state class of soil) and backfill of structures Cubic metres
and the following
302 (3) Excavation in classified rock
(state whether soft or hard) and
backfill of structures Cubic metres
302 (4) Excavation in marshy material and
backfill of structures Cubic metres
302 (5) Preparation of base of foundation Item
302 (6) Construction of necessary coffer dams,
cribs sheeting shoring and bracing and
their subseuqent removal Item
302 (7) Dewatering Item
Note
Refer sub section 106.6 regarding sub divisions of pay items.
23
303 BORROW EXCAVATION
303.1' Description
This work shall consist of excavation of suitable materials form approved borrow areas,
including those within the right - of - way for the construction of embankments, subbases,
bases, shoulders or for any other work required in the contract or by the Engineer.
303.2 Work Requirements
The contractor shall notify the Engineer sufficiently in advance of opening borrow
areas and obtain his approval prior to commencing borrow operations.
During borrow excavation the borrow areas shall be kept drained as far as possible
and the contractor shall take all necessary precautions to prevent any erosion or interference
with exiting drainage facilities. The contractor shall also ensure that borrow operations are
carried out in a manner not to affect the stability or safety of any structure or cause any
other damage to adjacent property.
The working of borrow areas within the right - of - way shall be subject to the
approval of the Engineer. No borrowing shall be permitted, below the level of the toe of the
embankment, without the prior approval of the Engineer.
All suitable material removed from borrow sources shall be used as directed by the
Engineer.
On completion of borrow operations, borrow areas shall be left in a neat condition
with proper drainage.
303.3 Measurement & Payment
No separate measurement and payment shall be made for borrow excavation.
24
304 EMBANKMENT CONSTRUCTION
304.1 Description
This work shall consist of the construction of embankment and other miscellaneous backfills
with approved material obtained either from the excavation of the roadway, borrow pits or
other sources.
304.2 Materials
(i) Type I embankment material used shall conform to sub section 1708.1 (a).
(ii) Type II embankment material used shall conform to sub section 1708.1 (b).
304.3 Consturction Requirements
(a) Sources of Supply of Embankment Material
All suitable material available from the roadway and other excavation shall be used
for embankment construction as directed by the Engineer. Where additional material is
necessary they shall be obtained from approved borrow pits or other approved sources.
Borrow excavation shall be carried out in accordance with section 303.
(b) Setting Out
After the site has been cleared the limits of embankment shall be set out as required,
The pegs or stakes showing the limits of the embankment shall be fixed a suitable distance
outside the actual limits of the fill and such pegs or stakes shall be painted in a distinctive
colour for visbility.
(c) Removal of Top Soil
Where the height of embankment fill is less than 3.0m the top soil shall be removed
as given in section 201. In such instances before the placing of any embankment fill, the
surface over the bottom width of the foundation shall be trimmed and levelled as necessary
and compacted either using 4 - 6 passes of a 8 - 10 tonne roller or by an approved number of
passes of any other roller.
The use and disposal of top soil so removed shall be as given in section 301.
Where the height of embankment fill is less than 300 mm or where the road is in
cutting the contractor shall excavate original ground or the surface exposed by the cut
respectively, upto a depth of 300 mm below the road formation level or to such other depths
as may be directed by the Engineer, if the density of compaction of the original ground 01'
the surface exposed by the cut is less than 100 percent of the maximum dry density as
determined by the standard compaction test specified in section 1804. Where unsuitable
material is encountered the contractor shall excavate to such depths as required by the
Engineer.
25
The surfaces exposed by this operation shall be compacted either by 4 - 6 passes of
a 8 - 10 tonne roller or by an approved number of passes of any other roller. The excavated
depth shall be refilled with suitable material and compacted in accordance with sub section
304.3 (d) to the density requirements as given in sub section 304.2 (e).
(d) Placing and compaction of Embankment Material
The top 450 mm of the embankment shall be constructed using type I material as
given in sub section 1708.1 (a) and the lower layers of the embankment shall be constructed
using type II material as given in sub section 1708.1 (b) unless otherwise specified.
The embankment material shall normally be placed in layers not exceeding 225 mm
loose thickness, for compaction using 8 - 10 tonne smooth wheel roller or any other roller of
comparable compactive effort. If rollers of higher compactive effort are used the lift thickness
may be increased based on field trials of compaction. It must however be ensured that the
entire thickness of each layer is adequately compacted. The embankment fill shall be
compacted at or near the optimum moisture content.
The moisture content of the material shall be checked as given in section 1804 at
the time of compaction and at the frequency specified in table 1602-1 or as directed by the
Enginer. If the material is too wet it shall be dried by aeration and if it is too dry the material
shall be sufficiently wetted prior to compaction.
Each successive layer shall be placed only after the degree of compaction of the
previous layer has been tested and found satisfactory as given in section 304.3 (e).
In the alternative each successive layer shall be placed after the previous layer has
been compacted using a specified number of passes of the roller as had been determined by
field trials.
Rolling shall commence at the edges and proceed towards the centre, except at super
elevated sections where the rolling shall commence at the lower edge and proceed towards
the higher edge.
(e) Degree of Compaction of Embankment Fills
Where so specified the degree of compaction of each layer of compactedembankment
shall be checked at the frequency given in Table 1602-1 or as directed by the Engineer. The
field density test shall be carried out as specified in section 1804.
The top 450 mm of the embankment shall be compacted to density not less than
100% of the maximum dry density and the lower layers of embankment and the embankment
foundation shall be compacted to a density not less than 95% of the maximum dry density as
determined by the standard compaction test specified in section 1804.
26
In the alternative the degree of compaction shall be assessed by the number of passes
of the roller. However, the contractor shall carry out random tests as required by the Engineer
to determine whether the specified degree of compaction has been achieved.
If the results of any test shows that the density is less than what is required the:
contractor shall carry out further compaction as may be necessary to obtain the required
density.
(f) Drainage and Protection of Embankments
Water shall not be allowed to accumulate at any point in the earthworks. The
. contractor shall arrange for the quick disposal of all water from the works, whatever the
source may be, and shall at his own expense effectively drain the whole of the works during
the entire period of construction. Such provision shall include carrying out the work of
forming the cuttings and embankments in such a manner that their surfaces are maintained
at all times to sufficient minimum crossfall and longitudinal gradient.
Any damage caused to the completed surface of embankment as a result of
construction traffic or lack of proper drainage or by any other means that could be attributed
to the negligence of the contractor shall be made good by the contractor at his own expense,
(g) Finishing Operations
The embankment shall be finished to levels, grades, slopes and cross sections shown
on the drawings or as directed by the Engineer, subject to the requirements of section 1601,
Both the upper and the lower edge of the side slopes shall be rounded off to improve:
appearance and to merge with the adjacent terrain.
Where specified the slopes of embankment shall be top soiled and grassed, measured
and paid in accordance with section and 802 respectively.
(h) Quality control
The control of quality of the materials and the work shall be carried out as given in
section 1602.
(j) Embankment Construction Under Special Conditions
(i) Widening existing embankments
Where existing embankments are to be widened, adequate bonding between the old
and new filling shall be established by removing the top soil and scarifying the sloping
faces of embankment.Where the slopes are steeper than 2 horizontal to 1 vertical, subject to
the decision of the Engineer, benching of the slopes shall be carried out at regular intervals.
(ii) Embankment on hill slopes
Where embankments are to be constructed on hill slopes the slopes shall be scarified
and benched as described in sub section 304.3 U) (i).
27
(iii) Embankment over existing paved surfaces
Where embankment material has to be placed over existing paved surfaces to a height
less than 1.0 m it shall be ensured that the existing surface is scarified prior to placing of the
material. Where the height of fill is greater than 1.0 m the need to scarrify the existing
surface shall be decided by the Engineer, depending on the site conditions.
(iv) Embankment around structures
The contractor shall take special precautions to see that the construction work of
structures is not disturbed as a result of the embankment filling operations and that the
filling in the vicinity of a structure shall not be carried out till the concrete or masonry had
been in position at least for 7 days,unless otherwise directed by the Engineer.
Filling around structures shall be carried out u ~ i n g suitable material and compacted
to densities given in sub section 304.3 (e) using special equipment such as mechanically
operated hand rammers. Care shall be exercised that no damage is done to the structure by
these operations.
The embankment shall be broutht up simltaneously on each side of the structure to
avoid unequal pressures acting on it.
Any damage that is caused to the sturctures by the negligence of the contractor shall
be made good by him at his own expense.
(v) Embankment over soft ground
Where embankments are constructed over soft ground which are unable to bear the
loads of compacting equipment, the compaction of the initial layers shall be carried out as
gi ven in contract documents or as directed by the Engineer.
(k) Construction of drainage (filter) layers behind structures
...., ,Drainale (filter) layers specified behind structures shall be constructed, in accordance
with section 70S, along with the laying of the fill material.
304.4 Measurement and Payment
(8) Measurement
Embankment construction shall be measured as compacted in cubic metres. The
volume of fill material shall be computed by the average end area method on cross sections
given in the drawings or on actual cross sections taken at site before and after the construction
of the embaftkment. Where the embankment foundation is likely to settle under the weight
of the fill. the extra volume of material required due to such settlement shall be included in
the measurement.
28
Embankment construction using roadway excavation and using borrow excavation
shall be measured separately. (see note below).
The trimming, levelling and compaction of original ground shall be measured in
square metres.
Application of top soil on embankment slopes and verges shall be measured as given
in section 801.
Filter medium behind earth retaining structures shall be measured as given in section
705.
Note
(The contractor is required to use all suitable materials resulting from roadway
excavation, except that which is in excess, in embankment construction as given in sub
section 301.3 (c) However the contractor may opt to discard suitable material from roadway
. .
excavation and use material from borrow excavation for his convenience, provided that this
additional volume of borrow material is reckoned to have resulted from roadway excavation).
(b) Payment
Payment will be based on the contract unit rate for the separate items as measured
above and shall include full compensation for all labour, materials, transport, tools equipment
and other incidentals necessary to complete the work to the specification. This work shall
include the following, where applicable.
(i) Setting out and pegging
(ii) Scarifying and benching slopes of existing embankments and hill sides
(iii) Scaritying existing paved roads
(iv) Special arrangements that may be necessary for working under restricated conditions
such as in the vicinity of sturctures.
(v) Excavation of borrow material
(vi) Compaction of fill
29
The Pay Items and Pay Units will be as follows:
. Pay Item
304 (1)
304 (2)
304 (3)
Embankment construction using material from
roadway excavation compacted in position
Embankment construction using borrow
material compacted in position
Trimming, levelling and compaction of
original ground
Pay Unit
Cubic meters
Cubic matres
Square metres
30
The Pay Items and Pay Units will be as followos :
'Pay Item
305 (1)
305 (2)
305 (3)
305 (4)
305 (5)
306 (6)
Note
Trench excavation in unclassified soil
Trench excavation in classified rock
(state whether soft or hard)
Trench excavation in pavement
layers (stae type)
Trench reinstatement upto formation level
using suitable material from the exvacation
Trench reinstatement upto formation
level using borrow material
Trench reinstatement in pavement layers
and shoulders (state type of layer and
type of construction)
Refer sub section 106.6 regarding sub divisions of pay items.
33
Pay Unit
Cubic metres
Cubic metres
Cubic metres
Cubic metres
Cubic metres
As given in the relevant
specification
306 EXPLOSIVES AND BLASTING OPERATIONS
306.1 Description
This work shall consist of handling, transport, storing, and use of explosives for
carrying out blasting operations in the formation of roads, preparation of foundations of
structures or for production of aggregates, according to these specifications and as approved
by the Engineer.
These specifications shall be read in conjuction with the explosives act and other
regualations issued from time to time by the controller of explosives.
306.2 Materials
All explosives used shall be of approved manufacture and shall belong to the
following categories.
Initiating Explosives
Low explosives
High explosives
(a) Intiating Explosives
These shall consist of detonators, safety fuse (firing cord), detonating fuse, and
ignitor cords, used to initiate the main charge.
(b) Low explosives
Low explosives are mixtrues of potassium nitrate or sodium nitrate, charcoal and
sulphur in suitable proportions manufactured to have a granular form with coarse, medium
or fine grains, glazed with graphite, usually, referred to as black blasting powder..
(c) High Explosives
High explosives shall be gelatines, gelignites, dynamites in powder form, all of which
contain nitroglycerine as sensitizers, or Amonium Nitrate or slurries based on Tri-Nitrotoluene
(TNT) or mixtures of Ammonium Nitrate and Fuel Oil (ANFO).
306.3 Blasting Operations
(a) Choice of Explosives
In the choice of explosives, in addition to job requirements, consideration shall be
given to the following factors.
(i) Type of rock
(Ii) Degree of fragmentation desired
(iii) Size and depth of drill hole
(iv) Ground vibrations and proximity to buildings and other structures.
34
(b) Initiation by Firing Cord (safety fuse)
Normally the standard plain detonator, No.6 or No.8, shall be used to initiate the
main charge.
To prepare the capped fuse, the fuse shall be cut striaght across with a sharp knife.
The detonator shall then be slipped over the freshly cut end of the fuse so that" the mixture"
" and fuse are in contact. The detonator shall then be crimped gently but secrurely with
approved crimpers. Force shall not be used when inserting the fuse into the detonator. The
part of the detonator containing the detonating mixture shall not be crimped. The ends of
the fuse shall not be allowed to be damped or contact oil of grease When capped fuses are to
be used in wet conditions the junction between the fuse and the detonator shall be well
coated with a water proofing or cap sealing compound. Sufficient length of free end of the
fuse shall be left so that ample time is available to fire al1 the bore holes charged and the
workmen to get away to a safe place.
Perparation of the capped fuse shall not be done at or close to the face of the rock.
This shall be done at a safe place immediately before the commencement of charging the
shot holes.
(c) Initiation by Detonating Fuse
Detonating fuse shall be used in large scale excavation or quarry work to initiate
high explosives. A plain detonator or an electric detonator No.6 or No.8 shall be attached
to the detonating fuse with adhesive tape, or string, firmly so that it points towards the
explosives charge. Delay or short delay detonators shall be used if methods of delay firing
is employed. When fixing the detonating fuse to the primer cartridge sufficient length of the
detonating fuse shall be in contact with detonating cord the free ends of the detonating cord
from the shot holes shall be firmly fixed to a main cord using adhesive tape, string or thin
wire. At least 50 mm of the branch lines shall be in contact with the main cord at the joint.
(d) Initiation by Electric Detonators
Electric detonators shall be used for initiating explosives when electric shot fixing
is adopted. Firing shall be done only with approved blasting machines. Mains firing shall
not be permitted. The primer shall be prepared by making a hole in the cartridge with an
aluminium or brass pricker and inserting the detonator until it is completely buried in the
explosive. The leading wires shall then be hitched round the cartridge to prevent the detonator
from being withdrawn. All electrical connections shall be made with clean wires well twisted
together. Care shall be taken to ensure that the insulation of leading wires, connecting wires
and cables is not damaged due to rough handling. All joints shall be well insulated. The
bared ends of the leading wires shall be well protected to prevent contact with any conductors.
Electric shot firing shall not be carried out if a thunder storm is imminent. The number of
shots to be fired shall not exceed the recommendation of the manufacturer of blasting
machines.
35
(e) Charging Boreholes
When the structure of the rock is distributed and irregular small diameter short
boreholes shall be used. The faces shall be worked in steps of benches by blasting with short
vertical holes of 1 - 5 metre ( 3 - 6 feet) in depth, drilled in a line parallel to the face. The
horizontal distance from the bottom of the borehole to the face shall be always less than the
depth of the borehole. The diameter of the boreole shall notrmally be 25 to 50 mm (1" - 2" ).
Special gelatine of 80% strength or as recommended for this type of work, shall be used.
The borehole shall be cleaned out with compressed air or other approved method. The
cartridges of explosives shall then be inserted into the borehole one at a time and pressed
with a wooden rod. The primer cartridge shall then be pushed until it rests against the main
charge.
Metal rods shall never be used to charge boreholes. No drill or metal equipment of
any kind shall be introduced into the hole once explosives have been inserted-After-loading
the explosives, stemming shall be inserted. Material for stemming shall be quarry fines or
sand which shall be gently tamped for the first few inches from the bottom. Pressure shall
be gradually increased for tamping so that the stemming is firmly packed in the hole. During
tamping the leading wires of the detonators, safety fuse or detonating cord shall be held taut
onto one side of the borehole to prevent damage to wire or fuse.
In quarrying operations, small diameter longboreholes charged with a high explosive
and fired at a predetermined pattern using short delay detonators shall be used to produce
well fragmented rock and reduce ground vibration.
(f) Secondary blasting
Secondary blasting in quarries shall be done either by pop shooting or plaster shooting
to reduce the size of boulders. produced from the primary blast. to smaller size for easy
handling.
(g) Misfires
(i) Misfires with safety fuse initiation
If a misfire occurs, no person shall be allowed to reach the area until a specified
period has lapsed. The specified period shall not be less than one hour. After the period has
lapsed the exposed fuse shall be examined. If it is found that the fuse has burnt only along
part of its lenght, the stemming shall be carefully washed out and a new primer cartridge
inserted and fired. No attempt shall be made to remove the explosive from the borehole. No
metal objects shall be used to remove the stemming. If the stemming cannot be removed, a
borehole shall be drilled at least 300 mm away from the misfired hole and parallel to it. This
shall be charged and fired to relieve the misfired shot. .
36
(ii) Misfires with electric shot firing
If a misfire occurs in electric shot firing a time lapse of at least fifteen minu tes shall
be allowed before any person is allowed to approach the misfire. After this time lapse, the
cables and connections shall be examined and any faults remedied. The circuit shall then be
tested using an ohmmeter from a safe place. If the circuit is found to be in order a further
attempt shall be made to fire the shots. If this attempt fails or if the circuit is incomplete the
explosive charge shall be reprimed or dislodged. Wherever possible the explosive shall be
fired using a fresh primer. The stemming shall be carefully removed using compressed air
or water introduced through plastic pipes or rubber hoses. No attempt shall be made to dig
out the stemming from the hole. If it is found to be impossible to wash out the stemming for
re-priming and firing, a small diameter drill hole shall be made parallel to the misfired shot
ensuring that there is no risk in drilling into the misfired shot. The new shot shall be fired
and the explosive cartridge and detonator soaIrBe searCheclror in the debris, carefully by
hand.
(h) Warning to Residents and Traffic
Adequate warning shall be given to neighbouring residents before blasting operations
are carried out. A siren should be sounded and men with red flags posted, on all roads at
close proximity to the quarry, to warn traffic, as approved by the Engineer.
306.4 Safety in Handling, Transport and Storage
1. Explosives, detonators, detonating fuse etc., shall not be stored except in a proper
magazine which is clean, dry, well ventilated, well locked and approved by the
controller of exlosives.
2. Explosives and detonators shall be stored separately either in separate magazines or in
a separate compartment of the magazine. Detonating fuse shall be stored with exclosives
and not with detonators.
3. Smoking, matches or open light shall not be allowed in or near the magazine or while
handling explosives and detonators. A permanent notice board in Sinhala, Tamil and
English warning 11 NO SMOKING shall be displayed in a prominent place near the 11
magazine.
4. Only wooden tools shall be used to open cases of explosives. No metal tools shall be
kept in the magazine or used. Cases shall not be opened inside the magazine.
5. Cases of explosives shall be handled with care and shall not be dropped, pushed or slid
in a rough manner.
37
6. When a case has been opened its contents shall be used before opening other cases.
7. Explosives and detonators shall be issued in the sequence of manufacturing dates marked
on the boxes.
8. Primer cartridge shall not be made in the magazine.
9. Explosives shall not be transported with any other materials, particularly with tools or
inflammable liquids.
10. Whenever possible, explosives and detonators shall be transported in separate vehicle
or conveyed by different men. If both have to be carried in the same vehicle they shall
be placed in separate compartments.
11. When transporting,the-exples-i-ves-sh-a-l-l-be-ke-pt-furthestfrom the-eng.inev-Explosives.;
shall not be carried in the drivers cabin.
12. Loading and unloading of explosives to the vehicle shall be done as gently as possible.
13. No explosives or detonators shall be transported without a valid transport pass.
14. Only the essential quantity of explosives and detonators shall be transported to the
blasting site. Explosives and detonators shall be kept apart until they are used.
1S. A monthly return of explosives indicating the quantity of each kind of explosives used,
the quantity of rock blasted, opening and closing stock balances shall be sent to the
Engineer and to the responsible authority for the district in which the explosives are
kept. .
38
400 SUBBASES, BASES:ANDSHOULDERS
401 SOIL SUBBASES
401.1 Description
This work shall consist of providing laying and compacting soil subbase meterial
on a prepared subgrade or on an existing pavement. The material used shall be as-dug soils
or material obtained by a process or blending soils referred to as mechancal stabilization.
401.2 Materials
The materials used shall be type I or type II sub base materials meeting the
requirements of sub section 1708.2.
401.3 Mechanical Stabilization (blending)
Mechanical stabilization (blending) shall either be done at the site or at the borrow
pits or at designated central yeards.
When site mixing is done for the above puropse soils to be blended shall be spread
uniformly on the prepared surface in the required proportions and then pulverized and mixed
by means of a rotorvator, disc harrow, rotary tiller or any other approved equipment or a
combination of these equipment. The pulverizing and mixing shall be continued until
uniformity of the mix is achieved as far as practicable.
Alternatively the different soils after pulverization shall be mixed by windrowing
using a motor grader.
Manual mixing using pickaxes, spades etc shall be carried out only on small jobs
and with the approval of the Engineer.
When the mixing is done at borrow pits or at designated central yards, it shall be
carried out in a manner as outlined above or any other manner as directed by the Engineer.
401.4 Construction Reuqirements
(a) Preliminaries
Normally the constuction of the subbase shall not commence in any section of the
works until the drainage works in that section have been completed. When this is not
practicable temporary cross drains shall be provided to suitably drain the subgrade as
approved by the Engineer.
Immediately prior to spreading of subbase material, the subgrade that has already
been prepared in conformity with section 304 shall be cleared of any extraneous matter,
notwith - standing any earlier approval of subgrade, and the surface shall be suitably
moistened.
39
Where the subbase is to be placed on an existing paved road, the bituminous crust
shall first be removed by scarifying. The exposed surface shall suitably be compacted prior
to laying of the subbase.
(b) Placing and Compaction of Subbase Material
The subbase material shall normally be spread in layers not exceeding 225 mm for
compaction using 8 - 10 tonne smooth wheeled rolled or any other roller of comparable
compactive effort. Where necessary the material may be spread in thicker layers with the
approval of the Engineer provided a heavier roller is used for the compaction.
Where the subbase is built up of more than one layer the layers to follow shall be
placed only after the degree of compaction of the previous layer has been tested and found
satisfactory as given in sub section 401.3 (c).
The compaction shall be carried out at or near the optimum moisture content.
The moisture content .of the material shall be checked at the time of compaction at
the frequency specified in Table 1602 - 1 or as directed by the Engineer. If the material is
too wet it shall be dried by aeration and if it is too dry, the material shall be sufficiently
wetted prior to compaction.
Rolling shall commence at the edge and proceed towards the centre longitudinally
except at super elevated sections where the rolling shall commence at the lower edge and
proceed towards the higher edge.
(c) Degree of Compaction of Subbase
The subbase shall be compacted to a density not less than 100 % of the maximum
dry density as determined by the standard compaction test specified in section 1804.
(d) Quality Control
. . ..
The control of quality of the material and the work shall be carried out as given in
section 1602.
(e) Finishing Qperations
, .
The compacted subbase shall be finished to levels, grades and cross sections shown
in the drawings and as directed by the Engineer, subject to the requirements given in sectio
1601.
(f) Protection of subbase
Prior to the construction of the base the contractor shall protect the subbase from
damage caused either by water or by traffic or by any other means. Any damage caused shall
be made good prior to the construction of the base. Where the damage may be attributed to
the negligence of the contractor the repairs shal be at his ownexpense.
40
401.5 Measurement and Payment
(a) .. Measurement
Method of measurement shall be anyone of the following as specified :
(i) soil subbase shall be measured as finished work in position in cubic metres as given
in sub section 106.2 (b).
(ii) Soil subbase meterial shall be measured as supplied and piled in cubic metres but
limited to the volume used in the accepted work and the construction of soil subbase
shall be measured based on the volume of material used in cubic metres (as piled) in
the accepted work.
(b) Payment
Payment will be based on the contract unit price/s for the item/s which shall include
full compensation for the components given below for the item/so
The price for soil subbase measured as finished work in position shall include full
compensation for providing all materials, transport, labour, tools, equipment and incidentals
necessary to complete the work to the specifications.
The price for soil subbase material supplied and piled shall include full compensation
for the supply, transport and piling of the material at site.
The price for the construction of soil subbase shall include full compensation for
providing all labour, tools, equipment and incidentals necessary to carry out the construction
work to the specifications.
The pay Items and pay Units will be as follows :
Pay Item Pay Unit
Either
401 (1) Soil subbase compacted in position
(state type of material)
Cubic metres
or the following
401 (2) Soil subbase material as piled
(state type of material) Cubic metres
401 (3) Construction of soil subbase Cubic metres
NOTE
Refer sub section 106.6 regarding sub divisions of pay items.
41
402 STABILIZED SOIL SUBBASES AND BASES
402.1 Description
This work shall consist of the construction of a subbase or base, using soil stabilized with
lime or cement, on a prepared sub grade or subbase.
402.2 Materials
Materials shall conform to the following requirements
(a) Soil for lime stabilization to sub section 1708.3.
(b) Soil for cement stabilization to sub section 1708.4.
(c) Lime for lime stabilization to SLS 552
(d) Cement for cement stabilization to sub section 1703.
402.3 Consturction Requirements
(a) Genen!l
Stabilized soil subbases and bases shall be constructed by the mix-in-place method
unless otherwise specified or approved by the Engineer.
The plant used for the mix-in-place construction shall be capable of pulverizing the
soil to the full thickness or the layer being processed and of achieveing uniformity of the
stabilized material on completion of the mixing.
The material to be stabilized could either be material brought to site or the insitu
material or a blend of these materials. Stabilizing the insitu material shall be allowed only
when suitable material for stabilization is not available within economic haul distance and
in places where the road need not be raised. .
(b) Quantity of Stabilizer in the Mix
The quantity of lime or cement to be added to the soil shall be that specified in the
contract or as directed by the Engineer based on laboratory tests depending on the strenght
requirements of the stabilized mixes and shall not exceed 5% and8% respectively, unless
otherwise specified.
(c) Strength Requirements of Stabilized Soil
The strength of lime and cement stabilized soils shall be measured in terms of the
CBR of the material at 100% maximum dry density. The CBR value and the maximum dry
density shal be determined by the CBR test and the standard compaction test respecti vely as
specified in section 1804. The samples shall be tested for the CBR value seven days after
casting which period shall include three days of moisture curing and four days soaking in
water.
The CBR value required shall be specified in the contract or by the Engineer
depending on whether the stabilized material is to be used as a subbase or base. In the case
of subbases the CBR shall not be less than 30% and in the case of bases the CBR shall not be
less than 80%
42
(d) Preparation of Surface
Prior to the commencement of stabilizing operations the existing surface shall be
cleaned of any extraeous matter.
(e) Depth of Spreading of Scarifying
The depth of spreading of soil brought to site and the depth of scarifying of the
existing soil shall depend on the machinery available for compaction, pulverization and
mixing. Where 8 - 10 tonne smooth wheeled rollers are used for compaction and where
agricultural machinery such as disc ploughs and rotary tillers are used for pulverizing and
mixing, the depth of loose soil spread or scarified shall not exceed 225 mm. Carefu I control
of the depth of spreading and/or scarifying shall be exercised at all times. The deapth of
spreading or scarifying may be increased with the approval of the Engineer provided a
havier roller is used for the compaction.
(f) Pul verization of soil
The loose soil shall be pulverized to the extent as required in sub sections 1708.3 or
1708.4 as relevant, using a disc plough, a rotary tiller, rotorvator or any other approved
plant. Care shall be taken to ensure that the depth of pulverization is equal to the depth of
loose soil. Water may be added to the soil if required for the necessary pulverization.
(g) . Blending of Soils (Mechanical Stabilizations)
Blending of the insitu material and the material brought to site where required shall
be carried out either by uniformaly spreading and mixing or by a process of windrowing as
directed, after such soil is suitably pulverized.
Where it is required to mix two different materials brought to site, to obtain the soil
type required, the blending of such soils shall be carried out as given in section 401.3. The
degree of pulverization of the mixed materials shall conform to the requirements of sections
1708.3 or 1708.4.
(h) Mixing of Stabilizer and Soil
The stabilizer shall be spread manually or by a suitable spreader uniformly over the
entire surface of the pulverized soil. Mixing of the stabilizer and soil shall then be carried
out using a rotary tiller, rotorvator or any other approved equipment until such time that the
soil mixed witn stabilizer is as nearly homogeneous as practicable. Careful control of the
depth of layer shall be maintained in order to obtain a uniform percentage of stabilizer in
the mix.
In the case of cement stabilization the soil and cement shall be dry mixed initially
prior to bringing the soil cement to the optimum moisture content. However, in the case of
lime stabilization the lime may be in the from of dry powder or a slurry.
43
U) CQmpaction of Stalillized Soil Mixture
The stabilized soil mix shall be compacted at or near the optimum moisture content
using a 8 - 10 tonne smooth wheeled roller or any other roller approved by the Engineer.
The moisture content of the material shall be checked at the time of compaction at
the frequency specified in Table 1602 - 1 or as directed by the Engineer.
The rolling shall commence at the edges and proceed towards the centre longitudinaly
except at super elevated sections, where the rolling shall commence at the lower edge and
proceed towards the higher edge. '
In the case of cement stabilized mixes, care shall be taken to complete the rolling
within 1 1/2 hours on addition of water or such smaller period as directed by the Engineer.
(k) Degree of Compaction of Stabilized Subbases and Bases
Stabilized soil subbases shall be compacted to a density not less that 100 % of the
maximum dry density of the soil mix as determined by the standard compaction test specified
in section 1804.
(1) Quality control
The control of quality of the material and the work shall be carried out as given in
section 1602.
(m) Finishing Operations
The compacted subbase or base shall be finished to levels, grades and cross sections
shown on the drawings or as directed by the Engineer, subject to the requirements of section
1601.
(n) Curing and Protection
The stabilized subbase or base shall be cured by keeping the surface continuously
moist by the Contractor by either sprinkling water at frequent intervals or by other approved
means for a period of seven days or for a period specified by the Engineer.
Until the construction of the subsequent pavement layers or surfacing the contractor
shall protect the stabilized subase or base from damage caused either by storm water or by
traffic or by any other means. Any damage caused shall be made good and where such damage
may be atributed to the negligence of the contractor the repair shall be at his own expense.
402.2 Measurement and Payment
(a) Measurement
Stabilized soil subbase or base shall be measured as finished work in cubic metres
as given in sub section 106.2 (b) or in any other manner approved by the Engineer.
44
The quantity of lime and cement used shall be measured separately in kg / tonnes.
(b) Payment
Payment for stabilized soil subbase or base shall be based on the contract unit rate
for the item which shall include full compensation for providing all materials (other than
lime or cement), transport, labour, tools, equipment and incidentals necessary to cornpalete
the work to the specifications.
Payment for the supply of lime and cement will be made on the contract unit rate.
which shall include transport to site.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
402 (l) Stabilized pavement layer
(state type of pavement layer, type of stabilization) Cu bic metres
402 (2) Lime kg / Tonne
402 (3) Cement kg / Tonne
Note
Refer sub section 106.6 regarding sub divisions of pay items.
45
403 SINGLE SIZED AGGREGATE BASES
403.1 Description
This work shall consist of the construction of base courses, using nominal single
sized crushed stone aggregate, on a prepared subgrade, subbase, or existing pavement.
The base courses are formed by mechanically interlocking larger sized aggregate
and choking the surface interstices with smaller sized aggregate.
403.2 Materials'
The aggregate used shall be of nominal single sizes 50 mm (2") or 37.5 mm (l 1/2")
and 19 mm (3/4") or 12.5 (1/2") respectively and nominal single size 100 mm (4"), all
conforming to the general requirements of sub section 1701.3 (a). The size requirements of
100 mm (4") aggregate shall be as given in 1701.3 (c) and the grading requirements of the
other aggregates shall be as given in Table 1701 - 4 of sub section 1701.3 (b).
403.3 Construction Requirements
(a) Thickness of Base C o u r ~
The nominal compacted thickness of the base course shall be 75 mm or 150 mm
depending on whether only two spreads of 50 mm aggregate or whether one spread of 100
mm aggregate and two spreads of 50 mm aggregate are used in the construction respectively.
Where 37.5 mm aggregate is used instead of the 50 mm aggregate, the nominal compacted
thicknesses given above shall be reduced to 55 mm and 130 mm respectively. For higher
thicknesses of bases, the composition of the aggregate courses shall be as specified, or as
directed by the Engineer.
(b) Preparation of Existins Surface
Where the base course is laid over a prepared subgrade or subbase, the surface,
shall be brushed free of dust and extraneous matter and, if required, wetted before laying
the base course.
Where the base course is laid over an existing gravel road any unevenness of the
surface and places of failure shall be corrected as required or as directed by the Engineer
and the surface shall be prepared and wetted as given above, prior to laying operations.
Where the base course is laid over an existing bituminous pavement, the surface
shall be scarified lightly and cleaned of any scarified material or in the alternative a tack
coat as specified in section 502 shall be applied, prior to laying operations.
(c) Construction of a Base with 50 mm or ;37.5 mm Assresate
(i): The 50 mm (2") or 37.5 mm (l .112") aggregate shall be spread evenly on the prepared
surface at a rate given in Table 403 - 1, to form a uniform layer two stones thick.
46
(ii) Prior to spreading the aggregate base, a partial width of the shoulder, not less than 0.6
m wide, shall be constructed to the elevation of the top of each compacted layer of
base being placed. The construction of the partial width of shoulder shall conform to
the requirements of section 409. The inside edges of this shoulder fill shall be made to
follow the proposed edge of the pavement and after compaction shall be trimmed to a
near vertical face.
The edge of base and the partial width of shoulder may be compacted together
provided mixing of soil and aggregate at the interface could be effectively prevented.
(iii) The aggregate shall be compacted using a 8 - 10 tonne steel wheeled roller or any .
other approved roller.
(iv) The rolling shall be done by a series of over lapping longtudinal passes of the roller
working from the edge towards the centre, except on super elevated sections where the
rolling shall progress from the lower edge to the higher edge.
(v) While the rolling proceeds fresh aggregateshall be added where necessary, and removed
from places where there is excess. The surface shall be watered to help the bedding in
of the aggregate except where the base course is laid o v ~ r an existing bituminous
pavement. Rolling shall be continued till the aggregate dod not shift or wave in front
of the roller. However, over rolling which would cause rounding of aggregate particles
. shall be avoided.
(vi) The 19 mm (3/4") or 12.5 mm (112") choker stone shall then be spread evenly at the
rate specified in Table 403 - 1 and rolled to ensure that the stones are well embedded in
the surface interstices of the base course. While the rolling is being done, the surface
shall be wetted and lightly brushed so as to ensure that the finer aggregate including
fines are worked into the crevices.
(d) Construction of Base with 100 mm and 50 mm / 37.5 mm A&&re&ate
A partial width of shoulder shall be constructed as given in sub section 403.3 (c)(ii).
Unless otherwise directed, 100 mm (4") aggregate shall be spread and where
necessary hand packed uniformaly to one stone thickness on the prepared surface at the rate
indicated in Table 403 -1, and shall be rolled using a 10 tonne roller, to achieve sufficient
embedment without excessive rounding of aggregate edges. Where directed, the surface voids
of the 100 mm (4") aggregate layer shall be infilled with crusher dust prior to spreading the
next layer. 50 mm (2") or 37.5 (1 1/2") aggregate of two stones thickness shall then be
spread uniformly at the rate indicated in Table 403 - 1, and compacted using an approved 8
- 10 tonne steel wheeled roller in accordance with the method of rolling. as given in sub
section 403 (c) (iii) to (v)..
47
The choker stone shall be spread and compacted in accordance with sub section 403
(c) (vi).
Table 403 :- 1 - Rates of Spread of Aggregate
Nominal Aggregates
Rate of Spread
thickness of Size
Cubic metres per
Cubic feet per
base layer
100 sq.m.
100 sq. ft.
75 mm (3") 50 mm (2") aggregate 8.5 - 10.0 28 - 33
19 mm (3/4") choker stone 1.0 - 1.3 3.3 - 4.2
55 mm (2 1/4") 37.5 mm (1 1/2") aggregate 6.6 - 7.5 21 - 25
12.5 mm (1/2") choker stone 0.8 - 1.0 2.5 - 3.2
150 mm (6") 100 mm (4") aggregate 8.5 - 10.0 28 - 33
50 mm (2") aggregate 8.5 - 10.0 28 - 33
19 mm (3/4") choker stone 1.0 - 1.3 3.3 - 4.2
130 mm (5 114") 100 mm (4") aggregate 8.5 - 10.0 28 - 33
37.5 mm (1 112") aggregate 6.6 - 7.5 21 - 25
12.5 mm (112") choker stone 0.8 - 1.0 2.5 - 3.2
48
(e) Surface Finish and Quality Control
The single sized aggregate base shall be finished to the requirements of section
1601.
The control on the quality of materials and works shall be exercised in accordance
with section 1602.
(f) Aftercare
The suface of the base so formed shall be maintained in its finished condition until a surfacing
is placed the-teon, and any damage caused prior to the placement of the surfacing which
could be attributed to the negligence of the contractor shall be made good by him at his own
expense.
403. 4 Measurement & Payment
(a) Measurement
Method of measurement shall be anyone of the following as specified.
(i) Aggregate base course, shall be measured as finished and accepted work in position of
each nominal thickness of base in square metres of plan area of surface.
(ii) The materials of the finished and accepted base course shall be measured as supplied
and piled in cubic metres and the construction of the aggregate base course shall be
measured in cubic metres of aggregate used separately in each layer of construction.
In this regard 100 mm (4") aggregate shall constitute one layer and the 50 mm (2") and
19mm (3/4") or the 37.5 mm (1 112") and 12.5 mm (112" ) aggregate shall constitute
another layer.
(b) Payment
The unit rate of payment of aggregate base course measured as finished work in
position shall include full compensation for providing all materials, transport, labour, tools,
equipment and incidentals necessary to complete the work to the specifications.
The unit rate for material/s supplied and piled shall include full compensation for
the supply, transport and piling of the materialls at site.
The unit rate for the construction of aggregate base course shall include full
compensation for providing all labour, tools, equipment and incidentals necessary to carry
out the construction work to specifications.
49
The and Pay Units wi! b as.JollQws:
Pay item
Either
Pay Unit
403 (1) Single sized aggregate base compacted
in position (state nominal thickness) Square metres
or the following
403 (2) Single sized aggregate base as piled
(state nominal sizes) Cubic metres
403 (3) Consturction of single sized aggregate
base (state nominal sizes of aggregate) Cubic metres
Refer sub section 106.6 regarding sub divisions of pay items.
50
404 WATER BOUND AND DRY BOUND MACADAM BASES
404.1 Description
This work shall consist of spreading and rolling crushed rock aggregate on a prepared
sub grade, subase, base or on an existing road to form a mechanically interlocked layer and
then filling the voids to refusal with crusher fines or gravel.
The infilling with fines shall be done by watering in water bound macadam and by
vibrating with vibratory roller in dry bound macadam.
Where more than one course has to be built, the process shall be repeated.
404.2 Materials
Materials used shall conform to the requirements of the following :
(a) The aggregate of nominal size 50 mm (2") or 63 mm (2 1/2") and cursher fines to
sub section 1701.3 (a) for general requirements and to table 1701 - 6 of sub section
1701.3 (b) for grading.
(b) Natural gravels to sub section 1708.6.
404.3 Construction Requirements
(a) Preparation of Existing Surface
The preparation of existing surface shall be carried out as per sub section 403.3 (b)
and as applicable, prior to the laying of the water bound or dry bound macadam base.
(b) Preliminary Layer of Fines
Unless otherwise specified or directed, where the water bound / dry bound macadam
is to be laid directly on the sub grade or on a soil subbase, a 20 - 30 rom course of crusher
fines shall be spread as a preliminary layer on the prepared sub grade or subbase prior to
spreading of coarse aggregate. Where the material infilling voids in the coarse aggregate is
a natural gravel the preliminary layer also shall be of the same natural gravel.
(c) Spreading and Rolling of Coarse Aggregate
Prior to spreading of aggregate a partial width of shoulder shall be constructed as
given in sub sectior 403.3 (c) (ii).
The coares aggregate shall be spread, uniformly over the prepared surface, so as to
ensure that the thickness of the course after compaction is between one and a half to two
times the nominal maximum size of aggregate. Rolling of the aggregate shall then be done
using 8 - 10 tonne steel wheeled rollers or approved vibratory rollers. The method' of
compaction shall be in accordance with sub section 403.3 (c) (iii) to (v).
51
(d) Application of Crusher Fines Qr.. Gravel
The crusher fines or gravel in a dry state, shall be worked into the compacted
aggregate layer by a gradual process of spreading, brushing and rolling. The crusher fines
or gravel shall not be dumped in piles but be spread uniformly in successive layers. When
tippers are used for spreading, care shall be excercised to see that the aggregate layer is not
disturbed in the process.
(e) Vibratory Rolling in Dry Bound Macadam Base
For Dry Bound Macadam base the crusher fines in a dry state, spread as given in sub
section 404.3 (d) shall be vibrated further into the interstices using a vibratory roller. Should
patches deficient in fines develop during compaction, additional fines shall be applied and
the process continued until no more can be worked in. The final compaction shall be carried
out by using, the same roller without vibration or a 8 - lO tonne steel wheeled roller.
(f) Wet Rolling in Water Bound Macadam Base and Curing
For Water Bound Macadam base, the surface of the layer shall be watered and
additional cursher fines or gravel applied and the rolling continued until all the voids are
completely filled and a wave of grout flushes in front of the roller.
The base course so formed shall be cured and allowed to dry out compaletely, before
another course or a bituminous coat is aplied.
(g) Construction of Additional Courses
Where additional courses are required to be constructed, the surface shall be brushed
free of dust using mechanical brooms or hand brooms or both until the aggregate surface
stands proud of the compacted fines. The construction procedure in sub section 404 (c)
404 (f) as relevent shall then be repeated to form the additional course/s, as required.
(h) Finishing Operations and Quality Control
The water bound / dry bound macadam base shall be finished to the requirements of
section 1601.
The control on the quality of materials and works shall be exercised by the Engineer
in accordance with section 1602.
U) Afterecare
Provisions of sub section 403.3 (f) shall apply.
404.4 Measure,mentand Payment
(a) Measurement
Water bound / dry bound macadam base shall be measured in square metres or in
cubic metres of accepted work in postion, as specified. Method of measurement shall be as
given in sub section 106.2 or as driected. The preliminary layer of crusher fines or gravel
shall be measured separately in square metres of area completed and accepted.
52
(b) Payment
Payment will be based on the contract unit rate for the item which shall include full
compensation for providing all materials, labour, tools, equipments and incidentals necessary
to complete the work to the specifications.
The Pay Items and Pay Units will be as follows ;
Pay Item Pay Unit
404 (1) Preliminary layer of fines (state whether
crusher fines or gravel) Square metres
Either
404 (2) Water bound / dry bound macadam base
(state size of aggregate and type of infill) Cubic metres
or
404 (3) . Water bound / dry bound macadam base
(state size of aggregate layer thickness
and type of infill) square metres
Refer sub section 106.6 regarding sub divisions of pay items.
53
405 DENSE GRADED AGGREGATE BASES
405.1 Description
This work shall consist of providing, laying and compacting a graded crushed rock aggregate
base on a prepared sub grade, subbase or base or existing pavement.
405.2 Materials
(a) The aggregate shall be graded crushed rock with nominal maximum size of 50 mm (2")
or 37.5 (40) mm (1 1/2") or 25 mm (1") or 19 mm (3/4") conforming to general requirements
of sub section 1701.3 (a) and grading requirements of Table 1701 - 5 of sub section 1701.3
(b).
405.3 Construction Requirements
(a) Preparation of Existing surface
The preparation of surface shall be carried out as per sub section 403.3 (b) prior to
the laying of the dense graded aggregate base.
(b) Spreading and Rolling
The aggregate shall be spread without segregation over the prepared surface of an
accepted subgrade, subbase, base or existing pavement uniformly and in sufficient quantities
to give the required thickness when compacted.
It shall be ensured that the thickness of each layer after compaction shall not be less
than 75 mm. Where 8 - 10 tonne smooth wheeled rollers are used the compacted thickness
shall normally not exceed 150 mm. However, with heavy vibratory rollers greater thicknesses
may be compacted with the prior approval of the Engineer.
Prior to spreading of aggregate a partial width of shoulder shall be constructed as
described in sub section 403.3 (c) (ii) unless directed otherwise.
In order to reduce the tendency for segregation, the material shall be kept wet during
transport and spreading. The material deposited on the prepared existing wsurface may be
spread and shaped by any method which will not cause the segregation of the coarse and
fine particles. When directed by the Engineer, all areas of segregated coarse or fine material
shall be corrected by removing and replacing with well graded meterial. The base material
shall be compacted using a 8 - 10 tonne smooth wheeled roller or any other approved roller.
Sufficient water shall be added to facilitate compaction and the required moisture content
shall be determined by carrying out a field trial. The method of rolling shall be as described
in sub section 403 (c) (iv).
The aggregate base shall be compacted to at least 100% of the maximu dry density
of the material as determined by the standard compaction test specified in sub section 1804.4.
54
(c) Field Density Testing
Field density tests shall be carried out at the frequency given in Table 1602 - 1 for
each layer or as directed by the Engineer. Tests shall be carried out as given in sub section
1801.10.
(d) Einishing Operations and Quality Control
The dense graded aggregate base shall be finished to the requirements of section
1601.
The control on the quality of materials and works shall be exercised in accordance
with section 1602.
(e) Aftercare
Provisions of sub section 403.3(f) shall apply.
405.4 Measurement and Payment
(a) Measurement
Dense graded aggregate base shall be measured in square metres or in cubic metres
of accepted work in position, as specified. Method of measurement shall be as given in sub
section 106.2 or as directed.
(b) Payment
Payment will be based on the contract unit rate for the compaleted work as measured
which shall include full compensation for providing all materials, labour, tools, equipment
and incidentals necessary to compalete the work to the specifications.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
Either
405 (1) Dense grade aggregate base
(state aggregate size) Cubic metres
405 (2) Dense grade aggregate base
(state aggregate size and thickness of layer) Square metres
Refer sub seetin 106.6 regarding sub divisions of pay items.
55
406 PENETRATION MACADAM BASES
406.1 Description
This work shall consist of the construction of a penetration macadam base on a
prepared subbase or an existing pavement.
The base shall consist of one or more courses of compacted coarse aggregate with
alternate applications of bituminous binder and key aggregate.
406.2 Materials
(a) The coarse aggregate shall be of nominal maximum size 50 mOl or 37.5 rnrn or 25 mm
and the key aggregates shall be of nominal maximum size 19 mm or 12.5 mm or 9.5
mm conforming to the general reuqirements of sub section 1701.3 (a) and the grading
requirements of table 1701 -7 in sub section 1701.3 (b).
(b) Bituminous binder shall be penetration grade bitumen or 10 - 20 percent cutback bitumen
or MC 800 or MC 3000 cutback bitumen or bitumen emulsion CRS - 1 or CRS -. 2
conforming to section 1702.
406.3 Construction requirements
(a) Thickness of Base Course
The nominal compacted thickness of each course of penetration macadam base shall
be 75 mrn or 55 mm or 40 mOl depending on whether the coarse aggregate used is of maximum
nominal size 50 mOl or 37.5 mm or 25 mm respectively. If higher thicknesses are required
such bases shall be built up by constructing two or more courses.
Normally, the 40 mm penetration macadam base shall be used only for correction
courses.
(b) Weather and Other Limitations
Penetration macadam base shall not be constructed during rainy weather or when
the ambient temperature is 15 degree centigrade or lower. It shall also not be constructed
when the underlying surface is damp unless the binder used is bitumen emulsion.
(c) Preparation of Existing Surface
The surface on which the penetration macadam is to be constructed shall be prepared
to the lines, grades and cross sections given in drawings or as directed by the Engineer.
In the case of existing pavements all potholes, ruts and depressions shall be repaired
in advance as per section 1102.
The surface shall be brushed free of dust and extraneous matter. Any prime coat or,
tack coat specified or directed to be applied shall be carried out in accordance with sections
501 and 502 respectively.
56
(d) Spreading and Compac.ting Coarse Aggregate
The coarse aggregate in a dry state shall be spread uniformly at the rate specified in
Table 406-1. The. spreading shall be carried out no further in advance of the rolling,
penetrating and laying operations than can be completed on the same day. The coarse
aggregate shall then be rolled, using a 8 '" 10 tonne smooth wheeled roller or any other
roller approved by the engineer, until the .aggregate .is.well interlocked and compacted.
The rolling shall commence at the edges and proceed towards the centre
longitudinally, except on super - elevated sections where it shall progress from the lower
edge to the upper edge.
On completion of the above rolling the surface regularity shall conform to the
tolerances given in sub section 1601. Irregularities exceeding the above tolerances shall be
corrected by removing or adding aggregate as required. The compacted surface shall have a
texture that will allow free and uniform penetration of the bituminous binder.
(e) Application of Bituminous Material
The bituminous binder shall be applied on the compacted aggregate at the rate of
application given in Table 406 - I, unless otherwise specified. The temperature of application
of the binder shall be as given in Table 406 - 2. The application of the bituminous binder
shall be carried out using pressure distributors. Manual application shall be resorted to only
with the approval of the Engineer.
Table 406 . 1
Rate of spread of binder and aggregate
Compacted Rate of spread of Rate of spread of
nominal aggregate cubic metres binder litres per square
thickness of per square metre metre
course
Coarse
Key Penetration
Cutback Bitumen
mm
aggregate
aggregate Grade bitumen
bitumen Emulsion
75 9.0 1.8 5.0 - 6.8 5.5 - 7.5 7.5 - 10
55 6.0 1.5 4.0 - 5.5 4.5 - 6.0 6.0 - 8.5
40 4.5 1.2 3.0 - 4.5 3.3 - 5.0 4.5 - 6.5
57
I
Table 406 2 a
Temperatures of application of binder
Temperature of
Binder
application - C
Penetration grade bitume 160 - 175
Me 3000 or 10% cutback butumen 120 - 130
MC 800 or 20 % cutback bitumen 150 - 115
Bitumen Emulsion CRS - 1 or CRS - 2 Ambient Temp.
Where the ambient temperature is low, the bitumen emulsion shall be sufficiently
heated to facilitate spraying. With CRS 2 heating will be necessary in most instances.
(f) Application of the Key Aggregate
Immediately after the application of the bituminous binder key aggregate in a dry
state shall be spread uniformly over the surface by means of an approved mechanical spreader
or by approved manual methods at the rate specified in Table 406 - 1. Where necessary the
surface shall be broomed to ensure uniform application of the key aggregate. Rolling shall
then be resumed and continued until the surface is hard and smooth and shows no visual
movement under the roller.
(g) Surface Finish and Quality Control
The penetration mecadam base shall be finished to levels, gradeand cross sections
shown in the drawings and as directed by the Engineer, subject to the reqquirements given
in section 1601. The control of the quality of materials and works shall be carried out as
given in section 1602. .
(h) Aftercare
Where a surfacing over the penetration macadam is specified it shall be protected
until the surfacing is provided. Any damage caused shall be made good to the completed
work prior to the placement of the surfacing. Any damage which could be attributed to the
negligence of the contractor shall be repaired by him at his own expense
406.4 Measurement and Payment
(a) ~ e a s u r e r n e n t
Method of measurement shall be anyone. of the following as specified ;
58
(i) Penetration macadam base shall be measured in square metres of accepted work. Bases
of different thicknesses shall be measured separately. .
(ii) Coarse aggregate and key aggregate shall be measured as supplied and piled in cubic
metres and the bitumen shall be measured as supplied in litres, both measurements
being limited to the quantities used in the accepted work. The construction of the
penetration macadam base shall be measured in square metres of completed and accepted
work. The construction of different thicknesses of the penetration macadam base shall
. be measured separately.
(b) Payment
Payment will be based on the contract unit price/s for the item/s which shall include
full compensation for the components given below for the item/so
The price for penetration macadam base measured as finished work shall include
full compensation for providing all materials, transport, labour, tools, equipment and
incidentals necessary to complete the work to the specifications.
The price for coarse aggregate and key aggregate supplied and piled shall include
full compensation for the supply, transport and piling of the material at site. The price for
bitumen shall be full compensation for the supply and transport to site.
The price for the construction of penetration macadam base shall include full
compensation for providing all labour, tools, equipment and incidentals necessary to carry
out the construction work to the specifications.
The Pay Items and Pay Units will be as follows :
Pay item Pay Unit
Either
406 (1) Penetration macadam base
(state thickness of layer) Square metres
or the followinG
406 (2) Coarse aggregate as piled (state size) Cubic metres
406 (3) Key aggregate as piled (state size) Cubic metres
406 (4) Bituminous binder (state type and grade) Litres
406 (5) Construction of penetration macadam
base (state thickness) Square metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
S9
407 BITUMEN BOUND BASES
407.1 Description
This work shall consist of the constructionof courses of dense graded or open graded
bitumen bound bases on prepared subbases, bases or existing roads. .
407.2 Materials
Unless otherwise specified by the Engineer, all materials shall conform to the
requirements of the following :
(a) The bindre shall be 80 - 100 penetration grade bitumen to sub section 1702.1.
(b) Coarse aggregate of nominal maximum size 37.5 mm (40 mm) & 19 mm and the
fine aggregate shall conform to general requirements of sub section 1701.3(a). Their
combined gradings shall conform to the requirements of sub section 407.3.
407.3 Mix Requirements
(a) Combined grading of Aggregate and Binder Content
The grading requirements for combined aggregate and the binder contents shall be as
given in Table 407 - 1 for the open graded and dense graded base courses.
TABLE 4071
Aggregate grading, binder content and thickness requirements
Mix Classification No. 1 2 3 4
Nominal maximum size of
aggregate inmm 37.5 37.5 19 19
Course
Thickness mm - Max 100 100 50 40
- Min. 50 50 30 30
Sieve Size Total % of weight passing
mm urn
,50 100 100
'37.5 95 - 100 95 - 100
25 75 - 90 35 - 65 100 100
19 70 - 100 95 - 100
12.5 60 -75 5 - 20 35 - 65
9.5
35 - 60 20 - 40
4.75 15 - 35
2.36 30 - 45 0- 10 5 - 20 5 - 20
75 3 - 6 0-2 0-4 o - 2
Percent binder
content by total 3.0 - 4.0 2.5 - 3.5 3.5 - 4.5 3.0 - 4.0
weight of mix
60
The sieve sizes used herein are as per ASTM disignation. However equivalent BS
sizes as given in Table 107 - 1 in section 107, may be used with the prior approval of the
Engineer.
407.4 .lob Mix Formyla
The contrac forshall conform to the requirements of sub section 506.4 in proposing
the job mix formula.
407.S Construction Requirements
(a) Clonstruction reuqirements shall conform to section 506.5 (a) to (m) subject to the
following modifications :
(i) The compaction procedure as given in 506.5 (h) shall apply, except for the .
requirement of the density check.
(ii) The maximum and minimum thickness of any compacted layer shall be as given in
Table 407 - 1.
(b) ,Finishini Qperations and Quality Control
The bitumen bound base shall be finished to the requirements given in section 1601.
The control on the quality of materials and works shall be exercised in accordance
with section 1602.
407.6 Measurement and Payment
(a) Measurement
Bitumen bound base shal be measured by anyone of the following methods specified
in the contract. . .
(i) In tonnes; weighed using a weigh bridge
The bitumen bound base measured shal be the number of tonnes in the accepted
pavement. The method of measurement shall be. as.follows : . .
The bitumen bound base shall be weighed after mixing using an approved weigh
bridge. The total quantity of bitumen bound base mixed and laid shall be computed daily
from load delivery tickets. This weight shall be adjusted by deducting the weight of mix
wasted at joints, the weight of mix laid in areas outside the defined pavement edge and the
weight of mix laid within the defined pavement but not accepted by the Engineer. The total
weight so deducted shall be as assessed by the Engineer.
The weight of bitumen bound base measured for payment each day shall be the
weight adjusted as above subject to the condition that it shall not exceed by more than 5%
the weight required for the accepted area laid for the day, based on the specified thickness
for the layer given in drawings or as directed by the Engineer and the mean value of compacted
density of the mix.' The compacted denity of the mix, shall be assessed by means of core
samples. The frequency of taking cores shall not be less than one per 500 square metres for
the area laid and accepted each day.
61
(ii) In cubic metres as compacted in position, measured by cutting cores
Measurements shall be based on the authorised and accepted area laid and the mean
value of thickness of cores cut in the accepted area. The quantituies shall be calculated for
work done on a daily basis. The quantity measured for payment each day shall not exceed
by more than 5% the volume required for the area laid and accepted for the day, based on the
thickness of the layer given in drawings or as directed by the Engineer.
The frequency of taking cores for thickness measurements shall not be less than one
per 500 square metres for the area laid and accepted each day The thickness of each core
shall be calculated by dividing the volume of the core by the mean area of cross section.
The volume shall be determined by weighing in air and in water (water displacement method).
the mean area of cross section of the core shall be calculated using the mean diameter. The
mean diameter shall be the average of four readings taken, two each at right angles to each
other at two circles near the top and bottom of the core. The diameter shall be measured
using callipers.
(iii) In cubic metres, as compacted in position measured by taking levels
Method of measurement shall be as given in sub section 106.2 (b).
(iv) In cubic metres measured as loose volume
The bitumen bound base shall be measured in the hauling truck. This method is
essentially for small works including small scale regulating courses.
The volume of bitumen bound base shall be measured in the hauling vehicle after
levelling in the loose state, at the point of delivery. The volume measured as above shall be
suitably adjusted for material wasted at the joints, for the material laid outside the 'defined
pavement edges, for excess thicknesses laid and for material laid within the defined pavement
edge but not accepted by the Engineer.
(b) Payment
Payment for bitumen bound base will be made at the contract unit price for the item
as measured above. The price shall be full compensation for furnishing all materials, for
mixing and placing of the mixed material and for providing all plant, machinery, equipment,
tools, labour and incidentals necessary to compalete the work to these specifications.
62
The Pay Items and Pay Units will be as follows: - .
Pay Item Pay Unit
Either
407 (1) Bitumen bound base Tonnes
or
407 (2) Bitumen bound base, compacted in
position (measured by cutting cores) Cubic metres
or
407 (3) bitumen bound base, compacted in
position (measured by taking levels) Cubic metres
or
407 (4) Bitumen bound base, (measured
in loose state in hauling vehicle) Cubic metres
Refer sub section 160.6 regarding sub divisions of pay items.
63
408 RECONSTURCTION OF AGGREGATE BASES
408.1 Description
This work consists of the reconstruction of existing bitumen surfaced aggregate bases
that require restrenghtening and reshaphing,
Work shall be carried out either by rebuilding the existing base along with added
aggregate or by overlaying with aggregate, penetration mecadam or bitumen bound macadam.
408.2 Materials
(a) Aggregate for aggregate bases, consisting of 50 mm, 37.5 mm, 19 mm and 12.5 mm
single sized aggregate and graded aggregate of maximum size 37.5 (40) mm, shall
conform to the general requirements of sub section 1701.3 (a). the grading of single
sized aggregate and the graded aggregates shall conform to the requirements of Tables
.1701 - 4 and 1701 - 5 respectively of sub section 1701.3 (b).
(b) Aggregate and binder for penetration macadam and bitumen bound macadam shall be
as given in the respective sections.
408.3 Construction Requirements
(a) Rebuilding of Existing Base
The existing pavement shall be sufficiently scarified using roller tynes or by other
approved means to enable all the bituminous surface crust to be removed. In removing the
bituminous pieces it shall be ensured that as much of the adhering aggregate is dislodged
from the pieces and left behind to be mixed with the added aggregate.
Extra aggregate either of the 50 mm or 37.5 mm single size or graded aggregate of
maximum size 37.5 (40) mm shall then be added as specified or directed, on the the existing
aggregate in the required quantities.
Where 50 mm or 37.5 mm single sized aggregate is used it shall be ensured that the
added aggregate and the existing aggregate, in the minimum, produces a layer that is at least
two stone thick and on compaction gets well interlocked. Layers more than three stone thick
shall not be constructed without the prior approval of the Engineer. The work shall be
completed to the required cross section, along with the rolling in of 19 mm or 12.5 mm
choker stone to cover the surface interstices, as given in section 403.
Where garaded aggregate of 37.5 (40) mm maximum size is used the added aggregate
shall be in such quantities that after compaction there shall be a minimum aggregate thickness,
at any place, of 75 mm and that the maximum thickness does not exceed 150 mm unless
otherwise specified. Work of compaction and surface finishing shall be carried out as given
in section 405.
64
(b) Overlaying
Overlays shall be constructed suing anyone of the following techniques as applicable.
Single sized aggregate base conforming to requirements of section 403, excluding
the use of 100 mm aggregate bottoming. .
Graded aggregate base conforming to requirements of section 405.
Penetration macadam base conforming to requirements of section 406.
Bitumen bound base conforming to requirements of section 407.
The thickness of the overlays shall be as specified or as determined by the Engineer
with due consideration to the following requirements.
(i) The minimum thickness of a single sized aggreggate layer shall be that formed by the
compaction of two spreads of aggregate, which are approximately 75 mm for 50 mm
aggregate and 60 mm for 37.5 (40) mm aggregate.
No layer shall be formed by more thean three spreads of single sized aggregate
except under exceptional circumstances approved by the Engineer.
(ii) The minimum compacted layer thickness of graded aggregatre shall be 75 mm and the
maximum thickness shall not exceed 150 mm except where heavy vibratory compaction
equipment are used.
The surfaces on which the overlays are laid shall be prepared as required, by
roughening or tack coating as directed.
408.4 Measurement and Payment
(a) Measurement
. (i) Rebuilding of existing base
Unless otherwise specified the aggregate supplied for base rebuilding shall be
measured in cubic metres and the correctd base by square metres of surface area. Scarifying
and removal of bituminous pieces shall be measured in square metres of surface area
(ii) Overlaying
Measurement shall be as per the appropriate section.
65
(b) Payment
(i) Rebuilding existing base
Payment will be based on the contract unit prices for the items which shall include
full compensation for the components given below for the items.
The price for the aggregate supplied. shall include full compensation for the supply,
transport and piling of the material at site.
The price for base correction and for scarifying existing base shal include full
compensation for providing all labour, tools, equipemetn and incidentals necessary to carry
out the work to the specifications. Removal of bituminous pieces shall be incidental to
scarifying the existing base.
(ii) Overlaying
Payment shall be as per the appropriate section.
The Pay Items and Pay Units will be as follows :
Pay item
408 (1)
408 (2)
408 (3)
Aggregate supplied (state size)
Base correction using available aggregate
Scarifying existing base
Pay Unit
Cubic metres
Square metres
Square metres
~
Refer sub section 106.6 regarding sub divisons of pay items.
66
409 SHOULDER CONSTRUCTION
409.1 Description
This work shall consist of the construction of road shoulders on either side of the
pavement.
409.2 Materials
Shoulder construction materials shall conform to the requirements of the following.
(i) Soil to sub section 1708.5
(ii) Porous material to sub section 1708.8
409.3 Construction Requirements
(a) General
Unless otherwise directed by the Engineer, the road shoulder shall be constructed
prior to or together with the construction of the base, except when the base is of bitumen
bound material.
Porous shoulder meterial wher specified, shall be filled in trenches at locations given
the drawaing or as directed by the Engineer.
(b) Placini and Compaction of Shoulder Material
The shoulder material shall normally be spread in layers not exceeding 225 mm for
compaction using a 8 - 10 ton smooth wheeled roller or any other roller of comparable
compactive effort. Where necessary the material may be spread in thicker layers with the
approval of the Engineer provided a heaviour roller is used for the compaction.
Where the shoulder is built up of more than one layer, the layers to follow shall be
placed only after the degree of compaction of the previous layer has been tested and found
satisfactory as given in sub section 409.3 (c).
The shoulder material shall be compacted at or near the optimum moisture content.
The moisture content of the material shall be checked at the time of compaction at
the frequency specified in Table 1602 - 1 or as directed by the Engineer. If the material is
too wet it shall be dried by aeration and if it is too dry, the material shall be sufficiently
wetted prior to compaction.
During all stages of shoulder construction the contractor shall ensure efficient
drainage of surface water from the entire road surface, to the approval of the Engineer.
Where porous material is specified such material shall be placed and compacted in
trenches cut in the completed shoulder, as indicated in drawings or as directed by the Engineer.
67
(c) Degree of Shoulders
The shoulder shall be compacted to a density not less than 100% of the maximum
dry density as determined by the standard compaction test specified in section 1804.
(d) Quality Contron
. The control fo quality of the material and the work whall be carried out as given in
section 1602.
(e) Finishing Operations
The compaleted road shoulder shall conform to the levels, slopes and cross sections
shown in the drawings and shal be such as to ensure that water from the road, drains over
the shoulder freely.
Where specified or directed by the Engineer, the top surface of the shoulder shall
either be grassed or given a bituminous surfacing to prevent erosion.
409.4 Measurement and Payment
(a) Measurement
Method of measurement shall be any one of the following as specified. :
(i) Shoulder construction shall be measured as finished work in position in cubic
metres. Trench construction in shoulders using porous material shall be measured
separately. The method of measurement shall be as givenin sub section 106.2 or as
directed.
(ii) Soil shoulder material and porous material shall be measured as supplied and piled
in cubic metres but limited to the volume of material used in cubic metres '(as piled)
in the accepted work.
Any bituminous surfacing or grassing done shall be measured separately as given in
the relevant specifications.
(b) Payment
Payment will be based on the contract unit prices for the items which shall include
full compasation for the components given below for separate items.
The prices for shoulder constuction and trench construction in shoulders measured
as finished work in position shall include full compensation for providing all materials,
transport, labour, tools, equipment and incidentals necessary to complete the work to the
specifications.
The prices for soil shoulder material and porous tenchmaterial supplied and piled
shall include full compensation for the supply, transport and piling of the material at site.
68
The prices for the construction of the soil shoulders and trench construction in
shoulders shall include full compensation for providing all labour, tools, equipment. and
incidental necessary to carry out the construction work to the specifications.
The Pay Items and Pay Units will be as follows :
Pay Item
Either
409 (1) Shoulder as compacted in position
i!lli!
409 (2) Trenches in shoulder using porous
material as compacted in position,
or the following
409 (3) Shoulder material as piled
409 (4) Porous trench material as piled
409 (5) Construction of shoulder
409 (6) Construction of trenches in shoulders
. Pay Unit
Cubic metres
Cubic metres
Cubic metres
Cubic metres
Cubic metres
Cubic metres
69
500 SURFACE APPLICATIONS, SURFACE DRESSINGS AND SURFACINGS
501 PRIME COAT
501.1 Description
This work shall consist of an application of a prime coat on a base or subbase newly
constructed using gravelley soil, stabilised soil or aggregate, prior to laying of a surface
dressing or a surface course, so as to provide a proper bond between the layers and also to.
serve as a protective measure for the base or subbase.
501.2 Materials
Materials used shall meet the requirements of the following unless otherwise directed :
(a) Binder shall be medium curing cutback bitumen (20 - 45 percent) or MC 30 or MC 70
or MC 250 or MC 800 to sub section 1702.2 or bituminous emulsion of grade CSS - 1
or CSS - l h to sub section 1702.3.
(b) Blotting (blinding) Material shall be coarse sand, to sub section 1701.4.
501.3 Construction Requirements
(a) weather Limitations
The prime coat shall generally be applied in dry weather and when the ambient
temperature is not below 15 degrees C. It shall not be applied when rain is imminent.
(b) Preparation of Surface
Prior to the application of prime coats the surfaces shall be well brushed to remove
all dust, loose particles and other objectionable material, with a power broom or any other
means approved by the Engineer. In the case of aggregate bases, such cleaning shall continue
until the entire surface shows a pattern of exposed large particles free from dust as far as
,
practicable. The surface shall be moistened with water prior to application of the binder,
unless otherwise directed by the Enginer.
(c) Application of Binder
The prime coat shall be applied by means of a mechanicl sprayer or a hand sprayer,
or any other means approved by the Engineer, at a temperatue within the range given in
Table 50 1 - 1.
70
Table 501 - 1 Spraying temperatures for binders
Temperatures
Binder Type
degrees C
MC 30 or 45 Percent Cutback Bitumen
MC 70 or 35 Percent Cutback Bitumen
MC 250 or 25 Percent Cutback Bitumen
MC 800 or 20 Percent Cutback Bitumen
\
Emulsions
40 - 50
55 - 70
80 - 90
105- 115
Ambient Temp.
Note
Where the ambient temperatures are low, the emulsions shall be suitably heated to
facilitate spraying.
The rate of application of binder shall be as specified or as directed and shall
generally range between 0.5 and 1.5 litres per square metre (1.0 and 3.0 gallons I square).
However this rate shall be such that the surface becomes dry with a matt finish within 4
hours when emulsions are used or within 24 hours when cutbacks are used. Emulsions shall
be diluted with water where so directed by the Engineer.
Any prescribed rate of application may be achieved by two or more repeated
applications, when necessary to prevent asphalt flowing off the surface. Also, where surface
conditions necessitate, additional binder shall be applied with the approval of the Engineer.
No base course or surfacing shall be constructed until the prime coat has cured or
set in the opinion of the Engineer.
In areas being treated, precautions shall be taken to prevent the surfaces of structures
and trees being spattered or marred and binder getting into channels, catchpits and drains.
(d) Aftercare
Traffic shall not be permitted on the primed surface for a period of 3 hours or longer
until the binder has penetrated and dried up and in the opinion of the Engineer will not be
picked up by traffic. However, where the Engineer deems it impracticable to detour traffic,
the contractor shall spread a sufficient quantity of blotting material in order to prevent the
prime coat from being picked up, prior to allowing the traffic to pass. Any areas which are
in excess of or deficient in priming material, shall be corrected by the addition of bolotting
material or binder, as appropriate. Such corrections shall be considered as incidental to the
work.
71
(e) Quality Control
Control on the quality of materials and works shall be exercised in accordance with
section 1602.
501.4 Measurement and Payment
(a) Measurement
Method of measurement shall be anyone of the following as specified :
(i) The work shall be measured in litres of binder used in the accepted work. The quantity
of binder measured shall be that required to comply with the specifications and the
requirements of the Engineer or shall be the actual quantity used and accepted,
whichever is the less.
(ii) The surface application shall be measured in square metres of work completed and
accepted. Surface measurements shall be based on the width and length of the surface
area as approved by the engineer.
(b) Payment
Payment will be made at the contract unit rate for the completed work as measured
which shall include full compensation for providing all materials, labour, equipment, tools
and incidentals necessary to complete the work to the specifications.
The Pay items and Pay Uits will be as follows :
Pay item Pay Unit
Either
501 (1) Prime Coat
(state type of binder) Litres
501 (2) Prime coat (state type and rate of
application of binder) Square metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
72
502 TACK COAT
This work shall consist of an application of a tack coat to an existing pavement
prior to construction of a surfacing, so as to provide a bond between the two layers.
502.2 Materials
Binder used shall be medium curing cutback bitumen (10 - 20 percent) or MC 800
or MC 3000 conforming. to the requirements of sub - sectio 1702.2 or bituminous emulsions
of any specified grade conforming to the requirements of sub - sect!o.. 1702.3
502.3 Construction Requirements
(a) Weather Limitations
The provisions of sub sedtion 501.3 (a) shall apply.
(b) Preparation of Surface
Prior to application of the tack coat, the surface shall be dried, thoroughly swept
and rendered clean of clay, dust and any other extraneous material. The tack coat shall be
applied only when the surface is dry, unless otherwise approved by the Bnigneer,
(c) Application of Binder
Where cutback bitumen is used the temperature of application shall be 105 to 130
degrees C (220 to 265 degrees F) and where emulsions are used they shall normally be
applied at ambient temperatures. However, the emulsions shall be warmed to facilitate
uniform application, where necessary. They shall be applied suing a mechanical sprayer,
hand sprayer or by any other means approved by the Engineer.
The rate of application of tack coats shall be as specified, or as directed by the
Engineer and shall generally range between 0.25 and 0.55 litre per square metre (0.50 and
1.10 gallons I square) depending on the surface condition.
In areas being being treated, precautions shall be taken to prevent the surfaces of
structures andtrees being spattered or marred, and th.e binder getting into channels, catchpits
and drains.
The emulsions may be diluted with clean water, if necessary, in order to control the
rate of spread. However, dilution of CRS types are normally not recommended.
73
Tacked surfaces shall be allowed to dry until the proper condition of tackiness is
achieved to receive the surface course. Tack coat shall be applied only so far in advance of
the surface course placement as is necessary to obtain the proper condition of tackiness.
Until the surface course is placed, the contractor shall protect the tack coat from damage.
Normally tack coats shall not be left applied for more than about 6 hours without the
placement of the surface course.
(d) Quality Control
Control on the quality of materials and works shall be exercised in accordance with
section 1602.
502.4 Measurement and Payment
(a) Measurement
Method of measurement shall be anyone of the following as specified>
(i) The work shall be measured in litres of binder used in the accepted work. The quantity
of binder measured shall be that required to comply with the specifications and the
requirements of the Engineer or shall be the actual quantity used and accepted,
whichever is the less.
(ii) The surface application' shall be measured in square metres of work completed and
accepted. Surface measurements shall be based on the width and lenght of th surface
area as approved by the Engineer.
(b) Payment
Payment will be based on the contract unit rate for the completed work as measured
which shall include full compensation for providing all materials, labour, equipment, tools
and incidentals necessary to complete the work to the specifications.
The Pay items and Pay Units will be as follows :
Pay Item Pay Unit
Either
502 (1) Tack coat
(state type of binder) Litres
502 (2) Tack coat (state type of binder and
rate of application) Square metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
74
503 HOT BITUMEN APPLICATIONS
503.1 Description
This work shall consist of the following hot bitumen applications :
(a) First coat on a single sized aggregate base constructed as given in section 403.
(b) Second I subsequent coat on a single sized aggregate base on which a first / second I
subsequent coat had been previously applied. .
The work shall be carried out by applying a coat of hot bitumen and blinding with
sand.
503.2 Materials
Materials used shall meet the requirements of the following :
(a) Binder shall be 80 - 100 penetration grade bitumen to sub section 1702.1.
(b) Blotting (blinding) material shall be coarse sand or gtavel to sub section 1701.4.
503.4 Construction Requirements
(a) Weather Limitations
Provisions of sub section 50 1.3(a) shall apply.
(b) Preparation of Surface
Prior to carrying out hot bitumen application, the surface shall be swept and rendered
clean of clay, dust and any other extraneous materials. These applications shall be applied
only when the surfacre is dry. In the case of second I subsequent coat applications, all
potholes, rats and depression shall be corrected, as per section 1102.
(c) Application of Binder
Prior to application, the binder shall be heated to a temperature not exceeding 175
degreesC (345 degrees F) and shall be applied at a minimum temperature of 160 degrees C
(320 degrees F)
The binder shall be applied by the use of a mechanical sprayer or hand sprayer or by
any other means approved by the Engineer.
The rates of application shall be as specified or as directed and shall normally be
between 1.5 to 2.0 litre per square metre (3.0 to 4.0 gallons I square) and 0.75 to 1.0 litres
per square metre (1.5 to 2.0 gallons I square) for first coat and second I subsequent coat
applications respectively.
75
In the case of the second I subsequent coat applications each application of binder
shall be limited to such an extent of area of road surface that would be possible to be covered
with boltting material before the binder hardens.
(d) ApplicatiQn Qf Blotting Material
The surface on which the binder has been applied shall then be immeditely blinded
with blotting material, using an approved method of spreading, at an approximate rate of 8
cubic metre per 1000 square metres (2.5 cu. ft per 100 sq. ft). If SQ directed.trolling of the
surface with two passes of a pneumatic tyred roller or any other roller shall be carried out,
(e) Rebrushing in the Case of Second I Subsequent CQats
The blotting material which gets whipped off by traffic on to the sides of the road
shall be rebrushed to the road surface, preferably at midday, as many times as would be
required by the Engineer and till such time as the surface bleeding completely disappears.
(f) Quality Control
The control on the quality of works shall be exercised in accordance with section
1602.
503.4 Measurement and Payment
(a) Measurement
The surface application shall be measured in square metres of work completed and
accepted. Surface measurements shall be based on the width and length of the surface area
as approved by the Engineer.
Rebrushing of blotting material shall be measured in square metres. Surface
measurements shall be based on the width and length of the area as approved by the Engineer.
(b) . Payment
Payment will be based on the contract unit rate for each item as measured which
shall include full compensation for providing all materials, labour, equipment, tools and
incidentals necessary tQ complete the work to the specifications.
The Pay Items and Pay Units will be as fQllQWS :
Pay Item Pay unit
503 (1) HQt bitumen application
(state rare of application) Square metres
503 (2) Rebrushing of boltting material C;;quare metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
76
504 SAND SEALING
504.1 Description
This work constitutes the construction of sand seals on existing bituminous pavements
which shall consist of the application of binder followed immediately by covering with coarse
sand and rolling using a pneumatic tyred roller.
504.2 Materials
Materials used shall meet the requirements of the following, unless otherwise directed by
the Engineer :
(a) Binder shall be 80 - 100 penetration bitumen to sub section 1702.1 or bituminous
emulsion CRS - 1 or CRS - 2 to sub section 1702.3 or cutback bitumen (8 -12
percent) or MC 3000 to sub section 1702.2.
(b) The cover material shall be coarse sand to sub section 1701.5.
504.3 Consturction Requirements
(a) Weather Limitations.
Sand seals shall generally be applied in dry weather and when the ambient temperature is
not below 15 degrees C.
(b) Preparation and C l e a n i m ~ of the Surface
The existing pavement surface shall first be corrected as required by suitably
patching potholes, ruts and depressions and eliminating all other surface irregularities, as
required by the Engineer.
Prior to the application of the binder, the surface shall be dried, thoroughly swept
.and rendered clean of clay dust and any other objectionable matter.
(c) Application of Binder
Penetration grade bitumen and cutback bitumen shall be heated to temperatures
between 160 degrees C and 175 degrees C (320 degrees F and 345 degrees F) and 105 degrees
C to 130 degrees C (220 degrees F and 265 degress F) respectively prior to application.
Emulsion, CRS - 1 or CRS - 2 shall be applied at the ambient temperatures. Where necessary
they shall be heated to facilitate spraying. In the use of CRS 2, however, for most ambient
temperatures, such heating will be necessary.
. The binder shall be applied uniformly at the rate specified, which shall very normally
between 0.75 to 1.0 litres I square metres (1.5 to 2.0 gallons I square), depending on the type
of binder used and the condition of the surface.
In the case of penetration grade bitumen or emulsions the application at anyone
time shall be limited to the area that can be covered with blotting material before the bitumen
hardens or the emulsion breaks.
77
(d) Application of Cover Material and Rolling
The surfaces where the binder has been applied shall be immediately covered with
coarse sand using an approved method of spreading at an aproximate rate of 8 cubic metres
I 1000 spuare metre (2.5 cu. ft per 100 squ. ft) and shall be immediately rolled with an
approved pneumatic tyred roller until the sand is firmly embedded in the binder.
(e) Rebrushini
The blotting material which gets whipped off by traffic on to the sides of the road
shall be rebrushed to the road surface preferably at midday, as many times as would be
required by the Engineer and till such time as the surface bleeding completely disappears.
(1) Alts;rcare
Traffic shall normally not be allowedover the newly treated surface area for a period
of at least 6 hours after completion of the work. This shall be particularly so where cutback
bitumen is used. In special circumstances, where the Engineer decides to allow traffic earlier,
the speeds shall be limited to less than 15 kilometres per hour (10 m. p. h.).
(g) Quality Control
Control on the quality of materials and works shall be exercised in accordance with
section 1602.
504.4 Measurement and Payment
(a)
Sand seals shall be measured in square metres of work completed and accepted.
Rebrushing of blotting material shall be measured in square metres and the
measurements shall be based on the widths and lengths of such areas rebrushed as directed.
(b) Payms;nt
Payment will be based on the contract unit rate for the different items which shall
include full compensation for providing all materials, labour, equipment, tools and incidentals
necessary to complete the work to the specifications.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unlt
504 (1) Sand seal (state type and rates of
application of binder) Square metres
504 (2) Rebrushing of blotting material Square metres
Note
Refer sub section 106.6 regarding sub divisons of pay items.
78
505 SEAL COAT TREATEMNTS (SURFACE DRESSINGS)
505.1 Description
The work shall normally consist of construction of Single Bitumen Surface
Treatments (SBST) or Double Bitumen Surface Treatments (DBST) on existing bituminous
surfaces.
Triple seal treatments where required shall also be constructed according to these
specifications, except that the aggregate sizes and rates of spread of aggregate and binder,
in such cases, shall be as given in contract documents or as directed by the Engineer.
The work for each seal of the above mentioned treatments essentially consists of the
aplication of binder followed immediately by spreading of single sized aggregate (precoated
if specified) and compacting with a pneumatic tyred roller or any other roller approved by
the Engineer.
Where these treatments are carried out on newly constructed single sized aggregate
bases, the surface shall first be treated with a first coat bitumen application complying with
section 503. In the case of WBM, DBM and dense graded aggregate bases the surface shall
be first treated with a prime coat complying with section 501. Alternatively in the case of
WBM or DBM aggregate bases, seal coat treatments may be constructed without the aplication
of a prime coat,provided the surface is prepared as given separately in these specifications.
505.2 Materials
The materials used shall conform to the following requirements :
(a) Aggregate to the general requirements of sub section 1701.3 (a) and grading
requirements of Table 1701 - 8 of sub section 1701.3 (b).
(b) The binder for surface aplication shall be penetration bitumen to sub section 1702.1 or
medium curing cutback bitumen (8 - 12) percent) or MC 3000 to sub section 1702.2 or
bituminous emulsions. CRS - 1, CRS - 2 to sub section 1702.3.
(c) The binder for precoating shall be medium curing cutback bitumen (8 - 12 percent) or
MC 800 or MC 3000 to sub section 1702.2 or bituminous emulsion (CMS - 2, CMS
2h, CSS - 1 or CSS - l h) to sub section 1702.3.
505.3 Preparation of Precoated Chips
Precoated chips shall be prepared by mixing single sized aggregate with cutback
bitumen or bituminous emulsion.
79
Where cutbacks are used as binder the aggregate shall be dry and free of dust. The
binder shall be heated to a temperature of 120 - 130 degrees C, before mixing and where
required the aggregate also shall be heated.
Where emulsion are used, the aggregate shall be free of dust and shall be wetted
prior to mixing. Where necessary emulsions shall be suitably warmed before mixing.
The binder content shall be 0.75 to 1.0 percent of the weight of aggregate and shall
be mixed thoroughly with the aggregate in an approved mixing plant or manually in an
approved manner, till all the paritcles are uniformly and thinly coated. The coating shalll
not contain excess binder.
The precoated chips shall be used within 5 dyas of preparation unless otherwise
allowed by the Engineer. Stockpiled materials shall be protected from dust and the elements.
Precoating of aggregate shall normally not be carried out during rainy weather unless
all operations are carried out in a place provided with adequate protection from rain .
.
In areas subject to dusty conditions, precoated aggregate shall not be stockpiled for
any period longer than is necessary. When there is a visible coating of dust on the particles,
the Engineer may direct such portions of the stockpiles to be precoated again.
505.5 Construction Requirements
(a) Weather and Other Limitations
(i) Surface treatment shall not be carried out in wet weather or when rain in imminent.
(ii) Precoated aggregate shall normally not be used when the binder used for seal coat is
a bituminous emulsion.
(b) Preparation of the Surface
(i) Existing pavement surfaces
Existing pavement surfaces shall first be brought to the required profile by suitably
patching depressions and defective areas and eliminating all irregularities.
Prior to the application of the binder, the surface shall be dried, thoroughly swept
and rendered clean of clay, dust and any other objectionable matter. This shall apply to the
second aplication as well as the first.
80
(ii) Newly constructed aggregate base
Where the surface treatment is done on newly constructed base courses, the surfaces
shall be cleaned thoroughly and a prime coat applied as given in section 501. Any binder
application for surface dressing shall not be carried out till such time as the prime coat is
sufficiently dried out as determined by the Engineer.
(iii) Alternative method of seal coating of WBM and DBM surfaces
In this case, the surface shall be brushed by means of power brooms and other
approved methods until the fines infilling the surface interstices of coarse aggregate are
removed to a depth of 12 to 20 mm. The surface shall then be sprinkled with water in order
to wash the dust on the exposed surface of the coarse aggregae and allowed to dry prior to
the application of the binder.
(c) Washing of Aggregate
Where specified or where directed by the Engineer, the aggregate shall be washed
and dried to eliminate the dust to improve bonding.
(d) Construction of SBST
(i) Application of the binder
The binder shall be uniformly applied over the surface with a mechanical sprayer or
hand sprayer or other approved means.
- The rates of appllcatlon of binder and the aggregate shall be as specified in the
contract or approved by the Engineer and shall normally be within the limits given in Table
505 - 1.
The application temperature of binder shall be as given in Table 505 - 2.
81
Table 505 - 1 Quantities of materials for SBST or for DBST - 1 st Method
Rate of Application
Nominal size
of aggregate
inmm
Aggregates Cu. m per 100 .
sq.m, (cu. ft per sq.)
Binder litres I sq. m.
(gallons I square)
19.0
12.5
9.5
6.3
1.3 to 1.7
( 4 ~ 0 to 5.5)
1.0 to 1.3
(3.0 to 4.0)
0.7 to 1.0
(2.25 to 3.0)
0.55 to 0.75
(1.65 to 2.25)
1.0 to 1.25
(2.0 to 2.5)
0.75 to 1.0
(l.5to 2.0)
0.65 to 0.9
(1.3 to 1.8)
0.50 to 0.75
(1.0 to 1.5)
Note
The rates of application of binder given above are that for penetration grade bitumen. In the
case of cutback bitumen and emulsion, corrections have to be made by dividing these rates
by the fraction of bitumen present in these binders.
... ....
Table 505 - 2 Spraying temperatures of binder
Binder Type Temperature
Cutback bitumen 120 - 130 C (250 - 265 C)
Pen. grade bitumen 160 - 175 C (320 - 345 F)
Emulsions Ambient Temperature
Note
Where the ambient temperatures are low emulsions shall be suitably heated to facilitate
spraying. In the USE of CRS - 2 such heating will be necessary in most instances.
82
The area to be sprayed with asphaltic material shall be such that it could be covered
with aggregate at the specified rate and compacted before the binder hardens. Normally the
maximum time duration from the commencement of spraying to completion of the first pass
of the roller shall not exceed 3 minutes. .
Care shall be taken that the application of the binder at the junction of spreads is not
in excess of the aproved amount. Areas of excess binder shall be suitably squeegeed and
areas that are deficient suitably reapplied.
In mechanical spraying, where the full width cannot be sprayed in one operation,
suitable spraying widths, shall be worked out, in order to avoid thin strips.
. In areas being treated, precautions shall be taken to prevent the surfaces of adjoining
structures and trees being spattered and the binder getting into channels, catchpits and drains.
(ii) Application of cover aggregate
Immediattely following the application of the binder, the aggregate of the designated
size, precoated or otherwise, shall be applied using approved spreading equipment at the
rates given in the contract or esbablished by the Engineer, which shall be within the ranges
given in Table 505 - 1. All thinly spread areas shall be covered suitably and where necessary,
the surface shall be broomed to ensure uniform spreading of the aggregate.
Hand spreading of the aggregate shall be done only on small jobs and with the
approval of the Engineer. .
(iii) Rolling
Rolling shall be carried out by using pneumatic tyred rollers approved by the
Engineer. Steel wheeled rollers shall be used only with the special approval of the Engineer.
Rolling shall commence immediately after the spreading of aggregate is complete
and continued until all the aggregate is well embedded in the binder.
(e) Contruction of PBST
A PBST shall be constucted by one of two methods. In the first method, traffic
shall be allowed to run on the first seal for a period of not less than 2 weeks before the
second seal is constructed. However this time lag shall normally not exceed 8 weeks.
83
In the second method, the first and the second seals shall be consturcted without
exposing the first seal to traffic. However, sufficient curing time between the two seals shall
be allowed if a cutback or emulsion is used as a binder. These curing times shal not be less
than one hour for emulsions and three hours for cutback bitumen.
In both these methods each seal shall be constructed exactly as that of SBST as
given in sub section 505.4 (a) to (d) except that the rates of application of aggragate and
binder for the second method shall normally be within the limits as given in Table 505 - 3.
Table 505 - 3 Quantities of materials for OBST - 2nd method
Rate of Application
Nominal size of Aggregates
aggregate
mm mrn
First Second First Second First Second
Seal seal seal seal seal seal
Cu. m per Cu. m per litre litre
100 sq. m 100 sq. m per sq. m per sq. m
(cu. ft per square) (cu. ft per square) (gallon/ square) (gallon/ square)
19.0 12.5 1.3 - 1.7 1.0 - 1.3 0.7 - 0.9 1.05 - 1.35
(4.0 - 5.5) . (3.0 - 4.0) (1.4 - 1.8) (2.1 - 2.7)
19.0 9.5 1.3 - 1.7 0.7 - 1.0 0.65 - 0.85 i.o - 1.3
(4.0 - 5.5) (2.25 - 3.0) (1.3 - 1.7) (2.0 - 2.6)
12.5 9.5 1.0 - 1.3 0.75 - 1.0 0.55 - 0.75 0.85 - 1.15
(3.0 - 4.0) (2.25 - 3.0) (1.1 - 1.5) (1.7-2.3)
12.5 6.3 1.0 - 1.3 0.55 - 0.75 0.5 - 0.7 0.75 - 1.05
(3.0 - 4.0) (1.65 - 2.25) (1.0 - 1.4) (1.5-2.1)
Note
The rates of application of binder given above are that for penetration grade bitumen.
In the case of cutback bitumen and emulsion, corrections have to be made by dividing these
rates by the fraction of bitumen present in these binders.
84
(f) The alternative method Qt.-construction of Seal on WBM and DBM
Base
(i) Single seal or frist seal of doube seal
The construction of single seal or first seal of double seal shall be carried as per sub
section 505.4 (a) to (d) except that the rates of application of aggregate and binder shall be
as given in Table 505 - 4. Thd size of aggregate used shall be 19.0 mm.
Table 505 - 4 Quantities of materials for the first seal of the alternative surfacing of
WBM orDBM
Rate of Application .
Nominal size
of aggregate in
Aggregates
Hot Bitumen
mm
Cu. m per 100 sq. m.
Litre per sq. .rn.
(cu.ft. / square)
(gallons / square)
19.0 1.7 to 1.9 2.0 to 2.5
(5.6 to 6.3) (4.0 to 5.0)
Note
The rates of application of binder given above are that for penetration grade bitumen. In the
case of cutback bitumen and emulsion, corrections have to be made by dividing these rates
by the fraction of bitumen present in these binders.
(g) Second Se'll of Double Sei\l
Unless otherwise specified, the second seal shall be carried out using 12.5 mm
aggregate and as per sub section 505.4 (a) to (d). The second seal shall not be constructed
till traffic is allowed on the first seal for atleast two weeks. Which period, however, shall
.normally not exceed 8 weeks.
(h). Aftercare
Traffic shall not be allowed over the newly treated surfaces till such time as the
aggregate is well embedded in the binder and no whip-off takes place. Normally this period
shall be not less than 12 hours. Where, for special reasons, the Engineer decides to allow
traffic earlier it shall be ensured that their speeds do not exceed 15 km. p. h (10 m. p. h.).
Where practicable, traffic shall be limited to less than 30 km. p. h. (20 m. p. h) during the
first one to two weeks after completion.
In th case of DBST second method traffic shall not be allowed .on the first seal
before the completion of the second seal.
85
505.5 Measurement and Payment
(a) Measurement
Seal.coatshall.be.measured by either of the two following methods as specified :
(i) . First method of measurement
The work shall be measured based on the quantities of the materials used in the
accepted work.
The binder shall be measured in litres and aggregate shall be measured loose in
cubic metres in the truck or as piled.
The quantity of each of the above materials measured shall be that required to comply
with the specification and the requirements of the Engineer or shall. be the actual quantity
used and accepted whichever is the less.
(ii) Second method of measurement
In the alternative, surface treatments shall be measured in square metres of each
type of completed and accepted work., Surface measurements shall be based on the width
and lengh of the surface area as accepted by the Engineer.
(b) Payment
In the first method of measurement given above, the quantities, measured as provided
above, will be paid for at the contract unit price for each of the items listed in the bill of
quantities. The payment shall be full compensation for furnishing the materials, and providing
all labour, equipment, tools and incidentals necessary to complete the work using the material
supplied.
. In the second method of measurement for payment will be based on the contract
unit rate which shall include full compensation fot providing all materials, labour, tools,
equipment and incidentals necessary to complete the work to specifications.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
Method 1
505 (1) Binder for seal coat work (state type) Litres
505 (2) Aggregate for seal coat (state size
and whether precoated) Cubic metres
Method 2
505 (3) Seal coat treatment (state type and other details)
Square metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
86
506 ASPHALTIC CONCRETE SURFACING
506.1 Descriotlon
This work shall consist of the construction of asphaltic concrete surfacings on newly
constructed bases or on existing pavements.
Theasphaltic concrete surfacing shall consistof a binder course and a wearing course
or a wearing course only, as specified.
506.2 Materials
Materials used shal conform to the requirements of the following, unless otherwise
specified :- .
(a) The binder shall be 80 -100 penetration grade bitumen to sub section 1702.1.
(b) The coarse aggregate of nominal maximum sizes 19 mm and 12.5 mm and the fine
aggregate shall conform to the general requirements of sub section 1701.3 (a)
When the coarse and fine aggregate are combined, along with filler where required,
the combined grading requirements shall be as given in sub section 506.3.
(c) Filler, where spearately used in the mix, shall be cement, hydrated lime, crusher fines
or other inert material to section 1706.
506.3 Mix Requirements
(a) Combined Gradini of aiiregate and Binder Content
The grading requirements for the combined aggregate and the binder content shall
be as given in Table 506-1 for the binder course and the wearing courses types 1 & 2.
87
TABLE 5061
Aggregate Grading, binder content and thickness requirements.
Mix Classification No.
Course
Binder Course Wearing Course
Type 1
Wearing Course
Type 2
75 75 45
35 35 25
Total % by weight passing
including filler if used
100 100
88 - 100 90 - 100 100
80 - 100
54 - 80 65 - 93 73 - 93
34 - 56 45 - 73 52 - 69
21 - 38 35 - 58 32 - 50
15 - 33 26 - 48 25 - 43
10 - 26 18 - 38 19 - 35
6 - 20 13 - 26 14 - 27
3 - 13 8 - 20 9 - 18
1 - 7 4 - 12 5 - 10
Percentage binder
content by total
3.5 - 5.5 5.5 - 6.5 5.0-7.0
weight of mix.
Note
The sieve sizes used herein are of ASTM designation. However, equivalent BS sizes as
given in Table 107 - 1 of section 107, may be used with the prior aproval of the Engineer.
(b) Mix Characteristics
The mix characteristics as determined by the Marshall Mix Designs procedure shall
be as given in Table 506 - 2 (a) & 506 - 2 (b) for binder courses and for wearing courses
respectively for low, medium or high traffic depending on whether the cumulative number
of standard axles, for the design life of the surfacing, is less than 10,000, or between 10,000
and 1,000,000 or greater than 1,000,000 respectively. '
In the determination of the above, laboratory samples shall be prepared and tested
as specified in sub section 1802.4 (a).
88
Table 506 - 2 (a) - Binder Courses
No Description Low Traffic Medium Traffic High Traffic
1 Marshall stability in KN Not less than Not less than Not less than
2.25 4.5 6.67
2 Marshall flow
(0.25 mm) 8 th 20 8 to 18 8 to 16.
3 Air voids in mix percent 3 to 7 3 to 7 3 to 7
4 Voids in mineral
aggregate percent Not less than Not less than Not less than
14 14 14
Table 506 - 2 (b) - Wearing Courses
No Description Low Traffic Medium Traffic High Traffic
1 Marshall stability in kN Not less than Not less than Not less than
2.25 3.33 6.67
2 Marshall flow
(0.25 mm) 8 to 20 8 to 18 8 to 16
3 Air voids in mix percent 3 to 5 3 to 5 3 to 5
4 Voids in mineral
aggregate percent Not lesds than Not less than Not less than
14 14 14
506.4 Job Mix Formula
The contractor shall intimate to the Engineer in writing at least two weeks before
the start of the work, the job mix formula proposed to be used by him for the work which
shall give the following details :
(i) A single percentage of aggregate passing each specified test sieve.
(ii) A single percentage of binder content by total weight of total mix.
89
(iii) A single temperature at which the mix is emptied from the mixer.
(iv) A single temperature at which the mix is to be delivered on the road
In additon the contractor shall give the sources, locations of all materials and the
details of the mix design based on requirements given in Table 506 - 2 (a) & 2 (b).
All mixes furnished shall conform to the job mix formula aproved by the Engineer
within the ranges of tolerances given in Table 506 - 3.
Table 506 . 3 . Job Mix Tolerance
Aggregate passing 9.5 mm and larger sieve 6%
Aggregate passing sieve between 9.5 mm and 75 urn 4%
Aggregate passing 75 urn sieve 2%
Binder content percent 03%
Temperature of mixture when emptied from mixer 10 C
Temperature of mixture when delivered on road 10 C
If a change in the materials or source of materials is proposed, a new job mix formula
shall be submitted and approved before the mix containing the new material is delivered to
site.
The mix if not within the specified limits given above shall be rejected;
When unsatisfactory results or changed conditions make it necessary, the contractor,
if required, shall submit a new job mix formula to the Engineer for approvaL
506.5 Construction Requirements
(a) Preparation of Existini Surface
(i) Where asphaltic concrete surfacings are laid over newly constructed aggregate bases,
prior to construction, the surface shall be cleaned of extraneous matter and applied
with a prime coat as per section 501.
90
(ii) Where asphaltic concrete surfacings are laid on existing pavements, the surfaces of
such pavements shall be corrected to the required width and profile as directed. All
potholes, ruts, depressions and damaged edges, shall be corrected as given in sections
1102 & 1103. Areas requiring reshaping and strengthening shall be corrected as per
section 408.
On these corrected surfaces, where required, a tack coat shall be applied as per section
502.
(iii) Where the mix is laid over cement concrete pavements or bridge decks, joints and
cracks shall be cleaned and filled wtthbttuminous material as approved, and any
unevenness of the surface shall be corrected as required. A tack coat as per section 502
shall then be applied to the surface.
(b) Weather Limitations
The bituminous mix shall not be laid during rainy weather or when the surface on
which it is laid is damp or wet.
(c) Limitations Due to Equipment Etc
No work shall be carried out when there is insufficient equipment for hauling,
spreading or finishing or insufficient labour to ensure progress at a rate compatible with the
output of the mixing plant.
(b) Thickness of Compacted Mix
The maximum and minimum thickness of any compacted layer shall be as given in
Table 506 - 1.
(e) M i x i n ~ Plant and the Preparation of Mix
An approved mixing plant of the batch type or of the continuous type shall be used
for the preparation of the mix, which shall have the capacity sufficient to supply the paver
continously.
The mixer shall be capable of accurately batching the aggregates, filler and binder
and mixing same thoroughly so that the mixed material on discharge from the mixer is
uniform in composition and that all aggregate particles are completely coated.
Batch type plants, shall be equipped with suitable means for accurately weighing of
each bin size of aggregate and the filler. The scales of such weighing mechanisms shall be
calibrated at the frequencies as determined by the Engineer using standard weights. The
contractor shall always have at hand sufficient 25 kg weights for such calibration.
In continuous type plants the gate openings of the aggregate shall be calibrated by
an approved process of weighing test samples. The bitumen feed line shall have a by - pass
arrangement in order that the meter could be calibrated. These calibrations shall be carried
out at frequencies determined by the Engineer.
91
The mixing plant shall be capable of heating the aggregate and the binder to the
appropriate temperatures. When wet aggregate is used,' the plant shall have an added capacity
to dry the aggregate before heathing.
The binder and mineral aggregate shall be heated separately to temperatures between
130 & 160 degrees C, and 150 & 175 degrees C respectively. The materials shall be mixed at
temperatures within absolute limits of 145 and 170 degrees C, even allowing for tolerances.
The plant shall, if situated in urban areas or required by the Ministry of Highways /
Environmental Authority be equipped with a dust collector so constructed as to waste or
return uniformly to the elevator all or any part of the material collected.
The mixing plant shall be capable of loading the mix into transport vehicles in such
a manner that segregation does not occur.
In addition the plant shall be provided with the folowing :
(i) Covered or protected ladders or stairways with secure hand rails in adequate number
which shall be placed at all points required for accessibility to all plant operations.
(ii) Covering devices for pulleys, belts and drive mechanisms and other moving parts.
(iii) Ample and unobstructed space on the maixing platform.
(iv) A clear and unobstructed passage at all times in and around tha tipper loading space
which shall be kept free from drippings from the the mixing platform.
(v) Insulated flexible pipe connections to carry hot bitumen.
(f) . Transport of Mix
The mix shall be transported from the mixing plant to the point of use in suitable
tipping trucks.
The trucks shall be in good mechanical condition at all times. They shall have clean
and smooth metal beds, that have been sprayed with soapy water or lime solution or any
other detergent solution approved by the Engineer, to prevent the mix from adhering to the
beds. The amount of sprayed fluid shall however be kept to a practical minimum. All
precautions shall be taken to avoid segregation of mixed materials and to ensure that they
do not be come contaminated with dust or foreing matter.
9'
Any truck causing excessive segregation of bituminous material by its spring
suspension or other contributing factors, or that shows oil leaks in detrimental amounts or
that causes undue delays, shall upon direction of the Engineer be removed from th works
until such conditions are corrected.
When directed by the Engineer, each load shall be covered with a properly fastened
canvas or other suitable material of such size as to protect the mix from the weather. In
order that the mix shall be delivered to the site within the specified temperature range,
during cold weather or during long hauls, a properly fastend insulating cover shall be used
when necessary. .
Loading and transporting shall be coordinated such that spreading, compacting and ...
finishing shall be completed during daylight hours unless adequate illumination,as approved
by the Engineer, is provided by the Contractor.
The mix shall be delivered at the site at a temperature within the absolute minimum
limit of 115 degree C.
(g) Laying Plant and Laying of the Mix
The mix shall be laid immediately after transporting, by means of approved
mechanical self powered pavers. They shall be capable of spreading,finishing and providing
initial compaction to the mix so that, the surfacing can be finished to the required lines,
grades, levels, dimensions and cross sections intended, either over the entire width or over
such other partial widths as may be practicable.
The pavers shall be equipped with recieiving hoppers and spreading screws of the
reversing type to place the mix evenly in front of adjustable steering devices and shall have
reverse as well as forward travelling speeds. They shall also be furnished with vibrating
screed (levelling) unit equipped with suitable burners or heaters and tamping bars or vibration
attachments.
The pavers shall be able to confine the edges of the pavement to true lines without
the use of stationary side forms. The equipment shall include blending or joint levelling
devices for smoothening and adjusting longitudinal joints between lanes. The assembly shall
be adjustable to give the cross sectional shape prescribed and shall be as designed and
operated as to place the required thickness and weight per square metres of material.
A fully trained and experienced operator shall be in direct charge of the paver at all
times. The pavers shall be operated so as to avoid dragging of the material.
The bituminous mix, after spreading, finishing andintial compaction by the paver,
shall have a smooth surface free of irriegularities caused by dragging, tearing or gouging.
93
L
During constuction, if it is seen that the paver in operation leaves on the surfacing
tracks or indented areas or other objectionable irregularities or segregation of mix, that
cannot be satisfactorily corrected by normal operations, the use of such a paver shall be
discontinued forthwith and another satisfactory paver shall be provided by the contractor.
In narrow widths and in restricted areas where the plant cannot operate, the mix
may be manually laid, in which case, care shall be taken to avoid segregation. Manually laid
strips shall be rolled at the same time as the paver laid work and allowance shall be made for
extra compaction of these strips. Any defects in the laid surface shall immediately be rectified
before rolling commences and there shall be no unnnecessary scattering back by hand of
material on paver laid work.
(h) Compaction Procedure
Immediately after the mix has been spread and struck off, the surface shall be checked
and any irregularities adjusted. Rolling shall commence as soon as the material will support
the roller without undue displacement or cracking. The mix shall then be thoroughly and
uniformly compacted by rolling, according to the sequence of rolling as given below :
(i) Transverse joints
(ii) Longitudinal joints, where applicable
(iii) Outside edge
(iv) Initial or breadkdown rolling
(v) Second or intermediate rolling
(vi) Finish or final rolling
Normally the first rolling of all joints and edges and the initial or breakdown rolling,
shall all be done with static weight (Tandem or three. wheel) or vibratory steel wheeled
tandem rollers and the second or intermediate rolling with pneumatic tyred rollers. Use of
any other rollers for the above purposes shall be with the prior approval of the Engineer.
During initial or breakdown rolling, the direction of travel of the roller shall be such that
the powered or driving wheel passes over the uncompacted mix first, before the driven wheel.
The second intermediate rolling shall follow the intial or breakdown rolling as close as
possible while the bituminous mix is still plastic and at a temperature that will result in
maximum density. The final rolling shall be accomplished with static weight tandems or
vibratory tandems (without vibration) while the material is still warm enough for removal
of roller marks.
In general the type of roller or roller combination to be used shall be nominated by
the contractor for the approval of the Engineer prior to the commencement of work and the
rollers shall satisfy the requirements given in 506.5 U).
The speed of the rollers shall not exceed the limits given in Table 506-4 and shall be
at all times be slow enough to avoid displacement of the hot mix.
94
TABLE 506-4
Speed in. km/hr
,'t:
Type of roller Breakdown Intermediate Finish
Steel Wheeled Rollers 3
's' 5
Pneumatic Tyred Rollers 5 5 8
Vibratory Rollers 5 5
During stages of intial, intermediate and final rolling, rolling shall commence at the
low side of the spread and progress towards the higher side parallel to the centre line of the
pavement.
When the roller has passed over the whole area once, any high spots or depressions
which become apparent shall be corrected by either removing or by adding fresh material.
The rolling shall be continued till the entire surface has been compacted edequately and the
roller marks have been eliminated. Each pass of the roller shall uniformly overlap not less
than one half of the preceeding pass. Tha roller wheels shall be kept damp if required to
avoid the material sticking to the wheels and being picked up. However, the quantity of
water used for this purpose shall be the minimum required.
When using a vibratory roller for the compaction of a surfacing the vibration shall
be turned off before the roller stops when reversing direction, and turned on after it starts in
the new direction.
Vibratory rollers shall not be used for surfacings of thickness less than 50 mm, unless
otherwise approved by the Engineer.
The breakdown and the intermediate rolling shall be carried out at temperatures not
less than 105 degrees C and 135 degree C respectively.
The final rolling shall be compaleted before the temperature of the mix falls below
85 degrees C.
Rollers shall not be allowed to stand on newly laid material until 6 hours has elapsed
after completion of the compaction of the . ""
When the bituminous mix is spread in areas that are inaccessible to rollers such as
places near kerbs and manholes etc., compaction shall be obtained by hand tampers,
mechanical tampers, or small vibrating plate compactors.
95
The density of all samples taken from the compacted surface course shall not be
less than 98% of the Marshall Density at the point appropriate to the locations. The sample
densities shall be determined as given in sub section 1802.4(c).
U) Requirements of Compacting Equipment
(i) General
Generally, with eacn po.. Y., U .ninimum of 3 rollers shall be provided by the
contractor. On small projects involving a total of less than 5000 tonnes of material the
minimum requirement shall be one tandem roller.
All rollers shall be self propelled, capable of being reversed without backlash and ..
equipped with power steering, dual controls allowing operation from eigher the right or left
side. They shall have water tanks with sprinkler systems to ensure even wetting of rolls or
tyres.
The rolling surface of the wheels of a steel wheel roller shall be checked for wear. If
grooves or pits have worn itno the rolling surface, the roller shall not be used on the job.
Each roller shall have a calibration chart showing the relationship between depth of
ballast and weight and giving the tare weight of the roller. Each roller shall be in a good
condition and shall be operated by a competent and experienced driver.
(ii) Steel Wheeled Rollers
Steel wheeled rollers (tandem or three wheel) shall weigh not less than 8 metric
tonnes. The minimum rolling pressure of the rear wheels of each three wheeled roller or at
least one roll or each tandem roller shall be 35 KN/m of roller width.
(iii) Pneumatic Iyred Rollers
Pneumatic tyred rollers shall have not less than seven wheels (3 wheels on the front
axle and four on the rear) fitted with smooth tread comapctor tyres, of equal size and
constrction, capable of operating at inflated pressures upto 850 KN/ square metre. The wheels
shall be able to move up and down independently of one another. Wheels shall be equaly
spaced along both axle lines and arranged so that tyres on one axle line tract falls midway
between those on the other with an overlap. The tyres shall be kept inflated to specified
operating pressures with variation not exceeding 36 KN / square metre. Means shall be
provided for checking and adjusting the tyre pressuress on the job at all times. for each size
and type of tyre used, each roller shall have charts or tabulations showing the relationship
between wheel load, inflation pressure and tyre contact pressure, width and area. Each roller
shall be equipped with means of adjusting its total weight by ballasting so that the load per
wheel can be varied from 1,500 to 2,500 kilograms. In operation the tyre inflation pressure
and the wheel load shall be adjusted, as required by the Engineer, to meet the requirements
of each particular application. In general the compaction of any course with a pneumatic
tyred roller shall be accomplished with contact pressures as high as the material will support.
96
(iv) Vibratory Rollers
Generally vibratory rollers shall be equipped with automatic vibration control which
cuts out the vibratory system before the machine comes to a halt.
The minimum operating weight of the roller shall be 6 tonnes and. minimum drum
width 0.9m, the minimum linear drum applied force 44 KN I m and the minimum frequency
of vibration 33 Hz (2000 cycles I min).
(k) Joints
Both longitudinal and transverse joints in successive courses shall be staggered so
as not to be one above the other. As far as precticable, longitudinal joints shall be arranged
so that the joints in the top course shall be at the location of the line dividing the traffic
lanes, and the transverse joints shall be staggered at a minimum of 250 mm and be straight.
Longitudinal and transverse joints shall be made in a careful manner so that well
bonded and sealed joints are provided for the full depth of the course No mixture shall be
placed against previously rolled material unless the edge is trimmed to line and applied with
a very thin coating of binder just before additional mix is placed against the previously
rolled material.
Spreading shall be as nearly contiunous as possible and rollers shall pass over the
unprotected end of freshly laid mix only when authorised by the Engineer. In all such cases
provisiion shall be made for a properly bonded and sealed joint with the new surface for the
full depth of the courses as specified above. Before placing mix against them, all contact
surfaces of kerbs, gutters, manholes, etc., shal be given a thin uniform coating of hot bitumen
and the joints between these structures and the surface mix shall be effectively sealed by the
subsequent spreading, finishing and compaction operations.
(1) Mixcellaneous Requirements
,
The contractor shall provide suitable means for keeping all small tools clean and
free from accumulations of bituminous material. He shall provide and have ready for use at
all times enough tarpaulins or covers, as may be directed by the Engineer, for use in any
emergency such as rain, chilling wind, or unaviodable delay, for the purpose of covering or
protecting any material that may have been dumped and not spread.
97
(m) Aftercare
Sections of the newly finished work shall be protected from traffic of any kind until
the mix has sufficiently hardened. Also traffic shall normally, not be permitted over newly
laid surfaces at least for six hours after laying.
In the event any binder course is consturcted inti ally the surface so formed shall be
maintained in its finished condition until the surface course is placed thereon, and any damage
caused shall be made good by the contractor. If the damage could be attributed to the
negligence of the contractor is it shall be corrected at his own expense.
(n) Surface Finish and Quality control
The Asphalitc Concrete Surfcings shall be finished to the requirements given in
secti on 1601.
The control on the quality of materials and works shall be exercised in accordance
with section 1602.
506.6 Measurement and Pwayment
(a)
Asphaltic concrete surfacings shall be measured by anyone of the following methods
specified in the contract. .
(i) In tonnes; weighed using a weigh bridge
The asphaltic concrete measured shall be the number of tonnes in the accepted
pavement. The method of measurement shall be as follows.
The asphaltic concrete shall be weighed after mixing using an approved weigh bridge.
The total quantity of asphaltic concrete mixed and laid shall be computed daily from load
dilivery tickets. This weight shall be adjusted by deducting the weight of mix wasted at
joints, the weight of mix laid in areas outside the defined pavement edge and the weight of
mix laid within the defined pavement but not accepted by the Engineer. The total weight so
deducted shall be as assessed by the Engineer.
The weight of asphaltic concrete measured for payment each day shall be the weight
adjusted as above subject to the condition that it shall not exceed by more than 5% tbe
weight required for the area laid and accepted for the day, based on the specified thickness
for the layer given in drawings or as directed by the Engineer and the mean value of compacted
density of the mix. The compacted density of the mix shall be assessed by means of core
samples. The frequency of taking cores shall not be less than one per 500 square metres for
the area laid and accepted each day.
98
(ii) In cubic metres as compacted in position, measured by cutting cores.
Measurements shall be based on the authorised and accepted area laid and the mean
value of thickness of cores cut in the accepted area. the quantities shall be calcutated for
work done on a daily basis. The quantity measured for payment each day shall not exceed
by more than 5% the volume required for the accepted area laid for the day, based on the
thickness of the layer given in drawings or as directed by the Engineer.
The frequency of taking cores for thickness measurements shall not be less than one
per 500 square metres for the area laid and accepted each day. The thickness of each core
shall be caluclated by dividing the volume of the core by the mean area of cross section. The
volume shall be determined by weighing in air and in water (water displacement method).
The mean area of cross section of the core shall be calculated using the mean diameter. The
mean diameter shall be the average of four readings taken, two each at right angles to each
other at two circles near the top and bottom of the core. The dimeters shall be measured
using callipers.
(iii) In cubic metres, as compacted in position measured by taking levels
Method of measurement shall be as given in sub section 106.2.
(iv) In cubic metres measured as loose volume
The asphaltic concrete shall be measured in the hauling truck. This method is
essentially for small works including small scale regulating courses.
The volume of asphaltic concrete shall be measured in the hauling vehicle after
levelling in the loose state, at the point of delivery. The vloume of asphaltic concrete measured
as above shall be suitably adjusted for material wasted at the joints, for the material laid
outside the defined pavement edges, for excess thicknesses laid and for material laid within
the defined pavement edge but not accepted by the Engineer.
(b) Payment
Payment for asphalitc concrete surfacing will be made at the contract unit price for
the item as measured above. The price shall be full compensation for furnishing all materials,
for mixing and placing of the mixed material and for providing all plant, machinery,
equipment, tools, labour and incidentals necessary to complete the work to these
specifications.
!
99
The Pay Items and Pay Units will be as follows :
Pay Unit
Pay item
Either
Tonnes
Asphaltic concrete surfacing
506 (1)
Asphaltic concrete surfacing. compacted
506 (2)
Cubic metres
in postition"(measured bycutting cores) .
Asphaltic concrete surfacing. compacted
506 (3)
Cubic metres
in position (measured by taking levels)
Asphaltic concrete surfacing.
506 (4)
Cubic metres
(measured in loose state in hauling vehicle)
Note
Refer sub section 106.6 regarding sub divisions of pay items.
100
507 COLD MIX SURFACINGS
507.1 Description
This work shall consist of construction of cold mix surfacings, on existing pavements
or on bridge decks.
These mixes shall either be dense graded or open graded. However, the open graded
mixes are normally not recommended for use on bridge decks.
507.2 Materials
All materials shall meet the requirements of the following, unless otherwise
specified:
(a) The binder shall be medium curing cutback bitumen (10 to 20 percent) or Me 800 or
MC 3000 to sub section 1702.2, or bituminous emulsions (CMS - 2, CMS - 2 h,CSS
- 1, or CSS - 1 h) to sub section 1702.3.
(b) The coaresaggregate of nominal maximum sizes 19 mm and 12.5 mm and the fine
aggregate shall conform to the general requirements of subsection 1701.3 (a) and
when combined they shall conform to the mix requirements of sub section 507.3.
(c) The fine aggregate shall be crusher fines or sand to sub section 1701.3.
507.3 Preparation of Cold Mix
(a) Proportioning of Aggregate and Binder
In preparing cold mix, aggregate and binder shall normally be proportioned by
weight.
On small jobs, however, with the approval of the Engineer, proportinoning may be
carried out on a volume basis.
. For wieight proportioning the combined aggregate gradings and the binder contents
given in Table 507 - 1 shall be used.
Volume batching shall be carried out on the basis of the approximate aggregatte
ratio's given in tabl4 507 - 2 and the proportioning of aggregates and binder as given in
Table 507 - 3.
101
Table 507 - 1 -Aggregate gradings and the binder contents
Grading Type Dense graded Open graded
Nominal max.
Size of agg. 19.0 mm 12.5 mm 19.0 mm 12.5 mm
Sieve Size Total percentage passing by weight
mm urn
25
19
12.5
9.5
4.75
2.36
300
75
100
90 - 100
56 - 80
35 - 65
23 - 49
5 - 20
0-5
100
90 - 100
44 - 74
28 - 56
5 - 22
0-8
100
90 - 100
60 - 80
18 - 35
0-3
100
85 - 100
35 - 50
15 - 30
0-3
Binder content
as % ofwt. of
aggregate
(a) cutback bitumen
(b) Emulsion
4.5 - 5.5
5.0 - 6.0
5.0 - 6.0
5.5 - 6.5
4.5 - 5.0
4.5 - 5.5
4.5 - 5.5
5.0 - 6.0
Table 507 - 2 - Volume rations for aggregate
Nominal maximum
Volume ratios; coarse: fine
size of aggregate
Dense graded Open graded
19 mm (3/4") 3 :2 4 :1
12.5 mm (1.2") 2:1 4:1
102
Table 507 - 3 volume proportioning of aggregates and binder
Nominal max:
Coarse agg. in
unit volumes
Fine aggin
unit
Cutback
in litres
Emulsions
in litres
volumes (gallons)
(gallons)
(a) Dense I:raded
19 mm (3/4") 21.8 - 23.6 22.7 - 24.5
6 4 (4.8 - 5.2) (5.0 - 5.4)
12.5 mm (112") 21.1 - 22.9 21.8 - 23.6
6 3 (4.6 - 5.0) . .(4.8 - 5.2)
(b) Open iraded
19 mm (3/4") 17.3 - 19.1 19.5 - 21.3
8 2 (3.8 - 4.2) (4.3 - 4.7)
12.5 mm (1/2 ") 19.5 - 21.3 21.1 - 22.9
8 2 (4.3 - 4.7) (4.6 - 5.0)
Note
A unit volume e I cu. ft. (0.028 cu.m). In measuring, unit volume boxes shall be made use
of.
(b) Preparation of the Mix usinl: Cutback in Bitumen
The coarse and fine aggregate shall be proportioned as specified, thoroughly mixed,
dried and heated to a temperature within the range of 105 to 130 degree C (220 degreeF to
265 degree F) in a suitable mixer or on heated metal plates or by any other appropriate
means as approved.
Cutback bitumen shall also be heated to a temperature within the same range and
mixed with the heated aggregate in a mixing plant or manually, till all the prticles are fully
coated.
(c) Preparation of the Mix usini Bituminous Emulsion
Bituminous emulsion of the medium and slow setting types shall be used for open
graded mixes, while for dense graded mixes, only the slow setting types shall be used.
Firstly, the coarse and fine aggregates shall be proportioned and mixed in a
mechanically operated mixer or by manual means as approved by the Engineer. Where the
mixer is used the period of mixing shall be 1 to 2 minutes. The aggregate shall not be
excessively wet nor shall be too dry at the time of mixing. Where it is too dry adequate
quantity of water shall be added to the aggregate before mixing. The specified quantity of
emulsion shall then be added and mixed in the mixer or manually with the aggregate, for a
period of 1/2 to 1 1/2 minutes. Over mixing shall be avoided. In machine mixing, the mixed
material shall be immediately discharged into vehicles or wheel barrows as appropriate for
purposes of transport.
103
i
I
L _
507.4 Transporting for Use Of Stockpiling of Mix
The mix shall then be transported to the point of use or stockpiles as required. The
vehicle employed for transport shall be clean and where required, the material shall be covered
in transit.
The material which is stockpiled for later use shall be protected froin the elements.
The mix shall be used within 7 days of preparation, unless otherwise allowed by the Engineer.
507.5 Construction Requirements
(a) Thickness of surfacings
The thicknesses of surfacings shall be as specified or as directed and shall normally
be within the limits of 20 - 30 mm for 12.5 mm a g g r . e ~ a t e and 30 - 45 mm for 19 mm
aggregate.
(b) Weather and Other Limitations
Cold mix surfacings shall not be laid during rainy weather or when the base is damp
or wet or when the atmospheric temperature is below 15 degrees C
(c) Preparation of Base
The base on which the bituminous surfacings are to be laid shall first be corrected,
as required, by suitably patching potholes, ruts, depressions and eliminating all other surface
irregularities.
(d) Application of a Prime Coat or Tack Coat
A prime coat complying with section 501 shall be applied over newly constructed
aggregate bases, or a tack coat complying with section 502 shall be applied over existing
bituminous surfacings, prior to laying of cold mix surfacings. Application of tack coat shall,
however, not be necessary when laying of a cold mix surfacing follows soon after the
construction of a bituminous base or levelling course. Also a tack coat shall not be necessary
where a second layer of cold mix is laid soon after the first.
(e) spreading and Rolling
The premixed material shall be spread, to the required thicknesses and levels either
manually using rakes and other suitable implements, or by using a paver, where appropriate.
. ;\
104
When using the cold mix shall prepared with cutback bitumen, the mix shall be
aerated by suitably spreading and exposing so as to reduce the volatile content.in the binder
prior to compaction. .
When using the cold mix prepared with emulsion, it is preferable to commence rolling
immediately before, or at the same time as the emulsion starts to break.
When sufficient length of the material has been laid, compaction shall be carried
out by using a 6 - 8 tonne smooth wheel tandem roller, or any other approved roller. The
method or rolling shall be carried out as described in sub section 403.3 (c)(iv).
As far as practicable, the mix shall be rolled in the following order, as described in
sub section 506.5 U).
(1) Transverse joints
(2) Longitudinal joints where applicable
(3) Outside edge
(4) Breakdownrolling
(5) Finish or final rolling
When the roller has passed over the whole area once, any high spots or depressions
shall be corrected by removing or adding premixed material. Rolling shall them be continued
until the entire surface has been compacted and all the roller marks are eliminated. 'The
wheels shall be kept damp to prevent the premix from adhering to the wheels and being
pickedup.
. . : ' .', ': ",'
'Rollers shall not be allowed to stand on newly laid surfacings.
(f) Joints
Joints shall be constructed in accordance with sub section 506.5 (k).
(g) Construction of a Seconq,Course
. '. ,.::, : . . , :--, -:'. '/ ':'.
Where cold mix prepared with cutback bitumen is used, the construction of a second
course if required, shall not be carried out for a period of at least 1. week, after the completion
of the first course, and till the first layer is completely cured and the solvent (kerosine) has
evaporated. Where cold mix prepared with emulsion is used, the time lag shall not be less
than 4 hours.
(h) Finishing Operations and Quality Control
..' .'" .
The cold mix surfacings shall be finished to the requirements of section 1601.
The control on the quality of materials and works shall be in accordance with section
. " /...'1 . . '.
1602.
lOS
.. U) . Aftercare
Traffic shall not be permitted to run on any newly laid areas until a period of 12
hours has elapsed after the completion of the construction of surfacing, unless otherwise
directed.
507. 5 Measurement and Payment
(a) Measurement
Cold mix surfacings shall be measured by one of the following methods specified in
the contract.
(i) In cubic metres, as compacted in position measured by taking levels
Method of measurement shall be as given in sub section 106.2.
(ii) In cubic metres measured as loose volume
The cold mix surfacing shall be measured as piled or in the hauling vehicle. This
method is essentially for small works including small scale regulatiing courses.
The volume of cold mix measured as above shall be adjusted for material wasted at
the joints, for material laid out side the defined pavement edges, for excess thicknesses laid
and for material laid within the defined pavement edge but not accepted by the Engineer.
(b) Payment
Payment for cold mix surfacings will be made at the contract unit price for the item
as measured above. The price shall be full compensation for furnishing all materials, for
mixing and placing of the mixed material and for providing all plant, machinery, equipment,
tools, labour and incidentals necessary to complete the work to these specifications.
Pay Items and Pay Units will be as follows :-,
Pay Item Pay Unlt '
Either
507 (1) Cold mix surfacings, compacted in position Cubic metres
507 (2) Cold mix surfacings, in loose state Cubic metres
106
600 UNPAVED ROADS
601 Gl'aveUing of Earth Roads and Regravellmg of Gravel )loads"
: ,: ..
'. ",..f ('.
601.1 Description
"
This work shall consist of the gravelling of earth roads or regravelling of gravel
roads. The gravelly soil used may be as dug soils or material obtained bya process of blending
soils referred to as mechanical stabilization.
601.2 Materials
I' ..
(a) The material be gravelly soil or such material obtained by 'blending two or
more soils and meeting the requirements of sub section 1708.5.
601.2 Mechanical Stabilization (Blending)
Where blending two or more soils is required, the method of mechanical stabilization
as given is sub section 401.3 shall be adopted, and the mixed material shall be checked for
grading by carriying out sieve analysis tests in accordance with sub section 1804.1.
consturction Requirements
(a) Minimum Thickness of or
The minimum thickness of gravelling or regravelling shall be 75 mm (3"), unless
otherwise specified.
(b) Preparation of surface
Unless otherwise spefified in the contract or directed by the Engineer, the following
shall be carried out prior to gravelling or regravelling.
The earth or gravel road to be gravelled or regravelled, shall be cleared of all
extraneous matter and the surface irregularities such as potholes; ruts and depressions
corrected as required. Places of failure shall be examined for the cause of failure and corrected
suitably either by excavating and filling or by filling over as appropriate. Any loose material
requiring removal shall be removed as directed. Where specified or directed the surface
shall be graded and recambered, scarified. The surface shall be moistened before the
placement of new gravelly soil."
and Compaction of Grayel
The gravel or blended soil shall be spread over the prepared earth road, or gravel road to a
uniform thickness which will give the required thickness when compacted.
107
l _
i
. .
The gravel shall be compacted, by using a 8 - 10 tonne steel wheeled roller or any
other roller approved by the Engineer, at or near the optimum moisture content. The moisture
content of the material shall be checked just before compaction at the frequrencies given in
Table 1602 - 1 or as directed by the Engineer. If the material is too wet it shall be dried by
aeration and if it is too dry water shall be sprinkled and mixed uniformly prior to compaction.
Rolling shall commence at the edges and proceed towards the centre, except at super elevated
sections of the road where the rolling shall commence at the lower edge and proceed towards
the higher edge. The rolled surface shall be checked transversely and longitudinally with
straight edges and camber boards and any irregularities corrected by loosening the surface,
adding or removing necessary amount of gravel, and recompacting the same until the entire
surface conforms to desired camber and grade. The gravel shall be compacted to at least 100
percent of the maximum standard dry density of the materials as determined by the standard
compaction tests carried out in accordance with section 1804.
(d) Surface Finish and Quality Control
The surface shall be finished to the tolerances given in section 1601.
The control on the quality of materials and works shall be exercised in accordance
with section 1602.
601.5 Measurement and Payment
(a) Measurement
Method of measurement shall be anyone of the following as specified :
(i) Gravelling or regravelling shall be measured as finished and accepted work in position
in cubic metres. Volume' measurements shall be based on the cross section shown on
the drawings or as directed by the Engineer and the actual length measured parallel to
the grade line of the road.
(ii) Gravelling or regravelling material shall be measured as supplied and piled in cubic
metres but limited to the volume used in the accepted work and the construction of
gravelling or regravelling work shall be measured on the volume of material used in
cubic metres (as piled) in the accepted work.
(b) Payment
Payment will be based on the contract unit price/s for the item/s and shall include
full compensation for the components given below for the item/so
The price for gravelling or regravelling shall be measured as finished work in position
shall include full compensation for providing all materials, transport, labour, tools, equipment
and incidentals necessary to complete the work to the specifications.
108
The price for gravelling or regravelling materialls supplied and piled shall include
full compensation for the supply, transport and piling of the materialls at site.
The price for the construction of gravelling or regravelling shall include fuJI
compensation for providing all labour, tools, equipment and incidentals necessary to carry
out the construction work to the specifications;
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
Either
601 (1) Gravelling or regravelling
compacted in position Cubic metres
or the followini :
601 (2) Gravelly soil, as piled Cubic metres
601 (3) Gravelling or regravelling construction Cubic metres
109
602 PRIMING OF GRAVEL ROADS
602.1 .' Description
This work shall consist of priming a prepared gravel road using a cutback bitumen.
, The work shall include moistening the surface, applying the cuback bitumen, blinding
with coarse sand andcompacting.
602.2 Materials
The material used shall meet the requirements of the following, unless otherwise
specified :
(a) The binder shall be a medium curing cutback bitumen (20 ~ 45 percent) or MC 30 or
MC 70 or MC 250 or MC 800 to sub section 1702.2.
(b) The blotting (blinding) material shall be coarse sand or gravel to sub section 1701.4.
602.3 Construction Requirements
(a) Preparation of x i s t i n ~ Surface
Prior to the application of the surfacing, the prepared gravel road shall be cleaned
of extraneous matter and dust.
(b) Weather Limitations
The cutback bitumen surfacing shall not be carried out in wet weather nor when rain
is imminent.
(c) Application of Binder
The prepared road shall be wetted uniformaly to obtain a lightly soaked snrface.
The cutback bitumen shall be heated to temperatures given in Table 501 - 1 and
shall be applied at a rate of 1.5 to 2.0 litres per square metre (3 to 4 gallons I squares) on the
prepared surface of the gravel base as uniformly as possible using hand sprayers, mechanical
sprayers or any other means approved by the Engineer.
The binder coat shall not be squeegeed and shall be allowed to stand for a period of
not less than 15 minutes. It shall then be blinded with coarse sand at the rate of about 16
cubic metre per 1000 metre square (5 cu. ft per 100 sq. ft), and rolled with a suitable smooth
wheeled roller.
(d) Aftercare
Traffic shall normally not be allowed over the newly treated surface for a period of
6 hours after the completion of the work. Where the Engineer decides to allow traffic earlier,
the speeds shall be limited to less than 15 kilometres per hour (10 m.p.h.).
110
(e) Quality Control
The control on the quality of materials and works shall be exercised in accordance
with section 1602.
602.4 Measurement and Payment
(a) Measurement
Priming of gravel roads shall be measured by either one of the two following methods,
as specified :
(i) First method of measurement
Priming of gravel roads shall be measured in square metres of each typeof completed
and accepted work. Surface measurements shall be based on the width and length of the
surface area as approved by the Engineer.
(ii) Second method of measurement
The work shall be measured based on the quantities of the materials used in the
accepted work.
The binder shall be meausred in litres and the aggregate shall be measured in cubic
metres as measured loose in the truck or as piled.
The quantity of each of the above materials measured shall be the quantity required
to comply with the specification and the requirements of the Engineer of shall be the actual
quantity used as accepted whichever is the less.
(b) Payment
In the first method of measurement given above, payment will be based on the
contract unit rate for the item which shall include full compensation for providing all labour,
tools, equipment and incidentals necessary to complete the work to the specifications.
In the second method of measurement given above, the quantities, meausred as
provided above, will be paid for at the contract unit price for each of the items which shall
include full compensation for furnishing and carrying out the work utilizing all materials,
including all labour, equipment, tools and incidentals necessary to complete the work.
111
The Pay Items and pay Units will be as follows :
Pay Item Pay Unit
Either
602 (1) Cutback bitumen surfacing (state type of
binder and rates of application of binder and sand) Square metres
or the following :
602 (2) Binder (state grade of binder) Litres
602 (3) Sand Cubic metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
. ',',
112
603 "MAINTENACE OF EARTH AND GRAVEL ROADS
603.1 Description
I"
This work shall consist of the following maintenance operations' on earth and gravel
roads.
(a) Repairing potholes, ruts, depressions and erosion gullies, and also dragging where
necessary, as recurrent maintenace activities.
(b) Grading and correcting the surface profile on a periodic basis.
603.2 Materials
Suitable soil for repair of earth roads shall be type II embankment material meeting
the requirements of sub section 1708.1. Gravelly soil for repair on gravel roads shall meet
the requirements of sub section 1708.S.
603.3 Work Requirements
(a) Recurrent Maintenance
All potholes, ruts, depressions and erosion gullies shall be repaired by using approved
suitable soil or approved gravelly soil as appropriate. '
Scch damaged places as above shall first be dressed as necessary, using mammoties,
pack axes and other implements and then sprinkled with water till uniformly wet. ,
The soil in a moist state (close to optimum moisture content) shall then be spread
sufficiently proud of the surface and compacted using tampers or rollers as appropriate and'
finished flush with the surface. Places of excessive depth shall be compacted in layers where
practicable.
Dragging shall be carried out, where necessary, to arrest the formation of corrugations
and to smoothen the surface, using suitable drags attached to tractors' or' by other suitable
means.
. l" '
(b) Periodic Maintenance
Where the road surface requires restoration of profile and removal of corrugations
in addition to other irregularities the surface shal be graded as required. '
Grading of the road surface shall be done using the Motor Grader or other approved
means, to move material and correct the surface as required. Where necessary, areas of
hardened soil may be ripped prior to grading using the grader tynes or other suitable means.
The material that had accumulated on the side shall also be graded to the centre as suitable.
I 113
I
L
..
These operations shall normally be carried out during suitable periods of the wet
season when it is easy to grade the surface.
After grading and correcting the surface to required profiles the loosened soil shall
be compacted with about 6 to 8 passes of a 8 - 10 tonne steel wheeled roller. The surfaces
shall be moistened as necessary before compaction.
603.4 MEASUREMENT AND PAYMENT
(a)
Unless otherwise specified work carried out shall be measured as follows:
(i) repair of potholes, ruts, depressions and erosion gullies, shall be measured in square
metres of surface correction. Soil used for such correction shall be measured in cubic
metres.
(b) Payment
Unit rate of payment for each item of work done shall include full compensation for
plant, equipment, tools, labour and other incidentals necessary to complete the work.
Payment for soils used for repair work shall be separate unless otherwise specified.
The Pay items and Pay Units will be as follows ;
Pay item Pay Unit
603 (1) Soil for repair work (sate type) Cubic metres
602 (2) Repair of potholes, ruts etc using
material supplied Cubic metres
603 (3) Dragging of surface Metres / km of roadway
603 (4) Grading of surface Metres / km of roadway
Note
Refer sub section 106.6 regarding sub divisons of pay items.
114
700 DRAINAGE CONSTRUCTION
701 ROADSIDE AND LEADAWAY SURFACE DRAINS
701.1 Description
This work shall consist of the construction of roadside and leadaway surface drains,
lined where required, to dimensions and grades and in positions shown in drawings or
established by the Engineer.
701.2 Materials
The materials used for lining the drains shall meet the req urernents of the following,
unless otherwise specified.
(a) Precast concrete units to section 1705
(b) Class A or B concrete for precast sections or for insitu lining to section 1001.
(c) R. R. masonry andbrick or block masonry to sections 1006 and 1007 respectively.
(d) Cement mortar for rubble work and jointing of precast section to sub section 1703.2.
701.3 Construction Requirements
(a) Cutting and forming of earth drains
Drains shall be cut to cross sectional dimensions and grades given in drawings or as
established by the Engineer. Where site conditions require changes of cross section or grades,
such changes shall be approved by the Engineer. ' ' " , I,,'
Rock out-crop or rock boulders, encountered during excavation for the drain shall
be removed by sledging or blasting or by other approved means. Where such operations are
not advisable to be carried out due to site conditon, the drains may be suitably deviated with
the prior approval of the Engineer. Such deviations however, shall not impair the smooth
flow of storm waterin the drain and where necessary, they shall be sutably lined, using
concrete or R. R. masonry as siutable.
All loose and erodible material shall be removed and such pockets shall be 'filled
back with suitable material and compacted as required. Where necessary, a random rubble
paving with cement mortar jointing shall be provided over such excavated and backfilled
areas.
115
Where the gradients are steep, due to site conditions, suitable drop structures and
stilling basins shall be constructed as given in drawings or as directed by the engineer.
(b) Lined drains
All drains that are designated to be lined shall be constructed as shown in drawings
or as directed by the Engineer.
Where the linings are of precast concrete sections, they shall be laid on a prepared
bed to line and level. The joints shall be filled using I : 2 or 1 : 3 cement mortar as specified.
Insitu contruction with concrete, R. R. masonry or brick or block work shall be
carried out as given in drawings or as directed. Where specified, or where found necessary,
they shall be surface lined with 1 : 2 cement mortar and smoothened as directed. Bricks,
blocks and other materials used shall be approved by the Engineer prior to their use.
Rubble paving with mortar jointing, where specified, shall be carried out using
selected rubble, hammer dressed as necessary, to ensure proper embedment of the rubble
and also to obtain a reasonable smoothness of the surface finish after the jointing with 1 : 2
cement mortar is completed.
701.4. Measurement & Payment
(a) Measurement
Drains cut shall be measured in cubic metress in the different type of materials
encountered.
Measurement of lining of drains shall be in linear metres for precast units. for insitu
construcitions with R. R. masonry brick or block masonry or concrete, the measurement
shall be in cubic metres.
116
Rubble paving shall be measured in square metres paved and accepted.
(b) Payment
.... Payment will be at the contract unit rate for the different items of work and shall
include full compensation for all labour, materials tools and incidentals necessary for
completion of the work.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
701 (1) Drains cut (state type of material cut) Cubic metres
701 (2) Lining of drains with precast units
(state class and grade of concrete) Linear metres
701 (3) Lining of drains insitu (state type of
material of construction) Cubic metres
701 (4) Rubble paving in drains Square metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
'.', I
:'1 .'
". )' ,,',
117
702 SUB SURFACE DRAINS (UNDERDRAINSL
702.1 Description
This work shall consist of construction of sub - surface drains (underdrains) and
drain outlets using perforated pipes non perforated pipes and granular filter material. The
work shall be carried out in accordance with these specificatios and in conformity with
levels and grades shown on plans or established by the Engineer.
702.2 Materials
(a) The non perforated pipes shall be of concrete, pvc or earthen, conforming to following
standards.
concrete pipes to SLS 452.
PVC pipes to SLS 147.
Earthen ware pipes to SLS 449.
When perforated pipes of suitable types are not available in the market, perforations
in the pipes shall be made during manufacture, or by the Contractor subsequently, in the
manner indicated in drawings, required in special provisions, or as required by the Engineer.
(b) Granular filter material, for bedding and for surrounding the pipe underdrains, shallbe
graded aggregate of maximum size 37.5 mm conforming to the requirements of sub
section 1701.1 unless otherwise specified by the Engineer.
702.3 Construction Requirements
(a) Underdrains
Trenches shall be excavated to the dimension and grades required and a minimum
of 100 mm thick bedding layer of granular filter material shall be compacted in the bottom
of the trench for its full width and lenght.
Perforated pipes unless otherwise required, shall be laid with the perforations down
and the pipe sections shall be securely jointed by collars, mortar joints etc., as specified or
.as directed.
118
Non-perforated pipes of the bell and spigot type when used, shall be laid with the
bell end upgrade and the spigot ends entered into the bell ends and spotmortared to provide
for centering of the pipe but open enough to allow the infiltration of water.
After the pipe installation has been approved, granular filter material shall be placed
to a depth, so as to completely surround the pipe as in the drawings or required by the
Engineer. The remaining portion of the trench shall then be filled and compacted with either
granular or impervious material, as may be specified.
(b) Underdrain Outlets
Trenches for the outlets shall be excavated to the dimensions required by the
Engineer. The outlet pipes shall be laid on an approved compacted bedding in the trench
with their ends firmly jointed as required. On aproval of the pipe installation the trench
shall be back filled with approved suitable material and compacted in layers.
702.4 Measurement & Payment
(a) Measurement
Underdrains and outlets shall be measured by the linear metre of the pipe for each
type and size specified.
Granular filter material, when specified in the contract as a separate pay item, shall
be measured in place by the cubic metre, completed and accepted.
Excavations and approved soil backfill shall be measured and paid for as provided
for in section 302.
(b) Payment
The quantities as determined above will be paid for at the contract unit price which
shall be full compensation for furnishing and placing of all materials including all labour
equipment tools and incidentals necessary to complete the work prescribed.
119
The Pay Items and Pay Units will be as follows ;
Pay Item Pay Unit
702 (1) Drain pipes (State type and size) Linear metres
702 (2) Granular filter material Cubic metres
Note
Refer sub section divisions of pay items.
".' "
120
703 MANHOLES, CATCHPITS AND INLETS
. <r-: .
703.1 Description
This work shall consist of construction of manholes catchpits and inlets for
underground drainage systems to lines and levels shown on drawings or established by the
Engineer.
The inlets may be of the gully type or side entry type or a combination of both as
shown indrawings.
703.2 . Materials
; ..
. .
Concrete for precast units or for insitu construction shall be of class A or B as
specified in section 1001. Materials for rubble masonry and brick or block masonry shall be
as specified in sections 1006 & 1007 respectively.
Other materials shall conform to the requirements of the following unless otherwise
specified.
(a) Reinforcing steel to SLS 375 or CS 26
(b) Cement mortar for jointing to Sub Section 1703.2
(c) Mastic joint filler shall be of the approved varieties.
(d), Frames, .grate, 'covers and any other incidental items shall be as given in the drawings
. or elsewhere in the-contract documents.
7 0 3 ~ 3 . Consturction Requirements
All excavations and backfill required for construction shall be carried out in
accordance with the requirements of section 302.
Inlets catchpits and manholes shall be either precast and installed or shall be
constructed insitu.
Precast units, reinforced or unreinforced, shall be manufactured using concrete of
class A or B and of the required strenght as specified in the contract. The installations of
precast units shall be to required lines and levels and on prepared beds of approved soils,
concrete of any other material as indicated in drawings or as directed by th Engineer.
121
Insitu construction of catchpits ans manholes shall be carried out using concrete
rubble masonry, brick masonry or block masonry as specified. Concrete used shall be of
class B or C and of mix proprtions 1 : 2 : 4 (19 or 25) or I : 3 : 6 (37.5) respectively, as
specified. Rubble masonry and brick or block masonry shall conform to the requirements of
sections 1006 and 1007 respectively.
Insitu construction of inlets shall be carried out using class B concrete of mix
proportions 1 : 2 : 4 (20) or 1 : 1 1/2 : 3 (19) as specified.
Form work for insitu concreting of units shall conform to the requirements of section
1008.
Joints of precast concrete manhole sections shall be made with 1 , 1 cement mortar,
mastic joint fillers or a combination of these or any other approved material as may be
specified. The completed mortar joint shall be finished smooth and suitably cured, The mastic
joint filler where used shall be applied in accordance with the manufacturers recommendations
or as required by the Engineer, so as to form a water tight seal.
Pipe ends that are connected to the catchpits or manholes shall be flush on the inside
of the structure wall and project outside sufficiently for proper connection with the next
pipe section.
Metal frames for gulley inlets shall be set in mortar beds or be otherwise properly
secured as indicated in drawings.
703.4 Grade Adjustment of Existing Structures
When grade adjustment of existing structures has to be carried out, the covers gratings
and frames shall be removed as necessary and the walls reconstructed as required. The
cleansed frames shall be reset at the required elevations. Frames, covers or gratings that are
unfit for further use shall be replaced with new units. Upon completion, each structure shall
be cleaned of any accoumulation of silt, debris or foreign matter of any kind and shall be
kept clean of such accumulation until final acceptance of the work..
122
On resurfacing contracts the metal frames for gull : ~ y inlets shall be adjusted to grade
after the base course in laid and prior to placing the ~ ; w :ice course.
703.5 Measurement and Payment
(a) Measurement
Manholes, inlets and catchpits, new or reconstructed shall be measured by the unit.
(b) Pa.yment
The accepted quantities of manholes, inlets and catchpits will be paid for at the
contract unit price for each complete in place and shall be full compensation for excavation,
bedding, backfill, replacing pavement where required. Disposal of surplus material shall
not be measured and paid for separately but shall be included in the contract price for each
structure unless otherwise specified.
The Pay Items and Pay Units wil be asfollows ;
Pay Item Pay Unit
". '.,'
703 (1) Manholes (state type) Number
703 (2) Manholes reconstructed (state type) Number
703 (3) Catchpits Number
703 (4) Inlets (state type) Number
Note
Refer sub section 106.6 regarding sub divisions of pay items.
123
704 UNDER GROUND PIPE DRAINS
,
704 Description
This work shall consist of construction of under ground pipe drains in accordance
with these specifications and in conformity with lines, grades and dimensions shown in
drawings or established by the Engineer.
704.2 Materials
Materials shall meet the requirements of the following, unless otherwise specified.
(a) Concrete pipes and fittings shall meet the requirements of SLS 452
(b) Earthen ware pipes shall meet the requirements of SLS 449.
(c) PVC pipes and fittings shall meet the requirements of SLS 147.
(d) Cement grout and cement mortar used for jointing of concrete and earthen ware pipes
shall meet the requirements of the sub sections 1703.1 & 1703.2 respectively.
(e) Plastic sealing compounds used for jointing of PVC pipes shall meet the manufacturer's
requirements. .
(f) Pipe bedding materials shall be concrete of class B conforming to requirements of
section 1001 or granular material conforming to requirements of sub section 1701.1
(b) as specified.
704.3 Construction Requirements
(a) Excavation of Trendhes
Excavation shall be done to a sufficient width to allow for proper jointing of pipes
and thorough compaction of bedding and backfill under and around the pipes. The sides of
the trenches shall be adequately supported till the construction is complete.
All excavated material not required for backfilling shall be disposed of as required
by the Engineer.
124
'(b) , layini and jointini of pipes,
Immediately following excavation, the bedding of concrete or granular material shall
be laid and compacted, as directed, to required levels. The pipes shall then be liad, so as to
uniformly bear on the bed, and jointed, The bed shall be cut away and removed at each
socket or sleeve, in the case of socketed or sleeve jointed pipes, to give a clearance of at
least 50 mm so that the socket or sleeve does not bear on the bed.
Pipes shall be jointed such that the inner surfaces are reasonalblyflushand even
and the ends are entered as required.
Joints shall be made with cement mortar (l : 2), cement v grout, 'plastic sealing
compund or by a combination of these types or any other approved material as may be
. ':.
specified.
Mortar joints shall be made with an excess of mortar to form a continuous bead
around the outside of the pipe and finished smooth on the inside. For grouted joints, moulds
or runners shall.be used to retain the poured grout. Joints in concrete and earthen ware pipes
shall be thoroughly wetted, before mortar or grout is applied. Cementmortar or grout, where
used shall be protected against rapid drying by a suitable curing method.
Pipes shall be inspected after the jointing operations is over. Any pipe found tobe
out of alignment, or damaged shall be relaid or replaced. Any other defective work such as
leaky joints and defective grouting shall be redone.
,I
704.4 Completion of bedding andsurrounding of pipes
,Completion of bedding and surrounding of pipes shall be done immediately following
the jointing of pipes, except where the Engineer decides Jpatthe .pipes have, to be tested.
The bedding shall be completed so that the pipes bear uniformly at least upto 10
percent of the vertical diameter in concrete and at least 25 percent in granular material.
. I' ," I '.
125
The material for pipe surround may be pipe bedding material or selected fill material
as shown in drawings or specified elsewhere in the contract documents or required by the
Engineer.
The surround shall be laid in layers not exceeding 150 mm thickness and carefully
compacted. The surround shall be taken upto a height of 300mm above the top of the pipe
unless otherwise stated in the contract or directed by the Engineer.
704.5 Backfilling of Trenches
. Backfilling of trenches above the surround shall be carried out as given in section
305, using material suitable for embankment construction.
704.6 Measurement & Payment
(a) Measurement
Pipes of different types and sizes shall be measured by the linear metre in place.
Branch connections and elbows may be included in the lenght measurement for pipe, or they
may be measured by the number of units installed if so specified. The above measurement,
unless otherwise specified, will include excavation, pipe bedding, surround and the backfill
upto the original ground level.
(b) Payment
The accepted quantities of pipe, will be paid for at the contract unit price per linear
metre of the type and size of pipe as specified, complete in place.
Branch connections, end connections, elbows if separately measured, will be paid
for at the contract unit price per each of the kind and size specified complete in place.
Appropriate deductions shall be made for these specials in the total length of pipe measured
for payment.
': Excavation and backfill where separately measured, will be paid for as given in
under section 305. Pipe bedding and pipe surround where separately measured will be paid
for at the contract 'unit price per cubic metre laid and compacted.
126
,'rhe Pay Items and Pay Units willbe as follows :- .
Pay Item
704 (1)
704 (2)
704 (3)
704 (4)
Note
Pipes laid (state type and size)
Specials (state type)
Pipe bedding
Pipe surround
Refer sub section 106.6 regarding sub divisions of pay items.
Pay Unit
. Linear metres
Number
Cubic metre
Cubic metres
: I
1'7'7
705 DRAINAGE BACKFILL BEHIND EARTH RETAINING STRUCTURES
705.1 Description
This work shall consist of the construction of a permissible double layer of aggregate
behind earth retaining structures to facilitate the free drainage of the retained soil layers
(including any backfill) through the weepholes of the structure.
The double layer shall consist of a layer of large sized aggregate backfill immediately
behind the wall and a layer of graded small aggregate, referred to as the filter medium placed
along the sloping face of the aggregate backfill.
All work shall be carried out in accordance with these specifications and in
conformity with drawings or as required by the Engineer.
705.2 Materials
(a) Aggregate Backfill
The aggregate backfill shall normally consist of aggregate larger than 50 mm and
smaller than 200 mm, shall consist of hard and durable curshed stone or naturally occuring
stones.
(b) Filter Medium
The filter material shall be graded aggregate of 37.5 mm maximum size and
conforming approximately to grading requirement given in sub section 1701.1.
The aggregate, in general shall be free of organic matter, clay and other materials
which will adversely effect the free drainage of water.
705.3 Construction Requirements
Prior to placement of the larger sized aggregate behind the structure, the soil layer,
on which the aggregate is placed, shall be well compacted and made impervious either by ,
constructing a clay puddle or by the application of a bituminousbincder as required.
128
The aggregate shall be palced along the wall and to a stable configuration, as
indicated in drawings or as required, and compacted using a hand rammer or other suitable
means.
The filter medium of graded aggregate, shall then be placed and compacted along
the sloping face of the larger aggregate to the required thickness to form a uniform compact
layer. Unless otherwise specified, the minimum thickness of this layer shall be 75 mm. The
compaction of the layer shall be done using hand tampers or by other means aproved by the
Engineer.
705.4 Measurement & Payment
(a) Measurement
The quantity to be measured shall be the number of cubic metres or cubes placed,
compacted and accepted in place, separately for the aggregate backfill and the filter medium.
Impervious layer shall be measured in square metres.
(b) Payment
This work measured as provided above will be paid for at the unit price per cubic
metre of drainage backfill behind earth retaining structures. The price shal be full
compensation for all labour materials, equipment and incidentals required to furnish and,
acceptably place the materials.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
705 (1) Aggregate backfill Cubic metres
705 (2) Filter medium Cubic metres
705 (3) Impervious layer Square metres
129
706 WEEPHOLES FOR EATRTH RETAINING STURCTURES
706.1 Description
This work shall consist of providing openings in earth retaining structures to facilitate
the drainage of any water collected at the back of the structure, as given in the drawings or
as directed by the Engineer, and in accordance with these specifications.
The weepholes may either be cast insitu or consist of pipes embedded in the structure.
706.2 Materials
The pipes shall be made of concrete, PVC or any other suitable material approved
by the Engineer.
The moulds for weepholes cast insitu shall be of timber or similar material approved
by the Engineer.
706.3 Construction Requirements
When pipes are embedded in the earth retaining structure, they shall be laid to the
slope given in drawings or required by the Engineer and shall extend from the rear face to.
the front face of the structure. They shall be protected from ingress of materials during
construction and shall be cleaned before backfilling behind the structure.
When the weepholes are cast insitu the moulds used shall be longitudinally straight,
and shall be laid to the required slope in their designated places as the work proceeds. Where
necessary extra cement mortar shall be placed round them and the moulds worked loose to
facilitate easy removal when the material round them has sufficiently hardened.
706.4 Measurement and Payment
(a) Measurement
The weepholes for earth retaining structures shall be measured in linear metres of
weepholes. Impervious layer shall be measured in square metres or cubic metres.
130
(b) Payment
Payment will be based on the contract unit price for the item and shall include full
compensation for all materials labour, tools, equipment and incidentals necessary to complete
the work to the specifications
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
706 (1) Weepholes using pipes (state type and size) Linear metres
706 (2) Weepholes formed insitu (state size) Linear metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
131
707 PIPE CULVERTS
707.1 Description
This work shall consist of supplying, jointing, bedding of reinforced concrete pipes
of the required type, diameter and length in the construction of culverts.
The work also includes the construction of headwalls, wingwalls, aprons, catchpits
and other ancillary items necessary for completion. All works shall be carried out to lines,
levels and dimensions shown in drawings or as directed by the Engineer.
707.2 Materials
Concrete for pipe bedding shall be of class C concrete as specified in section 1001.
Other materials shall conform to the following, unless otherwise specified.
(a) Reinforced concrete pipes and fittings to SLS 452.
(b) Granular pipe bedding material to Sub section 1701.1 (a).
(c) Cement mortar for pipe, jointing to Sub Section
Materials used for construction of head walls, wingwalls and other ancillary items
shall conform to the requirements given in section 1106 for R. R. masonry, 1107 for brick
masonry and 1001 for concrete.
707.3 Constuction Requirements
(a) Excayation
Excavation for pipe culverts shall conform to the requirement of section 302 of this
specification. Trench when shaped and completed to receive the pipes shall be of sufficient
width, depending on pipe size and other considerations', to provide working space for
satisfactory bedding, laying and jointing of the pipe and for satisfactory compaction of
bedding material and backfill. Provision shall be made, as necessary, to drain the trench and
bedding during construction.
132
When completed, the bottom of the trench shall be firm over its full length and
width.
When pipe culverts are to be constructed in embankment fill, excavation for culvert
construction shall be made, after construction of the embankment, to the specified depths
below the formation as shown in the drawings, unless otherwise directed by the Engineer.
Where the soil encountered at the designed grade is unsuitable, unless other
construction methods are shown on the aproved plans, or are required by the Engineer to be
carried out, all such unsuitable material shall be removed and replaced with approved
foundation fill materials and compacted as required.
(b) Bedding of Pipes
Unless othewise specified pipes shall be bedded according to one' of the methods
described in (i), (ii) or (iii) below depending on the site conditions and as given in drawings
or decided by the Engineer.
(i) Concrete Bedding
The pipes shall be bedded in a continuous cradle of class C concrete, of
mix proportions 1: 3 : 6 (37.5) having a minimum thickness of 0.25 times the
nominal diameter of pipe or 150 mm, whichever is more. The concrete shall extend
up the sides of the pipes to a height of at least 10 percent the external diameter or
as shown in drawings. The minimum width of the cradle shall be the external
diameter of pipe plus 20 mm and shall be constructed monolithically without
horizontal constuction joints. The creadle shallbe such that the pipe can be seated
fully in it. The pipe shall be laid on the concrete bedding before the concrete has
set.
(ii) Granular Bedding
The pipes shall be bedded, on fine granular bedding material compacted and shaped
to a minimum thickness of 100 mm and to fit the lower part of pipe exterior for at least 15
percent of external diameter. A template shall be used to obtain the required shape.
133
(iii) Stable Soil Bedding
Instable ground conditions. and where so indicated in drawings ordirected
by the Engineer. the pipes shall be bedded on existing hard soil suitably shaped to
uniformly fit the lower part of the pipe exterior for at least 10 percent of its diameter.
A template shall be used to obtain the required shape.
Prior to placing of the pipes the soil bed shall be lightly scarify and moistened
to facilitate uniform embedment and where necessary. fresh soil shall be added so
that the pipes when placed are firmly and uniformly bedded into the soil.
(c) Laying of pipes
Unless otherwise directed by the Engineer. laying of pipes on prepared foundation
shall be started at the outlet and proceeded twards inlets. with the abutting sections properly
matched and fitted in. Where collars are used for jointing the pipes, cross trenches shall be
excavated to accommodate the collar and to facilitate jointing. Ends of the pipe shall be
carefully cleaned before they are placed. As each length of pipe is placed. the mouth of the
pipe shall be protected to prevent entry of earth or bedding materials; Once laid the pipes
shall be properly aligned.
707.4 Jointing
Each pipe joint shall be sealed to prevent leakage and infiltration of water on to the
bedding, unless shown on the drawings or specified, jointing and sealing shall conform to
one of the following :
134 ,
(a) Cement Mortar Joints Using Collars
Abutting ends of adjacent pipes shall be connected with concrete collarsand the
space between the pipe and the collar shall be tightly sealed with stiff 1 : 2 cement mortar,
to uniform thickness round the pipe.
(b) Socket and Spigot Joints
Where a pipe with spigot at one end and socket at the other are jointed with pipe of
same type and size, the spigot of one pipe shall be inserted into the socket of the other with
the flexible joint ring fitted at the spigot end and where a mortar joint is specified, c e m ~ n t
mortar of 1 : 1 compositionshall be worked into the joint by hand or by an approved tool:
(c) Lap Joints
In jointing pipes with tapered ends, the end with external taper of one pipe shall be
joined with the end with internal taper of the other pipe, and the space between the pipes at
the joint shall be patched with 1 : 2 cement sand mortar. In addition to this the joint shall be
provided with a covering with cement mortar of the same composition having ~ minimum
width of 100 mm and minimum thickness of 25 mm placedacross, and running continously
round the pipe at the joint.
707.5 Backfilling
. , . ~
Backfilling shall be undertaken as early as practicable after concrete and jointing
material has sufficiently hardened. Work shall be carried out according to section 302.
707.6 . Headwalls, Wingwalls and other ancillary works
Headdwalls, wingwalls aprons and other ancillary works shall be constructed in
accordance with the details shown in the drawings or as directed by the Engineer. Rubble
masonry or brick masonry for the walls etc.,shall conform to requirements of section 1006
or 1007 respectively as specified and concrete for aprons etc., if so specified, shall conform
to concrete of class B of section 1001.
135
707.7 Measurement and Payment
(a) Measurement
Concrete bedding and granular aggregate bedding shall be measured in cubic meters
of material laid and compacted.
Pipes shall be measured as supplied laid and jointed in linear metres along the centre
line of the laid pipes.
Measunement for excavation and backfill and consturction of headwalls etc., shall
be as specified in the respective sections.
(b) Payment
Payment for bedding and laying of pipes measured as above will be based on the
contract unit rate for the items which shall include full compensation for all labour tools,
equipment and incidentals necessary.
Payment for excavation and backfilling and construction of headwalls etc., shall be
as specified in the respective sections.
the Pay Items and Pay Units will be asfollows :
Pay Item Pay Unit
707 (1) Concrete bedding Cubic metres
707 (2) Aggregate bedding Cubic metres
707 (3) Concrete pipes Linear metres
136
801.4 Measurement & Payment
(a) Measurement
The quantities to be paid for shall be the number of cubic metres of top soil completed
in place and accepted. Top soil furnished by the contractor shall be measured as piled at the
site unless otherewise directed.
(b) Payment
The quantities of top soil will be paid for at the contract unit price which shall be
full commpensation for furnishing piling and spreading material including all labour,
equipment, tools and incidentals necessary to complete the work.
The pay Items and Pay Units will be as follows :
Pay Item Pay Unit
801 (1) Top soil supplied and piled Cubic metres
801 (2) Top soil spread Cubic metres
I
I
1
138
800 INCIDENTAL CONSTRUCTION
801 TOP SOILING
801.1 Description
This work shall consist of top soil furnished, transported and spread or top soil removed
from stockpiles, hauled and spread in conformity with these specifications at locations shown
on drawings or as directed by the Engineer.
801.2 Materials
Top soil provided by the contractor shall consist of loose friable natural surface soil free of
admixtres of sub soil, refuse, stumps, roots, rocks, weeds or other material which would be
. . . ,
detrimental to proper development of vegetative growth.
801.3 Construction Requirements
The contractor shall notify the Engineer at least 7 days before he intends to start
top soil from specified areas.
Unless otherwise specified top soil shall not be spread on slopes steeper than 1.5 : 1 (1.5
horizontal to 1 vertical). Where slopes are steeper than 3 : 1 these slopes shall be scarified
to depths indicated in plans or established by the Engineer, prior to placing top soil.
After the Engineer has approved the prepared and graded areas, top soil shall be spread to a
depth which after settlement, will provide the normal depth shown on plans or required by
the Engineer. Spreading shall not be done when the ground or the top soil is excessi vely wet
or in a condition considered detrimental to the work.
The roadway surface shall be kept clean during hauling and spreading operations. After
spreading has been completed, large clods, stones larger than about 40 mm in diameter and
any roots, stumps and other litter shall be raked up and removed and disposed of at an
approved .location,
137
802 GRASSING
802.1 Description
This work shall consist of providing grass cover by seeding, sprigging or sodding,
including soil preparation, fertilizing, mulching and watering as required, on all areas shown
in drawings or in areas to be identified by the Engineer, in conformity with these
specifications.
802.2 Materials
(a) Grass Seeds
The grass seeds shall be of an accepted variety reputed to produce a good grass
cover. Seeds shall be furnished by the contractor in standard sealed containers along with
seed name, weight and other details as necessary.
Where required, a certificate from the vendor stating that the seeds have been tested
within a stipulated period of time, not exceeding 6 months, from the time of delivery shall
be furnished.
(b) Grass Spri&S
Grass sprigs' shall be healthy living stems, with attached roots of. accepted turf
forming grass specified in the contract and approved by the Engineer, harvested without
adhering soil and obtained from approved sources in the locality of work. .'" .
(c) Grass Sods
Grass sods shall be of living vigorous growth, of the type of grass and thickness
specified, having a dense root system, contained in suitable sods and free from weeds etc.
(d) Fertilizer
Fertilizer shall be from a standard commercial grade conforming to all relevant
regulations and shall provide the minimum percentage of nutrients specified. Where the
type of fertilizer is not specified the contractor shall obtain the Engineers approval prior to
use of a particlar fertilizer.
139
(e) Mulch
Mulch used shall be straw, hay, saw dust or any other similar material specified in
the contract. They shall be free fr0n:' material injurious to plant growth.
(f) Water
Water used in planting or care of vegetation shall be free from oils, acids, alkalis,
salts or any other substance injurious to plant life.
. . .' ,"'
802.3 Construction Requirements
The areas to be grassed shall meet the specified finish grades, be free of any weeds
or plant growth, stones and other debris.
If top soiling is required it shall be done in accordance with the requirements of
section 801. The surface, where required, shall be loosened by raking.
Seeding shall be done during seasons designated in the contract documents or
established by Engineer. The meothod of seeding and application of fertilizer, water and
mulch shall be subject to the approval ofthe Engineer.
In grassing by sprigging, the contractor shall notify the Engineer at least 7 days
before sprigs are, to be harvested, and the source shall be approved by the Engineer before
I,
harvesting begirigs. Not more than 24 hours shall elapse between harvesting and planting
sprigs, except that when weather or other uncontrollable condition interrupt the work, a
reasonable time extension may be granted by the Engineer.
Fertilizing, watering and mulching shall be done as required and with the Engineer's
approval. Unless otherwise specified or directed, sprigs shall be planted at approximate
intervals of 150 rom apart.
140
Seeded area where grass has not taken root, and sprigged and sodded areas where
grass has died, shall be made good by the contractor by suitably replanting before final
acceptance. At the time of acceptance, areas considered by Engineer as poorly grassed shall
not be measured for payment and the contractor may be given a further extension of time for
replanting and correction of such areas as required.
802.4 Measurement and Payment
(a) Measurement
The quantity measured for payment, in each method of grassing (i.e, seeding,
sprigging or sodding) shall be the area measured along the slope in square metres.
(b) Payment
The work measured as above will be paid for at the contract unit rate for the particular
.method of grassing. The payment shall be full compensation for furnishing of materials
labour equipment tools and incidentals necessary to complete the work.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
.:' ,
802 (1) Sprigging Square metres
802 (2) Seeding Square metres
802 (3) Sodding (specify type) Square metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
142
Sodding shall be done during designated seasons given in drawings or in the contract,
or as authorised by the Engineer, The contractor shall notify the Engineer not less than 7
days before cutting of sods begin. Sods will be aproved by the Engineer in its original position
before cutting and delivery to the site.
Sods shall be laid on the prepared sod-bed within 24 hours after cutting except where
the Engineer has approved their being stored in stacks or piles, grass to grass or root to root,
for a period not exceeding 3 days.
The moving and laying of sods shall be done' as far as possible, when weather
conditions and soil moisture are favourable. Sodding may be done in one of the following
methods as designated in the drawings or as approved by the engineer:
(a) Solid sodding (b) Strip sodding (c) Spot sodding
In solid sodding, sods shall ~ ~ laid edge to edge with staggered joints and the joints
, . ,.
where necessary shall be filled with suitable top soil. After laying and joint filling, sodding
shall be tamped in an approved manner to provide an even surface. On slopes of 2 : 1 or
steeper sods shall be pegged after tamping, at approximately 0.6 metre centres. Strip sods
shall be laid in paralled rows as indicated in drawings or as required by the Engineer. Each
strip of sod, of width shown on drawing or approved by the Enginer shall be laid in a shallow
trench and firmly tamped until the surface of the sod is pproximately level with the adjacent
ground.
Spot sodding shall consist of sod blocks laid as shown on drawings or as required
by the Enginer. The pieces of sod shall be firmly tamped so that the surfaces of sod blocks
are approximately level with the adjescent ground
All grassed areas, be it by seeding, sprigging or by sodding, shall be watered lind
cared for and maintained in a satisfactory condition until final inspection and acceptance of
the work.
141
803 PLANTING TREES, SHRUBS, VINES ETC
803.1 . 'Description'
This work shall consist of furnishing, delivering and planting trees, shrubs, vines
and ground cover plants of the required type, size or age indicated in contract documents
, including all material and incidental operations completed in conformity with these
specifications; the positioning of plants' etc., shall be as indicated in the drawings or as
established by the Engineer.
803.2 Materials
Materials shall meet the requirements of the following, unless otherwise specified.
(a) .Top soil shall meet the requirements of Sub section 801.2.
(b) Fertilizer, mulch & water shall meet the requriements of Sub Section 802.2.
(c) Plant Materials shall be acceptable representatives of their normal species or varieties..
Unless otherwise specified, they shall be nursery grown stock that has been transplanted.
All plants shall be of normal development and free from knots, injuries, abrasions, .
dead or dry wood or any other disfiqurements.
803.3 Planting Requirements
(a) Planting Season
The planting shall be done during the seasons specified in the contract or established
by the Engineer. No planting shall be done when the soil is in an unsatisfactory condition
for planting.
(b) Deliyery and Inspection
The contractor shall notify the Engineer in writing not less than 15 days in advance
of delivery of plants from the nursery of the collecting source. All plant materials shall be
available for inspection in the nursery or collecting fields before they are dug. Contractor
shall ensure that the plants are delivered at the site without damage during transit.
143
l
(c) Protection and temporaty storaie
1. .
Contactor shall keep all plant material moist and protected from drying out. Protection
shall include the time when the plants are in transit, in temporary storage or on the project
site awaiting planting.
(d) Location of Plants
Location of plants or plant beds shall be carried out as shown in plans or as directed
by the Engineer. Contractor may adjust positions, due to ground conditions, but such
adjustments shall be approved by the Engineer.
(e) Excayation for plant pits
Excavation for plant pits shall be done to dimensions shown in plansor .establlshed
by the Engineer. All weeds roots and other objectionable material from the excavation, which
is unsuitable for backfill, shall be removed from the site and disposed of by the contractor
in a manner acceptable to the Engineer.
(f) Settin& plants and backfillinll
The plants shall be set approximately plumb and at the same level or slightly lower
than the depth at which they were grown in the nursery or collecting field. The backfill soil,
prepared as specified, shall be placed in the plant pit and carefully worked round and over
the roots and firmly settled by tamping.
(g) Fertilizini
A commercial fertilizer of the type specified shall be provided and applied uniformly
around the pit area of individual trees and in bed areas of plants grown in prepared beds.
The rate of application and the time of application of fertilizer shall be as specified or as
established by the Engineer.
144
(h) Wateriang
All plants shall be watered during and immediately after planting and at such intervals
during the plant establishment period as determined by the Engineer. Water shall not contain
elements toxic to plant life. At each watering the soil around each plant shall be thoroughly
saturated.
(i) Prunina. St,uina and Mulchina
Pruning shall be done before or immediately after planting in such a manner as to
preserve the actual character of the plant. All pruning shall be done by experienced personal
in keeping with accepted horticultural practices.
Plants that require staking shall be staked in accordance with the details shown on
plans' or as required by the Engineer as soon as the plant is in place.
Mulch material shall' be furnished and placed over the pit area of individual plants
and over the entire bed area of shrub beds to the depth as indicated in plaris. Mulch shall be
placed within 24 hours after planting.
U) Restoration and Clean up
Where existing grass areas have been damaged during planting operations the
contractor shall be required to restore the disturbed areas to their original conditions as
directed by the Engineer at no additional cost to the client. The contractor shall clean up all
debris, spoil, piles etc., and have the project area in an acceptable condition.
(k) Plant Establishment Period and Replacements
During the period specified in the contract or by, the Engineer as the plant
establishment period, which is normally one full growing period, the contractor shall care
for the plants by watering, adjustment of stakes, pruning and such other work which are
necessary to preserve plants in a healthy growing condition. Dead or unsatisfactory plants
shall be promptly removed from the site and replaced by healthly plants approved by the
Engineer.
1 4 ~
803.4 Measurement & Payment
(a)
The quantity of plants to be paid for shall be the number of Iiving trees, shrubs and
vines of spcified kinds and sizes furnished and planted in accordance with these specifications
and accepted. (only living plants in healthy condition at the end of the establishment period
will be accepted).
(b) Payment
The quantity of trees, shrubs and vines, measured as provided above, planted and
maintained in accordance with these specifications, \viiI be paid for at the contract unit
. prices. The unit price shall include for prepared backfill and all activities of planting and
caring for, including watering.
. "';.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
803 (1) Plants supplied (state type) Number
803 (2) Plants planted, nurtured and maintained
during the establishment period Number
Note
. Refer sub section 106.6 regarding sub divisions of pay items.
:, ""'", .
.,; ..
. . < ,. ,"
146
804 RIP RAP PROTECTION FOR EMBANKMENT SLOPES
804.1 Description'
This work shall consist of rip rap, for embankment protection and erosion control,
furnished and constructed in accordance with these specifications and in conformity with
lines grades and dimensions and at locations shown on drawings or established by the
Engineer.
The types of rip rap included in this specification are:
(a) Dumped rip rap
(b) Enclosed rip rap
(c) Grouted rip rap
Where specified, a filter blanket, which consists of a graded material, shall be placed
on the bank, before placing the rip rap, in order to prevent the bank material from passing
through the rip rap material. The minimum thickness of this layer shall be 75 mm unless
othewise specified.
804.2 Materials
All materials shall meet the following requirements unless otherwise specified.
(a) Dumped rip rap
Stone used for dumped rip rap, shall be hard, durable, angular in shape; resistant to
weathering and to water action. Rounded stones will not be accepted unless authorised by
the Engineer. Broken concrete may be substituted for stone when authorised. They shall
normally be less than 500 mm in the maximum dimension and more than 100 mm in the
minimum dimension and be reasonably well graded between these two limiting dimensions.
(b) Enclosed rip rap
Enclosed rip rap shall consist of baskets fabricted from galvanized steel wire - mesh,
reinforced plastic material, or any other material, filled with stone, connected together and
anchored to the slope. Stone used shall conform to the requirements of section 804.2 (a)
above and the size and gradation of stone shall be such that they are well contained as a
compact mass within the' wire mesh.
147
I
I
I
,
.,
805. GABION WALLS
805.1 Description
The work shall consist ofconstruction of protection walls to hill slopes, embankment
slopes, stream banks etc., using rock filled wire mesh baskets which are referrred to as
Gabions.
The Gabions shall be of box shape, with rectangular sides, and in constructing the
walls they shall be placed one on top of the other, as indicated in drawings or as directed.
805.2 Materials
Materials used shall meet the requirements of the following, unless otherwise
Speecified.
(a) Galvanized wire netting for making baskets to SLS 493.
(b) Concrete for construction of base shall be of class B to section 1001.
(c) Granular backfill material to sub section 1701.1.
(d) Broken rock for filling baskets shall preferably be of sizes Normally varying from
about 100 mm in minimum dimension to about 300 mm in maximum dimension and
they shall be hard and durable, free form weathered pieces and extraneous matter. The
rock shall be reasonably well graded between the two limiting sizes.
(e) Rubble masonary for construction of the base to section 1006.
805.3 Construction Requirements
The hill slopes, embankment slopes or stream banks, which the Gabion walls are to
abut shall be suitably trimmed and the ground on which the base of gabion walls is to be
constructed shall be leveled and compacted-as required.
Where indicated in drawings or required by the Enginer a base layer of concrete
(reinforced or unreinforced) or rubble masonary shall be constructed to the required
dimensions prior to placement of gabions.
The concrete for the base layer shall be of class C and of mix proportions 1 : 3 : 6
(40) or of class B and of mix proportions 1 : 2 : 4 (20) as specified. Rubble masonary for the
i I
I
construction of the base shall be as specified in section 1006.
i
, I
I
ISO
Where no firm base layer is specified the ground shall be well compacted and levelled.
prior to placing of the gabions and, if required by the Engineer, a thin layer of granular
material of the same composition as the granular backfill material shall be spread over the
compacted soil.
The baskets for the gabions shall be constructed to reqular box shapes out of
galvanised wire netting of the specified gauge with sides suitably cut and tied round or
woven securely using wire of same gauge as that of the mesh or with wire of an approved
gauge. The upper side shall be kept open till the baskets are filled and then securely tied
round using strands of wire. The mesh - wire diameter shall normally not be less than 3.0
. .
mm.
The filling of baskets shall be carried out insitu, unless otherwise directed. This
requires that the empty baskets, open on the top, be positioned on the base or on top of the
gabions and infilled with the rock pieces in such a manner as to completely fill up the baskets
leaving only the minimum of voids prior to closing and securely tying the lid using wire of
approved gauge. In building the wall the gabions shall be placed with scattered joints and
where so required they shall be tied together using strands of wire.
As the wall is being constructed the space between the gabions and the slopes shall
be backfilled in stages with granular backfill material and compacted well by rodding and
other suitable means approved by the Engineer.
805.4 Measurement & Payment
(a) Measurement
The gabion walls shall be measured in cubic metres, completed and accepted.
Granular backfill material shall be measured in cubic metres as compacted in place.
. .
151
Concrete or rubble masonary for base shall be measured as given in sections 1001
or 1006 respectively. " .'
(b) Payment
The quantities determined for gabion walls and granular backfill material as provided
above will be paid for at the contract unit rate which price shall be full compensation for all
labour materials tools and incidentals necessary for completion of the work including cutting
and shaping the slopes and forming the ground on which the wall is built.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
805 (1) Gabions Cubic metres
805 (2) Granular backfill Cubic metres
IS2
, ,
806 PAVED SIDE WALKS
806.1 Descripotion
.' This work shall consist of the construction of paved side walks to lines, levels and
grades shown in drawings or established by the Engineer.
The pavings shall consists of the following:
(a) Precast or cast insitu concrete slabs laid on a bed.
(b) Bituminous surface applications, surface dressings or surfacings laid on a. selected
gravelly soil base layer.
(c) Bituminous surface applications, surface dressings or surfacings laid 'on an aggregate
base.
806.2 Materials
, :. '.'
The concrete
.,
used for precast slab construction shall be concrete of class A. For
cast insitu construction concrete used shall be of class A or B to sectionl 001 and as specified.
The other materials used shall meet the requirements of following, unless otherwise
specified.
(a) Aggregate for bases, surface dressings and surfacings to Sub Section 1701.3.
(b) Aggregates for bed course material to Sub Section 1701.1.
. (c) Gravelly soil for soil bases to Sub Section 1700.
(d) Cement mortar for slab joints to Sub Section 1700.
(e) Reinforcing steels for concrete slabs to SLS 375 or CS 26.
806.3 Construction Requirements
(a) of base layers
Gravelly soil bases, where specified, shall be constructed to the required thickness,
as per section 601.
Aggregate bases, where specified, shall be constructed to the required thicknesses,
as per section 403 & 405 for single sized aggregate and graded aggregate respectively.
153
(b) Construction of bituminous surfacings
Priming of gravel surfaces shall be carried out as per section 602.
Surface dressings SBST or DBST, shall be constructed a ~ per section 505.
Asphaltic concrete surfacings shall be constructed as specified in section 506.
(c) Precast concrete slab construction
The precast concrete slabs shall be laid to line and level on a prepared bed of soil or
on bed course material where specified. The bed course material shall be spread uniformly
and compacted to the thicknessess specified. Where the slabs are to be mortar jointed, the
joints shall be set approximately 10 mm wide and shall be filled with 1 : 2 or 1 : 3 cement
sand mortar as directed. Where the slabs are not to be jointed they shall be placed side by
side to a close fit, as directed and where required shall be infilled with fine sand or crusher
fines.
(d) Cast insitu concrete slab construction
The slabs shall be cast on a soil bed or on bed course material, prepared to line and
level as in (a) above, in suitable steel or timber forms under-laid with a polythene sheet or
;any such material approved by the Engineer, to prevent cement grout and water in the mix
from being lost to the bed course.
The concrete shall be deposited, preferably in one course, in such a manner as to
prevent segregation and compacted thoroughly by light rodding, tamping, vibration and such
other means approved by the Engineer.
The surface shall be finished with a wooden float and light brooming: no plastering
of the surface shall be permitted. The joints shall be in filled with joint mortar as directed.
They may be left without jointing if so directed provided thin steel forms are used in the
casting and the joint widths do not exceed a maximum of 5 mm. However, the joints shall be
filled with fine sand or crusher fines, if so directed.
154
806.4 Measurement & Payment
(a) Measurement
All pavings, irrespective of the type, shall be measured by square metres of the
finished surface.
Where specified, bed course material may be measured and paid for separately, in
square metres or cubic metres spread and compacted.
(b) Payment
Payment will be at the contract unit rate for work measured as above which shall be
full compensation for all labour, materials, tools equipment and other incidentals required
for completion of the work.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
806 (1) Pavings (state type) Square metres
806 (2) Bed course material Cubic metres I Square metres
N.ote
Refer sub section 106.6 regarding sub divisions of pay items.
. ~ ,
ISS
807 PRECAST CONCRETE KERBS AND CHANNELS
807.1 Description
.
This work shall consist of the construction or resetting of kerbs, channel or
combination kerb and channel units to lines and grades shown on drawings or established
by the Engineer.
The dimensions of the units shall be as given in drawings or as determined by the
Engineer.
807.2 Materials
, Concrete for precast or cast in place units and concrete for kerb beds shall be of
grade A or B given in section 1001, and as specified.
The other materials used shall meet the requirements of the following, unless
otherwise specified.
(a) Reinforcing steel to SLS 375 or CS 26.
(b) Bed course material to Sub Section 1701.1
(c) Cement mortar for jointing to Sub section 1703.2.
807.3 Construction Requirements
(a) Precast Concrete Units
Excavation for placement of precast combined kerb and channel units shall be made
to the required depths and the base upon which they are placed shall be compacted using
hand tampers or by other approved means to an even surface. All soft and unsuitable material
encountered during such excavation shall be removed and replaced with suitable material.
which too shall be thoroughly compacted.
. Bed course material where specified. shall be laid and compacted, on the prepared
surface, to the required thicknesses.
Where precast kerbs without the channel sections are usedthey shall be fitted in
place on a bed of class B concrete is indicated in drawings or as required by the Engineer.
156
The kerb and channel sections should be laid so that the face and top lines conform
to the line and grade required. Where jointing of the units is specified, the joint spacings
between kerb units or kerb and channel units shall be set approximately to a uniform width
of 12 min which chall be filled with 1 : 2 cement sand mortar and thoroughly rammed in.
The Joint surface shall then be troweled to a neat finish. Where the units are to be placed
side by side without mortar jointing the faces shall be made to fit as closely as practicable
and where approved the surfaces shall be chipped and / or applied with a thin film of cement
groutto achieve the desired fit and also a bond between the units.
". '... ." f- ".','
In resetting previously salvaged kerb and channel units the procedure given above
shall be followed.
(b) Cast Insitu kerbs. or Kerb and Channel
Excavation and bedding for insitu kerb or kerb and channel shall conform to the
requirements of sub section 807.3 (a).
Forms used for concreting shall be of wood, metal or other suitable material
conforming to the requirements of section 1008 and shall extend the full depth of the concrete.
All forms shall be free from warp and of sufficient strength to resist the pressure of the
concrete without displacement. Bracing and staking of forms shal be such that the forms
remain in both horizontal and ,vertical alignment until their removal. All forms shall be
cleaned and coated with an approved form oil before concrete is placed. Expansion joints
shall be made at the required intervals using spacer plates made of metal, and in a manner
shown in drawings or as directed by the Engineer.
On curves of 100 m. radius or less forms shall conform to the specification curvature.
Concrete shall be proportioned, mixed, and placed in accordance with the
requirements of grade of concrete specified. Compaction of concrete placed In the forms
shall be by vibration or by other acceptable means. Forms shall be left in place for 24 hours
or until the concrete has set sufficiently, so that they could be removed without injury to the
concrete placed. . . .
157
The concrete s4all he, struck off to the cross section specified, after whichit shall be
finished smooth by means of a wood float.
Plastering of concrete deficiencies shall be done only with the apporval of the
Engineer.
The finished concrete shall be kept continously moist for a minimum period of 3
days and the method of curing shall be subject to the approval of the Engineer. For a further
peroid of 4 dyas the concrete shall not be exposed to the hot sun.
After the concrete has set sufficently, the spaces in front and back of the kerb shall
be refilled to the required elevation using approved material which shall be thoroughly
compacted.
807.4 Measurement & Payment
(a) Measurement
Kerbing, new and reset, shall be measured by the linear metre along the front face
of the section. Combination kerb and channel will be measured along the face of the kerb.'
No deductions shall be made for drainage structures installed in the kerbs ..
(b) Payment
The meausred quantities will be paid at the contract unit price for matre length of
each particular item which shall be full compensation for furnishing and placing of all bedding
and jointing materials and shall include for all labour, equipment, tools and incidentals
necessary to complete the work. Excavation, backfilling and compaction of soils & other
materials in forming the bed etc., shall be considered as incidental to the construction
procedure.
158
,., ,
The Pay Items and Pay Units will be as follows :-: .
Pay Item Pay Unit
807 (1). Kerb (state whether new or reset) Linear metres
807 (2) Channel Linear metres
807 (3) Kerb and Channel . Linear metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
159
808 GRUARD RAILS AND WALLS, GUARD STONES AND GUIDE POSTS
808.1 Description
This work shall consist of construction of guard rails, guard walls, guard stones and
guide posts at the locations and to dimensions, lines and levels shown on drawings or
established by the Engineer.
Guard rails and guard walls which are meant essentially to protect vehicles from
running off the road in hazardous areas shall be positioned on ~ h e roadway platform but
sufficiently away from the carriageway edge so as not to interfere with normal movements
of traffic.
Guard stones, as they are traditionally called, are usually positioned on culvert
headwalls and on top of retaining walls both to guide and to guard vehicles at these places.
Guide posts shall be positioned at the edges of embankments and such other places
essentially to guide vehicles.
808.2 Materials
Concrete used for casting of posts, guard walls, guard stones and footings shall be
of grade A or B given in section 1001 and as specified. The other materials shall meet the
requirements of the following, unless otherwise specified.
(a) Steel reiforcements for posts to CS 26 or SLS 375.
(b) Timber for posts & railing to Section 1709.
(c) Galvanized steel sheeting for manufacture of railings to SLS 306.
(d) Cement plaster for guard stones to Sub Section 1703.2.
(e) Bolts, nuts and screws and washers used for fixing guard posts to SLS 97 & 238
respectively.
(f) Precast Units to Section 1705.
160
808.3 Construction Requirement
(a) Guard Rails
Guard rails shall consist of posts and railing. Their assembly and erection shall be
as shown in drawings or as required by the Engineer.
Posts made of reinforced concrete or timber shall be set plumb in dug holes or iJ.1
concrete footings unless driving is permitted. In the latter case the manner of driving shall
be such as not to damage or distort the posts. Post holes where necessary shall be backfilled
with acceptable material placed in layers and thoroughly compacted. When it is necessary
to excavate post holes in existing pavings, all loosened material shall be removed and the
paving placed, as necessary.
Railings made of galvanized steel sheetings or any other similar material specified,
in corrugated shape or box shape, or made of timber planks of the specified size shall be
fixed according to details given in drawings and in a manner resulting in a smooth continuous
installation. Laps in railings shall be parallel to the direction of flow of traffic.
Bolts and screws used for fixing shall be so located that there are no sharp projections.
All posts and railings made of timber shall be treated with wood presevatives of an
approved quality and painted with two coats of enamel paint unless required otherwise.
All galvanized steel sheets and steel nuts and bolts and washers shall be cleaned of
rust and where necessary shall be treated with a rust inhibitor and then applied with a coat
of anticorrosive paint and two coats of emanel paint as directed.
Metal sheet railings where manufactured under shop conditions shall be sprayed
with primer and spray paint of a specified brand as directed.
Any damage during assembly or erection to coatings of paint previously applied
shall be corrected by applying the necessary primer and paint as specified or as directed.
161
No site drilling or cutting of railings or posts shall be permitted without the prior
approval of the Engineer.
(b) Guard walls and guard stones
Guard walls and guard stones shall be precast or cast insitu using concrete of the
specified grade. Forms used for concreting shall be of wood, metal or suitable material and
shall extend the full depth of the concrete.
All forms shall be free from warp and of sufficient strength to resist pressure of the
concrete without displacement.
All forms shall be cleaned and coated with an approved form oil before concrete is
placed and compacted.
Concrete shall be proportioned, mixed and placed in accordance with the
requirements of the grade of concrete specified. Compaction of the concrete placed in the
forms shall be by vibration or by other acceptable methods. Forms shall be left in place for
24 hours or until the concrete has set sufficiently so that they could be removed without
injury to the concrete placed. The finished concrete shall be kept moist for a minimum of 7
days. The method of curing shall be subject to the approval of the Engineer.
If plastering is specified it shall be carried out only with the approval of the Engineer.
(c) Guide posts
Guide posts shall be precast concrete units or of treated timber as specified and
installed in designated places in stable footings in insitu soil.
They shall be planted to a minimum depth of 0.5 m in dug holes, backfilled and
compacted as required. Where necessary the footings shall be strengthed with a concrete
infill round the dug hole compacted as required. Posts shall be painted, before and after
'installation, as directed.
162
808.4 Measurement & Payment
(a) Measurement
Unless otherwise specified, guard rails shall be measured by the length in metres of
I ".
each type and guard stones and guide post by the number of each type.
(b) Payment
The unit rate of payment for each item of work shall be full compensation for all
labour, equipment, tools, materials and incidentals necessary to complete the work including
painting as specified.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
808 (1) Guard rails (state type) Linear metres
808 (2) Guard stones Number
808 (3) Guide posts
Number
Note
Refer sub section 106.6 regarding sub divisions of pay items.
163
809 FENCING
809.1 Description
This work shall consist of construction of property fences and gates at the locations
and to the dimensions, lines and levels indicated in drawings or established by the Engineer.
809.2 Materials
Concrete used for precast posts shall be concrete ofclass Aor B given in section
1001 and as specified.
The other materials shall meet the requirements of the following, unless otherwise
specified.
(a) . Steel reinforcements for concrete posts to CS 26 or SLS 375.
(b) Steel section for posts and gates to CS 73.
(c) Barbed wire strands for fences to SLS 31.
(d) Woven wire mats for fences to SLS 407 & 793.
(e) Timber for posts to Section 1708.
(f) Anti corrosive paints and enamel paints for steel section to Section 1706.
809.3 Construction Requirements
Prior to planting the fence posts (which shall normally be of precast concrete or
timber ) in the required manner, the ground should be graded where necessary, so as to
provide a nice appearance of the fence line. All posts shall be set vertically and backfilled
with suitable material compacted in layers.
Where the drawings require that the posts be embedded in concrete the contractor
shall install temporary supports as may be required to hold the posts in proper position,
until such time as the concrete has set sufficiently to hold the posts.. Unless otherwise
specified a minimum period of 7 days shall be allowed before such posts etc., are subjected
to any stress.
164
Bracings shall be provided to posts where specified or where required by the
Engineer.
Barbed, wire or woven wire mats of the type and size required, shall be firmly attached
to the fences, and braced in the manner indicated in the drawings or directed by the Engineer.
All barbed wire and woven wire mats shall be stretched out and shall be installed to the
required elevations.
Gates shall be assembled and positioned as shown on drawings or as directed by the
Engineer.
809.4 Measurement & Payment
(a) Measurement
Unless otherwise specified, fences, shall be measured by the length in metres of
each type of fence and gates by the number of each type.
(b) Payment
The unit rate of payment for each item of work shall be full compensation for all
labour, equipment, tools, materials, and incidentals necessary to complete the work including
painting as specified.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
809 (1) Fence (state type) Linear metres
809 (2) Gate(state type)
Square metres
Note
Refer sub section 106.6 regarding sub divisions of pay items.
165
810 .i. ROAD MARKINGS
810.1 Description
The work shall consist of the application of road markings including the installation
of reflecting road studs on the finished paved areas of roads in accordance with the drawings
or as directed by the Engineer and in conformity with the Motor Traffic Act ..
810.2 Materials
The material used for road markings shall be approved varieties of the following; c o n f o r m ~ n g
to the stipulations given below:
Non-reflectorised thermoplastic material
Reflectorised thermoplastic material
Non-reflectorised road marking paint
Reflectorised road marking paint
Reflecting road studs used as road markings or as a component of road markings.
(a) No-reflectorised thermoplastic material
Non-reflectortsed thermplastic material shall be, from an approved manufacturer,
suitable for application in tropical climatic conditions. The material, when used in road
markings shall have resistance to spreading under traffic at temperatures upto 40C and
shall be capable of retaining plasticity at temparatures down to 5C and shall give road
markings durable and effective for a period of at least 18 months from the time of application
of the material. The composition of the material and it's properties shall be furnished to the
Engineer. The material shall be supplied in durable containers which do not contaminate the
contents and shall be stored in accordance with the mamufacturer's insturctions.
(b) Reflectoriese thermoplastic material
Reflectorised thermoplastic material shall be a mixture of thermoplastic material
which shall meet the requirements of the sub section 810.2 (a) and ballotini incorporated in
the mixture during manufacture. The ballotini shall be spherical, transparent, glass particles
free from sharp angular particles and the whole of ballotini shall pass a 2 mm. sieve and no
more than 10% of the ballotini by weight shall be retained on a 425 11m sieve. The proportion
by weight of ballotini in the mixture shall be in the range 13 - 12 % of the weight of the
mixture.
166
(c) Non-reflectorised road markina paint
Non-reflectorised road marking paint shall be a hard gloss paint, from an approval
manufacturer, recommended for use as a road paint; suitable for application, in tropical
conditions by brush or mechanical means, on cemented, concrete and bituminous surfaces,
to give a chemically stable film of uniform thickness. The 'drying time' of the paint shall be
not more than 15 minutes. The' drying time' shall mean the time lapsed from the time of
application of the paint to a road surface to the time the paint ceases to be picked up by the
tyres of heavy vehicles traversing over it. The paint when applied shall give a non-bleeding
film of uniform thickness with a flat Don-greasy finish. The following particulars of paint
shall be furnished :
(i) Composition (analysed by weight)
(ii) Application (hot or cold applied)
(iii) Type and maximum amount of reducer (thinner)
(iv) Drying time (to touch)
(v) Setting time (to recoat)
(vi) Recommended coverage (litres per kilometer of 100 mm stripe)
(vii) Heat resistance - i. e. maximum road temperature
(viii) Details of any primer, undercoat or tack coat required.
For hot applied paint, the following additional information shall also be supplied.
(ix) The temperature range of heating and application
(x) The open flash point.
(d) Reflectorised road m a r k i n ~ paint
Reflectorised road marking paint shall be a mixture of non-reflectorised road marking
paint which shall meet the requirements of the sub section 810.2 (c) and ballotini incorporated
in the mixture during manufacture. The ballotini shall be spherical, transparent, glass particles
free from sharp angular particles and the whole of ballotini shall pass a 1.18 mm sieve ane'
no more than 5 % of the ballotini by weight shall pass a 150 urn sieve. The proportion of
ballotini in the mixture shall be in the range 300 - 500 grams per litre of the mixture.
167
(e) Reflectine Road Stu.ds
.' ,l. ' ~ r .,
Reflecting road studs (hereinafter referred to as 'Studs') shall 'be of the depressible
self cleaning type of approved manufacture. studs shall be provided with either one reflecting
lens for traffic in one direction (referred to as unidrectional type) or two reflecting lenses
for traffic in either direction (referred to as bi-directional type). Each reflecting lens shall
have a reflecting surfce not less than 80 square millimetres and shall be capable of
withstanding the impact of wheel loads. The design of the studs shall be such that no direct
contact is possible between vehicular wheels and the reflecting lens or lenses and the stud
bears adequately on the road pavement or bedding layer and the possibility of removal of
the stud, due to the passage of heavy vehicular wheels over it, is minimal. The reflacting
units shall be interchangeable and capable of easy and quick replacement.
810.3 Construction Requirements
Road marking materials shall be applied only over surfaces which are free from
extraneous matter, clean and dry. Road markings other than those laid by mechanical means
shall be set out using suitable stencils. All road markings shall be protected from traffic
until the road markings are traffic dry'. I
(a) Thermoplastic Material
On concrete.surfaces, where necessary, an approved tack coat shall be applied, prior
to the application of the thermoplastic material.
168
Thermoplastic material shall be prepared, and applied accorcding to the
manufacturer's recommendations or instructions 'using equipment approved by the Engineer.
Thermoplastic material shall be laid by approved mechanical means to produce a uniform
surface free from bubbles and streaks. .
(b) Road Markin& Paint
Any primer or under coat specified shall be applied at a rate of application approved
by the Engineer. Any cold applied paint shall be thoroughly mixed in the container just
before any application and shall be maintained in a thoroughly mixed state in the container
during the course of application. Any hot applied paint shall be prepared and applied
according to the manufacturer's instructions using equipment approved by the Engineer.
Road marking paints shall be applied manually or by machine using spraying or screeding
methods as approved by the Engineer.
(c) Reflectin& road studs
Where considered suitable each stud shall be affixed firmlyto the road by means of
an approved adhesive which is compatible withthe road surface and the stud, aecordlngto
the insturctions of the manufacturer. If in the opinion of the Engineer the pavement surface
is not suitable for fixing the stud in the aforesaid manner, the stud shall be bedded in a
cavity formed in the pavement. The bottom of the cavity shall be levelled with suitable
granular material placed and compacted and the stud shall be firmly bedded on this layer so
that it is correctly centred and stands proud of the finished road pavement as specified. The
cavity walls shall then be tackcoated with cement grout and the remaining cavity around
the base of the stud made good with bituminous material or concrete placed, compacted and
finished flushed with the pavement surface. Any material inadvertently spilled shall be
carefully removed so that a clean workmanlike job is presented with a fully effective reflector
unit. Traffic shall not be permitted to pass over the studs until any material used for fixing
the stud has set properly.
,'! .:"
169
(d) Defective Materials and Workmanship
Materials which are defective or not conforming to the specifications or have been
applied in an unsatisfactory manner or to incorrect dimensions or in a wrong location shall
be removed, according to specifications l 502, the road surface made good, the materials
replaced, the road marking reconstructed and / or properly located all at the contractor's
expense.
The contractor shall take traffic safety measures during construction of road markings
. in conformity with section 103. "
810.4 Measurement & Payment
(a) Measurement
Road markings shall be measured by the area in square metres completed and
accepted. Where the width or length of a road marking proves to be greater than that specified,
and is accepted by the Engineer, the specified width or length shall be used when calculating
the areas f.or payment.
Reflecting road studs shall be measured in number supplied, installed and accepted.
(b) Payment
The payment will be at the contract unit rate for work measured as above, which
shall be full compensation for providing and placing or installing the materials including all
labour, equipment, tools and incidentals necessary to complete the work.
The Pay Items and Pay Units will be as follows ;
Pay Item Pay Unit
810 (1) Application of road markings (state material) Square metres
810 (2) Installation of reflecting road studs Numbers
Note
Refer sub section 106.6 regarding sub divisions of pay items.
170
811 ROAD SIGNS
811.1 Description
.This work shall consist of providing and erection of road signs of a permanent nature
complete with posts, sign frames and necessary accessories in accordance with these
specifications and the drawings or as directed by the Engineer and in conformity with the
Motor Traffic Act.
811.2 Materials
All materials shall conform to the requirements of the following sub sections
(a) Mounting Posts
The materials used for mounting post of road signs shall meet the requirements of
the following.
(i) Mild steel structural sections to SLS 73
(ii) O. I. pipes of approved manufacture
(iii) Timber to subsection 1708.
(b) Sign Plates
Sign plates shall be of one of the foloowing materials.
(i) Flat M. S. galvanized sheet to SLS 306
(ii) Flat sheets of aluminimurn alloy to SLS 68
(iii) O. I. sheets of approved manufacture
(iv) Plastic material which shall be self coloured or which shall lend it's surface to painting
I marking indelibly, to compose the entire panel or in combination with another material
compatible with it, approved by the Engineer.
(c) Frames and Stiffening
Stiffening members of sign plates shall be of Mild Steel,Aluminium alloy or timber
which shall comply with the requirements of sections 811.2 (a) and 811.2 (b)
(d) Fixtures and Fittings
Brackets and clips shall be of Mild Steel, Aluminium alloy or 01 apporved by the
Engineer.
171
Screws, bolts, nuts and washers shall be of approved metal or Aluminium alloy,
other than washers in contact with painted / finished surfaces, which shall be of a suitable
approved weather resisting soft material.
Screws, bolts, nuts and washers which are in contact with a sign face shall be of
stainless steel, G. I. or other approved material which does not give rise to rust streaks on
the sign face. Rivets shall be of copper, brass, aluminium alloy.
Copper or copper alloys shall not be used in contact with aluminium.
(e) Preservatives, Paints and Finishes.
All preservatives. painting.andfinishing material shall be of an approvedmanufacture
and suitable for application in tropical climatic conditions, on the type of material and the
surface.
Prime coats, under coats and finishing coats, shall be from the same manufacturer
unless otherwise approved by the Engineer: All materials shall be stored and used within
such time limits as' instructed by the manufacturer or as directed by the Engineer.
Reflective sheeting shall be' Scotchlite II Engineer grade, retro - reflective sheeting
or other approved colourfast reflective sheeting material.
Finishes on plastic signs shall be in accordance' with the manufacturer's instructions
and approved by the Engineer.
(f) Reflective Beads
. ".
Beads for reflectorization of signs shall be of good quality glass, reasonably spherical,
without sharp angular particles and the binder for the beads shall provide a high degree of
bead retention, high specular reflection and firm bond with the surface to which it is applied
and of an approved manufacture.
172
The beads shall contain not less than 80 % by weight within one of the size ranges
specified below:
SIZE RANGE MICRONS SIZE RANGE ASTM SEIVE SIZES
250 - 177 60 - 80
210 - 149 70 - 100
, t" '\-,.: \
"
177 - 125 80 - 120
149 - 105 100 140
125 - 88
105 - 78 140 - 200
811.3 Construction Requirements.
(a) ". Mounting 'Posts
A single post for mounting any standard type of sign such as an advance warning
sign or a regulatory sign or any informative sign other than a direction or an advance direction .
sign made of material specified in section 811.2 shall have a cross section corresponding to
the standard sizes of the signs and the standard clear heights of the signs from the ground as
specified in Table 811 - 1.
Where it becomes necessary the size of the sign post or posts for mounting the sign
shall be increased as approved by the Engineer.
All posts having hollow section shall be effectively capped to prevent the entry of
water.
Timber posts above grond shall be planed smooth.
(b) Siin Plates
Minimum thickness or gauge of signs plates shall be as follows :
(i) Mild steel sign plates 1.25 mm or gauge 18
(ii) Aluminium alloy sign plates 2.0 mm or gauge 14
(iii) G. I. Sign plates 1.6 mm or gauge 16
173
Thickness of sign plates fabricated in other materials shall be as approved by the
Engineer. Sign plates shall be cut accurately to the shapes and sizes specified within the
tolerance permitted. All required holes shall be accurately located and drilled or punched..
Any burrs. rough spots and loose material in the holes shall be removed. All holes shall be
drilled before painting.
(c) Frames and Stiffenins
A metal sign plates having any side or its diameter greater sthan 1 metre shall be
stiffened. Any metal stiffenig member shall have a minimum thickness of 2 mm,
Joints in stiffening members, or a stiffening frame shall be formed by approved
means to have sufficient strength and stiffness. Timber stiffening menbers shall be smooth
planed and of rectangular cross section not less than 50 mm x 25 mm with half lapped
weather proofed joints. The side of a timber stiffening member which shall gave a dimension
not less than 50 mm shall be at right angles to the plane of the sign when the stiffening
member is fixed to the sign.
(d) Fixtures and Fittings
Where the site conditions warrant, signs may mounted on existing suitable road
furniture or other fixed objects ifapproved by the Engineer.
The assembly of the sign plate, stiffening frames and any brackets, shall be held
together rigidly and firmly and shall facilitate easy maintenance.
Any sign mounted on a round post shall be, effectively restrained from rotation on .
its post.
l; .'
The clips or other fixtures of the assembly shall not induce localised bending stresses
on the sign plate.
Precautions shall be taken against deterioration due to electrolytic action when
dissimilar metals are in contact with each other.
ll,;'.l.
The minimum thickness of metal in brackets shalll be 3 mm. Weldedjoints (if used)
:./hall be sound and their surfaces shall be smooth, Holes shall be accurately located and
before painting. Clips shall be fabricated in metal strips of thickness not less than 2
;:':m. Screws and bolt shall have a diameter not less than 8 mm and shall be properly secured.
/\ny screw, bolt or rivet head on the face of the sign shall not protrude more than 10 mm
from the surface of the sign face and shall match the colour of the .sign face adjacent to it.
Preparation and Painting
All painting and finishing ofsigns and components of sign assembly shall be carried
out in a paint shop or work shop as approved by the Engineer according to sub section 8: 1.3
(h)
All paints shall be applied with a pressure spray to form a smooth even film and all
surfaces and edges shall be coated unless stated otherwise. Paint shall be applied only when
the surface or previous coat is dry. The manufacturer's instructions shall be complied with
in preparatory work and painting of sign components.
The following requirements shall be complied with unless otherwise specified.
(i) Aluminimu Alloys - Before painting, the surface of the sign plate shall be thoroughly
degreased and pretreated by approved means. The prepared face of the sign plate shall
receive a prime coat. Other surfaces shall neither be treated nor-painted. The back and
the edges of sign plate shall receive a finishing coat.
(ii) Steel - Before painting all steel components shall be cleaned of any rust, degreased,
dried and anticorrosive primer applied. All surfaces other than sign faces shall receive
a finishing coat.
(iii) Timber - Before painting the surfaces shall be thoroughly cleaned and dried.: A prime
coat and then a finishing coat shall be applied. Surfaces in contact with earth or concrete
and uptoa-height of 0.2 metres above ground, shall be painted with two coats of an
approved preservative prior to painting.
175
(f) Finishes of Siin Faces
The contractor shall comply with the insturctions of the manufacturer of paint,
reflective materials, plastic or other finishing materials, for finishing operations.
The finish on the face of a sign shall present an even surface free from blemishes..
Legends, symbols, bordres of signs shall have well defined edges.
Any colour in the finishing coat ofa sign shall be homogenous and uniform. Colour
shades Or signs shall be according to the samples of colour shades as approved by the
Engineer. Unless otherwise specified painted sign faces shall have at least one undercoat
over the prime coat before the finishing coat is applied. On sign faces, wihtout reflective
sheeting, reflective beads in binder shall be applied where directed by the Engineer.
(g) Erection of Siin Assembly
(i) For mounting posts with concrete bases
A foundation pit of dimensions as specified in the table or as otherwise directed by
the Engineer shall be excavated. The sign assembly shall be correctly centred in the pit, the
post vertically aligned and the sign plate shall be correctly oriented. The post shall be held
in position with temporary struts and stays. Concrete of class B and of the mix 1 :3 : 6
(37.5) shall be placed in the pit and compacted. The top surface of the concrete shall be
finished smooth to a slight slope downwards from the centre to the edges. The temporary
struts shall be removed after concrete has hardened.'
(ii) For mounting posts without concrete bases '
A pit of depth not less than 1/3 the totallenght of the mounting post and wide enough
to facilitate compaction of the backfill around the post shall be. excavated. The bottom of
the pit shall be levelled and compacted. The sign assembly shall be correctly centred in the
pit, the alignment of the post shall be correctly oriented. The post shall be held in position
with temporaty struts and stays. Backfill shall be placed uniformly around the post in loose
layers not exceeding 100 mm and each layer compacted. When the backfill has reached a
level slightly higher than the surrounding ground level, the top surface of the backfill shall
be smoothened off. The temporary struts and stays shall be removed.
176
(h) InspectiQn and
Before approval is granted by the Engineer for the fabrication of signs, the contractor
shall :
(i) Supply a sample of each type of sign to the Engineer.
(ii) Furnish information to the Engineer on procedures / processes and the facilities the
contractor has or proposees to use for the fabrication of signs.
The Engineer shall grant approval for the fabrication of signs after satisfying himself
from the above and inspecting the facilities of the contractor for fabrication of signs.
811.4 Measuremtnt and Payment
(a)
Road signs furnished, accepted and placed shall be measured by the number. Each
type and size of road signs shall be measured separately.
(b) Payment
Payment will be based on the contract unit rate for items which shall include full
compensation for furnishing and erecting the road sign. Rate shall also include the cost of
all materials, labour, equipment, tools and other incidentals necessary to complete the work
to the specifications.
The Pay Item and Pay Unit will be as follows :
Pay Item
Pay Unit
811 (1) Providing erecting road signs
(state type and size) Number
177
TABLE 811-1
THESPECIFIED SIZES OF CROSS SECTION OFSIGN POSTS OFDIFFERENT MATERIALS ANDDIMENSIONS OFFOUNDATION PITFOR
CONCRETE FOOTINGS OFMOUNTINGPOSTSOF SIGNS.
-
-...J
00
DIMENSION OF SIGN .
Minimumheight * of
the lower most point
of sign from the
ground.
(metres)
Material of sign Minimumsize of cross
. sectionof sign post
Minimumdimensions of the
foundation pit Length xBreadthx
Depth.
(metres)
Lengthofa
sideif
rectangular
in shape
(metres)
Diametreof
a signif
circularin
shape
(metres)
0.6 0.75 2.1
(b)GIPipes
(c) TImber
(a)MildSteel angle iron
(b) 50 rom dia.
3 mmthick
(c) 100 x 76 mm **
(a) 75 x 75 x 6 mm
0.25 x 0.25 x 0.75
0.5 0.6 1.5 (a)MildSteel angle iron
(b)GIPipes
(c)Tunber
(a) 50 x 50 x 6 rom
(b) 40 rom dia,
2.8 mmthick
(c)75 x 50 tnm**
0.2 x 0.2 xO.6
Note
* : -referredto as the clearheight of the signfromthe groundin the specifications - 8113 (a).
** :- dimension of the face of the signpost at right anglesto the plane of the signwhenthe post is fixed to the sign.
900 RIGID PAVEMENTS
901 CEMENT CONCRETE PAVEMENT
901.1 Description
This work shall consist of the construction of unreinforced cement concrete
pavements where manual techniques, supplimented by suitably improvised equipment,are
used for the placing and compaction of concrete.
Where work of a large scale is envisaged necessitating the use of specilised
techniques of construction, either of the fixed-form type or of slip-form type and particulary
where the pavements are reinforced, special provisions shall be written into the contract
regarding the equipment and the construction procedure.
901.1 Materials
Materials used shall conform to the requirements of the following, unless otherwise
specified.
(a) Ordinary Portland Cement to SLS 107.
(b) Water for mixing and curing to SLS 522.
(c) Coarse and fine aggregate to sub section 1701.2.
(d) Admixtures to section 1705.'
(e) Polythene sheeting and other materials used as separation membranes between the
subbase and concrete slabs and any special materials used for curing of concrete shall
be approved by the Engineer prior to their use.
901.2 Concrete mix requirements and testing for quality
(a) Class & Strenllth
Concrete shall be of class A conforming to sub section 1001.3 and shall be designed
to have a minimum 28 day flexural strength of 3.9 N/mm
2
or a minimum 28 day cube crushing
strength of 28 N/mm
2
as determined on beams of 150 mm square section and length 750 mm
or on 150 mm cubes respectively. Casting, curing and testing of cubes shall be carried out as
given in sub section 1001.12 and for beams the procedure laid down in BS 1881 shall be
followed.
179
Unless otherwise specified, in the design of mixes a target average strength value
(flexural or crushing) of at least 20 percent in excess of the minimum value shall be achieved
during preliminary testing.
(b) Maximum size and of
The aggregate shall be of nominal maximum size 37.5 mm or 40 mm as specified
and the combined aggregate, normally obtained by mixing of coarse aggregate and fine
aggregate, shall be within the grading limits given in sub section 1701.2, unless allowed
otherwise after carrying out suitable trial mixes.
(c) Compliance
In compliance testing of concrete' the acceptance criterion shall be that the average
value of 3 consecutive results of tests, on random samples, at the age of 28 days shall not be
below the specified munimum value, either for flexural strength or for cube strength as
appropriate. "_ /
Compliance testing shall be such that for each 300 sq.m. of concrete laid or for each
day's work 6 test beams or 6 cubes shall be cast, 3 for 7 day testing and the other 3 for 28
days testing, each from a separate sample. Where the average of 7 day tests falls below 65
percent of the required 28 day strength, the Engineer may order a suitable increase of cement
content with no extra payment to the contractor. Where the 28 day strengths fall below the
required inimum value the Engineer shall decide to accept or reject that part of concrete
depending on strength values. The Engineer, however, may decide to accept the concrete on
reduced strength values and at reduced payments to the contractor depending on performance
and other criteria, as applicable.
180
901.3 Construction Requirements
(a) Slab dimensions 'and joints
(i) Widths and thicknesses
Slab widths shall normally be 3.0 to 3.7 m, corresponding to the widths of a traffic
lane. In any case the slab width shall not exced 4.5 m without-the approval of the Engineer.
Slab thicknesses shall normally vary between 150 mm and 250 mm depending on
sub grade conditions and traffic. However, thicknesses greater than 200 mm shallbe adopted
only where so specified or directed and only where it is considered uneconomical to imporve
the subgrade or subbase sufficiently to limit the thickness of the slab.
(ii) Transverse joints
Transverse joints shall normally be contraction joints and they shall be expansion
joints only where so indicated in drawings or directed by the Engineer. ,
, '
They shall be spaced between 4 to 6 m depending on the slab thicknesses.
Contraction joints shall be created by making crack inducers in the slab at the top or
at the bottom as specified. Top crack inducers shall be made, as indicated in drawings or as
directed, either by moulding a grove in fresh concrete or by sawing a narrow, cut in the
hardened concrete to depths of 1/4 to 1/3 of the thickness of the slab. Where bottom crack
inducers are provided; there shall be a .corresponding shallow groove on the top as well,
These top grooves shall later be filled with a suitable mix of sand and bitumen Of any other
approved joint filler.
Where specified the contraction joints shall be dowelled across and normally these
dowels shall be spaced at about 300 mm apart. They shall be M., S. rods 20 to 25 mm in
dimeter and about 500 mm in length and coated with a film of bitumen, a resin based varnish
or a plastic sheath, to protect them against corrosion and to facilitate sliding in the concrete.
181
They shall normally be installed at mid-depth in the slab and parallel to the surface
and the centre line of the road either by vibrating in during concreting or by positioning on
a suitable metal frame prior to concreting. Where joint spacings are relatively small and the
.traffic is relatively low the number of dowels may be suitably reduced or they may be totally
eliminated, with the approval of the Engineer.
Expansion joints where specified shall be made with the required space maintained
uniformly across the slab and dowelled where necessary according to details given in
drawings or established by the Engineer. They shall be subsequently infilled with a bitumen
sand mix or any other approved material. ... ,
(iii) Longitudinal joints
Normally there shall be a longitudinal joint at the centre of a two lane road, or at the
separation lines of lanes in a multilane road! and they shall be formed with or without a key,
and with or without tie bars, as specified.
A key where specified shall be formed to details given in drawings or established
by the Engineer.
Tie bars shall be of the size and length specified and shall be inserted at the spacings
given in the drawings or by the Engineer. The top of these joints shall be suitably grooved
and infilled with a sand bitumen mix or any other joint filler as approved.
(b) Sub grade requirements
The concrete pavement shall be placed on an improved subgradeor on a sub base of
approved type and thickness. The sub base may be of natural soil conforming to section 401
or of stabilized soils conforming to section 402. The subbase may also be of graded granular
material similar to that of graded aggregate base to section 405.
(c) Separating membrane
Prior to laying of the concrete pavement the surface of the approved subgrade or
subbase shall be cleared of extraneous material and over-laid with a separating membrane
of polythene sheeting of the specified thickness, unless otherwise specified.
v, \.:
," "
182
(d). Layini of Formwork
. '.' . . .' ';" ;:.... . .: . ," .
The formwork within which the concrete is to be laid shall then be positionedand
fixed to line and level and to the required lengths.
Unless otherwise directed, the formwork in addition to the requirements of section
1008 shall be of steel, and shall be made to L-shapre section using steel plates of minimum
thickness 6 mm. The height of the formwork shall be equal to the thickness of the pavement
and the base width shall be at least equal to 75 percent of the height. . .' '.,
The forms shall be placed on the base, and over the separating membrane, with full
bearing on it, to the required alignment of the pavement edge. They shall be held down in
place by means of steel stakes one at each end of each length of forms andat intermediate
points not greater than 1.5 m apart. Each from shall be firmly fixed to the adjoining form by ..
suitable edge fasteners which could easily be removed, but will hold them firmly preventing
any lateral movement when the concrete is placed and compacted.
(e) Manufacture and. Transport of Concrete
As a first step in the manufacture of concrete the Contractor shall ensure that the
production capacity of the mixing plant suits the laying equipment and the concreting rate.
The mixing of concrete shall conform to the requirement of sub section 1001.8.
In the transport of the mix care shall be exercised to minimize segregation and also
delay.
When concrete is transpoted from within the site or from a mixing place in the vicinity
of the site, ordinary trucks or dumpers with suitable tipping arrangements maybe used.
183
Preferably, they should be of low bed type and of small capacity, where manual
methods of placing and compaction are adopted. Such transport may be done using even
wheel borrows provided a sufficient number are employed and an efficient method of tipping
the concrete at the required places is arranged.
In central plant mixing the concrete shall normally be transported using suitable
truck mixers or truck agitators. In such circumestances the details of transport equipment
and the time duration of transport, laying and finishing operations shall be as specified in
the contract or as established by the Engineer.
(f) Laying Operations
The placing compaction and finishing operations of concrete shall 'normally be made
labour intensive, except in large scale work where specified equipment shall be used.
(i) Manual methods of laying and compaction
Laying of concrete manually shall in the minimum be assisted by a suitably
improvised method of placing the concrete in a uniform and sufficient mannerto suitthe
desired rate of concreting.
For compaction, suitable poker vibrators, plate vibrators and vibrating beams shall
be used. Also there shall be a sufficient number of skilled labour, each assigned with a
specific task.
To imporve the method of placing of concrete an improvised box hopper spreader
may be used. Under suitable conditions use may be made of an asphalt finisher.
(ii) Machine laying, compaction and finishing
For large scale work, where the pavement needs to meet higher quality criteria,
particularly for evenness, and where higher rates of laying are specified, use of specific
concreting equipment such as a concreting train on fixed forms or a small sized slip form
paver (of paving width not exceeding 5.0 m) shall be used. In such instances, however, the
details of paint and their methods of use shall be as given in the contract.
184
(g) Finishina Operations
The surfaces shall be finished rough as required by the Engineer. For this purpose a
mechanical broom or suitable hand brooms shall be used. Where necessary transverse grooves
shall be formed by using a vibrating beam or such other mechanism approved by the' Engineer.
Use of additives to roughen the surface shall be with the prior approval of the Engineer.
(h) Curina of Concrete
Curing of the laid concrete shall be carried out for a minimum period of 7 days as
provided for in Sub section 1001.11.
901.4 Measurement & Payment
(a) Measurement
Concrete pavements shall be measured as finished work in position in cubic metres
or in square metres of surface area. Joints shall be measured separately in linear metres as
specified.
(b) Payment
Payment will be based on the contract unit rate for each item of completed and
accepted work, which shall include full compensation for meterials, labour, equipment,'
transport, hire charges and incidentals necessary to complete the, work.
The Pay Items and Pay Units will be as follows :
Pay Item Pay Unit
901 (1) Concrete Pavement Cubic metres
901 (2) Concrete Pavement (state thickness) Square metres
901 (3) Joints (state type) Linear metres
.". :'
Note
Refer sub sectlonIue.e regarding sub divisions ofpay items
185
I
1000 BRIDGES & OTHER STRUCTURES
1001 CONCRETE FOR STRUCTURES
1001.1 Description
This work shall consist of the production of cement concrete for use in the
construction of bridges, culverts and other sturctures. The work shall also include.
proportioning and mixing of materials: transporting, placing and compacting, finishing and
protecting andcuring for specified periods;
1001.2 Materials
The constituent materials shall conform to the following, unless otherwise specified.
(a) Ordinary portuland cement to SLS 107 or BS 12.
(b) Rapid hardening cement to BS 12.
(c) Water for mixing and curing to SLS 522.
(d) Coarse aggregate and fine aggregate to Sub Section 1701.2.
(e) Admixtures to Sub Section 1704;
(f) Special cements and aggregates that are used in the special concretes of class S shall
be as specified in the contract.
1001.3 Classification and uses of concrete
Concrete used in bridge works and other structures shall be classified as given in
table 1001-1,depending on their uses.
1001.4 Proportioning of Materials
(a) General
The basis and the method of proportioning of concrete will depend o ~ the class of
concrete and the structural importance of the members being cast.
Concrete shall be proportioned or batched on the basis of nominal mixes, prescribed
mixes or on the basis of designed mixes as the case may be and the method of proportioning
of materials shall be by volume or by weight.
186
L .
. Table - 1001-1 - Classification of Concrete
Class Description Uses
A Concrete made with ordinary
portland cement (OPC) where
strength requirements are specified.
They shall be of prescribed or
designed mix proportions
. . '.
All prestressed concrete
items and for all reinforced
concrete slabs, beams
abutments, piers, columns,
'piles etc; where strength is a
. .criteriori .
B
Concrete made withOPC for small
works and ancillary works where
strength requirements mayor may
not be specified. Shall be of nominal
mix proportions
Mainly for ancillary items
such as paving slabs, kerbs,
handrails, posts facia slabs
etc; Also used on small
works such as culverts, slabs
etc.
C
Low strength concrete made with
\ . . .
OPC where strength requirements
are not specified.. Shall be of
nominal mix proportions
Mass concrete foundations,
retaining walls, abutments
etc; Fillings & Screedsr:
S Special concrete where
(a) Cement used or aggregates
used or both may be different
from that of classes A, B or C
above
1. Concrete for decorative
purposes;
2. Concretes resistant to
chemicals etc.
(b) Strength requirements mayor
may not be a criterion
3. High strength concretes
using additives and I or
special cement and
aggregates
They may be of nominal, prescribed
or designed mix proportions
187
(b) Volume proportionini of concrete
Volume proportioning of batching of constituents shall be limited to concrete of
class Band C and to concrete of class S where strength is not a criterion as given in table
1001-1, of sub section-lOo l.S.
For this purpose mix proportions of nominal mixes shall be used and the volumes
shall be based on.a unit volume of cement..
(i) Nominal Mixes
In nominal mixes the constituents - cement, fine aggregate and coarse aggregate
shall be expressed in simple proportions such as I : 2 : 4 or 1 : 3 ; 6 in which the relative
proportions of fine to coarse aggregates are generally kept constant at 1 : 2.
Table 1001-2 gives the nominal mixes that are in general use along with the class of
concrete to which they belong...
Table - 1001-2 - Nominal Mixes
Class of Concrete Approximate Grade
Nominal Mix Proportions
B
C
25
20
--
--.
--
e:
1 1I2
:
3 (12.5)
1:11/2:3 (19)
[I : 2: 4
(19)
1:2:4 (25)
I : 3: 6 (25)
1 : 3: 6 (37.5)
1:4:8 (37.5)
1: 4: 8 (50)
Note
Figures within brackets denote the nominal maximum size of aggregate in mm.
188
(ii)Unit Volume of Cement
Cement shall be considered to have a nominal weight of 1440 kg per cu.m (90 lbs
. per cu.ft). On this basis the equivalent volume of 50 kg bag of cement shall be 0.035 cu.m
(1.25 cu. ft) which shall be considered as the unit volume of cement for volume batching.
(iii) Measuring boxes for hatching of aggregates
In batching aggregates the unit volume of'cement shall be considered the unit of
volume and unit volume boxes shall be made to internal dimesions of 400 mm x 350 mm x
250 mm which equals .035 cubic metres.
These boxes shall be made of timber or any other suitable material and shall be
provided with suitable handles for easy handling.
The contractor may use different dimensions for these boxes with the approval of
the Engineer provided the internal volume equals 0.035 cu.m or a convenient fraction of
this volume.
(iv) Batching of cement
Batching of cement shall be by the bag unless otherwise allowed by the Engineer, in
which case unit volume boxes or boxes of fractional volumes shall be used with appropriate
allowances for bulking. The extra to be added for bulking shall be approved by th Engineer
but shall not be less than 15 percent by volume.
(v) Batching of Sand
In batching sand bulking of wet sand shall be taken into account. Where field tests
are not carried out to assess the premissible bulking of sanda bulkage upto 25% may be
allowed depending upon the moisture content of sand.
(c) Wei&ht proportionin& of concrete
(i) General
Weight proportioning (batching) of constituents shall be used in the production of
concrete of class A or concrete of class B or S where strength requirements are specified.
189
These mixes are for concrete ofmedium to high strength and shall be of grade 20 or
higher. They shall be either prescribed mixes or designed mixes except where nominal mixes
in class Bare batched by weight.
(ii) Prescribed Mixes
Prescribed mixes shall normally be limited to grades between 20 and 30. (see sub
section 1001.5 for the definition of grades). They shall not normally be used for prestressed
concrete members and for special concrete of high strengths.
With prescribed mixes, mix proportions which satisfy the requirements regarding
strength and workability shall be specified and the contractor is required to produce a properly
. mixed concrete to satisfy these requirements.
However, slight adjustments to the mix proportions, within reasonable limits, shall
be permitted at the site, to obtain the required conditions arid to accommodate the variations
due to the use of local aggregates. Where so directed, the contractor shall carry out suitable
trial mixes to assess the suitability of a given mix.
In specifying prescribed mixes normally the following shall be given.
1. Strength or grade
2. Nominal maximum size of aggregates
3. Minimum cement content
4. Mix proportions
5. Workability - low, medium orhigh (see subsection 1001.6)
However, in place of 3 & 4 above the aggregate proportions for a fixed quantity of
cement may be given, as in Table 1001-3, in specifying prescribed mixes.
190
Table 1001-3 gives a few typical prescribed mixes that could be adopted for general
use with slight adjustments where necessary. The Engineer, however, may specify other
prescribed mixes provided such mixes had been tested for suitability previously.
(d) Designed Mixes
In designed mixes the contractor shall select mix proportions of constituents to
achieve the strength I grade and workability required. In additionhe shall conform to the
requirements of minimum cement content and size of aggregate specified.
Where mixes are designed for class S concrete the contractor shall conform to the
special requirements given in contract documents or by the Engineer, such as type of cement
and type of aggregate, in addition to the above.
All prestressed concrete, and other concrete of grades higher than 30, shall normally
be designed. (see sub section 1001.5 for grades of concrete).
In the design of mix proportions for a particular concrete the contractor shall prepare
trial mixes and carry out preliminary tests as specified in sub section, 1001.6, in order to
achieve a target mean strength higher than the characteristic, strength by such a margin of
strength, that the minimum strength requirements of the works cube strengths shall be
satisfied.
The contractor may decide on the required target mean, strengths by a process of
statistical analysis provided sufficient data is available. Where such data is not available the
contractor shall adopt a margin of strength not less than 10 Nzmm", over and above the,
characteristic strength, in deciding on the target mean strengths. Table 1001-4 gives such
proposed minimum target strengths and minimum cement contents using aggregates of 20
mm Nominal maximum size.
191
Table 1001 - 3
Prescribed. Mixes - Proportions per 50 kg. bag of cement
Grade of
Concrete
20
25
30
Nominal max. size of
Aggregate mm
Workability
Total aggregate (kg)
Sand %