Bts 3900 Atp (Swap)

The document provides test procedures and results for ATP (Acceptance Test Procedure) of a Huawei BTS3900 base station swap. It contains two parts - offline tests of hardware items like cabinet, board and cable installation and online tests of service, O&M and RF specifications. The offline tests verify proper installation of cabinets, antennas, boards and cables. The online tests check service items, logging and reset functions, alarms and RF specifications like VSWR. Test results are recorded as pass, fail, not run or zapped for each item.

Uploaded by

Yasir Jami
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
451 views

Bts 3900 Atp (Swap)

The document provides test procedures and results for ATP (Acceptance Test Procedure) of a Huawei BTS3900 base station swap. It contains two parts - offline tests of hardware items like cabinet, board and cable installation and online tests of service, O&M and RF specifications. The offline tests verify proper installation of cabinets, antennas, boards and cables. The online tests check service items, logging and reset functions, alarms and RF specifications like VSWR. Test results are recorded as pass, fail, not run or zapped for each item.

Uploaded by

Yasir Jami
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 29

ATP Document HUAWEI BTS3900 Base Station (SWAP)

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 1

Site ID and Name:


BTS 3900 ATP Snags Classification
ATP Date Snag Details
Snag Classification (Major/Minor) Workmanship Factor(WM) * Product Factor (PrF) Planning Factor (PF)

Note: *WF: Means Snags reported due to Workmanship /Human Factor.(Technical Expertise , Skills lacking. Poor Workmanship etc) PRF: Means Snags reported due to Product Factor/Issues (Product & Design issues/flaws, High fault rate etc) PF: Means Snags reported due to planning factor/Issues (Poor planning and Management etc).

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 2

ATP Summary (For Part 1-OFF LINE TEST)


S.No.
T01

Test Items

Total

Status
Pass Fail

Hardware Acceptance Items


T01-01 T01-02 T01-03 T01-04 T01-0401 Cabinet Installation Antenna System Installation Board Installation Cables and Grounding Installation of Power Cables and PGND Cables T01-0402 Installation of Trunk Cables and Signal Cables T02 T02-01 T02-0101 8 6 9 6 2

Power-On Test
Running Test Board Indicators

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 3

ATP Summary (For Part 2-ON LINE TEST)


S.No. T01 T01-01 T02 T02-01 T02-02 T02-03 T02-04 T02-05 T02-0501 T02-06 T02-0601 T02-0602 Test Items Total Pass 3 Status Fail

Service Items
BCCH Mutual Help

O & M function Acceptance Items


Logging in to the Site Maintenance Terminal System Site reset in Levels Channel Status Check Board Operation 1 4 2 2

BTS Alarms
External Alarms 16

RF Specifications Test Items


VSWR Of The Antenna System DRFU/GRFU Antenna Power 3 4

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 4

Part I: OFF-LINE TEST

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 5

T01 Hardware Acceptance Items


T01-01 Cabinet Installation
Objective
Verify that the installation of the BTS3900 cabinet complies with the corresponding engineering specifications.

Result:
PassFailNot RunZapped

Comment & Remark:

Prerequisites

The installation of the BTS3900 cabinet is complete. Procedure 1. Check the placement of the cabinet. Expected result The placement of the BTS3900 cabinet complies with the engineering design. Result

Pass Fail Not Run Zapped

2.

Check the installation position of the cabinet.

The master cabinet is on left side. The slave cabinet is on right side.

Pass Fail Not Run Zapped

3.

Check all bolts, flat washers, and spring washers. Check the connection between the cabinet and the base. Check the horizontal error and vertical error of the cabinet.

All bolts are fastened. The spring washer is installed between the bolt and the flat washer. The base (support) is in proper position with the expansion bolt holes. The cabinet is securely connected to the base and is stable.

Pass Fail Not Run Zapped

4.

Pass Fail Not Run Zapped

5.

The cabinet must be installed correctly in horizontal view and vertical view.

Pass Fail Not Run Zapped

6. Check the cleanness and labels.

The cabinet must be cleaned. There is no dust inside and outside of the cabinet. The surface of the cabinet must be clean and neat. The painting on the cabinet surface is satisfactory.

Pass Fail Not Run Zapped

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 6

The labels are correct and clear.

7. Check the sanitation inside and outside of the cabinet.

There is no dust in or out of the sub rack. The outer side of the cabinet is brushed and the labels are well attached, complete, and legible to power cables..
Pass Fail Not Run Zapped

8. Check the cabinet door lock

The front door can be locked reliably and be unlocked by the key smoothly. The rear door can be locked reliably
Pass Fail Not Run Zapped

9.

Check the surface of cabinet

The cabinets are clean and neat. The exterior paint is satisfactory. All labels, tags, and nameplates are correct, legible, and complete. No transport damage can be found.
Pass Fail Not Run Zapped

T01-02 Antenna System Installation

Objective:
Verify that the antenna system installation meets the engineering requirements. The engineering parameters of antenna are as follows: Result: PassFailNot RunZapped Comment & Remark:

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 7

Prerequisites The antenna system is installed. Procedure Expected result The connectors of all the outdoor jumpers are waterproofed. Waterproof curves are made for the jumpers. Result

1. Check the jumpers,


Connector, Bending and proper labeling

The bending radius of the jumper should be 20times larger than its diameter. The vendor to ensure that all newly installed & commissioned RF feeders and jumpers (from cabinet top to antenna port) are properly & correctly marked (e.g. Sector Marking, Diversity Marking, and Band Marking etc.) Check whether all physical connections between antennas and BTS (sector) are correct.

Pass Fail Not Run Zapped

2.. Check for any sectors swap

Pass Fail Not Run Zapped

Remarks None.

T01-03 Board Installation

Objective: Verify that the installation of boards meets the engineering requirements. Result: PassFailNot RunZapped Comment & Remark:

Prerequisites

The board installation is complete. The slots without boards are installed with dummy panels.

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 8

Idle ports for power cables are protected with caps. Procedure Expected result Result

1. Check whether the installation positions of the DRFU/GRFU, DCDU, PSU, PDU, EMUA and BBU are correct. 2. Check whether the screws are secure. The screws are in secure connection with the subrack. Pass Fail Not Run Zapped The reference is as attached drawing. Pass Fail Not Run Zapped

T01-04 Cables and Grounding


T01-0401 Installation of Power Cables and PGND Cables
Objective Verify that the power cables and PGND cables are correctly processed and installed. Result: PassFailNot RunZapped Comment & Remark

Prerequisites

All internal cables are installed. Procedure Expected result Check the PGND cables. Result

1. Check the specifications of


power cables and PGND cables.

The cross-sectional area of the PGND cable is 2 equal to or larger than 16 mm . No joint lies in the middle of the power cable or the PGND cable. The power cables and PGND cables are intact. The connectors in use on the power cables are capped with protective sleeves.

Pass Fail Not Run Zapped

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 9

2. Check the power cables and


PGND cables of the battery.

The power cables for the positive pole and negative pole of the battery are connected. The OT terminals of the power cables are wrapped up with insulating tapes.

Pass Fail Not Run Zapped

(1)

The power cables and PGND cables are intact. Both ends of the power cable and PGND cable are attached with labels. The power cables and PGND cables are not short-circuited or connected reversely. The power cables and PGND cables are not damaged or broken. No joint lies in the middle of the power cable or the PGND cable.

(2)

3. Check the cables and related


labels. (3) (4)

Pass Fail Not Run Zapped

(1)

The lugs at both ends of the power cables and PGND cables are soldered or securely crimped. The bare wires and lug handles at the wiring terminals are tightly wrapped up with insulating tapes or heat-shrinkable tubes. Flat washers and spring washers are securely and closely mounted on wiring terminals.

(2)

4. Check the connectors and


wiring terminals of power cables and PGND cables. (3)

Pass Fail Not Run Zapped

(1)

5. Check the layout of power


cables and PGND cables.

The power cables and PGND cables are bundled separately from other cables. The redundant part of the power cables or PGND cables are trimmed rather than coiled.

Pass Fail Not Run Zapped

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 10

6. Check the Grounding


Connection to Earth Bus bar

Grounding Cable for Cabinet shall be properly terminated to Earthing Bus bar. End to End connectivity of grounding cable to Bus bar to Earthing pit shall be verified.

Pass Fail Not Run Zapped

T01-0402 Installation of Trunk Cables and Signal Cables


Objective: Verify that the installation of trunk cables and signal cables complies with the corresponding engineering specifications. Result: PassFailNot RunZapped Comment & Remark

Prerequisites

The trunk cables and signal cables are installed. Procedure Expected result (1) The connectors of trunk cables are intact. The connectors of E1 cable are reliable and intact. Result Pass Fail Not Run Zapped

Check the trunk cables. Connector Bending Check the cables on the cable rack.

The cables on the cable rack are bundled together tightly. The cables are routed orderly and neatly with cable ties at even internals and to proper tightness.

Pass Fail Not Run Zapped

Check the cable labels.

Both ends of trunk cables are attached with standard engineering labels to identify the position of the cables. The labels are correct and clear. The connectors of the RF cables are fixed in position to avoid false connection that may cause an abnormal voltage standing wave

Pass Fail Not Run Zapped

Check the installation and cabling of RF cables.

Pass Fail Not Run Zapped

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 11

ratio (VSWR). The RF cables are intact. The horizontal RF cables are clamped into the cable trough. Check the power cables. The power cable of each module is securely connected to the power socket. The screws are fastened. Cables with an extra length are reserved at the connectors of the power cables. Check the CPRI cable. Check the connection at both ends of the CPRI cable. All the CPRI cables are neatly bundled with cable ties at even intervals, to proper tightness, and in the same direction. An appropriate margin of the CPRI cable is reserved at the CPRI connector, which facilitates maintenance. Check the installation of indoor jumpers. Check the environment monitoring cables. The indoor 1/2 inch jumpers for different layers and sectors are laid separately. The environment monitoring cables are securely and neatly installed. Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped

Pass Fail Not Run Zapped

Huawei Representative Name:_____________________ Signature:__________________

PTML Representative Name:_____________________ Signature:__________________

Date:______________________

Date:______________________

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 12

T02 Power-On Test


T02-01 Running Test
T02-0101 Board Indicators
Objective: Verify that the LEDs on each board work properly. Result: PassFailNot RunZapped Comment & Remark: (1) (2) Pay attention to the status of LEDs on the GTMU, DRFU/GRFU, FMU, GATM, and PSU when the BTS is powered on or reset. For more information about board LEDs, see the BTS3900 GSM Product Description.

Prerequisites The BTS is being powered on or is running. Procedure Check the board LEDs. Running State Expected result The board LEDs indicate the running status of boards. For example, the generation and clearance of alarms are indicated by the board LEDs exactly and in time during power-on and loading. The LEDs are in normal state when the boards operate properly. Result

Pass Fail Not Run Zapped

Huawei Representative Name:_____________________ Signature:__________________

PTML Representative Name:_____________________ Signature:__________________

Date:______________________

Date:______________________

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 13

Part II: ON-LINE TEST

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 14

T01 Service Items


T01-01 BCCH Mutual Help
Objective: Verify that the BSC supports BCCH mutual help. Result: PassFailNot RunZapped Comment & Remark:

Prerequisites The local site management right must be released before the test. The cell has been in service for over 15 minutes. Procedure 1. Power off the TRX where the BCCH of the cell resides in, triggering the process of primary BCCH mutual help. Lock the BCCH TRX of the cell by remote NOC RADIO, triggering the process of primary BCCH mutual help. Expected result After five minutes later, the cell reinitializes. The channel state on the Site Maintenance System shows that the timeslot 0 of a TRX (not the primary BCCH TRX in the initial configuration) becomes the primary BCCH channel.

2.

Use the test MS in the cell to originate a call.

The

calls

are

originated

successfully,

and

the

communication is normal.

3.

Repeat the step 1-2 to test next cell

The

calls

are

originated

successfully,

and

the

communication is normal.

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 15

Cell No. Cell1 Cell2 Cell3

BCCH Mutual active

Result Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped

T02 O&M Function Acceptance Items


T02-01 Logging In to the Site Maintenance Terminal System
Objective: Verify that users can log in to the BTS3900 LMT and perform operations system. Result: PassFailNot RunZapped Comment & Remark:

The IP address connected to the BTS through a crossover cable . The default password for you to log in to the Site Maintenance Terminal System is NOC (lower case).

Prerequisites

The BTS system is running properly. You have obtained the user name and password for login. Procedure Expected result The user logs in to the BTS3900 LMT successfully and can perform the management and maintenance operations related to the BTS.

1. Start the BTS3900 LMT. 2. Enter the user name and password. 3. Enter the IP address of the BTS3900. 4. Set User Type to Local User. Click OK..

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 16

T02-02 Site Reset in Levels


Objective: Verify that the BTS can be reset in levels on the BTS3900 LMT. Result: PassFailNot RunZapped Comment & Remark:

During initialization after reset, you cannot perform any operations on the BTS. The level 3BTS reset loads the configuration data instead of program during initialization.

Prerequisites

The BTS system is running properly. The BSC6900 is running properly. Procedure Expected result (1) (2) (3) (4) The Reset BTS in Levels dialog box is displayed. After a moment, the system displays a message indicating the successful reset. The Reset BTS in Levels dialog box is displayed. After a moment, the system displays a message indicating the successful reset.

1.

On the BTS3900 LMT, right-click the site name for acceptance in Management Tree, and then choose Reset BTS in Levels from the shortcut menu. Select Level 3, and then click Reset. On the BTS3900 LMT, right-click the site name for acceptance in Management Tree, and then choose Reset BTS in Levels from the shortcut menu. Select Level 4, and then click Reset.

2. 3.

4.

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 17

T02-03 Channel Status Check


Objective: Verify that the channel check can be performed on the BTS3900 LMT. Result: PassFailNot RunZapped Comment & Remark:

Prerequisites 1. 2. The BTS system is running properly. The DRFU/GRFU to be tested is running properly. Procedure 1. On the BTS3900 LMT, right-click the TRX, and then choose Monitor Channel status from the shortcut menu. Make a call on the TRX, and check the Monitor Channel Status dialog box at the same time. (1) Expected result The Monitor Channel Status dialog box is displayed, showing the type and status of each channel. The idle channel is white, and the used channel is green.

2.

(2)

T02-04 Board Operation


Objective: Verify that the board-related operations can be performed on theBTS3900 LMT. Result: PassFailNot RunZapped Comment & Remark:

Prerequisites

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 18

The BTS system is running properly. The DRFU/GRFU to be tested is running properly. Procedure Expected result (1) (2) (3) (4) The shortcut menu is displayed. The Reset Board dialog box is displayed. The configuration is successful. A message is displayed, indicating that the reset is successful.

1. (1) (2) (3) (4)

Reset a board. Choose BTS Maintenance>Maintain Board. Choose Reset Board. Specify the parameters Site, Subrack, and Slot. Click Reset.

2. (1) (2) (3) (4)

Query the information of a board. Choose BTS Maintenance>Maintain Board. Choose Query Board Information. Specify the parameters Site, Subrack, and Slot. Click Query.

(1) (2) (3) (4)

The shortcut menu is displayed. The Query Board Information dialog box is displayed. The configuration is successful. A message is displayed, indicating the successful query.

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 19

T02-05 BTS Alarms


T02-0501 External alarm
Objective: Verify that all external alarms can be reported to NOC normally. Result: Pass Fail Not Run Zapped

Comment & Remark: There are 16 external environment alarms on site. All of alarms are Boolean values. If the alarm appears, the alarm can be displayed normally on NOC. When the alarm recovers, the corresponding alarm will disappear on NOC. Procedure Check the Intruder alarm Expected result Intruder sensor properly installed & terminated till BTS. Open & close BTS Room Door to generate & clear the intruder alarm respectively & verify from NOC RADIO Check the Fire Panel alarm Fire Panel properly installed & terminated till BTS. As a precaution, the Gas Activation Switch is switched off and after the activity changed back to ON. Open the main equipment rooms AC Distribution Box and turn the MCB for the Fire Panel Alarm to the "OFF" position. After few seconds an audible alarm should be heard from the Fire Alarm Panel. Check with NOC-R that they can see this alarm. In the AC Distribution Box switch ON the Fire Alarm Panel MCB. Check with the NOC-R that the alarm has gone. Check the Smoke Smoke sensors are properly installed & Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Result

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 20

Detector alarm

terminated till BTS. As a precaution, the Gas Activation Switch is switched off and after the activity changed back to ON. Open the Fire Alarm Control Panel front cover. Pull down the fire alarm "Pull Down Switch" located on the Equipment Room Wall, the Fire Alarm Bell should start to ring. Silence the bell with the "Silence Bell" soft key located on the Fire Alarm Control Panel. Check with the NOC-R that they can see this alarm. Reset the Fire Alarm Control Panel by pressing the "Reset Alarm" soft key on the Fire Alarm Control Panel. Check with the NOC-R that the alarm has gone. Close the Fire Alarm Control Panel front cover.

Check the Over temp alarm

Over temp sensor properly installed & terminated till BTS. On A/C Panel, Set the over temperature threshold below 28 C. Over Temperature alarm will be reported at the NOC RADIO. Verify from NOC RADIO & set over temperature threshold back to 28 C. Pass Fail Not Run Zapped

Check the Humidity alarm

Humidity sensor properly installed & terminated till BTS. Locate the Humidity Sensor, which is installed on one of the Equipment Room Walls. Set the humidity upper limit at 20% with NOC RADIO. After few seconds, Check with NOC-R that they can see this Pass Fail Not Run Zapped

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 21

alarm. Set the humidity upper limit back to 85%, Check with the NOC-R that the alarm has gone. Check the Water leakage alarm Water leakage sensor properly installed & terminated till BTS. Locate the Water Leakage Sensor, located on one of the Equipment Room Walls at floor level. Immerse the Water Leakage Sensor into water. After few seconds, Check with NOC-R that they can see this alarm. Take out the Water Leakage Sensor from the water, Check with the NOC-R that the alarm has gone. Check the Gas release alarm FSS properly installed & terminated till BTS. As a precaution, the Gas Activation Switch is switched off and after the activity changed back to ON. The Test will be done by using LOOP Test Method. Remove the [Jumper] cables of Gas Released on EMU, the alarm of Gas Released will be reported to NOC RADIO. Reconnect the [Jumper] cables; the alarm should be cleared in NOC RADIO Check the Generator Running alarm Open the Main Switch DB in Genset Room. Disconnect the WAPDA supply from the Main Switch. Genset will be started. Generator Running alarm will be reported at the NOC RADIO. Verify from NOC RADIO & Switch ON the MCB. Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 22

Check the Tower light alarm

Tower light sensor properly installed & terminated till BTS. Cover the sun switch with a cloth. Tower lights will turn on. Now remove one bulb from the holder & Tower light failure alarm will be reported at NOC RADIO. Clear the alarm once bulb is installed back & verify from NOC RADIO. Pass Fail Not Run Zapped

Check Air Conditioner Failure Alarm

Air Con Panel properly installed & terminated till BTS. Alarm to be actuated when both Air Conditioners are operating Pass Fail Not Run Zapped

Check Mains Failure Alarm

Alarm to be actuated when Input Commercial Supply for Rectifier has suspended / failed Pass Fail Not Run Zapped

Check Low Battery Voltage alarm Check the Rectifier Major alarm Check the Rectifier Minor Alarm Check the Generator Failure alarm

Alarm to be actuated when Battery Bank discharge voltage <= 49 volts No: of Rectifier modules having faults=>1, Condition: Alarm to be actuated when lightning surge has affected the system Open the Main Switch DB in Genset Room. Disconnect the WAPDA supply from the Main Switch. Genset will be started. Wait for consistent response of the Genset, for some time. Locate the Output Switch on the Front Panel of Genset. Change the Output Switch to OFF position. The Output supply of the Genset will be disconnected. The alarm of Generator Failure (Alarm 15) will be reported in

Pass Fail Not Run Zapped

Pass Fail Not Run Zapped

Pass Fail Not Run Zapped

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 23

NOC RADIO. Change the position of Output Switch to ON position. The supply of Genset will be again commenced. Reconnect the WAPDA supply by changing position of Main Switch to ON position.

Check the Gen Low Fuel alarm

Take the fuel float with the cover out of the tank. Check with NOC-R that they can see this alarm. At the fuel float with cover inserted to the tank. Check with the NOC-R that the alarm has gone. Pass Fail Not Run Zapped

Huawei Representative Name:_____________________ Signature:__________________

PTML Representative Name:_____________________ Signature:__________________

Date:______________________

Date:______________________

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 24

T02-06 RF Specifications
T02-0601 VSWR of the Antenna System
Objective: Verify that the antenna VSWR complies with the corresponding engineering specifications. Result: PassFailNot RunZapped Comment & Remark: The VSWR of each feeder must be no more than 1.3 (without combiner) The VSWR of each feeder must be no more than 1.4 (with combiner) For Swap Scope:
If the DTF exceeds newly installed jumper length then rectification of VSWR is not in swap scope. Rectification if required will be till feeder jumper connector near BTS end..

It is recommended that the site Master (ANRITSU, BIRD and PORTEK) is the instrument for VSWR test. Note:
If the DTF exceeds newly installed BTS jumper/connector length then rectification of VSWR is not in Huawei swap scope

Prerequisites 1. 2. The BTS system works normally. The antenna test device is available. Procedure A 1. Power off all the DRFU/GRFUs in the test cell. Disconnect the feeder from the BTS and connect the feeder to the antenna test device. Record the measured VSWR into Attached Table 1 of Part 4 Acceptance Result. Measure the VSWRs of all the components in the antenna system by using the preceding method. Restore the original connections after the test. We can check the VSWR of newly installed jumpers by setting distance to fault location at maximum of jumper length (i.e. maximum up to 3m or depend on Expected result (1) The connection between the feeder and the device is proper. Antenna system is not more than 1.3 (without Combiner) normally. But for the sites which with shorter feeder (less than 20 M) or the site with combiner, the VSWR should no more than 1.4 (With Combiner). (2) The test result is the same as that in step 2. (3) VSWR value is very near to 1.0 and show ideal value.

2. 3.

4.

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 25

used jumper length). 5. VSWR of newly installed jumper can be checked by connecting the dummy load at terminal end of newly installed jumper. In this case distance to fault location range is not matter what it is set.

Antenna VSWR Test result: Cell Feeder Cell1A Cell1B Cell1C Cell1 Cell1D Cell1E Cell1F Cell2A Cell2B Cell2C Cell2 Cell2D Cell2E Cell2F Cell3A Cell3B Cell3 Cell3C Cell3D Cell3E ATP Document HUAWEI BTS3900 Base Station (SWAP) Pass Pass Pass Pass Pass Pass Pass Pass Fail Fail Fail Fail Fail Fail Fail Fail Pass Pass Pass Pass Pass Pass Fail Fail Fail Fail Fail Fail VSWR Pass Pass Pass Result Fail Fail Fail

Ufone/Technical/ANO/DOC/05/00

Page 26

Cell3F

Pass

Fail

T02-0602 DRFU/GRFU Transmit Power

Objective: Verify that the actual transmit power of the DRFUs/GRFUs meets the requirements. Result: PassFailNot RunZapped

Prerequisites

The BTS operates normally, and the calls of the DRFUs/GRFUs are normal. After BSC6000 up gradation to BSC6900, as per Huawei GTAC solution DRFU/GRFUs should be reset before TRX transmit power testing. The reason why the DRFU/GRFU is given a reset is because during the normal operation only the timeslots that are active have the power amplifier enabled as per the power saving feature. So when the transceiver is given a rest the time slots get idle and a burst is transmitted on all the time slots in order to exploit a DRFUs full power transmit capability. Procedure A Expected result

1.

Measure the transmit power by Power meter.

As per ETSI EN 300 910 V7.4.0 (European Standard Telecommunication Series) The tolerance of the actual maximum output power of the BTS shall be 2 dB under normal conditions and 2,5 dB under

DRFU BAND Carrier TYPE DRFU DRFU Coupling System No combining Combining ToC Output Power(W) 45W 20W ToC Output Power(dBm) 46.53 43.01 Power Output Range(Normal) 2.0 dB 44.53 ~ 48.53 41.01 ~ 45.01 Power Output Range(Extreme) 2.5 dB 44.03 ~ 49.03 40.51 ~ 45.51

900M 900M

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 27

1800M 1800M

DRFU DRFU

No combining Combining

40W 18W

46.02 42.55

44.02 ~ 48.02 40.55 ~ 44.55

43.52 ~ 48.52 40.05 ~ 45.05

GRFU BAND Carrier TYPE GRFU Coupling System No combining ToC Output Power(W) 31W ToC Output Power(dBm) 45.26 Power Output Range(Normal) 2.0 dB 43.26 ~ 47.26 Power Output Range(Extreme) 2.5 dB 42.76 ~ 47.76

900M

900M 1800M

GRFU GRFU

Combining No combining

27W 31W

44.27 46.30

40.27 ~ 46.27 44.30~ 48.30

41.77 ~ 46.77 43.80~ 48.80

1800M

GRFU

Combining

27W

42.60

40.60~ 44.60

40.10~ 45.10

TRX No. 0 1 2 3 4 5 6 7

Measured value ( ( ( ( ( ( ( ( )dBm )dBm )dBm )dBm )dBm )dBm )dBm )dBm

Result Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 28

TRX No. 8 9 10 11 24 25 26 27 28 29

Measured value ( ( ( ( ( ( ( ( ( ( )dBm )dBm )dBm )dBm )dBm )dBm )dBm )dBm )dBm )dBm

Result Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped Pass Fail Not Run Zapped

Huawei Representative Name:_____________________ Signature:__________________

PTML Representative Name:_____________________ Signature:__________________

Date:______________________

Date:______________________

ATP Document HUAWEI BTS3900 Base Station (SWAP)

Ufone/Technical/ANO/DOC/05/00

Page 29