Marginal Field Development Concepts (Compatibility Mode)
Marginal Field Development Concepts (Compatibility Mode)
Structural concepts for minimum facility platforms for Marginal field development in western offshore, India A collaborative project By IIT Madras and IEOT,ONGC
24 April 2007
1 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
Outline
Conventional Wellhead Platforms Existing Marginal platforms Minimum Facility Platforms Basic Requirements Environmental Conditions Installation by Jackups Concepts Technical Feasibility Cost Comparison Conclusions
11/19/2012
B-15
B-55
S HG
B-188
2170000
B-48 B-46
SBM
NQO BHN
B-157# B-59
" 16
77
km
5 to B-5
B-127
2160000
2150000
MUMBAI HIGH
WO-24 ICW BHS
BHE-1
2140000
B-45
2130000
SH B-149 B-147
36" X 23 1 km Gas trunk 42" line X 24 Bass 4 km ein Gas to H trunk azira line BPB to H azira
BPA
BS-13 BS-16
B-192
2120000
28"
X 78 km
B-22# BPB
SH BPB Line
30 "
B-121/119
2110000
30 "
BS-12
BASSEIN
##
B-80
X 14 2 km SH P -H
WO-5
2100000
B-178 B-23A
EE RA
## B-193 B-28 ##
B-173A# B-179
##
WO-15
2090000
WO-16 D-33
2080000
##
B-180
Lin e
##
INDEX
D-1
D-18
2060000
18 " oi l an dg as
NEELAM
e nk lin ran to U to Ur an
# ##
24"
tru Oil
20 km
790000
30 km
800000
40 km
810000 820000
HEERA
830000 840000
G 26"
as tru
e nk lin
710000
720000
730000
740000
750000
760000
770000
850000
860000
11/19/2012
Combinations of 54 SKIRT WITH 48 MAIN PILE 54 SKIRT WITH 54 MAIN PILE 60 SKIRT WITH 54 MAIN PILE
Skirt Piles of 84 SKIRT WITH 48 LEG 84 SKIRT WITH 60 LEG FULL BRACING 84 SKIRT WITH 60 LEG
4 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
UK
5 11/19/2012
Norway
Australia
PROPOSED CONCEPTS FOR WESTERN OFFSHORE Mono Pile Concepts Jacket Type Concepts
11/19/2012
1(a)
1(b)
1(c)
Braced Mono Tower (Inside Conductor) Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
2(a)
2(b)
2(c)
3 (a)
3 (b)
The slender structure as proposed earlier are transversely supported by guy wires to reduce lateral deflection and bending stresses. Further the support reaction in terms of pile loads will be reduced considerably.
10 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
24 April 2007
50%
Limiting Parameters
Access to wells for drilling by jackup from north face, the skirt piles or projection of substructure on the north face to be avoided. The soil conditions and environmental parameters in shallow water is substantially different from conditions exist in many other parts of world Large deflection shall be avoided as the platform supports well heads. Dynamics of the slender platform shall be kept in mind to avoid resonant vibrations and subsequent fatigue related issues. Installation robustness to avoid delay in projects during execution
24 April 2007
13 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
24 April 2007
14 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
REPRESENTATIVE SITE
Environmental conditions at C-series location has been considered for this study. The location selected has some of the difficult parameters to be used in design such as wave, current and geotechnical conditions. Similar conditions are expected at other marginal field. It can be observed that the top 30m is a soft clay offering very les pile capacity.
Parameter Wave height (m) Wave period (sec) Surface current(m/sec) Water depth (m) Wind speed (km/h) (1-hr.Avg) 15 1 year return 10.366 10.4 1.341 30 77 100 year return 17.073 13.90 1.768 30 138
11/19/2012
16
11/19/2012
17
11/19/2012
Concepts for Marginal Field Development Western Offshore Mono Pile without Guy Wire
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight
: 750 Tonnes : 330 Tonnes : Crane Vessel : Crane Barge : 1 Main Pile : 142 : 80m : 350 Tonnes : 1430 Tonnes : 6 Days : US$ 16M
18
11/19/2012
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight Estimated Total Weight Estimated Offshore Time Estimated Cost Risk
: 750 Tonnes : 370 Tonnes : Crane Vessel : Crane Barge : 1 Main & 2 Skirt Piles : 142 (Main) : 60 (Skirt) : 80m : 630 Tonnes : 1750 Tonnes : 12 Days : US$ 22M
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight Estimated Total Weight Estimated Offshore Time Estimated Cost Risk
: 750 Tonnes : 300 Tonnes : Crane Vessel : Crane Barge : 1 Main & 2 Skirt Piles : 60 : 80m : 470 Tonnes : 1520 Tonnes : 12 Days : US$ 21M
10
Concepts for Marginal Field Development Western Offshore 4 Legged Jacket Structure
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight
: 750 Tonnes : 460 Tonnes : Crane Vessel : Crane Barge : 4 Main Piles : 60 : 80m : 640 Tonnes : 1850 Tonnes : 15 Days : US$ 25M
21
11/19/2012
Concepts for Marginal Field Development Western Offshore 4 Legged Jacket Structure with Batter piles
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight
: 750 Tonnes : 490 Tonnes : Crane Vessel : Crane Barge : 4 Main Piles : 60 : 80m : 640 Tonnes : 1880 Tonnes : 15 Days : US$ 25M
Estimated Total Weight Estimated Offshore Time Estimated Cost Risk Level
: No major issues
22
11/19/2012
11
Concepts for Marginal Field Development Western Offshore 3 Legged Jacket Structure
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight
: 750 Tonnes : 350 Tonnes : Crane Vessel : Crane Barge : 3 Main Piles : 60 : 88m : 510 Tonnes : 1610 Tonnes : 15 Days : US$ 23M
Estimated Total Weight Estimated Offshore Time Estimated Cost Risk Level
23
11/19/2012
Concepts for Marginal Field Development Western Offshore Braced Leg Jacket (4 Piles)
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight Estimated Total Weight Estimated Offshore Time Estimated Cost
Risk Level
: 750 Tonnes : 500 Tonnes : Crane Vessel : Crane Barge : 4 Skirt Piles : 60 : 77m : 530 Tonnes : 1780 Tonnes : 15 Days : US$ 24M
Critical fatigue Joint
: Conductor legs exposed for damage MSF is required Fatigue at brace junction
Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
24
11/19/2012
12
Concepts for Marginal Field Development Western Offshore Braced Leg Jacket (3 Piles)
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight Estimated Total Weight Estimated Offshore Time Estimated Cost
Risk Level
: 750 Tonnes : 450 Tonnes : Crane Vessel : Crane Barge : 3 Skirt Piles : 60 : 77m : 400 Tonnes : 1600 Tonnes : 12 Days : US$ 21M
: Conductor legs exposed for damage MSF is required Fatigue at brace junction Large pullout loads on south pile
25 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
Topside Weight Jacket Weight Caisson Weight Installation Offshore Work Estimated Total Weight Estimated Offshore Time Estimated Cost
Risks
: 750 Tonnes : 440 Tonnes : 400 Tonnes : Crane Vessel : Crane Barge : 1590 Tonnes : 18 Days : US$ 25M
4 Legged Jacket with Hollow Base Steel Caisson (with Guy Wire)
: Installation of guy systems Installation of large caisson Damage to guy wires Approach by boat Large anchor forces
26
11/19/2012
13
Topside Weight Jacket Weight Caisson Weight Installation Offshore Work Estimated Total Weight Estimated Offshore Time Estimated Cost
Risks
: 750 Tonnes : 480 Tonnes : 250 Tonnes : Crane Vessel : Crane Barge : 1480 Tonnes : 18 Days : US$ 24M
4 Legged Jacket with Steel Caisson with Each Legs (with Guy Wire)
: Installation of guy systems Damage to guy wires Approach by boat Large anchor forces
27
11/19/2012
Concepts for Marginal Field Development Western Offshore Mono Pile with Guy Wire
Topside Weight Jacket Weight Installation Offshore Work Number of piles Pile Diameter Penetration Pile Weight Estimated Total Weight Estimated Offshore Time Estimated Cost
Risk
: 750 Tonnes : 330 Tonnes : Crane Vessel : Crane Barge : 1 Main Pile : 142 : 80m : 350 Tonnes : 1430 Tonnes : 15 Days : US$ 22M
: Installation of guy systems Damage to guy wires Approach by boat Large anchor forces
28 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
14
Weight Comparison
S. No 1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c Mono pile Braced Mono tower (Inside Conductor) Braced Mono tower (Outside Conductor) 4 Legged Jacket Structure 4 Legged Jacket Structure with Batter Piles 3 Legged Jacket Structure Braced Legs (4 piles) Braced Legs (3 piles) 4 Legged Jacket with Hollow Base Steel Caisson (Guy Wire) 4 Legged Jacket with Steel Caisson with Each Legs (Guy wire) Mono pile with Guywire Description Jacket (MT) 330 370 300 460 490 350 500 450 440 480 330 Pile (MT) 350 630 470 640 640 510 530 400 400 250 350 Total (MT) 680 1000 770 1100 1130 860 1030 850 840 730 680 Recommendation Feasible for 1-2 conductors Recommended Recommended with large diameter mono pile Recommended Recommended Not Recommended Recommended Not Recommended Not Recommended Not Recommended Not Recommended
Variation of weight among the concepts is limited to 10 to 20% except for mono pile
29 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
Jacket concepts
Braced conductors
30
11/19/2012
15
Technical Feasibility Design of Mono pile and braced mono pile system has limitations on the deck foot print size. The concept can be adopted if the topside dimensions can be limited to less than 20m x 20m. Braced conductor leg concept can be implemented with sufficient conductor protection system which may alleviate the safety issue. The limitations on the deck foot print applies to this option also. Guy support structures require pile foundations for wire anchor system which will be costly. Further, guyed wire support systems not recommended based on installation and safety issues due to potential failure of guy wires. Hence an optimized conventional jacket will prove to be a potential candidate both in terms of safety and installation even though cost is slightly higher. Installation by jackup rigs shall be considered carefully only for water depths less than 30m.
31 11/19/2012 Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
Conclusions Mono pile with braced skirt pile system offers economical solution and can be installed by small derrick or pipe lay barge as the weight of each component is less than 650 Tonnes. Hence this can be implemented in upcoming marginal fields with water depth not exceeding 50m.
For other marginal fields where water depth is greater than 50m, optimized jacket concepts are recommended.
Braced conductor legs can be used with sufficient leg protection and fatigue design.
Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology Madras-36
32
11/19/2012
16
Thank you
33
11/19/2012
Options 1a 1b 1c 2a 2b 2c 3a 3b 4a 4b 4c
17