Construction of 168 Units Type III T/S Quarters at NMDC Bacheli DAILY SITE REPORT FOR SITE NO. I & II Dated- 20-Jan-12
WORK MEN DETAILS
REJA 25 0 18 27 0 7 COOLIE 12 0 2 3 0 5 MASON 0 4 0 0 CENTRING MISTRI CENTRING HELPER 0 16 12 7 1 16 7 9 SUPERVISOR As per attendance 1 1 0 OTHERS 0 1 0 0 TOTAL 38 0 58 50 16 12 REMARKS
Co's side, de watering, cleaning of slurry, raft rcc, road cleaning, boulder loading & breaking, sand boulder filling.
20-Jan-12
Sr No. 1 2 3 4 5 6 7 8 REMARK 4 hrs Plinth filling at bl-14, loading of soil for shifting, metal loading & misc works local shifting of soil, cement, boulders etc idle metal & soil shifting local at bl-07 at bl-06 Other details No. of trips 1 2 2 1 2 REMARK For co's mixure machine 3 4 5 6 7 8 9 9 10 11 12 13 14 15 16 A 0 Sr. No
Name of Staff & Designation Sunil Kulkarni (Proj. Mgr) Kailash Wakode (Engr) Pranav Patel (Engr) Prahlad Sharma (Works Mgr) P. L. Khande (Supervisor) N. Kumar (Supervisor) Raju Chapadi (Supervisor) Mukesh Bhaskar (Supervisor) (on leave since 24th Dec) Gautam Srivastav (Tract. Driv) Bhola Nag (Dumper Driv) Moti Ram More (Office Boy) Damyanti Bai (Cook) Night Watchmen, Idea Sec (1st Site) Night Watchmen, Idea Sec (2nd Site) Sushant (RM800 Operator) J. P. Wahane (Engr.) P 15 TODAYS Expences with balance Particulars NMDC BACHELI SITE B/f Photocopy & courior mess expences Data card recharge 29448 E 0 DR
Attendance P P P P L P P P P P P P P P P P L 1 20-Jan-12 CR
Electrical shutdown
Dept. (Brick making team) SSM Engineers (Murty/Madhav Rao) Shashikant Kanwar Tulsi Dass (Shuttering/centering team) Ramesh Agrawal (Brick making team)
MACHINERY DETAILS
TYPE OF MACHINE EX-110 Tractor Mixure RM-800 Dumper 2207 5 HP Diesel pump 2 HP elect pump Sleep No issued by us 8680 8681, 83 8679, 82 START READING 35.5 1447.7 75427 END READING 45.7 1447.7 75433 TOTAL RUNNING 10.2 0 6 5 hrs 5 hrs QTY (Cft) 300 2x308 2x308 Time of Unloading 11.2 12.30, 18 10.50, 17.15 VEHICLE DIMENSION 14.6x8x2.7 14.6x7.6x2.10 14.6x7.6x2.10 HSD ISSUED READING AT TIME OF ISSUE 26.9 Hr Mtr not working
Metal 20 mm (G) Durga st. cru. Sand Sand P.D. Sing P.D. Sing
50 191 98
SUPPLIER
*petrolium
QTY 1ltr
SIZE
VEHICLE DIMENSION
VEHICLE NO.
WORK DETAILS
NO'S QUANTITY 100 0 15 13.94 5 TARGETED 100 0 20 15 5 Required for the project 88288 834.48 48410
ACTUAL ACHIEVED
100 0 15 13.94 5
REMARKS At bl- 14 for 6 rafts at bl-07 5th fl at bl-01, 4 rafts at bl-06, 12 col at bl-09, 6 col & 11 caps at bl-11 for 6 rafts at bl-07
29448 29109
339
REQUIREMENT
ITEM
Curing pipe 1/2 inch Sprinkler with stand
STOCK POSITION
Details of material CEMENT Bag STEEL (MT) METAL 40 MM (Cft) METAL 20 MM Granite (Cft) METAL 20 MM Regular (Cft) METAL 12 MM (Cft) SAND (Cft) CC BRICKS NOS Boulders(cft) Upto date Qty 16200 273.34 17850 22110 197951 59318 53640 157700 340000 70000 24075 115018 17432 6650 9008 15015 36614 17796 1750 0.00 0.00 1232 66 0 9008 15015 37846 17862 1750 443 16 1137 0 378 8565 14999 36709 17862 1372.44 5 Total OPENING 377 50.53 1561 6005 RECEIVED 0 0.00 0.00 300.00 TOTAL 377 50.53 1561 6305.30 CONSUMPTION 99 0.60 159 BALANCE 278 49.93 1402 6305.30 Sr No. 1 2 3 4
HSD DETAILS Particulars Purchased Ex-110 diesel pump+mixure machine+vibrator 0+3+0 Tractor 4 Balance 0 4 4 Opening balance 4 Issued qty
QTY
4 bundle 3 nos
concrete breaker
Bl-01 : SF slab shuttering in prog. Bl-02 : Yet to start. Bl-03 :plinth complete, backfilling in prog. Bl-04 : Gf slab casting done on 8th Jan 12.
Bl-05 : GF slab complete, ff columns complete. Bl-06 : pb compl for 2 unit, col started, sand/boulder filling/PCC/ rafts started for remaining 2 units. Bl-07 : Excavn done for 2 units, sand/boulder filling / PCC started. Bl-08 : Filling upto pl bot in prog. Bl-09 : Plinth Beam complete, columns started.
Bl-10 : Ff slab casting done on 19th Jan. Bl-11 : Ff col in progress. Bl-12 : Shuttering for GF slab in progress. Bl-13 :col for gf complete. Bl-14 :Plinth beams complete, plinth filling in prog.
Out of 42 slabs, 7 slabs complete, 2 are sure in this month, backlog will be of 1 slab as per planning.