Lift Shaft
Lift Shaft
For the construction of lift core walls , a combination of L&T wall formwork system with lift shaft system for supporting internal shutters and Travelling climbing system for External shutters is suggested This gives the advantage of a faster progress for lift cores without waiting for the floor slab to complete
With the suggested methodology, the lift core walls can progress ahead independent of the slab casting
Typical section of a lift core wall showing inside and outside shutters with supporting platform arrangement
Formwork details:
L&T Wall formwork with Travelling climbing system (CB 150F) used for Outer face of core wall. L&T Lift shaft platform system used with wall formwork for Inner face / opening. Outer shutter panels are supported on a pair of brackets. Each pair of shutter panel with brackets having in-built safety such as necessary handrails for concreting & shutter platforms. Tower cranes used for lifting of shutters from one
SYSTEM DESCRIPTION: The lift shaft platform system is suitable for lift core / RC-walls close to each other. The Climbing Formwork System comprises of shaft main beam resting in pockets provided in the already cast RC-Wall. The cross beams are provided over this. Wooden planks over the cross beams form the lift shaft platform. Leveling of the platform is possible by operation of spindle within the gravity pawls. The main beam have gravity pawls which unlocks it self from the pockets when lifted upwards and lock itself at the next pocket location. The gravity pawls are hinged and have one way movement only, the platform thus has high levels of safety. The platform as a whole alongwith the main beam, gravity pawls, cross beams and platform can be lifted as one unit. This platform facilitates resting Crane of the wall formwork and alignment.
To be cast Lifting Bkt. To be cast Sling from
SALIENT FEATURES
Ideal system for speedy construction. Eliminates the need for scaffolding to support the Wall Formwork. High levels of safety - full proof system. Minimum skill & operation for anchoring & shuttering at each level.
Sling from Crane
Freshly cast
Details showing the arrangement of Lift shaft platform and shutters inside
VERTICAL WALER
ROLL BACK OF SHUTTERS SHIFTING OF PANEL TO NEXT LEVEL USING CRANE
Project: TSI Business Park At Hyderabad Contractor: M/s. Shapoorji Pallonji & Co Ltd.
L&T Formwork System is being used for the construction of the LIFT CORE WALLS
The total catered area is : 2 sets of lift core(typ floor) of phase I=1140 sqm 2 sets of lift core(typ floor) of phase II/III=1650 sqm The total catered area :2790 sqm
Structure details
Total number of lift core = 5 (Two in phase I, Two in phase-II and One in phase3) Thickness of wall 230mm (Inner) & 350 mm/500mm (Outer) Total number of vertical floors/ pours is 23 Pouring height per lift 4.00m (max.) The formwork is designed for: Design lateral concrete Pressure : 41.6 kN/Sq.m Allowable rate of pour :1.00 m /hour
Method statement
1. Casting of Starter with timber sides to suit wall dimensions. 2. Assembly of formwork: (For 1st Pour) 3.Removal of formwork (for 1st Pour) 4.Erection of Inside/outside platforms and erection of formwork for second/next lift and concreting 5. De-shuttering of formwork and transfer to next level along with platforms with the help of crane. Step 4&5 repeated till the entire structure is
Assembly of formwork: (For 1st Pour) 1. Placing of Shutter panel, check the line and level, then placing along the one side of the wall. 2. Inserting the Tierods upto other side wall surface covered by PVC pipe at the required locations (ie. As per scheme drawing & design calculations) 3. Placing of other side Shutter panel and check the edges with plumb, then placing other shutter panels continuously. 4. Extending the Tie rods and fixing with Anchor plate & wingnut. 5. Placing Alignment props / Supporting bracket with Head adapter assembly & Foot adapter assembly. 6. Joining the shutter panels together by Splices with Connecting pins. 7. Fixing of Timber spacers (for wall thickness) on the top between the shutter panels 8. Plumbing of shutters by using alignment struts / plumb bobs.,Checking the straight line/Checking the wall thickness at the top. 9. Universal inside corners and Universal outside fixing to be fixed according to the requirements of wall corners. 10.Stop anchors, Ties ,Anchor cones covered with PVC sleeves to be fixed for subsequent lift done for climbing system. Place the shaft pocket for shaft
LIFTING BRACKET
TIE SYSTEM
ALIGNMENT SYSTEM
PLAN