100% found this document useful (2 votes)
3K views

Lift Shaft

The document provides methodology for casting lift core walls using a combination of L&T wall formwork system and lift shaft platform system. This allows lift core walls to progress independently of floor slabs. The lift shaft platform system supports internal shutters and allows lifting of formwork to the next level. Formwork details and system description are provided along with salient features, typical sections, and step-by-step method statements for assembly, concreting, and dismantling/shifting formwork to the next level.

Uploaded by

vijking
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
3K views

Lift Shaft

The document provides methodology for casting lift core walls using a combination of L&T wall formwork system and lift shaft platform system. This allows lift core walls to progress independently of floor slabs. The lift shaft platform system supports internal shutters and allows lifting of formwork to the next level. Formwork details and system description are provided along with salient features, typical sections, and step-by-step method statements for assembly, concreting, and dismantling/shifting formwork to the next level.

Uploaded by

vijking
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 21

Methodology for Casting of Lift Core walls

For the construction of lift core walls , a combination of L&T wall formwork system with lift shaft system for supporting internal shutters and Travelling climbing system for External shutters is suggested This gives the advantage of a faster progress for lift cores without waiting for the floor slab to complete

With the suggested methodology, the lift core walls can progress ahead independent of the slab casting

Typical section of a lift core wall showing inside and outside shutters with supporting platform arrangement

Formwork details:
L&T Wall formwork with Travelling climbing system (CB 150F) used for Outer face of core wall. L&T Lift shaft platform system used with wall formwork for Inner face / opening. Outer shutter panels are supported on a pair of brackets. Each pair of shutter panel with brackets having in-built safety such as necessary handrails for concreting & shutter platforms. Tower cranes used for lifting of shutters from one

SYSTEM DESCRIPTION: The lift shaft platform system is suitable for lift core / RC-walls close to each other. The Climbing Formwork System comprises of shaft main beam resting in pockets provided in the already cast RC-Wall. The cross beams are provided over this. Wooden planks over the cross beams form the lift shaft platform. Leveling of the platform is possible by operation of spindle within the gravity pawls. The main beam have gravity pawls which unlocks it self from the pockets when lifted upwards and lock itself at the next pocket location. The gravity pawls are hinged and have one way movement only, the platform thus has high levels of safety. The platform as a whole alongwith the main beam, gravity pawls, cross beams and platform can be lifted as one unit. This platform facilitates resting Crane of the wall formwork and alignment.
To be cast Lifting Bkt. To be cast Sling from

SALIENT FEATURES
Ideal system for speedy construction. Eliminates the need for scaffolding to support the Wall Formwork. High levels of safety - full proof system. Minimum skill & operation for anchoring & shuttering at each level.
Sling from Crane

Pocket to suit Pawl

Freshly cast

Lift shaft platform resting in the pockets


Climbing Pawl Already Cast Wall Lift shaft Platform

Pocket to suit Pawl

Freshly cast Lift shaft Platform

Climbing Pawl Pocket to suit Pawl

Already Cast Wall

lift shaft platform being lifted to the next level

Details showing the arrangement of Lift shaft platform and shutters inside

VERTICAL WALER
ROLL BACK OF SHUTTERS SHIFTING OF PANEL TO NEXT LEVEL USING CRANE

Details showing the climbing system 150 F and shutters outside

Project: TSI Business Park At Hyderabad Contractor: M/s. Shapoorji Pallonji & Co Ltd.

L&T Formwork System is being used for the construction of the LIFT CORE WALLS

The total catered area is : 2 sets of lift core(typ floor) of phase I=1140 sqm 2 sets of lift core(typ floor) of phase II/III=1650 sqm The total catered area :2790 sqm

Structure details
Total number of lift core = 5 (Two in phase I, Two in phase-II and One in phase3) Thickness of wall 230mm (Inner) & 350 mm/500mm (Outer) Total number of vertical floors/ pours is 23 Pouring height per lift 4.00m (max.) The formwork is designed for: Design lateral concrete Pressure : 41.6 kN/Sq.m Allowable rate of pour :1.00 m /hour

Plan of Lift core wall shuttering for phase 1

Method statement
1. Casting of Starter with timber sides to suit wall dimensions. 2. Assembly of formwork: (For 1st Pour) 3.Removal of formwork (for 1st Pour) 4.Erection of Inside/outside platforms and erection of formwork for second/next lift and concreting 5. De-shuttering of formwork and transfer to next level along with platforms with the help of crane. Step 4&5 repeated till the entire structure is

Assembly of formwork: (For 1st Pour) 1. Placing of Shutter panel, check the line and level, then placing along the one side of the wall. 2. Inserting the Tierods upto other side wall surface covered by PVC pipe at the required locations (ie. As per scheme drawing & design calculations) 3. Placing of other side Shutter panel and check the edges with plumb, then placing other shutter panels continuously. 4. Extending the Tie rods and fixing with Anchor plate & wingnut. 5. Placing Alignment props / Supporting bracket with Head adapter assembly & Foot adapter assembly. 6. Joining the shutter panels together by Splices with Connecting pins. 7. Fixing of Timber spacers (for wall thickness) on the top between the shutter panels 8. Plumbing of shutters by using alignment struts / plumb bobs.,Checking the straight line/Checking the wall thickness at the top. 9. Universal inside corners and Universal outside fixing to be fixed according to the requirements of wall corners. 10.Stop anchors, Ties ,Anchor cones covered with PVC sleeves to be fixed for subsequent lift done for climbing system. Place the shaft pocket for shaft

Method statement ..contd

LIFTING BRACKET

WORKING PLATFORM STD. STEEL WALER H16 - BEAM

TIE SYSTEM

STEEL WALER H-BEAMS 12 MM THK PLY.


12 MM DENS PLY

ALIGNMENT SYSTEM

PLAN

C /S ELEVATION

WALL FORMWORK SYSTEM

Method statement ..contd


Removal of formwork: First removal of Tie rods, Alignment struts, accessories Removal of shutters (each separately) with the help of crane Cleaning and shifting of shutter panels (with alignment props / supporting brackets) to next lift / length.

Method statement ..contd


CB150F-making 1. After dismantling the shutters, remove anchor cone using DK spanner and fix climbing cone. 2. Climbing bracket 150F 2 nos (to suit stop anchor location which is already left in conc.) should be made as a set by bracing with NB 40 pipes and couplers. 3. Fix working platforms with ISMC runners and 2 thick planks. 4. Fix the Vertical waling (roler below the waler should sit over the bracket and scissor action spindle (in collapsed condition) with the help of Locking pins. 5. Brace the vertical walers properly with horizontal and Diagonal by NB 40 pipes & couplers. 6. Fix the vertical waler with Climbing bracket tightly with wedges to prevent movement. 7. Fix Handraill post on each bracket and hand railing at 2 levels should be done with NB 40 pipes & couplers.

Climbing system 150F with outside shutters

Method statement ..contd


CB150F/Lift shaft platforms erection 1 Lift the entire assembly of climbing bracket 150F (by putting the sling on the top of the vertical walers) with the help of crane and place over the climbing cone correctly. Lock the climbing bracket with the locking pin to arrest upward movement of bracket from climbing cone head. 2 Follow the procedures described in the assembly of wall formwork, however the alignment props to be removed. 3. Vertical walers should be connected with horizontal walers using waling to bracket holders. 4. Top leveling of shutters and adjustment of verticality done by adjusting the screws at the bottom of the vertical walers. Aligning of shutters should be done with Scissor action spindles. 5. Check the verticality of the shutter using plumb bob. 6. Make lift shaft platform at ground with climbing pawl. 7. Shift the platform with help of crane & place it where the pockets already provided.

Botom View of shaft platform inside

Lift shaft platform with inside shutters

Method statement ..contd


Dismantling and shifting to next level after concreting of typical pour Roll back the shutters from concrete face. Put the crane sling in the hook provided in the Vertical waler. Take out the locking pin in the climbing bracket, so that the climbing bracket can be free for lifting. Lift the entire assembly (including shutter panel and climbing bracket 150F assembly) and place it in next position. Remove Inner shutter panels & shift by crane to available place temporarily. (low level slab if any) Lift the Inner shaft platform to next higher level. This entire operation is repeated to complete the core wall Folded Dowel bars will be taken out by chipping & Bent to required position. Structural consultants should approve the slab casting & freestanding height of core walls.

You might also like