Chapter 10
Chapter 10
19kV
speed of operation is essentially instantaneous for all in-
CT1
zone faults. The CT ratio, polarity and connection must
58/23/35MVA all be correct in order for the correct operation of the
19/6.6/22kV
differential protection. Hence it is imperative that the
G
CT2 CT3 differential protection be commissioned before first time
19kV
250MW energization of the transformer. The article will share my
6.6kV 22kV
19kV primary CT1 - located at transformer
experience in the commissioning of a differential
6.6kV secondary CT2 - located at 6.6kV switchgear
22kV tertiary CT3 - located at 22kV switchgear protection for a three winding transformer at a power
FIGURE 10.1 : Single Line Diagram station as shown in Figure 10.1.
impedance between any pairs of windings with the third winding in open circuit. Therefore we will have:
Zps - impedance at primary with secondary short-circuit and Tertiary open circuit.
Zpt - impedance at primary with Tertiary short-circuit and secondary open circuit.
Zst - impedance at secondary with Tertiary short-circuit and primary open circuit.
Zps = Z p + Zs = 31%
Zpt = Z p + Zt = 19%
Zst = Z s + Zt = 62%
Zp = - 6% ; Zs = 37% ; Zt = 25%
J.M. PANG & SEAH PTE LTD 3
Commissioning
An external 3 phase, 400 volts diesel generator was connected at the 19kV side with three different
combinations of open/short circuit at the 6.6kV and 22kV.
The KVA rating of the external generator was calculated using the impedance data of the three
winding transformer of Table 10.1. The required KVA rating of the external generator for the three
different connections were ;
Percentage of
Connection KVA rating of Generator
Full Load Current
A 3 phase, 400 volts, 300KVA generator was selected for the commissioning test. The calculated
value of 416A at the 19kV winding is about 23% of the full load current and so considered high enough to
commission the differential protection relay. Table 10.2 is the summary of the measured values for Figure
10.3A, Figure 10.3B and Figure 10.3C under external fault conditions. Incorrect CT polarity at the 22kV CT
was suspected because ;
High value of differential current for the case of Figures 10.3B and 10.3C
The star point of the 22kV CT was reversed to rectify the incorrect CT polarity. Table 10.3 is the
summary of the measured values with the correct CT polarity. The differential protection was considered
stable for the out of zone fault because the differential current was zero. The short circuit at the 22kV side
was relocated to create an in-zone fault and the differential current was non-zero and of high value. The
differential relay was considered commissioned.
J.M. PANG & SEAH PTE LTD 4
Conclusion
In this case study, the polarity of the 22kV CT was incorrect and fortunately discovered during the
commissioning test. If such a commissioning test was not done, the differential relay will operate under
normal loading of the transformer, or during an external fault condition.
I red 91 mA 59 mA 197 mA
I blue 91 mA 59 mA 197 mA
In-Zone Fault In-Zone Fault In-Zone Fault Out Zone Fault Out Zone Fault Out Zone Fault
External Generator Short Circuit at Short Circuit at
Connected to 19kV Short Circuit Short Circuit Short Circuit at Short Circuit at
22kV and 6.6kV 6.6kV and 22kV
Side at 22kV at 6.6kV 22kV and 6.6kV 22kV and 6.6kV
Open Circuit Open Circuit
(Fig. 10.3C)
(Fig. 10.3B) (Fig. 10.3A)
I red 344A 344 A 344A 162A 105A 344A
400V 400V
3Ø Generator 3Ø Generator
~ ~
Ip i
Zp = -6% Z = 31%
400V 400V
3Ø Generator 3Ø Generator
~ ~
Ip i
Zp = -6% Z = 19%
400V 400V
3Ø Generator 3Ø Generator
~ ~
Ip i
Zp = -6% Z = 8.9%
i= 0.4 x Full load
Is It 0.089 x 19 Current
-- END --