Sap Sap
Sap Sap
S.No 1. 2. 3.
4.
CONSTANCE
PAGE NUMBER
3 5 11 15 18 19 19 20 23 24 28 45 46 50 51 52 54 56 57 59 61 62 63 68 75 76 79 80 82 87 88 91 97 108 111 116 117 121 123 124 125 126 127 130 130 131 132 133 139 141 145 147 147 147 148
INTRODUCTION TO CONTROLLING MAINTAIN CONTROLLING AREA MAINTAIN NUMBER RANGES FOR CONTROLLING DOCUMENTS AINTAIN VERSION PROFIT CENTER ACCOUNTING MAINTAIN CONTROLLING SETTING CREATION OF DUMMY PROFIT CENTER DEFINE PROFIT CENTER COST ELEMENT ACCOUNTING AUTOMATIC CREATION OF PRIMARY & SECONDARY COST ELEMENTS
5.
6.
7. 8.
9.
10. 11. CHANGE SECONDARY COST ELEMENT 12. DISPLAY COST ELEMENT INFORMATION
13. 14. 15. 16. 17. CREATION OF COST ELEMENT GROUP COST CENTER ACCOUNTING COST CENTER CATEGORY CREATION OF COST CENTER GROUP CREATION OF COST CENTER COST CENTER INFORMATION REPORT
44. 45. POST SENDER ACTIVITY 46. POSTING ACTUAL PRICE 47. ENTERING ACTUAL STATISTICAL KEY FIGURES 48. DEFINE ASSESSMENT CYCLE FOR ASSESSMENT METHOD 49. ACTUAL PRICE CALCULATION
50. INDIRECT ACTIVITY ALLOCATION 51. SPLITTING OF COST 52. COMMITMENT MANAGEMENT
FI/CO MATERIAL VERSION ECC 6.0 56. ASSIGH COMMITMENT ITEM TO G/L ACCOUNT 57. ENTER VALUE TO COMMITMENT ITEM 58. INTERNAL ORDERS
59. DEFINE ORDER TYPE 60. MAINTAIN SETTLEMENT
149 150 156 157 160 161 162 167 169 182 184 186 192 196 203 203 204 208 212 214 217 219 220 222 223 225 227 228 229 230 233 234 235 236 238 241 242 243 245 246 247 250
73. DEFINE COST COMPONENT STRUCTURE 74. COST ESTIMATE WITH QUANTITY STRUCTURE
75. PRICE UPDATE 76. COST OBJECT CONTROLLING DEFINE ORDER TYPE 77. DEFINE ORDER TYPE-DEPENDENT PARAMETERS 78. DEFINE CHECKING CONTROL 79. DEFINE SCHEDULING PARAMETERS FOR PRODUCTION ORDERS
80. DEFINE CONFIRMATION PARAMETERS 81. CHECK COSTING VARIANTS FOR MANUFACTURING ORDERS (PP) 82. DEFINE GOODS RECEIVED VALUATION FOR ORDER DELIVERY
83. DEFINE RESULTS ANALYSIS KEYS 84. DEFINE RESULTS ANALYSIS VERSIONS
85. DEFINE VALUATION METHOD (ACTUAL COSTS) 86. DEFINE LINE IDS
87. DEFINE ASSIGNMENT 88. DEFINE UPDATE
98. DEFINE OPERATING CONCERN 252 99. ASSIGN CONTROLLING AREA TO OPERATING CONCERN 257 100. SET OPERATING CONCERN 101. ASSIGN VALUE FIELDS 102. ASSIGN QUANTITY FIELDS 103. DIRECT POSTING FROM FI/MM(Maintain PA Transfer Structure for Direct Postings)
104. DEFINE STRUCTURE OF COST CENTER ASSESSMENT/PROCESS COST ASSESSMENT 105. ACTIVATE PROFITABILITY ANALYSIS 264
DEFINE KEY FIGURE SCHEMES CREATE PROFITABILITY REPORT SET CONTROL PARAMETERS FOR ACTUAL DATA MAINTAIN PLAN VERSION ACTUAL POSTING MAINTAIN AUTOMATIC ACCOUNT ASSIGNMENT OF REVENUE ELEMENTS
FI/CO MATERIAL VERSION ECC 6.0 112. CHOOSE ADDITIONAL BALANCE SHEET AND P&L ACCOUNTS 113. SALES ORDER 114. OUTBOUND DELIVERY 115. BILLING OF DOCUMENT 116. POSTING OF G/L 117. EXECUTE ASSESSMENT CYCLE TO TRANSFER OVERHEADS 118. PROFIT CENTER INFORMATION
Controlling Module in SAP provides supporting information to Management for the purpose of planning, reporting, as
well as monitoring the operations of their business. Management decision-making can be achieved with the level of information provided by this module. Some of the components of the CO (Controlling) Module are as follows: Cost Element Accounting Cost Center Accounting Internal Orders Activity-Based Costing (ABC) Product Cost Controlling Profitability Analysis Profit Center Accounting
Cost Element Accounting: component provides information which includes the costs and revenue for an organization. These postings are automatically updated from FI (Financial Accounting) to CO (Controlling). The cost elements are the basis for cost accounting and enable the User the ability to display costs for each of the accounts that have been assigned to the cost element. Examples of accounts that can be assigned are Cost Centers, Internal Orders, WBS(work breakdown structures). Cost Center Accounting: provides information on the costs incurred by your business. Within SAP, you have the ability to assign Cost Centers to departments and /or Managers responsible for certain areas of the business as well as functional areas within your organization. Cost Centers can be created for such functional areas as Marketing, Purchasing, Human Resources, Finance, Facilities, Information Systems, Administrative Support, Legal, Shipping/Receiving, or even Quality. Some of the benefits of Cost Center Accounting: (1) Managers can set Budget /Cost Center targets; (2) Cost Center visibility of functional departments/areas of your business; (3) Planning; (4) Availability of Cost allocation methods; and (5) Assessments/Distribution of costs to other cost objects. Internal Orders: provide a means of tracking costs of a specific job, service, or task. Internal Orders are used as a method to collect those costs and business transactions related to the task. This level of monitoring can be very detailed but allows management the ability to review Internal Order activity for better-decision making purposes. Activity-Based Costing: allows a better definition of the source of costs to the process driving the cost. Activity-Based Costing enhances Cost Center Accounting in that it allows for a process-oriented and cross-functional view of your cost centers. It can also be used with Product Costing and Profitability Analysis. Product Cost Controlling: allows management the ability to analyze their product costs and to make decisions on the optimal price(s) to market their products. It is within this module of CO (Controlling) that planned, actual and target values are analyzed. Sub-components of the module are: Product Cost Planning which includes Material Costing( Cost estimates with Quantity structure, Cost estimates without quantity structure, Master data for Mixed Cost Estimates, Production lot Cost Estimates) , Price Updates, and Reference and Simulation Costing. Cost Object Controlling includes Product Cost by Period, Product Cost by Order, Product Costs by Sales Orders, Intangible Goods and Services, and CRM Service Processes. Actual Costing/Material Ledger includes Periodic Material valuation, Actual Costing, and Price Changes.
Profit Center Accounting: provides visibility of an organizations profit and losses by profit center. The methods which can be utilized for EC-PCA (Profit Center Accounting) are period accounting or by the cost-of-sales approach. Profit Centers can be set-up to identify product lines, divisions, geographical regions, offices, production sites or by functions. Profit Centers are used for Internal Control purposes enabling management the ability to review areas of responsibility within their organization. The difference between a Cost Center and a Profit Center is that the Cost Center represents individual costs incurred during a given period and Profit Centers contain the balances of costs and revenues. Controlling (CO) and Financial Accounting (FI) are independent components in the SAP system. The data flow between the two components takes place on a regular basis. The data relevant to cost, flows automatically to Controlling from Financial Accounting. At the same time, the system assigns the costs and revenues to different CO account assignment objects, such as cost centers, business processes, projects or orders. The relevant accounts in Financial Accounting are managed in Controlling as cost elements or revenue elements. This enables you to compare and reconcile the values from Controlling and Financial Accounting.
If you assign more than one company code to one controlling area, then you need to note the following: You need to use a consistent chart of accounts
You need to treat each cost element (in all company codes) in the same way (for example, as a primary cost element, or as an accrual cost element). In Financial Accounting, you can also use country-specific charts of accounts. The operative fiscal year variants in the company codes must match the fiscal year variants in the controlling area. You should execute period-end closing in Controlling for all company codes at the same time. Separate periodend closing for each company code would be too time-consuming.
You can only execute period-end closing for a shared controlling area once closing is complete in Financial Accounting. If you wish to calculate plan prices automatically, you need to wait until planning is complete. The system only posts reconciliation postings across company codes without tax, which means that it cannot automatically create invoices.
For tax reasons, cost flows (that are cross-company code) in Controlling can only be passed onto Financial Accounting if the company codes form an integrated company with sales tax. If you wish to prevent cross-company code postings in Controlling, then you need to create a detailed authorization concept. Retrospectively excluding a company code in another SAP system or client, requires more time and effort than in cost accounting by company code. If you only use one controlling area, you can only use one operating concern. You can only display profit center allocations in a controlling area. You can only use transfer prices within a controlling area.
You need to take the following into consideration when deciding on the controlling area company code assignment: It is currently not possible to make CO allocations across controlling areas.
SAP recommends a 1:1 relationship between controlling area and company code for the following situations: Consolidated analysis of settled transactions across company codes in Profitability Analysis (CO-PA) In this situation, you assign more than one controlling area to an operating concern Representation of intercom any processes, whereby producing and delivering plant are the same.
it will take to following screen. button so it will display following small window.
Enter your company code and pres enter button or click on continue key. So it will copy few parameters to this screen form company code parameters as follow.
Just pres enter key or pres on yes button it will save automatically. Now double click on Assignment of company code at left side as in follow window:
Now click on
10
Now double click on Activate Components/Control Indicators at left side as I shown in following window:
It will take to another screen here pres on active. So we have active all of them as follow:
11
And go back
to SPRO screen.
One or more number range intervals are specified for each number range, as well as the type of number assignment.
There are two types of number assignment: Internal: when saving a data record, the SAP system assigns a sequential number that lies within the corresponding number range interval. External: When saving a data record, either the user or an external system assigns a number. The number must lie within the corresponding number range interval. The system generates a document number for each business transaction. Business transactions are classified according to CO transactions. The business transaction Direct Internal Activity Allocation belongs to the Controlling transaction Actual Activity Allocation. This means that you must assign each transaction to a number range interval. It is also possible to define multiple business transactions in one number range interval. The Controlling component provides a large number of transactions for each controlling area.
12
Path: SPRO Controlling General Controlling Organization Maintain Number Ranges for Controlling Documents. Transaction Code: KANK Click on (IM Activity),
In above window enter your Controlling Area and pres on Maintain Groups button So it will take to following screen:
13
In above window go to mane bar Group + Insert it will display following window:
In the above window enter text and number range and pres enter key or click on insert appear on the top of main window as follow:
button so it will
Select the check box and double click number range objects as follow (when you double click on each number range objects the color of each object will change to blue from black)
14
Like above do for all number objects. Now pres on button which appears at top of the screen.
So your all number range objects will assign to your number range as follow:
to SPRO screen.
15
Maintain Versions
Path: SPRO Controlling General Controlling Organization Maintain Versions. Transaction Code: OKEQ Click on (IM Activity),
Select Version 0 and double click on Settings for Each Fiscal Year. It will display following screen:
In this window enter your controlling area and pres enter or click on continue key.
16
17
In the above window type LP01 as Output Device and pres enter button or click on continue button:
Now click on
to SPRO screen.
18
19
to SPRO screen.
20
Double click on EC-PCA: Create Dummy Profit Center or select that and click on
button.
Type 1000 number as Dummy Profit center and click on Basic Data or pres enter key.
Maintain above parameters. Click on save button to save the activity, and back to SPRO screen.
21
Double click on EC-PCA: Create Profit Center or select that and click on
button.
In Profit center field any number and click on Master Data button, it will take to following screen:
22
Note: like above process you can create any number of profit centers as per client or project requirement. Scenario in General Ledger Accounting The scenario combines Customizing settings from different business views. In these Customizing settings, you specify which posting data is transferred from different application components in General Ledger accounting, such as cost center update or profit center update. For each scenario, the system transfers the posting data relevant for General Ledger Accounting from the actual and plan documents. Overview of the Scenarios Delivered by SAP Scenario Fields Filled Technical Field Name Cost center update Cost center RCNTR Sender cost center SCNTR Preparation for consolidation Trading partner RASSC Transaction type RMVCT Business area Business area RBUSA Trading partner business area SBUSA Profit center update Profit center PPRCTR Partner profit center PRCTR Segment reporting Profit center PRCTR Segment PSEGMENT Partner segment SEGMENT Cost of sales accounting Functional area RFAREA Partner functional area SFAREA You have to set up cost of sales accounting. The Functional Area field is not filled automatically by the assignment of the scenario to your ledger.
23
24
Setting
Path: SPROControllingCost Element AccountingMaster DataCost ElementsAutomatic Creation of Primary and Secondary Cost ElementsMake Default Settings. Transaction Code: OKB2 Database Table: TKSKA Click on IMG activity the following window will display:
Enter your chart of account and press enter key or click on continue button. In the next screen click on .
25
26
27
FI/CO MATERIAL VERSION ECC 6.0 Step 3: Execute Batch Input Session
Path: SPROControllingCost Element AccountingMaster DataCost ElementsAutomatic Creation of Primary and Secondary Cost Elements Execute Batch Input Session. Transaction Code: SM35 Click on IMG activity the following window will display:
In the above window select Display errors only radio button and click on Process button.
The session has been executed and above window will display here just click on Exit Batch Input button It will exit the session and take you to normal screen.
NOTE: TO CREATE INDIVIDUAL PRIMARY COST ELEMENT TRANSACTION CODE IS KA01 TO CREATE INDIVIDUAL SECONDARY COST ELEMENT TRANSACTION CODE IS KA06
28
Enter the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Internal activity allocation. Change this as follow:
29
Now click on save button so it save the activity and com back to previous screen. 2) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Internal activity allocation. Change this as follow:
30
Now click on save button so it save the activity and com back to previous screen. 3) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Internal activity allocation. Change this as follow:
31
Now click on save button so it save the activity and com back to previous screen. 4) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Internal activity allocation. Change this as follow:
32
Now click on save button so it save the activity and com back to previous screen. 5) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Internal activity allocation. Change this as follow:
33
Now click on save button so it save the activity and com back to previous screen. 6) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Internal activity allocation. Change this as follow:
34
Now click on save button so it save the activity and com back to previous screen. 7) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Internal activity allocation. Change this as follow:
35
Now click on save button so it save the activity and com back to previous screen. 8) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Assessment. Change this as follow:
36
Now click on save button so it save the activity and com back to previous screen. 9) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Assessment. Change this as follow:
37
Now click on save button so it save the activity and com back to previous screen. 10) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Internal settlement. Change this as follow:
38
Now click on save button so it save the activity and com back to previous screen. 11) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Overhead Rates. Change this as follow:
39
Now click on save button so it save the activity and com back to previous screen. 12) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Overhead Rates. Change this as follow:
40
Now click on save button so it save the activity and com back to previous screen. 13) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Overhead Rates. Change this as follow:
41
Now click on save button so it save the activity and com back to previous screen. 13) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Order/project results analysis. Change this as follow:
42
Now click on save button so it save the activity and com back to previous screen. 14) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Order/project results analysis. Change this as follow:
43
Now click on save button so it save the activity and com back to previous screen. 15) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Order/project results analysis. Change this as follow:
44
Now click on save button so it save the activity and com back to previous screen. 16) Now enter another Secondary Cost Element:
After entering the secondary cost element and pres enter button or click on Master Data button: It will come to following screen; In this screen the name and description field contain Order/project results analysis. Change this as follow:
45
Now click on save button so it save the activity and com back to previous screen. Click on back button to go back to SPRO screen.
button.
46
47
Path: Accounting Controlling Cost Element Accounting Master Data Cost Element Group KAH1 Create. Enter into the screen the following screen will display:
In the above screen enter Cost Element Group and press enter or click on Hierarchy button It will take you to following screen:
and Type this description the on ser cur place the same
Now place the curser on above yellow line pres Lower Level button so it will display another level under this structure as follow:
48
Like above screen type Cost Element Group and Description in each line one by one. To assign Cost Elements to each group place the curser on 1000 and click on Cost Element Button
Now click on Down arrow button so it will display another window. In that small window click on continue button so it will display another window as follow:
49
In the above window double click on required and relevant cost element so that it will automatically assign to cost element group. In above case double click on 400000 Cost element. Do the same activity for right side box also (Click on down arrow button. It will display elements window) and double click on 412000 cost element and pres enter button so it will assign all cost elements automatically as follow:
Do the same steps for all other cost Elements Groups and assign cost elements and click on save button to save the activity and click on back button to go back.
50
Dividing an organization into cost centers allows you to follow several goals, depending on the cost accounting method. Assigning costs to cost centers lets you determine where costs are incurred within the organization. If you plan costs at cost center level, you can check cost efficiency at the point where costs are incurred. If you want to assign overhead costs accurately to individual products, services, or market segments, you need to further allocate the costs to those cost centers directly involved in the creation of the products or services. From these cost centers you can then use different methods to assign the activities and costs to the relevant products, services, and market segments.
This enables you to valuate semi-finished and finished products in Product Cost Controlling (CO-PC), and to calculate contribution margins in Profitability Analysis (CO-PA). The activities of cost centers represent internal resources for business processes in Activity-Based Costing. Cost Center Accounting (CO-OM-CCA) is often used in the first phase of implementation, together with the main areas of Financial Accounting (General Ledger (FI-GL), Assets Payable (FI-AP), Assets Receivable (FI-AR)) and Overhead Orders (CO-OM-OPA). You can also implement Cost Center Accounting without Financial Accounting. Some settings, however, such as chart of accounts, company code, must be made in Financial Accounting. The costs of each cost-accounting-relevant business transaction portrayed in the system through can be assigned through Cost and Revenue Element Accounting (CO-OM-CEL) to an account assignment object in the Controlling component (CO). For overhead costs this can be cost centers, internal orders, business processes, or overhead projects. Recording and assigning overhead costs allows you to control costs and prepare information for the subsequent areas of Cost Accounting. You can use the methods of activity allocation, assessment or distribution to further allocate costs, for example, to internal orders (CO-OM-OPA), projects (PS), cost objects (CO-PC) or market segments (CO-PA). Features:
Entering actual costs: Primary costs can be transferred to Cost Accounting from other components, for example,
Materials Management (MM), Asset Accounting (AA), Payroll Accounting (PY).Additional costs and outlay costs are recorded using the accrual method. Allocating actual costs: You can use various methods to further allocate the actual costs you have recorded, according to their source. The system distinguishes between transaction-based allocations, which occur within one period, and period-based allocations, which occur at period end.
51
Information system: The information system provides tools with which you can analyze the cost flows that have occurred in your organization. You can carry out standard recurring evaluations; and create special reports for unique tasks or situations.
Path: SPRO Controlling Cost Center Accounting Master Data Cost Centers Define Cost Center Categories Transaction code: OKA2 Click on IMG activity, so it will take you to following window:
52
SAP provided all types of Cost Centers Categories as we shown above. If you want to create any new click on parameters. Now save and back to SPRO screen. and specify Cost Center Category (CCTC), name and all other
53
Click on Hierarchy button Cost Center Group name that already we specified it will display automatically
In above screen Cost Center Group name will display automatically and just click on Hierarchy button
The above small window will display just click on YES button. 2. Click on this button
1. Type the description and place the curser on the same line
In the above screen type the description and place the curser on the same window and click on Lower Level button so it will display Lower Level Group, in that enter the parameters. Now keep the curser on the same Lower level Group and pres the Button Same Level 6 times.
54
In the above screen enter other Cost Center Groups and pres save button to save the activity and click on back button to go back to access screen.
In the above window enter values to: 1) Cost Center number 2) Valid From 3) To And pres enter key or click on . So it will take you to following screen
55
Enter above parameters and click on save button to save the activity. Immediately after you click on save button it will save and take you to previous screen. So you can change the Cost Center number and create another one. Following is the table of cost centers to be created:
Cost Cente r 1110 1120 1130 1200 1300 1400 2100 3100 4100 4200 4300 6100 Valid From 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 To Name / Description Person Res Mr.Moha n Mr. Vanu Mr. Roy Mr. Gopi Mrs. Radi Mr. Rells Mr. Hari Mr. Jon Mr. Pall Mr. Noyal Mrs. Kalpana MR. Joyal Departmen t Cost Center Categor y 1 1 1 1 1 1 4 M 3 3 3 7 Hierarch y Area Busines s Area Function al Area Currenc y Profit Cente r 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000
01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8 01.01.0 8
Wages Direct Expenses Production overhead Machine A Machine B Assembling Administratio n Material Management Sale & Distribution Marketing Advertisemen t Personal Department
Admin Production Production Production Production Production Production Production Sale & Distribution Sale & Distribution Sale & Distribution Admin
1000 1000 1000 1000 1000 1000 2000 3000 4000 4000 4000 6000
11B1 11B1 11B2 11B2 11B2 11B1 11B2 11B1 11B2 11B1 11B2 11B1
1FA2 1FA2 1FA2 1FA2 1FA2 1FA2 1FA2 1FA2 1FA3 1FA3 1FA3 1FA2
INR INR INR INR INR INR INR INR INR INR INR INR
56
button.
Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting Master Data Indexes KA23 - Cost Elements: Master Data Report KS13 - Cost Centers: Master Data Report Transaction Code: KS23
57
button.
You can use them as the basis for internal allocations, such as Distribution and Assessment. You assess the costs for the cafeteria to the individual cost centers, based on the number of employees in each cost center. To do this, you need to enter the number of employees in each cost center as a statistical key figure.
Structure
You can define statistical key figures as either: Fixed values Totals values
Key figures defined as fixed values are valid as of the posting period, and in all subsequent posting periods of the fiscal year. Example: The statistical key figure Employees is defined as a fixed value. In period 1 of the fiscal year, you post 10 Employees on cost center 4100. The system then automatically posts 10 employees in periods 2 through 12. In period 6, the number of employees is increased to 15. This means that in period 6, you post 15 Employees on the cost center. The system automatically posts 15 employees in periods 6 through 12. Key figures defined as Totals values are valid only in the posting period in which they are entered.
58
Path: AccountingControllingCost Center AccountingMaster DataStatistical Key FiguresIndividual ProcessingKK01 Create Transaction Code: KK01 Double click on the Transaction Code so it will display the following screen:
In the above screen enter the Stat. Key Figure number and pres enter or click on It will take you to following screen:
Buton.
Enter the above parameters and Save the screen. In the same way create moor Statistical key Figure as follow: Stat. Key Figure 1000 Name No. Of employees Stat.Key.Fig. UnM. EA Key fig. cat: Fxd Val Select Key fig. cat: Tot. Value ------------------------
59
After creating all above Statistical key Figure save the screen and back to mane.
ACTIVITY TYPE
Creation Activity Type
Activity type describes and classifies the activities performed or produced by cost center. These activities are recorded in the form of activity, quantity, which is measured in activity units. Activity types classify the activities produced in the cost centers within a controlling area. To plan and allocate the activities, the system records quantities that are measured in activity units. Activity quantities are valuated using a price (allocation price). In Overhead Cost Controlling, costs based on the activity quantity of an activity type are posted separately in fixed and variable portions. When you divide the activities of a cost center into activity types, you should consider whether the costs can be allocated effectively to the activity types. The prices of the activity types of a cost center can be either entered manually, or calculated by the system based on the costs allocated to the activities. Prices can be calculated either using plan costs or actual costs. You can plan, allocate, and control costs either at the activity type level of a cost center, or at the cost center level. You can enter actual costs at the cost center level. Costs entered at the cost center level are assigned using splitting. You can also assign the activity type of a cost center directly. This use was designed for certain application areas (such as personnel costs and depreciation postings). When the activities produced by a cost center are used by other cost centers, orders, processes, and so on, this means that the resources of the sending cost center are being used by the other objects. You can assign one activity type, multiple activity types, or no activity types to a cost center. Examples: Activity types for cost centers are machine hours, administrator hours, CPU minutes or units produced. These activity types are categorized based on the information availability for the purpose of allocation. 1. 2. 3. 4. Manual Entry / Manual allocation Indirect Determination, Indirect Allocation Manual Entry / Indirect allocation Manual Entry, No Allocation
Price Indicators: 1. 2. 3. 4. 001: Plan Price Indicator 002: Plan Price Determined Automatically based on plan activity. 003: Plan Price Determine Automatically 004: Determine Manually
60
Path: AccountingControllingCost Center AccountingMaster Data Activity TypeIndividual Processing KL01 - Create Transaction Code: KL01 Double click on the Transaction Code so it will display the following screen:
In the above screen enter Activity Type number and pres enter or So it will take to next screen as follow:
button.
61
After you create all above Activity Types save the screen and back to easy access.
Activity Category
Activity type category 1: (Manual entry, manual allocation) you plan activity quantities manually for activity types in this category. You enter actual activity quantities in internal activity allocation, based on business transactions. Plan activities are allocated using activity input planning on the receivers. It may be necessary to reconcile the plan sender quantities and the plan scheduled activities. Activity type category 2: (Indirect calculation, indirect allocation) For activity types of this category, you plan activity types on the sender cost center. You can calculate the plan and actual activity quantities for activity types of this category as follows: Automatically, using receiver tracing factors, which you can value with weighting factors and are defined for each sender, or Using a fixed quantity, which you define in the segment definition of the indirect activity allocation The system automatically reconciles the plan and scheduled activity quantities.
Activity type category 3: (Manual entry, indirect allocation) you plan activity quantities manually for activity types in this category. To enter the actual activity quantities by business transaction, access the Cost Center Accounting menu, and choose Actual postings Sender activities. You cannot enter receiver objects here. Plan and actual activity quantities are allocated automatically using defined sender/receiver relationships. The system calculates the activity quantity to be allocated to each receiver, based on the relationship of the tracing factors to all receivers. Manually planned or posted activity quantities are further allocated in full to the receivers. This means that the activity types in the plan are always reconciled following the activity allocation. Activity type category 4: (Manual entry, no allocation) you plan activity quantities manually for activity types in this category. To enter the actual activity quantities by business transaction, access the Cost Center Accounting menu, and choose Actual postings Sender activities. You cannot enter receiver objects here. You cannot allocate to other objects. Activity type category 5: (Calculation and allocation through target=actual activity allocation)
62
Price Indicators
The Price indicator determines how the price of a business process or an activity type is calculated for a cost center. There are two fields: The Price indicator determines the way the system calculates prices for actual values. For actual allocations, you can enter a price indicator different from that in the plan. You can enter the following values for the (plan) price indicator: 001: The system calculates the price of the activity type automatically, based on the plan activity and the plan costs required by the cost center. Fixed price: Fixed plan costs plan activity Variable price: Variable plan costs plan activity Total price: Fixed price + variable price 002: The system calculates the variable portion of the price, based on the plan activity. The fixed portion, however, is based on capacity. This method usually results in an under absorption for the cost center. This is because the cost center is not credited in full for the costs of providing the capacity. Fixed price: Fixed plan costs capacity Variable price: Variable plan costs plan activity Total price: Fixed price + variable price If you have set values 001 or 002, the system calculates new prices when you execute Plan Price Calculation. 003: You set the price of the activity type manually. 004: Activation from version maintenance
You cannot enter price indicator 004 (the plan price of the activity is calculated purely iteratively). If you activate Purely iterative price in the version, the SAP System calculates a purely iterative price, in addition to the price resulting from planning. You can enter the following values for the (actual) price indicator: 005: The SAP System calculates the actual price based on the actual activity if you execute Actual Price Calculation. (Actual Price Calculation: The method used to calculate the prices of planned activities iteratively for combinations of cost center and activity type or for business processes, taking all activities performed for other cost centers or business processes into account. This can be done for both planned and actual data.) 006: The system calculates the variable portion of the price, based on actual activity. The fixed portion, however, is based on the capacity.
63
64
Statistical key figures can be planned for different purposes, for example, as a basis for distribution, assessment, or creating key figures in the information system. You can plan statistical key figures on cost centers or on the activity types of the cost centers. In addition to manually planning statistical figures you can also transfer statistical key figures from the Logistics Information System (LIS) For more information. In activity type planning, you plan the activity produced by a cost center. This represents the quantity-based output of a cost center. During planning you can manually set the price with which the SAP system valuates the activity during allocations. You can choose to retain this price or have the system overwrite it during plan price calculation. You can also plan the capacity required for providing the activity type. The input side of the cost center is affected when the primary and secondary cost values are planned. The primary and secondary plan costs refer to the costs incurred in producing the plan output on the cost center. Value-based cost planning can be executed manually or automatically. For the automatic planning of primary costs you can use plan distribution For automatic planning of secondary costs, you can use assessment. The SAP system determines the planning values on the basis of user-defined rules. For planning purposes, you can transfer primary costs to cost center planning from Human Resources and Asset Accounting
65
Features
Here is a selection of the periodic formulas offered by the system for the planning of CO objects: Fixed + variable = Overall (only activity-dependent)
1. Fixed
Costs Fixed costs/variable costs
= Overall (activity-independent in Cost Center Accounting) = price/price unit * plan activity quantity = Fixed consumption/variable consumption Currency translations <-> <-> <-> <-> <-> <-> <-> Fixed object currency Variable object currency Fixed transaction currency Variable transaction currency Fixed user-definable currency Variable user-definable currency Overall user-definable currency
2. 3. 4. 5. 6. 7. 8.
Fixed controlling area currency Variable controlling area currency Fixed controlling area currency Variable controlling area currency Fixed controlling area currency Variable controlling area currency Overall controlling area currency
66
You plan the following primary costs: Fixed $20 Variable $40 Overall $80 The system calculates an overall value of $60 and overwrites the value of $80 in line with the first priority. 2. Overall - variable = fixed 3. Overall - fixed = variable
Fixed Costs = Overall Costs/ Fixed Quantities = Overall Quantities (Activity-Independent in Cost Center Accounting)
The system uses this formula if you are not planning any activity-dependent costs. If only overall costs exist, the system updates this value as fixed costs. Overall costs = overall price/price unit * overall quantity Variable costs = variable price/price unit * variable quantity The system uses this formula when you plan activity-dependent secondary costs. If you have entered manual prices in activity type planning, or have carried out price calculation, the system uses these values in the activity input planning for valuation of the plan consumption If you have not planned any prices, you cannot carry out a valuation during secondary planning. Only after price calculation or manual price planning does the system execute a recalculation of the received activity quantities using the prices. If the following values in the activity type planning: Activity quantity of the fixed activity type Drills. 100 hrs Activity quantity of the variable activity type Drills. 200 hrs Fixed price $10/hr Variable price: $20/hr Price unit 1, that is, the price is valid for 1 hour of activity type Drills. From this, the system calculates the following costs for the receiver of the activity. Overall plan costs = = = = Overall price*Total quantity (Fixed price + variable price) (101 + 20/1) $9000 * *(Fixed qty + Variable qty) (100 + 200)
67
The system carries out the following calculations: $2000 / $3000 = 100 hrs / 300 hrs As you have planned all the values manually and the relationships in the formula are not identical, the system overwrites the Fixed consumption value with Fixed consumption = $2000 * 300 hrs / $3000 = 200 hrs With the value 200 hrs for the fixed consumption, the formula is once again correct.
Currency Translations
During manual planning, the system executes any necessary currency translations if these have been activated in the controlling area. Generally, the system carries out manual planning in the controlling area currency. Additionally, however, you can also use plan values in transaction, object or a freely-definable currency. To do this, you need to add another column to the corresponding planning layout for each additional leading amount in a different currency. The following translations are possible: Controlling area currency to transaction currency Controlling area currency to object currency Controlling area currency to user-definable currency Transaction currency to controlling area currency
68
4.
Planning in SAP ma be: 1. Manual Planning (Allocation Process) 2. Automatic Planning (Apportionment process)
Path: AccountingControllingCost Center AccountingPlanning Statistical Key Figures KP46 Change Transaction Code: KP46 Double click on the Transaction Code so it will display the following screen:
69
Enter the above parameters and select Overview Screen It will display the following Screen:
button.
Now click on Next Combination button to go to next Cost Center with Combination of Statistical Key Figures till you reach the Cost Center 1130 Production overheads as follow:
Enter the above values and click on next combination It will display as follow:
70
Enter the above values and click on next combination It will display as follow:
Enter the above values and click on next combination It will display as follow:
71
Enter the above values and click on next combination Center It will display as follow:
Enter the above values and click on next combination It will display as follow:
for the Cost Center 4100 Sales & Distribution Cost Center
72
Enter the above values and click on next combination It will display as follow:
Enter the above values and click on next combination It will display as follow:
73
Enter the above values and click on next combination It will display as follow:
for the Cost Center 6200 Canteen & Welfare Cost Center
Enter the above values and click on next combination It will display as follow:
74
Enter the above values and click on next combination It will display as follow:
Enter the above values and click on next combination Center It will display as follow:
75
Enter the above values and click on next combination It will display as follow:
Enter the above values and click on Save Button so your planning activity will save and back to Manu screen.
76
button.
Path: AccountingControllingCost Center AccountingPlanning Activity Output/Prices KP26 - Change Transaction Code: KP26 Double click on the Transaction Code so it will display the following screen:
77
In the above screen first click on Next combination In this screen maintain above parameters.
Click on Next combination Button till u comes to 1300 Machine B Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 1400 Assembling Cost Center. It will display the following screen:
78
Click on Next combination Button till u comes to 6600 Repairing & Maintains Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6700 Quality & Control Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6800 Power Cost Center. It will display the following screen:
79
After entering above parameters click on save the button to save planning activity and back to Manu screen.
button.
80
81
Now maintain the above parameters and click on Overview Screen So it will take you to another screen as follow:
button.
Click on Next combination Button till u comes to 1300 Machine B Cost Center. It will display the following screen:
82
Click on Next combination Button till u comes to 6600 repairs & Maintains Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6700 Quality control Cost Center. It will display the following screen:
After entering above parameters save the activity and back to Manu screen. REPORT ON COST CENTER Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance It will display the following screen:
83
button.
84
Click on Next combination Button till u comes to 1130 Production Overheads Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 2100 Administration Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 3100 Material Management Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 4100 Sales & Distribution Cost Center. It will display the following screen:
85
Click on Next combination Button till u comes to 4200 Marketing Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6100 Personal Dept Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6200 Canteen & Welfare Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6300 Dispensary Cost Center. It will display the following screen:
86
Click on Next combination Button till u comes to 6200 Canteen & Welfare Cost Center. It will display the following screen:
After entering above parameters just click on save button and back to Manu screen.
button.
87
Select the parameters as above and select execute button It displays the following screen:
88
Once you execute the screen just go back from this screen to Easy Access screen. REPORT ON COST CENTER Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance It will display the following screen:
button.
89
After maintaining the above parameters just click on overview screen So it will take to following screen:
button.
Click on Next combination Button till u comes to 1200 Machine A Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 1300 Machine B Cost Center. It will display the following screen:
90
Click on Next combination Button till u comes to 1400 Assembling Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6600 Repairs & Maintains Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 67600 Quality Control Cost Center. It will display the following screen:
91
Click on Next combination Button till u comes to 6800 Power dept Cost Center. It will display the following screen:
After entering above parameters save the activity and back to easy access screen.
button.
92
After maintaining the above parameters just click on overview screen So it will take to following screen:
button.
Click on Next combination Button till u comes to 1110 Wages Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 1130 Production Overheads Cost Center. It will display the following screen:
93
Click on Next combination Button till u comes to 1200 Machine A Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 2100 Administration Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 3100 Material Management Cost Center. It will display the following screen:
94
Click on Next combination Button till u comes to 4100 Sales & Distribution Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 4200 Marketing Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 4300 Advertisement Cost Center. It will display the following screen:
95
Click on Next combination Button till u comes to 6100 Personal dept Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6200 Canteen & welfare Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6300 Dispensary Cost Center. It will display the following screen:
96
Click on Next combination Button till u comes to 6400 storage dept Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6500 Vehicles & Internal Cost Center. It will display the following screen:
Click on Next combination Button till u comes to 6900 Telephone Dept Cost Center. It will display the following screen:
97
Click on Next combination Button till u comes to 6910 Rent Dept Cost Center. It will display the following screen:
After entering above parameters save the activity and back to easy access screen.
REPORT ON COST CENTER Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting Plan/Actual Comparisons S_ALR_87013611 - Cost Centers: Actual/Plan/Variance It will display the following screen:
98
button.
----------------------------------------------------------------------------------------------------------------------Allocation of services cost centers cost among services receiving cost center: The allocation may be made basing on posted to cost center or a activities of a cost center. The system provides the following allocation methods: 1. 2. 3. 4. Periodic Re-Posting Distribution Assessment Indirect Activity Allocation In above first 3 methods are used for Distribution of cost and last method is used for Distribution of Activates
In the above screen give Cycle name and Start Date and pres enter button. It will display the following screen:
99
In the above screen maintain the Text and flag the check box Iterative and pres on It takes you to another screen as follow:
button.
In the above screen maintain Segment name and description. Under Segment Header tab Receiver rule 1 Variable Portions and Var.Portion Type 6 plan stat. key figures. After maintain above parameters click on another tab Sender/Receivers so it will display following screen:
100
In the above screen maintain sender cost center, sender cost element and receiver cost center under Senders/Receivers tab. After this click on Receiver Tracing Factor tab so it will take you to following screen;
In the above screen maintain Version , Stat.Key fig and pres on save button to save the activity. After saving click on button so it will display new screen for another segment as follow:
101
In the above screen maintain Segment name and description. Under Segment Header tab Receiver rule 1 Variable Portions and Var.Portion Type 6 plan stat. key figures. After maintain above parameters click on another tab Sender/Receivers so it will display following screen:
In the above screen maintain sender cost center, sender cost element and receiver cost center under Senders/Receivers tab. After this click on Receiver Tracing Factor tab so it will take you to following screen:
102
In the above screen maintain Version, Stat. Key fig and pres on save button to save the activity. After saving click on button so it will display new screen for another segment as follow:
In the above screen maintain Segment name and description. Under Segment Header tab Receiver rule 1 Variable Portions and Var.Portion Type 6 plan stat. key figures. After maintain above parameters click on another tab Sender/Receivers so it will display following screen:
103
In the above screen maintain sender cost center, sender cost element and receiver cost center under Senders/Receivers tab. After this click on Receiver Tracing Factor tab so it will take you to following screen;
In the above screen maintain Version , Stat.Key fig and pres on save button to save the activity. After saving click on button so it will display new screen for another segment as follow:
104
In the above screen maintain Segment name and description. Under Segment Header tab Receiver rule 1 Variable Portions and Var.Portion Type 6 plan stat. key figures. After maintain above parameters click on another tab Sender/Receivers so it will display following screen:
In the above screen maintain sender cost center, sender cost element and receiver cost center under Senders/Receivers tab. After this click on Receiver Tracing Factor tab so it will take you to following screen;
105
In the above screen maintain Version , Stat.Key fig and pres on save button to save the activity. After saving click on button so it will display new screen for another segment as follow:
In the above screen maintain Segment name and description. Under Segment Header tab Receiver rule 3 Fixed Percentages. After maintain above parameters click on another tab Sender/Receivers so it will display following screen:
106
In the above screen maintain sender cost center, sender cost element and receiver cost center under Senders/Receivers tab. After this click on Receiver Tracing Factor tab so it will take you to following screen;
After entering above parameters click on save button and go back to easy access screen.
107
In the above screen after maintaining all parameters click on So it will display the following screen:
button.
108
Now click on back and put you curser on Number of receivers and click on window:
109
Now click on back button till you go back to easy access screen:
button.
110
In the above screen just Deselect Test run and click on execute button. It will display the following screen:
111
button.
112
In the above screen enter new Cycle name and start date and pres enter button. So it will display following screen:
button:
113
In the above screen under Tab Segment Header enter segment name and description, maintain Rule as 1 Variable Portions, Var.Portion Type as 8 Plan Activity and click on TAB Sender/Receivers
In above screen maintain Sender and Receiver parameters and click on Tab Receiver Tracing Factor
114
After maintain parameters in above screen just save the activity and back to easy access screen.
115
In above screen put curser on Senders and click on So it will show the following screen:
button.
Back the to main screen. Now put your curse on Receivers and click on So it will display the following screen:
116
button.
117
SPLITING
In every cost center we may have activity dependent cost or activity independent cost. It the cost center has a multiple activities the activity independent cost is to be related distributed among the activities by specifying same distribution rule it no distribution rule is specify the system split the activity independent cost equally among the activity. Path: AccountingControllingCost Center AccountingPlanning Allocations KSS4 - Splitting Transaction Code: KSS4 Splitting Database Table: TSC0A, TSC0B, TSC0C, TSC0D, TSC0E, TSC0F, TSC0G, TSC0H, TSC0I By above transaction code it will display the following screen:
Deselect this Check Box else master records will not be update
\In the above screen maintain the parameters as specified and click on executive button. So it displays the following screen:
In the above screen keep curser on CTR 1200 and click on So it displays the following screen:
button .
118
Once Click on Splitting Rules it will display the following screen: In this screen click on button.
119
After saving the activity select this button to select your rule
In the above screen enter new Rule name, text and method as 22, pres enter and save the screen. Now select the rule which you created and double click on Selection for rules under Dialog Structures. In this screen click on button. It will display the following screen:
In the above screen once you assign version 0 double click on Splitting Structures under Dialog Structure. So it will display another screen as shown below: In this screen click on button.
120
In the above screen give new assgnmnt, text and select your rule and pres enter. Select your assgnmnt as you created above and double click on Selection for Assignment under Dialog Structure In this screen click on button.
In the above screen assign Cost elements and Activity Types and save the screen. Once you saved the activity back to easy access screen.
121
In above screen maintain the parameters and click on change button So it will take to another screen as below:
In the above screen select your cost center check box and keep the curser on your splitting Structure Now following Manu path as follow:
122
In the above screen you can see your cost center is assigned to your Splitting Structure Now save the screen and back to easy access.
Deselect this Check Box else master records will not be update
123
In the above screen keep curser on CTR 1200 click on So it will show the following screen:
button.
124
button.
You can see the budget data in a budget report. The budget report compares plan data , commitment data, and actual data (resulting from actual postings) as well as the allotted and available amounts.
Prerequisites
Before you can plan your budget, you must create a budget profile during Customizing for Cost Center Accounting. Alternatively, you may use an existing profile. You can change the following budget profile settings when you are planning your budget: Budgeting time frame Decimal places Scaling factor Distribution Keys
125
The budgeting time period, in the past, or in the future The starting year in which budget planning is to begin The scaling and decimal places for the display of values in budget planning Period planning or fiscal year planning Default values for the distribution key.
3.Choose Overview screen to access the overview screen of the annual values. You can then change the budget of your cost center. 1. If you entered a cost center group in the initial screen of budget planning, you can choose Group structure y/n function to display or hide the group structure. If you choose Y, the system displays the top node of the group with the sum of all the planned budgets of the lower-level cost centers. 2. If you have selected period values in the budget profile, you can choose Period overview to switch from the list of annual values to the list of period values for a cost center. The system distributes the plan annual value to the individual periods according to the distribution key defined in the budget profile. You can change this distribution key in the period screen if required. You can only select true distribution keys. True distribution keys break down an annual value into monthly values, so that the sum of the monthly values equals the original annual value. 3. Choose Period values in the Annual values overview screen to display the individual period values for each cost center. You can select a given period, or view all the period values of a cost center or cost center group.
126
Select your Profile, Cost Center Group and pres enter button or So it will take you to follow screen:
button.
127
Now click on button and save the transaction so it will post the transaction. When it posted it will posted with an Document number. in above case that document number is 100002
128
button.
Enter the above parameters and click on executive button. It will display the following screen:
129
In the above screen 150000 is the amount posted to 1110 cost center. If we need to repost of that amount to other cost center that means out of 150000 you want to post 50000 to other cost center like 1200 so for that do as follow:
130
button.
131
After entering the data save the screen and back to easy access. Sender Activity Path: Accounting Controlling Cost Center Accounting Actual Postings Sender Activities KB51N Enter Transaction Code: KB51N Enter Enter the transaction it will display the following screen:
132
Actual Price Path: Accounting Controlling Cost Center Accounting Actual Postings Actual Price KBK6 - Enter Transaction Code: KBK6 Enter
Enter the transaction it will display the following screen:
Enter the above parameters and pres on overview screen button. So it will take you to following screen with cost center 1200 Machine A
Once you enter the above parameters click on Machine B enter required entries as below:
133
Once you enter the above parameters click on Assembling enter required entries as below:
After entering above entries save the activity and back to easy access.
KB31N -
134
After you enter the above entries save the screen and back to easy access.
135
In above screen provide Segment Name, Description and for Receiver Rule 1 Variable Portions for Var.Portion Type 5 Actual Statistical Key Figures. And go to Tab Senders/Receivers
136
In above screen maintain above parameters for Cost Center, Cost Element and Cost Center under Receiver. Not go to Tab Receiver Tracing Factor
In the above screen for Stat.Key Fig maintain value and click on save button to save the activity. Now click on button to attach another Segment as below:
137
In above screen provide Segment Name, Description and for Receiver Rule 1 Variable Portions for Var.Portion Type 5 Actual Statistical Key Figures. And go to Tab Senders/Receivers
In above screen maintain above parameters for Cost Center, Cost Element and Cost Center under Receiver. Not go to Tab Receiver Tracing Factor
138
In the above screen for Stat.Key Fig maintain value and click on save button to save the activity. Now back to easy access screen.
Single Functions
Deselect this check Box other wise it wont update master records
In the above screen assign your assessment cycle which your created in above step, maintain other parameters and executive the section
139
Now place your curser on Senders and pres on Sender button. So it will display all sender list as follow:
Now back to the screen and place the curser on Number of Receivers and click on Receiver button. So it will display the following screen:
140
141
Maintain the above parameters and click on execute button It will display the following screen:
Put the curser on either of the Objects in above table and click on calculation as follow:
142
In the above screen give new Cycle name, Start date and click enter button so it will take you to following screen:
143
In the above screen first maintain Segment name and Description, under Tab Segment Header as Rule 1 Variable Portions and as Var.Portion Type 7 Actual Activity. Now click on Tab Sender/Receivers, so it will display the following screen:
In the above screen maintain the Cost center, Activity Type under Sender and under Receiver maintain cost Center and click on Tab Receiver Tracing Factor so it will display the following screen:
144
In the above screen maintain only Activity Type. Save the screen and back to easy access screen.
In the above screen under Cycle assign above cycle name and maintain the above parameters.
145
In the above screen you can absover the sender details now back to previous screen. Now place the curser on Number of receivers and click on so it will display the screen as below:
In the above screen you can find the no of recovers an amount received now back to easy access screen.
146
In the above screen maintain cost center and other parameters and click on screen:
In the above screen place the curse on cost center line item and click on detail list:
147
Back to easy access screen. NOTE 1: Formula for Operation Ratio: Actual Activity ------------------ X 100 Plan Activity NOTE 2: Formula for Target Cost: Target Fixed Cost = Plan Fixed Cost Target Variable Cost = Planed Variable Cost X Operating Rate Target Cost is used to compare with the actual cost for variance analysis.
148
In the above screen against to your FM area we have to assign our Fiscal Year Variant which we already created in finance. Now click on (SAVE) button to save the activity and back to SPRO screen.
STEP 4: Assign Field Status Variant To Company Code Path: SPRO Controlling Cost Center Accounting Commitments and Funds Commitments Field Control for Funds Commitment Assign field status variant to company code Transaction code: FMUV Database Table: T001
Enter into the above path or transaction code so it will display the below screen: Click on button so it will display the below screen:
149
In the above screen enter your company code and click enter button or click on So your company code will appear at the top of screen as below:
button.
In the above screen against to your company code on clicking of F4 function assigh FMRE that is Earmarked fund Status Variant assign. Now click on (SAVE) button to save the activity and back to SPRO screen.
Step 5: Create Commitment Item Path: Accounting Public Sector Management Funds Management Master Data Account Assignment Elements Commitment Item FMCIA - Individual Processing Transaction code: FMCIA - Individual Processing Enter into the above path or transaction code so it will display the below screen:
In the above window enter your FM area and pres enter button. So it will display the following screen:
In the above screen enter Commitment item and click on It will activate other below fields as below:
(Create) button.
150
In the above screen enter name, Description of Commitment and Financial Trans as 30 , Commitment item cat as 3 Because this commitment I am creating for Purchase account. Like above you can create any number of commitment items as client required. Each commitment item should assign to a relevant GL Account as below step. Now save the activity and back to easy access screen.
151
1) Enter your purchase GL a/c number. 2) Click on Edit Button. 3) Click on this Tab Create/Bank/Interest.
In the above screen enter your GL Account number and click on edit button. Now go to Create/Bank/Interest tab under Bank/financial details in company code assign your commitment item to Commitment Item field. After maintain all above parameters save the GL Account and back to Easy access screen. Step 7: Enter Value to Commitment Item Path: Accounting Controlling Cost Center Accounting Actual Postings Funds Commitment FMZ1 Create Transaction code: FMZ1 - Create Enter into the above path or transaction code so it will display the below screen:
152
In the above screen maintain Original amount and commitment item as we create above step and assign G/L Account, Cot center. Save the activity and back to ease access screen. NOTE: In field Status Variant keep optional to 1. Commitment Item,2.Earmarked Funds.
153
In the above screen enter invoice amount in Amount Coolum, enter Text, Pstky (Posting key that is GL Debit) and Account that is G/L Account of Purchases. After entering above parameters click Enter button so it will display the following screen:
154
In above screen select your Business area, Cost Center, Profit Center, Earmarked Funds and pres enter button. Now in the same screen go to Manu bar Document Simulate as it shows below:
155
156
157
Internal orders are normally used to plan, collect, and settle the costs of internal jobs and tasks. The SAP system enables you to monitor your internal orders throughout their entire life-cycle; from initial creation, through the planning and posting of all the actual costs, to the final settlement and archiving: Order management within a company usually differentiates between sales-oriented orders, and internal orders. Salesoriented orders (production or sales orders) are intended mainly for the logistical control of input factors and sales activities. Internal orders are categorized as either: Orders used only for monitoring objects in Cost Accounting (such as, advertising or trade fair orders) Productive orders that are value-added, that is, orders that can be capitalized (such as in-house construction of an assembly line).
Internal order management is the most detailed operational level of cost and activity accounting. It can be used for: Cost monitoring, for example, where costs need to be looked at from object-related aspects, unlike in Cost Element Accounting or Cost Center Accounting Assisting decision-making, when you need to decide between in-house production and external procurement
An enterprises internal orders can be used for different controlling purposes. For more information, see Classified by Controlling Objectives.
Features
You can use master data to assign certain characteristics to your internal orders, which enables you to control which business transactions can be used with the internal order. Internal order planning enables you to roughly estimate the costs of a job before the order starts and to make an exact calculation at a later date. You can choose between various planning approaches to compare the effectiveness of different methods. You can assign and manage budgets for internal orders.
158
An internal order is used to monitor parts of the costs, and under certain circumstances, the revenues of the organization. You can create an internal order to monitor the costs of a time-restricted job or the costs (and revenues, if required) for the production of activities. Internal orders can also be used for the long-term monitoring of costs. Overhead cost orders are used for the time-restricted monitoring of overhead costs (that are incurred when you execute a job) or for the long-term monitoring of parts of the overhead costs. Investment orders let you monitor investment costs that can be capitalized and settled to fixed assets. Accrual orders enable you to monitor period-related accrual calculation between expenses posted in Financial Accounting and the costing-based costs debited in Cost Accounting. Orders with revenues let you monitor costs and revenues that are incurred for activities for external partners, or for internal activities that do not form part of the core business for your organization. You can use model orders as a reference, when creating new internal orders.
You can find further information on the internal order types mentioned above, in Orders Classified by Content.
The system also uses the order type to determine default values for the various master data fields and to define given attributes for the assigned orders. Path: SPROControllingInternal OrdersOrder Master DataDefine Order Types Transaction code: OKT2
159
In the above small window enter 01 as Order Category and pres enter button. So it will display the below screen:
In the above screen maintain all above parameters. In the next step u have to maintain number ranges so click on Number range Interval Edit button So it will take you to another screen as below:
In the above screen go to Manu bar Group Insert so it will display the following window:
160
In the above screen maintain text, from number and to number. Now click on enter button or click on (insert) button. So your number range will appear at he end of screen below screen
In the above screen you can watch your Internal Order number range. Now flag the check box and double click your internal order type which appears under the Not Assigned and click on Order Type will assign to your number range as below: button. So your Internal
161
As the above screen showes your internal order type is assigned to your number range. Now save the screen and back to SPRO screen.
Maintain Settlement
Path: SPROControllingInternal Orders Planning Maintain Settlement Transaction code: KOA1 Click on above transaction, so it will display the following screen:
In the above screen double click on Assign Number Range for Settlement Documents
162
In the above screen flat the check box Standard accounting document. Select and double click on your controlling area under Not assigned. Now click on number range as follow: button so your controlling area will automatically assigned to
163
In the above screen maintain the parameters and save the screen and back to SPRO screen.
164
When you set the indicator for internal orders or projects, note that a project cannot be plan integrated and statistical at the same time. The system also displays, for example, whether: Period-end closing Period-end closing Revenue postings are allowed Commitments management is active
This is where you maintain, for example: Parameters for costing (Results analysis key) Parameters for overhead costing (Costing sheet and overhead key) Parameters for interest calculation (Interest calculation sheet)
This is where you maintain the parameters for order settlement to one receiver (Settlement cost element and receiving Cost center or receiving G/L account). To settle more than one receiver, choose Settlement rule. The settlement rule consists of one or more distribution rules, which define the distribution for the costs incurred on the order to the various receivers. You can find more information on this subject under:
General data
General data
In this sub screen you maintain general data, such as Applicant and Responsible person for the order. This data is for information purposes only and is not checked by the system. This is where you maintain all the parameters required for capital investment orders (for example, Investment profile, Scale, Investment reason) This is where you assign the order to one or more investment program items.
Investments
Investment management Assignment to investment program / Appropriation request Simulation data for
This is where you maintain the data for asset depreciation of the
165
Path: AccountingControllingInternal OrdersMaster DataSpecial FunctionsOrderKO01 Create Transaction Code: KO01 - Create Enter to screen with above transaction code:
In the above screen entry your Order Type which you created above steps. Now pres enter or click on button so it enter into following screen:
In the above screen enter the text and other parameters as you required and go to tab Prd-end closing It will as below:
166
In the above screen we entered the Settlement Cost element and Cost Center now clicks on tab Control data:
In the above screen your System Status should be REL SFMT. Now save the order. When u save the order it will save with a number that will display in the status bar as bellow.
The above 90001 is the first internal order number. To create another internal order pres enter button again
167
Maintain the above parameters under tab Assignments and go to another tab Control Data In the above screen we entered the Settlement Cost element and Cost Center now clicks on tab Control data:
In the above screen your System Status should be REL SFMT. Now save the order. When u save the order it will save with a number that will display in the status bar as bellow.
The above 90002 is another internal order number. Like this we can create any number of internal as per the client requirement.
168
Cost center two plans to take 2000 production hours from cost center one, using an internal order. The planning of activities on the cost center and internal order can be integrated, because the internal order already exists in the system, and the same time horizon is planned. If integrated planning is active, the scheduled activity for the order is updated on cost center one. The settlement of the internal order in the plan is updated on cost center two (the receiving cost center). Cost center three plans to take 700 production hours from cost center one. No internal order exists at the time of cost center planning. The internal order is created later and so cannot be integrated into planning. You need to execute cost center planning manually, and independently from order planning.
Integrated Planning of Internal Orders with Profit centers, and the Extended General Ledger
If you activate integrated planning with Profit Center Accounting and the Extended General Ledger, the system transfers planning data for internal orders and Cost Center Accounting to Profit Center Accounting and the Extended General Ledger.
169
You need to activate the Integrated Planning indicator in the version. This ensures that the system makes the planning data for internal orders available to other applications in the SAP system. Path: AccountingControllingInternal Orders Planning Cost and Activity Inputs KPF6 - Change Transaction Code: KPF6 Enter to screen with above transaction code:
In the above screen maintain all parameters and pres on overview screen button So it takes you to the following screen as follow:
170
In the above screen enter all relevant values to order 90002 Profit analysis Save the screen and back to easy access screen.
Budget Updates Unforeseen events, additional requirements, for example, price rises for external activities, and so on. This may mean you need to update the original budget, in the form of: Supplements Returns Current This is derived from the budget types already mentioned: Budget
Original budget
+ =
171
In the above screen enter your order number and pres enter or click on So it will display the screen as bellow:
button.
In the above screen enter the values for overall, 2008 and save the screen. It takes to previous screen. Now enter another order as below:
172
In the above screen enter the values for overall, 2008 and save the screen and back to easy access screen.
In the above screen maintain the above information and click on It will display the following screen with information:
button.
173
In the above screen it displays the plan, variance values. Once have a look on that and back to easy access.
Once you enter the above parameters click on enter button so it will take to following screen:
174
In the above screen maintain Amount, Cost Center, Order, PStky (Posting key), Account and click on enter button. It will display another screen as below:
175
In the above screen maintain Amount, Cost Center, Order, PStky (Posting key), Account and click on enter button. It will display another screen as below:
176
In the above screen assign Segment as Project - 1 and pres on enter button Now go to Manu bar Document - Simulate so it will display the following screen as below:
Go to Manu bar Document Post so it will post the above document to tables with the reference an document number a bellow:
177
In the above screen maintain the above information and click on It will display the following screen with information:
button.
178
In the above screen I maintain the Document Date, Posting Date, Company Code, Currency/Rate, PstKy (Posting Key), Account (Customer Account number). Once you maintain all above click enter button so it will display another screen as follow:
In the above screen maintain the amount, PstKy, Account (Sales Account) and pres enter button so it will display another Screen. In the following screen click on button. So it will display the following screen:
179
In the above screen maintain above parameters and pres in enter button.
180
To post go to Manu bar Document - Post So it will post with as Document number.
In the above screen maintain the above information and click on It will display the following screen with information:
button.
181
182
183
COMPONENTS OF COST 5. 6. 7. Material Cost Process or Conversion cost Overheads Manufacturing or Production Overheads Administrative Overheads Selling and Distribution Overheads
Product Cost Planning (CO-PC-PCP) is an area within Product Cost Controlling (CO-PC) where you can plan costs for materials without reference to orders, and set prices for materials and other cost accounting objects. You can use Product Cost Planning to analyze the costs of your companys products such as: Manufactured materials Services Other intangible goods
You can analyze costs to help provide answers to questions such as: What is the value added of a particular step in the production process? What proportion of the value added can be attributed to a particular organizational unit? What is the cost breakdown including primary costs or transfer prices? How high are the material, production, and overhead costs? How can production efficiency be improved? Can the product be supplied at a competitive price?
Product Cost Planning comprises the following components: Cost Estimate with Quantity Structure Cost Estimate Structure Price Update without Quantity Costing materials based on a quantity structure in PP Costing materials without a quantity structure in PP
Transferring the results of material cost estimates to the material master Planning new products and services using base planning objects Rapid cost planning without master data within an ad hoc cost estimate
Reference and Simulation Costing Easy Cost Planning and Execution Services
For further information, see the following: Purpose of Product Cost Planning Costing Sequence
184
Features
The following table gives you an overview of the menu and functions of Product Cost Planning:
Menu Option Material Costing Edit Costing Run Material Costing Cost Estimate with Quantity Structure Material Cost Estimate with Quantity Structure Additive Costs Material Costing Cost Estimate Without Quantity Structure Reference and Simulation Costing Easy Cost Planning & Execution Services Edit Ad hoc Cost Estimate
Function Cost estimate for multiple materials with BOM and routing Cost estimate for a material with BOM and routing or master recipe
Cost Estimate Used to process mass data, and is created automatically with Production Planning data (product cost estimate) Created automatically with Production Planning data (product cost estimate)
Created using data you enter manually (unit costing) or transfer from a non-SAP system Created using data you enter manually (unit costing) ... Created using a planning form (costing model) that can access the data in the SAP system
185
Definition of procurement alternatives and mixing ratios for a mixed cost estimate
Examples Lists of existing material and base object cost estimates Detailed reports Comparison reports Archiving and deletion of costing data Distribution of cost component splits (ALE)
Environment
in
186
Maintain all possible parameters while you creating finished goods In the above selections Forecasting is mandatory selection view to selection and to maintain some of the fields in that screen.
187
In the above screen provide your Raw Material number, plant, BOM Usage, Valid From and pres enter button so it display actual screen as below:
In the above screen under components provide all raw materials and quantities which are used to produce a finished good in this BOM. Now save the activity. It will display the following message: Back to easy access.
188
In the above screen enter your plant, new entry for Work center and Work center Category and pres enter button so it will take you to another screen below:
189
In the above screen under Tab Basic data enter Location, usage and Standard value key. After entering above parameter click on Tab Costing. So it will display following screen:
In the above screen enter Start Date, Cost center. Under Activities Overview table enter Activity type, Activity unit and Formula key which are standard in sap. Now save the activity so it takes you to first screen as below:
190
In the above screen new Work Center and click on enter button so it will display below screen:
In the above screen under Tab Basic data enter Location, usage and Standard value key. After entering above parameter click on Tab Costing. So it will display following screen:
191
In the above screen enter Start Date, Cost center. Under Activities Overview table enter Activity type, Activity unit and Formula key which are standard in sap. Now save the activity so it takes you to first screen as below:
In the above screen new Work Center and click on enter button so it will display below screen:
192
In the above screen under Tab Basic data enter Location, usage and Standard value key. After entering above parameter click on Tab Costing. So it will display following screen:
In the above screen enter Start Date, Cost center. Under Activities Overview table enter Activity type, Activity unit and Formula key which are standard in sap.
193
A routing is used as a source for creating a production order or a run schedule header by copying. Routings enable you to plan the production of materials (products). Therefore, routings are used as a template for production orders and run schedules as well as a basis for product costing. Integration In order to Plan the usage of materials Plan the use of work centers Plan the external processing of operations Plan quality inspections that accompany production Prepare cost routings calculation according to You also require the components Material master (LO-MD-MM) Work centers (PP-BD-WKC) Purchasing (MM-PUR) Quality planning (QM-PT) Controlling (CO) Engineering Change Management (LO-ECH) Classification system (CA-CL) CAPP Standard Value Calculation (PP-BD-CAP)
Plan and to document changes to routings Classify routings Automatically calculate the planned values for the activities to be produced
In the SAP system, routings have the same basic structure as the following objects: Master recipes Inspection plans Maintenance plans Standard networks Therefore, routings are cumulated with these objects under the super ordinate term Task list. In a routing you plan The operations (work steps) to be carried out during production The activities to be performed in the operations as a basis for determining dates, capacity requirements, and costs The use of materials during production The use of work centers The quality checks to be carried out during production
194
In the above screen assign your Raw material number, plant and Key date details and pres enter button so it take to another screen as below:
In the above screen maintain usage and Status and click on as below:
195
Inter above screen enter work centers as we created above screen and select PP01as Control key for all Work centers under Control Key field. Now select first line 0010 as shown above and double click on Control key PP01 against 1000 Work center so it will display following screen:
In the above screen maintain Setup, Machine, Labor values under Std Value and Un values and pres take you to following screen:
back button so it
In the above screen select 0020 and double click on PP01 under Control Key field so it display the following screen:
196
In the above screen maintain Setup, Machine, Labor valued under Std Value and Un values and pres take you to following screen:
back button so it
In the above screen select 0030 and double click on PP01 under Control Key field so it display the following screen:
In the above screen maintain Labor value under Std Value and Un values and save the activity so it will display the following message:
197
These contain the amount or quantity on which the overhead is calculated. Base rows contain the calculation base of the overhead costing: the cost elements and origins to which overhead is to be applied you can take the calculation bases directly from the costing sheet and then maintain them as necessary. For each controlling area, you assign individual cost elements or cost element intervals, or organs or origin intervals, to the calculation bases. For production overhead costs, we can differentiate between fixed and variable costs for the calculation base. In this way, you can charge the fixed and variable portions of the activity price differently for activity types. For material overhead cost, you can differentiate the materials used. If you want to define different material overhead costs for particular raw materials we can define origin groups and define your own calculation bases for particular or origin groups. 2. 3. Calculation Lines These contain the percentage rate to be applied to one or more baselines Total Lines These contain the sum of the base amount and calculated amounts. Overhead Order and Product Cost Controlling
4.
Where they used to calculate overhead. We define the overhead rows by assigning an overhead rate to them. An overhead row references one or more base rows or totals rows. The amount contained in these rows along with the percentage rate calculated using the overhead rates determines the overhead amount. You can take the overhead rates directly from the costing shet and then maintain them as necessary, or define them separately. The overhead row contains a credit key that defines which object is credited during the overhead calculation. You can either take the credit keys directly from the costing sheet and then maintain them as necessary, or define them separately in the define credit activity. 5. 6. Profitability analysis, where they are used to calculate anticipated values Overhead cost controlling, where they are used to calculate resource pries
Path: SPRO Controlling Product Cost Controlling Product Cost Planning Basic Settings for Material Costing Overhead Define Costing sheet rows Transaction Code: KZS2 Database table: T683, T683S, T683T, T683U, TKZU1, TKZU2, TKZU3, TKZUTR By the above transaction it will display the following screen pres on button:
198
In the above under Costing field give new entry and description and save the activity. Now select the same and click on Costing Sheet Rows under Dialog Structure. It will display the following screen: In following screen first pres button.
In the above screen maintain above table and select firs row 10 and click on Base under Dialog Structure. So it will display the following screen: It will ask for Controlling area in a small box enter it and pres enter button. In following screen first pres button
In the above screen enter cost elements range and double click on Costing sheet rows under Dialog Structure so it will display the following screen:
199
Now in the above row select row 30 and double click on Base under Dialog Structure, so it will display the following screen: It will ask for controlling area in a small box enter it and pres enter button. In following screen first pres button
In the above screen enter cost elements range and double click on Costing sheet rows under Dialog Structure so it will display the following screen:
Now in the above row select row 50 and double click on Base under Dialog Structure, so it will display the following screen: It will ask for controlling area in a small box enter it and pres enter button. In following screen first pres button
200
In the above screen enter cost elements range and double click on Costing sheet rows under Dialog Structure so it will display the following screen:
In the above screen select row 20 and double click on Overhead rate under Dialog Structure. So it will display following screen: In following screen first pres button
In the above screen maintain Overhead rate table and click on Costing sheet rows Rows under Dialog Structure. So it will display the following screen:
201
In the above select Row 20 and click on Credit under Dialog Structure. So it will display the following screen: It will ask for Controlling area in a small box enter it and pres enter button. In following screen first pres button
In the above screen under Credit table maintain the above parameters and click on Costing sheet rows under Dialog Structure. So it will display the following screen:
In the above screen select row 40 and double click on Overhead rate under Dialog Structure. So it will display following screen: In following screen first pres button
202
In the above screen maintain Overhead rate table and click on Costing sheet rows Rows under Dialog Structure. So it will display the following screen:
In the above select Row 20 and click on Credit under Dialog Structure. So it will display the following screen: It will ask for controlling area in a small box enter it and pres enter button. In following screen first pres button
In the above screen under Credit table maintain the above parameters and click on Costing sheet rows under Dialog Structure. So it will display the following screen:
203
In the above screen maintain Overhead rate table and click on Costing sheet rows Rows under Dialog Structure. So it will display the following screen:
In the above select Row 20 and click on Credit under Dialog Structure. So it will display the following screen: It will ask for controlling area in a small box enter it and pres enter button. In following screen first pres button
After maintain above Credit table save the activity and back to SPRO screen.
204
FI/CO MATERIAL VERSION ECC 6.0 Material Cost Estimate with Quantity Structure
Purpose Costing with a quantity structure is a tool for planning costs and setting prices for materials without reference to orders. It is used to calculate the cost of goods manufactured and cost of goods sold for each product unit. You can use the results of material cost estimates with a quantity structure to valuate materials at standard prices. Implementation Considerations Before a cost estimate with a quantity structure can be created, a bill of materials and routing (PP) or a master recipe (PPPI) must exist for the material being costed. A cost estimate with a quantity structure uses the PP or PP-PI master data to determine the materials and internal activities required to manufacture the product. The cost estimate is created automatically using this data.
Calculation of (Cost of Goods Manufactured) COGM and (Cost of Goods Sold) COGS
You can use the Product Cost Planning functions to calculate the cost of goods manufactured (COGM) and cost of goods sold (COGS) for products such as materials and services. The costs may then be analyzed and used in business decisions (such as whether to make or buy). The cost of goods manufactured is composed of material and production costs, process costs and overhead (such as material and production overhead). The cost of goods sold consists of the cost of goods manufactured together with sales and administration overhead costs. The following graphic shows how the COGM and COGS are calculated using Product Cost Planning:
To calculate the COGM and COGS for materials, you can execute a material cost estimate (with or without quantity structure).
To calculate the COGM and COGS for products that do not have any master data (such as services or materials at the planning stage), you can avail yourself of the Reference and Simulation Costing functions. For further information, see the following:
Material Cost Estimate with Quantity Structure Material Cost Estimate Without Quantity Structure
Before costing, check all the settings in Customizing for Product Cost Planning that apply to the calculation of costs. For further information, see the following:
205
You can use the following reports in the Product Cost Controlling Information System to analyze the costs:
Cost Component Reports (Cost Component Display) Itemization Costed Multilevel BOM
A costing variant for material cost estimates contains additional control parameters, such as for automatic determination of the quantity structure and for updating the prices in the material master. The costing variant contains all the control parameters for costing. The costing variant for a material cost estimate contains the following control parameters: Costing type Valuation variant ate control Quantity structure control (only relevant for cost estimates with quantity structure) Transfer control (optional) Reference variant (optional)
Since this costing variant can be used for cost estimates both with and without quantity structure, you must also make the settings that are only relevant for cost estimates with quantity structure even if you are only executing a cost estimate without quantity structure. In Quantity structure you determine the following: o How the costing lot size is handled o Whether cost estimates without quantity structure are included (
206
207
In the above screen select PPC1 Costing Variants and click on Details button as I shown in above screen. It displays the following screen:
208
In the above screen first go to tab Overhead in this tab you can view tow Buttons 1. Costing Sheet (Overhead on Finished Goods, Semi Finished Goods), 2. Costing Sheet (Overhead on Material Consumption). 1) Agents 1st button Costing Sheet (Overhead on Finished Goods, Semi Finished Goods) drag the button and select your Costing sheet (in above case it is 1102 1102 Cost of goods Manufacturi) 2) Agents 2nd button Costing Sheet (Overhead on Material Consumption) drag the button and select your Costing sheet (in above case it is 1102 1102 Cost of goods Manufacturi) So it will be as bellow:
209
Now click on save button to save the activity and back to SPRO screen.
Cost Component
The costs from a cost estimate are assigned to cost elements and cost components. The following graphic illustrates how cost components, cost component structures, and cost views are customized:
210
Cost components are grouped into a cost component structure. A cost component structure can have up to 40 cost components. However, if the cost components contain both fixed and variable costs, the number of costs components is limited to 20. Examples of cost components are: Raw materials Personnel costs Production costs Overhead: material Overhead: production Overhead: administration Overhead: sales and distribution External activities
Other costs If you are using a particular costing variant, the system determines the cost component structure for this costing variant and creates the cost component split for the costing results accordingly. All costing variants for the standard cost estimate in a company code must be linked to the same cost component structure. Otherwise you cannot transfer costing results from other plants for specially-procured materials. For costing variants that are not set for the standard cost estimate, you can assign the cost component structure separately for each plant or for each costing variant. The values for each cost component are updated in the currency of the company code to which the material is assigned.
Specifies which costs are contained in the cost component split. You can use the cost component structure to specify that certain costs: Remain visible in the cost estimate Are passed on to Profitability Analysis You can define a cost component structure so that the cost estimate for a finished product shows the origin of the costs for the semifinished products and raw materials. You can define the cost component structure to have a validity period. You can specify the date from which the structure is to be valid. This means that you can use an alternative cost component structure for the cost estimate without having to change an existing structure. In addition, cost estimates that have already been saved can still be interpreted by the system.
211
Path: SPRO Controlling Product Cost Controlling Product Cost Controlling Basic Settings for Material Costing Define Cost Component Structure Transaction Code: OKTZ Database Table: TCKH1, TCKH2, TCKH3, TCKH4, TCKH5 By the above path it display the below screen:
in the above screen select 01 under Cost Comp.Str field and double click on Assignment: Cost Component Cost Element Interval. An new window will display as below: In this window click on .
212
In above screen main table with cost elements and cost components. Now double click on Cost Components with Attributes under Dialog Structure So it will display following screen:
In the above screen double click on Raw Materials so it will display the following screen:
213
In the above screen select Active check box for Cost.Comp.Str - 01. Save the screen and back to SPRO screen.
The cost estimate with quantity structure enables you to calculate the non-order-related cost of goods manufactured and the cost of goods sold for products, based on the BOMs and routings (PP). Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing Cost Estimate with Quantity Structure CK11N Create Enter into above transaction so it will display the following screen:
In the above screen enter your Finished good number, plant, Costing variant as PPC1 (Standard Cost Estimation) and Costing Version as 1
214
In the above screen under Tab Dates for Costing Date from, Qty Structure Date, Valuation Date should maintain future dates and Costing Date To should be maintain last date of plan of production. Now pres enter button. So it will show the following screen:
215
Mark the standard cost estimate Release the standard cost estimate Release a new standard cost estimate. The current standard price becomes the previous standard price.
You can use the results of the standard cost estimate to valuate the materials for standard prices (see graphic). When you release the standard cost estimate, the price in the material master is updated as the standard price and the materials are revaluated. From this point on, all the material movements are valuated at the new price. However, this applies only to materials with S price control. Costing can access the future or current standard price in the material master for material valuation purposes, provided you have defined the appropriate strategy in the valuation variant in Customizing for material valuation (see graphic). For more information, see Define Valuation Variants in the Implementation Guide for Product Cost Planning.
Prerequisites To update the standard cost estimate results as the standard price in the material master record, the following conditions must be met: The cost estimate has the status KA: Costed without errors. Only the results of cost estimates without errors can be updated. The costing results have been saved to the database. To be able to save a cost estimate, you must ensure that the indicator Saving allowed is turned on in the costing variant. The setting has been made to update the costing results as the standard price. For this, the indicator Standard price indicator must be turned on in the costing type. In addition, the costing type must also specify that the date of costing is saved to the database, and that this date is always the start of period.
The period of validity of the cost estimate (Costing date from) must correspond with the current period in the material master. You cannot update the standard price for periods that have elapsed. To release the costing results, you must wait until the relevant posting period has arrived.
216
To set a new standard price in the material master, you must mark and release the standard cost estimate. Before you can mark and release a standard cost estimate, you must allow standard cost estimates to be marked and released in a company code. If you mark a standard cost estimate for a material, the price calculated in the standard cost estimate is transferred into the material master record as the future standard price (see graphic). However, the materials with "S" price control continue to be valuated with the current standard price (see graphic). If you release a standard cost estimate for a material, the marked price is transferred into the material master record as the current standard price for the current period. This price is then active for external accounting. The materials with "S" price control are valuated with the new standard price. The current standard price becomes the previous standard price (see graphic). You can repeat the marking at any time. However, this can only be done once in a period. For this reason, you should check the costing results before marking and releasing. To do this, use the reports in the Product Cost Controlling Information System. You can use the Information System to make comparisons, such as using a price from the material master, or the future or current standard price, to the costing results. This enables you to correct any variances before the materials are valuated with the new standard price. Once you have released the cost estimate, you cannot create a new standard cost estimate in this period. Although you can delete a released cost estimate, the materials are still valuated with the released standard price. When a current standard cost estimate is deleted, the previous standard price no longer becomes the current standard price. To determine a new standard price, you have to carry out costing, marking and releasing afresh. Marking, releasing, and marking allowance are protected by authorization checks. The person authorized to execute these functions must enter the authorization object K_FVMK (CO-PC: Release/marking product costing) in the user master record. Path: Accounting Controlling Product Cost Controlling Product Cost Planning Material Costing CK24 Price Update By above transaction it displays the following screen:
217
In the above window give future month periods details in Posting period/Fiscal year field and provide information to Company code, plant, Material and click on button so it will display the below screen:
In the above screen click on your company code so it will display an small sindow in that window select PPC1 as Costing variant and save the activity and back to main sceen.
218
Features
You can use the production order to specify: What is to be produced? When production is to take place Which capacity is to process the order? How much production costs?
219
220
We define the data that influences master data selection or order master data maintenance: You can decide whether production versions are selected automatically or manually. The task list application is predefined as 'P'. However, you can also specify an additional task list application. The routing selection ID defines, for example, the ranking order for routing selection. Routing selection defines whether routings are to be selected and if so, how (manually or automatically) and whether reference operation sets can also be selected. Alternative sequences and sequence exchange define whether alternative sequences are permitted and how the sequences are to be exchanged. The task list type defines which routing type is permitted for production orders. Operation check defines whether operation detail screens are to be checked when the operations are transferred to the order. Routing text defines that the text from the routing header is copied into the order. You can activate the entry tool for operations to help you when you create operations. BOM application defines how the BOM alternatives are to be automatically selected.
Path: SPRO Production Shop Floor Control Master Data Order Define order type-dependent parameters Database table: T399X By the above transaction it will display the following screen: In the displayed screen click on button so it will display the following window:
In the above window take plant as 1000 and Order Type as PP01 and click on continue button or click on enter, so the selection plant 1000 will appears on the top of the window as below:
221
These fields contain 101 as value. Delete that and keep it blank
In the above screen change Plant value to your plant value in above case my plant is 1102and Reduction Strategy under Operation, Substitute MRP ctrller , Substitute Scheduler under Assignment should blank, so delete the values in these fields. Now pres enter button so it will display previous screen now click on (save) button and back to SPRO screen.
222
FI/CO MATERIAL VERSION ECC 6.0 Step 11: Define Checking Control
You can make the checking rule as well as the actual check itself dependent on the following parameters: Plant Order type Operation The operation can have the following characteristics: Order created release (d) order Whether an availability check is to be carried out when you create or release an order Whether an availability check is to be carried out when you save an order that has been created or released Which checking rule is to be used? What affect a material shortfall is to have on the creation or release of an order
Path: SPRO Production Shop Floor Control Operations Availability Check Define Checking Control Transaction code: OPJK Database table: TCO11 By the above transaction it will display the following screen:
In the above window take plant as 1000 and order type as pp01 and pres enter button so it will display those values at the top to window as below:
Now like above screen showes select two values 1) 1000 (Plant), PP01 (Type) 1 (Business Function); 2) 1000 (Plant), PP01 (Type), 2 (Business Function) and click on (Copy) button. So it will display below screen.
223
In the above screen to Plant field give your plant number and other all parameters are same and pres enter button so it will display another screen as below:
In the above screen to Plant field give your plant number and other all parameters are same and pres enter button so it will display another screen, save the activity and back to SPRO screen. Step 12: Define Scheduling
the scheduling function calculates the production dates and capacity requirements for all operations within an order or a collective order. A system function that determines the start and end time of a service assignment. Scheduling is based on the start and end time and estimated duration of a service task, taking availability information for the service employee into account. Scheduling can be performed manually by the resource planner for the service center, or be executed by the system according to certain specifications. Transportation and Distribution (IS-OIL-DS-TD) The main objectives of the scheduling function of IS-Oil downstream are as follows: Group deliveries into shipments Assign shipments to an appropriate vehicle Optimize grouping of deliveries and shipment processing with respect to cost, efficiency, and customer service.
Production Planning and Control (PP) The system calculates the start and finish dates of orders or of operations in an order. Scheduling is performed in:
Material requirements planning: In-house production times and delivery times specified in the material master record are taken into account. Capacity planning: Scheduling is performed using routings. A distinction is made between lead time scheduling in which capacity loads are not taken into account, and finite scheduling in which capacity loads are taken into account.
224
Scheduling types include: Forward scheduling: scheduling starting from the start date Backward scheduling: scheduling starting from the finish date Scheduling to current date: scheduling starting from the current date "Today" scheduling: a scheduling type for rescheduling an order if the start date is in the past
Path: SPRO Production Shop Floor Control Operations Scheduling Define Scheduling Parameters for Production Orders Transaction code: OPU3 Database table: TCX00 By the above transaction it will display the following screen: In the displayed screen click on button so it will display the following window:
In the above small window provide required parameters as above and pres enter button so it will display the those at the top of window:
225
Step 12: Define Confirmation Parameters We define the confirmation parameters for each plant and order type. The parameters are split up as follows on tab pages o Control The properties of the control key Process control are defined elsewhere in Customizing (it can also be called using the symbol next to the control key). It controls the execution of the confirmation processes. You can define how quantities are determined for automatically generated confirmations (milestone/progress confirmation).
What happens when the sequence of operations is not adhered to during confirmation or What happens when you want to confirm a larger quantity than was confirmed for the preceding operation You can choose between a termination message, an error message, a warning message and an information message. whether you want the total confirmed quantity of an operation checked for under delivery or over delivery tolerance in the order header What effect a QM result recording has on the confirmation. whether dates (for example, posting date, end of lead time, etc) should also be displayed with a date that is further in the future than the time of creation
o Selection
You specify that only open orders are selected in the collective order.
o Propose time units You can select a time unit that is to be proposed during confirmation.
o Goods movements Using the all components indicator, you can specify that the system should display all the components assigned to the operation in the goods movement overview (in other words, not only back flushed components). However, if you do not branch to the material overview at confirmation, the system only posts back flushed components.
226
o Error handling/logs
You can use the indicator Actual costs to specify that the log is also displayed if there are no error messages (thus only warnings or information messages). You can use the Error handling indicator to specify that an error log is displayed for incorrect items in goods movements (for back flush or automatic goods receipts). You then have another opportunity to correct the items with errors before saving, with the aid of the material overview. Define the confirmation parameters for each plant and order type.
Path: SPRO Production Shop Floor Control Operations Confirmation Define Confirmation Parameters Transaction code: OPK4 Database table: TCORU By the above transaction it will display the following screen: In the displayed screen click on button so it will display the following window:
In the above window take plant as 1000 and Order Type as PP01 and click on continue button or click on enter, so the selection plant 1000 will appears on the top of the window as below:
In the above screen change plant number to your plant number and pres on enter button. It will display the previous screen with your plant. Now save the activity and back to SPRO screen.
227
FI/CO MATERIAL VERSION ECC 6.0 Step 13: Check Costing Variants for Manufacturing Orders (PP)
The costing variant contains the control parameters for the cost estimate. In this step you check the costing variants that are used for the following in Product Cost by Order: o For the preliminary costing of manufacturing orders o For the simultaneous costing and final costing of manufacturing orders The SAP standard system contains the following costing variants for manufacturing orders: 1) PPP1 Production Order - Plan These costing variants consist of the following: - Costing type 06 - Production Order Plan This costing type specifies that the costing results are updated as planned costs.
This valuation variant controls which prices are used for the valuation of materials, external activities and subcontracting and which activity prices are used for the valuation of activity types and business processes. Furthermore, the costing sheet that you assign to this valuation variant is defaulted into the master data of the manufacturing order. This costing sheet is used for overhead calculation in preliminary costing for the manufacturing order and actual overhead calculation in period-end closing. 2) PPP2 Production Order Actual Costing Type 07 - Production Order, Actual
This costing type specifies that the costing results are updated as actual costs.
This valuation variant determines which activity prices are used to valuate the activity types and business processes on which the following activites are performed in the actual data: - Manual allocation - Automatic allocation through confirmation in PP - The manufacturing order is charged through the template allocation
Note: While it is technically possible to have two costing variants with the same costing type and valuation variant, this should be avoided to prevent data from being overwritten. This is because the key structure for the costing results in the database uses the costing type and the valuation variant, rather than the costing variant.
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Manufacturing Orders Check Costing Variants for Manufacturing Orders (PP) Transaction code: OPL1 Database table: TCK05, TCK06 By the above transaction it will display the following screen:
228
In the above screen select PPP1 Costing Variant and double click on that, so it will display the following screen:
In the above screen first click on Overhead tab. In this screen against Costing Sheet button assigh your Costing sheet as above shown. Now save the activity and back to SPRO screen. Step 14: Define Goods
This step is only relevant if your have specified price control V in the material master records of semifinished products or finished products. In this step you specify how the receipts for materials with price control V are valuated. When the master record of a material specifies price control V, the value for the credit is determined using a valuation variant. You must define this valuation variant separately for each valuation area. The valuation variant determines which material price is used for the credit posting. For materials with price control S, on the other hand, the credit posting is always made at standard price.If you deliver to stock at a price that is not the standard price, the system will report an output price variance in variance calculation.
229
In the above screen give your plant number under Val.Area and Val.Var as 007. Now save the activity and back to SPRO screen.
Step 15:
A key specifying that the object is to be selected during results analysis or when work in process is calculated. A number of valuation control parameters are linked to this key. whether results analysis is revenue-based, quantity-based or manual On which basis (planned or actual data) results analysis is carried out How profits are realized whether the inventories, reserves and cost of sales are to be split
Each order for which you want to create work in process (WIP) must receive a results analysis key. The presence of a results analysis key in the order means that the order is included in WIP calculation during period-end closing. The results analysis key can be specified as a default value for each order type and plant. It is then added to the order master record when an order of a particular order type is created. For each combination of controlling area, results analysis version, and results analysis key, you then later specify the valuation methods according to status. You can also assign the source cost elements under which an order is debited to different line IDs for each results analysis key. This updates the results analysis data under different results analysis cost elements. This is recommended when you are using multiple results analysis methods in parallel. For example, if you calculate work in process at actual costs in the Product Cost by Order component and want to calculate results analysis data in the Product Cost by Sales Order component, the results analysis data is updated under results analysis version 0. To enable different groupings of costs, you update the results analysis data according to the results analysis key. Whether you update the results analysis data according to the results analysis key is defined in the results analysis version. WIP calculation determines the value of the unfinished products in the Product Cost by Period component and in the Product Cost by Order component. WIP calculation in Product Cost by Order or Period is used chiefly in make-to-stock production, sales-order-related production with a valuated sales order stock, and engineer-to-order environments with a
230
If no results analysis key is specified in the order, the actual costs for the order are included in results analysis for the sales order or project. Settlement is through the sales order or project. If a results analysis key is specified in the order, work in process is created and settled for the order in the amount of the actual costs incurred. These costs are not included in results analysis for the sales order or project. This method is particularly recommended when you are manufacturing across company codes.
You control whether a sales order stock or a project stock is valuated or non valuated in the requirements class. Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order PeriodEnd Closing Work in Process Define Results Analysis Keys Transaction code: OKG1 Database table: TKKAA, TKKAD By the above transaction it will display the following screen, click on button.
In the above key enter RA Key and Text. Now save the activity and back to SPRO screen. Step 15: Define Results
Analysis Versions
A version that enables multiple valuations of the same object (such as a sales order item) in results analysis and in the calculation of work in process. Example For balance sheet purposes, the object is valuated using a method that determines the value of the unfinished products on the basis of the actual cost incurred to date. For internal analysis purposes, the value of the unfinished products is determined using a method that includes unrealized profits.
All results analysis data (work in process in the Product Cost by Period component, and work in process or reserves for unrealized costs in the Product Cost by Order component) calculated in results analysis is updated on the order with reference to the results analysis version. This enables you to calculate work in process on the basis of multiple results analysis versions simultaneously. This means that you can use different results analysis versions to do the following:
231
FI/CO MATERIAL VERSION ECC 6.0 Define different methods of WIP calculation You can create results analysis versions along with operational
valuation that are based an "internal" results analysis version created for internal purposes, rather than on multiple valuation. This means that you can use different results analysis versions to: Define different methods of WIP calculation Define different amounts of work in process to be capitalized If you are operating in different countries, you can Define different results analysis versions to take into account the different legal requirements in each country.
Calculate work in process at actual costs in up to three valuation views in the Product Cost by Order component If you are using transfer prices, you can calculate the results analysis data in the following valuation views: Legal view Group view Profit center view
In the Product Cost by Period component, the work in process at target costs is always calculated in the operational valuation view. Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order PeriodEnd Closing Work in Process Define Results Analysis Versions Transaction code: OKG9 Database Table: TKKAP, TKKAT By the above transaction it will display the following screen, click on button.
In the above screen when you click on New Entries it will display an Restrictions window. In that window double click on your Controlling area. So it will display the following window:
232
In the above window against Technical RA Cost Element assign your Secondary Cost element as I shown in above window. Now save the activity and back to SPRO screen. Step 17: Define Valuation
In this step you define a valuation method for the calculation of work in process. This creates the link between the controlling area, the results analysis key, the results analysis version, and the system status. When you create new valuation methods, you specify whether the work in process should be valuated at target costs or actual costs. Work in Process at Target Costs In the Product Cost by Period component the work in process is valuated at target costs. The valuation is made on the basis of the quantities confirmed at the operations or reporting points. The system determines the following in each period: - Which materials were delivered to stock - Which materials were confirmed at the operations - Which materials and activities are not included in WIP calculation due to scrap confirmations at subsequent operations In the period-end closing activities in the Product Cost by Period component, the relevant quantities (WIP quantities) are valuated according to the valuation variant for work in process and scrap (target costs) and reported as work in process. Work in Process at Actual Costs In the Product Cost by Order component the work in process is normally valuated at actual costs. The value of the work in process is the difference between the debit and the credit of an order as long as the order has the status PREL (partially released) or REL (released). Work in process at actual costs The following status codes are relevant for WIP calculation in this component:
233
If the status is PREL or REL, the system creates work in process in the amount of the actual costs with which the order is debited. If the status is DLV or TECO, the system cancels the work in process. The difference between the debit through actual costs postings and the actual credit of the order from goods receipts is interpreted as a variance with this status. If you want to calculate the work in process at actual costs, create a valuation method for each combination of controlling area, results analysis version, and results analysis key for the statuses that are relevant to WIP calculation. This valuation method must specify the following: How the work in process should be calculated when the order status is PREL How the work in process should be calculated when the order status is REL How the work in process should be calculated when the order status is DLV How the work in process should be calculated when the order status is TECO
If you valuate the work in process at actual costs, you must make sure that the work in process that is created and settled in a period can be canceled at a later time. You do this by defining valuation methods for the cancellation. Work in process at target costs In the Product Cost by Period component, the status management functionality is reduced. In the Product Cost by Period component, the following statuses are relevant in WIP calculation: o PREL - The order is partially released. An order is partially released for which the individual operations are released. o REL - The order is released When an order has the status PREL and REL, in the Product Cost by Period component the system creates work in process by multiplying the WIP quantity by the target costs in accordance with the valuation variant for work in process and scrap (target costs). If you want to calculate work in process at target costs, then for each combination of controlling area, results analysis version, and results analysis key, you must specify a valuation method for the statuses relevant to WIP calculation. Proceed as follows:
For the status PREL, enter the status number 1. The system generates a valuation method of results analysis type S (calculate work in process based on the target costs). For the status REL, enter status number 2. The system generates a valuation method of results analysis type S (calculate work in process based on the target costs).
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order PeriodEnd Closing Work in Process Define Valuation Method (Actual Costs) Transaction code: OKG3 Database Table: TKKAS, TKKAS_L By the above transaction it will display the following screen, click on button.
234
In the above Valuation type window click on Actual Costs so it will display the following screen:
In the above window maintain parameters as in shown and click on continue button or click on enter button so it will take you to previous screen: Now again click on button, it will display the Valuation type window.
In the above Valuation type window click on Target Costs so it will display the following screen:
In the above window maintain parameters as in shown and click on continue button or click on enter button. Save the activity and back to SPRO screen. Step 18: Define Line IDs In this step you create line IDs. The line IDs group the work in process and reserves for unrealized costs according to the requirements of Financial Accounting.
235
In the above screen maintain above 3 parameters. Save the activity and back to SPRO screen. Step 19: Define Assignment 1. Determine which cost elements you have to assign to line IDs. To display the cost elements valid in your controlling area, go into Cost Center Accounting and select Reporting -> Master data index -> Cost elements.You must also assign settlement cost elements that you use in the allocation structure to a line ID. Example: Suppose you are using a nonvaluated sales order stock. You have not selected Settlement by cost element in the allocation structure. The system settles the actual costs charged to manufacturing orders to a sales order item. Settlement is made under a settlement cost element that you have specified in the allocation structure. You must assign this settlement cost element to a line ID. 2. Enter the controlling area, your results analysis version and, if necessary, your results analysis key. 3. Enter the cost elements, as in your cost element list, under which the primary postings are to be written to the orders, or to the standard cost estimate. You can mask these entries. If you enter 00004+++++, for example, all cost elements from 400000 to 499999 will be included. If you want particular cost elements to be treated separately, enter them without masking (example: 0000415000). Numeric values must be entered right-justified. Alphanumeric values must be entered left-justified. For material costs, you can define separate line IDs for particular origin groups by entering origin groups in the costing views of the relevant material master records, and entering these origin groups with the relevant cost elements in the line IDs. If you don't want to differentiate the line IDs by origin group, mask the origin group (i.e., enter ++++). 4. Enter the secondary cost elements under which internal cost allocations are written to the orders or under which the cost estimate on which the the target cost calculation is based are updated. For production costs, you can define separate line IDs for particular cost centers, or cost centers and activity types, by entering a cost center and an activity type for secondary cost elements. If you want to differentiate the production costs only by cost elements, mask the cost center and activity type with ++++. If you want to create separate line IDs for the fixed and variable costs from Cost Center Accounting, you can enter "V" or "F" in the var-fixed costs column.
236
After maintaining the above parameters save the activity and back to SPRO screen. Step 20: Define
Update
If you use a results analysis version that is in the standard system, you only have to enter the results analysis cost elements for the data to be calculated. 1. Enter the following: - Controlling area - Results analysis version - Results analysis key If you defined, in the results analysis version, that the update is to be carried out without reference to the results analysis key, the entry is blank. 2. Enter the following data for each line ID: - The category (K, A, or N)
237
238
After maintaining the above parameters save the activity and back to SPRO screen.
In this step you specify the G/L accounts in Financial Accounting to which the work in process is settled. You assign a results analysis cost element or a group of results analysis cost elements to two G/L accounts. A posting document is generated in Financial Accounting on the basis of the settlement of work in process. o Data is written to the balance sheet. o Data is written to the profit and loss statement. If you have specified a profit center in the order (product cost collector or manufacturing order) the data is also forwarded to Profit Center Accounting. You can assign the results analysis data to the G/L accounts at the following levels: o Results analysis categories The results analysis categories are created on the basis of the assignment of the costs to line IDs: - WIPR - Work in process with requirement to capitalize costs - WIPO - Work in process with option to capitalize costs - WIPP - Work in process with prohibition to capitalize costs
239
Path: SPRO Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order PeriodEnd Closing Define Posting Rules for Settling Work in Process Transaction Code: OKG8 Database Table: TKKAB By the above transaction it will display the following screen, click on button.
240
After maintaining the above parameters save the activity and back to SPRO screen. Step 22: Creation
of Production Order
When a production order is created the following actions are carried out: A routing is selected, its operations and sequences are transferred to the order The bill of materials is exploded and the items in the bill of material are transferred to the order Reservations are generated for bill of material items held in stock The planned costs for the order are generated The capacity requirements are generated for the work centers Purchase requisitions are generated for non-stock items and externally-processed operations A production order specifies which material is to be produced, where it is to be produced, which operations are required to do this and on which date production is to take place. It also defines how the order costs are to be settled. As described in this procedure, production orders can be created manually without being previously requested. Alternatively, they can be automatically created by converting a planned order. During requirements planning (MRP run), planned orders are created at every BOM level to cover requirements. For materials produced in-house, a secondary requirement is also generated when the BOM is exploded, which is necessary for producing the end product or assembly. For externally produced materials, an ordering transaction is initiated when a purchase requisition is generated. Planned orders generated in the MRP run can be converted individually into production orders from the current stock/requirements list. They can also be grouped together by the MRP run and converted into production orders together. These production orders can be released together.
Date on which the required quantity of the material is available (requirements date) Earliest date on which order execution can start Key which specifies the
Retain, if necessary
D R
241
Priority of an order, for information purposes Key with which the system determines the required floats (opening period, float after production, float before production, release period)
Path: Logistics Production Shop Floor Control Order Create CO01 - With Material Transaction Code: CO01 By the above transaction it will display the following screen:
242
In the above screen enter Total quantity to be produced and under Dates enter future dates to Finish, Start and pres enter button. It will give you a message:
Now go to Manu bar Goto Cost Cost comp. structure By the above it will display the following table:
243
Make a note of the order number and back to easy access screen. Step 22: Goods
Movements
Path: Logistics Production Shop Floor Control Goods Movements MB1A - Goods Issue Transaction Code: MB1A By the above transaction it will display the following screen:
In the above screen give Movement Type is 261, plant and Storage Location. Now pres enter button. It will display the following screen:
244
In the above screen enter your Production order number and pres enter:
In above screen under Confirmation Type take Final Confirmtn radio button. Yield to Conf is 500 Now save the activity and back to easy access.
245
Calculation
Path: Logistics Production Shop Floor Control Period-End Closing Overhead Calculation KGI2 Individual Processing Transaction Code: KGI2 By the above transaction it will display the following screen:
In the above screen maintain period, de-select Test Run and select Dialog Display check box and execute
In the above screen it show the cost of production Back from this screen.
246
247
FI/CO MATERIAL VERSION ECC 6.0 Step 25: Specify Transfer to Financial Accounting:
Transaction Code: OKG9 By the above transaction it will display the following screen:
In the above screen select your Co.Area and click on Details Button. It will take you to following screen:
In the above screen flag the check box of Transfer to financial Accounting. Save the activity and back.
248
FI/CO MATERIAL VERSION ECC 6.0 Step 26: Calculation of Work in Process
Path: Accounting Controlling Product Cost Controlling Cost Object Controlling Product Cost by Order Period-End Closing Single Functions Work in Process Individual Processing KKAX - Calculate Transaction Code: KKAX By the above transaction it will display the following screen:
Now place your curser on ORD 60003305 and go to Man bar Goto Wip report. It will display WIP report as below:
249
Path: Logistics Materials Management Inventory Management Goods Movement Goods Receipt MB31 For Order Transaction Code: MB31 By the above transaction it will display the following screen:
In the above screen maintain required parameters as above and pres enter. So it will display the following screen:
250
In the above screen pres enter button and save the screen. so it will issue the following message.
251
252
PROFITABILITY ANALYSIS
Profitability Analysis (CO-PA) enables you to evaluate market segments, which can be classified according to products, customers, orders or any combination of these, or strategic business units, such as sales organizations or business areas, with respect to your company's profit or contribution margin. The aim of the system is to provide your sales, marketing, product management and corporate planning departments with information to support internal accounting and decision-making. Two forms of Profitability Analysis are supported: costing-based and account-based. Costing-based Profitability Analysis is the form of profitability analysis that groups costs and revenues according to value fields and costing-based valuation approaches, both of which you can define yourself. It guarantees you access at all times to a complete, short-term profitability report. Account-based Profitability Analysis is a form of profitability analysis organized in accounts and using an account-based valuation approach. The distinguishing characteristic of this form is its use of cost and revenue elements. It provides you with a profitability report that is permanently reconciled with financial accounting.
Using the SAP master data (customer, product, customer hierarchy) or CO-PA derivation rules, the system can derive additional characteristics based on the ones entered manually or transferred from primary transactions. The combination of characteristic values forms a multidimensional profitability segment, for which you can analyze profitability by comparing its costs and revenues. The actual postings represent the most important source of information in CO-PA. You can transfer both sales orders and billing documents from the Sales and Distribution (SD) application component to CO-PA in real time. In addition, an interface program is available to let you transfer external data to the SAP system. You can also transfer costs from cost centers, orders and projects, as well as costs and revenues from direct postings (G/L account postings in FI, orders received in MM, and so on) or settle costs from CO to profitability segments. In costing-based CO-PA, you can valuate incoming sales orders or billing documents to automatically determine anticipated sales deductions or costs. You can also revaluate your data periodically to adjust the initial, real-time valuation or add the actual costs of goods manufactured. In CO-PA Planning, you can create a sales and profit plan. Whereas both types of Profitability Analysis can receive actual data in parallel, there is no common source of planning data. Consequently, you always plan either in accounts (account-based CO-PA) or in value fields (costing-based CO-PA). In costing-based CO-PA you can use automatic valuation to calculate planned revenues, sales deductions and costs of goods manufactured based on the planned sales quantity.
Structures
To use Profitability Analysis (CO-PA), you have to create structures first. The possible valuation levels are determined in the creation of structures. To create the structures, you need to define the operating concern as well as the characteristics and value fields belonging to the operating concern. From a technical point of view, you are actually creating different tables. To find out how these tables are related to each other, you can consult the section Database Tables for CO-PA Transaction Data. In the operating concern, you can define your structures so that the revenues and sales deductions (= value fields) that are shown correspond to the respective levels (customer, customer group, sales office, and product (= characteristics)).
Characteristics
The characteristics in Profitability Analysis represent those criteria according to which you analyze your operating results and your sales and profit plan.
253
A number of fundamental characteristics are automatically predefined in every operating concern. These include the product number, company code, billing type, business area, sales order, customer, and the controlling area, to name but a few. In addition, each type of Profitability Analysis has its own fixed characteristics: Record type (costing-based CO-PA)
Cost element
Predefined characteristics
In addition to the fixed characteristics, a number of other predefined characteristics are available in the field catalog. Such characteristics include customer group, customer district, and country, and they can be added to your operating concern if desired.
Customer-Defined Characteristics
In addition to these predefined characteristics, you can also define your own additional ones. You define these in the field catalog independent of any client or operating concern and can later add them to your operating concerns. Adopting characteristics from SAP tables
You can define your operating concerns by using characteristics that already exist in other applications. For example, you can select fields from the tables for customer master records, material master records, and sales documents. You can also select the partner roles defined in the structure PAPARTNER in the Sales and Distribution (SD) application and use them as characteristics in Profitability Analysis. The table that you take a characteristic from is referred to as that characteristics origin table. Characteristics that you take from the SAP table are then derived automatically from the key fields in the SAP table. The system creates the necessary derivation steps automatically. Your operating concern contains the characteristic Customer district, which comes from the sales data in customer master table KNVV. The key fields of this table are the customer number, sales organization, distribution channel, and division. When you make a posting that contains these four characteristics, the system automatically derives the correct customer district. Custom Characteristics
If the characteristic categories are insufficient for your needs, you can define completely new characteristics from scratch for exclusive use in Profitability Analysis. To derive values for these newly defined characteristics, you need to create your own derivation rules.
254
Value fields
The value fields contain values and quantities that were updated or planned for particular objects. In costing-based profitability analysis, value fields represent the highest level of detail at which you can analyze quantities, revenues, sales deductions, and costs for profitability segments in profitability analysis or contribution margin accounting. You are able to define the revenues and costs that go into specific value fields for profitability reports or sales and profit planning when you set up your SAP System. Example You can define your sales deductions to reflect the structure of sales deductions in SD conditions. For the cost of goods manufactured, costs can be represented in accordance with the costing sheet in material costing (or summaries thereof).
Value fields are only required in costing-based Profitability Analysis. These are the fields that contain the currency amounts and quantities that you want to analyze in CO-PA. They represent the structure of your costs and revenues. The semantic meaning of a value field is determined by the data element to which it is assigned. The data element contains the texts that appear on the screen and in reports for the value field. There are two types of value fields: Value fields that contain amounts in currencies are also referred to as "amount fields". All amount fields in a single line item use the same currency. Value fields that contain quantities are referred to as "quantity fields". Each quantity field is assigned a field containing a unit of measure. Consequently, each quantity field in a line item can use a different unit. Value fields can be categorized according to how and when they are defined: Predefined value fields Value fields that are used frequently are predefined in the standard system. These include fields such as revenue, sales quantity, incoming freight, outgoing freight, and others. You can select those predefined value fields that you wish to transfer into your own operating concern. User-defined value fields In addition to the predefined value fields, you can also define your own value fields. You define these in the field catalog independent of any client or operating concern and can later add them to your operating concerns. The definition of a value field consists of its name, texts, a rule defining how it is aggregated over characteristics of time, and whether it is an amount field or a quantity field. There are two texts for each value field a description and a short text. These texts are displayed on the screen to label the value field. The aggregation rule determines how the values in a value field are to be handled when data is aggregated over multiple periods in planning and in reports. This does not affect the posting logic. You can choose from three aggregation rules: Addition, Average, and Last value. In most cases, you will want to add the values. Only no cumulative values, such as the number of employees, require the other options.
255
When you first call up a function that requires an operating concern, the dialog box appears automatically if the operating concern has not yet been set. If you only have one operating concern or generally only work with one operating concern, it makes sense to enter this operating concern and the required type of Profitability Analysis in your user master data. By doing so, the dialog box will no longer appear, even when you logon again to the system. The system then uses the operating concern and the type of Profitability Analysis stored in the user master record. Moreover, you can call up the dialog box at any time to switch to a different operating concern or to the other type of Profitability Analysis. The entries stored in the user master record then apply all the while you are still logged on to the system. Path: SPROControlling Profitability Analysis Structures Define Operating Concern Maintain Operating Concern Transaction Code: KEA0 By above transaction it will display the following window:
In the above window give new name to Operating concern, and click enter button so it will display the following information window:
256
In the above box just pres enter button. So it will activate the window as below:
In above screen provide Description, flag check boxes Costing-based, Account-base and first save the activity and click on button. It will display another screen below:
In the above window in Chars tab under Transfer from select REGID Region as I shown above and click on (Transfer Fields) so the field will transfer to Data Structure window as below:
257
Now click on Value fields tab. It will display the following screen:
In the above screen in Value Fields tab under Copy from window select required Value fields. Required Value fields are: 1. 2. 3. 4. 5. ABSMG ERLOS KWMKAD KWSMKT KWVKPV VV040 VV030 VV140 Sales Quantity Revenues Advertisement Sales & Marketing Sales Commission Material Discount Customer Discount Cost of Goods Sold (Transfer Fields) so
6. 7.
8.
As the above list base on your requirement select Value Fields as I shown above and click on the field will transfer to Data Structure window as below:
258
Now click on
It issues the above conformation message as the activity is activated. Now click on back button, it will display the following message:
In the above window click on yes button. It will display another window in that window select ATTRIBUTS tab and enter parameters as below;
In the above screen under ATTRIBUTES tab provide Operating Concern Currency, Fiscal Year Variant and click on save button, it will give you the following box with a message:
259
Path: SPRO Enterprise Structure Assignment Controlling Assign controlling area to operating concern Transaction code: KEKK Database Table: TKA01 By the above transaction it will display an screen in that click on It will display the following screen: .
in the above window give your controlling area and pres enter so it will appears you controlling area on the top to window.
260
In the above screen your controlling area is at top so assign your Operating Concern now save the activity and back to SPRO screen.
In the above window enter your Operating Concern and click on enter button.
261
It is not necessary to activate the conditions for transferring sales order data, since this transfer is solely for statistical purposes. Path: SPRO Controlling Profitability Analysis Flows of Actual Values Transfer of Billing Documents Assign Value Fields Transaction Code: KE4I Database Table: T258I By the above transaction it will display the following screen:
In the above screen double click on Maintain Assignment of SD Conditions to CO-PA Value Fields So it will display the following screen in that click on button:
262
Maintain the above parameters and save the activity and back to SPRO screen.
In the above screen select the relevant fields, save the activity and back to SPRO screen.
263
You create automatic postings in Materials Management and you want these revenues and expenses from the evaluation of material stocks to be posted automatically to Profitability Analysis. This instance also requires that you define "Automatic assignment to a profitability segment".
264
In the above screen select FI Financial Accounting --> CO-PA and click on Assignment lines under Dialog Structure. It will display the following screen: On that click on button:
In above screen enter new Assgnmnt values like 60,70 with Text and save the activity. Now select Assgnmt line 60 and click on Source under Dialog Structure It will display the following screen:
In the above screen enter Cost Element values and click on Value Fields under Dialog Structure.
265
In the above screen provide parameters as I shown and click on Assignment lines under Dialog Structure. It will display the following screen:
In the above screen select 70 Advertisement and click on Source under Dialog Structure, It will display the following screen:
In the above screen enter Cost Element values and click on Value Fields under Dialog Structure. It will display another screen in it click on button.
266
Enter above parameters in above screen. Save the activity and back to SPRO screen.
1. The header of the cycle contains the parameters that are valid for the entire cycle. This includes the sender
selection type, where you specify for actual data whether you want to assess all costs together or fixed and variable costs separately.
2. The segments contain the combinations of sender cost centers/sender processes and receiver profitability
segments that are processed using a single distribution rule.
Specify either an assessment cost element or an allocation structure, which determines more than one assessment cost element for each cost element group. The sender cost centers/sender processes are credited using these secondary cost elements (cost element category 42). In account-based CO-PA, the receiver profitability segments are also credited using this cost element. Specify either single value fields for the fixed and variable costs, respectively, or a PA transfer structure that determines more than one value field for each cost element group. Specify the rule which you want to use to credit the sender.
Note that, for technical reasons, you can only use an allocation structure or a PA transfer structure with sender rule "1" (posted amounts).
Define the tracing factor, the rule which determines how the values are distributed to the receivers. For example, you can distribute certain percentages to the different receivers or distribute using certain values (such as the quantity sold or the revenue) as an allocation base. If you choose to use an allocation base, choose the receiver rule "Variable portions". Specify the senders and receivers in the allocation characteristics.
Path: SPROControlling Profitability Analysis Flows of Actual Values Transfer of Overhead Assess Cost Center Costs / Process Costs Define Structure of Cost Center Assessment/Process Cost Assessment Transaction Code: KEU1
267
In the above screen double click on Create Actual Assessment, it will display the following screen:
In the above screen provide Cycle name to Cycle field and enter Start Date pres enter butto so it will take you to following screen:
In the above screen enter values to Text, CO Area, and TF basis as I shown above and click on Attach Segment Button. It will display another screen as below:
268
In the above screen enter value to : Segment Name Fixed value field Val.Fld Var.Cst Alloc.Structure After you enter those values pres enter button and click on display the following screen:
In the above screen select 13 PS Settlement under Alloc. structure and double click on Assignments under Dialog Structure, so it will display the following screen click on :
269
In the above screen enter new assignment with text and pres enter button. Select above assignment line which we just enter and click on Source under dialog structure, it will display the following screen:
In the above screen enter cost elements and click on Assessment cost element under dialog structure, it will display the following screen:
In above screen click on and assign Assessment cost element. Click on Settlement cost elements so it will display the following screen:
270
enter PSG under Receiver cat and flag the check box By Cost
Save the activity and click on back button till you get segment screen as below:
In the above screen enter parameters as I shown under Senders/Receivers tab. Now click on Receiver Tracing Factor tab and values as below:
271
In the above screen under Receiver Tracing Factor enter Recore type, Plan/Act.Indic values and save the activity. Back to SPRO screen.
In the above screen against to your Co.Area assign 4 Component active for bouth types of profitability analysis. Save the activity and back to SPRO screen.
272
In the above screen enter new values to Key Figure Scheme, Medium-Lenth Text. Click on Element of the key figure scheme under dialog structure. It will display the following screen:
273
In the above select 9002 Revenue in Value field and pres on Now click on symbol.
button.
In the above screen select 9008 Cost of goods sole in Value field and pres It will shows as below:
button.
In the above screen after entering all information click on Back to SPRO screen.
274
In the above screen double click on Create Profitability Report it display the following screen:
In the above screen give new name to report (name should start with Y or Z) and description. Select radio button Basic Report Click on Create button it will displays the following screen:
In the above screen right side under Chart List select following fields 1. Country 2. Region 3. Company code
275
In the above screen click on check box against country so it will display following screen:
In the above screen to Local Variable field enter Country and click continue button or click enter button. Now click on check box against region so it will display following screen:
In the above screen to Local Variable field enter Region and click continue button or click enter button. Now click on check box against Company Code so it will display following screen:
276
In the above screen to Local Variable field enter ComCode and click continue button or click enter button. Now click on check box against Fyscal Year so it will display following screen:
In the above screen to Local Variable field enter FyscalYear and click continue button or click enter button It will display the following screen:
In the above screen click on Key figures tab so it will display the following screen:
277
In the above screen under Variables tab, against key figure scheme field select your key figure. Under Available Key Figure box select your Key figure and click on Left arrow button so it will transfer to next box as below
In the above screen you can view the key figure transfer. Now click on Variables tab.soit will display the following screen:
278
In the above screen under Variable tab enter parameters as I showen. Save the activity and back to SPRO screen
In the above screen for your controlling area provide year and flag the check boxes to Line items, Online Transer fields. Save the activity and back to SPRO screen.
279
In the above screen select version 0 and double click on Setting for Profit Center Accounting It will display the following screen, click on :
In the above screen maintain those parameters. Save the screen and back to SPRO screen:
280
Go to Manu bar Group + insert it will display a box asking Company code:
In the above screen enter your company code and pres enter button. So it will display the following screen:
In above screen maintain number inter values as I shown save the activity and back to SPRO screen.
281
In the above screen provide the information to: VAla (Valuation Area that is plant) BusA (Business area) Profit Ctr Save the activity and back to SPRO screen
In the above screen enter you elements range and enter Default Profit center. Now click on it will display the following screen:
282
In the above screen enter description, Source fields as above I shown. Click on Maintain Rules Values it will display the following screen:
In the above screen maintain parameters as I shown above. Save the activity and back to SPRO screen
283
In the above screen enter all the values as I shown and pres enter button so ti will display the following screen:
in the above screen enter the values for: Sold-to party (Customer number) Po Number Material (Material Number) Order Quantity Profit Center After you entering above values pres on enter button select the line item and double click on the same it will display the following screen:
284
In the above screen first go to Shipping tab in that assign Storage location as I shown in above and save the activity. it will post the order and issues the following message.
In the above message it shows order number. Back to easy access screen.
285
In the above screen first click on Picking tab and in it under Picked Qty field give the quantity of goods how much you want to pick now(General total quantity that order contain) Now click on Post goods issue button so it will post the data and issue the following message.
In the above message it give delivery document number. Back to easy access screen
In the above screen provide the delivery document number and click on enter button so it willdisplay the following screen:
286
In the above document just click on save button so it will save the document and post the entry to FI. It will display the following screen
In the above screen go to manu bar Billing document + change it will display the following screen:
In the above screen click on Accounting button so it will display the following window:
287
Enter the above debit values with Cost Center, Profit Center, and Segment. Click on button so it will display the following screen:
288
In the above screen give periods (From, To values), Deselect Test Run check box, Assign your cycle to Cycle field and execute the activity it will display the following screen:
289
In the above screen keep your curser on Senders value and click on Sender button it will show the values in the same way keep your curser on Number of receivers value and click on Receiver button it will display the values back to easy access screen.
In the above screen select those parameters for which you want to drag the report and click on executive button it will display following:
290
-------------------------------------------------------******-------------------------------------------------------------------
291
292
293
294
Internal orders
18) What is the purpose of defining Internal Orders? An example would help us understand this much better. Lets say in an organization there are various events such as trade fairs, training seminars, which occur during the year. Now lets assume for a second that these Trade fairs are organized by the Marketing cost center of the organization. Therefore in this case marketing cost center is responsible for all the trade fairs costs. All these trade fairs costs are posted to the marketing cost centers. Now if the management wants an analysis of the cost incurred for each of the trade fair organized by the marketing cost center how would the marketing manager get this piece of information across to them? The cost center report would not give this piece of info Now this is where Internal Order steps in .If you go through all cost center reports this information is not readily available since all the costs are posted to the cost center. SAP, therefore rovides the facility of using internal orders which comes in real handy in such situations. In the above scenario the controlling department would then need to create an internal order for each of the trade fair organized. The cost incurred for each of the trade fair will be posted to the internal orders during the month. At the month end, these costs which are collected in the internal order will be settled from these orders to the marketing cost center. Thus the controlling person is now in a position to analyze the cost for each of the trade fair separately. Thus internal order is used to monitor costs for short term events, activities. It helps in providing more information than that is provided on the cost centers. It can be widely used for various purposes .
295
Product Costing
21) What are the important Terminologies in Product Costing? Results Analysis Key This key determines how the Work in Progress is calculated Cost Components - The break up of the costs which get reflected in the product costing eg. Material Cost, Labour Cost, Overhead etc Costing Sheets - This is used to calculate the overhead in Controlling Costing Variant - For All manufactured products the price control recommended is Standard Price. To come up with this standard price for the finished good material this material has to be costed. This is done using Costing Variant. Further questions down below will explain this concept better. 22) What are the configuration settings maintained in the costing variant? Costing variant forms the link between the application and Customizing, since all cost estimates are carried out and saved with reference to a costing variant. The costing variant contains all the control parameters for costing. The configuration parameters are maintained for costing type, valuation variants, date control, and quantity structure control. In costing type we specify which field in the material master should be updated. In valuation variant we specify the following: a) The sequence or order the system should go about accessing prices for the material master (planned price, standard price, moving average price etc). b) It also contains which price should be considered for activity price calculation and. c) How the system should select BOM and routing. 23) How does SAP go about costing a Product having multiple Bill of materials within it? SAP first costs the lowest level product, arrives at the cost and then goes and cost the next highest level and finally arrives at the cost of the final product. 24) What does the concept of cost roll up mean in product costing context? The purpose of the cost roll up is to include the cost of goods manufactured of all materials in a multilevel production structure at the topmost level of the BOM(Bill of Material) The costs are rolled up automatically using the costing levels. 1) The system first calculates the costs for the materials with the lowest costing level and assigns them to cost components. 2) The materials in the next highest costing level (such as semi finished materials) are then costed. The costs for the materials costed first are rolled up and become part of the material costs of the next highest level. 25) What is a settlement profile and why is it needed? All the costs or revenues which are collected in the Production order or Sales order for example have to be settled to a receiver at the end of the period. This receiver could be a Gl account, a cost center, profitability analysis or asset. Also read the question What is a cost object in the section Controlling. In order to settle
296
297
298
299
300
301
302
74) Is the WIP calculated in the product cost by order component at actual costs or standard costs? In the product cost by order component the WIP is calculated at actual costs. 75) Is the WIP calculated in the product cost by period component at actual costs or target costs? In the product cost by period component the WIP is calculated at target costs.
303
304
Profitability Analysis
86) Explain the organizational assignment in the PA module? The operating Concern is the highest node in Profitability Analysis. The operating concern is assigned to the Controlling Area. Within the operating concern all the transactions of Profitability Analysis are stored. The operating concern is nothing but a nomenclature for defining the highest node in PA. 87) What is the functionality of the PA module? PA module is the most important module when it comes to analyzing the results of the organization. In this module you basically collect the revenues from the sale order, the costs from the production order, cost center or internal order and analyze their results. The interesting part about this module is that when it collects the costs and revenues it also collects the characteristics associated with the costs and revenues and this is what makes it stand out So for e.g. using PA module you can find out the following: Profit of a certain product Profit of a certain product in a certain region Profit of a certain product in a certain region by a certain customer Profit of a certain product in a certain region by a certain sales person and the list can go on in depth It is one of the most wonderful modules in the SAP 88) How do you get all those characteristics defined above and how do you analyze them? To do so while defining Operating concern one has to define Characteristics and Value fields. 89) What are characteristics and Value Fields? In the operating concern two things are basically defined a) Characteristics b) Value Fields Characteristics are nothing but those aspects on which we want to break down the profit logically such as customer, region product, product hierarchy, sales person etc Value Fields are nothing but the values associated with these characteristics Eg Sales, Raw Material Cost, Labour Cost, Overheads etc Once you define the characteristics and value fields these values are updated in the table.
305
96) What is the difference between Account based Profitability Analysis and Costing based Profitability Analysis? Account based Profitability analysis is a form of Profitability analysis (PA) that uses accounts as its base and has an account based approach. It uses costs and revenue elements. Costing based Profitability Analysis is a form of profitability analysis that groups costs and revenues according to value fields and costing based valuation approaches. The cost and revenues are shown in value fields. 97) What are the advantages and disadvantages of Account based profitability analysis vis--vis costing based profitability analysis? The advantage of Account based PA is that it is permanently reconciled with Financial accounting. The disadvantages are that it is not powerful as the costing based PA, since it uses accounts to get values. No Contribution margin planning can be done since it cannot access the standard cost estimate. Further no variance analysis is readily available. The advantages of the Costing based PA are manifold. They are as
306
307
308
309
310
311
312
313