0% found this document useful (0 votes)
67 views

Daily Program Dec-2011

The document contains daily work program updates for the NCT BACK-UP PROJECT in Chittagong, Bangladesh from December 1st to December 9th, 2011. It lists the various construction activities planned each day across different segments of the project, including drainage pipe installation, sub-base preparation, concrete pouring, and dismantling of structures. The status of ongoing works is also noted. The document is signed off by the Project Manager and engineering staff to record the planned activities.

Uploaded by

Mahibul Hasan
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views

Daily Program Dec-2011

The document contains daily work program updates for the NCT BACK-UP PROJECT in Chittagong, Bangladesh from December 1st to December 9th, 2011. It lists the various construction activities planned each day across different segments of the project, including drainage pipe installation, sub-base preparation, concrete pouring, and dismantling of structures. The status of ongoing works is also noted. The document is signed off by the Project Manager and engineering staff to record the planned activities.

Uploaded by

Mahibul Hasan
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 21

NCT BACK-UP PROJECT, CHITTAGONG Work Program,1st Dec, 2011

S.l. No. Description Work Program of 1st Dec. 2011 Drainage pipe installation 1 Segment 1A Sub-base materials laying Water Supply pipe Installation work Layout of HT Cable Trench 2 3 Segment 2A Segment 1 Surcharge material placement Wall casting/Yard side/1st lift (CH 865-885) 4 Open Deep Drain Concrete Pouring of Base (CH 885-900) 5 Rail Relocation Sub base preparation (CH 550-620) Shuttering of slab 6 Electric Sub station Concrete pouring of Column 7 8 9 Wasa Relocation Laboratory / Field Test Interlocking Block ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Newly installed line is functioning Rebar fabrication executed Sub base preparation (CH 550-620) in progress Shuttering of slab in progress Surcharge material placement in progress Concrete pouring of Base finished Settlement Record Sand bagging for preloading work Settlement Record in progress Sand bagging for preloading work in progress Achievement of 30th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Water Supply pipe Installation work in progress
Remarks

10 Dismantling work
11

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,2nd Dec, 2011


S.l. No. Description Work Program of 2nd Dec. 2011 Drainage pipe installation 1 Segment 1A Sub-base materials(Shingles) laying Water Supply pipe Installation work Earth excavation of HT Cable Trench 2 3 Segment 2A Segment 1 Surcharge material placement 4 Open Deep Drain Wall casting/Yard side/1st lift (CH 865-885) CC casting 5 Rail Relocation Sub base preparation (CH 550-620) Shuttering of slab 6 Electric Sub station Concrete pouring of Column Sheet Pile RCC Drainage Pipe 7 Wasa Relocation PDB Relocation 8 9 Laboratory / Field Test Interlocking Block ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Sheet Pile casting Concrete pouring Newly installed line is functioning Shutdown & new installed 33 KV line connection Sheet Pile casting in progress Concrete Pouring in progress Surcharge material placement in progress Concrete pouring of Base finished Soling executed Sub base preparation (CH 550-620) in progress Shuttering of slab in progress Settlement Record Sand bagging for preloading work Achievement of 1st Dec2011 Drainage pipe installation in progress Sub-base materials(Shingles) laying in progress Water Supply pipe Installation work in progress Layout has given Settlement Record in progress Sand bagging for preloading work in progress
Remarks

10 Dismantling work
11

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 3rd Dec,11


S.l. No. Description Work Program of 3rd Dec.11 Drainage pipe installation 1 Segment 1A Sub-base materials(Shingles) laying Water Supply pipe Installation work Earth excavation of HT Cable Trench 2 3 Segment 2A Segment 1 Surcharge material placement 4 Open Deep Drain Wall casting/Yard side/1st lift (CH 865-885) Rebar fabrication of Base 5 Rail Relocation Sub base preparation (CH 550-620) Shuttering of slab 6 Electric Sub station Concrete pouring of Column 7 8 9 Sheet Pile RCC Drainage Pipe Wasa Relocation Sheet Pile casting Concrete pouring(300mm) Newly installed line is functioning Dismantling of 11 KV Line Newly installed 33 KV line is live now. Concrete pouring of Column in progress Sheet Pile casting in progress Concrete Pouring in progress Surcharge material placement in progress Concrete pouring of Base finished CC executed Sub base preparation (CH 550-620) in progress Shuttering of slab in progress Settlement Record Sand bagging for preloading work Achievement of 2nd Dec.11 Drainage pipe installation in progress Sub-base materials(Shingles) laying in progress Water Supply pipe Installation work in progress Layout has given Settlement Record in progress Sand bagging for preloading work in progress
Remarks

10 PDB Relocation 11 Laboratory / Field Test 12 Interlocking Block 13 Dismantling work


14

ILB production Mosque dismantling

ILB production in progress Mosque dismantling work in progress

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 4th Dec,11


S.l. No. Description Work Program of 4th Dec.11 Drainage pipe installation 1 Segment 1A Sub-base materials(Shingles) laying Water Supply pipe Installation work Earth excavation of HT Cable Trench 2 3 Segment 2A Segment 1 Surcharge material placement 4 Open Deep Drain Wall casting/Yard side/1st lift (CH 865-885) Concrete pouring of Base 5 Rail Relocation Sub base preparation (CH 550-620) Shuttering of slab 6 Electric Sub station Concrete pouring of Column 7 8 9 Sheet Pile RCC Drainage Pipe Wasa Relocation Sheet Pile casting Concrete pouring(300mm) Newly installed line is functioning Dismantling of 11 KV Line Newly installed 33 KV line is live now. Concrete pouring of Column in progress Sheet Pile casting in progress Concrete Pouring in progress Surcharge material placement in progress Concrete pouring of Base finished Rebar fabrication executed Sub base preparation (CH 550-620) in progress Shuttering of slab in progress Settlement Record Sand bagging for preloading work Achievement of 3rd Dec.11 Drainage pipe installation in progress Sub-base materials(Shingles) laying in progress Water Supply pipe Installation work in progress Layout has given Settlement Record in progress Sand bagging for preloading work in progress
Remarks

10 PDB Relocation 11 Laboratory / Field Test 12 Interlocking Block 13 Dismantling work


14

ILB production Mosque dismantling

ILB production in progress Mosque dismantling work in progress

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 5th Dec,11


S.l. No. Description Work Program of 5th Dec.11 Drainage pipe installation 1 Segment 1A Sub-base materials(Shingles) laying Water Supply pipe Installation work Earth excavation of HT Cable Trench 2 3 Segment 2A Segment 1 Surcharge material placement 4 5 6 7 8 9 Open Deep Drain Rail Relocation Electric Sub station Sheet Pile RCC Drainage Pipe Wasa Relocation Wall casting/Country side/1st lift (CH 865-885) Concrete pouring of Base Sub base preparation (CH 550-620) Shuttering of slab Sheet Pile casting Concrete pouring(300mm) Newly installed line is functioning Dismantling of 11 KV Line Newly installed 33 KV line is live now. Surcharge material placement in progress Concrete pouring of Base finished Rebar fabrication executed Sub base preparation (CH 550-620) in progress Shuttering of slab in progress Sheet Pile casting in progress Concrete Pouring in progress Settlement Record Sand bagging for preloading work Achievement of 4th Dec.11 Drainage pipe installation in progress Sub-base materials(Shingles) laying in progress Water Supply pipe Installation work in progress Layout has given Settlement Record in progress Sand bagging for preloading work in progress
Remarks

10 PDB Relocation 11 Laboratory / Field Test 12 Interlocking Block 13 Dismantling work


14

ILB production Mosque dismantling

ILB production in progress Mosque dismantling work in progress

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 6th Dec,11


S.l. No. 1 2 3 4 5 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG Track (Seg-1A) Segment 2A Segment 1 Surcharge material placement Wall casting/Country side/2nd lift ,CH 870890,(Quantity=6cum) 6 Open Deep Drain Earth excavation,soling,CC, CH755-765 7 Rail Relocation Sub base preparation (CH 550-620) Sub base watering & Shoulder preparation 8 9 10 12 13 14 15 Electric Sub station Sheet Pile RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Released Material removing ILB production ILB production in progress (Quantity=8000 Nos)
2 trip Rail bit deposite to CPA Store no-1

Work Program of 6th Dec.11 Earth excavation and pipe installation Earth Excavation for Pipe laying Sub-base materials laying & Bed Rolling Settlement Record Sand bagging for preloading work

Achievement of 5th Dec.11

Remarks

250mm pipe welding (04 Nos) Shingles-Sand mixing (500cft) Settlement Record in progress for 45th day Sand bagging of preloading work in progress (2000 Nos) Surcharge material placement (40,000cft) Wall casting/Country side/1st lift ,CH 910930,(Quantity= 6cum) Wall casting/Yard side/1st lift ,CH 870880,(Quantity=4.5 cum) Sub base preparation in progress(CH 550-620) Sub base watering & Shoulder preparation in progress Shuttering and Rebar binding of slab in progress Concrete pouring of Sheet Pile (01 Nos) Concrete Pouring (300mm dia=26 Nos) Excavation executed for pole driving (11KV Line),Quantity=7 Nos

Shuttering and Rebar binding of slab Concrete pouring of Sheet Pile(01 Nos) Concrete pouring(300mm) Dismantling of 11 KV Line

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 9th Dec,11


S.l. No. 1 2 3 4 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG Track (Seg-1A) Segment 2A Work Program of 9th Dec.11 CC casting Welding & Placing Earth excavation (remaining 26m) Settlement Record Sand bagging for preloading work 5 Segment 1 Surcharge material placement PVD Driving Wall casting/Country side/3rd lift ,CH 900920,(Quantity=7cum) 6 Open Deep Drain Bracing fixing Soling,CC, CH 1000-1020 Sub base preparation (CH 550-620) 7 Rail Relocation Sub base watering & Shoulder preparation 8 9 10 12 13 14 15 Electric Sub station Sheet Pile RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Released Material removing ILB production ILB production in progress (Quantity=10300 Nos) Shuttering and Rebar binding of slab Concrete pouring of Sheet Pile(01 Nos) Concrete pouring(300mm) Pole erection Sub base watering & Shoulder preparation in progress Shuttering and Rebar binding of slab in progress Concrete pouring of Sheet Pile (01 Nos) Concrete Pouring (300mm dia=21 Nos,500 mm=2 nos) Pole erection (2 Nos) Earth Excavation Sub base preparation in progress(CH 550-620) Wall casting/Country side/1st lift ,CH 930950,(Quantity= 6cum) Achievement of 8th Dec.11 500mm pipe fixing (5 Nos) Earth Excavation executed Rolling Settlement Record in progress for 48th day Sand bagging of preloading work in progress (1900 Nos) Surcharge material placement (42,000cft)
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 10th Dec,11


S.l. No. 1 2 3 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG Track (Seg-1A) Work Program of 10th Dec.11 300 mm pipe fixing Welding & Placing Sub-base material laying Achievement of 9th Dec.11 CC casting executed Welding & Placing in progress Earth excavation executed for remaining 26 m
Remarks

Ballast mixing & laying


4 Segment 2A Settlement Record Sand bagging for preloading work 5 Segment 1 Surcharge material placement PVD Driving Shuttering/Yard side/3rd lift ,CH 900-920 6 Open Deep Drain Bracing fixing Soling,CC, CH 1000-1020 Sub base preparation (CH 550-620) 7 Rail Relocation Sub base watering & Shoulder preparation 8 9 10 12 13 14 15 Electric Sub station Sheet Pile RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Released Material removing Shuttering and Rebar binding of parapet Concrete pouring of Sheet Pile(01 Nos) Concrete pouring(300mm) Pole erection Regular Test (ILB/Cylinder) ILB production Sub base watering & Shoulder preparation in progress Shuttering and Rebar binding of parapet in progress Concrete pouring of Sheet Pile (01 Nos) Concrete Pouring (300mm dia=23 Nos,500 mm=2 nos) Pole erection (3 Nos) Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=10300 Nos) Sub base preparation in progress(CH 550-620) Settlement Record in progress for 49th day Sand bagging of preloading work in progress (1600 Nos) Surcharge material placement (40,000cft) PVD Driving in progress Wall casting/Country side/3rd lift ,CH 900920,(Quantity= 6cum) Bracing fixing in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 11th Dec,11


S.l. No. 1 2 3 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG Track (Seg-1A) Work Program of 11th Dec.11 Base CC & Side CC Casting Welding & Placing Sub-base material laying Achievement of 10th Dec.11 CC Casting of 3 Nos Gullyhole. Welding & Placing in progress Earth excavation executed for remaining 26 m
Remarks

Ballast mixing & laying


4 Segment 2A Settlement Record Sand bagging for preloading work 5 Segment 1 Surcharge material placement PVD Driving Wall casting/Country side/2nd lift ,CH 860880,(Quantity= 5cum) 6 Open Deep Drain Bracing fixing CC Casting CH (1020-1040) Sub base preparation (CH 550-620) 7 Rail Relocation Sub base watering & Shoulder preparation 8 9 10 12 13 14 15 Electric Sub station Sheet Pile RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Released Material removing Shuttering and Rebar binding of parapet Concrete pouring of Sheet Pile(01 Nos) Concrete pouring(300mm) Cable fitting Regular Test (ILB/Cylinder) ILB production

Ballast mixing & laying in progress


Settlement Record in progress for 50th day Sand bagging of preloading work in progress (2000 Nos) Surcharge material placement in progress (50,000cft) PVD Driving in progress (3000 rm) Wall casting/Country side/2nd lift ,CH 880900,(Quantity= 5cum) Bracing fixing in progress CC Casting executed (CH 1000-1020) Sub base preparation in progress(CH 550-620) Sub base watering & Shoulder preparation in progress Concrete casting of Parapet (Part) Concrete pouring of Sheet Pile (01 Nos) Concrete Pouring (300mm dia=21 Nos,500 mm=1 no) Pole erection (3 Nos) Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=10,000 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 12th Dec,11


S.l. No. 1 2 3 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG Track (Seg-1A) Work Program of 12th Dec.11 500mm pipe fixing Welding & Placing Sub-base material laying Achievement of 11th Dec.11 Base CC & Side CC Casting executed Welding & Placing in progress(03 Nos) Sub-base material laying in progress(2000 cft)
Remarks

Ballast mixing & laying


4 Segment 2A Settlement Record Sand bagging for preloading work 5 Segment 1 Surcharge material placement PVD Driving Shuttering and Rebar binding ,CH 840-860 6 Open Deep Drain Bracing fixing Rebar binding of Base Sub base preparation (CH 550-620) 7 Rail Relocation Sub base watering & Shoulder preparation 8 9 Electric Sub station Sheet Pile Transverse Sleeper 10 12 13 14 15 RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Released Material removing Concrete casting of Parapet Concrete pouring of Sheet Pile(01 Nos) Concrete pouring Concrete pouring(300mm) Cable fitting Regular Test (ILB/Cylinder) ILB production

Ballast mixing & laying in progress(1000 cft)


Settlement Record in progress for 51th day Sand bagging of preloading work in progress (1800 Nos) Surcharge material placement in progress (55,000cft) PVD Driving in progress (3200 rm) Wall casting/Country side/2nd lift ,CH 860880,(Quantity= 5cum) Bracing fixing in progress CC Casting executed CH (1000-1040) Sub base preparation in progress(CH 550-620) Sub base watering & Shoulder preparation in progress Concrete casting of Parapet in progress (Part) Concrete pouring of Sheet Pile (01 Nos) Concrete pouring in progress(13 Nos) Concrete Pouring (300mm dia=21 Nos,500 mm=1 no) Pole erection (3 Nos) Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=10,000 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 13th Dec,11


S.l. No. 1 2 3 4 5 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG Track (Seg-1A) Segment 2A Segment 1 Surcharge material placement Concrete pouring of Base(CH 1000-1020) 6 Open Deep Drain Bracing fixing Rebar binding of Base Sub base preparation (CH 550-620) 7 8 9 10 11 12 13 14 15 Rail Relocation Sub base watering & Shoulder preparation Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Concrete casting of Parapet Concrete pouring of Sheet Pile(01 Nos) Concrete pouring Concrete pouring(300mm) Cable fitting Regular Test (ILB/Cylinder) ILB production CC Dismantling Sub base watering & Shoulder preparation in progress Concrete casting of Parapet in progress (Part) Concrete pouring of Sheet Pile (01 Nos) Concrete pouring in progress(12 Nos) Concrete Pouring (300mm dia=22 Nos,500 mm=1 no) Cable fitting in progress Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,220 Nos) CC Dismantling in progress Surcharge material placement in progress (50,000cft) Wall casting/Country side/2nd lift ,CH 860880,(Quantity= 5cum) Bracing fixing in progress CC Casting executed CH (1000-1040) Sub base preparation in progress(CH 550-620) Work Program of 13th Dec.11 600 mm dia Pipe fixing Base casting of Gully hole Welding & Placing Levelling & Rolling Welding & Placing in progress(02 Nos) Sub-base material(520mm thick) laying finished Achievement of 12th Dec.11 500mm pipe fixing in progress (02 Nos)
Remarks

Ballast mixing & laying


Settlement Record Sand bagging for preloading work

Ballast mixing & laying in progress(1000 cft)


Settlement Record in progress for 52th day Sand bagging of preloading work in progress (2000 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 14th Dec,11


S.l. No. 1 2 3 4 5 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG (Seg-1A) Segment 2A Segment 1 Surcharge material placement Wall casting /1st lift(CH 1000-1020) 6 Open Deep Drain Plastering & Net cement finishing 7 8 9 10 11 12 13 14 15 Rail Relocation Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Ballast mixing & laying Concrete casting of Parapet Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(300mm) Cable fitting Regular Test (ILB/Cylinder) ILB production CC Dismantling Ballast mixing & laying in progress Rebar fabrication & Shuttering executed Shuttering of slab in progress (2nd portion) Rebar fabrication & Shuttering executed Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=23 Nos) Cable fitting in progress Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,400 Nos) CC Dismantling in progress Surcharge material placement in progress (45,000cft) Concrete pouring of Base (9 cum) CH 1000-1020 Work Program of 14th Dec.11 300 mm dia Pipe fixing Base casting of Gully hole Welding & Placing Achievement of 13th Dec.11 600 mm dia Pipe fixing in progress Base casting of Gully hole in progress Welding & Placing in progress(02 Nos)
Remarks

Ballast mixing & laying


Settlement Record Sand bagging for preloading work

Ballast mixing & laying in progress(800 cft)


Settlement Record in progress for 53th day Sand bagging of preloading work in progress (2200 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 15th Dec,11


S.l. No. 1 2 3 4 5 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG (Seg-1A) Segment 2A Segment 1 Surcharge material placement 6 7 8 9 10 11 12 13 14 15 16 Segment-2 Open Deep Drain Rail Relocation Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Clearing & Grubbing Wall casting /1st lift/Yard Side(CH 1000-1020) Ballast mixing & laying Concrete casting of Parapet Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring Concrete pouring(300mm) Cable fitting Regular Test (ILB/Cylinder) ILB production CC Dismantling (Seg-2) Wall casting /1st lift / Navy Side(CH 1000-1020)/ 9cum Ballast mixing & laying in progress Concrete casting of Parapet in progress Shuttering of slab in progress (2nd portion) Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=21 Nos) Cable fitting in progress Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=13,200 Nos) CC Dismantling(Seg-2) in progress Surcharge material placement in progress (45,000cft) Work Program of 15th Dec.11 600 mm dia Pipe fixing & Side CC Base casting of Gully hole Welding & Placing Achievement of 14th Dec.11 300 mm dia Pipe fixing (03 Nos) Base casting of Gully hole in progress(02 Nos ) Welding & Placing in progress(01 Nos)
Remarks

Ballast mixing & laying


Settlement Record Sand bagging for preloading work

Ballast mixing & laying in progress(800 cft)


Settlement Record in progress for 54th day Sand bagging of preloading work in progress (2000 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 18th Dec,11


S.l. No. 1 2 3 4 5 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG (Seg-1A) Segment 2A Segment 1 Surcharge material placement 6 7 Segment-2 Open Deep Drain Clearing & Grubbing Wall casting /1st lift/Navy Side(CH 1100-1105) Wall casting /3rd lift/country Side(CH 890-908) 8 9 10 11 12 13 14 15 16 Rail Relocation Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Ballast mixing & laying Concrete casting of Parapet Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring Concrete pouring(300mm) Cable fitting Regular Test (ILB/Cylinder) ILB production CC Dismantling (Seg-2) Concrete casting of Parapet in progress Shuttering of slab in progress (2nd portion) Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=21 Nos) Cable fitting in progress Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=13,000 Nos) CC Dismantling(Seg-2) in progress Surcharge material placement in progress (40,000cft) Clearing & Grubbing in progress Base Casting,10 cum (CH 1100-1105) Bracing fixing (18 Nos) Work Program of 18th Dec.11 Gully hole wall shuttering & Casting (04 Nos) Manhole CC Casting 100 mm dia MS pipe welding Achievement of 17th Dec.11 Base CC Casting (15rm),Side CC Casting (15rm) Manhole Base Casting (01 no) 250 mm dia MS Pipe welding & laying finished (78 rm)
Remarks

Ballast mixing & laying


Settlement Record Sand bagging for preloading work

Ballast mixing & laying in progress/second layer(1000 cft)


Settlement Record in progress for 57th day Sand bagging of preloading work in progress (2000 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 21th Dec,11


S.l. No. 1 2 3 Description Yard Drainage(Seg-1A) Water supply line (Seg-1A) RMG (Seg-1A) Work Program of 21th Dec.11 300mm(8 Nos),700mm(6 Nos) dia pipe fixing 15rm Base CC & 45rm side CC casting 100 mm dia MS pipe welding 250 mm dia MS Pipe welding & laying finished (78 rm) Achievement of 20th Dec.11 700 mm (06 Nos) & 300mm (08 Nos)dia pipe fixing
Remarks

Ballast mixing & laying Shingles laying (180mm layer)

Ballast mixing & laying in progress/second layer(1200 cft)

4 5 6

Pre-cast pile driving(Seg-1A) 02 Nos Segment 2A Segment 1 Surcharge material placement Settlement Record Sand bagging for preloading work

03 Nos driving finished (Light mast)


Settlement Record in progress for 60th day Sand bagging of preloading work in progress (2000 Nos) Surcharge material placement in progress (42,000cft) Clearing & Grubbing in progress Rebar fabrication & Shuttering executed. Ballast mixing & laying in progress (1000 cft) Shuttering of slab in progress (2nd portion) Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=20Nos) Cable fitting in progress Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,600 Nos) CC Dismantling(Seg-2) in progress

7 8 9 10 11 12 13 14 15 16 17

Segment-2 Open Deep Drain Rail Relocation Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work

Clearing & Grubbing Wall casting /2nd lift/Port Side(CH 1100-1125) Ballast mixing & laying(Ch 0-200) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring Concrete pouring(300mm) Cable fitting Regular Test (ILB/Cylinder) ILB production CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 22th Dec,11


S.l. No. 1 Description Yard Drainage(Seg-1A) Work Program of 22th Dec.11 15rm Base CC & 45rm side CC casting Achievement of 21th Dec.11 300mm(8 Nos),700mm(6 Nos) installation completed. 2 nos Gully hole wall casting complete
Remarks

Ballast mixing & laying 1st layer (Area=15mX22m)


3 RMG (Seg-1A)

Ballast mixing & laying in progress/second layer(Area=22mX10m))

Shingles laying (180mm layer) Earth Excavation for 2nd portion (59 rm)

4 5

Pre-cast pile driving(Seg-1A) 01 No (Anchor proof) Segment 2A Settlement Record Sand bagging for preloading work (2500 Nos)

01 No driving finished (Light mast)


Settlement Record in progress for 61th day Sand bagging of preloading work in progress (1700 Nos) Surcharge material placement in progress (40,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress (Area=20mX20m) Wall casting /2nd lift/Yard Side(CH 1100-1125)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 150mm local sand laying Wall casting /2nd lift/Navy Side(CH 1100-1125)

Open Deep Drain Wall casting /3rd lift/Navy Side(CH 900-915)

9 10 11 12 13 14 15 16 17

Rail Relocation Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-200) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(300mm=22 Nos)) Cable fitting Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Ballast mixing & laying in progress (Ch 0-200) Shuttering of slab in progress (2nd portion) Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=21Nos) Cable fitting in progress Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 24th Dec,11


S.l. No. 1 2 3 4 Description Yard Drainage(Seg-1A) RMG (Seg-1A) Work Program of 24th Dec.11 800mm(6 Nos) & 300mm (8Nos) Installation 15rm Base CC 15 rm Side CC Achievement of 23th Dec.11 300mm(8 Nos), installation completed. 15rm Base CC 15 rm Side CC completed
Remarks

Shingles laying (180mm layer)

Ballast mixing & laying in progress/second layer(Area=22mX12m) 01 No driving finished (Pile No-24/Anchor proof)
Settlement Record in progress for 63th day Sand bagging of preloading work in progress (1700 Nos) Surcharge material placement in progress (40,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress (Area=20mX20m) Wall casting /2nd lift/Navy Side(CH 1100-1125)

Pre-cast pile driving(Seg-1A) 01 No (Pile No-01/Anchor proof) Segment 2A Settlement Record Sand bagging for preloading work (2500 Nos)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 150mm local sand laying Wall casting /3rd lift/Navy Side(CH 1100-1125)

Open Deep Drain Wall casting /3rd lift/Country Side(CH 900-915) Ballast mixing & laying(Ch 0-200) Ballast mixing & laying in progress (Ch 0-200) Sleepers & Rail bit fixing in progress Shuttering of slab in progress (2nd portion) Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=21Nos) Cable fitting completed Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,400 Nos) CC Dismantling(Seg-2) in progress

8 9 10 11 12 13 14 15 16

Rail Relocation Sleepers & Rail bit fixing Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(300mm=22 Nos)) Shut down and Connection with main line Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 25th Dec,11


S.l. No. 1 Description Work Program of 25th Dec.11 800mm(6 Nos) & 300mm (8Nos) Installation Yard Drainage(Seg-1A) 30 rm Side CC CC Casting of 3 Nos Gully hole. 2 3 4 5 RMG (Seg-1A) Achievement of 24th Dec.11 800mm(6 Nos) & 300mm (8Nos) Installation 15rm Base CC 15 rm Side CC completed
Remarks

Shingles laying (180mm layer)

Shingles laying (180mm layer),Area=55mX22m No driving for mechanical fault


Settlement Record in progress for 64th day Sand bagging of preloading work in progress (1700 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress (Area=25mX25m) Bracing fixing (10 rm)

Pre-cast pile driving(Seg-1A) 01 No (Pile No-01/Anchor proof) Segment 2A Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing Settlement Record Sand bagging for preloading work (2500 Nos)

Segment-2 150mm local sand laying Wall casting /3rd lift/Navy Side(CH 1100-1125)

Open Deep Drain Wall casting /3rd lift/Country Side(CH 900-915) Ballast mixing & laying(Ch 0-200) Ballast mixing & laying in progress (Ch 0-200) Sleepers & Rail bit fixing in progress Shuttering of slab in progress (2nd portion)

8 9 10 11 12 13 14 15 16

Rail Relocation Sleepers & Rail bit fixing Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(300mm=23 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=22Nos) connection of 11KV line completed Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 27th Dec,11


S.l. No. 1 Description Work Program of 27th Dec.11 Base CC of 15rm (for 300mm) Base casting of 4 Nos Gully hole 2 3 4 5 Water Supply Line RMG (Seg-1A) Welding of100mm dia pipe Achievement of 26th Dec.11 800mm(1 No) ,700mm(1No) & 300mm (1No) Installation Rebar binding of Base of Gully hole (04 Nos) Welding of100mm dia pipe in progress
Remarks

Yard Drainage(Seg-1A)

Earth Excavation (Length=59m)

Shingles laying (180mm layer),Area=60mX22m


01 No (Pile No-01/Anchor proof) Settlement Record in progress for 65th day Sand bagging of preloading work in progress (1700 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 150mm local sand laying finished (Area=120mX44m) Navy gate wall casting,1st lift/Yard side(2 rm)

Pre-cast pile driving(Seg-1A) 01 No (Pile No-02/Anchor proof) Segment 2A Settlement Record Sand bagging for preloading work (2500 Nos)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 300mm sand blanket laying

Open Deep Drain

Ballast mixing & laying(Ch 0-200) 9 Rail Relocation Sleepers & Rail bit fixing 10 11 12 13 14 15 16 17 18 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Road maintainance work(Program of Prime Minister) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(500mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Rolling & water spraying

Ballast mixing & laying in progress (Ch 0-200) Sleepers & Rail bit fixing in progress
Due to program of Prime Minister all road adjacent work is stop, ordered by CPA.

Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress FDD Test of 150mm local sand layer (Seg-2A) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress Pipe removing,Road Levelling ,Rolling & water spraying in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 29th Dec,11


S.l. No. Description Work Program of 29th Dec.11 300 mm dia (02 Nos) pipe installation 1 Yard Drainage(Seg-1A) Base CC (30rm) Gully hole base casting (01 no),wall casting (2 nos),manhole base casting (1 no) Achievement of 28th Dec.11 500mm(1 No) , 300mm (1No) pipe Installation Side CC (10rm) Base casting of Gully hole(4 nos),manhole wall casting ( 1 no )
Remarks

Earth excavation
2 RMG (Seg-1A)

Ballast laying (300mm layer),Area=20mX22m

Rebar fabrication of longitudinal sleepers


3 4 Pre-cast pile driving(Seg-1A) 01 No (Pile No-22/Anchor proof) Segment 2A Settlement Record Sand bagging for preloading work (2000 Nos) 5 Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing 6 Segment-2 300mm sand blanket laying Back filling at Navy gate 7 Open Deep Drain Earth excavation (CH 900-920) Ballast mixing & laying(Ch 0-400) 8 9 10 11 12 13 14 15 16 17 Rail Relocation Sleepers & Rail bit fixing Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(500mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,300 Nos) CC Dismantling(Seg-2) in progress Sleepers & Rail bit fixing in progress Ballast mixing & laying in progress (Ch 0-400) 300mm sand blanket laying in progress Navy gate wall casting,1st lift/Yard side(2 rm) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 01 No (Pile No-03/Anchor proof) Settlement Record in progress for 67th day Sand bagging of preloading work in progress (1500 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of 31th Dec,11


S.l. No. Description Work Program of 31th Dec.11 300 mm dia (02 Nos) pipe installation 1 Yard Drainage(Seg-1A) Base CC (30rm) Gully hole base casting (01 no),wall casting (2 nos),manhole base casting (1 no) Achievement of 30th Dec.11 500mm(1 No) , 300mm (1No) pipe Installation Side CC (10rm) Base casting of Gully hole(4 nos),manhole wall casting ( 1 no )
Remarks

Singles Laying 1st layer(520mm thick)


2 RMG (Seg-1A)

Rebar fabrication of longitudinal sleepers


3 4 Pre-cast pile driving(Seg-1A) Segment 2A All materials of load test reached at site and preparation in progress Settlement Record Sand bagging for preloading work (2000 Nos) 5 Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing 6 Segment-2 300mm sand blanket laying Back filling at Navy gate 7 Open Deep Drain Earth excavation (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying(Ch 0-600) 8 9 10 11 12 13 14 15 16 17 Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(500mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Earth excavation executed (30m out of 59mof 2nd phase) Rebar fabrication of longitudinal sleepers in progress
01 No (Pile No-23/Anchor proof) Settlement Record in progress for 69th day Sand bagging of preloading work in progress (1000 Nos) Surcharge material placement in progress (37,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress Earth excavation (CH 1000-1040) in progress Rebar fabrication executed Ballast mixing & laying in progress (Ch 0-400) Sleepers & Rail bit fixing in progress Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

You might also like