Daily Program Dec-2011
Daily Program Dec-2011
S.l. No. Description Work Program of 1st Dec. 2011 Drainage pipe installation 1 Segment 1A Sub-base materials laying Water Supply pipe Installation work Layout of HT Cable Trench 2 3 Segment 2A Segment 1 Surcharge material placement Wall casting/Yard side/1st lift (CH 865-885) 4 Open Deep Drain Concrete Pouring of Base (CH 885-900) 5 Rail Relocation Sub base preparation (CH 550-620) Shuttering of slab 6 Electric Sub station Concrete pouring of Column 7 8 9 Wasa Relocation Laboratory / Field Test Interlocking Block ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Newly installed line is functioning Rebar fabrication executed Sub base preparation (CH 550-620) in progress Shuttering of slab in progress Surcharge material placement in progress Concrete pouring of Base finished Settlement Record Sand bagging for preloading work Settlement Record in progress Sand bagging for preloading work in progress Achievement of 30th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Water Supply pipe Installation work in progress
Remarks
10 Dismantling work
11
10 Dismantling work
11
Work Program of 6th Dec.11 Earth excavation and pipe installation Earth Excavation for Pipe laying Sub-base materials laying & Bed Rolling Settlement Record Sand bagging for preloading work
Remarks
250mm pipe welding (04 Nos) Shingles-Sand mixing (500cft) Settlement Record in progress for 45th day Sand bagging of preloading work in progress (2000 Nos) Surcharge material placement (40,000cft) Wall casting/Country side/1st lift ,CH 910930,(Quantity= 6cum) Wall casting/Yard side/1st lift ,CH 870880,(Quantity=4.5 cum) Sub base preparation in progress(CH 550-620) Sub base watering & Shoulder preparation in progress Shuttering and Rebar binding of slab in progress Concrete pouring of Sheet Pile (01 Nos) Concrete Pouring (300mm dia=26 Nos) Excavation executed for pole driving (11KV Line),Quantity=7 Nos
Shuttering and Rebar binding of slab Concrete pouring of Sheet Pile(01 Nos) Concrete pouring(300mm) Dismantling of 11 KV Line
4 5 6
Pre-cast pile driving(Seg-1A) 02 Nos Segment 2A Segment 1 Surcharge material placement Settlement Record Sand bagging for preloading work
7 8 9 10 11 12 13 14 15 16 17
Segment-2 Open Deep Drain Rail Relocation Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work
Clearing & Grubbing Wall casting /2nd lift/Port Side(CH 1100-1125) Ballast mixing & laying(Ch 0-200) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring Concrete pouring(300mm) Cable fitting Regular Test (ILB/Cylinder) ILB production CC Dismantling (Seg-2)
Shingles laying (180mm layer) Earth Excavation for 2nd portion (59 rm)
4 5
Pre-cast pile driving(Seg-1A) 01 No (Anchor proof) Segment 2A Settlement Record Sand bagging for preloading work (2500 Nos)
Segment-2 150mm local sand laying Wall casting /2nd lift/Navy Side(CH 1100-1125)
9 10 11 12 13 14 15 16 17
Rail Relocation Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work
Ballast mixing & laying(Ch 0-200) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(300mm=22 Nos)) Cable fitting Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
Ballast mixing & laying in progress (Ch 0-200) Shuttering of slab in progress (2nd portion) Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=21Nos) Cable fitting in progress Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress
Ballast mixing & laying in progress/second layer(Area=22mX12m) 01 No driving finished (Pile No-24/Anchor proof)
Settlement Record in progress for 63th day Sand bagging of preloading work in progress (1700 Nos) Surcharge material placement in progress (40,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress (Area=20mX20m) Wall casting /2nd lift/Navy Side(CH 1100-1125)
Pre-cast pile driving(Seg-1A) 01 No (Pile No-01/Anchor proof) Segment 2A Settlement Record Sand bagging for preloading work (2500 Nos)
Segment-2 150mm local sand laying Wall casting /3rd lift/Navy Side(CH 1100-1125)
Open Deep Drain Wall casting /3rd lift/Country Side(CH 900-915) Ballast mixing & laying(Ch 0-200) Ballast mixing & laying in progress (Ch 0-200) Sleepers & Rail bit fixing in progress Shuttering of slab in progress (2nd portion) Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=21Nos) Cable fitting completed Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,400 Nos) CC Dismantling(Seg-2) in progress
8 9 10 11 12 13 14 15 16
Rail Relocation Sleepers & Rail bit fixing Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(300mm=22 Nos)) Shut down and Connection with main line Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
Pre-cast pile driving(Seg-1A) 01 No (Pile No-01/Anchor proof) Segment 2A Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing Settlement Record Sand bagging for preloading work (2500 Nos)
Segment-2 150mm local sand laying Wall casting /3rd lift/Navy Side(CH 1100-1125)
Open Deep Drain Wall casting /3rd lift/Country Side(CH 900-915) Ballast mixing & laying(Ch 0-200) Ballast mixing & laying in progress (Ch 0-200) Sleepers & Rail bit fixing in progress Shuttering of slab in progress (2nd portion)
8 9 10 11 12 13 14 15 16
Rail Relocation Sleepers & Rail bit fixing Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(300mm=23 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Concrete pouring in progress(10Nos) Concrete Pouring (300mm dia=22Nos) connection of 11KV line completed Regular Test (ILB/Cylinder) in progress ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress
Yard Drainage(Seg-1A)
Pre-cast pile driving(Seg-1A) 01 No (Pile No-02/Anchor proof) Segment 2A Settlement Record Sand bagging for preloading work (2500 Nos)
Ballast mixing & laying(Ch 0-200) 9 Rail Relocation Sleepers & Rail bit fixing 10 11 12 13 14 15 16 17 18 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Road maintainance work(Program of Prime Minister) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(500mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Rolling & water spraying
Ballast mixing & laying in progress (Ch 0-200) Sleepers & Rail bit fixing in progress
Due to program of Prime Minister all road adjacent work is stop, ordered by CPA.
Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress FDD Test of 150mm local sand layer (Seg-2A) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress Pipe removing,Road Levelling ,Rolling & water spraying in progress
Earth excavation
2 RMG (Seg-1A)
Earth excavation executed (30m out of 59mof 2nd phase) Rebar fabrication of longitudinal sleepers in progress
01 No (Pile No-23/Anchor proof) Settlement Record in progress for 69th day Sand bagging of preloading work in progress (1000 Nos) Surcharge material placement in progress (37,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress Earth excavation (CH 1000-1040) in progress Rebar fabrication executed Ballast mixing & laying in progress (Ch 0-400) Sleepers & Rail bit fixing in progress Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress