Daily Program January-2012

The document provides the work program and progress updates for the NCT Back-up Project in Chittagong, Bangladesh for multiple dates in January 2012. It details the planned and completed tasks across different segments of the project, including rebar fabrication, pre-cast pile driving, drainage works, road works, and railway works. Key tasks addressed include laying ballast and sleepers, casting concrete structures, installing sheet piles, placing surcharge material for preloading, and conducting settlement monitoring and testing. Progress is reported against targets by project managers and engineers overseeing different sections.

Uploaded by

Mahibul Hasan
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views

Daily Program January-2012

The document provides the work program and progress updates for the NCT Back-up Project in Chittagong, Bangladesh for multiple dates in January 2012. It details the planned and completed tasks across different segments of the project, including rebar fabrication, pre-cast pile driving, drainage works, road works, and railway works. Key tasks addressed include laying ballast and sleepers, casting concrete structures, installing sheet piles, placing surcharge material for preloading, and conducting settlement monitoring and testing. Progress is reported against targets by project managers and engineers overseeing different sections.

Uploaded by

Mahibul Hasan
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 25

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 1,2012

S.l. No. Description Work Program of January 1,2012 Achievement of December 31,2011 300mm (16No) pipe Installation 1 Yard Drainage(Seg-1A) Base CC (15rm) CC casting of 2 nos gully hole and 1 no manhole Side CC (30 rm)
Remarks

RMG (Seg-1A)

Singles Laying 2nd layer(520mm thick) / Ch 78Singles Laying 1st layer(520mm thick)/Ch 78-137 137 Rebar fabrication of longitudinal sleepers (Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-78) 78) in progress
All materials of load test reached at site and preparation in progress Settlement Record in progress for 70th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress Earth excavation (CH 1000-1040) in progress Rebar fabrication executed Ballast mixing & laying in progress (Ch 0-400) Sleepers & Rail bit fixing in progress Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=11,800 Nos) CC Dismantling(Seg-2) in progress

3 4

Pre-cast pile driving(Seg-1A) Identify pile for load test Segment 2A Settlement Record Sand bagging for preloading work (2000 Nos)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 300mm sand blanket laying Back filling at Navy gate

Open Deep Drain

Earth excavation (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying(Ch 0-600)

8 9 10 11 12 13 14 15 16 17

Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(500mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 2,2012


S.l. No. 1 CC Casting of 1 no manhole. CC casting of 2 nos gully hole Description Work Program of January 2,2012 CC Casting of Cable trench. Achievement of January 1,2011 Base CC (15rm)
Remarks

RMG (Seg-1A)

Singles Laying 2nd layer(520mm thick) / Ch 78137 Rebar fabrication of longitudinal sleepers (Ch 078)

Singles Laying 2nd layer(520mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-78) in progress
Preparation of load test in progress Settlement Record in progress for 71th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress Earth excavation finished (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,000 Nos) CC Dismantling(Seg-2) in progress

3 4

Pre-cast pile driving(Seg-1A) Preparation of load test Segment 2A Settlement Record Sand bagging for preloading work (2000 Nos)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 300mm sand blanket laying Back filling at Navy gate

Open Deep Drain

CC Casting (CH 1000-1040) Earth Excavation (Ch 1125-1140) Ballast mixing & laying(Ch 0-600)

8 9 10 11 12 13 14 15 16 17

Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(800mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 3,2012


S.l. No. 1 Description Yard Drainage Work Program of January 3,2012 Base CC (15rm) Achievement of January 2,2011 Earth excavation (15rm)
Remarks

RMG (Seg-1A)

Singles Laying 2nd layer(520mm thick) / Ch 78137 Rebar fabrication of longitudinal sleepers (Ch 078)

Singles Laying 2nd layer(520mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-78) in progress
Preparation of load test in progress Earth Excavation executed. Settlement Record in progress for 72th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress CC Casting (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress

3 4 5

Pre-cast pile driving(Seg-1A) Preparation of load test Cable Trench (Seg-1A) Segment 2A CC Casting Settlement Record Sand bagging for preloading work (2000 Nos)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 300mm sand blanket laying Back filling at Navy gate

Open Deep Drain

Rebar fabrication of Base (CH 1000-1040) Earth Excavation (Ch 1125-1140) Ballast mixing & laying(Ch 0-600)

9 10 11 12 13 14 15 16 17 18

Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(800mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 4,2012


S.l. No. 1 Description Work Program of January 4,2012 Side CC (30rm) Yard Drainage Pipe Installation 30 rm(300mm dia) Wall casting of 01 No Manhole Base Casting of 02 Nos Gully hole & 01 No Manhole Achievement of January 3,2011 Base CC executed (30rm)
Remarks

RMG (Seg-1A)

Singles Laying 2nd layer(520mm thick) / Ch 78-137 finished Rebar fabrication of longitudinal sleepers (Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-78) 78) in progress Ballast Laying (300mm thick) / Ch 78-137
Sand bagging for load test in progress Earth Excavation executed. Settlement Record in progress for 73th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft)

3 4 5

Pre-cast pile driving(Seg-1A) Sand bagging for load test Cable Trench (Seg-1A) Segment 2A CC Casting Settlement Record Sand bagging for preloading work (2000 Nos)

Segment 1

Surcharge material placement (50,000 cft) Pre-cast Bracing installation

Segment-2

Clearing & Grubbing 300mm sand blanket laying Back filling at Navy gate

Clearing & Grubbing in progress 300mm sand blanket laying in progress(500 sqm) Back filling at Navy gate in progress Rebar fabrication of Base (CH 1000-1040)

Open Deep Drain

Base casting (CH 1000-1040) Bracing fixing (6rm)

9 10 11 12 13 14 15 16 17 18

Rail Relocation Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer) Shuttering & Rebar binding of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos)

Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering & Rebar binding of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos)

Concrete pouring(800mm=03 Nos,900mm=02 Nos) Concrete Pouring (800mm=03Nos & 900mm=02 Nos) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=10,500 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 7,2012


S.l. No. 1 Description Yard Drainage Work Program of January 7,2012 Base Casting of 02 Nos Gully hole & 01 No Man hole. Achievement of January 6,2011 Rebar binding of Base (02 Nos Gully hole & 01 No Man hole)
Remarks

Shingles Laying (180mm thick) / Ch 78-137


2 RMG (Seg-1A)

Longitudinal sleeper casting (Ch 0-10)


3 4 5 6 Pre-cast pile driving(Seg-1A) Sand bagging for load test Sheet Pile Driving Cable Trench (Seg-1A) Segment 2A Preparation of Pile shifting to bank. CC Casting Settlement Record Sand bagging for preloading work (2000 Nos) Surcharge material placement (50,000 cft) 8 Segment-2 Clearing & Grubbing 300mm sand blanket laying 9 Open Deep Drain CC Casting (Outlet point) Wall casting / Port side/1st lift (CH 1015-1040) 10 11 12 13 14 15 16 17 Rail Relocation Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper Laboratory / Field Test Interlocking Block Dismantling work Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer) Shuttering & Rebar binding of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Ballast layer compaction (300mm thick) / Ch 78137 finished Rebar fabrication of longitudinal sleepers(Ch 0-10) finished.
Sand bagging for load test in progress

CC Casting executed. Settlement Record in progress for 77th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress(500 sqm) Soling executed. Rebar fabrication executed (CH 1015-1040) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering & Rebar binding of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Regular Test (ILB/Cylinder) ILB production in progress (Quantity=10,500 Nos) CC Dismantling(Seg-2) in progress

Segment 1

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 9,2012


S.l. No. 1 Description Work Program of January 9,2012 15 m Base CC casting (300mm) Yard Drainage(Seg-1A) Wall Casting of 03 Nos Gully hole . Rebar binding executed (wall of 03 Nos Gully hole) Achievement of January 8,2011 15m Earth Excavation

Shingles Laying (180mm thick) / Ch 78-137


2 RMG (Seg-1A)

Longitudinal sleeper casting (Ch 0-10)


3 4 5 6 Sheet Pile Driving Water Supply Line Cable Trench (Seg-1A) Segment 1 Pile shifting to bank. Leak test of 50m pipe (250mm dia) Brick masonry of wall Sand bagging for preloading work (2000 Nos) Surcharge material placement (50,000 cft) 7 Segment-2 Clearing & Grubbing PVD Driving 8 Open Deep Drain Wall casting / Navy side/2nd lift (CH 1015-1040) 9 10 11 12 13 14 15 Rail Relocation Road Type-1 Electric Sub station Sheet Pile Laboratory / Field Test Interlocking Block Dismantling work Concrete pouring of Sheet Pile(01 Nos) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer)

Shingles Laying (180mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-10) in progress.
Pile shifting to bank in progress 50 m pipe welding completed (250mm dia) Brick masonry of wall in progress Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress FDD test executed at 300mm sand blanket

Wall casting / Port side/1st lift (CH 1015-1040) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Slab casting of 2nd portion executed Concrete pouring of Sheet Pile(01 Nos) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,400 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 9,2012


Remarks

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 10,2012


S.l. No. 1 Description Work Program of January 10,2012 300mm Pipe installation(15rm) Yard Drainage(Seg-1A) Wall Casting of 03 Nos Gully hole and base casting of 02 Nos Gully hole. Achievement of January 9,2011 15 m Base CC casting executed. Wall Casting of 03 Nos Gully hole executed

RMG (Seg-1A)

Rolling of Shingles Layer (180mm thick) / Ch 78Shingles Laying (180mm thick) / Ch 78-137 finished 137 Rebar fabrication of longitudinal sleepers(Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-10) 10) in progress. in progress.
Pile shifting to bank. Leak test of 50m pipe (250mm dia) Brick masonry of wall Sand bagging for preloading work (2000 Nos) Surcharge material placement (50,000 cft) Pile shifting to bank in progress 50 m pipe welding completed (250mm dia) Brick masonry of wall in progress Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress PVD Driving in progress Wall casting / Navy side/2nd lift (CH 1015-1040) executed. Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=11,300 Nos) CC Dismantling(Seg-2) in progress

3 4 5 6

Sheet Pile Driving Water Supply Line Cable Trench (Seg-1A) Segment 1

Segment-2

Clearing & Grubbing PVD Driving Earth Excavation (CH 1040-1060)

Open Deep Drain Wall casting / Yard side/2nd lift (CH 1015-1040) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

9 10 11 12 13 14

Rail Relocation Road Type-1 Sheet Pile Laboratory / Field Test Interlocking Block Dismantling work

Sub base material placement (2nd layer) Concrete pouring of Sheet Pile(01 Nos) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 10,2012


Remarks

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 14,2012


S.l. No. 1 2 3 4 5 6 7 8 Description Yard Drainage(Seg-1A) RMG Track(Seg-1A) Seg-1A(mosque portion) Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2 Work Program of January 14,2012 Side CC Casting/30rm/300mm dia pipe Achievement of January 13,2011 Shuttering executed

Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving Base Casting (CH 985-1015)

Soling work in progress


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Brick masonry of wall in progress Surcharge material placement in progress (40,000cft) Clearing & Grubbing in progress PVD Driving in progress Rebar binding executed. Rebar binding executed. Pre-cast Bracing Casting (02 Nos) in progress Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,300 Nos) CC Dismantling(Seg-2) in progress

Open Deep Drain

Wall casting / Yard side/2nd lift (CH 1015-1040) Pre-cast Bracing Casting (06 Nos)

10 11 12 13 14

Rail Relocation Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 14,2012


Remarks

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 15,2012


S.l. No. 1 Description Work Program of January 15,2012 Side CC Casting/30rm/300mm dia pipe Yard Drainage(Seg-1A) Wall casting of 03 Nos Gully hole and 01 No Man hole Achievement of January 14,2011 Shuttering executed Shuttering executed

2 3 4 5 6 7 8

RMG Track(Seg-1A) Seg-1A(mosque portion) Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2

Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving

Soling work in progress


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Brick masonry of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress PVD Driving in progress Base Casting (CH 985-1000) Pre-cast Bracing Casting (06 Nos) in progress Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Rebar fabrication and Shuttering executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress

Open Deep Drain

Base Casting (CH 1000-1015) Pre-cast Bracing Casting (06 Nos)

10 11 12 13 14 15

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 15,2012


Remarks

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 16,2012


S.l. No. 1 Description Work Program of January 16,2012 Achievement of January 15,2011 Side CC Casting/30rm/300mm dia pipe Yard Drainage(Seg-1A) Wall casting of 01 No Gully hole and 01 No Man hole Wall casting of 02 Nos Gully hole and 01 No Man hole .
Remarks

2 3 4 5 6 7 8

RMG Track(Seg-1A) Seg-1A(mosque portion) Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2

Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving

Soling work in progress


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Brick masonry of wall in progress Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress PVD Driving in progress Base Casting (CH 1000-1015)

Open Deep Drain

Wall casting 1st lift(CH 985-1015) Pre-cast Bracing Casting (06 Nos)

10 11 12 13 14 15

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Rebar fabrication and Shuttering executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=13,600 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 17,2012


S.l. No. 1 Description Work Program of January 17,2012 02 Nos 300mm dia pipe,01 No 700mm dia pipe fixing. Shuttering & Rebar fabrication of 02 Nos Gully hole. Wall casting of 01 No Gully hole and 01 No Man hole 2 3 4 5 6 7 8 9 RMG Track(Seg-1A) Seg-1A(mosque portion) Sub-station Building Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2 Achievement of January 16,2011
Remarks

Yard Drainage(Seg-1A)

Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Sand filling & Soling work Plaster work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing Soling & CC work (CH 1015-1030) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress Earth Excavation executed. Shuttering & Rebar fabrication executed. Pre-cast Bracing Casting (06 Nos) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Pre-cast Sleepers casting (10 Nos) in progress. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,250 Nos) CC Dismantling(Seg-2) in progress

Sand filling & Soling work in progress Plaster work in progress.


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress.

10

Open Deep Drain

Wall casting 1st lift(CH 985-1015) Pre-cast Bracing Casting (06 Nos)

11 12 13 14 15 16

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 18,2012


S.l. No. Description 1 Yard Drainage(Seg-1A) Shuttering & Rebar fabrication of 02 Nos Gully hole. 2 3 4 5 6 7 8 RMG Track(Seg-1A) Seg-1A(mosque portion) Sub-station Building Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Work Program of January 18,2012 Side CC Casting of 10rm Achievement of January 17,2011 02 Nos 300mm dia pipe,01 No 700mm dia pipe fixing. Shuttering & Rebar fabrication of 02 Nos Gully hole and 02 Nos Manhole.
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) in progress. in progress. Sand filling & Soling work Plaster work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing

Sand filling & Soling work in progress Plaster work in progress.


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress 200mm sand blanket laying in progress Soling & CC work (CH 1015-1030)

Segment-2

150mm local sand laying 200mm sand blanket laying Rebar fabrication of Base (CH 1015-1030)

10

Open Deep Drain

Rebar fabrication of Wall 1st lift(CH 985-1015)/Navy Wall casting 1st lift(CH 985-1015)/Yard Side side. Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (05 Nos) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder)

11 12 13 14 15 16

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 20,2012


S.l. No. Description 1 Yard Drainage(Seg-1A) Wall Shuttering of 02 Nos Man hole Wall casting of 02 Nos Gully hole Work Program of January 20,2012 Rebar fabrication of 03 Nos Gully hole Achievement of January 19,2011
Remarks

RMG Track(Seg-1A)

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) in progress. in progress. Pre-cast sleepers shifting to Seg-1

3 4 5 6 7 8 9

Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1

Soling work Sub-base material laying Plaster work & Parapet shuttering
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing

Soling work in progress Bed preparation finished Plaster work & Parapet casting in progress.
Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress 200mm sand blanket laying in progress Base casting (CH 970-990) Wall casting 1st lift(CH 990-1015)/Navy Side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production (Quantity=11000 Nos) CC Dismantling(Seg-2) in progress

10

Segment-2

150mm local sand laying 200mm sand blanket laying Shuttering of wall (CH 1015-1030)

11

Open Deep Drain Back filling(CH 990-1015)/Navy side. Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

12 13 14 15 16 17

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 21,2012


S.l. No. Description 1 Yard Drainage(Seg-1A) Wall Shuttering of 02 Nos Man hole Wall Shuttering of 02 Nos Man hole in progress Work Program of January 21,2012 Rebar fabrication of 03 Nos Gully hole Achievement of January 20,2011 Rebar fabrication of 03 Nos Gully hole in progress
Remarks

RMG Track(Seg-1A)

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Pre-cast sleepers shifting to Seg-1 Pre-cast sleepers shifting to Seg-1 in progress Soling work finished. Sub-base material laying finished. Plaster work & Parapet shuttering.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket compaction finished. 200mm sand blanket laying in progress Earth excavation (CH 950-970) Back filling(CH 990-1015)/Navy side. Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) finished. Regular Test (ILB/Cylinder) ILB production (Quantity=12000 Nos) CC Dismantling(Seg-2) in progress

3 4 5 6 7 8

Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Cable Trench (Seg-1A) Segment-1

Rebar binding of raft foundation. Sub-base material compaction. Plaster work & Parapet casting.
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2

PVD Driving 200mm sand blanket laying Wall casting 2nd lift (CH 990-1015)/Navy Side

10

Open Deep Drain Soling & CC (CH 950-970)/Navy side. Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

11 12 13 14 15 16

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Pre-cast Sleepers casting (10 Nos) Field density test of sub-base. Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 22,2012


S.l. No. Description 1 Yard Drainage (Seg 1A) Work Program of January 22,2012 Man hole wall casting (01 No) Achievement of January 21,2011 Man hole wall casting (01 No)
Remarks

Concrete Pouring (CH 0-20)


2 RMG Track(Seg-1A)

Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress. Pre-cast sleepers shifting to Seg-1 in progress Rebar binding of raft foundation in progress. Sub-base material laying finished. Plaster work & Parapet casting.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 200mm sand blanket laying in progress Wall casting 2nd lift (CH 990-1015)/Navy Side Soling (CH 950-970) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Trial Mix design (40 Mpa) ILB production (Quantity=11500 Nos) CC Dismantling(Seg-2) in progress

Pre-cast sleepers shifting to Seg-1


3 4 5 6 7 8 9 Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Cable Trench (Seg-1A) Segment-1 Segment-2

Rebar binding of raft foundation. Sub-base material compaction. Plaster work .


Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing 200mm sand blanket laying Wall casting 2nd lift (CH 990-1015)/Yard Side

10

Open Deep Drain CC (CH 950-970) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

11 12 13 14

Rail Relocation Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 23,2012


S.l. No. Description 1 2 3 4 5 6 7 8 9 Yard Drainage (Seg 1A) RMG Track(Seg-1A) Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Cable Trench (Seg-1A) Segment-1 Segment-2 Work Program of January 23,2012 Man hole wall casting (01 No) Achievement of January 22,2011 Shuttering executed.
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30Concrete Pouring (CH 0-10) 40) in progress. Rebar binding of raft foundation. Sub-base material laying Plaster work .
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing 200mm sand blanket laying Wall casting 1st lift (CH 970-990)/Yard Side

Rebar binding of raft foundation in progress. Sub-base material laying in progress Plaster work in progress
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 200mm sand blanket laying in progress Wall casting 1st lift (CH 970-990)/Navy Side Soling & CC (CH 950-970) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Regular Test (ILB/Cylinder) ILB production (Quantity=10500 Nos) CC Dismantling(Seg-2) in progress

10

Open Deep Drain Earth Excavation (CH 935-950) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

11 12 13 14

Rail Relocation Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 24,2012


S.l. No. Description 1 2 3 4 5 6 7 8 9 10 Yard Drainage (Seg 1A) RMG Track(Seg-1A) Seg-1A(mosque portion) Service Area Sub-station Building Segment-2A Sheet Pile Driving Cable Trench (Seg-1A) Segment-1 Segment-2 Work Program of January 24,2012 Man hole wall casting (01 No) Achievement of January 23,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Sub-base material laying & compaction Plaster work . Surcharge Removing
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) PVD Driving 200mm sand blanket laying Wall casting 2nd lift (CH 970-990)/Yard Side 200mm sand blanket laying in progress Wall casting 1st lift (CH 970-990)/Yard Side Earth Excavation (CH 935-950) In progress

Rebar binding of raft foundation in progress. Sub-base material laying & compaction in progress Plaster work in progress Surcharge Removing in progress.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (40,000cft)

11

Open Deep Drain

Earth Excavation (CH 935-950) Bracing fixing (06 Nos)

12 13 14

Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Regular Test (ILB/Cylinder) ILB production (Quantity=13200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 25,2012


S.l. No. 1 2 3 4 5 6 7 8 Description RMG Track(Seg-1A) Seg-1A(mosque portion) Service Area Sub-station Building Segment-2A Sheet Pile Driving Segment-1 Segment-2 Work Program of January 25,2012 Achievement of January 24,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Sub-base material compaction Plaster work . Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) PVD Driving 150mm local sand laying. Wall casting 2nd lift (CH 970-990)/Yard Side

Rebar binding of raft foundation in progress. Sub-base material laying finished. Plaster work in progress Surcharge Removing in progress.
Pile shifting to bank in progress Surcharge material placement in progress (35,000cft) PVD Driving in progress. 150mm local sand laying in progress. Wall casting 1st lift (CH 970-990)/Yard Side Earth Excavation (CH 935-950)

Open Deep Drain

CC ,Soling (CH 935-950) Bracing fixing (06 Nos)

10 11 12

Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 26,2012


S.l. No. 1 2 3 4 5 6 7 8 9 10 11 12 Description RMG Track(Seg-1A) Seg-1A(mosque portion) Service Area Sub-station Building Segment-2A Sheet Pile Driving Segment-1 Segment-2 Open Deep Drain Rebar binding of Base (CH 935-970) Laboratory / Field Test Interlocking Block Dismantling work Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Work Program of January 26,2012 Achievement of January 25,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Lean concrete casting Bricks masonry work Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) 150mm local sand laying.

Rebar binding of raft foundation in progress.

Surcharge Removing in progress.


Pile shifting to bank in progress Surcharge material placement in progress (42,000cft) 150mm local sand laying in progress. Wall casting 2nd lift (CH 970-990)/Yard Side CC ,Soling (CH 935-950) Regular Test (ILB/Cylinder) ILB production (Quantity=14200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 30,2012


S.l. No. 1 Description RMG Track(Seg-1A) Work Program of January 30,2012 Achievement of January 29,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Base casting of 03 Nos Gully holes & wall casting of 01 No Manhole. Bricks masonry work FDD Test of 150mm local sand layer Rebar fabrication and shuttering executed. Bricks masonry work in progress.

2 3

Yard Drainage Sub-station Building

Segment-2

FDD Test of 200mm sand blanket layer


5 6 7 8 9 10 11 Segment-2A Sheet Pile Driving Segment-1 Open Deep Drain Laboratory / Field Test Interlocking Block Dismantling work

Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) Wall casting 1st lift (CH 955-970)/Navy Side Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Surcharge Removing in progress.


Pile shifting to bank in progress Surcharge material placement in progress (45,000cft) Wall casting 1st lift (CH 935-955)/Navy Side Regular Test (ILB/Cylinder) ILB production (Quantity=14200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 31,2012


S.l. No. 1 2 Description RMG Track(Seg-1A) Yard Drainage Work Program of January 31,2012 Achievement of January 30,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Earth excavation for pipe laying. Bricks masonry work Base casting of 03 Nos Gully holes & wall casting of 01 No Manhole. Bricks masonry work in progress. CC Casting executed.

Sub-station Building Bricks masonry work of Safety Tank. FDD Test of 150mm local sand layer

4 5 6 7 8 9 10

Segment-2

FDD Test of 200mm sand blanket layer


Segment-2A Segment-1 Open Deep Drain Laboratory / Field Test Interlocking Block Dismantling work

Surcharge Removing
Surcharge material placement (50,000 cft) Wall casting 1st lift (CH 955-970)/Yard Side Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Surcharge Removing in progress.(60,000 cft)


Surcharge material placement in progress (45,000cft) Wall casting 1st lift (CH 955-970)/Navy Side Regular Test (ILB/Cylinder) ILB production (Quantity=13,850 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA