Daily Program Sept-2011
Daily Program Sept-2011
5 6 7 8 9
Road Work Rail Relocation Electric Relocation Interlocking Block Dismantling work
Embankment Preparation Embankment Preparation Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4 ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress Embankment Preparation in progress
Remarks
5 6 7 8 9
Road Work Rail Relocation Electric Relocation Interlocking Block Dismantling work
Embankment Preparation Embankment Preparation Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4
Remarks
Bracing fixing in progress Rebar fabrication in progress Embankment Preparation in progress Embankment Preparation in progress Pole Erection in progress ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress
5 6 7 8 9
Road Work Rail Relocation Electric Relocation Interlocking Block Dismantling work
Embankment Preparation Embankment Preparation Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4
Remarks
5 6
7 8 9 10
Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4
Plant Shifting in progress Pole Erection in progress ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress
Remarks
5 6
7 8 9 10 11
Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work
Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4
Rebar fabrication and shuttering Plant Shifting in progress Pole Erection in progress ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress
Remarks
5 6
Embankment Preparation in progress Embankment Preparation in progress Allignment checked by CPA,BRTC & Railway
7 8 9 10 11
Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work
Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4
Rebar fabrication and shuttering Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 3 & 4 in progress
Remarks
Surcharge Material Placement in progress Sub grade Preparation in progress Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication in progress Earth Excavation Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 3 & 4 in progress
5 6 7 8 9 10 11
Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work
Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4
Achievement of 21 th Sept.2011
Test Boring in progress Surcharge Material Placement in progress Sub grade Preparation in progress Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication in progress Earth Excavation Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 3 & 4 in progress
Remarks
5 6 7 8 9 10 11
Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work
Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4
Achievement of 22 th Sept.2011
Test Boring in progress Surcharge Material Placement in progress Sub grade Preparation finished Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication in progress CC casting finished Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress
Remarks
5 6 7 8 9 10 11
Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work
Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3
Achievement of 23 th Sept.2011
Test Boring executed Surcharge Material Placement in progress 150 mm local sand compaction executed
Remarks
Bracing fixing PC Bracing Casting Rebar fabrication Concrete pouring of Base (CH 840-870 )
Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication in progress Rebar fabrication & Shuttering executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress
5 6 7 8 9 10 11
Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work
Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3
Achievement of 24 th Sept.2011
Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket laying in progress
Remarks
Bracing fixing PC Bracing Casting Rebar fabrication & Shuttering of wall (CH 840-860 ) CC Casting (CH 860-870 )
Bracing fixing in progress PC Bracing Casting in Progress Concrete Pouring of Base executed Earth excavation & Soling executed Earth excavation & Soling executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress
5 6 7 8 9 10 11 12
Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work
CC Casting Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3
Achievement of 25 th Sept.2011
Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket laying in progress
Remarks
Bracing fixing PC Bracing Casting Concrete pouring of wall (CH 840-860 ) Concrete pouring of Base (CH 860-870 )
Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication & shuttering executed CC executed Earth excavation & Soling executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress
5 6 7 8 9 10 11 12
Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work
CC Casting Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3
Work Program of 27 Sept. 2011 Preparing the ground for RCC drainage pipe placement Surcharge Material Placement PVD Driving Sub grade preparation
Achievement of 26 th Sept.2011 Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket compaction executed
Remarks
Concrete pouring of wall, country side 1st lift(CH Concrete pouring of wall yard side 1st lift 840-860 ) Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) Open Deep Drain(Culvert adjacent Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Laboratory Interlocking Block Dismantling work Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection Mix design of C40 ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress
Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) 5 6 7 8 9 10 11 12 13 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Laboratory Interlocking Block Dismantling work Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Circuit (33/33/11/0.44 KV ) overhead cable fixing Mix design of C40 ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress
Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) 5 6 7 8 9 10 11 12 13 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Circuit (33/33/11/0.44 KV ) overhead cable fixing CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress
Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) 5 6 7 8 9 10 11 12 13 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Circuit (33/33/11/0.44 KV ) overhead cable fixing CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress
Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) 5 6 7 8 9 10 11 12 13 14 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing executed Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress
Rebar fabrication & Shuttering of wall (CH 830-840) CC Executed 5 6 7 8 9 10 11 12 13 14 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Laboratory Interlocking Block Dismantling work Rebar fabrication & Shuttering of wall Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing Cylinder Crushing of 7 days strength (40Mpa) ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Concrete of Base executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing executed Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress