0% found this document useful (0 votes)
42 views

Daily Program Mayl-2012

The document provides daily work programs and progress updates for the NCT Back-up Project in Chittagong, Bangladesh from May 7 to May 19, 2012. It outlines the planned work, achievements of the previous day, and remarks for various segments of the project including yard drainage, lean concrete work, substation building construction, and dismantling of existing structures. The project manager and engineering team provide status updates and track progress across multiple work stages.

Uploaded by

Mahibul Hasan
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views

Daily Program Mayl-2012

The document provides daily work programs and progress updates for the NCT Back-up Project in Chittagong, Bangladesh from May 7 to May 19, 2012. It outlines the planned work, achievements of the previous day, and remarks for various segments of the project including yard drainage, lean concrete work, substation building construction, and dismantling of existing structures. The project manager and engineering team provide status updates and track progress across multiple work stages.

Uploaded by

Mahibul Hasan
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

NCT BACK-UP PROJECT, CHITTAGONG Work Program of May 7,2012 S.l. Description No.

Segment-1A 1 Yard Drainage 2 Lean Concrete 3 Sub-station Building 4 5 6 RTG Track Service Area Cable Trench work

Work Program of May 7,2012

Achievement of May 6,2012

Remarks

Bricks work & Plastering Thai glass work of window. Rebar binding & Shuttering Wall casting of Electric Pit & Reffer DB.

Bricks work & Plastering in progress.

Rebar binding & Shuttering in progress

Segment-2A 1 Yard Drainage 2 Manhole & Gully hole 3 Cable Trench work Segment-1 1 Surcharge 2 Yard Drainage Segment-2 1 Surcharge Segment-3 1 Dismantling Segment-4 1 Surcharge Segment-4A 1 Ground Improvement Navy Area 1 Surface drain work 2 Cable Line Installation 3 1 1 1 Main gate Column Work Bracing Interlocking Block Boundary Wall

Pipe laying & CC casting

Pipe laying & CC casting in progress

Surcharge material removing Earth excavation Settlement Record Existing pavement dismantling Settlement Record Sub-grade Preparation

Surcharge material removing in progress. Earth excavation in progress. Settlement Record in progress. Existing pavement dismantling in progress. Settlement Record in progress. Sub-grade Preparation in progress.

Termination of laid cable

Termination suspended due to objection of Navy

Shutter removing Pre-cast bracing casting (10 Nos) Compressive strength test / ILB Rebar binding & Shuttering executed. Compressive strength test / ILB

Open Deep Drain Laboratory / Field Test Bank Protection work 1 Sheet Pile Interlocking Block Production (ILB) ILB Production.

ILB Production (10,520 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of May 8,2012 S.l. Description No.
Segment-1A 1 Yard Drainage 2 Lean Concrete 3 Sub-station Building 4 5 6 RTG Track Service Area Cable Trench work

Work Program of May 8,2012

Achievement of May 7,2012

Remarks

Bricks work & Plastering Thai glass work of window. Lean mix concrete. Rebar binding & Shuttering Top slab casting

Bricks work & Plastering in progress. Thai glass work of window in progress. Lean mix concrete in progress. Rebar binding & Shuttering in progress Rebar binding & Shuttering executed.

Segment-2A 1 Yard Drainage 2 Manhole & Gully hole 3 Cable Trench work Segment-1 1 Surcharge 2 Yard Drainage Segment-2 1 Surcharge Segment-3 1 Dismantling Segment-4 1 Surcharge Segment-4A 1 Ground Improvement Navy Area 1 Surface drain work 2 Cable Line Installation 3 1 1 Main gate Bracing Interlocking Block Open Deep Drain

Pipe laying & CC casting

Pipe laying & CC casting in progress

Surcharge material removing Earth excavation Settlement Record Existing pavement dismantling Settlement Record Sub-grade Preparation

Surcharge material removing in progress. Earth excavation in progress. Settlement Record in progress. Existing pavement dismantling in progress. Settlement Record in progress. Sub-grade Preparation in progress.

Cable laying

Cable laying in progress.

Pre-cast bracing casting (10 Nos) Compressive strength test / ILB

Rebar binding & Shuttering executed. Compressive strength test / ILB

Laboratory / Field Test Bank Protection work 1 Sheet Pile Interlocking Block Production (ILB) ILB Production.

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of May 9,2012 S.l. Description No.
Segment-1A 1 Yard Drainage 2 Lean Concrete 3 Sub-station Building 4 5 6 RTG Track Service Area Cable Trench work

Work Program of May 9,2012

Achievement of May 8,2012

Remarks

Bricks work & Plastering Thai glass work of window. Lean mix concrete (18 Mpa) Rebar binding & Shuttering Wall casting

Bricks work & Plastering in progress. Thai glass work of window in progress. Lean mix concrete in progress. Rebar binding & Shuttering in progress Rebar binding & Shuttering executed.

Segment-2A 1 Yard Drainage 2 Manhole & Gully hole 3 Cable Trench work Segment-1 1 Surcharge 2 Yard Drainage Segment-2 1 Surcharge Segment-3 1 Dismantling 2 Ground Improvement Segment-4 1 Surcharge Segment-4A 1 Ground Improvement Navy Area 1 Surface drain work 2 Cable Line Installation 3 1 1 Main gate Bracing Interlocking Block Open Deep Drain Laboratory / Field Test

Pipe laying & CC casting

Pipe laying & CC casting in progress

Surcharge material removing Earth excavation Settlement Record Existing pavement dismantling Sub-grade Preparation Settlement Record Sub-grade Preparation

Surcharge material removing in progress. Earth excavation in progress. Settlement Record in progress. Existing pavement dismantling in progress. Sub-grade Preparation in progress. Settlement Record in progress. Sub-grade Preparation in progress.

Cable laying

Cable laying in progress.

Compressive strength test / ILB

Compressive strength test / ILB Dismantling work in progress.

Dismantling Work 1 Boundary Wall Dismantling work 2 Existing Road Road cutting & Removal Interlocking Block Production (ILB) ILB Production

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of May 10,2012 S.l. Description No.
Segment-1A 1 Yard Drainage 2 Lean Concrete(Yard) 3 Sub-station Building 4 RTG Track 5 Service Area 6 Cable Trench work 7 RMG Track Segment-2A 1 Yard Drainage 2 Manhole & Gully hole 3 Cable Trench work Segment-1 1 Surcharge 2 Yard Drainage Segment-2 1 Surcharge Segment-3 1 Dismantling 2 Ground Improvement Segment-4 1 Surcharge Segment-4A 1 Ground Improvement Navy Area 1 Surface drain work 2 Cable Line Installation 3 1 1 Main gate Bracing Interlocking Block Compressive strength test / ILB Compressive strength test / ILB Dismantling work in progress. Road cutting & Removal in progress. Open Deep Drain Laboratory / Field Test Dismantling Work 1 Boundary Wall Dismantling work 2 Existing Road Road cutting & Removal Interlocking Block Production (ILB) ILB Production

Work Program of May 10,2012

Achievement of May 9,2012

Remarks

Bricks work & Plastering Thai glass work of window. Lean mix concrete (18 Mpa) Concrete Pouring (02 Nos block) Wall casting Concrete Pouring (02 Nos span) Pipe laying & CC casting Wall casting of 01 Nos Gully hole.

Bricks work & Plastering in progress. Thai glass work of window in progress. Lean mix concrete in progress. Rebar binding & Shuttering executed. Rebar binding & Shuttering executed.

Pipe laying & CC casting in progress

Surcharge material removing Earth excavation Settlement Record Existing pavement dismantling Sub-grade Preparation Settlement Record Sub-grade Preparation

Surcharge material removing in progress. Earth excavation in progress. Settlement Record in progress. Existing pavement dismantling in progress. Sub-grade Preparation in progress. Settlement Record in progress. Sub-grade Preparation in progress.

Cable laying

Cable laying in progress.

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of May 11,2012 S.l. Description No.
Segment-1A 1 Yard Drainage 2 Lean Concrete(Yard) 3 Sub-station Building 4 RTG Track 5 Service Area 6 Cable Trench work 7 RMG Track Segment-2A 1 Yard Drainage 2 Manhole & Gully hole 3 Cable Trench work Segment-1 1 Surcharge 2 Yard Drainage Segment-2 1 Surcharge Segment-3 1 Dismantling 2 Ground Improvement Segment-4 1 Surcharge Segment-4A 1 Ground Improvement Navy Area 1 Surface drain work 2 Cable Line Installation 3 1 1 Main gate Bracing Interlocking Block Compressive strength test / ILB Compressive strength test / ILB Dismantling work in progress. Road cutting & Removal in progress. ILB Production in progress (11200 Nos) Open Deep Drain Laboratory / Field Test Dismantling Work 1 Boundary Wall Dismantling work 2 Existing Road Road cutting & Removal Interlocking Block Production (ILB) 1 ILB Production

Work Program of May 11,2012

Achievement of May 10,2012

Remarks

Bricks work & Plastering Rebar binding & Shuttering work. Rebar binding & Shuttering work. Concrete Pouring (02 Nos span) Pipe laying & CC casting

Bricks work & Plastering in progress. Lean mix concrete executed. Wall casting executed Rebar binding & Shuttering executed. Pipe laying & CC casting in progress Wall casting of 01 No Gully hole.

Surcharge material removing Earth excavation Settlement Record Existing pavement dismantling Sub-grade Preparation Settlement Record Sub-grade Preparation

Surcharge material removing in progress. Earth excavation in progress. Settlement Record in progress. Existing pavement dismantling in progress. Sub-grade Preparation in progress. Settlement Record in progress. Sub-grade Preparation in progress.

Shutdown of laid cable.

Cable laying executed.

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of May 19,2012 S.l. Description No.
Segment-1A 1 Sub-base work 2 Lean Concrete(Yard) 3 Sub-station Building 4 RTG Track 5 Service Area 6 Cable Trench work 7 RMG Track Segment-2A 1 Yard Drainage 2 Manhole & Gully hole 3 Cable Trench work Segment-1 1 Yard Drainage Segment-2 1 Surcharge Segment-3 1 Dismantling

Work Program of May 19,2012


Sub-base work of Yard Bricks work & Plastering Shuttering of RTG pavement Rebar binding & Shuttering of Reffer (Base)

Achievement of May 18,2012


Sub-base work of Yard in progress. Bricks work & Plastering in progress. Rebar binding executed.

Remarks

Pipe laying & CC casting

Pipe laying & CC casting in progress

RCC pipe laying. Settlement Record Existing pavement dismantling

RCC pipe laying in progress. Settlement Record in progress. Existing pavement dismantling in progress. Sub-grade Preparation in progress. Settlement Record in progress. Sub-grade Preparation in progress.

2 Ground Improvement Sub-grade Preparation Segment-4 1 Surcharge Settlement Record Segment-4A 1 Ground Improvement Sub-grade Preparation Navy Area 1 Surface drain work 2 Cable Line Installation 3 1 1 Navy Boundary wall Bracing Interlocking Block Compressive strength test / ILB Navy boundary wall dismantling. Open Deep Drain Laboratory / Field Test

Compressive strength test / ILB

Dismantling Work 1 Boundary Wall 2 Existing Road Road cutting & Removal Interlocking Block Production (ILB) 1 ILB Production

Road cutting & Removal in progress. ILB Production in progress (10460 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

You might also like