Daily Program March-2012
Daily Program March-2012
S.l. No. Description Work Program of January 1,2012 Achievement of December 31,2011 300mm (16No) pipe Installation 1 Yard Drainage(Seg-1A) Base CC (15rm) CC casting of 2 nos gully hole and 1 no manhole Side CC (30 rm)
Remarks
RMG (Seg-1A)
Singles Laying 2nd layer(520mm thick) / Ch 78Singles Laying 1st layer(520mm thick)/Ch 78-137 137 Rebar fabrication of longitudinal sleepers (Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-78) 78) in progress
All materials of load test reached at site and preparation in progress Settlement Record in progress for 70th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress Earth excavation (CH 1000-1040) in progress Rebar fabrication executed Ballast mixing & laying in progress (Ch 0-400) Sleepers & Rail bit fixing in progress Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=11,800 Nos) CC Dismantling(Seg-2) in progress
3 4
Pre-cast pile driving(Seg-1A) Identify pile for load test Segment 2A Settlement Record Sand bagging for preloading work (2000 Nos)
Earth excavation (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying(Ch 0-600)
8 9 10 11 12 13 14 15 16 17
Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(500mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
RMG (Seg-1A)
Singles Laying 2nd layer(520mm thick) / Ch 78137 Rebar fabrication of longitudinal sleepers (Ch 078)
Singles Laying 2nd layer(520mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-78) in progress
Preparation of load test in progress Settlement Record in progress for 71th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress Earth excavation finished (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,000 Nos) CC Dismantling(Seg-2) in progress
3 4
Pre-cast pile driving(Seg-1A) Preparation of load test Segment 2A Settlement Record Sand bagging for preloading work (2000 Nos)
CC Casting (CH 1000-1040) Earth Excavation (Ch 1125-1140) Ballast mixing & laying(Ch 0-600)
8 9 10 11 12 13 14 15 16 17
Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(800mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
RMG (Seg-1A)
Singles Laying 2nd layer(520mm thick) / Ch 78137 Rebar fabrication of longitudinal sleepers (Ch 078)
Singles Laying 2nd layer(520mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-78) in progress
Preparation of load test in progress Earth Excavation executed. Settlement Record in progress for 72th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress CC Casting (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress
3 4 5
Pre-cast pile driving(Seg-1A) Preparation of load test Cable Trench (Seg-1A) Segment 2A CC Casting Settlement Record Sand bagging for preloading work (2000 Nos)
Rebar fabrication of Base (CH 1000-1040) Earth Excavation (Ch 1125-1140) Ballast mixing & laying(Ch 0-600)
9 10 11 12 13 14 15 16 17 18
Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(800mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
RMG (Seg-1A)
Singles Laying 2nd layer(520mm thick) / Ch 78-137 finished Rebar fabrication of longitudinal sleepers (Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-78) 78) in progress Ballast Laying (300mm thick) / Ch 78-137
Sand bagging for load test in progress Earth Excavation executed. Settlement Record in progress for 73th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft)
3 4 5
Pre-cast pile driving(Seg-1A) Sand bagging for load test Cable Trench (Seg-1A) Segment 2A CC Casting Settlement Record Sand bagging for preloading work (2000 Nos)
Segment 1
Segment-2
Clearing & Grubbing 300mm sand blanket laying Back filling at Navy gate
Clearing & Grubbing in progress 300mm sand blanket laying in progress(500 sqm) Back filling at Navy gate in progress Rebar fabrication of Base (CH 1000-1040)
9 10 11 12 13 14 15 16 17 18
Rail Relocation Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work
Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer) Shuttering & Rebar binding of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos)
Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering & Rebar binding of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos)
Concrete pouring(800mm=03 Nos,900mm=02 Nos) Concrete Pouring (800mm=03Nos & 900mm=02 Nos) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=10,500 Nos) CC Dismantling(Seg-2) in progress
Ballast layer compaction (300mm thick) / Ch 78137 finished Rebar fabrication of longitudinal sleepers(Ch 0-10) finished.
Sand bagging for load test in progress
CC Casting executed. Settlement Record in progress for 77th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress(500 sqm) Soling executed. Rebar fabrication executed (CH 1015-1040) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering & Rebar binding of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Regular Test (ILB/Cylinder) ILB production in progress (Quantity=10,500 Nos) CC Dismantling(Seg-2) in progress
Segment 1
Shingles Laying (180mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-10) in progress.
Pile shifting to bank in progress 50 m pipe welding completed (250mm dia) Brick masonry of wall in progress Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress FDD test executed at 300mm sand blanket
Wall casting / Port side/1st lift (CH 1015-1040) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Slab casting of 2nd portion executed Concrete pouring of Sheet Pile(01 Nos) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,400 Nos) CC Dismantling(Seg-2) in progress
RMG (Seg-1A)
Rolling of Shingles Layer (180mm thick) / Ch 78Shingles Laying (180mm thick) / Ch 78-137 finished 137 Rebar fabrication of longitudinal sleepers(Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-10) 10) in progress. in progress.
Pile shifting to bank. Leak test of 50m pipe (250mm dia) Brick masonry of wall Sand bagging for preloading work (2000 Nos) Surcharge material placement (50,000 cft) Pile shifting to bank in progress 50 m pipe welding completed (250mm dia) Brick masonry of wall in progress Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress PVD Driving in progress Wall casting / Navy side/2nd lift (CH 1015-1040) executed. Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=11,300 Nos) CC Dismantling(Seg-2) in progress
3 4 5 6
Sheet Pile Driving Water Supply Line Cable Trench (Seg-1A) Segment 1
Segment-2
Open Deep Drain Wall casting / Yard side/2nd lift (CH 1015-1040) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)
9 10 11 12 13 14
Rail Relocation Road Type-1 Sheet Pile Laboratory / Field Test Interlocking Block Dismantling work
Sub base material placement (2nd layer) Concrete pouring of Sheet Pile(01 Nos) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving Base Casting (CH 985-1015)
Wall casting / Yard side/2nd lift (CH 1015-1040) Pre-cast Bracing Casting (06 Nos)
10 11 12 13 14
Rail Relocation Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work
Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
2 3 4 5 6 7 8
RMG Track(Seg-1A) Seg-1A(mosque portion) Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2
Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving
10 11 12 13 14 15
Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work
Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
2 3 4 5 6 7 8
RMG Track(Seg-1A) Seg-1A(mosque portion) Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2
Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving
Wall casting 1st lift(CH 985-1015) Pre-cast Bracing Casting (06 Nos)
10 11 12 13 14 15
Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work
Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Rebar fabrication and Shuttering executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=13,600 Nos) CC Dismantling(Seg-2) in progress
Yard Drainage(Seg-1A)
Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Sand filling & Soling work Plaster work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing Soling & CC work (CH 1015-1030) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress Earth Excavation executed. Shuttering & Rebar fabrication executed. Pre-cast Bracing Casting (06 Nos) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Pre-cast Sleepers casting (10 Nos) in progress. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,250 Nos) CC Dismantling(Seg-2) in progress
10
Wall casting 1st lift(CH 985-1015) Pre-cast Bracing Casting (06 Nos)
11 12 13 14 15 16
Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work
Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) in progress. in progress. Sand filling & Soling work Plaster work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing
Segment-2
150mm local sand laying 200mm sand blanket laying Rebar fabrication of Base (CH 1015-1030)
10
Rebar fabrication of Wall 1st lift(CH 985-1015)/Navy Wall casting 1st lift(CH 985-1015)/Yard Side side. Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (05 Nos) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder)
11 12 13 14 15 16
Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work
Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
CC Dismantling(Seg-2) in progress
RMG Track(Seg-1A)
Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) in progress. in progress. Pre-cast sleepers shifting to Seg-1
3 4 5 6 7 8 9
Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1
Soling work Sub-base material laying Plaster work & Parapet shuttering
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing
Soling work in progress Bed preparation finished Plaster work & Parapet casting in progress.
Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress 200mm sand blanket laying in progress Base casting (CH 970-990) Wall casting 1st lift(CH 990-1015)/Navy Side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production (Quantity=11000 Nos) CC Dismantling(Seg-2) in progress
10
Segment-2
150mm local sand laying 200mm sand blanket laying Shuttering of wall (CH 1015-1030)
11
Open Deep Drain Back filling(CH 990-1015)/Navy side. Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)
12 13 14 15 16 17
Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work
Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
RMG Track(Seg-1A)
Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Pre-cast sleepers shifting to Seg-1 Pre-cast sleepers shifting to Seg-1 in progress Soling work finished. Sub-base material laying finished. Plaster work & Parapet shuttering.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket compaction finished. 200mm sand blanket laying in progress Earth excavation (CH 950-970) Back filling(CH 990-1015)/Navy side. Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) finished. Regular Test (ILB/Cylinder) ILB production (Quantity=12000 Nos) CC Dismantling(Seg-2) in progress
3 4 5 6 7 8
Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Cable Trench (Seg-1A) Segment-1
Rebar binding of raft foundation. Sub-base material compaction. Plaster work & Parapet casting.
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing
Segment-2
PVD Driving 200mm sand blanket laying Wall casting 2nd lift (CH 990-1015)/Navy Side
10
Open Deep Drain Soling & CC (CH 950-970)/Navy side. Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)
11 12 13 14 15 16
Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work
Pre-cast Sleepers casting (10 Nos) Field density test of sub-base. Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress. Pre-cast sleepers shifting to Seg-1 in progress Rebar binding of raft foundation in progress. Sub-base material laying finished. Plaster work & Parapet casting.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 200mm sand blanket laying in progress Wall casting 2nd lift (CH 990-1015)/Navy Side Soling (CH 950-970) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Trial Mix design (40 Mpa) ILB production (Quantity=11500 Nos) CC Dismantling(Seg-2) in progress
10
Open Deep Drain CC (CH 950-970) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)
11 12 13 14
Rebar fabrication of longitudinal sleepers(Ch 30Concrete Pouring (CH 0-10) 40) in progress. Rebar binding of raft foundation. Sub-base material laying Plaster work .
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing 200mm sand blanket laying Wall casting 1st lift (CH 970-990)/Yard Side
Rebar binding of raft foundation in progress. Sub-base material laying in progress Plaster work in progress
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 200mm sand blanket laying in progress Wall casting 1st lift (CH 970-990)/Navy Side Soling & CC (CH 950-970) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Regular Test (ILB/Cylinder) ILB production (Quantity=10500 Nos) CC Dismantling(Seg-2) in progress
10
Open Deep Drain Earth Excavation (CH 935-950) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)
11 12 13 14
Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Sub-base material laying & compaction Plaster work . Surcharge Removing
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) PVD Driving 200mm sand blanket laying Wall casting 2nd lift (CH 970-990)/Yard Side 200mm sand blanket laying in progress Wall casting 1st lift (CH 970-990)/Yard Side Earth Excavation (CH 935-950) In progress
Rebar binding of raft foundation in progress. Sub-base material laying & compaction in progress Plaster work in progress Surcharge Removing in progress.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (40,000cft)
11
12 13 14
Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Sub-base material compaction Plaster work . Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) PVD Driving 150mm local sand laying. Wall casting 2nd lift (CH 970-990)/Yard Side
Rebar binding of raft foundation in progress. Sub-base material laying finished. Plaster work in progress Surcharge Removing in progress.
Pile shifting to bank in progress Surcharge material placement in progress (35,000cft) PVD Driving in progress. 150mm local sand laying in progress. Wall casting 1st lift (CH 970-990)/Yard Side Earth Excavation (CH 935-950)
10 11 12
Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Lean concrete casting Bricks masonry work Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) 150mm local sand laying.
Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Base casting of 03 Nos Gully holes & wall casting of 01 No Manhole. Bricks masonry work FDD Test of 150mm local sand layer Rebar fabrication and shuttering executed. Bricks masonry work in progress.
2 3
Segment-2
Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) Wall casting 1st lift (CH 955-970)/Navy Side Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)
Rebar fabrication of longitudinal sleepers(Ch 3040) . Net cement finishing of Gully hole. Bricks masonry work
Bricks masonry work in progress. Bricks masonry work of Safety Tank in progress.
Sub-station Building Bricks masonry work of Safety Tank. Settlement plate fixing (08 Nos)
Segment-2
300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(70,000 cft)
Surcharge material placement in progress (35,000cft) Wall casting 1st lift (CH 955-970)/Yard Side Regular Test (ILB/Cylinder) ILB production (Quantity=14,500 Nos) CC Dismantling(Seg-2) in progress
Surcharge Removing
Surcharge material placement (50,000 cft) Sub-base work Wall casting 1st lift (CH 935-955)/Yard Side Regular Test (ILB/Cylinder) ILB production (Quantity=15000 Nos) CC Dismantling (Seg-2)
Rebar fabrication of longitudinal sleepers(Ch 3040) . Net cement finishing of Gully hole. Bricks masonry work
Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress. Net cement finishing of Gully hole in progress. Bricks masonry work in progress. Bricks masonry work of Safety Tank in progress.
Sub-station Building Bricks masonry work of Safety Tank. Settlement plate fixing (08 Nos)
Segment-2
300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(70,000 cft)
Surcharge material placement in progress (35,000cft) Sub-base work in progress Wall casting 1st lift (CH 935-955)/Yard Side Regular Test (ILB/Cylinder) ILB production (Quantity=12,500 Nos) CC Dismantling(Seg-2) in progress
Surcharge Removing
Surcharge material placement (50,000 cft) Sub-base work at Navy area (CH 620-820) Sub-base work Wall casting 2nd lift (CH 950-970)/Navy Side Regular Test (ILB/Cylinder) ILB production (Quantity=15000 Nos) CC Dismantling (Seg-2)
Rebar fabrication of longitudinal sleepers(Ch 3040) . Net cement finishing of Gully hole.
Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress. Base casting of 01 Nos Gully hole & 01 No Manhole Wall casting of 02 Nos Gully hole.
Yard Drainage
Bricks masonry work in progress. Bricks masonry work of Safety Tank in progress.
Sub-station Building Base casting of fuel tank. Sunshade Casting Sunshade Casting in progress. 300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (50,000cft) Rail fixing at Navy area (CH 620-820) finished. Improved Sub-grade & Sub-base work in progress. Wall casting 3rd lift (CH 925-950)/Navy Side
4 5 6 7 8 9 10 11 12
Segment-2 Segment-2A Segment-1 Rail Relocation Road Type-2 Open Deep Drain
Rebar fabrication of longitudinal sleepers(Ch 3040) . Net cement finishing of Gully hole.
Yard Drainage
Base CC Casting of 300 mm dia pipe (40rm) Bricks masonry work & Plastering of Wall. Rebar fabrication & Shuttering of slab of septic tank. Base casting of Fuel tank. Sunshade Casting
4 5 6 7 8 9 10 11 12 Segment-2 Segment-2A Segment-1 & 2 Rail Relocation Road Type-2 Open Deep Drain Bracing fixing (near sub-station) Laboratory / Field Test Interlocking Block Dismantling work Regular Test (ILB/Cylinder) ILB production (Quantity=15000 Nos) CC Dismantling (Seg-2)
Earth excavation & Levelling. Bricks masonry work & Plastering of Wall in progress. Bricks masonry work & Plastering completed.
Sub-station Building
Sunshade Casting in progress. 300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (60,000cft) Rail fixing at Navy area (CH 620-820) finished. Improved Sub-grade & Sub-base work in progress. Wall casting 3rd lift (CH 925-950)/Navy Side.
Pre-cast Sleepers casting (10 Nos) Side CC ,40rm(300mm dia pipe) Bricks masonry work & Plastering of Wall.
Pre-cast Sleepers casting (10 Nos) Base CC,40rm Bricks masonry work & Plastering of Wall in progress. Slab Casting of Septic tank Base casting of Fuel tank
Sub-station Building
Sunshade Casting
4 5 6 7 8 9 10 11 12 13 Segment-2 Segment-2A Segment-1 & 2 Rail Relocation Boundar Wall Road Type-2 Open Deep Drain Bracing fixing (near sub-station) Laboratory / Field Test Interlocking Block Dismantling work Regular Test (ILB/Cylinder) ILB production Navy gate.
Sunshade Casting in progress. 300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (60,000cft)
Improved Sub-grade & Sub-base work in progress. Wall casting 3rd lift (CH 950-970)/Navy Side
Pre-cast Sleepers casting (10 Nos) Side CC ,40rm(300mm dia pipe) Bricks masonry work & Plastering of Wall. Sunshade Casting
Pre-cast Sleepers casting in progress (10 Nos) Pipe fixing executed. Bricks masonry work & Plastering of Wall in progress. Sunshade Casting in progress. 300 mm sand blanket laying in progress. Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (70,000cft) Old line removal in progress. Bricks masonry work near sub-station in progress. Improved Sub-grade & Sub-base work in progress.
Sub-station Building
4 5 6 7 8 9 10 11 12 13
Segment-2 Segment-2A Segment-1 & 2 Rail Relocation Boundar Wall Road Type-2 Open Deep Drain
Regular Test (ILB/Cylinder) ILB production in progress.(10,000 Nos) Dismantling work at Navy gate in progress.
Yard Drainage
CC Castng of 2 Nos Gullyhole & 01 No Manhole. Bricks masonry work & Plastering . Sunshade Casting
4 5 6 7 8 9 10 11 12 13 Sub-base work (Seg-1A) Segment-2A Segment-1 & 2 Rail Relocation Boundar Wall Road Type-2 Open Deep Drain Bracing fixing (near sub-station) Laboratory / Field Test Interlocking Block Dismantling work FDD test of 300 mm sand blanket at Seg-2 ILB production Dismantling work at Navy gate. Regular Test (ILB/Cylinder) ILB production in progress.(10,000 Nos) Dismantling work at Navy gate in progress.
Sub-station Building
Bricks masonry work & Plastering in progress. Sunshade Casting in progress. Shingles laying (200mm) Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (70,000cft) Old line removal in progress. Bricks masonry work finished near sub-station . Improved Sub-grade & Sub-base work in progress. Wall casting 3rd lift (CH 990-1010)/Navy Side
Pre-cast Sleepers casting in progress (10 Nos) Side CC ,40rm(300mm dia pipe)
Yard Drainage
CC Castng of 2 Nos Gullyhole Bricks masonry work & Plastering . Sunshade Casting
4 5 6 7 8 9 10 11 12 13 14 15 Sub-base work (Seg-1A) Service Area Segment-2 Segment-2A Segment-1 & 2 Rail Relocation Boundar Wall Road Type-2 Open Deep Drain Bracing fixing (near sub-station) Laboratory / Field Test Interlocking Block Dismantling work Regular Test (ILB/Cylinder) ILB production Dismantling work at Navy gate. Regular Test (ILB/Cylinder) ILB production in progress.(11,000 Nos) Dismantling work at Navy gate in progress.
Sub-station Building
Bricks masonry work & Plastering in progress. Sunshade Casting in progress. Shingles laying (200mm)
Water spraying & Rolling Lean concrete casting(18 Mpa) PVD Driving Surcharge Removing
Surcharge material placement (70,000 cft) Old line removal Plastering of wall near sub-station Improved Sub-grade Shuttering work (CH 1010-1030)/Navy Side
Wall casting of 01 No Gully hole. CC Castng of 4 Nos Gullyhole Bricks masonry work & Plastering . Surcharge material placement (70,000 cft) Surcharge material placement PVD Driving
5 6 7 8 9 Sub-base work (Seg-1A) Service Area Seg-2A Road Type-1 Open Drain Work
2 3 4
Bricks masonry work & Plastering in progress. Surcharge material placement in progress (60,000cft) Surcharge material placement in progress. PVD Driving in progress.
RTG Track area Lean concrete casting(18 Mpa) Soil boring Sub-base work.
Soling,CC work (CH 1040-1050) Regular Test (ILB/Cylinder) ILB production
Bricks masonry work & Plastering . Concrete pouring (16 cum) Surcharge material placement (70,000 cft) Up lift test for driven pre-cast pile (Seg-1A) Surcharge material placement PVD Driving Sub-base work for RTG Track Lean concrete casting(18 Mpa) Soil boring for sample collection Sub-base work.
Bracing welding (near Navy gate.) Wall casting CH 920-940/3rd lift/Yard side Wall casting CH 940-950/1st lift/Navy side
Bricks masonry work & Plastering in progress. Rebar binding and shuttering executed. Surcharge material placement in progress (60,000cft)
Surcharge material placement in progress. PVD Driving in progress. Sub-base work for RTG Track in progress. Lean concrete casting(18 Mpa) in progress. Soil boring for sample collection in progress. Sub-base work in progress
Earth excavation executed.
Bricks masonry work & Plastering . Rebar binding & Shuttering. Sub-base work Settlement Record Surcharge material placement PVD Driving Soil boring for sample collection Existing Road excavation
Bracing Fixing (near Navy gate.) Wall casting CH 940-950/1st lift/Yard side
Bricks masonry work & Plastering in progress. Concrete pouring (16 cum) Sub-base work in progress Settlement Record in progress. Surcharge material placement in progress. PVD Driving in progress. Soil boring for sample collection in progress.
Earth excavation executed. Wall casting CH 920-940/3rd lift/Yard side Wall casting CH 940-950/1st lift/Navy side Regular Test (ILB/Cylinder) ILB production in progress.(12,400 Nos)
Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting. Segment-1 Segment-2 Road Type-1 Open Drain Work Settlement Record Surcharge material placement Sub-base work Bracing Fixing (near Navy gate.) Wall casting CH 900-920/2nd lift/Yard side Sub-grade Preparation Regular Test (ILB/Cylinder) ILB production Regular Test (ILB/Cylinder) ILB production in progress.(11,800 Nos) Settlement Record in progress. Surcharge material placement in progress. Sub-base work in progress Bracing Fixing (near Navy gate.) in progress Rebar fabrication & Shuttering executed.
Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting. Segment-1 Segment-2 Segment-4 Segment-3 Settlement Record Surcharge material placement 150mm local sand compaction Dismantling work Sub-base work Bracing Fixing (near Navy gate.) Wall casting CH 900-920/2nd lift/Yard side Sub-grade Preparation Regular Test (ILB/Cylinder) ILB production
10 Road Type-1 11 Open Drain Work 12 Truck Parking Area 13 Laboratory / Field Test 14 Interlocking Block
10 Road Type-1 11 Open Drain Work 12 Truck Parking Area 13 Laboratory / Field Test 14 Interlocking Block (02 Nos Plant)
10 Road Type-1 11 Open Drain Work 12 Boundary Wall 13 Laboratory / Field Test Interlocking Block (02 Nos 14 Plant)
Rebar binding & Shuttering of wall of Gully hole. Concrete Pouring of wall of Gully hole (02 Nos) Concrete Pouring (02 Nos span) Platering work Lime Tracing work of slab
Rebar binding & Shuttering executed. Platering work in progress. Lime Tracing work of slab in progress. Rebar binding & Shuttering in progress.
Service Area
Segment-2A 1 Yard Drainage Pipe laying & Side cc casting Base of Manhole(02 Nos). CC casting of Gullyhole(02 Nos) Segment-1 1 1 Surcharge Surcharge Surcharge material removing Surcharge material placement Surcharge material removing in progress. Surcharge material placement in progress. Segment-2 Pipe laying & Side cc casting in progress Rebar binding & Shuttering executed.
Navy Area 1 2 3 Surface drain work Cable Laying Main gate Brick masonry work Earth excavation Layout fixing & Earth excavation for column Brick masonry work in progress
Road Type-1 1 Base Course(300mm) Crushed stone laying. Crushed stone laying in progress.
Open Deep Drain Work 1 1 1 Chainage (920-930) Chainage (1-50) Interlocking Block Base casting Column shuttering & Casting Compressive strength test Rebar binding & Shuttering. Column shuttering & Casting in progress Boundary Wall Laboratory / Field Test
Sheet Pile Driving 1 2 Hammer Installation Site Clearance Hammer Installation at bank site Bank site clearing.
Rebar binding & Shuttering . Platering work Lime Tracing work of slab Rebar binding & Shuttering . Pipe laying & Side cc casting Base of Manhole(02 Nos). CC casting of Gullyhole(02 Nos) Surcharge material removing Surcharge material placement Existing pavement dismantling PVD Driving Brick masonry work Earth excavation Layout fixing & Earth excavation for column
Segment-1 1 Surcharge Segment-2 1 Surcharge Segment-3 1 Dismantling Segment-4 1 PVD Navy Area 1 Surface drain work 2 Cable Laying 3 1 1 1 1 Main gate Road Type-1
Surcharge material removing in progress. Surcharge material placement in progress. Existing pavement dismantling in progress. PVD Driving in progress. Brick masonry work in progress Earth excavation in progress.
Base Course(300mm) Crushed stone laying. Chainage (720-730) Chainage (1-50) Interlocking Block Earth excavation Column shuttering & Casting Compressive strength test
Open Deep Drain Work Boundary Wall Column shuttering & Casting in progress Laboratory / Field Test Sheet Pile Driving 1 Hammer Installation Hammer Installation at bank site 2 Site Clearance Bank site clearing. Interlocking Block Production 1 ILB production
Hammer Installation at bank site in progress. Bank site clearing in progress No production due to mechanical fault.
NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 29,2012 S.l. Description No.
Segment-1A 1 Yard Drainage 2 RMG Track 3 Sub-station Building 4 Service Area 5 Cable Trench work Segment-2A 1 Yard Drainage
Remarks
Rebar binding & Shuttering . Platering work Lime Tracing work of slab Rebar binding & Shuttering . Soling & Rebar binding. Pipe laying & Side CC casting Base Casting of Gullyhole(02 Nos).
Rebar binding & Shuttering in progress. Platering work in progress. Lime Tracing work of slab in progress. Rebar binding & Shuttering in progress. Soling & Rebar binding in progress. Pipe laying & Side CC casting in progress Rebar binding & Shuttering executed.
Segment-1 1 Surcharge Segment-2 1 Surcharge Segment-3 1 Dismantling Segment-4 1 PVD Navy Area 1 Surface drain work 2 Cable Laying 3 Main gate Road Type-1
Surcharge material removing Surcharge material placement Existing pavement dismantling PVD Driving Brick masonry work Earth excavation Layout fixing & Earth excavation for column
Surcharge material removing in progress. Surcharge material placement in progress. Existing pavement dismantling in progress. PVD Driving in progress. Brick masonry work in progress Earth excavation in progress.
1 Base Course(300mm) Crushed stone laying. Open Deep Drain Work 1 1 1 Chainage (720-730) Chainage (1-50) Interlocking Block Base casting. Column shuttering & Casting Compressive strength test Boundary Wall Laboratory / Field Test
Compressive strength test Hammer Installation at bank site in progress. Bank site cleaning in progress No production due to mechanical fault.
Sheet Pile Driving 1 Hammer Installation Hammer Installation at bank site 2 Site Cleaning Bank site cleaning. Interlocking Block Production 1 ILB production
NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 31,2012 S.l. Description No.
Segment-1A 1 Yard Drainage 2 RMG Track 3 Sub-station Building RTG Track 4 Service Area 5 Cable Trench work Segment-2A 1 Yard Drainage
Remarks
Segment-1 1 Surcharge Segment-2 1 Surcharge Segment-3 1 Dismantling Segment-4 1 200mm sand blanket Navy Area 1 Surface drain work 2 Cable Laying 3 1 1 1 1 Main gate Road Type-1
Surcharge material removing in progress. Surcharge material placement in progress. Existing pavement dismantling in progress.
Base Course(300mm) Crushed stone laying. Chainage (720-730) Chainage (1-50) Interlocking Block Wall casting. Column shuttering & Casting Compressive strength test
Open Deep Drain Work Boundary Wall Laboratory / Field Test Compressive strength test Hammer Installation at bank site in progress. Bank site cleaning in progress ILB production (11,860 Nos) Sheet Pile Driving 1 Hammer Installation Hammer Installation at bank site 2 Site Cleaning Bank site cleaning. Interlocking Block Production 1 ILB production