NCP 30 Assignment
NCP 30 Assignment
ASSIGNMENT
COURSE: PGPCM
MODULE: 13
ASSIGNMENT NO.: 09
SUBMITTED BY:
NICMAR
ASSIGNMENT
Your company has been awarded a prestigious contract of building 500m length presteressed
concrete bridge on national highway crossing the major river. Due to cultivation on both sides of
highway, very restricted space of only 100m in width and 300m in length is available on both sides
of highway.
To mobilize the site, your management has asked you to house 350T of cement, 300T of steel, 2
size II crawler- Tractor dozer, one mobile crane, one JCB, ten dumpers. Labour force of 100 men
Discuss your plan to organize the site, draw layout sketch showing all details. Wind direction is
1- INTRODUCTION:
The aim here is being Construction and Development of a National Highway across a river, where
restricted space has been made available on either side of the National Highway for mobilization.
Thus a thorough study of equipment requirement, manpower needed, etc. in order to plan them
Once the project goal was established, the construction project, which goes into three stages as
1) Pre-Construction Planning
2) Construction Stage
Formulation of Project
Pre-construction Planning stage is the most important stage in itself, since being the beginning of
the project. Keeping in mind any delay caused or any setbacks created at this stage, can bring
Thus taking full co-operation from our head office and from our CEO, an operation to prepare a
thorough “MASTER CONTROL NETWORK” was taken up as the first and foremost move.
After making a thorough study on the project with regards to parameter of the project,
methodology of construction, planning, time frame, cost aspect, quality norm and manpower
Based upon the management, technical functions and the facets of the construction work the
requirement of managerial and as well as other staff including supervisors can be finalized as
below:-
1) Project Manager: - He shall be the legal and the social head of the housing colony
project site and shall be responsible for making decisions, ceremonial functions, team
and controlling all the activities at project site that are necessary to complete the
project with in agreed time and cost schedule. He shall be the sole representative to
conduct all communication with the client or other external parties and shall be
to the concerned personnel in the work place and also represents the organizations on
comparable project.
A good leader capable of galvanizing the project team to achieve common goal.
A trouble shooter, should be able to pickup the problem areas for affecting solution.
Project scheduling and achieving the scheduled program to complete the project.
Monitoring performance on regular basis, and reporting to head office and top management.
Maintaining close liaison with the top management and transmitting their perception to the
project team.
Coordination and liaison with all agencies e.g. statutory bodies, Government, Owner,
Consultant, Public Bodies. He would create a positive image of the project, maintain good
communication and dispel fear or doubt, removing misconception about the project.
Management of project team and personnel. The organization should operate as a group, and not
Maintain financial propriety and observe professional norm, to depict picture of transparency
of the contract and shall be assisting the Project Manager in the preparation review
control of Contract Manager and one Deputy Manager including two Engineers and one
matters (Design and Drawing related) including setting out at site, preparation and
activities. He shall be assisted by one Civil Engineer (design), one junior architect and
coordinating the project works in order to complete the project as per agreed time and
the planned targets, actual progress achieved and the likely trends along with the
Any site is headed by a Planning manager, who works closely with the Project
Manager/ Engineer In Charge. His technical knowledge of the project, scheduling and
controlling techniques are important for the project success. He prepares and updates
the Master Control Network and sub –network. At major sites a computer should be
installed which would keep the network updated and take out resources and input
He should ensure that the site and the head office work in total co-ordination. Thus
5) Finance and Costing: - He shall be responsible for the internal accounting system
(cash flow, expenses etc.) and financial accounting (financial forecast, project budget
and cost controlling of the project) required for the project. He shall be assisted by one
A Finance Manager is an important part of the team. His function is not a controller of
accounts, but his job is to provide an important input to the project i.e. “Finance”. His
Follow-up payments etc., but he has to innovate and ensure that required cash flow is
prepared for the project. Many a times the finance representatives and engineers at a
project do not work in unison, when individual egos conflict with project priority. It is
necessary to avoid situation by proper team building and communication. The financial
resources of a project are limited, and largely have to be managed by generation from
the project itself. It is seen that, if a project manager keep finance Managers in the
picture of what is happening at the project, helps in the later getting a true perspective.
It also involves the Finance Manager into the project team to become proactive.
staff including supervisors (to be recruited on temporary basis with in the vicinity of the
project site) required for the project. He shall be assisted by one recruitment Officer and
2 Office Assistants.
A project has considerable activity related to manpower deployed. This is taken care by
the personnel Department. All record of employees, with respect to their pay, leave,
transfer, promotion, training etc. is kept here. Though the project was of limited
duration, but for the period of its operation record had to be maintained. At construction
site, certain social problems may also be encountered. Most sites are at far off and
inaccessible location, where employees would be staying with their families. The
project authorities must decide upon at the beginning of the project itself, whether a
short duration projects up to 2 years. It is better to treat the site as non-family station.
The employees in turn can be given 2 weeks off after one year to spend time with their
consider families above certain level to stay at site, in which case necessary provision
of residential accommodation, transport, school, medical facilities etc. at the project site
is necessary.
Various administrative functions of a project like keeping co-ordination with local and
statutory authorities, labor commissioner, public relation etc. is looked after under this
department.
materials hoisting plant, cranes) and minor construction equipments required during the
execution of the work. He shall be assisted by two Mechanical Engineers and four
foremen/supervisors.
8) Quality Manager: - He shall be responsible for the overall quality formulation and
A quality Control laboratory and testing facilities are set up at every major site. The
quality control Engineer will ensure that work is progressing with the quality norms. It
is a good practice to prepare a “Field Quality Assurance manual” at the very start of the
project. This document will detail all the requirement of quality test and checks, which
will be carried out at various stages as the project proceeds. The norm of quality should
be “Quality first time, every time”. A Field Quality Assurance Manual serves the
purpose of sensitizing all the project team including the client representative’s to the
project, where along with civil engineering other disciplines such as electrical,
communication etc. also come into operation, needs provision of equipment, machinery
and fixtures, which have laid down specification and quality norm to be followed. Such
9) Material Manager: - He shall be responsible for the timely supply and procurement
of the materials required during the construction work. He shall be assisted by a store
B) Field Staff:-
progress of work at site by carrying out of the construction activities in consultation with
effectively execute and monitor the various activities to complete the work with in agreed
As mentioned earlier the housing colony project is divided into two sub projects and further
to work centres so as to effectively manage and monitor the progress of work. The field
3- PROJECT COMMUNICATION
3.1 INTRODUCTION
The essence of our method of work was on emphasis on communication, particularly in the lateral
direction, among the teams and within the teams. In a way, communication was the key to
managing this gigantic project. To get the best from our team members, being the person In-charge
of the site, I spoke to them frequently on the goals and objectives of the organization, emphasizing
the importance of each member’s specific contribution towards realization of these goals. At the
same time, I tried to be receptive to every constructive idea emanating from any sub-ordinates and
the problems that existed and in identifying the action necessary to be taken to solve them.
Authentic communication was the tool used for managing the project.
Single most important managerial tactic in this successful program, is a pro-active follow-up.
Through the follow-up on the work done at different department, rapid progress has been achieved
“God can do tremendous things through the person who doesn’t care about who gets the credit.
The ego involvement must go. Before God trusts you with success, you have to prove yourself
……… Schullers
We learned the hard way that the biggest problem of the project management is to achieve a
regular and efficient interfacing between the different individuals (Team members at site) and
work centers i.e. the head office. Hard work can be set at naught in absence of proper co-
ordination. Close intervention with different work centers create such harmony, that the fine
threads of individual efforts were woven into a mighty fabric of great strength.
It was here that the actual site execution work would really take off. It is the activity through which
all plans are transferred into reality. The completion of project and realization of goal is achieved
As it is said,” Proof of Pudding is in eating it” therefore execution only can determine whether the
project is going on well or otherwise. In site management operation, actual execution is the
important theatre activity. The planning process, organization, agencies, material and equipment
It’s so truly said that emergencies and unforeseen problems might crop up. But they should not
upset or delay the normal activities planned for the day. Facing the pressure with commitment,
determination and positive approach, would certainly lead to success in achieving the goal.
Construction projects are best organized by tasks into task responsibility centers. They are best
managed by work packages and best planned and monitored by activities. Here This Project
organized successfully by linking & coordinating activities for successful completion of Project.
Also Formal organization structure has been Prepared Keeping in view “Lean & Thin ’’
Structuring.
During Structuring Authority has been also delegated as Assign Responsibility without Authority
is meaningless.
Other than above Effective communication have vital Role in Management Control
Communication for organization is like that As Blood is for Human Body. If blood
Flow stops, Human Body collapse .In today’s organizations Information must flow faster than
Very costly in terms of lost output. Here Effective communication is being used to integrate the
managerial Functions, to lead, direct, motivate, and create a climate in which people want to
The performance of any project can be evaluated from the daily reports and other correspondence
that it maintains. Well framed reporting systems serve as an effective tool of information, which if
compiled, documented and analyzed, provides a record on the project for 'future reference. The
management can adopt certain systems to control the progress of a project. The documentation
required, acts as an effective tool of control over the overall performance of every individual, from
the engineer, the site staff, consultants to the architect, involved in these systems. The procedure
for documentation of the in-house and outside correspondence, at different stages of work, is
standardized, In this chapter we discuss some of these procedures and the methods of
correspondence, that facilitate the working and help gain overall control over the staff and systems.
Formal communication
Communication flows in four directions: downwards, upwards, and horizontally and laterally. The
Project
Manager
Assignment on Site Organizations and management NCP 30 Page 13 of 37
National Institute of Construction Management and Research, Pune
School of Distance Education
Downward
Lateral
Engineering
QS Team
Team
Downward communication starts at the top and flows down through the project levels to
modified, or halted at each level as managers decide what should be passed down to employees.
Upward communication - When employees send a message to their superiors, they are using
Horizontal communication occurs between people on the same level of the hierarchy and is
designed to ensure or improve co-ordination of the work effort. It is formal communication, but
does not follow a chain of command. Effective horizontal communication should prevent tunnel
Lateral communication takes place between people at different levels of the hierarchy and is
Informal communication
Informal communication, commonly called ³the grapevine´, can begin with anyone in the
organization and can flow in any direction. The grapevines prime function is to disseminate
information to employees that is relevant to their needs. In the construction industry, the following
Regular contact
Mind reading
Motivation to speak
Correspondence from the site to Head Office is an important communication channel for the senior
management.-
The required frequency of reports and the correspondence from the site to Head office is directly
proportional.-
Daily correspondence-
Fortnightly correspondence-
Monthly correspondence
DAILY CORRESPONDENCE
This is the day to day reporting to the Head Office by the Project Engineer or site in-charge.-
The Project Engineer should leave the site, half an hour prior to the closing time for reporting to
If many sites are in progress, all site engineers, reporting to the Head Office, should note down the
The documents should be collected in their respective site trays at the H.O.
It is in a tabular format, indicating the actual work completed at the site on a particular day, the
quantity of cement bags consumed per building and the ratio of cement bags/sq.m.
D.P.R. of the previous day should be written and submitted immediately on the next day.
Work program of each building, for the next day, should be written separately.-
The arrival time of the contractor's labour and the departmental labour is note desperately.
Every D.P.R. must carry the name of the site, date and should be duly signed by the senior
The D.P.R. is a tool for the higher authorities / Chief Engineer to check the activities of the day.
This report deals with the opening and closing balance of cement, empty bags, lime, blocks etc.
It gives information of all the materials received and is attached with the challans from suppliers.
Supplier's name-
Challan number-
Date-
Site-
Time-
On every challan, the measurement of the truck, receiving time and the vehicle number must be
noted.-
The challan for the material received, should be stamped on the other side, along with the Project
Engineer's signature.-
It makes records of all material received. Material transferred from site to site can also be noted
It is the receipt for any material transferred from one site to the other. It notes down the quantity
along with the S.R.P. (Stock register page) No. and the M.T.R. No.
This slip is used by the site engineer/supervisor for issuing materials to the contractor /
The storekeeper must not issue any material without the material issue slip. The Engineer must
It helps control all work activities, since every material is issued by the engineer. Materials can be
utilized properly.
Material reconciliation for a particular work in a particular building can be done. Signature of
It notes the material issued to the contractor along with the date, particulars, quantity and the
building where it is used. It also gives details like who issued it, to whom and the S.R.P. No.-
This report should be kept at the site along with the original issue slip.-
This report records the details of labourers, directly appointed by the company as departmental
The Engineer should check the sites where these labourers work.-
The report gives self explanatory description of the work done by the departmental labourers along
with their designations. It should be signed by the site engineer and the Project Engineer.-
The report enables in the verification and preparing of the weekly cash bill of departmental labour.
Avoid issuing a memo to contractors. If at all it is to be written ensure that it is signed by the
Memo notes can be sent to contractors for deduction of payment from his bill, for reasons like non-
fulfilment of work as per the agreement, failure in maintaining the work schedule, wastage of
After the Chief Engineer signs the memo, a copy should go to the contractor and the other to the
WEEKLY CORRESPONDENCE
Cash bills should be submitted to the Head Office every week on pre-arranged day.
On account' money can be given to the site engineer depending on the expenses that might be
incurred during the coming week.- Cash voucher receipt (Refer Format No. 13.10) should be made
with complete narration and supporting documents. It should be forwarded to the Head Office on a
(3)INDENT (REQUISITION)
Indent is a printed format to raise demands for materials required at the site. It can be submitted
(4)PENDING INDENT
Pending indents are re-submitted when the material for indents submitted earlier has not been
received, nor has the information regarding their supply been received from the purchase
department.-
FORTNIGHTLY REPORTING
RA. Bills could be a labour bill for RC.C. Masonry, tiling, plumbing etc.-
Customer enquiry report should be submitted every 15 days to the sales department.
MONTHLY REPORTING
The site should send the following reports to the Head Office every month on a fixed day.
This statement records the total material consumption during a particular month and sent to the
IT gives an idea of the total receipt, previous balance, updated stock, consumption during the
This report records the opening balance every day, cement received, total stock, consumption per
day, transfer to any other site (+/-), closing stock and S.RP. No. It is submitted to the Head Office.
If the bills are more than expected, it might be due to wrong feeding of the meter reading. Have it
Approach the Electricity Board for getting the bill corrected according to the actual reading.
This report helps calculate the total consumption of water at the construction site for a given
month. Also the bills received from the Municipal Corporation can be cross checked.
These readings will help calculate the constant of water charges per sq.m/s.ft. Of built-up and for
future estimations.
Construction sites have construction machineries and instruments such as concrete mixer, lift,
Ongoing work at different sites can make very difficult to find out the conditions of machineries at
each site.-
These reports are to be sent to the maintenance division every month, along with details of the
machine, make/type, numbers, H.P., phase condition of the machines, causes for maintenance,
Excess material list indicates the material available at the site, not required for a certain period and
time.-
The report should be sent to the purchase department through the Chief Engineer, to cater to the
It records and helps calculate the work progress of each activity, for a particular building, as a
percentage.
The percentage derived, is based on the average calculation of the estimated expenses for each
activity.-
The quantum of the work completed during the month, for each site/ each building, can be justified
and total funds used can also be compared and justified using this chart.
Over and above this report, a monthly report should be prepared by the Chief Engineer and
It should contain the relevant information regarding the progress of project. Details of this report
are as follows
It should include details of all the work completed at the site, during that month.
The report should be submitted to the Director to inform him of the progress of work at the site
Apart from these reports, the site staff should send concrete cubes taken during concreting work to
Records should be maintained at site and a copy of cube testing report should be sent to Head
Site in-charge should leave the site half an hour prior to the closing hour for reporting to the C.E.
Apart from this, he should discuss the following aspects of the daily schedule -
Progress of work -
Rejection of materials-
Quality of materials-
NOTE
The site engineer should collect the required certificates/documents during the site visits of the
For any corrections after checking the working drawings with the RC.C. Drawings, the site in-
charge should directly contact the structural designer after informing the C.E.
Checking of reinforcement for O.H.W.T./ U.G.W.T. / septic tanks/other critical work Queries
Checking the strength and stability of a particular member of the structure after casting-
NOTE
: The site engineer should collect the required certificates/documents during the site visits of the
For installation of meter for construction purposes and shifting of meter while the work is in
progress-
NOTE
: The site engineer should collect the required certificates/documents during the site visits of the
The plumbing consultant should be contacted after receiving all the drawings,-
To show the sample collection of plumbing pipes, fittings and accessories.-To check and certify
water and drainage stacks, details using different testing methods like pressure testing, smoke
testing etc.-
To get the corrections done if any changes occur due to extra amenity/practical difficulties.-To
check the water supply grid development work, drainage line development work and storm water
drainage work.-
To collect actual measurements on site for preparing record drawings.-For all queries confirmation
The site in-charge should discuss and enter all the points in the memo book/letter. A copy should
Progress of work
Quality of work
Program of work
Preparation of RA bills
Work out material requirement at various stages and estimates for the same-
Site cleaning.
Misbehaviour of labourers
This includes all documents received from the Head Office to the site-
Circulars-
Minutes of meeting-
Agreements-
Specifications-
Queries regarding bills, quality report, challans etc. from the account department
This is includes discussions between the subcontractors and the management for--
Work speed-
Balance work.-
Quality of work.-
Site meetings.-
Payment status-
Issue of cheques-
Control of wastage-
Mistakes at site-
Work program-
Legal formalities-
4- LAYOUT PLAN
Good site layout is important to improve productivity. You need to arrange your construction site
in such a way as to make it function as efficiently as possible. With bad layout, time and materials
are wasted through double handling. Transport and handling of materials always cost money.
Every time you more a stack of bricks around your site, the real cost to you increases. One of the
reasons for slow progress and high cost of construction projects is the lack of site planning,
The layout plan of the site will depend upon two main factors: the methods and sequence of
operations to be employed in carrying out he work, and the space available. The methods and
sequence will have been considered at the time that the estimate and tender were prepared. When
the contract is awarded, you should take another careful look at these ideas before preparing a
detailed site layout plan. These plans must be prepared in advance and they must be prepared by
someone with good planning skills and experience. It is often easier to save money through
planning than by raising site productivity, but these savings can only be obtained if you take
enough time to think about all the possible alternatives before deciding on how to layout the site.
Contract documents:
The contract document for the proposed project is voluminous and contains the following
documents:
f) Tender drawings.
i) Performance guarantee.
While the provisions existing in various clauses of the different sections of the document have
their own independent intent, meaning and interpretation, a proper management of the contract is
set up for interpretation of individual clauses in harmony with others, so that it is in the interest of
efficient and timely execution of work. This is applicable both to the client and the contractor. For
the proposed work, work below ground is allotted as cost plus percentage rate and for work above
ground it is allotted as item rate contract. It is also assumed that the contract drawn up is fair and
equitable and takes into account requirements of client and possible difficulties that may be
5- SITE CLEARANCE
Before setting up of enabling works, it is necessary to make the site clear from various aspects
such as: -Any stockpile of irrelevant material laid on site. Any machinery, equipment or vehicle
not related to proposed site work. Plant, vegetation or crops of reasonable height in the proposed
site area. Depending upon the direction of wind mentioned, provision of temporary unit such as
barrier is made on the west side of the bridge to avoid accumulation of unnecessary dust & rubbish
materials. Removal of small pebbles, sharp edge stones, loose soil material from the surface of site
The following infrastructure facilities should be constructed for the proposed bridge site:
1) Temporary roads should be leveled and a sufficient base course should be provided to
2) Regular power supply should be made available from the grid passing nearby Or
electric power will have to be generated by installing diesel-penetrating sets at the site.
3) Water supply can be arranged by providing underground storage tank and distribution
through a pumping system and overhead tank. For sewage disposal, septic tank should
Site camps are erected on site for resident engineers & persons working onsite. These
are in the form of light steel or wooden structure, which are mounted on skid beams or
wheels, so that they can be moved as and when required. These are provided with
electrical, plumbing and sanitary fixture, and the system becomes operational at site by
plugging into the electrical and water supply. The site is also provided with the latest
possible communication technology, such as cellular phone, Internet, intranet, wan etc.
ORGANIZING UTILITIES
All the utilities and resources available on the proposed bridge should be organized properly so as
to avail the maximum benefit. Storeroom containing ‘A’ class items should be provided by a
watchman’s cabin adjacent to it. Steel should stacked in open yard, protected by fencing. The
utility yard should be attached to the steel yard by a common fencing. Aggregates should be
stacked as near as possible to the batching plant or concrete mix, so as to avoid unnecessary
movement and double handling of material. Camp for persons working on site should be located
on one side of the site for avoiding dust and noise, generated on site. Store rooms:- Store rooms
should be constructed in a place where access for unloading of materials is easier, which leads to
safety of the work forces. Toilets, latrines should be constructed downwind with proper slope for
drainage.
Specialist shops like steel bender, carpenter, and block makers should be located/constructed near
SECURITY
The proposed bridge site should be secured against possible thefts and damage causing loss to the
governing authority. It should be secured for: Loss of material, mobile machinery or equipment, at
night times or at times when work is not in progress. 2 nos. of watchmen, each working for a 12-
hour shift will serve for this purpose. Confidential information prevailing outside the organization:
This can be prevented by storing the confidential data in systems and records, approachable only to
the top management with the M.D. keeping the password key. The entire document, paperwork
related to site work should be properly stored in cupboards under the jurisdiction of a reliable
accountant/clerk, acting as a common person to all the concerned departments. All the persons
working on site should be well secured against thefts, robbery, political influence & undue
pressure of higher authorities. Also the personnel working on site should be secured against any
sort of mishap or accident, likely to occur due to negligence of safety conditions. Reconciliation of
materials: A daily checkups should be done on site especially for the stores, from the Storekeeper.
There are three ways to find out how much money the company is losing because of damage and
deterioration of materials.
a) Looking carefully around the site and checking through the site, usually shows example of poor
b) Comparing figures given in orders, receipts and issues, and checking of remaining stocks.
6- MOBILIZATION:
Departmental Staff: -
a) Before mobilizing staff members like engineers, supervisors and workmen, it is necessary
to construct and prepare proper accommodation such as residential quarters & workmen’s
b) Security check post should be fixed at gates, with guiding instructions to the security
c) Departmental site office shall be erected at proper location i.e. free from any noise, dust,
easily accessible from all directions of site. Also the location should not obstruct movement
d) The departmental staff should be mobilized at least 3 days prior to commencement of work
& a mandatory visit of the complete site should be arranged for the entire department
(technical & non- technical) so as to get acquainted with the site area for convenience in
working.
e) The departmental staff shall be informed well in advance about the mobilization date by a
formal notice, and on that particular date, the entire staff shall be mobilized by means of
conveyance arranged. i.e. Bus, for people residing in the range of 100 km. & trains for
Contractors:
a) Contractors should be informed with a formal notice, after the allotment of work (i.e.
Contract) for mobilization of their staff, machineries & other required resources.
b) It is the duty of contractor to get himself & his resources mobilized well in advance before
the initiation of work i.e. before the actual execution of work starts i.e. around a week
c) After mobilizing on site physically, he should impart instruction & guidelines to his staff &
sub contractors about the proposed work & thereby the work line of action. He should also,
make his staff well acquainted with the site area & arrange his machinery in consultation
with the client’s engineer so as to avoid unnecessary wastage of time & materials.
SUBCONTRACTORS:
a) For the proposed work, the contractor has appointed subcontractors related to various
stages of work such as: Labours for pre-stressing work.. Labour for casting work. Labour
according to his planned mobilization so as to get himself & the sub-contractors ensured
about the adequacy of resources &information required for the execution of work.
c) In case of any requirement from the contractor’s side, the subcontractor should intimate
him, well before the work starts so that the contractor will arrange for it or arrange for a
suitable alternative, after consulting with the clients engineer. Mobilisation also includes
Enabling works
Under works of this category, structures and appurtenants which facilitate undertaking the actual
project work are included. In the Master Control Network and planning for the project details of
enabling work would be included. The extent of enabling work would vary depending the size and
nature of the project. On a large project costing a few hundred cores, the enabling work itself could
form into a mini- project. The enabling works would include the following items
a) Fencing/boundary wall around the project, fixing security check post and gates.
b) Site Office
f) Static plant such as concrete batching plant, pre-cast concrete element plant, block making
g) Mobile plant such as Trucks, Dumper, Bulldozer Grader, Vibratory and pneumatic Road
Roller, Bitumen sprayer Transit mixer, Concrete Pump, Crane, front end loader,
compressor. These Plant and Equipment are mobile, and can be shifted from place to place
on regular basis.
Storage areas should be located near to the static plants. For storage of 350 tons of cement,
stacking yards should be covered with shed. But here as the cement is to be used in large quantity
for concreting by batching plant and pre-stressed element plant, so it is stored in bulk in vertical
silos. Also 300 tons of steel is to be stored which can be stored in open yards with proper fencing
and near to bar bender’s workshop. Care should be taken that water does not get accumulated in
this yard and there is proper slope to drain the rain water. Stone metal and sand can be stored in
open yards, stacked in heaps with proper fencing so that the material does not get mix up with the
outer material. The suppliers in the vicinity of Delhi should be invited on site by a formal notice
and a meeting should be held up with the consultation of clients engineer and contractor,
a. Quantity of material.
b. Quality of material.
d. Mode of transportation.
The suppliers should make the above factors clear in a formal quotation and submit it to the
organization. The department will further scrutinize the quotations of various suppliers and allot
Workshop
For the maintenance of plant and equipment both static and mobile, it is necessary to have a
workshop which will undertake the maintenance, repair, overhauling and major replacement of
equipment. Workshop is geared up to; carry out preventive and scheduled maintenance which is
essential to keep the break-down of equipment to bare minimum. The workshop should have
facilities for servicing, carrying outgeneral repair, engine over-haul, calibration of Diesel Pump
etc. Workshop should have a small machine shop attached with lathes, drilling machine, welding,
boring machine, painting, denting, sheet metal work etc. It is also to be equipped with auto-
QUARRY:
For the proposed bridge site near Panvel certain queries are searched and found for arranging
a) At a distance of 10 kms. from the site, strata below the ground i.e. around 3m below
crushers.
b) Also at a distance of 25 kms. from the site, along the coastal side, natural sand is available
If transportation cost is affordable, then in between Lonavla & Khopoli, abundant of hard rock,
boulder & stones are available, which can be used at various construction stages of pre-stressed
concrete bridge.
In the project site, sufficient covered stores or open storage is necessary for maintaining the
material in good condition. Cement is usually supplied in bags, which is stored at the site in
covered shed. The sheds are constructed with brick wall, IPS floor, tubular structure trusses,
roofing with sheets. Bags not exceeding 10 are stacked one over another. If more than 10 bags are
stacked, then the lower bags tend to set, making cement non-usable. In case cement is used in large
quantities for concreting by the batching plant, and pre-cast element plant, is stored in bulk in
vertical silos. The silos are filled up by a pneumatic pump fixed on the cement bulk carrier. From
the silo cement is conveyed into the mixer of the batching plant and pre-cast element plant,
Services
The site camp is to be provided with services like electric supply, sewage disposal,
communication, telephone. In case regular power supply is available from the grid, it can be
tapped and necessary substation with transformer installed at site. If grid power is not available
then, it may be necessary to generate own power by installing diesel generators at the site. Water
supply can similarly be tapped, if water lines are passing nearby in the vicinity, by providing
underground storage tank and distribution through a pumping system and over head tank. In case
water mains are not available, tube well could be bored for water. Necessary treatment of water to
make it safe for intended consumption will have to be carried out. For sewage disposal, since the
camp is only for a temporary duration septic tank, could be provided. If it is a large site, and
enough land is available, then it may be possible to provide an oxidation pond for sewage disposal.
The effluent from the pond could be used for horticultural purposes of the site.
In order to carry out the enabling work which is required at the very initial stage of the project
itself, it may be desirable for the organization, to set up a 'crack team' which can go in advance to
the site and build up all the temporary structures, services required for the enabling works. This
will cut down the time required by the main project team, on their arrival at the site, and they could
embark upon straight-away on execution of the main project. Such a 'crack team' can move from
project to project for the organization, and they would be well trained in carrying out this activity.
On the other hand, if project team assigned with the main work, is to first build up the enabling
works, a lot of time is lost for the project. On most international project, and on some major
projects within country, of structure being adopted for the site camp is of portable nature. These
are in the form of light steel or wooden structure, which are mounted on skid beams or wheels, and
can be moved to the camp site, at a very short notice. The Port cabins are provided with electrical,
plumbing and sanitary fixture, and the system becomes operational at site by plugging into the
electrical and water supply. Through the initial cost of the system may be more but over a period
of time it would become economically viable since the structure can be shifted to site, whereas, if
the camp is built with conventional materials. Like steel, concrete, the cost would be higher in the
longer run, besides the extra time required to build the Camp.
TRANSPORTATION:
This Construction Traffic and Transportation Plan has been prepared to describe how our
organization will safely and effectively control, maintain and minimize impacts from the bridge
This plan has also been developed to satisfy all the mitigation measures set forth by Local
A Traffic Management Plan shall be prepared for the site access roads to ensure that no hazards
would result from the increased truck traffic and that traffic flow would not be adversely impacted.
Under this plan, informational signs would be used to inform the public of temporary traffic
hazards, flaggers would be employed when equipment would block throughways, and traffic cones
would be used to identify any temporary changes in lane configuration necessary to minimize
traffic impacts. This plan would be submitted to the Local administration- traffic control board and
**********XXXXXXXX*********