Cable Pulling Report (Instrument Cable) : Project Name Customer

This document contains a cable pulling report for the Oyong Development Project Phase II Onshore Processing Facilities. It lists 4 instrument cables that were pulled on April 14, 2009, including their cable numbers, type/size, start and end points, and actual lengths. It also lists 3 additional cables that were pulled on April 15, 2009. The report provides details of the cable pulling work performed and includes signatures for those who performed, witnessed, and approved the work.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
186 views

Cable Pulling Report (Instrument Cable) : Project Name Customer

This document contains a cable pulling report for the Oyong Development Project Phase II Onshore Processing Facilities. It lists 4 instrument cables that were pulled on April 14, 2009, including their cable numbers, type/size, start and end points, and actual lengths. It also lists 3 additional cables that were pulled on April 15, 2009. The report provides details of the cable pulling work performed and includes signatures for those who performed, witnessed, and approved the work.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 3

INSTRUMENT MECHANICAL COMPLETION CHECK SHEETS

SANTOS (SAMPANG ) PTY LTD

CABLE PULLING REPORT (INSTRUMENT CABLE)


Oyong Development Project Phase II Onshore Processing Facilities (OPF) GRATI SANTOS (Sampang) Pty. Ltd. 9820-70-121 N/A E/I Building System / Sub System No. System Description Sub System Description
PULLING DATE DESCRIPTION CABLE TYPE/SIZE FROM TO ACTUAL LENGTH

PT. PAL INDONESIA

Project Name Customer


Drawing No. / Rev Single Line No. / Rev Location / Area

: :
: : :

E04BMC : : :

No

EQUIPMENT

CABLE NUMBER

RESULT

REMARK

1 2 3 4

9820-AJB/DJB-004 9820-AJB/DJB-006 9820-AJB/DJB-009 9820-AJB/DJB-280

9820-DJB-004-ESD-102 9820-DJB-006-ESD-102 9820-DJB-009-ESD-102 9820-DJB-280-102

14/04/09 14/04/09 14/04/09 14/04/09

19/C#14 AWG 19/C#14 AWG 19/C#14 AWG 19/C#14 AWG

9820-AJB/DJB-004 9820-AJB/DJB-006 9820-AJB/DJB-009 9820-AJB/DJB-280

9820-MC-103 9820-MC-103 9820-MC-103 9820-MC-103

265 m 321 m 275 m 267 m

Notes :

Description Company

Performed by IBP

Witnessed / Approved by PT. PAL

Witnessed / Approved by SANTOS

Signature

Print Name Date

INSTRUMENT MECHANICAL COMPLETION CHECK SHEETS

SANTOS (SAMPANG ) PTY LTD

CABLE PULLING REPORT (INSTRUMENT CABLE)


Oyong Development Project Phase II Onshore Processing Facilities (OPF) GRATI SANTOS (Sampang) Pty. Ltd. System / Sub System No. 9820-70-401 : N/A E/I Building System Description : Sub System Description :
PULLING DATE DESCRIPTION CABLE TYPE/SIZE FROM TO ACTUAL LENGTH

PT. PAL INDONESIA


E04BMC

Project Name Customer


Drawing No. / Rev Single Line No. / Rev Location / Area

: :
: : :

No

EQUIPMENT

CABLE NUMBER

RESULT

REMARK

1 2 3

9820-AJB/DJB-004 9820-AJB/DJB-006 9820-AJB/DJB-009

9820-DJB-010-ESD-102 9820-DJB-9081-UCP-9080 9820-LCP-232-2-101

15/04/09 15/04/09 15/04/09

19/C#14 AWG 19/C#14 AWG 24/PR#18 AWG

9820-AJB/DJB-010 9820-AJB/DJB-9081 9820-LCP-232

9820-MC-103 9820-UCP-9080 9820-MC-101/102

199 m 245 m 355 m

Notes :

Description Company Signature Print Name Date

Performed by IBP

Witnessed / Approved by PT. PAL

Witnessed / Approved by SANTOS

19/C#14AWG; , DJB-9085-R-UCP-9080=245M