Generator OS43024
Generator OS43024
Lifting-device shall only be used when lifting the cooler housing. Cooler housing Max 90
o
3) 5)
2)
1)
Alternative 1
D=30, Ellipsed
Working procedure of assembly and disassembly of cooler top: 1. Loosen and remove the bolts holding the flat protection plate on top of the machine and lift it off. 2. Observe the rubber hoses attached to the stator end plates. Loosen them, but do not drop them into the machine. 3. Place the cooler housing with coolers on top of the machine with a gap 10-20cm between the cooler housing and machine. 4. Connect the rubber hoses, for leakage water, to the connections on the cooler drainers and tighten the hose clamps. 5. Lower the cooler housing on to the machine and tighten the bolts holding it to the side panels. Be careful NOT to drop any bolts or nuts into the machine. Re-assembly the cooler top in the reverse order as describe.
Prod. class:
Part no.
No. of p.
3
Page
Doc. no.
3BSM001483-A
; SAVEDATE: 2008-03-13 14:16
en
Max 90
Alternative 2
Working procedure of assembly and disassembly of cooler top: 1. Loosen and remove the bolts holding the flat protection plate on top of the machine and lift it off. 2. Lower the cooler housing on to the machine and tighten the bolts holding it to the side panels. Be careful NOT to drop any bolts or nuts into the machine. 3. Connect the leak water detector by insert the adapter with the sensor into the union. Re-assembly the cooler top in the reverse order as describe.
Doc. no.
Lang.
Rev. ind.
Page
3BSM001483-A
en
REVISION Rev. ind. Page (P) Chapt. (C) Description Date Dept./Init.
Doc. no.
Lang.
Rev. ind.
Page
3BSM001483-A
en
6\QFKURQRXV PDFKLQH
Dismantling and assembly of PMG-stator
Document No.: 3BSM 005438
Contents
6DIHW\
1.1 General safety instructions ............................................ 3
6\QFKURQRXV PDFKLQH
127,&( The information in this document is subject to change without notice and should not be construed as a commitment by ABB. ABB assumes no responsibility for any errors that may appear in this document. In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or hardware described in this document. This document and parts thereof must not be reproduced or copied without ABBs written permission, and the contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM 005438
ii
6DIHW\
3BSM 005438
Remove the bolts on the rear end cover and take away the cover. See Figure 2-1 on page 4.
)LJXUH
3BSM 005438
Remove the cable from the earth fault brush holder and disconnect the cable from the cable clamps of the sheet metal housing for PMG stator. See Figure 2-2 on page 5.
)LJXUH
Remove the brushes and the brush holder in accordance with Figure 2-3 on page 5.
)LJXUH
3BSM 005438
Loosen the bolts and remove both halves of the PMG protective cover plates. See Figure 2-4 on page 6.
)LJXUH
Remove the cover drum after removing the bolts. Be careful not to damage the slip ring for rotor earth fault protection. See Figure 2-5 on page 6.
)LJXUH
3BSM 005438
Remove the PMG stator cables from the terminal block. See Figure 2-6 on page 7.
)LJXUH
Place a sheet of stiff paper or plastic in the air gap around the rotor as shown in Figure 2-7 on page 7.
)LJXUH
3BSM 005438
Attach a lifting chain to the PMG stator housing and remove the bolts. See Figure 2-8 on page 8.
)LJXUH
3BSM 005438
Lift away the PMG housing carefully with the crane. See Figure 2-9 on page 9.
)LJXUH
3BSM 005438
Now you are ready for changing diodes or thyristor according to section Dismantling and assembly of diodes and thyristor. See Figure 2-10 on page 10
)LJXUH
3BSM 005438
10
Before assembling the stator, make a simple protection sleeve of stiff paper or plastic and tape the ends together. See Figure 2-11 on page 11.
)LJXUH
3BSM 005438
11
Check that the wires from the PMG stator are correctly strapped to the bracket as shown in Figure 2-12 on page 12.
)LJXUH
3BSM 005438
12
)LJXUH Be sure that the guide pins fit into the holes in the exciter stator housing.
While the stator is suspended, put all the bolts in place including flat washers and start tightening them very lightly. The air gap between rotor and stator is approx. 1.75 mm.
3BSM 005438
13
After tightening the bolts, place feeler gauges between stator and rotor with the desired thickness at 9 oclock, 3 oclock and 12 oclock position to check that the air gap is still correct. See Figure 2-14 on page 14.
)LJXUH
Remove the feeler gauges. Check the air gap with a feeler gauge in a final check around the periphery. The air gap (tolerance) must not exceed 0.2 mm. ,I WKH WROHUDQFH EHWZHHQ DQG RFORFN RU EHWZHHQ DQG RFORFN H[FHHGV PP WKH EROWV PXVW EH ORRVHQHG DQG FDUHIXOO\ UHWLJKWHQHG 7KH SHULSKHU\ PXVW EH UHFKHFNHG ZLWK IHHOHU JDXJHV XQWLO WKH UHTXLUHG WROHUDQFH LV REWDLQHG $IWHU WKH WROHUDQFH LV UHDFKHG UHGULOO WKH JXLGH SLQ KROHV DQG LQVHUW WKH UROO SLQV Connect the wires from the PMG stator to the terminal as shown in Section 2.1 Figure 2-6 on page 7.
3BSM 005438
14
Take one half of the protective cover plate and slide it behind the brush holder mounting bracket. Insert a bolt loosely. Take the other half and place it on top. Attach two bolts to assemble the two halves. Insert all the other bolts on the periphery. Tighten these carefully with a pinch bar while checking visually that the white plastic ring does not touch the rotating shaft extension (sleeve). See Figure 2-15 on page 15.
)LJXUH
Adjust the two brush arms so that the angle between the inserted brush and the centre line of the rotor is 90 degree. See Figure 2-16 on page 15 and Figure 2-17 on page 16.
)LJXUH
3BSM 005438
15
90o
)LJXUH Insert the brushes and connect the leads to the brass plate below. Connect the cable from box GL. Replace the rear end cover and tighten all bolts.
3BSM 005438
16
0 22.5 16.6
0 45 33
0 79 58
0 190 140
0 420 300
0 735 550
0 1500 1100
3BSM 005438
17
3BSM 005438
2003-01-15
6\QFKURQRXV PDFKLQH
Dismantling and assembly of exciter stator
Document No.:3BSM 005439
Contents
6DIHW\ 1.1 General safety instructions .........................3 5HPRYDO DQG DVVHPEO\ RI WKH H[FLWHU VWDWRU 2.1 Removal of the exciter stator......................4 2.2 Assembly of exciter stator ........................10 2.3 Recommended tightening torque for bolts11
6\QFKURQRXV PDFKLQH
127,&( The information in this document is subject to change without notice and should not be construed as a commitment by ABB. ABB assumes no responsibility for any errors that may appear in this document. In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or hardware described in this document. This document and parts thereof must not be reproduced or copied without ABBs written permission, and the contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM 005439
-ii
6DIHW\
3BSM 005439
Remove all external cables from the junction boxes on the exciter stator housing. Remove the upper clamping bar of the cooling duct and those on the sides. See Figure 2-1 on page 4.
)LJXUH
3BSM 005439
Remove the screws of the inner cover plates between the stator housing plates and the exciter stator with a pneumatic power tool. See Figure 2-2 on page 5.
)LJXUH
Remove the guide pins (one on each side) from the mounting flanges as shown in Figure 2-3 on page 5 and Figure 2-4 on page 6.
)LJXUH
3BSM 005439
)LJXUH
Remove the four M16 hex. head socket cap screws, (two on each side) with the socket wrench using a pipe extension. See Figure 2-5 on page 6.
)LJXUH
3BSM 005439, Rev. B EN -
3BSM 005439
Place a pipe or steel rod through the lifting eyes, attach a lifting strap between the welded lifting eyes and the iron rod or pipe as shown, and carefully try to lift the unit. See Figure 2-6 on page 7.
)LJXUH
3BSM 005439
Check the centre of gravity and adjust the straps, test carefully until the unit can be lifted straight up without tipping to the rear or to the front. See Figure 2-7 on page 8.
)LJXUH
Having lifted the unit, slide the unit axially away from the generator and put it on two wooden blocks. See Figure 2-8 on page 8 and Figure 2-9 on page 9.
)LJXUH
3BSM 005439
)LJXUH
Each set of brass shims must be held together, marked and stored so that they are returned to the same side when reassembling the stator housing.
3BSM 005439
3BSM 005439
10
0 22.5 16.6
0 45 33
0 79 58
0 190 140
0 420 300
0 735 550
0 1500 1100
3BSM 005439
11
3BSM 005439
2003-01-15
6\QFKURQRXV PDFKLQH
Dismantling and assembly of bearings
Document No.: 3BSM 005446
Contents
6DIHW\ 1.1 General safety instructions .........................3 'LVPDQWOLQJ DQG DVVHPEO\ RI EHDULQJV 2.1 Dismantling of bearings..............................4 2.2 Change of bearing liner ............................15 2.3 Assembly of bearings ...............................21 2.4 Recommended tightening torque for bolts .....................................................30
6\QFKURQRXV PDFKLQH
127,&( The information in this document is subject to change without notice and should not be construed as a commitment by ABB. ABB assumes no responsibility for any errors that may appear in this document. In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any nature or kind arising from the use of this document, nor shall ABB be liable for incidental or consequential damages arising from use of any software or hardware described in this document. This document and parts thereof must not be reproduced or copied without ABBs written permission, and the contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM 005446
ii
6DIHW\
3BSM 005446
Before starting the dismantling of the bearing, rotate the rotor so that the poles are at 90 degrees to the vertical. Loosen all cables from the cable brackets. Remove the tubes from the air-lock seal, see Figure 2-1 on page 4. Loosen the cable from the vibration detector and remove the vibration probes. If lower half of the bearing shell will be removed from the bearing housing, the temperature probes has to be dismantled from the bearing housing. See Figure 2-2 on page 5 7KH WHPSHUDWXUH SUREH LV D SDUW RI ERWK WKH EHDULQJ VKHOO DQG WKH EHDULQJ KRXVLQJ DQG KDV WR EH UHPRYHG LI WKH EHDULQJ VKHOO ZLOO EH PRYHG IURP LWV SRVLWLRQ.
)LJXUH
3BSM 005446, Rev. B EN -
3BSM 005446
Temperature probe
)LJXUH
Bearing housing
Bearing shell
Disconnect the tubes between the run-out tanks and the upper halves of the bearing. Disconnect the level-indicators on the run-out tanks. Remove the cooler top and the sheet metal end covers around the bearing and the part including the run-out tank if such exist. Remove even the cooling duct for the exciter at the ND-end if both bearings are to be inspected or repaired. Remove the bolts of the upper half of the air-lock seal which attach the air-lock seal to the bearing housing before attempting to dismantling of the bearing. Refer to Figure 2-3 on page 5.
)LJXUH
(The air-lock seal prevents the rotor from sucking in oil along the shaft. The seal provides an air-lock at atmospheric pressure).
3BSM 005446
To be sure not to destroy the air-lock seal, remove the upper half by removing two bolts. See Figure 2-4 on page 6.
)LJXUH
Loosen and remove the eight M24 hex. head socket bolts in the upper half of the bearing housing. See Figure 2-5 on page 6.
)LJXUH
3BSM 005446, Rev. B EN -
3BSM 005446
Insert a lifting eye and carefully lift the upper half away from the lower half. See Figure 2-6 on page 7.
)LJXUH
3BSM 005446
Remove the bolts from the upper half of the bearing shell. See Figure 2-7 on page 8.
)LJXUH
To separate the bearing shell, use the bolt in Figure 2-8 on page 8 and Figure 2-9 on page 9.
)LJXUH
3BSM 005446
This bolt is for used to separate the two halves of the bearing shell.
)LJXUH Insert a lifting eye and lift away the upper bearing shell. See Figure 2-10 on page 9.
)LJXUH
3BSM 005446
Remove the springs on each bearing seal and remove the bearing seal. See Figure 2-11 on page 10.
)LJXUH
Loosen the jacking-oil connections to the bearing shell by removing the two bolts on the connections. See Figure 2-12 on page 10.
)LJXUH
3BSM 005446, Rev. B EN -
3BSM 005446
10
)LJXUH
3BSM 005446
11
Place a magnetic foot with a dial indicator so that the indicator can measure a vertical movement (lift) of the rotor as shown in Figure 2-14 on page 12. Place a hydraulic jack (30 ton lifting capacity) underneath the rotor shaft as shown and lift the rotor 0.3-0.4 mm.
)LJXUH
3BSM 005446
12
Place two distance elements in the air gap between the rotor poles and the stator. Attach 2 lifting eyes into the lower half of the bearing shell as shown in Figure 2-15 on page 13 and draw the assembly toward you so that it slides around the journal, with use of a hand-ratchet.
)LJXUH
Insert a lifting eye as shown in Figure 2-16 on page 13 and remove the lower bearing shell, see Figure 2-17 on page 14. Be careful.
)LJXUH
3BSM 005446, Rev. B EN -
3BSM 005446
13
)LJXUH
Store both halves of the bearing shells in a very clean place. It is strictly forbidden to store metal chips and other metallic components together with the bearings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
3BSM 005446
14
)LJXUH
Place a piece of wood against the bearing liner on the opposite side where the screw is still in place. Knock carefully against the edge of the liner until it can be removed at the side where the screw has been removed. See Figure 2-19 on page 15.
)LJXUH
3BSM 005446
15
The liner material is very soft. Be very careful, when installing the new liner, not to scratch or to damage the new liner. Tap down the new liner with very little force by using a plastic hammer as shown in Figure 2-20 on page 16 until the liner projects approx. 5 mm above the horizontal joint of the bearing shell.
)LJXUH Place a drop of Loctite in the tapped hole. See Figure 2-21 on page 16.
)LJXUH
3BSM 005446, Rev. B EN -
Place the washer in the tapped hole and tighten the cross-recessed countersunk screw with a Phillips screw driver (Figure 2-22 on page 17). Tap down the liner very carefully by using a
3BSM 005446
16
plastic hammer as shown in Figure 2-20 on page 16 until the liner is even with the horizontal joint.
)LJXUH
After both halves have been fitted with new bearing liners, place both halves with the plane machined surfaces down onto the work bench. Insert the four M 24 hex. socket head cap bolts and tighten carefully each bolt a little at a time with a torque wrench until both halves are assembled with a torque of 735 Nm. Hold down the bearing shell assembly while tightening the bolts. See Figure 2-23 on page 17.
)LJXUH
3BSM 005446
17
Measure the inner bearing liner diameter at both ends of the liner in the bearing shell and at least two diametrically opposite places with an inside micrometer as shown in Figure 2-24 on page 18 and Figure 2-25 on page 18.
)LJXUH
)LJXUH Write down the values measured and compare them with the shaft diameter values from the final test protocols. A radial play between bearing liner diameter and rotor shaft diameter of a minimum of 0.34 mm and a maximum of 0.45 mm is acceptable. Separate the bearing shell halves for assembly into the bearing housing.
3BSM 005446
18
%($5,1* ,168/$7,21 The bearing insulation consists of a self-adhesive teflon strip which is attached to the spherical contact surface of the bearing shell.
)LJXUH
When cutting the insulation strip into shape of the spherical surface, an excess edge must be left all around, this surface including the holes in the bottom shell. The excess edge is at least 5 mm. It is an advantage to bend the excess edge around the corners in order to protect edges when handling the bearing shell.
3BSM 005446
19
)LJXUH
%($5,1* 6($/6 Grooves to accomodate bearing seals are provided on each side of the bearing housing. The seals are of a glass-fibre construction, containing a labyrinth seal facing the rotor shaft and a rubber seal on the outer diameter facing the bearing housing. The seal must be assembled so that the axial oil drain hole is located at the 6 oclock postion and the radial guide pin (roll pin) fits into the upper half of the bearing housing at the 12 oclock position (The roll pin prevents rotation of the bearing seal). See Figure 2-28 on page 20.
)LJXUH
3BSM 005446
20
&KHFN WKDW WKH EHDULQJ KRXVLQJV DUH DEVROXWHO\ FOHDQ DQG IUHH IURP IRUHLJQ PDWWHU
Basically, reassembly is executed in the reverse order as described in Section 2.1. The hydraulic jack is still underneath the rotor shaft as described in Section 2.1 Figure 2-14 on page 12. Apply a thin coat of oil to components which are to be assembled.
3BSM 005446
21
Insert five lifting eyes in the lower bearing shell and lift the shell over and onto the rotor shaft. Lower the bearing half on the shaft, remove the upper lifting eye, hold onto 2 of the lifting eyes as shown in Figure 2-29 on page 22 and allow the shell to glide around the journal until the lower shell is inserted. See Figure 2-30 on page 22 and Figure 2-31 on page 23.
)LJXUH
)LJXUH
3BSM 005446, Rev. B EN -
3BSM 005446
22
)LJXUH
Connect the jacking oil connections and the earth connection to the bearing shell. See Figure 2-32 on page 23.
)LJXUH
Lower the rotor shaft carefully into the bearing liner. Check the distance between the bearing journal and the bearing liner with a feeler gauge on front and rear end of liner and on both sides. The tolerances must be as equal as possible and the minimum distance between bearing liner and journal must be 0.1 mm. Otherwise the rotor must be jacked up again. Using a plastic hammer knock slightly at the horizontal joint of the bearing
3BSM 005446
23
shell to adjust the spherical position of the bearing. Repeat until an acceptable tolerance is obtained. See Figure 2-33 on page 24.
)LJXUH
Assemble the air-lock seal and the bearing seals. Check the clearance (about 0.5 mm) between the air-lock seal and the shaft. See Figure 2-34 on page 24.
)LJXUH
3BSM 005446, Rev. B EN -
3BSM 005446
24
Lift the upper bearing shell into position as shown in Figure 2-35 on page 25.
)LJXUH
Insert the four M24 hex. head cap bolts and tighten the bolts with a torque wrench to 735 Nm. See Figure 2-36 on page 25. Be sure that the bolts for separating the shell are in the original position as before the dismantling.
)LJXUH
3BSM 005446, Rev. B EN -
3BSM 005446
25
Clean the upper part of the bearing housing and apply a thin coat of oil to the spherical bearing seat. See Figure 2-37 on page 26.
)LJXUH
3BSM 005446
26
)LJXUH
3BSM 005446
27
)LJXUH
)LJXUH
3BSM 005446, Rev. B EN -
Lift the upper bearing half into place. Tighten the eight M24 hex. head socket cap bolts with a torque wrench to 735 Nm. See Figure 2-5 on page 6 in Section 2.1.
3BSM 005446
28
Check the bearing insulation by megging as shown in Figure 2-41 on page 29 and Figure 2-42 on page 29.
Loosen the hub for the earth device and pull out the earth connector and connect for megging )LJXUH
)LJXUH
3BSM 005446, Rev. B EN -
3BSM 005446
29
0 22.5 16.6
0 45 33
0 79 58
0 190 140
0 420 300
0 735 550
0 1500 1100
3BSM 005446
30
3BSM 005446
2001-09-13
Service Notes
A protable process requires that all the component parts function satisfactorily. ABB is naturally well aware of this and of the responsibility it takes as supplier of motors and generators. This responsibility is not limited to the supply of reliable motors/generators commissioned in an appropriate way. ABB therefore offers services aimed at giving the motor/generator as trouble-free operation as possible over its entire life cycle. These services are also intended to extend the life of the motors/generators. The range of services comprises spare parts, workshop services, site services, service packages and technical support. They are implemented in co-operation with service companies both within and outside the ABB Group, which gives a global coverage. It is no exaggeration to say that ABB feels a sense of responsibility for the motors and generators it has supplied a long time after the warranty period has expired. The entire organization takes responsibility for the delivered motors/generators. But this responsibility is rooted above all in the service market group. The main task of this group is to develop services products and to make certain that they are implemented in the best interests of our customers. This involves
everything from the addition of new spares to the stock of spare parts, top-class system analyses to availability analyses to establish whether actions are needed to assure the reliability or life of a motor/generator. Despite extremely reliable products and all reasonable preventive maintenance, it is inevitable that production disturbances occur on some occasion. Fast emergency actions are then the only thing that can minimize production losses. And the closer the assistance is available, the faster can actions be taken. The nearest assistance is always to be found in the customers own maintenance organization. Our role is therefore to offer support to the customers organization or for this to be done by a local service company under supervision from us. Support is available in the form of troubleshooting documentation, distance support, supervision and training courses The service market group is made up of people whose knowledge complements that of each other. Together, they cover a very broad range of competencies. All the members of the group share one thing in common, namely their solid experience of rotating electrical machines in general.
3BSM005556 RevH_0802
Preventive maintenance preserves the plants production capacity The goal of preventive maintenance is to change the maintenance work from being mainly emergency interventions, where each problem is addressed as it arises, to planned actions with focus on reliability and minimizing of production disturbances. The basis of preventive maintenance is the implementation of a maintenance programme with recommended intervals. When supplemented by maintenance based on condition monitoring, analyses and checking of the performance carried out by experienced personnel, any deterioration can be discovered in time and corrective actions taken. Improved plants through value-raising measures The machines supplied by us are always matched with the drive application for which they are intended. They are also state-of-the-art machines at the time of their delivery. However, developments never stand still. We are constantly gaining new experience. Todays products consequently have a better performance and better operating characteristics per than the motors/generators supplied earlier. The upgrading/modernization of motors and generators supplied earlier and in service in many cases can therefore be a very protable way to increase value. This value lies in higher production, less maintenance, higher raliability and longer life. Central support With an installed base throughout the world, it is impossible to maintain in-depth specialist competence close to each individual customer. The solution is therefore to provide strongly centralized support services. Support that enables local ABB staff in sales and service companies to act as if the centrally located specialists were on the spot.
Krister Johansson Manager Working since 1989 at ABB as prod. engineering, supply management and the last four years as responsible for sales & marketing of motors. Phone +46 (0)21 329509, Email: [email protected] Bjrn Lindberg Technical support Has been with ABB since 1994 and rotatng machinery since 2002, the latest year with development. Phone +46 (0)21 329667, Email: [email protected]
Yngve Anundsson specialist Sales and Technical support Working since 1975 at ABB. Worked as head of the test room and project manager. Since 1998 with After Sales. Phone +46 (0)21 329521, Email: [email protected] Jonas Burstrm Sales and Technical support Working since 1988 at ABB. The last years with synchronous motors and generators as projectmanager and area sales manager Phone +46 (0)21 329527, Email: [email protected] Erik Englund Sales and Technical support Working since 2005 at ABB and with rotating electrical machines since 2006. Phone: +46 (0)21 325802 Email: [email protected] Stefan Wilson Sales and technical support Working since 1970 with rotating electrical machines in production, supply management, and after sales service.
Phone: +46 (0)73 044 05 03 E-mail: [email protected] sa rnstedt Orderhandling Working in ABB since 1987 and within Machines form 2007.
Roger Andersson Orderhandling Working since 1988 at ABB. The last years with electrical machines.
Service Notes
Tobias sterholm Technical support Working since 2002 at ABB with rotating electrical machines as development engineer and with technical support. Phone +46 (0)21 329446, Email: [email protected] Mikael Levin Sales and Technical support, orderhandling Working since 1989 at ABB with electrical machines as mechanical designer and project manager. Phone +46 (0)21 329579, Email: [email protected] ke Lfberg Commissioning Working since 1990 at ABB with commissioning of control systems and electrical machines.
Phone:+46(0)21329499 Email:[email protected]
Jonas Carlsson Orderhandling Working in ABB since 2001 within Machines from 2005.
Phone + 46 (0)70-3997937, Email: [email protected] Mikael Karlsson Commissioning Working with commissioning of control systems and electrical machines.
Phone + +46 (0)21 329456, Email: [email protected] Kjell Gaufn Orderhandling Working since 1964 with rotating electrical machines, with sales and production.
Phone: +46 703 30 86 80 E-mail: [email protected] Marko Pikkarainen Commissioning Working with commissioning of control systems and electrical machines.
Phone +46 (0)21 329561, Email: [email protected] Leila Yli-Kerko Orderhandling Working since 1975 with rotating electrical machines as machine operator, quality control inspector and mechanical designer.
Type of motors and generators manufactured by the Machines factory in Vsters. These machines are of the following types: Synchronous machines; AMS, AMT, GAE, GBA Induction machines; AMB 710, AMC, MAA, MAE, MBA, MBE, AMI 710-900
3BSM005991 RevB_0510
Service Notes
Summary Recommendations for suitable spares can be made on the basis of the knowledge of the supplied product/plant, experience of the application and the operating conditions. We have prepared for our motors and generators with accessories a list of recommended spares classied for different stages in the lifetime of the motor/generator. The recommended sets of spares have been coupled to our recommended maintenance programmes. Furthermore, we have matched them with different safety levels.
Benefits The recommended spares are based on operating experience gained from thousands of machines. The total investment in spares need not occur at the same time as the investment in a new machine. It is often sufcient to cover the rst 3 to 4 years in conjunction with a new investment. The long-term scope of spares is suitably determined after a few years of operating experience. With the classied recommended spares, each customer has the opportunity to choose the scope of spares matched with the reliability demanded by the application and the calculated risks that are reasonable to take.
3BSM005991 RevB_0510
ABB Automation Technologies AB Machines Elmotorgatan 2, Building 394 Tel: +46 21 32 90 00 Fax: +46 21 32 90 10 www.abb.com/motors&drives e-mail: [email protected]
Service Notes
Consumables that are to be replaced at certain intervals and spares that are critical to operation. Spares for further increasing the availability.
Capital spares
Spares which in afew cases maybe be justied when extra reliability is needed. The scope can vary within wide limits from rotor coils to a complete spare machine.
Review of spare parts ABB Machines after-sales group les all the documents for each supplied machine. Based on the motors or generators serial number, detailed information can be retrieved for use later on to review the spares. In these reviews recommendations are given not only for the replacement of parts but also changing over to more modern solutions. Spares support With a well-planned stock of spares a stock where the spares are based on spares recommendations where the spares are easy to nd the basis for a high availability has been set for the machines supplied by us. But despite this, it is inevitable that spares must be procured. Spares utilized have to be replaced. It is not always possible to predict the need for spares and to stock them.
In these cases it is necessary to have a supplier having good spares logistics who is able to dispatch quickly the missing component. We have a well-planned spares support arranged in co-operation with ABB Logistic Center. By means of well-developed logistics, individually adapted routines for spares of different types and co-operation with global courier services, we are able to provide suitable spares support. For certain spares, e.g., printed circuit boards, repairs and return to the stock are a cost-effective solution. We have the routines for this. With access to the drawings, also for older machines, we are able to manufacture spares or propose new, modern solutions.
We reserve all rights in this document and in the information contained therein. Reproduction,use or disclosure to third parties without express authority is strictly forbidden. ABB Automation Technology Products; 2003
1.
Purpose The purpose of this instruction is to define the grouting methods that we recommend as a supplier of electric machines. There are other methods for grouting but the following methods have been found to work well in most cases.
2.
General safety instructions The work described in this manual is only to be performed by trained and authorized personnel. The manufacturer is not responsible for incorrect use, which affect the safety due to change, use of components from other supplier than ABB, neglect or misuse. The actual design can differ from the illustrations in this instruction. Contact ABB at slightest uncertainty that can affect the safety. Use of solvents when cleaning and use of lubricants and other chemicals can affect the health and/or the safety of the personnel. The recommended safety measures and procedures from the supplier shall be followed. The user must see to that the machine is properly secured in all points when lifting and other work that may cause injuries.
3.
References This document refers to a number of order specific documents. 1. Outline drawing The measurements of the electric machine are indicated on the outline drawing valid for the order. 2. Foundation detail drawing See valid figure drawing for mounting of foundation details (stated on outline drawing) for measurements of foundation details.
Part no.
2003-05-27 Approved
No. of p.
7
Page
Doc. no.
3BSM007280
en
4.
Preparations before mounting and coarse alignment Before mounting of the machine is begun, check that the foundation corresponds with the valid foundation detail drawing. The rotor is not in the magnetic neutral position at delivery due to transport locking. The theoretical measurement for the axial neutral position of the machine is indicated on the valid outline drawing (measurement L5 on the foundation detail drawing). See test protocol in the machine manual for the exact as built measurement and use this measurement for final fine alignment. The foundation details are normally supplied with the contact surfaces untreated. If the surfaces are treated with paint or other rust prevention, these surfaces must be sand blasted clean before grouting is done.
5. 5.1
Mounting and alignment Separate grouting of sole plates The sole plates should be aligned in accordance with the specified outline drawing and foundation detail drawing. 1. Check on the underside that the threaded holes in the sole plates for the electric machine mounting screws are covered with foam rubber strips and that the holes for taper pins are covered with tape. The threaded holes are covered with foam rubber strips so the list, when mounting the machine, can be compressed and create space for the top of screws under the sole plates. Every thread in the sole plate will then be used. The holes for taper pins are covered to avoid that these are filled with grouting mix. 2. Mount the anchor bolts in the holes in the sole plate (see figure 1). The nuts of the anchor bolts shall be screwed on so the plastic tubes are tight mounted between the square washers and the sole plates, and the top of the anchor bolts are in level with, or just above the upper edges of the nuts (See figure 3). Cut the plastic tubes if necessary.
Doc. no.
Lang.
Rev. ind.
Page
3BSM007280
en
Figure 1
3. Lift the sole plates in place. The plates are supported by adjustment screws that run through the sole plate and rest on steel washers. The adjustment screws are later used to adjust the plates vertically. (See figure 2.)
Machine CL Machine center height according to outline drawing + 2 mm for shims Adjustment screw
Steel washer
Figure 2 4. Adjust the position of the plates horizontally and vertically (See figure 2) 5. The plates should be appropriately locked horizontally before grouting is begun. 6. Check the location of the sole plates acc. to drawing: Foundation details. 7. After grouting process the adjustment screws should be cut flush with the sole plate 5.2 Grouting of machine with pre-mounted sole plates When grouting a machine with sole plates, the plates shall be mounted on the machine according to valid foundation detail drawing. Taper pins are to be mounted after final fine adjustment. Mounting of sole plates to machine: 1. Min. 2 mm shims should be placed between the machine and sole plates before the machine is put on the sole plates (See figure 3.) 2. Assemble the pipes (item 9 on drawing: Foundation details) on the mounting screws of the machine. This is done to centre the hole of the machine foot to the sole plate, which will allow horizontal adjustment after grouting. When the sole plates are centred, the mounting bolts are tightened so that the plate is fixed against the machine feet (See figure 3). 3. The anchor bolts are mounted in the holes according to valid foundation detail drawing before the machine is lifted into place. The nuts of the anchor bolts shall be screwed on so the plastic tubes are tight mounted between the square washers and the sole plates, and the top of the anchor bolts are in level with, or just above the upper edges of the nuts (See figure 3). Cut the plastic tubes if necessary.
Doc. no.
Lang.
Rev. ind.
Page
3BSM007280
en
Figure 3 4. Mount the M16 adjustment screws from beneath the sole plate (see figure 3.1). Tighten the screws so they run free from the bottom of the recess in the foundation. If necessary cut the bolt flush with the topside of the sole plate. The adjustment screws are used to create extra support for the plate after grouting. They have no adjustment function.
Figure 3.1
5. Trestle the machine according to valid foundation detail drawing during grouting. Adjustment of height is done with appropriate shims. To raise the machine lifting jacks with low design (max 80 mm). The lifting jacks are placed between foundation and sole plate.
*)
*) A
Lifting jacks
Doc. no.
Lang.
Rev. ind.
Page
3BSM007280
en
Figure 4. 6. Grouting
Grouting is done in the recesses of the foundation. The grouting shall be done with a for the application appropriate fluent shrink-free grouting mix. To achieve a good result, the use of Masterflow 928 or other equivalent product is recommended. Follow the suppliers instructions and work descriptions accurately. During the grouting the anchor bolts hangs down in the recess holes of the foundation, see valid foundation detail drawing. If Masterflow 928 is used, it is recommended to perform the grouting in two stages. For other grouting mixes the supplier recommendations shall be followed. Firstly, the holes for the anchor bolts are grouted. These are filled with grouting mix to about 2 cm from the upper edge. (See figure 1) When this has cured, any water that has protruded is removed and the final grouting under the sole plates is done. The whole space under and around the sole plates is to be filled with grouting mix. It is of outmost importance that no air pockets are formed under the sole plates, as this can lead to operation disturbances such as e.g. vibration problems. The mixing of the grouting mix shall be done exactly according to the manufacturers instructions. 7. Fine alignment Before the machine is fine aligned, the grouting mix must cure. Contact the supplier of the grout for information about curing times. After the grouting has cured the anchor bolts shall be tightened to the torque value indicated on the foundation detail drawing. This procedure shall be done before the fine alignment is begun. Fine alignment is done according to the electric machine operations and maintenance manual. The machine can be adjusted horizontally when the bolts have been loosened. The height of the machine is adjusted with shims. Some machines are equipped with vertical adjustment screws that can be used to lift the machine. In other cases lifting jack with low design are used. When desired alignment result is achieved the screws are tightened to the torque value indicated on the foundation detail drawing. Taper pins are mounted after final fine alignment.
Doc. no.
Lang.
Rev. ind.
Page
3BSM007280
en
8.
Other
9.
Responsibility The purchaser is responsible that the foundation is dimensioned and designed correctly. Consideration shall be taken to, amongst others local conditions, occurring forces, passage for pipes and cables and also that service and maintenance can be performed.
Doc. no.
Lang.
Rev. ind.
Page
3BSM007280
en
REVISION Rev. ind. Page (P) Chapt. (C) A B C D General Fig: 1 & 3 General P 2-5 Description Warning signs and text added Anchoring bolts were counter sunk Sole plates where foundation plates, point 4 add in 5.2 Chapter 4; 5.1.1; 5.1.2; 5.2; 5.2.3; 5.2.4; 7 Date Dept./Init. MK/SP MKU/WM MK/SP MKU / HAAK
Doc. no.
Lang.
Rev. ind.
Page
3BSM007280
en
Synchronous machine
Instruction for removal of rotor on site
(GBA/AMS 1000, 1120, 1250, 1250A)
Document No.: 3BSM 009020
Contents
1 - Safety 1.1 General safety instructions ......................... 3 2 - Instruction for removal of rotor on site. 2.1 Overhaul of machines according to Level 4 inspection in the manual............................. 4 2.2 Planned work.............................................. 5 2.3 Removal of main rotor ............................... 6 2.4 Assembly of main rotor............................ 13 2.5 Recommended tightening torque for bolts16
NOTICE The information in this document is subject to change without notice and should not be construed as a commitment by ABB. ABB assumes no responsibility for any errors that may appear in this document. In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or hardware described in this document. This document and parts thereof must not be reproduced or copied without ABBs written permission, and the contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM 009020
ii
1 Safety
1.1 General safety instructions
The procedures described in this manual are only to be performed by trained personnel authorized by the user. The manufacturer is not responsible for malfunctions that comprise safety as a result of alteration, use of non ABB replacement parts, neglect or misuse. Replacement parts may vary from those shown in this manual. Should you have questions on those parts please contact ABB Automation Technologies AB. The actual appearance of the machine may vary from the illustration in this manual. Should pre-owned ABB equipment be purchased and reconditioned, the equipment should not be used until testing and analysis demonstrate that the equipment meet the original or upgraded specifications. The use of solvents as cleaning agents and the use of lubricants can involve health and/or safety hazards. The recommended precautions and procedures of the manufacturers should be followed.
3BSM 009020
Site PPE requirements. Hi Viz Jacket Safety Helmet Safety Glasses Safety Boots
3BSM 009020
WARNING - High voltage This work involves the main circuits of the generator normally connected to the high voltage supply net. Before you start to work: 1. Make sure the generator is disconnected from the high voltage net and that the circuit breaker is locked in the open position so it not accidentally (or otherwise) can be closed during the measurements. Note also that capacitors can contain dangerous voltages, so be sure to ground all details before you touch them.
2.
Remove the cooler top, covers, bearings, main rotor and perform level 4 inspection. Dismantling, assembling and inspections including measurements in accordance with the order specific manual for the machine.
3BSM 009020
WARNING - Risk of personal injury When the rotor is moved out of the stator and is supported for fitting a new extension piece, make sure to place an external support under the exciter end. The centre of gravity is otherwise outside the support and the rotor will tip, possibly endangering personnel.
Figure 2-1 NOTE: It is strongly recommended that rotor removal and reassembly should be performed by professional service or commissioning engineers authorised by ABB. 1. Ensure that a valid work permit is applicable and all members of the working party are familiar with the work method statement, the specific maintenance procedures and test required. Ensure before working on any electrical equipment, general electrical safety precautions are to be taken and local regulation are to be respected, according to instructions of the customer personal in charge of security, in order to prevent personnel accidents. See users manual, Chapter 7.
2.
3BSM 009020
3.
Ensure before start of work that the machine is disconnected from the high voltage net and that the circuit breaker is locked in the open position so it not accidentally (or otherwise) can be closed during work and measurements. Ensure that the machine is grounded. See user manual, Chapter 5. Before use inspect the installed lifting equipment and ensure that all lifting equipments have current test certificates. Disconnect the machine shaft from all the driven objects. The rotor pole position should be 3, 6, 9 and 12 oclock. Remove the end plates on the cover and cooler top by the crane. Remove the PMG stator and in accordance with the users manual. Remove the exciter stator by the truck and in accordance with the users manual. Remove the oil pipes, temperature probes etc from the bearing in accordance with the manual.
4. 5. 6. 7. 8. 9.
10. Assembly the draw plate to the shaft end on ND-end. 11. Apply the towing equipment on D-end and ND-end, use tackle blocks/chain hoists (optional equipment) and slings (optional equipment). See Figure 2-2 on page 7. D-end - shall be mounted somewhere on the gearbox/steam turbine, on a hook in the wall or something else and around the shaft end, and shall be used as counterstay to prevent to much movement during the removal of the rotor. ND-end - shall be mounted on a hook in the wall or somewhere else and to the draw plate mounted on the shaft, and shall be used to draw the rotor out of the stator.
Max 5kN
Towing equipment
3BSM 009020, Rev. B EN 060628
Figure 2-2
3BSM 009020
12. Before the slings are mounted around the shaft the sliding support plate must be mounted. Place the sliding support plate into the air gap between the rotor and stator in pole position 12 and then slide the plate around to pole position 6. Extreme care should be taken when inserting and sliding the tool not to damage the stator core and winding. See Figure 2-3 on page 8. Sliding support plate
Figure 2-3
3BSM 009020
13. Erect the mobile/overhead crane on the ND-end side for removing of the rotor. See Figure 2-4 on page 9.
Figure 2-4 14. Loosen the end shield on the ND-end. 15. Dismantle the upper half of D-end bearing in accordance with the users manual.
3BSM 009020
16. Lift the rotor on D-end about 0.5 mm by a 20-30 tons lifting jack. 17. Remove the lower half of the D-end bearing shell in accordance with the users manual. 18. Place the sliding plate into the sliding support plate at the D-end, see Figure 2-5 on page 10.
Sliding plate
Figure 2-5 19. Lower the rotor so that it rests on the sliding plate. 20. Gently pull the rotor towards to the ND-end and at the same time loosen on the D-end until upper part of the sliding tool reach the ND-end of the stator core, about 50 mm left of the end of the stator core. Support underneath the ND-end shield. See Figure 2-6 on page 10.
5kN
50
3BSM 009020, Rev. B EN 060628
Sliding plate
Figure 2-6
3BSM 009020
10
21. Move the slings to be around the rotor body and lift with the mobile/overhead crane and move carefully towards the ND-end. Be sure that the rotor is in balance before moving so the rotor not will destroy the stator coil ends. Move until the rotor is free to be removed.
Figure 2-7 22. Support underneath the shaft on the D-end and underneath the pole on ND-end by hard wood and remove the support underneath the ND-end shield. See Figure 2-8 on page 11.
3BSM 009020
11
24. Lift the rotor and lay it down on the cradle. See Figure 2-9 on page 12.
Figure 2-9 25. Perform the inspection Level 4 in accordance with the users manual. Store the rotor on solid supports and high enough so that the exciter not will be destroyed. Protect the rotor with a tapaulin. Store both halves of the bearing shells in a very clean place. It is strictly forbidden to store metal chips and other metallic compontents together with the bearings. Make sure that the bearing halves are stored together and that they cannot be mixed with other components when both bearings (D-end and ND-end) are store together. The bearing halves are marked with identity numbers to avoid incorrect assembly which could cause serious problems.
3BSM 009020
12
Figure 2-10 5. Lift the rotor in position as in Figure 2-11 on page 13 and put a support underneath the ND-end shield. The rotor pole possition should be 3,6,9 and 12 oclock. The rotor shall now rest approx. 250 mm on the sliding plate. Be sure that the rotor is in balance when moving the rotor into the stator so the rotor will not destroy the stator winding.
Sliding plate
3BSM 009020, Rev. B EN 060628
Figure 2-11
3BSM 009020
13
6. 7.
Move the slings from the rotor body to between the exciter and the bearing, see Figure 2-12 on page 14. Apply the towing equipment on D-end and ND-end, use tackle blocks/chain hoists (optional equipment) and slings (optional equipment). See Figure 2-12 on page 14. D-end - shall be mounted somewhere on the gearbox/steam turbine, on a hook in the wall or something else and around the shaft end, and shall be used to draw the rotor into the stator. ND-end - shall be mounted on a hook in the wall or somewhere else and to the draw plate mounted on the shaft, and shall be used as counterstay to prevent to much movement during assembling of the rotor. Towing equipment
Figure 2-12 8. 9. Gently pull the rotor towards to the D-end and at same time loose on ND-end until the rotor is back in same position as before dismantling. Place a 20-30tons lifting jack underneath the shaft on D-end. See Figure 2-13 on page 14.
Sliding plate
3BSM 009020, Rev. B EN 060628
Figure 2-13
3BSM 009020
14
10. Lift the rotor, on D-end, about 0.5mm with the lifting jack. 11. Reassembly the end shield on the D-end. 12. Assembly the lower half of the D-end bearing and end shield in accordance with the users manual. 13. Remove the towing equipments. 14. Remove the sliding plate from the sliding support plate. 15. Lower the rotor down into the D-end bearing wiht the lifting jack. 16. Remove the lifting jack from the D-end. 17. Remove the lifting slings. 18. Remove the sliding support plate by sliding the plate from position 6 to position 12 and remove the plate carefully from the air gap. Be careful not destroy the stator winding and stator coil ends. 19. Reassembly the upperhalf of the D-end bearing accordance with the users manual. 20. Reassembly the oil pipes, temperature probes, etc to the bearing in accordings with the manual. 21. Reassembly the exciter stator and in accordance with the users manual. 22. (If PMG) Reassembly the PMG stator in accordance with the users manual. 23. Reassembly the end plates on the cover. 24. Reassembly the cooler top. 25. Connect the machine shaft to the driven/driving object. 26. Clean and clear site working area of all tools and equipment.
3BSM 009020
15
M8 22.5 16.6
M 10 45 33
M 12 79 58
M 16 190 140
M 20 420 300
M 24 735 550
M 30 1500 1100
3BSM 009020
16
3BSM 009020
2006-06-28
Synchronous machine
Replacement of diodes and thyristors
Document No.: 3BSM901869
Contents
1 - Safety
1.1 General safety instructions ............................................ 3
Synchronous machine
NOTICE The information in this document is subject to change without notice and should not be construed as a commitment by ABB. ABB assumes no responsibility for any errors that may appear in this document. In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or hardware described in this document. This document and parts thereof must not be reproduced or copied without ABBs written permission, and the contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM901869, Rev. - EN -
3BSM901869
ii
Safety
The procedures described in this manual are only to be performed by trained personnel authorized by the user. The manufacturer is not responsible for malfunctions that comprise safety as a result of alteration, use of non ABB replacement parts, neglect or misuse. Replacement parts may vary from those shown in this manual. Should you have questions on those parts please contact ABB Automation Technologies AB. The actual appearance of the machine may vary from the illustration in this manual. Should pre-owned ABB equipment be purchased and reconditioned, the equipment should not be used until testing and analysis demonstrate that the equipment meet the original or upgraded specifications. The use of solvents as cleaning agents and the use of lubricants can involve health and/or safety hazards. The recommended precautions and procedures of the manufacturers should be followed.
3BSM901869, Rev. - EN -
3BSM901869
3BSM901869, Rev. - EN -
Figure 2-1
(1250-11)
3BSM901869
Figure 2-2
(1250-12)
Loosen the hex. head socket cap bolts while pushing out the spring lock and lower the bracket so much that the diode can be removed. See Figure 2-3 on page 5.
3BSM901869, Rev. - EN -
Figure 2-3
(1250-13)
Observe and write down the direction of the black arrow on the front of the diode. The replacement diode must point in the same direction during the assembly proceedure.
3BSM901869
The guide pin (roll pins) on each side of the diode are loose items. Make sure to place them in a safe place to avoid loss. See Figure 2-4 on page 6
Figure 2-4
(1250-14)
Clean the contact surface between the diode and the assembly bracket and the contact surface between the diode and the heat sink with piece of cloth damped in ACETONE. See Figure 2-5 on page 6.
3BSM901869, Rev. - EN -
Figure 2-5
(1250-15)
3BSM901869
Clean the contact surfaces of the new diode by using steel wool and a cloth damped with ACETONE. See Figure 2-6 on page 7 and Figure 2-7 on page 7.
Figure 2-6
(1250-16)
3BSM901869, Rev. - EN -
Figure 2-7
(1250-17)
3BSM901869
Apply a thin coat of Silicon grease (ABB part number 1269 0011-105) to both sides (contact areas) of the diode. See Figure 2-8 on page 8.
Figure 2-8 Place the diode back between the heat sink and the mounting bracket.
(1250-18)
NOTE: Rotate the diode so that the arrow marking of the diode is visible at the front. Check that the black arrow on the diode points in the same direction as the one that was removed earlier. See Figure 2-9 on page 8.
3BSM901869, Rev. - EN -
Figure 2-9
(1250-19)
3BSM901869
Be careful that both guide pins (roll pins) are in place before tightening the bolts. See Figure 2-10 on page 9.
Figure 2-10
(1250-20)
Tighten the screws carefully one at a time so that the mounting bracket applies an even pressure to the diode. A spring is attached at the rear side of the mounting bracket which snaps in place when the right torque is reached. (Note that in the dismantling mode, the screw driver was used to remove this spring to permit loosening of the screws). Use a dentists mirror (a mirror with a handle) behind the spring to check that the spring has snapped in place. Check with the mirror that there
3BSM901869, Rev. - EN -
3BSM901869
is no visible gap between the spring and the mounting bracket body. The spring must be in place before the assembly is completed. See Figure 2-11 on page 10.
(1250-21)
3BSM901869, Rev. - EN -
3BSM901869
10
Figure 2-12 Observe the connection of the control pulse unit, the new control pulse unit should have same connection. For reassembly, mount the components in the reverse order.
3BSM901869, Rev. - EN -
3BSM901869
11
M 16 190 140
M 20 420 300
M 24 735 550
M 30 1500 1100
3BSM901869, Rev. - EN -
3BSM901869
12
3BSM901869
2009-03-18
Synchronous generator, type AMS 1250LD Project: TABACAL Project no.: L 000979
NOTICE The information in this document is subject to change without notice and should not be construed as a commitment by ABB AB, Machines. ABB AB, Machines assumes no responsibility for any errors that may appear in this document. In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or hardware described in this document. This document and parts thereof must not be reproduced or copied without ABB AB, Machiness written permission, and the contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
Chapter 1 - Introduction
1.1 1.2 1.3 1.4 1.5 1.6 General information.................................................................................................... 7 Safety .......................................................................................................................... 7 Site conditions............................................................................................................. 7 Prerequisites................................................................................................................ 8 Contraindications ........................................................................................................ 8 Manual system and related documents ....................................................................... 9
Chapter 3 - Alignment
3.1 3.2 3.3 3.4 3.5 Preparations for generator installation...................................................................... 22 Rough levelling of generator after erection .............................................................. 23 3.2.1 Rough alignment...................................................................................... 23 Grouting .................................................................................................................... 24 Correction for thermal expansion ............................................................................. 25 Final alignment and inspection ................................................................................. 25
Mechanical installation ............................................................................................. 26 4.1.1 4.1.2 4.1.3 Cooling arrangement................................................................................ 26 Connection of oil pipes ........................................................................... 26 Mounting of main terminal box ............................................................... 27
4.2
Electrical installation ................................................................................................ 28 4.2.1 4.2.2 4.2.3 Connection of control equipment ............................................................ 28 Connection of high voltage cables........................................................... 28 Earth connection ...................................................................................... 28
Chapter 5 - Commissioning
5.1 5.2 5.3 5.4 5.5 5.6 Check of mechanical installation.............................................................................. 29 Check of electrical installation ................................................................................. 30 Electrical checks ....................................................................................................... 31 Before the first start attempt ..................................................................................... 36 The first start attempts .............................................................................................. 36 5.5.1 5.6.1 Start interlocking...................................................................................... 36 Normal vibration levels ........................................................................... 37 5.6.1.1 5.6.1.2 5.6.1.3 5.6.2 5.7 5.7.1 5.7.2 5.7.3 Bearing housings ...............................................................37 Structural vibrations ..........................................................37 Shaft vibrations .................................................................38 Checks during running of the generator ................................................................... 36
Chapter 6 - Operation
6.1 6.2 6.3 6.4 Start up procedure..................................................................................................... 42 Continuous supervision............................................................................................. 42 Shut down procedures............................................................................................... 43 Alarm during operation............................................................................................. 43
Chapter 7 - Maintenance
7.1 7.2 7.3 Preventive maintenance ............................................................................................ 46 Before all maintenance work .................................................................................... 46 Recommended maintenance program....................................................................... 47 7.3.1 7.3.2 7.3.3 7.3.4
Skeleton No. 3BSM005469, Rev. - EN -
Generator ................................................................................................. 48 Stator........................................................................................................ 49 Stator terminal.......................................................................................... 50 Rotor ........................................................................................................ 51 Bearings ................................................................................................... 53 PMG (Permanent magnetic generator) .................................................... 55 Exciter and Rectifier ............................................................................... 57
ii
Main rotor coil turn insulation (voltage drop test).................................................... 60 Fault finding.............................................................................................................. 60 7.5.1 7.5.2 7.5.3 7.5.4 Diode fault ............................................................................................... 61 Altering the firing voltage........................................................................ 63 Lubrication............................................................................................... 64 High temperature in bearing .................................................................... 66 7.5.4.1 7.5.4.2 7.5.4.3 7.5.5 7.5.5.1 Trouble shooting 1 ............................................................66 Trouble shooting 2 ............................................................67 Trouble shooting 3 ............................................................68 Trouble shooting ...............................................................69
iii
Chapter 1 Introduction
1.2 Safety
The machine is manufactured and intended for use only as described by this manual. Modification, alteration, or lack of maintenance as described in the manual, may adversely affect the safety and efficacy of this machine. The manufacturer is not responsible for malfunctions that comprise machinesafety as a result of alteration, use of non ABB replacements parts, neglect or misuse. Replacements parts may vary from those shown in this manual. Should you have questions on those parts please contact ABB AB, Machines. The actual apperarance of the machine may vary from the illustration in this manual. Should pre-owned ABB equipment be purchased and reconditioned, the equipment should not be used until testing and analysis demonstrate that the equipment meets the original or upgraded specifications. The use of solvents as cleaning agents and the use of lubricants can involve health and/or safety hazards. The recommended precautions and procedures of the manufacturer should be followed.
1-7
1.4 Prerequisites
The operator must: be proficient in the application of the machine and electricity. be thoroughly trained in the skills and have the knowledge required to operate this machine. be thoroughly familiar with the contents of this manual and other operators manuals that deals with the machine and accessory devices that may be used with this machine. be fully qualified and trained in the operation of this machine and able to distinguish normal from aberrant device behaviour. never reset an alarm or trip until the reason for the alarm/trip has been located and necessary remedy has been made to make a safe restart of the machine.
1.5 Contraindications
The machine is not designed, sold or intended for any use except as indicated above. Furthermore, it is not intended to be used outside of the machine specifications or limitations. The machine must be in good working order.
1-8
ABB AB, Machines Scope of Supply General ABB AB, Machines AMS Synchronous generator Technical Specification Drawings for the generator Circuit Diagrams Machine part list
Test Reports
Installation & Maintenance manual Accessories & Instructions Main terminal box
1-9
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
2-10
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
Anchoring point
Figure 2-1 Anchor points during transport on lorry. Beware of area that is dotted in accordance with Figure 2-1 on page 11.
2-11
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
Anchor point
Figure 2-2 Anchor points during transport on lorry or by vessel, located on both sides of the crate.
2-12
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
0.86xB
60o
Figure 2-3
2.1.6 Unpacking
Skeleton No. 3BSM005471, EN, Rev. G
Place the generator so that it is out of the way of any other goods handling and on a flat, vibration-free surface. Remove top and sides of the wooden crate. When the crating has been removed a check should be made to see that the generator is not damaged and that all accessories are included. Tick off the accessories on the packing list which is enclosed. Report immediately to the supplier if there is any damage, suspected damage or if accessories are missing.
2-13
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
When lifting the machine, with the cooler top delivered separate, ensure to have accurate angle on lifting slings, as shown in Figure 2-4. (Otherwise there will be risk of damaging the upper sheet metal housing).
60o
60o
Figure 2-4 When lifting the cooling top see Figure 2-5 and also the instruction Mounting of cooler top included in the binder Users Manual
2-14
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
D=30, Ellipsed
Lifting device
Figure 2-5
Use lifting equipment that is appropriate for the load, see outline drawing included in the binder Users Manual.
Figure 2-6 on page 15 shows an example how the main terminal box should be lifted. As an option a smaller box could be included in the scope of supply, instead of as shown in Figure 2-6 on page 15. Then it will just be supplied with two lifting loops on top. Not included
Figure 2-6
2-15
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
2.2 Storage (this generator is prepared for long term storage) 2.2.1 Short term storage of crated generator
Storage < 9 month Measures to be taken by customer or other part. The machine should be left in the crate. The crate should preferably be stored indoors and shall be placed on a vibration-free, flat and well-drained surface. If the crate is to be stored outdoors, the crate must be covered with a tarpaulin on the top extending at least 1 meter out from the crate to avoid direct rain on the crate. The crate should be kept dry, protected from rain and moisture.
Before commissioning the following items should be carried out: Visual external inspection of bearings and entering shaft Check insulation resistance in accordance with Section 5.3
Remove top and sides of the wooden crate. (Indoors) Open the plastic protection to allow for a good ventilation. If cooler top is delivered separate, the cooler top must be mounted immediately on the machine or if not applicable dont remove the temporary transport covers. (Indoors) The machine should be protected from rain and moisture. If the machine is stored in a harsh environment measures should be taken to protect it against dust and dirt. To avoid condensation in the machine, the heating elements in main machine and exciter must be connected according to the circuit diagram, included in the binder Users Manual. Check regularly the anti-corrosion coating on NOT painted areas like shaft, flanges etc. and touch up if necessary. Measures should be taken to ensure that the heaters work properly at all time.
6. 7.
2-16
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
8. 9.
Corrosion preventive oil should be filled in the bearings, according to section 3.1 on page 22, once every 12 month. Rotation of the rotor is not required. The axial transport-locking device must always be mounted during transportation of the machine.
Before commissioning the following items should be carried out: Visual external inspection of bearings and entering shaft. Visual inspection of exciter. Visual inspection of rotor and stator windings. The corrosion preventive oil in the bearings must be drained before rotation. Check insulation resistance in accordance with Section 5.3 .
5. 6. 7.
Visual external inspection of bearings and entering shaft. Check insulation resistance in accordance with Section 5.3 .
2-17
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
Before commissioning the following items should be carried out: Visual external inspection of bearings and entering shaft. Visual inspection of exciter. Visual inspection of rotor and stator windings. The corrosion preventive oil in the bearings must be drained before rotation. Check insulation resistance in accordance with Section 5.3 .
2-18
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
CL
Figure 2-7
Skeleton No. 3BSM005471, EN, Rev. G
2-19
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
Hose
Pump
Figure 2-8
Footplate, machine
Shims
2-20
Synchronous generator, type AMS Chapter 2 Transport, Storage and Preparation for erection
Figure 2-10
2-21
Chapter 3 Alignment
Introduction Good planning and preparation result in fast, simple and correct installation. Safe running conditions with maximum of accessibility are assured.
Figure 3-1. A simple lever is needed for turning the rotor. While turning the rotor, oil must be continuously poured into the funnels at both end of the generator.
Skeleton No. 3BSM005472, EN, Rev. F
If the generator is to be erected outdoors, sun and rain protection must be provided to eliminate measuring errors.
NOTE: When the surroundings are neither heated nor dry, heating equipment must be provided.
3-22
Lift the generator onto the foundation plates as close to the actual position as possible. NOTE: The rotor is NOT in the magnetic neutral position when the generator is delivered. The rotor is in the magnetic neutral position when the dimension B and C is fulfilled, see Figure 3-2 on page 23. Read the correct distance in the Inspection and Test record Magnetic neutral position, included in the binder Users Manual.
A A to D-end to N-end
Figure 3-2. NOTE: It is important that the rotor is IN the magnetic neutral position when the generator is in operation.
3-23
3.3 Grouting
When the generator has been properly aligned, its base elements are attached to the foundation by grouting. Use only non-shrinking concrete for grouting to ensure proper adhesion between the base frame and grouting. Make sure that the grouting fills properly the whole space around and under the base element. Do not use a vibrator in order to avoid any disturbance in the alignment. After the grouting has set (cured), adjust vertically to the final elevation by putting shims between the base frame and the base element. Check also the other alignments of the generator and adjust, if necessary. Non-shrink grout is recommended for the best results. For shaping and grouting, the manufacturers instructions to be followed.
3-24
r b a
The tolerances given by the coupling manufacturers must not be used in deciding how accurate the alignment should be because these tolerances indicate what the coupling can accept. Excessive tolerances will give rise to vibrations, bearing damage etc. and therefore should tolerances as narrow as recommended above be aimed at. Finally check the axial distance between the two coupling halves.
Skeleton No. 3BSM005472, EN, Rev. F
3-25
4.
4-26
For required oil flow and pressure see outline drawing. The oil pipes should be carefully flushed before they are connected to the generator.
5.
4-27
4-28
Chapter 5 Commissioning
On the commissioning personnel lies a great responsibility for a safe and trouble free operation of the generator during its lifetime. Commissioning should only be made by qualified personal. The following are tests and checks on the generator that are recommended by the manufacturer. If other tests are to be performed, the manufaturer should be consulted.
Check that the generator is properly anchored to the foundation. Check for cracks in the foundation and the general condition of the foundation.
Bearing insulation Megging of bearings should be performed before the generator is coupled to the turbine . See section 5.3 on page 31.
Other checks Open the generator at both ends and check that no loose parts are present inside the generator. Check that no parts have come loose during transportation and that the air-gap is free. If possible, turn the rotor and make sure that the rotor turns freely and that no abnormal sound can be heard. See section 3.1 on page 22. Check the airgap between the exciter stator and rotor, see the test record Air gap measurement (included in binder Users manual).
1. 2.
Remove your own wrist watch, credit cards and other digital equipment before working around those strong magnetic forces. Personnel with pace maker should not be working in the vicinity of the PMG. Check the air gap between the PMG stator and rotor, see the test record Air gap measurement (included in binder Users manual).
5-29
NOTE: The lubrication system must be commissioned and running before the rotor is turned. Check the assembly of the main terminal box and cooling system. Check pressure and flow for oil and cooling system according to outline drawing (included in binder Users manual).
5-30
2.
All connections of control equipment are to be checked and function tested. A bearing insulation check should be carried out before the generator is connected to the turbine . Remove the earth device located on the bearing on the drive end side. Megger the shaft to ground using no more than 500 Volt DC. See Figure 5-1 on page 31 and Figure 5-2 on page 32.
Loosen the hub for the earth device and pull out the earth connector and connect for megging Figure 5-1
5-31
Figure 5-2 Insulation resistance is acceptable if the megger value is more than 1 Mohm.
5-32
General for rotor and stator The winding shall be dry during the test and therefore the standstill heating elements should have been active for at least some days before the megging is performed. The winding temperature should also be recorded. According to normal standards the winding insulation resistance is to be stated at a winding temperature of 40 o C. The value measured is therefore converted to a corresponding 40 o C-value, with the help of the following diagram. Conversion factor, k 100 50
10 5
1 0.5 (0.25)-
0.1 0.05
o -10 0 10 20 30 40 50 60 70 80 90 100 ( C) Winding temperature 14 32 50 68 86 104 122 140 158 176 194 212 (oF) when meggering
R = Megger-value at a specific temperature R40 = Equivalent insulation resistance at 40oC Example: R40 = k x R R = 30 M measured at 20oC k = 0.25 R40 = 0.25x30=7.5 M Recommended minimum insulation resistance at 40oC must exceed the following value
Skeleton No. 3BSM005474, EN, Rev. F
R(40)> U+1 Mohm Where R(40)= Equivalent insulation resistance at 40 oC. U = Rated generator voltage in kV (stator or rotor). The insulation resistance of a new generator, having a clean and dry winding, is considerably higher as will be found in the test report of the generator. If the measured value is considered too low the winding must be cleaned and/or dried.
5-33
2. 3. 4. 5.
Megging should be performed in the terminal box and from the synchronizing circuit breaker (when the high voltage cables has been connected). If the insulation resistance is low when measuring from the synchronizing circuit breaker, disconnect high voltage cables and perform the megging direct on the terminals in the terminal box. A 5000 Volt DC megger should be used. Reading should be made after 1 minute. Main stator Polarization Index check The Polarization Index Test (dielectric absorption test) is an extension of the conventional oneminute resistance test, where the testing time is extended to 10 minutes. To make the test a motor-driven or an electronic megger is necessary to give a sufficiently steady voltage during the testing. The insulation resistance shall be read every minute. The ration of the resistance value after 10 minutes to the resistance value after 1 minute is called the Polarization Index. R10 R1 R1 = Insulation resistance after 1 - minute R10 = Insulation resistance after 10- minute
The Polarization Index should exceed 2. Field circuit insulation resistance (main- and exciter rotor)
Meggering should be performed at the exciter rotor connection to the main rotor. A 500 V DC megger should be used. Reading should be made after 1 minute.
5-34
NOTE: If 1000V DC megger is used the rectifier has to be short circuit before measuring. PMG- and Exciter stator winding insulation resistance A 500 V DC megger should be used. Reading should be made after 1 minute. (When the cables to the terminal box have been disconnected). Drying high-voltage windings The drying process generally takes several days and the insulation resistance, in principle, follows the curve shown below: R (M)
1 Figure 5-3
Time (Days)
During the drying process it is important that the temperature does not increase too rapidly and that the final temperature is not too high. The temperature increase may not exceed 5 oC per hour and the final temperature may not exceed 100 oC. The temperature must be watched carefully throughout the drying process and the insulation resistance measured at intervals. When a steady value for the insulation resistance has been achieved, the winding is dry. Cleaning high-voltage windings The following cleaning precautions are recommended. When the outer casing and winding cover have been dismantled, first remove as much as possible of the extraneous matter with a paintbrush, stiff brush and a vacuum cleaner. Note that dirt may be blown into cooling ducts and pockets and lodge there if compressed air is used. If the winding is covered with oil or oil mixed with dust, it should be cleaned using a suitable solvent: HAKU 1025/920 (ABB AB, Machines part number: 1245 0011-175), varnolene or white spirit may be used. Take great care, see manufacturers recommended precautions.
5-35
5-36
The alarm and trip levels should in no case be above what is given in the tables below. Example: The normal vibration level during operation at site is 1.5 mm/s. The alarm level should then be set at 3 mm/s, and the trip level at 6 mm/s.
Table 5-1: Acceptable vibration levels for bearing housings. The values are valid for all speeds. (Measured frequency range 10-1000 Hz)
Axial mills p-p 3.2 5.0 10.6 mm/s rms 4.5 11.0 20.0 in/sec rms 0.18 0.43 0.79 micron p-p 81.0 198.1 360.1 mills p-p 3.2 7.8 14.2
Alarm Trip
Table 5-2: Acceptable vibration levels for supporting structures. The values are valid for all speeds. (Measured frequency range 10-1000 Hz)
5-37
Table 5-3: Acceptable vibration levels for shaft vibrations. The values are valid for all speeds.
5-38
5.7.1 Page 1
Customer: Site name: Serial number: Order number: Date: Name and company of responsible commissioning engineer:
o First run up, date ..................................... o Direction of rotation: clockwise (Seen from D-end) o Direction of rotation: counterclockwise (Seen from D-end) o No abnormal noise
Comments ............................................................................................................................................................... ................................................................................................................................................................
Generator data
Output: Frequency: Excitation: V kVA Hz A Power factor: Speed: Oil quality: Voltage: r/min Current: V A
5-39
5.7.2 Page 2
Customer: Site name: Serial number: Order number: Date: Name and company of responsible commissioning engineer:
Inlet Oil
Vibr. (mm/s, m)
Dside
Nside
(oC)
(l/s)
Dside
Nside
max
min
5-40
5.7.3 Page 3
Customer: Site name: Serial number: Order number: Date: Name and company of responsible commissioning engineer:
Time (A)
Load (MW)
5-41
Chapter 6 Operation
6-42
The generator has to be unloaded and deenergized (triped). After coasting down the generator make necessary investigation to find out the reason for the alarm before next start.
6-43
Date:
Inlet Oil
Vibr. (mm/s, m)
Dside
Nside
(oC)
(l/s)
Dside
Nside
max
min
6-44
Date:
Time (A)
Load (MW)
6-45
Chapter 7 Maintenance
3.
Preparation and preplanning of maintenance Preparation and preplanning is recommended before all maintenance, special level 3 and 4. Requirements of:
Skeleton No. 3BSM005477, EN, Rev. F
Lifting capacity. Tools including rotor removal at level 4. Manpower and needed competence. Spare parts and other overhaul kit (replacement and consumables).
7-46
Level 2 (L2)
max. 20 000h (equivalent hours) of operation or max. 3 years
Level 3 (L3)
max 40 000h (equivalent hours) of operation or max. 6 years
Level 4 (L4)
max 80 000h (equivalent hours) of operation or max. 12 years
Disassembly covers. Disassembly PMG stator. Open bearings. Open water coolers. Megger, stator Megger, rotor Fibre-optic or video borescope. Oscilloscope/Test equipment.
Open bearings. Removal rotor and exciter. Open water coolers. Megger, stator. Megger, rotor. Rotor removal equipment. Torque wrench. Oscilloscope/Test equipment. Acc. to L3 and suggestion from inspection L1, L2 and L3. Rotor kit.
Instrument/ Tools
Bearing liners, Brushes, Air-lock filter (bearing), Control pulse unit, Thyristors, Diodes. Other order specific parts. Approx. 1 day.
Acc. to L1 and suggestion Acc. to L2 and suggestion from inspection L1. from inspection L1 and Silicon tape. L2. Water cooler. Rectifier kit. Bearing kit. Gaskets. Approx. 2 days. Approx. 5 days.
Expected downtime
Approx. 10 days.
Option: Diagnostic insulation test of the stator winding. Equivalent hours = Total operation hours + No of starts x 20 Example of maintenance schedule:
Interval
Hours x 1000
10 L1
20 L2
30 L1
40 L3
50 L1
60 L2
70 L1
80 L4
Program
Timing of the inspection and overhauls are largely determined by the number of operating hours, the mode of operation and the number of starts of the generator. Local condition has to be considered.
Skeleton No. 3BSM005477, EN, Rev. F
The maintenance intervals shall be co-ordinated for the generator, in a suitable way.
7-47
7.3.1 Generator
Location 1. Generator L1 X L2 X L3 X L4 X Activity 1. Look through all logged or recorded data available; load, temperature, vibrations etc. Fill in the report. If values deviate from time of commissioning or earlier inspection please contact supplier. 2. Inspect exterior of generator for rust, leaks or other defects. 3. Check tightness of all fastenings. 4. Replace air filter, if necessary. 5. Ensure ventilation ducts are clean and free of obstruction if connected to external air. 1. Inspect grouting and anchored bolts. Check for excessive clearances and correct as required. Inspect for cracks in the foundation. 1. Replacing, cleaning and modification acc to recommendation in earlier inspections and suppliers service bulletin.
Approved
X X X X 2. Foundation
X X X X
X X X X X
X X X X X
3. Service/Repair
General cross-section AMS machine (actual design acc. to outline included in binder Users Manual.)
Figure 7-1.
7-48
7.3.2 Stator
Location 1. Stator winding L1 X X L2 X X L3 X X X L4 X X X Activity 1. Inspect winding connections. 2. Inspect winding and bracing rope. 3. Inspection for cleanliness, discoloration, condition of insulation, looseness, movement and wear. Clean if necessary. 4. Measure and record insulation resistance. Refer to Section 5.3 . 5. Measure Polarization Index. Refer to instruction Commissioning section Electrical checks, included in the binder Users Manual. 1. Inspect for discoloration. 1. Check sealing. 1. Verify function of all RTDs. 1. Function check.
Approved
X X
X X
X X
X X X
X X X
X X X X
X X X X
Stator coils
Figure 7-2.
7-49
Example of a terminal box for a generator (actual design acc. to outline for terminal box). See drawing XYK 210780-FLD in users manual.
7-50
7.3.4 Rotor
Location 1. Rotor X 2. Rotor coils X X L1 L2 L3 X X X X X 3. Rotor coil support X X X X L4 X X X X X X X Activity 1. Check all brazed connections for cracks. 2. Measure field circuit insulation resistance, 500V DC megger. Refer to Section 5.3 . 1. Check turn insulation, discoloration etc. 2. Check inter connections. 3. Check turn insulation (voltage drop test). Refer to Section 7.4 . 1. Inspect coil supports, screws, washers and insulation. 2. Check upper coil support insulation plate, Max. movement, 10mm radially out of original position.
Approved
Connection rotor and exciter rotor Upper coil support Figure 7-3.
Insulation plate
7-51
L1 X
L2 X
L3 X
L4 X X
Activity 1. Check pole shoes for discoloration. 1. Inspect by knocking on bolt head. If pole bolts are loose or corroded, ABB has to be contacted. 1. Inspect fan blades and weldings. 1. Inspect balancing weights and fastening details. 1. Check air gap after assembling of machine.
BY BY ABB Cust.
X X
X X X
Fan
7-52
7.3.5 Bearings
Location 1. Bearing inspection 2. Bearing housing and support 3. Shaft seals X X X X X X X X L1 L2 L3 X X X X X X L4 X X X X X X Activity 1. Open bearings. 1. Inspect for leaks. 2. Inspect all bolted joints. 3. Inspect guide support. 1. Check for leaks. If leaks check wear and damages. 2. Clean drain holes in the shaft seals. 3. Check the clearance between the shaft seals and shaft with a feeler gauge after assembling. 4. Shaft surface 5. Bearing liners 6. Bearing insulation 7. Oil piping 8. Measuring instrument 9. Lube oil X X X X X X X X X X X X X X X X 1. Verify that sealing surface are free from corrosion and wearing. 1. Visual inspection of contact surfaces. 1. Measure insulation resistance. Refer to Section 5.3 . 1. Inspect for leaks. 1. Verify function of all measuring instrument. 1. Analyse oil for contamination and replace oil and clean the system if necessary. Refer to Section 7.5.3 . 2. Check for water in each bearing and remove if necessary. 10. Air filter X X X X 1. If necessary replace filter for air intake to the air-lock seals, located on bearing pedestals.
Approved
7-53
Air-lock seals
Bearing housing
Bearing insulation
Figure 7-5.
7-54
Be extremely careful when removing the PMG stator housing to avoid damage to components due to magnetic forces. Remove your wrist watch, credit cards and other digital equipment before working around those magnetic forces. Personnel with pace maker should not be working in the vicinity of the PMG. L3 X L4 X X X X Activity 1. Visual inspection. 2. Measure insulation resistance, 500V DC megger. Refer to Section 5.3 . 1. Visual inspection. 1. Check air gap.
Approved
L1
L2
X X X
7-55
PMG stator
PMG rotor
Permanent magnets
Figure 7-6.
7-56
Figure 7-7.
7-57
Shaft
Figure 7-8.
+ + + + +
Brush holder
Brush
7-58
L1 X X*) X*)
L2 X X*) X*)
L3 X X X X
L4 X X X X X X
Activity 1. Visual inspection. 2. Check for cleanliness, corrosion and erosion of air and water sides. 3. Clean air and water sides. 4. Inspect protection anodes (placed in tube sheet) for proper activity and replace if necessary. 5. Pressure test. 6. Function check of casing water leakage detector.
Approved
X*) X
X*) X
X X
*) If bad efficiency clean the heatexchanger by using brush or chemical rinsing. Actual design acc. to outline included in binder Users Manual
Tube
Tube plate
Water box
Skeleton No. 3BSM005477, EN, Rev. F
7-59
Synchronous generator, type AMS Chapter 7 Maintenance If temperature detectors show normal temperature, usually no additional maintenance to supervision inspection is required for the cooling system. If the coolers have to be cleaned, find instruction included in binder Users Manual. If temperature detectors show an abnormal temperature, or close to alarm level, in winding or cooling air a check of the cooling system has to be made. If the coolers have to be cleaned, find instructions included in binder Users Manual. Water leakage detector To empty the water leakage detector of water, open the ball valve at the bottom of leakage detector, see drawing included in the binder User Manual. Figure 7-10
The test is carried out by applying an AC-voltage over the entire field winding and measuring the current and the voltage drop across the total winding as well as each single coil, see Figure 7-11. The applied voltage should be 230 V or 400 V 50 Hz / 208 or 480 V 60 Hz depending on the rated frequency of the machine.
+ U
U1 The voltage over a single coil (U) should not differ more than 3% from U/4.
2 U
U4
Skeleton No. 3BSM005477, EN, Rev. F
Figure 7-11
Examples of protections that if they give an alarm or trip, may need further investigations to be located are: Diode fault protection. High temperature in bearing. High temperature in winding or in cooling air. Vibration protection.
Note: An equipment specially made for this test is possible to buy from ABB AB, Machines. Test equipment
Rectifier unit
osc
Exciter side
Increase the voltage and check with an oscilloscope the triggering voltage level of the firing unit and the thyristors as shown in figure 7-13 chart 2 and 3. Decrease the voltage to a level under the firing units trigger level, see figure 7-13 chart 1 and measure over each diode separately. A shorted diode will show zero (0) volt on the oscilloscope.
7-61
1. < Triggering voltage level ac < UT Triggering voltage UT level 2. = Triggering voltage level ac = UT UT ac Test Voltage ac
ac Figure 7-13
7-62
Thyristor B Thyristor A
150V 225V 300V 450V 600V 750V 900V 1.1kV 1.3kV 1.5kV
K K-G
K K-G
x x
7-63
7.5.3 Lubrication
The generators are provided with sleeve bearings with an almost unlimited service life provided that the lubrication functions continuously and that the oil is changed at suitable intervals. Temperature To enable the bearing temperature to stabilize at a normal level, the correct amount or flow of oil is required. The normal bearing temperature is 65 - 85 oC. NOTE: The oil may be warm. Characteristic properties of the oil qualities listed are: The oil is a lubricant based on paraffin having high viscosity coefficient (VI>90) and a particularly low fluid temperature. It includes the following additives: oxidation inhibitor anti-foaming mild EP action, anti-wear additive rust inhibitor
Condition of the lubricant Check the oil with respect to colour, smell, turbidity and deposits in a test bottle. The following requirements shall be fulfilled: The oil should be clear or negligibly turbid. The turbidity may not be caused by water. Strong acid or burnt smell is not acceptable. The quantity of metal impurities may not exceed 0.05% by weight. The original viscosity must be maintained within a tolerance of 10-15%. The original acid number should not be exceeded by more than 1 mg KOH per gram oil.
An oil check should be performed a few days after the first test run of the generator and subsequently as required. If the oil is changed just after the commissioning, it can be used again after removing wear particles by filtering or centrifuging. In doubtful cases an oil sample may be sent to the laboratory to determine viscosity, acid number, foaming tendency, etc. A duty period of 3-8 years before an oil change is necessary is not unusual.
7-64
Oil qualities Unless otherwise stated on ABB AB, Machines drawing Outline synchronous generator included in the binder Users Manual, the bearings are designed for any of the following oil qualities: Oil 7 1201-301 (Oil 7061) ISO VG 32 Viscosity 32 cSt at 40C (20 at 50C) Pour point max. -30C. BP: Energol HLP 32 Castrol: Hyspin AWS 32 Esso: Nuto HP 32 Gulf: Harmony 32 AW Klber: Lamora 32 Mobil: D. T. E. 24 Optimol: Ultra 5025 Shell: Tellus Oil 32 Texaco: Rando Oil HD A 32 Oil 7 1201-302 (Oil 7071) ISO VG 46 Viscosity 46 cSt at 40C (28 at 50C) Pour point max. -30C. BP: Energol HLP 46 Castrol: Hyspin AWS 46 Esso: Nuto HP 46 Gulf: Harmony 46 AW Klber: Lamora 46 Mobil: D. T. E. 25 Optimol: Ultra 5035 Shell: Tellus Oil 46 Texaco: Rando Oil HD B 46
Oil 7 1201-303 (Oil 7081) ISO VG 68 Viscosity 68 cSt at 40C (40 at 50C) Pour point max. -27C. BP: Energol HLP 68 Castrol: Hyspin AWS 68 Esso: Nuto HP 68 Gulf: Harmony 68 AW Klber: Lamora 68 Mobil: D. T. E. 26 Optimol: Ultra 5045 Shell: Tellus Oil 68 Texaco: Rando Oil HD C 68
7-65
Insufficient lubrication
Section 7.5.4.2
Faulty coupling
Damaged liners
Change oil
Repair bearing insulation Repair bearing journal Replace liners Renewed commissioning
Faulty instrument?
7-66
Oil pump not reliable? Low oil flow Oil filter clogged? Reduction valve shut?
Adjust flow
7-67
Repair the seals Repair/replace the air-lock seal and check the air filters Correct oil flow Incorrect inclination of the return pipe?
Air-lock seal out of action Oil leaks Too high oil flow
7-68
Faulty instrument
Faulty sensor
Low cooling water flow Cooling water temperature to high Dirty or plugged cooler
Leaking cooler
Overload
Process control
Dirty stator
7-69
Dismantling the machine is done by simply separating all the components of the machine. Since the machine mainly is assembled with screws and nuts, it is rather simple to carry out the dismantling. When the machine has been dismantled into its different components, the different components has to be separated and grouped together dependent upon the different types of material.
Oil tubes from the lubrication system. If the tubes are made of stainless steal, it is necessary to separate them from the rest of the steel components. If not the stainless steel will cause a very low quality of the total steel collected - it is a poison for the steel manufacturer. Teminal box with the copper separated Bolts and nuts etc ... etc. 8-70
These laminations are welded to respective components and can be separated with a gas burner.
The coolers often contains Cu/Ni tubes or stainless steel tubes. In the cases of stainless steel these may be separated by using a gas burner or similar and collected in the group for stainless steel. The rest of the cooler may be considered as mixed material.
8.3.7 Aluminium
The following components are separated into one group for aluminium:
Skeleton No. 3BSM005478, EN, Rev. E
Coil supports of the rotor Heat sinks for thyristors and diodes in the exciter.
8-71
8.3.8 Copper
Copper is mostly integrated in the actual components and require some effort in order to be separated. There exist some special tools for making the separation but normally wedges, large hammers, gas burners and manpower is used. The following components are separated into one group for copper: Stator coils The copper is integrated in the stator and is glued to the stator by use of an impregnation resin. Thereafter the copper in the stator is surrounded by several mm of micabased insulation. The separation of copper from the insulation is done by the method granulation, which is used by larger recycling companies. The granulation method cuts the copper into pieces and the copper is then separated from the insulation by a mechanical process. This can also be done by manpower using hammer and wedges. The amount of copper in the stator is large. Stator connection The copper is integrated within the stator winding. It may be cut off and separated from its insulation by granulation or by manpower. Rotor coils in the machines rotor This is clean copper mixed together with layers of insulation. It may be separated from the rotor by loosening the pole bolts of the rotor body and by removing the coil supports. This copper is of high quality and value, and the amout is large. The copper from the rotor coils is to be kept separate from all insulated copper. Rotor connections in the machines rotor This is cable copper that may be separated from the rotor by a gas burner combined with manpower.
8-72
If there is some questions of enviromental matters not considered in this instruction we ask the user to get in contact with the Environmental Coordinator of the Machine Division.
8-73
We reserve all rights in this document and in the information contained therein. Reproduction,use or disclosure to third parties without express authority is strictly forbidden. ABB Automation Technologies AB; 2003
Bolted joints for current-carrying busbars. Instructions pertaining to assembly. 1. Foreword This document contains general instructions regarding the procedure to be adopted when making bolted joints in busbars. For series-manufactured switchgear, apparatus etc., special assembly instructions are normally provided and these apply to the complete installation including the bolted joints in busbars. For joints in other equipment, where special measures must be taken, e.g. control of tightening torque, special locking facilities etc., instructions are either given on the assembly drawing or are supplied separately for the joints in question. If modifications are necessary during the on-site installation work, it is of the utmost importance that the joints are made in accordance with the applicable standard to ensure satisfactory performance. 2. 2.1 Preparation of contact surfaces Cleaning Dirt, oil and grease are to be removed with white spirits or other suitable degreasing agent. Paints, insulating varnishes, resin residues etc., are to be removed with a steel-wire brush or by scraping with a keen-edged tool. Surface-treated busbars (tinned, nickel plated, silver plated) must not be subjected to mechanical cleaning. Great care must be exercised when cleaning EXCONAL busbars to avoid damaging the copper layer. 2.2 Deburring Burrs and mechanical defects are to be removed with the aid of suitable keen-edged tools. When removing burrs from holes in EXCONAL busbars, the edges should not be chamfered more than necessary. Mechanical grinding, especially of EXCONAL busbars, should be avoided. Care must be taken to ensure that the flatness and the texture of the surfaces are not influenced in any way.
3BSM001263R0001 en MO / A. Kruse 1997-04-21 / Engelen Christina Approved Description Assembly Instruction, current-carrying busbars
ABB Automation Technologies AB
MO
Lang. Rev. ind. Page No. of p.
3BSM001263R0001
en
1 5
FILE: Assembly Instruction current-carrying busbars.doc; TEMPLATE: Techn_Doc_Deliv_P.dot B; SKELETON: ; SAVEDATE: 2005-01-20 10:33:00 AM
2.3
Measures to prevent oxidation and corrosion Depending on the type of busbars material and the environment in which the bars are to be installed, the contact surfaces are to be prepared as specified in the following table:
Material
Copper, copper-clad aluminium, tinned, silver or nickel plated bars/surfaces No measures necessary.
Aluminium, both pure and alloyed, the aluminium surfaces in joints aluminiumcopper Surfaces of the joint to be roughened with a wire brush or a rough file and cleaned from sward and oxide particles. Immediately (within 5 minutes), the surfaces are to be coated with petrolatum (vaseline) 1171 5011-102 and the joint fitted together. As above. On joints of aluminiumcopper in severe corrosive atmospheres, use either Cu-Al-strip or paint as per 2965 2273.
The contact surfaces are to be coated with petrolatum (vaseline) 1171 5011-102.
Table 1 If the customer or other authorities require that a paste, other than that mentioned above, is to be used, the directions for use must be carefully followed. 3. Bolted joints The design of the joint is shown in Figure 1. Note The plane washer need to be mounted nearest the bar, according to Figure 1.
Project Customer Proj. no. Doc. no. Lang. Rev. ind. Page No. of p.
3BSM001263R0001
en
2 5
It is essential that the correct types of plane and spring tension washer are used (refer to the applicable standard pertaining to bolted joints), and that the spring tension washers are correctly positioned, i.e., the outer edge of the washer mates against the busbar or the plane washer.
Project Customer Proj. no. Doc. no. Lang. Rev. ind. Page No. of p.
3BSM001263R0001
en
3 5
To provide some idea of the amount of leverage required, i.e. the distance from the centre of the bolt to the middle of the hand used for applying the force, for larger sizes of bolt, the requisite leverage for an applied force of 300N and for achieving the requisite torque, is given in Table 2.
Bolt M 6 8 10 12 16 20 Table 2
Tightening torque Nm 10 18-25 35-50 60-85 150-200 330-430 1 1,8-2,5 3,5-5 6-8,5 15-20 33-43 kgfm lbf x ft 7,4 13-19 26-37 45-63 110-150 240-320
Leverage distance m
Project Customer Proj. no. Doc. no. Lang. Rev. ind. Page No. of p.
3BSM001263R0001
en
4 5
REVISION Rev. A B Description Change of template. Changed org. name to ABB Automation Technologies AB. Date, Resp. 03-01-08 MVO/PP 04-06-22 MVO/MK
Project Customer Proj. no. Doc. no. Lang. Rev. ind. Page No. of p.
3BSM001263R0001
en
5 5
Installation
The air cooler has to be secured to its location. The fixing points of the cooler are sufficiently stable to carry the dry weight of the cooler and the weight of the liquid in the cooler.
The cooler is designed to withstand normal loads during transport. Any transport damage detected must be immediately reported to the shipper and to Coiltech. Make a note of the damage on the consignment note as well.
Labelling
The cooler data plate is located on the connection side of the cooler and indicates the following: Manufacturer. Max. working pressure. Test pressure. Order number. Year of manufacture. Dry weight. Internal liquid volume.
Operating Pressure
The cooler can only be used with a max. working pressure as specified on the data plate, designated: MWP (MPa).
Commissioning
The cooler can be installed for either horizontal or vertical airflow. The standard cooler is constructed with cross-flow water circuit. The direction of the airflow through the coil is therefore insignificant. The supply and return pipes leading to the cooler must be flushed before they are connected to the cooler. When pressurizing the pipe system with the cooler connected, the pressure may not exceed the working pressure indicated on the data plate supplied. When testing the pressure and starting the ventilation system, the venting plugs should be loosened in order to let out any air in the pipe system. This should be done several times during the first period of operation. Adjust the correct water flow. If the flow is too low, the cooling capacity of the coil is reduced and there is risk of deposits accumulating inside the tubes. On the other hand, if the flow is too high, the cooling capacity is increased but there is risk of erosion. If the QDKR cooler is fitted with a leakage detector, the size G 1/4 upper air venting nipple must be removed to prevent exposing the detector system to an excessive pressure. The leakage detector should be fitted to the lowest nipple. We recommend tightening the header bolts before commissioning the cooler. For particulars of the tightening torque and the order in which they are to be tightened, see under the heading: Fitting the QLKZ-01 Replacement Gasket.
Connections
Connect the pipework with the cooler flanges in such a manner that neither the dilatation forces nor the deadweight of the pipework will put a strain on the cooler flanges. The flanges have to be protected against impacts, external stress and strain. CAUTION! Loading and impacts may damage the cooler.
Quality System
Coiltech AB has a certified Quality Assurance System to ISO 9001 and a Certified Environmental Management System to ISO 14001.
Lifting
The dry weight of the cooler is specified on the data plate located between the liquid connections. The air cooler is equipped with lifting lugs located on the connection and return headers.
Transport
After unloading, carry out a visual inspection to make sure that the cooler hasnt been damaged during transport. It is very important to examine the finned surface of the heat exchanger.
Coiltech
2(4)
Spare Parts
Maintenance
Contamination on the outside and/or inside of the cooler reduces its cooling capacity. The cooler must therefore be cleaned at regular intervals, depending on the constitution of the air and cooling water. During the initial period of operation, the cooler should be inspected frequently.
Coiltech guarantee does not cover costs for coolers that are damaged due to improper installation or freezing. 3. Use a QLKZ/QDKZ-08 brush to When ordering spare coolers, speciclean the inside of the finned tubes fy the production number and type as you flush them with water. number that appear on the data plate of the original cooler. 4. Clean the sealing surface of the headers with benzene or acetone The principal Parts of a and fit new QLKZ-01 Gaskets Cleanable Air Cooler according to he instructions in 1. Side panel Figure 2. The gasket is made 2. Finned body of selfadhesive EPDM rubber. The 3. Tube plate U-strip on the partition wall is 4. Connection header reusable. 5. Return header 6. Venting plug 5. When refitting the headers, note 7. Drain plug how they are marked and refit them to their proper locations. Use a torque wrench to tighten the bolted joint to a torque of 70 Nm. Tighten according to the pattern in Figure 2.
1. Drain the coil thoroughly and remove it from the ventilation system, if necessary.
Coiltech
3(4)
Coiltech AB: SE-614 81 Sderkping Phone +46 121-19100 Fax +46 121-10101 www.coiltech.com Coiltech, Afrikalaan 303, BE-9000 Gent, Belgium Phone +32 9 218 71 30 Fax +32 9 218 71 39 Coiltech, Schnbrunner Allee 11 AT-1120 VIENNA, Austria Phone +43 1 81 20 206 Fax: +43 1 81 20 250
WuXi ECO Coils&Coolers Co.,Ltd. No.19 Xin Nan Zhong Road, Mei Cun Wuxi national High Tech Industrial Development PRC Post code: 214112 Phone +86 (0)510 88558031 Fax +86 (0)510 88558038 www.ecogroup.com [email protected]
Head Office: 33050 POCENIA (UD) | Via Giulio Locatelli, 22 Phone +39 0432.772.001 Fax +39 0432.779.594 www.ecogroup.com [email protected]
Coiltech
4(4)
10
11
Date Change Order
12
Description
13
14
Name
This document is confidential and proprietary to AQ Enclosure AB and shall not without the expressed written permission of CTI be copied, imparted to a third party or used for any other unauthorized purpose.
T10
Q89
T7-9
B
R1
E E
K1-3
F F
K4 GP
H
C1-3 T4-6
E1-3
Created by
GENERAL TOL. ISO UNLESS OTHERWISE 2768 m STATED
Date (yyyy-mm-dd)
Checked By
Date (yyyy-mm-dd)
AQ Articlenumber
KeJo
Material
090123
Project Scale
2762
Units MM
UP TO 6 30 120 400 1000 2000 0.1MM 0.2MM 0.3MM 0.5MM 0.8MM 1.2MM
3mm
Finish Product Name
1:20 TABACAL
Drw No Rev
A1
Sheet
XYK 210780-FLD
01
1/2
5 70
6 1630
8 1630 1470
10
Date
11
Change Order Description
12
13
14
Name
A
This document is confidential and proprietary to AQ Enclosure AB and shall not without the expressed written permission of CTI be copied, imparted to a third party or used for any other unauthorized purpose.
1630
A 70 60
M12
+MTB.GC1
280 D
AQ Enclosure System AB Box 109 - 567 22 Vaggeryd - Sweden tel +46.393.44400 - fax +46.393.44410
200
1004
Gland plate
2525 F 1905 F
1000
1200 H
700 H
300
300
Cu 2x10x80
Created by
GENERAL TOL. ISO UNLESS OTHERWISE OVER UP TO 6 30 120 400 1000 2000 0.1MM 0.2MM 0.3MM 0.5MM 0.8MM 1.2MM 2768 m STATED
Date (yyyy-mm-dd)
Checked By
Date (yyyy-mm-dd)
AQ Articlenumber
KeJo
Material
090123
Project Scale
2762
Units MM
3mm
Finish Product Name
1:20 TABACAL
Drw No Rev
SECTION A-A 1 2 3 4 5 6 7 8 9
A2
Sheet
XYK 210780-FLD
01
2/2
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
No. 902 Data Name Lagerbussning Bearing bushing Lagerbussning, J-O Bearing bushing, J-O Lagerisolering, liten Bearing insulation,small Lagerisolation, stor Bearing insulation,large Luftfilter Air filter Axelttning Shaft sealing Montering ttning Mounting of sealing Slang Hose Slang fr jacking-oil Hose for jacking-oil Borste Brush Open document Note
Article No. 2211 0348-2 2211 0348-6 2219 300-2 2219 300-4 2591 038-1 3BSM 007334-A 3BSM 005928-D 2219 303-4 2515 291-L 3BSM 011092-1
ISS Tabacal Siemens ltd Brazil Type des. AMS 1250LD Intended for Trade name
Based on Prepared Approved Resp dept Pcl
808346
Reg No
08-12-17 P-E Lindh 09-05-26 Anders Lindin Take over dept AP/MAA
Orderbunden stycklista Reservdelar Spare parts Revision A L000979-A XYK 200 500-FLD
sv 1 -
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
No. 902 Data Name Diod Diode Tyristor Thyristor Styrpulsdon Control pulse unit Open document Note
ISS Tabacal Siemens ltd Brazil Type des. AMS 1250LD Intended for Trade name
Based on Prepared Approved Resp dept Pcl
808346
Reg No
09-05-25 P-E Lindh 09-05-26 Anders Lindin Take over dept AP/MAA
Page Cont
sv 1 -
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
INSPECTION PLAN
CUSTOMER PROJECT TYPE OUR REFERENCE SERIAL NO. : : : : : Siemens Ltd Brazil Tabacal AMS 1250LD L000979-A1 8268 088
APPROVED
Customer name: Approved by, sign: Date:
AE058721-1
Prep. Appr. Resp. dept.
No. of sh.
10
Lang. Rev. ind. Sheet
L000979-A1
Document number
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Kodnyckel:
Kod 1 Indikerar plats fr prov S = Hos underleverantr till ABB L = I egen verkstad T = I eget provrum E = P uppstllningsplats Kod 2 Indikerar vem som skall nrvara vid och vervaka provet D = Representant frn orderavdelningen Q = Utsedd intern kontrollant X = Representant frn kund - Endast besk vid prov W = Representant frn kund - Bevittnat prov. Om kund eller kundens representant inte infinner sig i tid till provet, kommer provet att utfras utan dennes nrvaro H = Representant frn kund - Obligatorisk hllpunkt. Provet skall utfras med kund eller kundens representant nrvarande - = Icke signifikant tecken Kod 3 Indikerar att provresultatet eller certifikat skall rapporteras skriftligen och till vem protokollen skall skickas C = Kund via orderavdelning D = Orderavdelning Q = Arkiveras p provplats eller hos ansvarig avdelning - = Icke signifikant tecken Kod 4 Indikerar provets omfattning 1 = Endast frsta maskinen i ordern A = Alla maskinerna i ordern
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
ITEM DESCRIPTION Internal tests: 1 Dimensions stacked stator Dimensioner pltlagd stator
DOCUMENT FORM RECORD Acc. drawing 2000 733-009 XYK 215 100-FLD Acc. drawing 2000 733E-537 XYK 215 142-FLD 4104 016E-27 2000 733E-608 XYK 215 710-FLD 3BSM 000830 2000 733E-539 XYK 215 144-FLD 3BSM 000830 2000 733E-580 XYK 215 442-FLD 3BSM 000831 2000 733E-580 XYK 215 442-FLD 4104 016E-34 2000 733E-580 XYK 215 442-FLD
CODE REMARKS 1 2 3 4 L Q Q A
Visual inspection of uninsulated stator coil Okulrbesiktning av oisolerad flkt statorhrva Testing of strand-insulation of stator coil Provning av partisolering p statorhrvor Impulse voltage test on stator coils Sttspnningsprov p statorhrvor Impulse voltage test on stator coils in stator Sttspnningsprov p statorhrvor i stator Dielectric tests of the stator winding before and after VPI Spnningsprov p statorlindning fre och efter VPI Visual inspection of wound stator Okulrbesiktning av lindad stator Dimensions and run-outs of rotorbody complete Dimensioner och kast p rotorstomme komplett Shaft end with flange Uppmtning av hlbild p axeltapp med flns
L Q Q A
L Q Q A
L Q Q A
L Q Q A
L Q Q A
L Q Q A
Acc. drawing 2000 733E-378 XYK 215 106-FLD Acc. drawing 2000 733-542 XYK 215 111-FLD Acc. drawing 2000 733E-609 XYK 215 711-FLD
L Q Q A
L Q Q A
L Q Q A
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
11 Dimension check of rotor coils Dimensionskontroll av rotorspolar 12 High frequency test of rotor coils Hgfrekvensprov p rotorspolar 13 Tightening torque and angular tightening of pole bolts tdragningsmoment och vinkelstyrd dragning av polbultar 14 Tightening torque for support to rotor coils tdragningsmoment fr spolstd 15 High frequency test on wound rotor Hgfrekvensprov p lindad rotor 16 High voltage test on wound rotor Hgspnningsprov p lindad rotor 17 Impulse voltage test on wound rotor Sttspnningsprov p lindad rotor 18 Visual inspection of wound rotor Okulrbesiktning av lindad rotor
Acc. drawing 2000 733E-531 XYK 215 125-FLD 3BSM 005428 2000 733E-531 XYK 215 125-FLD Acc. drawing 2000 733E-639 XYK 215 463-FLD Acc. drawing 2000 733E-639 XYK 215 463-FLD 3BSM 005427 2000 733E-639 XYK 215 463-FLD 3BSM 005427 2000 733E-639 XYK 215 463-FLD 3BSM 005427 2000 733E-639 XYK 215 463-FLD Acc. drawing 2000 733E-639 XYK 215 463-FLD Acc. drawing 2000 733E-546 XYK 215 435-FLD 3BSM 005426 2000 733E-546 XYK 215 435-FLD Acc. drawing 2000 733E-264 XYK 215 708-FLD Acc. drawing 2000 733-156 XYK 215 152-FLD
L Q Q A
L Q Q A
L Q Q A
L Q Q A
L Q Q A
L Q Q A
L Q Q A
L Q Q A
19 Run-out of rotor complete, run-out of shaft end Kast p rotor komplett, kast p axeltapp 20 Measurement of rotor impedance without stator Uppmtning av rotorimpedans utan stator 21 Dimension check of bearing house Dimensionskontroll av lagerhus 22 Measurements of bearing liners mounted in bearing shell Mtning av lagerfoder monterad i lagersklen
L Q Q A
L Q Q A
L Q Q A
L Q Q A
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
23 Inspection of wound exciter rotor Kontroll av lindad matarrotor 24 Balancing of complete exciter rotor Balansering av komplett matarrotor 25 Winding control of wound exciter stator Lindningskontroll av lindad matarstator 26 Feet location Fotplattors placering 27 Control of contact surface on machine foot Kontroll av fotplattornas kontaktyta 28 Visual inspection of complete machine Okulr besiktning av komplett maskin 29 Weighing of machine, cooler top and terminal box Vgning av maskin, kylartopp och uttagslda
4104 016E-41 2000 733E-629 XYK 215 469-FLD 4104 016E-42 2000 733E-714 XYK 215 701-FLD
L Q Q A
L Q Q A
L Q Q A
Acc. drawing 2000 733-545 XYK 215 160-FLD 4107 011E-17 2000 733E-540 XYK 215 131-FLD
L Q Q A
L Q Q A
T Q Q A
L Q Q A
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
ITEM DESCRIPTION Official tests: 60 Material check of blank for rotorbody Materialkontroll av mne till rotorkropp 61 Material check of blank to pole tips Materialkontroll av mne till polplattor 62 Pressure test of water cooler Tryckprov av vattenkylare 63 Certificate for Pilot Exciter (PMG) Certifikat fr hjlpmatare (PMG)
CODE REMARKS 1 2 3 4 S - C A
S - C A
S - C A
S - C A
64 Balancing of rotor complete Balansering rotor komplett 65 Radial bearing clearance Radiell frigng i lager 66 Air gap measurement Luftgapsmtning
4107 011E-5 2000 733E-546 XYK 215 435-FLD 4107 011E-7 2000 733E-551 XYK 215 305-FLD 4107 011E-8 2000 733E-529 XYK 215 150-FLD
L Q C A
L Q C A
L Q C A
67 Dissipationfactor ( tan delta) measurement on complete machine Frlustfaktormtning ( tan delta) p komplett maskin 68 Resistance measurement Resistansmtning
4104 016E-43 2000 733E-596 XYK 215 400-FLD 4104 016E-5 2000 733E-552 XYK 215 310-FLD
T Q C A
T Q C A
T WC 1
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
70 No-load losses at P.F. = 1 Tomgngsfrluster vid cos = 1 71 No-load characteristic and losses Tomgngskurva och -frluster 72 Short-circuit characteristic and losses Kortslutningskurva och -frluster 73 Load point at P.F. = 0 Belastningspunkt vid cos = 0
4104 016E-6 2000 733E-557 XYK 215 335-FLD 4104 016E-6 2000 733E-557 XYK 215 335-FLD 4104 016E-7 2000 733E-557 XYK 215 335-FLD 4104 016E-15 2000 733E-557 XYK 215 335-FLD 4104 016E-14 2000 733E-554 XYK 215 320-FLD 4104 016E-10 2000 733E-555 XYK 215 325-FLD 4104 016E-11 2000 733E-569 XYK 215 395-FLD 4104 016E-12 2000 733E-556 XYK 215 330-FLD 4107 011E-11 2000 733E-560 XYK 215 350-FLD 4107 011E-15 2000 733E-560 XYK 215 354-FLD
T WC A
T WC A
T WC A
T WC A
T WC A
75 Phase sequence and terminal marking Fasfljd och uttagsmrkning 76 Voltage and current balance Spnnings- och strmbalans
T WC A
T WC A
T WC A
78 Vibration measurements Vibrationsmtningar 79 Vibration measurement during retardation or acceleration Vibrationsmtning under utlpning eller upprullning 80 Functional test of jacking oil system Funktionstest av jacking oil system
T WC A
T WC A
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
81
Calibration of orifice in lubricating oil system Kalibrering av strypbrickor till smrjolje systemet
82 PMG, Output voltage and frequency PMG, utspnning och frekvens 83 Control of leak water detector Kontroll av lckvattenvakt
Acc.drawing 2000 733E-576 XYK 215 438-FLD 3BSM 003641-1 2000 733E-588 XYK 215 450-FLD 4107 011E-9 2000 733E-553 XYK 215 315-FLD
T WC A
T WC A
84 Magnetic neutral pos., axial play in bearing and distance shaft-end to footplate Magnetiskt neutrallge, axiellt lagerspel och avstnd axeltapp fotplatta
T WC A
85 Measurement of insulation resistance before and after dielectric test Mtning av isolationsresistans fre och efter hgspnningsprov 86 Dielectric test Hgspnningsprov
T WC A
T WC A
T WC A
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
88 Determination of rated excitation current Bestmning av mrkmagnetisering 89 Determination of efficiency at rated P.F. and 100, 75, 50 and 25% load Bestmning av verkningsgraden vid mrk cos och 100, 75, 50 och 25% last
4104 016E-20 2000 733E-611 XYK 215 490-FLD IEC 60034-2 cl. 11 2000 733E-612 XYK 215 480-FLD
T D C A
T D C A
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Description
Date Dept./Init.
Document number
Lang.
Rev. ind.
Sheet
XYK210044-FLD
en
10
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 3:06:00 PM; SAVEDATE: 2008-05-08 10:33:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
TECHNICAL SPECIFICATION FOR BRUSHLESS SYNCHRONOUS GENERATOR CLIENT PROJECT TYPE OUR REFERENCE DRIVEN BY DATE : : : : : : Siemens Ltd Brazil Tabacal AMS 1250LD L000979-A1 Steam Turbine 2008-05-05
___________________________________________________
SECTION A. RATED DATA B. STANDARDS C. OTHER PERFORMANCE DATA D. SITE CONDITIONS F. INSTALLATION DATA G. INCLUDED ACCESSORIES H. WORKSHOP TESTS PAGE 2 2 2 3 4 5 8
ENCLOSURE INSPECTION PLAN GENERATOR CURVES : - EFFICIENCY CURVES - SATURATION CURVES - A - V-CURVES - CAPABILITY DIAGRAM - GENERATOR OVERLOAD CURVES - NEGATIVE SEQUENCE CURRENT CAPABILITY CURVES - DECREMENT CURVES SHORT CIRCUIT EQUATIONS
NUMBER XYK 210 044-FLD XYK 210 094-FLD PAGE 1 2 3 4 5 6 7 XYK 210 089-FLD
AE058721
Prep. Appr. Resp. dept.
No. of sh.
9
Lang. Rev. ind. Sheet
L000979-A1
Document number
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
A. RATED DATA Output Power factor ( overexcited ) Voltage Frequency Speed Current Exciter type Excitation B. STANDARDS Applicable standards Insulation class stator and exciter Insulation class main rotor Temperature rise, stator within class Temperature rise, rotor within class C. OTHER PERFORMANCE DATA Efficiency at P.F. 0.85 and 100 / 75 / 50 / 25 % load Reactances: - Xd - Xd' unsat/sat - Xd" unsat/sat - X0 - X2 Time constants: - Td' - Td" - Td0' - Ta Excitation main machine: - voltage no load - voltage full load - current no load - current full load % : 98.43 (15%) % " % " % % % s s s s : : : : : : : : : 98.35 98.01 96.68 : : : : : IEC 60034-1 F H B B kVA : : V (5%) : Hz (5%) : r/min : A : : V/A : 45100 0.85 13200 50 1500 1973 GLA 600D 103 / 11
192 30.5 / 26.2 19.6 / 16.7 8.1 19.6 1.12 0.028 9.57 0.18
V V A A
: : : :
Document number
Lang.
Rev. ind.
Sheet
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Sudden short circuit current (peak) Short circuit ratio Max. field forcing for 10 seconds (percentage of rated excitation) Sustained short circuit, stator current for 10 seconds at symetrical conditions Max. permissible overspeed Output with one cooler element out of service Max. continuous negative sequence current Fault condition capability (I2/IN)2t
kA : 33 % : 57
Allowed current harmonic content, with base 45100 kVA Harmonic 5 th 7 th 11 th 13 th 17 th 19 th 23 th 25 th Current content 2.0 1.7 1.2 1.1 1.0 1.0 0.9 0.6 % % % % % % % %
If the current harmonic content is higher than above values, the temperature of the machine may rise above the specified limits.
D. SITE CONDITIONS Ambient temperature range Altitude Location Water temperature range Hazardous area classification Seismic zone C : 0 - +50 m : < 1000 : Indoors C : 10 - +30 : Non hazardous area : Acc. to UBC, Zone 4
Document number
Lang.
Rev. ind.
Sheet
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
F. INSTALLATION DATA Protection form/cooling form Cooler location/No of coolers Water cooling: - Required cooling water flow - Cooling water temperature max. - Temperature rise cooling water - Pressure drop cooling water - Fouling factor - Cooling water type Heat losses: - Cooling water - Lubrication oil Arrangement form Sleeve bearings: - Max. axial play towards D-end - Max. axial play towards N-end - Max. permissible axial thrust - Min. barring speed - Required oil flow to bearings (Total) - Oil temperature range to bearings - Required oil pressure at 40 C At higher pressure an orifice should be used. - Type of oil - Degree of purity for oil Weights: - Total (complete machine, excluding terminal box) - Stator - Rotor - Terminal box Rotor inertia (J=m*rm2) Direction of rotation (at drive end, facing shaft end) mm mm kN rpm l/min C kPa m3/h C K kPa m2C/W : IP 54 IC8 A1W7 : Top / 2+2 : : : : : : 73.0 30 7.4 30 0.0000900 Customer water analysis required
First lateral critical speed (based on stiff foundation) r/min : 1800 Noise level (at 1m acc.to ISO 3744) Static force on each machine foot Dynamic force on each machine foot Auxiliary equipment power supply: - Anticondensation heaters in the main machine - Anticondensation heater in the exciter - Anticondensation heater in main terminal box
Document number
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
G. INCLUDED ACCESSORIES Cooling arrangement IC8 A1W7 Self circulated inner air circuit cooled by built-on water-air heat exchanger. Protection form IP54. The cooler has following material: Tube material Tube end plates Water box Plate fins Customer connection flange Flange location Design pressure Test pressure : : : : : : Cu 90%/Ni 10% Muntz metal Rilsan coated steel Aluminium ANSI B16.5 Cl.150 Left hand
4 cooler elements. Two in series on each air side. Exciter Main brushless exciter type GLA for DC excitation complete with diode bridge, thyristors, RC-circuits and control box. Pilot Exciter (PMG) single phase type. MCB - PMG over current protection: 20 A. Mounting arrangement IM 1005 Horizontal machine with two bearings, one shaft extension. DE shaft end forged flange. Foundation details Machine provided with 8 feet. Long sole plate kit for grouting with non-shrinking grout including: Foundation plates (2 pcs), anchoring bolts, holding down bolts, mounting shims, dowel pins and horizontal machine jacking bolts. No alignment or grouting included in ABB scope of supply. Jacking bolts vertical adjustment.
Document number
Lang.
Rev. ind.
Sheet
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Bearings Sleeve bearings suitable for flood oil lubrication provided by others, connection at left side on each bearing. The lube oil drain pressure must be less than or equal to the machine ambient pressure. An oil drain pressure of 200-1000 Pa lower than the bearing ambient is recommended. Customer connection flange acc. to DIN. Inlet pipe in stainless steel. Outlet pipe in stainless steel. Lockable pressure reducing valve in stainless steel. Provision for jacking oil only. Emergency oil requirement
Main terminal Heaters in HV terminal box. Large stator terminal box, right side. Stator terminal box protection IP54 with all 12 ends brought out and neutral point terminated inside the box. Connection from underneath. Grounding clamps inside and outside. The main terminal box is delivered as a loose item, assembly on site is not included in ABB's scope of supply. The main terminal box needs to be supported from beneath. Supports are not included in ABB's scope of supply. For terminal box weight see section F.
Document number
Lang.
Rev. ind.
Sheet
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Line side 3 - Surge capacitors 3 - Lightning arrestors 3 - Voltage transformers 1 - Earthing device 3 phase, ball-bolt. Neutral side 3 - Current transformers with 2 cores 1 - Current transformer with single core 1 - Neutral grounding resistor, 10 A for 10 sec. 1 - Low voltage contactor 1 Grounding switch with auxiliary contacts Anticondensation heaters Standard 1 phase elements for 3 phase supply. In both main machine, exciter and terminal box. Termination in separate boxes (normally opposite main supply side). The anticondensation heaters should always be connected during stand still. Measurement and control Resistance temperature detectors All PT100 double elements (excl. stator) DIN. 6 in the stator winding 2 in each bearing 2 in cold air 1 in hot air Flow control glass in oil outlet, carbon steel, 1 per bearing. DIN-flanges. Cooling water leakage detector, brass, capacitive sensor with switching amplifier, 230 Vac. Shaft grounding brush on D-end. Painted carbon steel junction boxes provided with standard cable glands.
A
Document number
Lang.
Rev. ind.
Sheet
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Surface treatment Standard industrial coating acc. to ISO 12944 C2. Primer coating - modified epoxy1 Top coating - modified epoxy1 1 The binder is an acid cured epoxidized oil. Standard colour : 60 m. : 60 m. : Blue NCS 4822-B05G
H. WORKSHOP TESTS ABB AB Machines standard procedure is to perform a type test for a single machine order. If two or more identical machines are ordered, then a type test is performed on the first machine and routine tests on the remaining machines. Proposed workshop tests according to enclosed INSPECTION PLAN are part of our manufacturing program and are part of the quoted price of the machine. Witnessing of testing Participation in a test specially arranged, time to be agreed between ABB AB Machines and customer, 2 weeks advance notice, date will be confirmed 1 week prior to scheduled test date. The performance calculations are carried out and presented to customer during his visit.
Document number
Lang.
Rev. ind.
Sheet
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
REVISION Rev. Page (P) Description ind. Chapt.(C) A P4 Sound level updated to 85 dB(A) P7 1 grounding switch added
Document number
Lang.
Rev. ind.
Sheet
XYK210045-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 1/30/2009 12:35:00 PM; SAVEDATE: 1/30/2009 12:38:00 PM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
808346 AMS 1250 LD Location D-AND ND-BEARING BETWEEN STATOR FLANGES (INSIDE ENCLOSURE) OUTSIDE STATOR FLANGES (INSIDE ENCLOSURE) INSIDE MACHINE (BETWEEN STATOR FLANGES) INSIDE EXCITER INSIDE TERMINAL BOX D- AND N-BEARING INSIDE MACHINE, OUTSIDE D- AND N-BEARING D- AND N-BEARING D- AND N-BEARING IN EXCITER IN EXCITER IN EXCITER IN EXCITER D-BEARING D- AND N-BEARING Article no 5695 418-29 5695 420-7 5695 420-7 6677 0037-E 3AAM 700199-5 6677 0037-D 3BSM 006087-D 2216 0066-G 2211 0348-2 2211 0348-6 4894 580-A 3BSM 000249-1 3BSM 000248-1 3BSM 000313-A 2211 487-9 2219 300-4 Specification Name RESISTANCE THERMO DETECTOR PT 100 OHM RESISTANCE THERMO DETECTOR PT 100 OHM RESISTANCE THERMO DETECTOR PT 100 OHM STAND STILL HEATER STAND STILL HEATER STAND STILL HEATER SHAFT SEAL COMPLETE AIR COVER BEARING SHELL BEARING SHELL JACKING OIL RC-CIRCUIT THYRISTOR DIODE CONTROL PULSE UNIT THRUST WASHER BEARING INSULATION UPPER HALF LOWER HALF Remark D-AND NDBEARING TEMP. TEMP. HOT AIR TEMP. COLD AIR CONNECTION VOLTAGE ACC. XYK 214100-FMD CONNECTION VOLTAGE ACC. XYK 214100-FMD CONNECTION VOLTAGE ACC. XYK 214100-FMD IN AND OUTBOARD D- AND N-BEARING
ISS 08-12-18 P-E Lindh Approved 09-01-23 Anders Lindin Tabacal Siemens Ltd Brazil
Prepared
Resp dept
AP/MAA
Rev Ind
sv 1 2
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Itm 18 19 20 21 22 23
Qty 2 1 1 4 20 1
Location D- AND N-BEARING AT SHAFT ON D-BEARING D-BEARING D- AND N-BEARING INSIDE BOX GA OUTSIDE MACHINE
Article no 2219 300-5 3BSM 011092-1 4395 917-2 2591 038-1 5248 152-1 3BSM 005679-1
Specification
Name BEARING INSULATION EARTH BRUSH BRUSH HOLDER AIR FILTER VARISTOR LEAK WATER DETECTOR
Remark
ISS 08-12-18 P-E Lindh Approved 09-01-23 Anders Lindin Tabacal Siemens Ltd Brazil
Prepared
Resp dept
AP/MAA
Rev Ind
sv 2 -
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Airgap torque equation - 3-phase short circuit Torque(t) = 6.72 * e(-t/0.136) * sin(wt) + 1.47 * e(-t/0.122) p.u. Max. torque = 7.90 p.u. after 4.89 ms
Airgap torque equation - 2-phase short circuit Torque(t) = 5.29 * e(-t/0.226) * sin(wt) - 2.65 * e(-t/0.708) * sin(2wt) + 1.47 * e(-t/0.370) p.u. Max. torque = 8.17 p.u. after 6.66 ms
AE058721
Prep. Appr. Resp. dept.
No. of sh.
2
Lang. Rev. ind. Sheet
L000979-A1
Document number
XYK210089-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:41:00 AM; SAVEDATE: 2008-05-08 10:25:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Description
Date Dept./Init.
Document number
Lang.
Rev. ind.
Sheet
XYK210089-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:41:00 AM; SAVEDATE: 2008-05-08 10:25:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
ABB AB
Machines
Author Date of issue
Scope of Supply
Lang. Print date Internal reference
2008-04-10
en
2009-09-09
Document number
L000979 TABACAL
Rev Page
XYK210093-FLD
1/1
Item Qty
001 1
Description of goods
Generator AMS 1250, LD,TEWAC, IP54 45.1 MVA, 13.2kV, 50Hz, 1500r/m, IM1005
Serial No:
8268088
Design No:
XYK210000-FLD
Comments
C2 Epoxy Standard Industrial Blue
1 1 1 1
Rotorwithdrawal sliding plate type Large Terminal Box Spare Parts for 2 years operation Spare Parts for commissioning
ABB AB
Postal address ABB AB Machines SE-721 70 Vsters/Sweden Telephone +46 (0)21 32 90 00 Telefax +46 (0)21 32 95 10 Reg. no.: 556029-7029 VAT no: SE556029702901 Bank: SEB SE-106 40 Stockholm Sweden SWIFT address: ESSESESS IBAN: SE04 5000 0000 0555 4824 3780
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
EFFICIENCY CURVES
AMS 1250LD 45100 kVA
1.000
50 Hz
0.85 PF
13200 V
1973 A
1500 rpm
0.995
0.990 2. 0.985 1.
0.980
0.975
0.970
0.965
0.960
0.955
0.950 0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
AE058721
Prep. Appr. Resp. dept.
No. of sh.
8
Lang. Rev. ind. Sheet
L000979-A1
Document number
XYK210094-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:42:00 AM; SAVEDATE: 2008-05-08 10:24:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
SATURATION CURVES - A
AMS 1250LD 45100 kVA 50 Hz 0.85 PF 13200 V 1973 A 1500 rpm
1.6
1.4
1.2 1. 1.0 2.
0.8
0.6
0.4
0.2
0.0 0.0 0.4 0.8 1.2 1.6 2.0 2.4 2.8 3.2
Document number
Lang.
Rev. ind.
Sheet
XYK210094-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:42:00 AM; SAVEDATE: 2008-05-08 10:24:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
V-CURVES
AMS 1250LD 45100 kVA 50 Hz 0.85 PF 13200 V 1973 A 1500 rpm
1.4
1.2
0.5
0.7
0.9
1.0
0.8
+ + + + + + + + + + + + + + +
2.
1.0
3.
+
1. 0.6 0.0 0.4 0.2 UNDEREXCITED 0.0 0.0 0.4 0.8
Document number
Lang.
Rev. ind.
Sheet
XYK210094-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:42:00 AM; SAVEDATE: 2008-05-08 10:24:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
50 Hz
0.85 PF
13200 V
1973 A
1500 rpm
0.2
-0.0
0.1
0.3
1.1
1.3
-0.2
5.
U = 1.00
-0.4
3. 0.90
-0.6
4.
-0.8
0.70
-1.0 UNDEREXCITED
0.50
BASE APPARENT POWER 1 p.u. = 1. STATOR HEATING LIMIT 2. ROTOR HEATING LIMIT 3. PRACTICAL STABILITY LIMIT
Document number
Lang.
Rev. ind.
Sheet
XYK210094-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:42:00 AM; SAVEDATE: 2008-05-08 10:24:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
4.0
3.6
3.2
2.8
2.4
2.0
1.6
1.2
0.8
0.4
TIME [S]
IEC 60034-3 Clause 4.15 (I 2- 1) x t = 37.5 s
Document number
Lang.
Rev. ind.
Sheet
XYK210094-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:42:00 AM; SAVEDATE: 2008-05-08 10:24:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
50 Hz
0.85 PF
13200 V
1973 A
1500 rpm
100.
TIME [SEC.]
10.0
1.0
0.1
0.05 0.06
2
0.1 I N = 1973
1.0 A
10.0
100.0
Document number
Lang.
Rev. ind.
Sheet
XYK210094-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:42:00 AM; SAVEDATE: 2008-05-08 10:24:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
50 Hz
0.85 PF
13200 V
1973 A
1500 rpm
2.0
0.2
TIME [S]
Document number
Lang.
Rev. ind.
Sheet
XYK210094-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:42:00 AM; SAVEDATE: 2008-05-08 10:24:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Description
Date Dept./Init.
Document number
Lang.
Rev. ind.
Sheet
XYK210094-FLD
en
TEMPLATE: NORMAL.DOT; PRINTDATE: 2008-05-08 10:42:00 AM; SAVEDATE: 2008-05-08 10:24:00 AM; OSKAR VERSION: 3.48 (2008-03-17)
Project no:
1 2 34 5 6 7 8 9 10 11 12
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
List of contents Line connection, Surge arresters Voltage transformers Machine Current transformers Neutral side Heaters Temperature detectors in stator Temperature detectors in bearings Temperature detectors in air Other detectors Revision Notes
Based on
Prepared
20080829 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
External doc. id. Ref. designation Document id. Rev. Lang. Page Cont.
Approved
List of contents
Document kind
F
C en 1 2
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
1
L1
B
Earthing balls
W1
V1
U1
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
/3.A2
/3.A2
Based on
/3.A2
W1
V1
U1
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Approved
F
Rev. Lang. Page Cont.
Document kind
Document id.
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
en
1
+MTB
2
/2.E2 /2.E2 /2.E2
3
+MTB.GC1
V1
W1
U1
T4 A N
a n da dn
B
X12 5 14 12 F1 11 6 7 5 3 1 6 4 2
I>/
T5 A N
a n da dn
T6 A
a n da dn
1 2 3 4 X13 5
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
C
1UNE
14 F2 12
11
6 7
5 3 1
6 4 2
I>/
1 2 3 4 X14 5
14 F3 12
11
6 7
5 3
6 4 2
I>/
1 2 3 4
E
UL3 UL2
W1
V1
U1
/4.B5
Prepared
/4.B5
/5.A2
/5.A2
Based on
/5.A2
/4.B5
UL1
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Approved
F
Rev. Lang. Page Cont.
Document kind
Document id.
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
en
4
+MTB.GC1
A
/3.E5 UL3 /3.E5 UL2 /3.E5 UL1
B
14 F4 12 11
X15 5 6 7 5 3 1 6 4 2
I>/
1 2 3 4 X16 5
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
14 F5 12
11
6 7
5 3 1
6 4 2
I>/
1 2 3 4 X17 5
D
14 F6 12 11
6 7
5 3 1
6 4 2
I>/
1 2 3 4
Based on
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Approved
F
Rev. Lang. Page Cont.
Document kind
Document id.
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
en
1
/3.E2 /3.E2
2
/3.E2
V1
B
+GEN.GF
W1
U1
B
F8 21 13 A1 A2 1 3 22 14 2 4
I>/
3 4 5 6 1 2 Voltage regulator
+GEN
PMG
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
C
F1 G1 45100 kVA x 0,85 13200 V 50 Hz 1973 A
GS
VOLTAGE REGULATOR F2
EXCITER
/6.A2
/6.A2
Based on
/6.A2
W2
V2
U2
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Title Machine
External doc. id. Ref. designation Document kind Document id. Rev. Lang. Page Cont.
Approved
F
C en 5 6
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
1
+MTB
2
/5.E2 /5.E2 /5.E2
4
+MTB.GC1
A
P2
A
X2 11 12 13
V2 2s2 T8 2s1
T7
2s2 T9 2s1
W2 2s2 2s1
U2
14 15 16 17 18 21 22 23
T7
1s2 T8 1s1
1s2 T9 1s1
1s2 1s1
24 25 26 27 28 X21 1 2 3 4 5
+Q89.01
P1
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
14
10
13
16
V2
12
15
18
W2
U2
17
11
D
X21 11 12 13
1s2
R1 10A 10sek
Based on
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Approved
Neutral side
Document kind
F
Rev. Lang. Page Cont.
Document id.
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
en
1
+GEN
6
+MTB
Heaters in stator
Heater in Exciter
HE1 1
HE2 1 800 W
HE3 1 800 W
HE4 1 450 W
HE5 1 450 W
800 W
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
C
+GE +MTB.GC1
4HE2
4HE1
2HE2
3HE2
5HE2
2HE1
5HE1
3HE1
1HE2
D
1HE1
5HE2
5HE1
D
Connected at site
3 x 380 V
Based on
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Title Heaters
External doc. id. Ref. designation Document kind Document id. Rev. Lang. Page Cont.
Approved
F
C en 7 8
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
1
+GEN
Stator winding U
Stator winding V
Stator winding W
Stator winding U
Stator winding V
Stator winding W
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
C
+GA
4R2
4R2
2R2
2R2
3R2
3R2
5R2
5R2
6R2
6R2
4R1
1R2
1R2
2R1
3R1
5R1
6R1
1R1
Based on
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Approved
F
Rev. Lang. Page Cont.
Document kind
Document id.
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
en
1
+GEN
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
C
+GA
10R4
10R4
10R2
10R2
10R3
10R1
7R4
7R4
8R4
8R4
9R4
9R4
7R2
7R2
7R3
8R2
8R2
8R3
9R2
9R2
9R3
7R1
8R1
9R1
Based on
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Approved
F
Rev. Lang. Page Cont.
Document kind
Document id.
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
en
10
1
+GEN
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
C
+GA
12R4
12R4
13R4
13R4
12R2
12R2
12R3
13R2
13R2
13R3
11R4
11R4
11R2
11R2
11R3
12R1
13R1
11R1
Based on
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Approved
F
Rev. Lang. Page Cont.
Document kind
Document id.
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
en
10
11
1
+GEN
S1 Com
NO
NC
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
C
+GA
1S2
1S3
1S1
Based on
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
Approved
F
Rev. Lang. Page Cont.
Document kind
Document id.
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6
en
11
12
REVISION
Rev.ind.
A B C
Page
2,3,6 810 5 6 6 6
Description
Changed device designations, value on earthing resistor, transformer ratios. Changed terminal designations Changed auxiliary contact of MCB F8 from SPDT to 1NO/1NC Added auxiliary contacts to Q89 Changed CT ratio from 10/1A to 100/1A Changed earthing resistor from 760 to 762
Date/Init.
080829/RP 081104/RP 081205/BG
C
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. ABB
Based on
Prepared
20080619 20081205
B Gothilander PE Lindh
Resp. (division/department) Released
External doc. id. Ref. designation Document kind Document id. Rev. Lang. Page Cont.
Approved
F
C en 12
L000979
D041_A3
Tabacal
L000979A1
MAE
Circuit diagram 4 5 6