Daily Report 20.01.2014

This daily activity report summarizes the contractor's activities on a transport department contract to design, supply, install, and maintain air-conditioned bus shelters. It provides details of the project staff, equipment, and materials used for the week. Key activities included paving tile laying works in progress. The contractor noted they will submit an extension of time and cost claim as they do not expect to complete the contract by the scheduled date due to various factors.

Uploaded by

Syed Shahbaz
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
729 views

Daily Report 20.01.2014

This daily activity report summarizes the contractor's activities on a transport department contract to design, supply, install, and maintain air-conditioned bus shelters. It provides details of the project staff, equipment, and materials used for the week. Key activities included paving tile laying works in progress. The contractor noted they will submit an extension of time and cost claim as they do not expect to complete the contract by the scheduled date due to various factors.

Uploaded by

Syed Shahbaz
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

CONTRACTORS DAILY ACTIVITY REPORT

Contract No.: DOT/C/PT/189/09 Period Project No. Contract No. DOT/C/PT/189/09 20 January 2014
th

Project Title Contract Title Client Contractor Client 3 Party Inspectors


rd rd rd

Design, Supply, Installation & Maintenance of Air Conditioned Bus Shelters

Department of Transport RWS Construction Middle East LLC Bureau Veritas TC International SGS Gulf Limited 10/07/2013 Rainy Dusty No. of Days Left for Completion HUMIDITY High TBA Days Low

3 Party Consultants/ 3 Party Inspectors

Contractual Completion Date WEATHER Sunny

Cloudy

Medium

TEMPERATURE 0 RANG E C

Max

22

Min

19

AVERAGE CONTRACTOR'S MANPOWER Category Project Manager Project Engineer Planning Engineer Structural Engineer Competent person QA/QC Engineer Surveyor Inspector NOC Coordinator Document Controller CAD Draftsman Safety Officer Indirect labour Operator Electrician AC Technician Welder Drivers Fabrication Team Total 4 3 8 6 47 86 No. 1 2 1 1 1 1 3 2 2 1 2 1 Category Construction Supervisor Steel Fixer Carpenter Mason Tillers Unskilled Cleaner Sub contractor (Cable laying) Safety office Foreman Electrician Mason Labour Competent person No. 4 2 2 3 0 11 0

AVARAGE EQUIPMENT Type BOB Cat Excavator Compactor Welding Machine Jack Hammer Generator (For site works) Spot Light 3 Ton Truck 10 Ton Truck 1 1 1 0 1 1 1 Ton Truck 15 Seater Passenger van 5 ton Crane 88 Seater Bus 20 Ton Mobile crane 400 flat bed trailer with truck Heavy duty Hilti Drills Vibrator Porker JCB Asphalt cutter Paving cutter Qty 0 0 23 0 3 8 2 1 3 3 0 1 0 1 0 1 0 0 47 Hours Status Worked 8 8 8 8 8 8 8 8 8 8 0 8 8 8 8 8 8 8 8

Total

27
Page 1 of 6

AVERAGE CONSULTANT / SUBCONTRACTOR RESOURCES Subcontractor Name TC International SGS Gulf Falcon Baynunah Lab Matrix Ras Al Wadi General Contracting Co LLC 1 1 Engr 1 1 Mech & Elect Design Consultant 1 1 3 Party Inspector
rd

Survey

Finishes

Total 2 2

TOTAL MATERIALS / SHELTERS DELIVERED TO SITE Items Delivery of paving tile blocks Unit Sqmtr Qty

S.N 1

WEEKLY SITE CONSTRUCTION ACTIVITIES Paving of tile laying works in progress

SITE No. 447b

LOCATION

Page 2 of 6

WEEKLEY CONSTRUCTION PERMITS/CONTRACTORs CONCERN S. No Region No of Shelter s Obtain Site Plans Obtain Construction Permits Site Under Progress Site Completed Comments

Abu Dhabi Island

120

00

00

00

Abu Dhabi Suburbs

40

00

00

00

Al Gharbia

80

00

00

00

Al Ain City

80

00

00

00

Eastern Region (Al Ain Suburbs)

40

00

00

00

Page 3 of 6

CONTRACTORs CONCERN & CRITICAL MATTERS

RWS will submit the Extension of time claim and relevant cost as contract unable to complete on or before the completion due to numerous factors.

SUMMARY OF THE SITE PHOTOGRAPHS OF WORK CARRIED FOR THE WEEK:

Laying of paving tile works in progress

Page 4 of 6

Issued By RWS Contractor: Name : Raymond Spence Date : 20.01.2014 Signature:

Received By DOT: Name : Date : Signature: