James Walker RotaBolt Ltd Peartree Business Park Peartree Lane Dudley West Midlands DY2 0UW United Kingdom Tel: +44 (0) 1384 214442
Safety
Throughout all bolt assembly and tightening processes it is essential to follow standard safety procedures and instructions on any equipment. Protective safety clothing should be worn at all times.
Pre-Assembly
Pictured are 8 RotaBolt all thread studs. 1.1/8 diameter by 8! long, 16 nuts and washers. The studs were calibrated at manufacture with 12 tonnes pre-load. NB: RotaBolt studs have been used rather than RotaBolts to give a detailed illustration of correct stud assembly and tightening. When using either RotaBolts 1, 2 or the RotaBolt Vision, the assembly process would be simplified. (see RotaBolt products)
The assembly of stud, nut and washer is inserted into the first flange hole. This is repeated for each RotaBolt stud assembly. A washer and nut is now threaded onto the bottom of the first stud and hand tightened. This is repeated for each RotaBolt stud.
Checking Studs
Before the preliminary and main tightening cycles, each stud is checked again to see that 3 threads are showing above the top of each nut The height can be adjusted by loosening both nuts and turning the stud until the correct height is achieved, before re-tightening by hand. An alternative option is to check by measuring. From the base of the nut to the top of the stud should be 1.3/8. This represents 1 for the nut and 3/8 for three threads (1 thread = 1/8).
Numbering Studs
To ensure that the flange is tightened properly, the studs have to be tightened in a set diagonal sequence.
Each stud is numbered to reflect the order of the sequence to be followed. Each stud number is then chalked onto the outward face of the flange where it can be seen easily.
Calculating Tightening
It is the air gap technology built-in to each fastener that will provide the accurate measurement during the tightening process. The fastener will measure the tension (or clamping force) being achieved across the joint. The RotaBolt studs have been calibrated at manufacture with a pre-load of 12 tonnes to achieve the desired tension across this particular flange. It will be when the RotaCap on top of each RotaBolt stud locks that the correct tension is achieved. However, it is still necessary to estimate the tightening force (torque) that needs to be used, so that the tightening tools can be pre-set.
Preliminary Tightening
To uniformly bed-in the RotaBolt studs, a manual torque wrench (in this case set to 40 Newton Metres) is used to tighten the first stud in the sequence, with a spanner applied to the bottom nut to prevent turning. The same tightening is then done to each stud following the correct numbered sequence.