100% found this document useful (1 vote)
846 views5 pages

23th Floor de Snag Lists

This document lists finishing work that remains to be completed on the 23rd floor of Building QC2. It details snagging items needing attention in areas like lift lobbies, corridors, toilets, store rooms, and shafts. Common issues include touch up painting, flooring repairs, ceiling and lighting fixtures needing adjustment, and ensuring proper sealing and finishes at wall/floor/ceiling junctions. Over 50 individual spaces and items requiring further finishing work are outlined.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
846 views5 pages

23th Floor de Snag Lists

This document lists finishing work that remains to be completed on the 23rd floor of Building QC2. It details snagging items needing attention in areas like lift lobbies, corridors, toilets, store rooms, and shafts. Common issues include touch up painting, flooring repairs, ceiling and lighting fixtures needing adjustment, and ensuring proper sealing and finishes at wall/floor/ceiling junctions. Over 50 individual spaces and items requiring further finishing work are outlined.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Building : QC 2

23th FLOOR DE SNAG LIST (Finishing works only)

Attendee : PMC ANC Sr

Dhiren Barot , Anil Vaniya Arafat,Siji,Chandran Description of balance work Lift lobby 1 Floor excess cable terminal at celing cove finishing arround trap door mirror and ceiling juntion neaten Wall GRC All : Background normal touch up required GRC and mirror junction to be properly treated and cleaned Ceiling Clean ceiling fixtures Neaten finish around ceiling fixtures Lift lobby 2 Floor Wall GRC All : Background normal touch up required neaten swiis brown marble to ceiling juntion GRC and mirror junction to be properly treated and cleaned mirror to ceiling juntion cleaning spot at mirror p7 finishing arround trap door Ceiling Clean ceiling fixtures Neaten finish around ceiling fixtures Sprinkler not flush in ceiling 1.8 Corridor Tile chip to be properly treated and replayed where ever camea balance at ceiling crack tile found at stair case 1. door Finishing required above skirting skirting edge damage at many location skirting not in one line at stir case 1,2 Clean ceiling fixtures Neaten finish around ceiling fixtures Wall paint touch to be done 20mm gap found at nos of 1,2,3,4 metal doors Photograph/Remark

finishing arround metal door 1,2,3,4 finishing arroungd trap door marble chip arround glass door 1, 2.4 Corridor Neaten grout finish at floor tile colour variation at granite floor marble Clean ceiling fixtures Neaten finish around ceiling fixtures chip to be properly treated and cleaned Ceiling fixturce not in one line Service lift lobby grout balance at top of lift architrave to marble juntion skirting short at woodan door architrave at internal side granite floor marble colour variation floor tile offset and colour variation Clean ceiling Ceiling to channel junction gap visible major gap ss architrave to wall marble granite juntion door varnish touchup Dustproof strike not installed Excess gap between timber architrave to wall tile Excess tile cutting above elc. Room finish required at band beam Disabled Toilet chip tile to be treated and cleaned Shadow line groove is uneven - needs to be finished properly Paint incomplete / Blotchy finish Remove paint from ceiling fixtures sqrew hole found at door frame Excess gap between timber architrave to wall tile tile damage at architrave PVC corner guard proper finish balance Elecrical room Remove paint from services Internal shaft - door not installed metal door frame grouting balance Paint touch up blalance Toilet no 1 Vestibule finishing above skirting Clean ceiling fixtures Touch up balance Neaten finish around ceiling fixtures door varnish touchup Excess gap between timber architrave to wall Janitor

3 tile big offset at wall PVC corner guard short at bottom door varnish touchup Incomplete installation of ceiling fixtures Undulation at Ceiling finish ceiling Touch up balance Excess gap between timber architrave to wall tile Male 2 tlie damage at floor PVC corner guard short at bottom 4 location 1 wall tile damage at near urinal 1 tile damage below w,b,c pvc coner guard band Urinal near 1 tile damage door varnish touchup Finishing work incomplete at top of mirror Undulation around trap door Ceiling to wall joint junction groove paint balance Ceiling Cove- finishing work incomplete Clean ceiling fixtures Excess gap between timber architrave to wall tile Toilet paper holder , Hand drier , Soap dispenser , Paper dispenser , Waste paper bin etc are not installed Female 1 tile damage at w.c 2 tile damage at floor pvc corner guard 50mm short at top of tile claddind chip to be properly treated and cleaned improper finish above mirror Ceiling to wall joint junction groove paint balance Finishing work incomplete at top of mirror Ceiling Cove- finishing work incomplete Ceiling undulation door varnish touchup Clean ceiling fixtures Excess gap between timber architrave to wall tile Toilet paper holder , Hand drier , Soap dispenser , Paper dispenser , Waste paper bin etc are not installed Store room 2 nos shaft 12 m2x 12 m2) = 24m2 plaster balance.

Plaster balance at back wall of shaft (partly balance) Floor balance Wall paint touch up balance Romove paint from ceiling services Grouting of metal frame is balance Extra room

Floor balance Excess gap between timber architrave to wall tile Toilet no 2 Vestibule finishing above skirting Clean ceiling fixtures Touch up balance Neaten finish around ceiling fixtures door varnish touchup Excess gap between timber architrave to wall Janitor chip tile treated and cleaned door varnish touchup Incomplete installation of ceiling fixtures Undulation at Ceiling finish ceiling Touch up balance Excess gap between timber architrave to wall tile Male 2 tlie damage at urinal unit near PVC garud damage at 3 location 1 tile damge at w/c near wall Health facoat around grout balance red paint touchup arround puss plate Urinal near 1 tile damage chip tile treated and cleaned door varnish touchup wall tile colour variation Undulation around trap door Ceiling to wall joint junction groove paint balance Ceiling Cove- finishing work incomplete Clean ceiling fixtures pvc corner guard band bottel trap not in alignment wall tile colour variation Excess gap between timber architrave to wall tile Toilet paper holder , Hand drier , Soap dispenser , Paper dispenser , Waste paper bin etc are not installed Female 1 nos tile wall damage 4 nos tile big offset at wall PVC corner guard damage mirror damage at bottom final paint touch up balance floor tile damage at floor trap wall tiledamage at w.c chip to be properly treated and cleaned door architrave damage

improper finish above mirror pvc corner guard band Ceiling to wall joint junction groove paint balance Finishing work incomplete at top of mirror Ceiling Cove- finishing work incomplete Ceiling undulation door varnish touchup Clean ceiling fixtures Excess gap between timber architrave to wall tile Toilet paper holder , Hand drier , Soap dispenser , Paper dispenser , Waste paper bin etc are not installed Store room 2 nos shaft 12 m2x 12 m2) = 24m2 plaster balance.

Plaster balance at back wall of shaft (partly balance) Floor balance Wall paint touch up balance Romove paint from ceiling services Grouting of metal frame is balance Extra room Floor balance Paint balance plaster at back wallof shaft(partly balance) Excess gap between timber architrave to wall tile Shaft floor balance Tenant area Remove plastic from slab soffit Sanding/Grinding required at offset at slab soffit Stair case 1 & 2 shade variation observed

All shaft