1 - Project Management Framework
1 - Project Management Framework
Unit 1
Agenda
Unit 1: Introduction to PMP Examination Preparation Unit 2: Project Management Framework and Standard for Project Management Unit 3: Project Integration Management Unit 4: Project Scope Management Unit 5: Project Time Management Unit 6: Project Cost Management Unit 7: Project Quality Management Unit 8: Project Human resources Management Unit 9: Project Communications Management Unit 10 Project Risk Management Unit 11 11: : Project Procurement Management Unit 12: 12: Project Stakeholder Management Unit 12: 12: Professional Responsibility
Course Objectives
After completing this course, you should be able to:
Make the most of limited study time for taking the PMP exam Become familiar with the exam format and question types Develop a personal study plan Identify personal areas of competency weakness Reinforce knowledge of the tenProject Management Institute (PMI ) Knowledge Areas, five Project Management Process Groups
Unit 3
PM Framework
What is a Project? A project is a temporary endeavor undertaken to create a unique product, service, or result. Temporary
( definite beginning and definite end) Most projects are undertaken to create a lasting outcome.
Unique
( different location, different design, different circumstances, different contractors etc.)
Progressive Elaboration
Continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available.
The application of knowledge, skills, tools and techniques to project activities to meet the project requirements.
Project Team
All the project team members, including the project management team, the project manager and, for some projects, the project sponsor
Areas of Expertise
Project Integration Management Project Scope Management Project Time Management Project Cost Management Project Quality Management Project Human Resources Management Project Communications Management Project Risk Management Project Procurement Management Project Stakeholder Management
Process Group
Initiating
Integration
Develop Project Charter
Planning
Develop Project Management Plan
Executing
Direct & Manage Project Execution
Scope
Plan Scope Management Collect Requirements Define Scope Create WBS Plan Schedule Management Define Activities Sequence Activities Estimate Activity Resource Estimate Activity Duration
Time
Control Schedule
Knowledge Area
Cost Quality HR
Develop Schedule Plan Cost Management Estimate Costs Determine Budget Plan Quality Management Develop HR Plan Perform Quality Assurance Acquire Project Team Develop Project Team Manage Project Team
Control Costs
Control Quality
Comm.
Manage Communications
Control Communication
Risk
Plan Risk Management Identify Risks Perform Qualitative Analysis Perform Quantitative Analysis Plan Risk Responses
Control Risks
Procurement
Plan Procurements
Conduct Procurements
Control Procurements
Triple constraints
Scope
cost
scope
time
Customer satisfaction
Resources
quality
risk
Unlike the ongoing nature of operations, projects are temporary endeavors. Operations Management Examples
Administrative operations, Manufacturing operations, Accounting operations
Program Management
A program is defined as a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.
Portfolio Management
A portfolio is a collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives.
Stakeholders
Stakeholders are persons or organizations (e.g., customers, sponsors, the performing organization, or the public), who are actively involved in the project or whose interests may be positively or negatively affected by the performance or completion of the project.
Organizational Influences
Since projects are typically part of an organization that is larger than the project, the project is influenced by a number of aspects of the larger organizational structure: Organizational process assets
include any or all process related assets, from any or all of the organizations involved in the project that can be used to influence the projects success
Organizational Structure
The structure of the performing organization often constrains the availability of resources.
Organizational Influences
Organizational process assets
Organizational process assets may be grouped into two categories:
Process Interactions
Project Management Process Groups are linked by the objectives they produce, with the results or outcomes of one generally becoming an input to another or is a deliverable of the project
Note: Many of the Inputs, Tools & Techniques, and Outputs for the 42 Project Management processes appear in more than one of the Project Management Process Groups; many of these will be addressed only once in the following Units unless additional information specific to a Process Group needs to be addressed
Questions
2 ) the project managers role during the executing process group of the project can BEST be described as a (an) :
A ) Director. B ) Integrator. C ) Coordinator. D ) leader.
2 ) the project managers role during the executing process group of the project can BEST be described as a (an) :
A ) Director. B ) Integrator. C ) Coordinator. D ) leader.
3 ) Which of the following would be the MOST appropriate thing to do during the planning process group?
A ) work with stakeholders to determine their communication preferences. B ) Determine the initial project organization. C ) refine control limits. D ) complete scope verification.
3 ) Which of the following would be the MOST appropriate thing to do during the planning process group?
A ) work with stakeholders to determine their communication preferences. B ) Determine the initial project organization. C ) refine control limits. D ) complete scope verification.
4 ) The high-level project schedule constraints have just been determined. What project management process group are you in?
4 ) The high-level project schedule constraints have just been determined. What project management process group are you in?
6 ) One of your team members informs you that he does not know which of the many projects he is working on is the most important. Who should determine the priorities among projects in a company?
6 ) One of your team members informs you that he does not know which of the many projects he is working on is the most important. Who should determine the priorities among projects in a company?
9 ) To obtain support for the project throughout the performing organization. Its BEST if the project manager:
A ) Ensure there is a communication management plan. B ) Correlates the need for the project to the organizations strategic plan. C ) Connects the project to the personal objectives of the sponsor. D ) Ensures that the management plan includes the management of the team members.
9 ) To obtain support for the project throughout the performing organization. Its BEST if the project manager:
A ) Ensure there is a communication management plan. B ) Correlates the need for the project to the organizations strategic plan. C ) Connects the project to the personal objectives of the sponsor. D ) Ensures that the management plan includes the management of the team members.
Thank you