Pipeline Design
Pipeline Design
Year4
Group Name
Ahmed Mohamed Ibrahim Suliman 110510 Mohamed Ibrahem Halawa 109895
ID
2|Page
Acknowledgement
All thanks to Dr. Atef Abdel Hadi for solidarity with us to solve all the problems related to the department as head of the Department of Petroleum. We would thank him for his efforts to provide a production module in petroleum engineering.
3|Page
Abstract
Surface production facilities are one of the important modules in petroleum engineering. Pipeline is playing an important role in oil and gas fields because it effect to flow a gas or crude oil in production process. This project contains a pipeline planning and construction, design of pipeline, types of pipeline and the capacity for each type. Also contain problems related to pipelines and appropriate solutions of these problems. There are a part of safety and how to inspection for pipes. The document contains components of pipe line and explanation each component. Dry pipes are important section in design especial in offshore fields. There is a case study on the pipelines and it consist a problem which company faced it in production process and mention the inspection and recommendations thats must be followed.
4|Page
Table of contents
Acknowledgement2 Abstract ....3 Lists of figures..7 Chapter 1: Introduction 8 Chapter 2: Major problems in pipeline and solution...9 2.1: Waxing9 2.2: Corrosion10 2.3: Scaling11 2.4: Heavy crude oil transportation...11 Chapter 3: General design and criteria12 3.1 Fluid Characteristics and Properties12 3.1.1 Facilities Description.13 3.1.2 Flow Control..14 3.1.3 Isolation of the pipes..14 3.1.4 Pressure Monitoring and Relief..14 3.1.5 Start-up...14 3.1.6 Flow Constraints15 3.1.7 Normal Operations.15 3.1.8 Planned and Unplanned Shutdown of Pipeline(s) 15
5|Page
Chapter 4: Pipeline planning and construction.16 4.1 Process of planning and construction16 4.1.1 Procedures which follow in planning and construction..16 4.1.2 Procedures to allow pipelines expands16 4.2 Bending of pipes17 4.2.1 Steel pipe bending methods.18 4.3 Pipeline connections..20 4.3.1 Disadvantages Pipeline Welding.22 Chapter 5: Types of pipe lines and component......24 5.1 Crude oil and natural gas gathering lines...24 5.1.1 Crude oil trunk lines.24 5.2 Natural gas transmission lines ..24 5.3 Pipeline components..24 5.3.1 Transmission pipes line........25 5.3.2 Valves of pipelines..........26 5.3.3 Metering station....26 5.3.4 Pig launcher and receiver.27 5.3.5 Compressor stations27 5.3.6 Control system, Scada.28 Chapter 6: INTEGRATED CONTROL AND SAFETY SYSTEM (ICSS)..29 6.1 Introduction..29 6.2 Process Control System (PCS) 29 6.3 Safety Instrumented System (SIS) ..29 6.4 Fire Detection System (FDS) ..29
6|Page
6.5 Communication System..29 Chapter 7: pipeline drying methods.30 7.1: introduction...30 7.2: Techniques of pipeline drying...30 7.2.1: METHANOL AND GLYCO SWABBING..30 7.2.2: Air drying...31 7.2.3: Vacuum dry...32 7.2.4: Evacuation..32 7.2.5: Evaporation32 7.2.6: final drying.32 Chapter 8: case studying33 8.1: introduction .......33 8.2: Pipeline Design ..33 8.3: Pipeline upgrading..34 8.3.1: UPGRADING BASIS COMPAIRED WITH CURRENT PRODUCTION ..34 8.3.2: Users current daily costs................35 8.4: Recommendations..36 8.5: Pipeline system after upgrading 37 8.5.1: User shipping data...38 8.6: Pipeline maintenance..39 8.7: Inspection of pipeline by intelligent pig.39 8.8: Conclusion...39
References...40
7|Page
List of figures
Figure.1 wax formation in pipeline..9 Figure.2 external pipeline corrosion10 Figure.3 internal pipeline corrosion10 Figure.4 shows scale formation inside pipeline...11 Figure 5: generic pigging facilities..13 Figure: 6 courtesy Tulsa tube bending companies...17 Figure 7: compression bending18 Figure 8: draw bending19 Figure 9: Ram bending19 Figure 10: Courtesy of Tulsa tube bending.20 Figure 11: Long distance pipe..21 Figure 12: Ditching..21 Figure 13: welding...22 Figure 14: Transmission pipe...25 Figure 15: valves..26 Figure 16: Compress station27 Figure 17: SCADA system..28 Figure 18: pipeline routes33 Figure 19: Pipeline system before upgrade..34 Figure 20: current pipeline system...35 Figure 21: pipeline system after upgrade.37 Figure 22: users storage capacity.38
8|Page
Chapter 1: Introduction
As, the Hydrocarbon resources become variable and costly source of power , studying and planning should take place for a perfect project without any loss (human , equipments , resources,etc.).
One of the major planning to keep the hydrocarbon in safe mode and to prevent it from losses and its bad effect on environment, is the planning for a suitable pipeline design that can wise stands the extreme climate ( pressure , temperature ,soil,etc.) , to be safe with the environmental changes and to reduce the project costs. Produced oil, gas and water will be from the well and it will be sent to a Production Facility where gas, oil and water will be separated by a production facility. Pipeline should take its criteria from the fluid moving through it , as each type of fluid got its properties , this will reduces risk and prevent pipeline from sudden cracking or any other risk. The pipeline may be buried, exposure or in the seabed so its very important to take in consideration the media and climate a pipeline is in it.
Safety and insurance is most important part in the pipeline design a pipeline construction should carry valves and its types, should be having a monitoring system in a control room that works only on the pipeline and to be monitoring it all over the time.
9|Page
10 | P a g e
2.2 Corrosion
Corrosion is one of the major problems happened to a pipeline. Hydrocarbons all over the world are not the same they are different in properties and characterization. The main reasons for causing corrosion to pipelines is the presence of carbon dioxide (co2), hydrogen sulphide (H2S) and also the presence of water. (g, 2005) Gas condensate pipeline had mush ability forming corrosion, and to prevent it the PH of the water phase must be increased. This is known as corrosion rate stabilization and this method had used many times ago and had a rate 0.1 mm/year. Also pipeline under sea (subsea pipeline) can easily affected if there is not a good study for the environmental impact such as: temperature, pressure and Ph. And other conditions like: fluid velocity and contents. The pipeline is a very important part in oil and gas production. Its a major way to transport oil and gas. So a proper study and design can minimum and save it from corrosion.figure.3 and figure.4 shows external and internal pipeline corrosion. (g, 2005)
11 | P a g e
2.3 Scaling
As long the Production of hydrocarbons there is impurities as salts and inorganic matters. These salts precipitate cause blocking in the pipeline which will affect the flow of the fluid badly and will decrease it figure.5 shows how can scale precipitate causing decreasing in production types of scales are: CaSO4, BaSO4. Formation of scale have an economical impact as it costs much in removing scales as it can precipitate in valves and safety valves which will cause it to not working properly and some scales are radioactive that it have a special way to be treated with. The removing of scale needs to monitor the quantity and its type, the cleanup process should be quick as possible with taking in consideration the environmental impacts and to prevent forming it again in the future.
Figure.4 shows scale formation inside pipeline 2.4 Heavy crude oil transportation
Crude oil all over the world is not the same, different viscosities are one of these changes. It ranges between 200cp 500 000 Heavy crude oil got high viscosity. However some combines in Canada got the same problem and to solve it they added C4+ hydrocarbons and synthetic crude.
12 | P a g e
Where suitable, the values up will be in the standard conditions (60 F and 1 atmosphere) or operating design conditions (pressure and temperature). The gas condensate will be considered as a hydrocarbon fluid for purposes of the stress analysis. The code of the gas pipeline and related coding within the stress programs as assuming that the contents have a fiddling weight. So the liquid of the pipe line consists of condensates have to be stress analyzed as a B 31.4 pipeline.
13 | P a g e
All the facilities will start at a point which is defined example flange connection or butt weld on the shipping pump discharge the downstream piping from the shipping pumps or from the compressors, including the pressure relief facilities and flow control. Any related block valves and pig launcher and piping are considered part of the subject facilities. Cleaning, gauging, dewatering pigs and in line inspection devices are a required facilities for the pipe line to have as to set and receive both maintenance pigs. The ILI device is such as the smart pigs, geopigs and anomaly detection devices.
All the facilities will end and terminated at the defined point at the tie-in between the pump station one and the Eastern North Slope oil pipeline. All associated VSMs and the pipelines between the two points of the start and end of the facilities is considered as a part of facilities.
14 | P a g e
At the facility of processing, the shipping pumps will be used to pump fluid. This equipment is used to get higher pressure in the pipe line as wanted as to have the target flow rate.
A real time monitoring will be making for the pressure on the discharge of the compressors or the shipping pumps. To prevent the over pressuring the pipe line, the compressors or the shipping pumps will have high pressure shutdowns. A multiple independent pressure control methods will be required on pipelines as to conform the regulations. Where convenient, downstream pipelines backpressure control shall be included. Moreover, a pressure-relief capability must be found in the pipeline, added with drains and vents, where convenient. Liquid pipelines preferred not to have (BOP) bottom of pipe drains, because of the potential of collecting water and freezing.
3.1.5 Start-up
The beginning start-up will be made by the production fluid. A developed to the start up procedures will be made during the design of the system and submitted to the natural resources department. Personnel from DNR may monitor the startup of the pipeline by himself.
15 | P a g e
Engineering and design shall evaluate the monitoring of the flow rates, pressures and temperatures, and how this information will be used by the SCADA, control room and other control and reporting functions.
16 | P a g e
- This is same for under and above ground - Above ground pipelines often used U or loop instead this. - Special joints are obtainable for expands Spigot and bell joints are ready Swivel joints and Slip joints Some of mechanical joints Flexible pipe joint is used for pipeline which has small diameter
18 | P a g e
19 | P a g e
20 | P a g e
21 | P a g e
22 | P a g e
23 | P a g e
Fusion not complete The moving of the welding is very high Surface of the pipe is foul Gas present in welding Insufficient penetration bevel end is not completed The moving of the welding process is very high
24 | P a g e
25 | P a g e
Figure 14: Transmission pipe Pipelines can measure anywhere 6-48 inches in diameter, depending on the function. Some sections in the pipe has small diameter. The diameter for small section may be 0.5 inches. The small section diameter of the pipeline is used in collection and distributions. The major pipelines and pipeline standard in a particular system are generally between 16 and 48 inches in diameter. Sidelong pipelines, which provide natural gas or of a major and is usually between 6 and 16 inches in diameter. Often pipes ranging in major countries between 24 and 36 inches. The actual pipeline itself and so-called pipeline , consists of a strong material, carbon steel and designed to meet the standards set by the American Petroleum Institute (API). On the other hand, some are made of plastic pipe distribution is extremely advanced, and because flexibility needed and the change be easy. The pipes are produced in the transfer of steel mills, which is specialized in some cases to produce pipeline only. There are two methods for production. One of method specialized for small diameter pipes and other for large diameter pipe. The large diameter pipes ranging between 20 to 42 inches in diameter, and is produced pipes of sheet metal which is tucked in the pipe, with the ends welding come together to section of pipe formed. The small diameter pipes can be production easily. This mean that the metal rod is heating by high temperature then punch the hole over the middle of the rod to producing a blank tubes. In all of cases there are test stage been before ship from the steel factory to assure if the pipe has the ability to bear the pressure of the natural gas.
26 | P a g e
Pipe line is additionally secured with a particular covering to guarantee that it doesn't erode once set in the ground. The motivation behind the covering is to secure the pipes from dampness, which causes consumption and rusting. There are various distinctive covering strategies. Previously, pipelines were covered with particular coal tar finish. Today, pipe is regularly ensured with what is regarded as a combination bond epoxy, which gives the channel a recognizable light blue color. Moreover, cathode security is regularly utilized; which is a method of running an electric present through the channel to ward off consumption and rusting.
5.3.2 Valves
27 | P a g e
28 | P a g e
Figure 17: SCADA system Supervisory control and data acquisition as known Scada has some of functions. The system is commonly developing communications systems that take measurements and gather data along the pipeline to transmit it to central control station. The temperature and the operation pressure are using to evaluate the pipes condition at same time. Scada system has much other function such as able to control some of equipments remotely. This feature is very useful to engineers because they have the ability to control on pipelines flow through it.
29 | P a g e
30 | P a g e
31 | P a g e
7.2.2: AIRDRYNG
It is a wide range term that covers many activities from blowing air through the line to the run of hundreds of pigs through the line. There are a technique which is developed and patented by pipeline dehydrators Inc. This technique developed from drying of carbon dioxide lines and high purity petrochemicals. It is suitable for onshore lines that could be sectional dried. It also has the advantage that it clean the line optionally to standard which is higher than any other drying techniques. This technique has basis which is running a series of light which has 2Ib/ polyurethane foam swabs which is through the pipeline with super dry air that has dew point of -90F. The pigs are launched on regular basis so. there is many pigs at the pipeline at any time. There are special low pressure, launchers, quick action that are used, that allow the launching an loading of a swab in less than a minute and also it has no disruption to the air flow. The swab absorb large quantity of water initially and also it ensure that water at the pipeline is spreading out in thin film, and the evaporation into the dry air stream is facilitated. The pipeline will be dried from the end of the launch and progress gradually down the pipeline. Also to be sure that the pressure of air is above the atmospheric pressure, pigs are received in a bottomless receiver. As the pressure is low, the air could absorb more water vapor and the pipeline is getting quicker dried.
The main disadvantages of the technique of the air drying are: 1) The length of the section that has to be dried is limited and it depends on the diameter. 2) It is required for the equipment a large area on large diameter lines. 3) For running compressors, it requires the consuming of large amount of fuel. 4) This technique is not well suited to offshore pipelines.
32 | P a g e
7.2.4 Evacuation
The pressure of the pipeline is drawn down from the atmospheric pressure to the saturated vapor pressure, and according to the ambient pipeline temperature there will be a variation and this is at the first phase. During this phase, most of the air is removed from the pipeline. During the first phase also, there is a test that will be done during the first phase to check for leaks that must be repaired.
7.2.5 Evaporation:
Water would start evaporation and maintain the pressure equilibrium, as the pressure reach the saturated vapor pressure. During the trying of the pressure to fall, also water evaporates and the pressures stay constant. So, the vacuum pump sucked out this vapor of the line, and there is more water that evaporates to take its place, and the continue of this process will last until all the free water evaporated from the pipeline.
33 | P a g e
Pumping Station at Meleiha: 3 pumps Connected in series ( In / Out pressure : 85/880 psi) Receiving station at El Hamra: 2 meter runs (Capacity = 40,000 BPD Each) Five Tie-In Points along the P/L starting from Meleiha side at (@ 28 Km, @ 55 Km, @ 83 Km, @ 111 Km, @ 138 Km)
34 | P a g e
8.3.1: UPGRADING BASIS COMPAIRED WITH CURRENT PRODUCTION Users 1998 design basing Current production AGIBA 23,000 28,000 KHALDA 25000 43000 SALAM 3000 12000 TAREK 3000 10000 SUMPETCO 5000 27000 BAPETCO 55000 20000 TOTAL 114000 14000
35 | P a g e
+/- 28000 BPD +/- 92000 BPD +/- 20000 BPD +/- 140000BPD
36 | P a g e
8.4: Recommendations
Short Term: 1- Upgrade Khalda crude oil shipping pumps to be capable for commingle shipping with Salam & users (not done). 2- Increasing shipping hrs to be 23.5 hrs/day instead of 23 hrs/day. 3- Switch back Faras Shipping to be through Bapetco pL 12 to increase window for khalda. Done. 4- Diverted raml shipping to dabaa line 12, done. 5- Using drag reducer to increasing flow rate, done. LONG TERM STUDY THE FEASIBILITY OF THE FOLLOWING OPTIONS: 1- Up grading electrical motor of 3 old pumps at meleiha. Under progress, end time may 09. 2- Install forth booster pump at PK 83 pumping station under study. 3- In any of the above options metering skid at El Hamra Terminal is required up grading. Under progress . 4- Duplication Meleiha Elhamra pipeline. 5- New booster pumping station.
37 | P a g e
38 | P a g e
5 2 3 4 4 3 3 9 2 --
135,000 32,000 22,000 9,400 200,000 45,000 45,000 173,000 160,000 821,400
13.00 18.00 14.00 18.00 23.5 8.00 8.00 9.00 11.00 32.50
8.8: Conclusion
The company is succeeding to achieve the pipeline upgrading and this is a great progress. They upgrade the diameter of impellers and install bigger electric motor. Construct midpoint station. Finally construct 2 loops until the Flow is divided into 2 loops to reduction the loading on the on loop.
40 | P a g e
References
Bibliography
Andrew J Barden, M. D. (1996). Evaluation of pipeline-drying techniques. g, R. o. (2005). Controlling Internal Corrosion in Oil and Gas Pipelines. Wax.and.Waxy.Crude. (1993). Retrieved 12 11, 2013, from Wax.and.Waxy.Crude: http://tigger.uic.edu/~mansoori/Wax.and.Waxy.Crude_html
41 | P a g e
42 | P a g e