Building Works - Dismantaling & Demolishing
Building Works - Dismantaling & Demolishing
SH:14/DISMANTLING_DEMOLISH
For dismantling of structures, which remain submerged in water, the cost may be enhanced by 50%. If site condition warrant lowering of water level to facilitate dismantling, the cost may be enhanced by additional 25%. Dismantling of utilities like water supply lines, electric and telephone lines is required to be done under the supervision of concerned departments with prior information to the users. The dismantled materials should be examined and a realistic assessment and provision should be made after due process for the salvage value for such materials, can be utilised for works or auctioned.
Description Demolishing lime concrete manually / by mechanical means including disposal of material with all lifts and upto 50 m lead etc. complete as per direction of the Engineer- in-charge. Demolishing cement concrete manually / by mechanical means including disposal of material with all lifts and upto 50 m lead etc. complete as per direction of the Engineer- in-charge:1 : 3 : 6 or leaner mix. 1 : 2 : 4 or richer mix. Demolishing reinforced cement concrete manually / by mechanical means including stacking of steel bars properly and disposal of unserviceable material with all lifts and upto 50 m lead etc. complete as per direction of the Engineer- in-charge.
Unit
Rate
Cum.
R 136.70
14.2
Cum Cum
R 305.50 R 460.40
Cum
R 583.20
14.4
Demolishing reinforced brick work manually / by mechanical means including stacking of steel bars, bricks/ brick slump properly and disposal of unserviceable material with all lifts and upto 50 m lead etc. complete as per direction of the Engineer- incharge. Extra for cutting reinforcement in RCC or R.B. work manually / by mechanical means (payment to made on the cross sectional area of RCC or R.B. work) etc. complete as per direction of the Engineer- in-charge.
Cum
R 435.00
14.5
Sqm.
R 257.80
\\vboxsrv\conversion_tmp\scratch_6\218141169.xls.ms_office/Schedule
SH:14-Page:2
SH:14/DISMANTLING_DEMOLISH Code No. 14.6 Description Extra for scrapping, cleaning and straightening reinforcement obtained from RCC or R.B. work etc. complete as per direction of the Engineer- in-charge. Unit Rate
Kg.
R 1.30
14.7
Demolishing brick work including stacking of serviceable materials and disposal of unserviceable materials with all lifts and upto a lead of 50m etc. complete as per direction of the Engineer- in-charge:In mud mortar. In lime mortar. In cement mortar. Removing mortar from brick and cleaning bricks including stacking bricks and disposal rubbish with all lifts and upto a lead of 50 m etc. complete as per direction of the Engineer- in-charge:In mud mortar. In lime mortar. In cement mortar. Dismantling doors, windows and clerestory windows ( steel or wood ) shutter including chowkhats, architrave, hold fasts etc. complete including stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50m etc. complete as per direction of the Engineer- in-charge:Of area 3 sqm and below. Of area beyond 3 sqm. Dismantling doors, windows and clerestory windows ( steel or wood ) shutter including stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50m etc. complete as per direction of the Engineer- in-charge:Each Each R 36.00 R 46.00 Each Each R 83.60 R 113.20 Each Each Each R 0.80 R 0.90 R 1.10 Cum Cum Cum R 117.00 R 139.40 R 335.60
\\vboxsrv\conversion_tmp\scratch_6\218141169.xls.ms_office/Schedule
SH:14-Page:3
SH:14/DISMANTLING_DEMOLISH Code No. 14.11 Description Dismantling wood work in frames, trusses, purlins, rafters, etc. upto 10m span and 5m height including stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50 m etc. complete as per direction of the Engineer- incharge:Mtr. Cum. R 5.00 R 712.90 Unit Rate
14.11.1 Of sectional area 40 sq cm and below. 14.11.2 Of sectional area beyond 40 sq cm. 14.12 Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of 1 m or part thereof beyond 10 m etc. complete as per direction of the Engineer- in-charge:-
14.12.1 Of sectional area 40 sq cm and below. 14.12.2 Of sectional area beyond 40 sq cm.
R 0.40 R 96.10
14.13
Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of 1 m or part thereof beyond 5 m etc. complete as per direction of the Engineer- in-charge:Metre/ metre height Cum/ metre height
14.13.1 Of sectional area 40 sq cm and below. 14.13.2 Of sectional area beyond 40 sq cm.
R 0.70 R 178.80
14.14
Dismantling steel work in single section including dismembering and stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50 m etc.complete as per direction of the Engineer- in-charge:Kg. Kg. R 0.80 R 0.60
14.14.1 R.S Joists. 14.14.2 Channels, angles, tees and flats. 14.15 Dismantling steel work in built up section in channels, angles, tees, flats including all gusset plates, bolts, nuts, cutting rivets, welding including dismembering and stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50 m etc. complete as per direction of the Engineer- incharge.
Kg.
R 1.50
\\vboxsrv\conversion_tmp\scratch_6\218141169.xls.ms_office/Schedule
SH:14-Page:4
SH:14/DISMANTLING_DEMOLISH Code No. 14.16 Description Dismantling steel work in built up section manually / mechanically without dismembering and stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50 m etc. complete as per direction of the Engineer- in-charge. Unit Rate
Kg.
R 1.20
14.17
Dismantling steel work in frames, trusses, purlins, and rafters etc. upto 10 m span and 5 m height including dismembering and stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50 m etc. complete as per direction of the Engineer- in-charge.
Kg.
R 1.60
14.18
Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional span of 1 m or part thereof beyond 10 m etc. complete as per direction of the Engineer- in-charge. Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional height of 1 m or part thereof beyond 5 m etc. complete as per direction of the Engineer- in-charge. Dismantling dry brick pitching in floors, drains etc. including stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50 m etc.complete as per direction of the Engineer- in-charge. Dismantling GS sheet roofing including ridges, hips, valleys, gutters wind ties etc. including dismembering and stacking of serviceable materials and unserviceable materials separately with all lifts and upto a lead of 50 m etc.complete as per direction of the Engineer- in-charge.
R 0.20
14.19
R 0.40
14.2
Cum.
R 211.80
14.21
Sqm.
R 26.30
14.22
Dismantling old plaster or pointing, raking out joints, cleaning and preparing the surface for re-plastering or re-pointing including disposal of rubbish to the dumping ground with all leads and lifts etc.complete as per direction of the Engineer- in-charge.
Sqm.
R 14.20
14.23
Dismantling old glass panes from wooden / steel structures including stacking of serviceable materials and disposal of rubbish and unserviceable materials to the dumping ground with all leads and lifts etc.complete as per direction of the Engineer- incharge. 3.0 6.30
Sqm.
R 7.50
\\vboxsrv\conversion_tmp\scratch_6\218141169.xls.ms_office/Schedule
SH:14-Page:5