Introduction To Panel Caving
Introduction To Panel Caving
Agenda
Context why the interest in caving How block caving works and key technical considerations Risks Value drivers
1 March 2011
1 March 2011
1 March 2011
1 March 2011
Why Caving?
Use of gravity to break the rock (instead of explosives), thus low operating cost compared with other underground methods High production rates can be achieved allowing economies of scale Allows high degree of mechanization Safe However High initial capital costs Conceptually simple let gravity do the work - but technically very challenging Requires large design effort; high quality construction; and rigorously managed operations
1 March 2011 BMO Capital Markets 2011 Global Metals & Mining Conference 6
1 March 2011
160000
Palabora Henderson Homestake - S Dakota
140000
1000m
Magma
Western Deeps
Kidd Creek
Open pits
2000m
Super caves
3000m
4000m
San Manuel Climax Kiruna Malmberget Premier Kidd Creek Salvador Henderson Andina
Conventional underground
1900
1920
1940
1960
1980
2000
2020
2040
YEAR
1 March 2011 BMO Capital Markets 2011 Global Metals & Mining Conference
DOZ
Henderson
Oyu Tolgoi
Resolution
Note: size is for illustrative purpose only and has been sourced from published information
BMO Capital Markets 2011 Global Metals & Mining Conference 10
1 March 2011
1 March 2011
Rio Tinto Planned Currently operating Closed mines BMO Capital Markets 2011 Global Metals & Mining Conference
11
Agenda
Context why the interest in caving How block caving works and key technical considerations Risks Value drivers
1 March 2011
13
Method Resuing Cut and Fill Shrinkage Room and Pillar Open Stoping Sub-level Caving Block Caving
1 March 2011
Avg. T / Day 50 - 100+ 500 1,500 200 - 800 1,500 10,000 1,500 25,000 1,500 50,000 10,000 100,000
14
Orebody
Draw bells
Production tunnels
Haulage system
1 March 2011
16
Caving Process
20
Progressive spalling
Block cave mining is based on the principle that, once a sufficiently large area of a block has been undercut by drilling and blasting, the overlying block of ore will start to cave under the influence of gravity. The process will continue until caving propagates through the entire block to surface or to the open pit above
25
35
45
Caved Ground
Undercut
$
CAVEDYNAMICS SOURCESOF UNCERTAINTY
Vyazmensky 2007
TIME CAVEMANAGEMENT
1 March 2011 BMO Capital Markets 2011 Global Metals & Mining Conference 19
1 March 2011
20
1 March 2011
cave fragmentation
21
1 March 2011
22
Geometry of drawbells
DRAWBELLS
1 March 2011
23
1 March 2011
24
Impacts of Fragmentation
PRODUCTIVITY
SECONDARY BLASTING
VALUE AT RISK
1 March 2011 BMO Capital Markets 2011 Global Metals & Mining Conference 25
Primary Fragmentation
Secondary fragmentation
HoD
FlowInterruptionIndex (events/tonsx1000)
Secondary Fragmentation
1 March 2011
26
1 March 2011
27
Primary fragmentation
expansion void
Secondary fragmentation
f(fragment size)
Fine material
Coarse material
IDZ
1 March 2011
28
Cave Flow
Zone of Loosening
(blocks that were displaced vertically at least once)
Waste
waste
waste
ore
ore
ore
HoD
WASTE ROCK
WASTE ENTRY
cylindrical IEZ
EXTRACTED ORE
elliptical or frustum shaped IEZ; height equivalent to~100-200 mean fragment size
ORE BODY
$
WASTE ROCK
WASTE ROCK
TIME
REPEAT
1 March 2011 BMO Capital Markets 2011 Global Metals & Mining Conference 31
ORE BODY
$
WASTE ROCK
WASTE ROCK
TIME
1 March 2011
32
Undercutting
UNCAVED ORE
Rings to be blasted
CAVED ORE
1 March 2011
33
1 March 2011
34
Agenda
Context why the interest in caving How block caving works and key technical considerations Risks Value drivers
1 March 2011
36
1 March 2011
37
Initiation point close to surface Substantial information No geotechnical constraints Ore drilled and typically sampled as part of mining process detailed knowledge for short term planning Initiation point remote from surface Limited information Substantial geotechnical constraints
1 March 2011
38
Scale
1 March 2011
39
Escondida, Chile
IOZ
DOZ
Courtesy of PTFI
1 March 2011 BMO Capital Markets 2011 Global Metals & Mining Conference 40
Control
OPENPITMINING CAVEMINING
uncertainty
limitedcontrol
Risk
Characterisation the resource; understanding the size of the prize Design resource to reserve; time for imagination Construction the big spend and first taste of reality Operation recovery and payback
Paper (Design) Value vs. Actual Value
1,5 m
CONCRETE DAMAGE
CONCRETE DAMAGE
1 March 2011
42
1 March 2011
Mine infrastructure
Agenda
Context why the interest in caving How block caving works and key technical considerations Risks Value drivers
1 March 2011
44
Value is a function of Run of Mine (ROM) grade which is an outcome of three interrelated factors
1. The resource grade; a measure of the metal that is in the ground 2. The reserve grade, a measure of the effectiveness of the design 3. The recovered grade, a measure of how the cave is managed and cave dynamics
1 March 2011
45
Indicative Costs
Capital
The capital and operating costs shown are relative and provide an indication of the spread. Both green field and brown field projects are included as are operations where access is via shaft or by decline. They were developed simply by normalising to lowest cost producers in terms of capital and operating cost.
Operating
1 March 2011
46
1 March 2011
47
Realising Value
New generation of Cave Mines represent a step change in the size of operations require investment levels of $2 to 10 billion and require significant time to achieve operating targets
There are value drivers common to any mining project: 1. Costs (capital and operating) 2. Revenue 3. Time
1 March 2011 BMO Capital Markets 2011 Global Metals & Mining Conference 48
Intelligent Mining Autonomous equipment Block cave operations well suited to concept of intelligent mining; real time information Operating efficiencies
1 March 2011
49
1 March 2011
50
Energy (Distance Traveled) Reliable Ore Flow Predictable Fragmentation (+ grade) Ore Transport and Sizing
1 March 2011
51
Thank You
Allan Moss, General manager Rio Tinto Copper Projects