Fixture Design
Fixture Design
Phase I Report
Phase I Report
Acknowledgements
We express our sincere gratitude to the Tinker Air Force base, and particularly to Mr. Gary Stroud for providing this wonderful opportunity to study Fixture Design at Tinker and for creating a wonderful work environment. This project has allowed us to learn much about Fixtures as well as the facilities afforded by Tinker in manufacturing processing. We extend our sincere appreciation to Mr. Steve Moore and Mr. Pat Grissom of CSD, Mr. Bob Ochs and Mr. Robert Winters of Design, and Ms. Dalia Lopez and Mr. Hank Schank of Engine Augmenters for spending several hours of their time to assist us with this project. We also thank Mr. Bill Crane of Altec for all his efforts in expediting this project. Last but not least, we acknowledge the support of Carl Hatlelid, Tom Landers and John Nazemetz of CASI and Wayne Jones of the Tinker AFB in facilitating this project.
Table of Contents
Project Summary Introduction Acknowledgments Table of Contents Consolidated Report Background Different Modules of Manual Hydraulic Chucks Design of Jigs and Fixtures Dos/ Donts Practices Fixture Design Manual Cost Analysis Conclusions 1 1 2 2 3 3 4 5 6 7 8 13
Phase I Report
Phase I Report
HYDRAULIC CHUCKS: In general, chuck is a device that holds a part on its outer or inner surface. Typically, wherever the part has to be rotated in a lathe, the holding device is a chuck. The chuck may also be a tool holding chuck in other situations. In this section information regarding basic features of chucks, different types of chucks, improvements in the design of chucks, various applications of chucks and different manufacturers of chucks are collected and compiled for ready reference. This module was principally developed at the request of the sponsor. Tool holding chucks: Concentricity, holding force, presetting, vibrations and rigidity are the basic selection criteria when going for a new tool holding device. The different types of chucks collet chuck, hydraulic chuck, shrunk fit chuck, hydro mechanical chuck - are described in this section with their relative accuracies, advantages and disadvantages. The advantages of using a hydraulic chuck over collet-type chuck is that it does not have as many moving parts to hold the tool, and the pressure is applied uniformly throughout the gripping area. Hydraulic chucks provide, !" Lesser vibration !" Easy pre-setting !" Uniform pressure throughout the tool shank !" Access to use different sleeves to accommodate tools of different sizes.
Phase I Report
Phase I Report
The information about the basic principles to be followed and the positioning of the work piece and the cutting tool are collected in this section. The correct usage and provision of locators, clamps, supports, hinges and cutter action, and proper alignment contact surfaces, cutting forces are specified with examples in this section. Verification of the information available in this section when a jig or fixture is designed will reduce the deviations from the principles to be followed. The information provided in this section shows both the correct and incorrect arrangement so that the incorrect one can be avoided. Sample Fixtures (Animations) In this module of the manual, animations of the arrangement of several jigs and fixtures are shown. The seven animations prepared explain the arrangement of the work holding devices for different types of operation. This will facilitate the designer to observe the arrangement and effect corrections in the existing design.
6
Phase I Report
The last two bullets are 3 actual fixtures developed by CSD engineers, Steve Moore and Pat Grissom. DESIGN MANUAL This module of the project is textual and is a more detailed write-up of the second module. It helps designing from concept to prototype. In the case of jigs and fixtures, the initial stage is one of planning while the finishing stage is the practical workholder proofof-concept. Before designing a fixture the practical applicability of the fixture should be considered. It is not meaningful to design a fixture which cannot be manufactured with the available machines or which cannot be used for the practical working environment. The material to be used, rigidity of the fixture, upkeep of fixture, salvageability and the safety of the operator in using the fixture has to be each considered before designing the fixture. Information regarding all these points is explained in detail. Material behavior is important in the sense that the working conditions must be fulfilled by the chosen materials. Mechanical stresses, cycling and heat are some of the dynamics under which the fixture operates. The material has to be chosen depending upon the requirement. The manufacturing processes by which the fixtures are made also differ depending upon the working conditions. The three broad classifications are welding structure, built-up structure and cast structure, out of which the welding structure is the most material saving process while the built-up structure is the most modular and flexible. Similarly, the operating mechanism should also be determined by the working conditions and the resources being utilized. Locators, supports, clamps, cutter action on the work, set blocks and chip clearance are some of the key concepts in the design of jigs and fixtures. Standardization is the economical factor to be considered while designing which helps to re-use the standard parts even after the device becomes obsolete. The information regarding all the above factors is detailed in the design manual that could be used as a ready reference to follow. The various types of Jigs, jig bushes and fixtures are also described in this part.
Phase I Report
Phase I Report
Re-design.
Conforms Yes / No
No
No
Yes Manufacture
No
End
Phase I Report
15% 10%
Testing cost Manufacturing cost Material cost
Design Cost
5% 70%
Consider the production of a fixture from its concept to prototype. The following Gantt chart shows the time spent on different steps in fixture design.
Re-work (Design error) Re-work (Mfg error)
Prototype testing Manufacturing Design Analysis Fixture Design Part Analysis
Time (cost)
10
Phase I Report
= $2,135,000.00
Consider there is 30 % non-conformance of fixtures. The production lines get overloaded by at least 40%. And the increase in lead-time increases the cost (due to idle aircrafts) by 30 %. 30% crafts stay idle for 30 more days Cost of non-conformance (man power) Cost of overload on other machinery (40% of total cost) Total Cost of non conformance Total cost incurred for batch in 2 months = $600,000.00 = $270,000.00 = $854,000.00 = $ 1,724,000.00 = $3,859,000.00 + +
11
Phase I Report
= $1,990,150.00
Cost analysis
4,000,000.00 3,000,000.00 1,724,000.00 282,150.00 988,000.00 720,000.00 2 282,150.00 988,000.00 720,000.00
Cost $
Thus total saving = $3,859,000.00 - $1,990,150.00 (Over span of 2 months) = $1,868,850.00 Annual saving = $11,213,100.00 This illustrates the potential savings that a proper set of guidelines can provide.
12
Phase I Report
13