The document provides specifications for a winch and mooring system for a medium size aerostat. It describes the key subsystems of the system including a fabricated structure, docking and tether routing units, winch assemblies, hydraulic system, electrical and electronic subsystem, and miscellaneous subsystem. The system will use a capstan type hydraulic winch and hard nose type mooring and will have the capability to operate in both deployed and transportable conditions on a trailer compatible with a TATA LPS 4018 vehicle. The system is required to meet various performance specifications related to winding speeds, brake capacities, operational wind speeds, and data logging/storage capabilities.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
373 views
Specification Adrde 210212
The document provides specifications for a winch and mooring system for a medium size aerostat. It describes the key subsystems of the system including a fabricated structure, docking and tether routing units, winch assemblies, hydraulic system, electrical and electronic subsystem, and miscellaneous subsystem. The system will use a capstan type hydraulic winch and hard nose type mooring and will have the capability to operate in both deployed and transportable conditions on a trailer compatible with a TATA LPS 4018 vehicle. The system is required to meet various performance specifications related to winding speeds, brake capacities, operational wind speeds, and data logging/storage capabilities.
AERIAL DELIVERY RESEARCH & DEVELOPMENT ESTABLISHMENT DEFENCE RESEARCH & DEVELOPMENT ORGANISATION MINISTRY OF DEFENCE, GOVERNMENT OF INDIA P. B NO. 51, STATION ROAD, AGRA CANTT 282 001
Information in this document is property of Aerial Delivery Research & Development Establishment. Unless otherwise specified, no part of this document may be reproduced or utilized in any form or by any means, electronic or mechanical, including photocopying and microfilm, without permission in writing from Director, Aerial Delivery Research & Development Establishment, Agra.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 2
TABLE OF CONTENTS
Chapter No. Chapter name Page no. 1.0 Introduction 3 2.0 System Description 7 3.0 System Specification/Requirements 11 4.0 Subsystem Description 21 5.0 Scope of work 58 6.0 Inspection and Acceptance Procedures 59 7.0 Painting 59 8.0 Integration, Installation and commissioning 60 9.0 Materials for Fabrication/integration/installation 60 10.0 Quality control 61 11.0 Perfection of work 62 12.0 Safety requirements 63 13.0 Tools for maintenance 64 14.0 Jigs and fixtures 64 15.0 Deliverables 64 16.0 Time schedule 65 17.0 Guarantee/Warranty 66 18.0 Product Support 66 19.0 Presentation 66 20.0 Compliance sheet 66
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 3
1.0 Introduction
Winching and Mooring system is one of the major subsystems of an Aerostat. It has two parts, one is winch, which is required for raising, lowering & holding the balloon at a desired height, Second a mooring system on which the balloon is anchored when not in flight. The system is required to be fabricated for medium size of Aerostat. Mooring system must have freedom of wind-vaning.
This system consists of a winch system, which is required for hoisting & de-hosting of the aerostat under controlled conditions, to a desired attitude and/or making necessary operational adjustments to the aerostat at different altitude during flight. Mooring System is used to moor the aerostat at ground in case of high wind conditions or maintenance / integration purpose. Mooring is an important stage of the aerostat launch program. For the integration of the equipment on the balloon, its maintenance and several other reasons, aerostat needs to be brought down on the ground and moored in such a way so as the stresses on the aerostat structure are minimal in the moored condition.
The complete system has to be mounted on the trailer through the slewing bearing. This slewing bearing will provide the wind vaning of the system. However trailer will provide the relocatibility of the system. The trailer should be provided keeping in the view that it should be compatible with the TATA LPS 4018.
The configuration of this system is shown at figure no 1 in Deployed condition and figure no 2 in transportable condition. The winch and mooring system with balloon in moored condition and with flying condition is shown in the figure 3 & 4 respectively.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 4
Figure 1: Winch and mooring system in deployed condition Figure 2: Winch and mooring system in transportable condition
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 5
Figure 3: Winch and mooring system with balloon in moored condition
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 6
Figure 4: Winch and mooring system with balloon in flying condition
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 7
2.0 System Description
The winch and mooring system provides platform to hold the balloon for the fitment of the payload to it and maintenance requirements of the Aerostat. It is also used for launching and recovery of the balloon. The winching system is used for inhauling and outhauling of the balloon at required height with required speed. The various subsystems of the winch and mooring system are shown in the system tree (figure no 05) and in the pictorial view in figure no. 06 & 07. One similar winch and mooring system is available with ADRDE. All the parts have been assembled together to form a single unit from which aerostat launch, recovery, mooring, maintenance and controlling can be done. The mooring tower along with boom, winch enclosure and flying sheave rotates about the vertical axis passing through the center of the main bearing. A Double capstan type hydraulic winch system is chosen for the above configuration with spooler for uniform winding of tether. A hard nose with nose probe and a latch assembly is chosen for mooring system. The entire winch and mooring system will be mounted on the trailer to make the system relocatable i.e. it will be transportable in a stowed condition. This will be achieved by incorporating folding side arms for the close haul winches and a foldable tower for the cradle and latch assembly. The winch assembly and hydraulic power pack are enclosed inside a shelter (enclosure), which is mounted over the boom. This enclose is an air-conditioned chamber. The prime mover for towing the trailer mounted winch and mooring system is TATA LPS 4018. The winch and mooring system consists of following subsystems: I) Fabricated Structure II) Docking and tether routing units III) Winch assemblies IV) Hydraulic system V) Electrical and electronic subsystem VI) Miscellaneous subsystem
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 8
Figure 5: System tree
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 9
Figure 6: Various subsystems of Winch and mooring system
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 10
Figure 7: Various subsystems of Winch and mooring system
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 11
3.0 System Specifications/Requirements: 3.1 Brief Specification: S. No. Parameters Value i Winch Type Capstan type hydraulic ii Mooring type Hard nose type, wind vanning iii Dimension in transportable condition As per given in the figure 8 iv Relocatibility Mounted on trailer and compatible with TATA LPS 4018 v Max. Winding/unwinding speed of main tether winch 75 m/min at 34000 N vi Max. winding/unwinding speed of close haul/nose line winch 30 m/min at 1500O N vii Brake holding capacity 100000 N viii Max. winding/unwinding speed in syncro mode for all winches 30 m/min ix Survival wind speed (when moored) 70 knots x Operational wind speed (when parked at altitude) 50 knots xi Operation a) Through joystick, through lever, Manual cranking etc. b) System should also be operated through remote control panel by Radio Frequency command system xii Stow drum Storage Capacity 1500m of tether xiii Tether Fiber optic, power conducting, lightning braid having diameter 180.5 mm xiv FORJ At winch drum xv Material Marine grade anti-corrosive steel xvi Data logging facility Record to store the various data xvii Storage Rugged storage device should be provided for storage of data for minimum 15 Days xviii EMI/EMC All electrical/electronic equipments must be EMI/EMC protected xix Portability of data It should be possible to transfer data from archive media into suitable removable hard discs/CDs/zip drives etc.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 12
Fig 8: Loads coming on Winch and Mooring Platform 1 2 . 7
m
12.9 m F 2
F 1
38 m 1 2 . 7
m
18.8 m 23.6 m 19.7 m C P C G Confluence Point W C B F 3
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 13
These dimensions are indicative value only the final dimension will be finalised during design review. Figure 9: Winch and mooring system dimension in folded condition H e i g h t
=
4 m
Length = 14m Width = 2.5m
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 14
3.2 Detail Specification: i) The Winch and mooring system is required to hold the medium size Aerostat. The brief dimension of the Aerostat has been given at the Figure no. 9. ii) Mooring structure should be made in foldable modules to enhance the ease in transportation. The dimension of the winch and mooring system in the folded condition should not be more than 14 m (length) X 2.5 m (width) X 3.7m (height). The folding/unfolding operation should be mechanised (preferably hydraulically/electro- mechanical). The suitable locking arrangements should be provided during transportation and actual operational condition. iii) The winch is required to be capstan type with level winding arrangement (spooler) for uniform winding of tether, Single tether with hydraulic as well as electronic control. iv) Mooring system should be turn table type, hard nose with nose cradle and a latch assembly. Mooring system must have freedom of wind - vaning. v) A pedestal hydraulic power drive is required to orient the winch and mooring system as per the requirement of the Aerostat. vi) The winch should be capable of hoisting and de hoisting the Aerostat at a tether tension of 34000 N at winding speed of 75 m/min. vii) The speed of the winch and mooring system should be varied from 0 to 75 m/min. viii) The Nose line winch and close haul winches should be designed to operate at 30 m/min at a load of 15000 N. However it should withstand a load of 30000 N.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 15
ix) perating limits: The system should be capable of withstanding the following conditions in different orientations: (a) 70 Knots (36 m/s) wind speed when the balloon is moored on the structure and faces into the wind. (b) Side force corresponding to 20 knots (10.29 m/s) wind speed, which acts in case the bearing fails to rotate. x) Winch and mooring system is capable of withstanding 100000 N acting at the flying sheave. The structure, flying sheave, Pulleys etc should be design to withstand that much of load. xi) The whole structure should able to rotate freely at a torque value 1200 Nm or less. xii) The brake holding capacity of the winch system should be 100 kN. It means that when this much of load will come on the tether, the tether should not unwind itself from the winding drum. xiii) All Aerostat program e.g. launching, recovery, mooring, controlling etc can be done should be done at single place i.e. at the operator cabin inside the winch enclosure. Provision should be made so that operator can communicate with other crew members. xiv) A provision should be made in the cradle and latch assembly for automatic release of nose probe from the cradle. xv) Provision should be made to digital display and record the various parameters e.g. winding/unwinding speed of the main winch, tether tension value before and after the capstan, tension value of the nose line and close haul lines, Tether released out from the drum and tether storage length, Temperature of hydraulic oil, level of the hydraulic oil in the reservoir etc.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 16
xvi) Data logging facility should be provided to record the data for minimum Fifteen (15) days. A rugged storage data device should be provided along with the system. xvii) A portable data storage and analysis device and a online rugged data streaming device should also be provided for analysis of the store data. xviii) All operation should be done by joystick provided at operator cabin. However provision should also be made to operate the system through hydraulic lever through Proportional control valve for redundancy. In case power failure the manual operation should also be provided. xix) The operator can also operate the system form the ground through remote/operator panel, instead of sitting in the operating cabin if the need arises. A Radio Frequency link in this regard should also be available. xx) Pneumatic Power Pack and airbag is controlled and operated from the controller cabin. xxi) The winch should be automatically stop the operation when the seventh (7 th ) turn of the lowest layer of the tether remains on the stow drum. xxii) Synchronization of two close haul winches, nose line winch, capstan and stow drum will be made. This means capstan, stow drum, two close haul winch and nose line winch should be operated simultaneously at same speed. The maximum winding/unwinding speed in this case will be 30 m/min xxiii) The winch and mooring should be suitable for inflation and deflation of the Aerostat when moored at the mooring structure.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 17
xxiv) All the items should be used for the fabrication of the winch and mooring system should be of flameproof & explosion proof quality. xxv) All fasteners e.g. nuts and bolts, studs etc used in the assembly should be of suitable strength and protection with corrosion. xxvi) The system should be transportable by road in folded conditions. xxvii) Access ladder should be provided to access the operator cabin and the roof of the winch enclosure. Access ladder should have proper side and overhead protection. xxviii) The hydraulic oil shall be selected as per following temperature range. Storage temperature 20 0 C to +70 0 C, Operating temperature 10 0 C to +55 0 C xxix) Cradle is able to tilt +125 0 and 45 0 from the horizontal xxx) A slewing bearing of suitable capacity is to be provided which can withstand radial, axial and tilting moments. xxxi) Material to be used for fabrication of the structure is marine grade anti-corrosive steel or equivalent. xxxii) One sets of Slip rigs integrated with FORJ are provided to supply the power to the prime mover as well as two way transfer the data from the airborne to the ground. Such slip ring and FORJ is to be provided at the stow drum to provide power and data to the tether. The Power slip ring with central hole is to be provided at the pedestal to transfer the power from the main supply to the rotating winch and mooring system. xxxiii) The trailer should be suitably selected/designed to house the system. It should also be able to travel in desert terrain and compatible with the prime mover TATA LPS 4018.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 18
xxxiv) Provision should be made to grounding the lightening braid of the tether. xxxv) The winch enclosure should be properly covered so that the winch enclosure is protected from dust, rain etc. To reduce the heat load on the air conditioner the panels of the cover should be made of insulating material. xxxvi) The critical components of the system should sustain the following environmental conditions: a) Ambient temperature Operating temperature range: 10 0 C to +55 0 C Storage temperature range: 20 0 C to +70 0 C b) Humidity: up to 95% at +40 o C, non-condensing conditions. c) Altitude up to 3350 m from AMSL d) Rain intensity (IS: 9000 part 16, Static pressure 100 15 kpa, 4 shower used at an angle of 45 0 for 01 hour duration). e) Salinity (IS: 8252 part 10 Clause 4.2.2) f) Dust as encountered in desert areas (IS: 9000 part 12, Temperature 40 3 0 C, relative humidity 40% steam of dust laden air , dust concentration less than 10 3 g for a duration one hour). g) Fungus growth as encountered in tropical climates (not encountered in mechanical components). xxxvii) The various input data for system are as follows* a. Aerostat Parameters Aerostat Volume : 3500 cum Maximum Buoyant Force : 32570 N Aerostat Weight : 1492 kg + 300 kg payload Offset of Confluence Point : 12.9 m, from Nose : 12.7 m, below from central axis * These data are indicative only however actual value will be finalised at the time of design review
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 19
Offset of CP : 19.7 m, from Nose Offset of CB : 18.8 m, from Nose Offset of CG : 23.6 m, from Nose b. Tether Parameters Maximum Tether Length : 1500 m Diameter : 18 + 0.5 mm Tether Bending Diameter (Minimum) : 0.6 m Tether Weight : 0.4 kg/m c. Capstan design Parameters Maximum Tether Tension : 50000 N Maximum Full Load Speed : 75 m/min (at 34000 N) Brake Holding Capacity : 100000 N d. Stow drum & Spooler Parameters Storage capacity : 1500 m length of tether Maximum Tether Tension : 15000 N e. Close Haul Winch Parameters Maximum Cable Length Handled : 60 m Maximum Operational Speed : 30 m/min (at 15000 N) Brake Holding Capacity : 30000 N f. Load values Case I: Balloon is in moored condition, Wind Direction Parallel to balloon longitudinal Axis and blowing at a speed of 70 knots (36 m/s), both the close haul lines are secured: Drag and lift forces are Wind speed (m/sec) Balloon Angle of attack Drag Force Lift Force 36 0 0 6071 N -74 N 36 +6 0 7592 N 16839 N 36 -6 0 6322 N -16706 N
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 20
Case II: Balloon is in moored condition; Wind Direction Parallel to balloon longitudinal Axis and blowing at a speed of 70 knots (36 m/s), one of the close haul lines snaps off.: Case III: Balloon is in moored condition; Wind Direction Parallel to balloon longitudinal Axis and blowing at a speed of 70 knots (36 m/s), both the close haul lines snaps off.: Case IV: Balloon is in moored condition; Wind Direction Parallel to balloon longitudinal Axis and blowing at a speed of 70 knots (36 m/s), nose lines snaps off.: Case V: Balloon is in moored condition; Wind Direction perpendicular to balloon longitudinal Axis and blowing at the speed of 20 knots (10.29 m/s), Bearing fails and not rotating: Case VI: Balloon is in flying condition; Tether tension at 50 knots (25.72 m/s) wind speed: 50000 N Case VII: Winch and mooring system is in transportation mode and system is in collapsed condition; Vertical Acceleration : 2g Horizontal Acceleration : 2g, with 1g vertical acceleration Lateral Acceleration : 1.2g, with 1g vertical acceleration All accelerations occur exclusive to each other
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 21
4.0 Subsystem Description: 4.1 Fabricated structure: The fabricated structure consists of following subsystems: I) Mooring tower II) Boom III) Close haul swing frame IV) Frame skin (shelter) V) Pedestal VI) Trailer with outriggers
4.1.1 Mooring Tower: Mooring Tower is required to hold and anchor the balloon at nose with the help of cradle and latch assembly. It is made of marine grade anti-corrosive steel. The structural design is well supported by FEM analysis. It can be folded in transportable mode.
Fig. 10: Mooring Tower (dimensions are for reference only)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 22
Fig. 11: boom 4.1.2 Boom: Boom is the main platform upon which mooring tower, inflatable trestle airbags, close haul swing frame, flying sheave, capstan, stow drum and spooler, hydraulic power pack and other sub-systems with winch enclosure are mounted. It is a made of marine grade anti- corrosive steel. The design of the boom is well supported by FEM analysis.
4.1.3 Close haul Swing frames: Close haul swing frames one each at the port and starboard side of the boom is to be provided to mount the close haul winches. The frames are foldable so that it can be folded during transportation. The design of the boom is well supported by FEM analysis.
Fig.12: Close Haul Swing Frame (dimensions are for reference only)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 23
Fig. 13: integrated mooring tower, boom and close haul swing frames SPECIFICATION SHEET FOR ASTAT MOORING STRUCTURE 1. Application To mount winch system and its all accessories 2. Quantity 01 No. 3. Configuration Compact and light weight design 4. Design Requirements It must have one point support at slewing bearing To mount winch system and its all accessories, one main frame should be there (usually known as boom). To mount cradle, it should have mooring tower. To mount two close haul winches, it must have two close haul swing frames To vary the position of close haul winches, close haul swing frame must have locking arrangement at a particular location The system is transportable so mooring tower and close haul swing frames must be foldable All accessories to be mounted on boom in such a way that the CG of system is very close to axis of slewing bearing 5. Design Parameters Forces transferred from balloon to mooring structure 6. Design methodology Theoretical analysis supported by FEM analysis for all four load cases (ref Para no. 3.2 (xxxvii)(f)) 7. Overall Dimension For transportable condition: Length (l): 12 m, Width (w): 2.5 m, Height (h): 3.7 m 8. Material Marine grade anti-corrosive steel or equivalent 9. Weight Minimum
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 24
4.1.4 Frame skin (shelter): To protect the vital tether in stored condition from environmental condition Winch enclosure, which contain hydraulic power pack, Capstan, stow drum etc. is covered with shelter. The winch enclosure is air-conditioned.
4.1.5 Pedestal: Pedestal forms an interface between trailer and rotating mooring station. It is mounted on the trailer using bolts. The pedestal cavity houses the slewing bearing and the system power slip ring and FORJ assembly, which is required for two way power and data transmission.
4.1.6 Trailer: The entire winch and mooring system is mounted on a trailer to ease the transportation. The trailer used is of a semi low-bed configuration with four extending outriggers, which can be attached to a tow vehicle for relocation. The trailer should be able to travel in the desert condition. The extended outriggers offer added stability to the system during operation. Electrically/hydraulically operated side riggers will be provided to secure the trailer during deployment of Aerostat. Four (4) numbers of hooks should be provided to lift the whole system (trailer plus winch and mooring system) through crane.
Fig. 14: Pedestal
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 25
Fig 15: Trailer
4.2 Docking and tether routing Units: The docking unit is normally used for docking the balloon to the winch and mooring system however the tether routing units guide the tether from the balloon to the stow drum. The docking unit consists of following i) Cradle assembly ii) Flying sheave iii) Tether Guide rollers assembly iv) Tether Guide sheave assembly v) High tension sensor assembly vi) Low tension sensor assembly
4.2.1 Cradle assembly The Cradle is mounted on the top of the Mooring tower and serves as a docking point for the balloon Nose during launching and recovery of the Aerostat. It is in the form of conical shape. Cradle is fitted with latching
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 26
assembly and capable of tilting +125 degree up and -45 degree down in the vertical plane by means of a hydraulic actuator. The actuation of the hydraulic actuator is controlled by operator sitting in the control cabin. The nose probe is design and fabricated to suit the latch assembly for proper and easier docking and undocking.
Fig 16: Cradle assembly 4.2.2 Flying sheave Flying sheave is used to guide the tether coming from Aerostat to capstan and the main winch through the set of pulleys. It consists of large pulley that is pivoted so as to allow rotation about the two axes. It is fitted with the counterweight. The design of flying sheave allows it to orient itself based on Aerostat location and maintain the minimum bending diameter of the tether.
Fig 17: Flying Sheave
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 27
4.2.3 Tether guide rollers assembly These units help the tether to route from the flying sheave to the capstan. These units are used where the space is not available to mount the sheave.
Fig 18: Tether guide roller assembly 4.2.4 Tether guide sheave assembly Tether guide sheave assembly helps to guide tether from the flying sheave to the capstan.
Fig 19: Tether guide sheave assembly 4.2.5 High tension sensor assembly Two tension-sensing units are used to measure the tension of the tether. The first unit, which is called the high tension sensor assembly is fitted between the Flying Sheave and the Capstan and
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 28
used to measure the tether tension which is on the higher tension side of the capstan. The tension on this side ranges from 0-90000 N.
Fig 20: High tension sensor assembly 4.2.6 Low tension sensor assembly The second unit which is called the high tension sensor assembly is fitted between the Capstan and the spooler pulley and used to measure the tether tension coming after the reduction of tension from the capstan. The maximum tension experienced in this region is 6500 N.
Fig 21: Low tension sensor assembly
4.3 Winch Assemblies Launching, recovery, in-hauling, out-hauling operation of the balloon are carried out using the various winches. The Capstan, Stow Drum and the Spooler are used for tether handling. Launching & recovery operation is achieved by two Close Haul winches and the Nose Line Winch. All controls to
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 29
these winches are available to the operator at the Operator Control Desk. Winch assembly consists of following: i) Capstan, ii) Stow drum with spooler, iii) Close haul & nose line winches
4.3.1 Capstan The function of the Capstan is to reduce the tether tension prior to stowage on the Stow Drum, therefore preventing the tether from getting crushed when stored in multiple layers. The Capstan consists of two grooved drums around which the tether is wrapped prior to feeding the stow drum. These drums are mechanically synchronized and are driven by a single hydraulic motor via a reduction gearbox and clutch. It is primarily driven by the hydraulic motor, the speed of which is controlled from the Operator Control Desk. A manual drive should also be provided for redundancy. For this shifting provision should also be given. The capstan should be provided with integral fail-safe parking brake unit that prevents the tether from unwinding under operational loads. The brakes are sized for braking torque equivalent to 9000 kgf tether tension at capstan.
Fig 22: Capstan
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 30
SPECIFICATION SHEET FOR ASTAT CAPSTAN 1. Application : Tether tension relieving prior to storage on stow drum 2. Quantity : 1 no. 3. Configuration :
Dual Cantilevered drums Vertical stacking 4. Tether Details : Diameter : 18+0.5 mm Total Length : 1500 m Tether weight :0.4 kg/m (estimated) 5. Drum Dimensions : Grooved Hollow Drum (Linear Grooves) Mean Diameter at drum groove : 620 mm No. of grooves on drum : 5 No. of layers : 1 Groove Outer Diameter : 640 650 mm Drums to have identical construction Drums when assembled to have half pitch groove offset Vertical offset between drums to be minimized 6. Drum Shafts : Hollow shafts ( 2 Nos.) 7. Design Parameters: Maximum Tether Speed : 75 m/min Operational Tether Tension : 34000 N Brake Holding Tether Tension : 100000 N 8. Input Power From Hydraulic motor 9. Gearbox :
1 No. integrated gearbox *Gearbox Efficiency > 85 % to be ensured *Manual operation: Should function with hydraulic motor braked *Manual clutch engagement / disengagement *Easy access to all manual handles from outside *Integral Multi-disc brake units *Brake units to be compact and optimally located
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 31
10. Features : Peripheral rollers to be provided around drums to ensure tether does not leave groove when slack Protective cover to be provided over drums, absence of which should not hinder Capstan operation Protective cover to have tether inlet and exit cut-outs Provision for lifting lugs to lift entire Capstan unit vertically System weight optimization to be enforced during design All manual interfaces to be accessible from motor side All sharp corners in path of tether to be rounded off 11. Weight: Minimum Note : This specification sheet are for reference only.
4.3.2 Stow drum with spooler Stow Drum and Spooler are used for tether stowage after tension relieving at Capstan. It should have capacity to store 1500m length of tether. The stow drum and spooler are driven using a single hydraulic motor. It should be fitted with an integral fail-safe brake to prevent tether unwinding when not in operation. Provision should also be made on the stow drum for manual operation using a hand lever. Due to increase in diameter when tether is stored in multiple layers on the stow drum, the linear velocity of tether at stow drum and at capstan tend to vary, leading to fluctuation in tether tension. So a synchronization of speed between the capstan and stow drum is required to be taken care during designing of the system. This synchronization should be done electronically as well as the mechanically. The Spooler is used for level winding of tether on the Stow Drum. This is achieved by double helix diamond screw and pawl arrangements. The diamond screw is driven by stow drum hydraulic motor via the gearbox. The Stow Drum is mechanically synchronized with the Spooler for uniform tether winding on the drum. For every turn
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 32
of the drum the spooler pulley moves by 1(one) tether pitch distance linearly. The Stow Drum can be disengaged from the spooler by removing the coupling between them to allow manual correction to spooler carriage location during initial tether winding on the drum or intermittently.
Fig 23: Stow drum & spooler
SPECIFICATION SHEET FOR ASTAT STOW DRUM & SPOOLER 1. Application : Storage of tether after tension relieving at capstan 2. Quantity : 1 no. 3. Configuration : Perpendicular tether feed (parallel to drum axis) 4. Tether Details : Diameter : 18+0.5 mm Total Length : 1500 m Tether weight : 400 g/m (estimated) 5. Drum Dimension: Flat Drum Diameter: 600 mm Drum Flange Diameter : 1200 mm Flange - Flange inner offset : Min. 1230 mm Max. 1235 mm Drum Slot width (for cable termination) : 45 mm 6. Drum storage Capacity 1500 m 7. Drum Shafts : Flanged hollow shafts ( 2 Nos.) Shaft Inner Diameters : 150 mm, each Shaft Bolted to Drum 8. Input power From Hydraulic motor 9. Design Parameters Maximum cable Speed: Maximum Tension:
75 m/min (corresponding to 34000 N at Capstan) 15000 N 10. Gearbox : 1 No. integrated gearbox *Gearbox Efficiency > 85 % to be ensured *Manual operation: Should function with hydraulic
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 33
motor braked *Manual clutch engagement / disengagement *Easy access to all manual handles from outside *Integral Multi-disc brake units *Brake units to be compact and optimally located 11. Spooler : *Light weight pulley with vertical axis, mounted on carriage with Diamond Screw & Pawl Arrangement and Hollow guide shafts (2 Nos.) *Pulley Diameter : 600 mm *Pulley width to cater for spooling on 1st and last layers 12. Features: *Protective covers to be provided where necessary *All sharp corners to be rounded of in tether path *All manual operations to be possible from spooler side *System weight optimization to be enforced during design
Note : This specification sheet are for reference only.
4.3.3 Close haul & nose line winches The two Close Haul winches are used to hold the Aerostat from the port and starboard side of the balloon. The Close Haul winches are mounted on two swing frames that can be folded during transportation. The construction of the Nose Line winch is identical to the close haul winches. The Nose Line Winch is located below the mooring tower and is used for guiding the Aerostat nose probe into the Cradle for docking through the nose line cable. These drums should have capacity to store 80 m of mooring cable and are driven by a hydraulic motor via a reduction gearbox. The operation of these winches is controlled from the Operator Control Desk and they can be selectively synchronized with all other winch. These winches are fitted with an integral fail-safe brake that prevents winch slippage when not in operation. Provision should be made for a manual over ride for operation using a hand pump to drive the close haul winch motor.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 34
Fig. 24: Close haul/Nose line winch
Specification Sheet For Close Haul/Nose line Winch
1. Application: Storage and handling of close haul lines 2. Quantity: 3 nos. 3. Configuration: Compact & Light weight Design 4. Close Haul Line Details: (ADRDE will supply) Diameter : 12 mm Total Length to be stowed: 80 m Material : Nylon 5. Drum Dimension: Cylindrical Drum without grooves Drum Diameter: 300 mm Flange Diameter : 450 mm Flange Slot width (for line termination) : 20 mm 6. Design Parameters Maximum cable Speed: Maximum Tension: Brake load:
30 m/min 12000 N 24000 N 7. Weight: minimum
Note: These specification sheets are for reference only.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 35
4.4 Hydraulic System Hydraulic system consists of i) Electric motor ii) Hydraulic pump iii) Hydraulic motor and actuator, iv) Proportional Valves Assembly v) Oil tank vi) Oil cooler system vii) Various Valves & Accessories. The hydraulic drives are required to drive capstan, stow drum, two close haul winches, a nose line winch, tower actuator, pedestal drive and cradle actuator. The drives to these actuators should come from a single hydraulic power pack. This hydraulic power pack is integrated with the proportional direction control valve and counterbalance valve. High response shock and cavitation valve should also be incorporated to absorb high shocks when the joystick will be released and Capstan brakes immediately. Additionally one relief valve should be provided in every actuator circuit. The system should be designed at Maximum system pressure 350 bar and maximum flow of 300 lpm. All the operation of the actuator is through Joystick & through hydraulic lever which is placed at the control cabin. Some of the actuator like stow drum and capstan can also be operated through manual cranking. The reference hydraulic circuit which may be used for this operation is given in figure no.25. The bill of material and their make is also given in table no.1. The given circuit and bill of materials are only for the reference, the actual circuit and bill of material fill be finalized during the design and its review and vetted by DIRECTOR ADRDE or his authorized representative. The entire system should be designed and configured by using high quality Commercially Off The Shelf (COTS) equipment.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 36
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 37
Table 1 Sl. No. Part description Specification Make 1. Electric Motor 3-, 415V, 75 kW, Qty: 2no. Crompton Greaves or equivalent 2. Hydraulic Pump Variable Displacement, 100cc/rev, HP limiter with load sensing and pressure compensator, Qty: 2no Rexroth or equivalent 3. Heater 12 kW, 3-, 230 V A/C Elmec or Equivalent 4. Hydraulic Reservoir Capacity of 1000 ltrs with access door for cleaning Reputed make 5. Oil level Gauge For giving information of oil level Stauff or equivalent 6. Level switch For switching operation between two oil level Monitor India or equivalent 7. Temperature sensor Range -50 0 C to +250 0 C Wika or equivalent 8. Air breather 2m rating Argo or equivalent 9. Direction control valve Various sizes Rexroth or equivalent 10. Check Valve
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 38
11. Pressure line filter 12 m size filter with clog indicator Pall or equivalent 12. Return line filter 5 m size filter with clog indicator Pall or equivalent 13. Pressure relief Valve Capacity Quantity 95 lpm 03 no. 320 lpm 01 no. Rexroth or equivalent 14. Pressure reducing valve With various pressure setting and sizes Rexroth or equivalent 15. Pressure Gauge Range 0 to 450 bar Forbes Marshal or equivalent 16. Proportional valve 180 lpm , 115 lpm (3 valve module) and 180lpm (4valve module) Rexroth or equivalent 17. Shuttle Valve Pressure Capacity Quantity 315 bar 30 lpm 01 no. 350 bar 10 lpm 05 no. Rexroth or equivalent 18. Counterbalance valve (Air vented) Capacity Quantity 60 lpm 06 no. 120 lpm 08 no. 480 lpm 02 no. Rexroth or equivalent 19. Shut-off valve Input Pressure: 350 bar Capacity: 80 lpm Quantity: 01 no. Rexroth or equivalent 20. Needle Valve Input Pressure: 350 bar Capacity: 40 lpm Quantity: 02 no. Rexroth or equivalent 21. Ball Valve Size: 1, 2, 3 Rexroth or equivalent 22. Hydraulic Motor 625 cc/rev, 1800 rpm, Qty: 03 no. 468 cc/rev,1800 rpm, Qty: 01 no. 1130 cc/rev, 110 rpm, Qty: 01 no 2857 cc/rev, 63 rpm, Qty: 01 no Rexroth or equivalent
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 39
23. Hydraulic Cylinder Bore Dia: 140mm Rod Dia: 90mm Stroke: 1150mm Rexroth or equivalent 24. Oil Cooler Unit Cooling capacity 45 kW Emmegi or equivalent 25. Rotary Actuator Bore 50.8 mm, Rotation 120 0 , both direction rotation Rexroth or equivalent 26. High Response Shock and Cavitation Valve To be suitably selected Rexroth, Parker or equivalent 27. Hydraulic Hose Various sizes, to be suitably selected Parker or equivalent 28. Fitting Weld nipple type of Parker soft seal Parker or equivalent
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 40
4.5 Electrical and Electronic Sub-Systems Electrical and electronic sub-system consists of control desk master controller (PLC based), PLC,HMI and SCADA software, MCC Panel, winch power panel, encoders & sensors, operator display with HMI software, operator control desk, power slip ring and FORJ assembly, cradle camera and accessories. PLC based master controller controls and monitors the winch operation. Winch power panel supplies power to all platform equipments. To measure, display and record of various parameters of the winch and mooring system encoders and sensors are used. Power slip ring transfers the power between stationery and rotary parts and FORJ will transfer the data from the rotary to stationary parts and vice versa. Data storage facility should also be provided to store the various data for a period of at least one week. The main subsystem is described in succeeding paragraph.
4.5.1 Operator Cabin and Control Panel: A control console will be provided with a joystick for various winch control and a display for viewing operating parameters. It should be ergonomically designed and should have push button/touch pad, selector switches and indicating lamp for control and monitor of the system. It should also have indicators to indicate the winding and unwinding position of main winch, close haul winch, nose line winch and status of electrical and hydraulic subsystems. The operator cabin consists of following:
(a) Main controller: It would provide controls for operating the motors and indicate system status. (i) Should consists of a Human Machine Interface (MIL grade flat Panel TFT display and keyboard and touchpad ) (ii) Should operate on 230 V AC, 50 Hz (iii) A back-up power supply should be provided to operate the system for at least 30 min.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 41
(iv) CPU having state of art processor and motherboard with PC slots (4 minimum) for analog/digital input/output. (v) Should be accompanied by a software for co figurate the system and to monitor system status. (vi) System should have at least 500 GB hard disk. (vii) Should have soft switches as listed below a. HOME b. ERROR LOG c. PARAMETER SET d. ALARM (viii) Should also have lighted push buttons for controlling winch independently & LED indicator for indicating status of winch. (ix) Graphics Terminal: The graphics terminal is configured to display the status of system. Various soft switches are activated via feather touch switches to the left of the display. The various soft switches are listed below (a) HOME: Returns the display to the HOME screen. (b) ERROR LOG: Display the error log, which maintains the record of occurrences of all the errors in the system for a period of 30 days. The information displayed on the screen should be recorded for offline viewing. The field tabulated in the error log are: Serial number Error Description Time of occurrence Time when the error was accepted (Alarm Reset Time) Time when error was corrected (c) PARAMETER SET: Display screen where control parameters can be set: Serial number Parameter
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 42
Setting of the parameter New value for setting Restore original value Restore to default value (d) ALARM ACCEPT: Key to acknowledge all identified alarms and mute speaker.
The reference detail of PLC is as follows: The entire Winch and Mooring system is realized around a Programmable Logic Controller The PLC is divided into the following MODULES:
i. Power Supply Module: CPS ii. Central Processing Unit module: CPU iii. 64 Channel Digital I/P Module: DI1 iv. 64 Channel Digital O/P Module: DO1 v. 8 Channel Analog I/P module: AI1 vi. 8 Channel Analog O/P module: AO1 vii. 2 Channel Counter module:CMT1 viii. 4 Channel Counter module: CMT2 ix. Spare Channel x. Spare channel xi. Spare channel
The Ladder Logic Software should be used for the PLC is PL7- pro or higher version or equivalent software. The Human Machine Interface (HMI) Software for the operating system (OS1) should be Citect or equivalent having minimum 500 tags. The PLC controls the following Digital Input/ Output elements of Winch and Mooring system:
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 43
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 44
XXXII) Main Supply is OFF (Display) XXXIII) 7 th turn proxy tripped XXXIV) Spooler manual (Engaged/ Disengaged) XXXV) Hydraulic Power Pack Motor 1 ON XXXVI) Hydraulic Power Pack Motor 2 ON XXXVII) Pneumatic ON XXXVIII) HPP (Loading/Unloading) XXXIX) Cradle Actuator (free Slide) XL) Capstan Motor ( Displacement Pilot signal- Solenoid 1) XLI) Pedestal Clutch Operation XLII) Pneumatic Solenoid 1 XLIII) Pneumatic Solenoid 2 XLIV) Stowing drum Lamp ( Primary / Emergency mode) XLV) Capstan Drum Lamp ( Primary / Emergency mode) XLVI) Left Haul Winch Lamp (Primary / Emergency mode) XLVII) Right Haul Winch Lamp (Primary / Emergency mode) XLVIII) Cradle Actuator Lamp (Primary / Emergency mode) XLIX) Tower Elevated Lamp (Primary / Emergency mode) L) Pedestal Lamp (Primary / Emergency mode) LI) Nose Probe Docked Lamp LII) HPP Motor-1 Lamp ON LIII) HPP Motor-2 Lamp ON LIV) Nose Probe Lock Engaged LV) Pneumatics lamp ON LVI) Trestle(Airbag) Inflate Lamp
The PLC controls in Analog mode the following elements of WM system:
i. Pneumatic Pressure Sensor ii. Temperature Sensor
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 45
iii. Joystick Travel (X/Y Axis) iv. Tensometer-1 feedback (HTS) v. Tensometer-2 feedback (LTS) vi. Stowing drum Proportional Valve vii. Capstan Proportional Valve viii. Close Haul Winch Right Proportional Valve ix. Close Haul Winch Left Proportional Valve x. Nose Line Winch Proportional Valve
The two counter modules of 2 Channel and 4 Channel controls the Capstan and Stow drum.
The Block diagrams of the various channel is shown in the succeeding pages. These block diagrams are for reference only. The actual configuration and the system will be finalized during design and review of the system.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 46
i. Block Diagram of PLC based WM System:
The details of the Digital Signals, Analog signals and Counter Modules are mentioned below:
Central Power Supply
Operating System (HMI Software) Central Processing unit with Ethernet Port
Digital Input Port Digital Output Port
Analog Input Port
Analog Output Port
Counter Module 2 CH Counter Module 4 CH
Joystick and Keyboard Inputs Analog O/p Signals Ack. and Feedback Signal Digital Signals Ack. and Feedback Signal
Capstan Stow drum Feedback Sig
Feedback Sig
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 47
Joystick and Toggle Switch Input for the Operation of Actuators Cradle
Pedestal
Close Haul winch (R) Close Haul winch (L)
Nose Line Winch
Tower Elevator
Capstan Stowdrum Hydraulic Actuators of Winching Assembly
Ack. and Feedback Signal Display on Screen Via (HMI Software) 230 VAC Turn Count Signal of Capstan Turn Count Signal of Stowdrum
Ack. and Feedback Signal
Digital Signal Central Power Supply
Central Processing unit with Ethernet Port
Analog Input Port Analog Output Port Digital Input Port
Digital Output Port
Counter Module 2 CH 04 Redundant Channels for further Expansion Counter Module 4 CH
0-10 V 0-10 V 0-10 V 0-10 V 0-10 V 0-10 V 0-10 V 0-10 V 0-10 V (x-axis) 0-10 V (y-axis) 24 V Encoder Encoder Encoder Encod er Encod er Limit Switch Limit Switch Praportional Valve to control oil flow
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 48
iii) Digital Input/ Output elements of WM system
iv) Analog Input/ Output elements of WM system Pedestal (S/ P/ E mode) Tower Elevate (S/ P / E mode) Nose Probe lock (Eng/ Diseng) Nose Line Winch (S/ P / E mode) Capstan Manual( Eng/ Diseng) Capstan (S/ P/ E) Stowdrum manual (Eng/Diseng) Stowing Drum( S/ P/ E mode) Left Haul Winch (S/ P/ E mode) Right Haul Winch (S/ P/ E mode) Spooler Manual (Eng/ Diseng) Suction line offline/1/2 Pressure/ Return line filter Clogged Capstn Motor ( Disp. Pilot sig- Solen 1) Spooler manual (Eng/ Disen) 7 th turn proxy tripped Cradle Actuator (S/ P/ E mode) Cradle Free Slide (ON/OFF) Cradle Actuator (free Slide)
Pneumatics (ON/OFF) Pneumatic Pressure Sensor Pneumatic Solenoid 1/2 Trestle (Inflate/ Deflate) Footswitch (Trigger) Chiller Unit (OFF) Pedestal Clutch Operation Hooter (Acknowledge) Main Supply is OFF (Display) Lamp (P/ E mode): Trestale Inflate /Pneumatics /HPP Motor 1-2 / Nose Probe Docked /Stowing drum /Capstan Drum /Left Haul Winch /Right Haul Winch /Cradle Actuator /Pedestal/ Tower Elevated Motor-1/2 (ON/OFF); HYD Motor 1/2 (ON F/B) Oil level Critical HYD Power Pack Motor 1/2 ON HPP (Loading/Unloading) Digital Input Port Digital Output Port
Central Processing unit with Ethernet Port (Slot 1) Feedback/Ac knowledgeme nt
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 49
v) Counter Module elements of WM system
(b) Motor starter Panel: Stowing drum Proportional Valve Capstan Proportional Valve Close Haul Winch Rht Prop. Valve Close Haul Winch Lft Prop. Valve Nose Line Winch Prop. Valve Joystick Travel (X/Y Axis) Tensometer-1 feedback (HTS); Tensometer-2 feedback (LTS) Temperature Sensor Pneumatic Pressure Sensor Central Processing unit with Ethernet Port (Slot 1) Analog Input Port Analog Output Port
Feedback/ Acknowledgement Central Processing unit with Ethernet Port Feedback/ Acknowledgement Counter Module 2 CH Counter Module 4 CH
Capstan Stow drum
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 50
Main purpose of this panel is to control the operation of the motors and provide a means of protecting the motors under such fault conditions as main motor winding overheat, single phasing, sustained overloads and stalling. Above information related to motor condition should be displayed in the main control panel.
(c) Encoders and load cell: These are sensors used for sensing the various signals such as position of the paid out length of cable or tether so that speed of paying out of the length paid out can be calculated and number of other parameters also. Load cell are used to measure the tether tension before and after the capstan.The Specification of the load cells are: Data sheet for High tension load cell 1. Application Measurement of load in High tension side of Capstan 2. Load Range 0 to 50000 N 3. Safe load limit 200% of full Scale Reading 4. Protection class IP 65 Data sheet for Low tension load cell 1. Application Measurement of load in High tension side of Capstan 2. Load Range 0 to 15000 N 3. Safe load limit 200% of full Scale Reading 4. Protection class IP 65
(d) Slip rings and FORJ: The slip ring and FORJ hybrid assembly to be fitted at the stow drum however only slip ring with 50mm central hole is to be fitted at the pedestal. Technical Specifications of HYBRID FORJ Assembly at Stow Drum
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 51
i. Optical Details Numbers of optical channel : 06, Single Mode (SM) Wave length window () : 1310 1550 nm Insertion loss : 3.0 dB Connector/Adaptor : ST preferably ii. Electrical Slip rings Sl. No. Application Nos. of rings Current Rating Voltage rating Material 1. Power 03 02 15A 40A 1000V 1000V Silver plated copper Silver plated copper 2. Lightning current drainage 01 Slip ring should be capable of passing 100KA current for time duration of 500sec. 3. Adaptor 01 A electrical Mil grade adaptor to be provided to meet above requirement.
iii. Mechanical Details: Material : Aircraft Al (ASTM B 221) preferably Rotation of power or data signal : 360 continuous Weight : < 12 kg Dimensions : Length 400 10mm, 200 5 mm iv. Environmental Details: Environmental protection : IP 65 Temperature range Operational : -10 to + 55 c Storage : -20 to + 70 c Vibration : Mil-std-167-1 ship vibration v. Quantity: Quantity required : 02 Nos.(keeping 01 as spare) Make: M/s Princetel Inc., NJ, USA Figure 25: Drawing of Hybrid slip ring and
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 52
Specification of the slip ring at the Pedestal The above specification is for reference only.
(e) 3 Automatic voltage controller (8 kVA): 3 Automatic voltage controller is required to maintain 415 V (phase to Phase) at airborne end when power supply of 8 kVA is feed through 1500 m length of tether. A suitable automatic voltage controller is required to made to suit this requirement.
1. Make Schleifring and apparatebau GmbH, Germany or equivalent 2. Power Rating 250 kVA 3. Channel 11, One channel is dedicated for grounding the lightening current of 100 kA for time duration of 500sec, one channel is used for taking the data out and giving command when remote operation is required 4. Current rating 600 A (min) 5. Voltage rating 415 15 v 6. Central hole diameter 50 mm 7. Protection class IP 65 8. Temperature range Operational Storage
-10 to + 55 c -20 to + 70 c 9. Vibration Mil-std-167-1 ship vibration 10. Adaptor A electrical Mil grade adaptor to be provided to meet above requirement. 11. Frequency 50 Hz
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 53
(f) Portable Rugged Online data steaming and data storage & analysis device: A portable rugged online data streaming device and a portable data storage and analysis device should be provided with the system for analysis and data back up at the trial site. Each of one number is required. The rugged portable online data streaming device should have MIL grade components and of reputed make. The some of the minimum features are: 250 GB Hard disc(or higher), 2 GB DDR2 RAM (or higher), 13.3 LCD, Intel core 2 duo with corresponding motherboard, standard port and interfaces like RJ 11, RJ 45, Serial, 4 USB, port replicator interface, VGA out, Audio in out, Intel 3945 a/b/g, 10/100/1000 Gigabit NIC, Blue tooth, DVD writer, standard keyboard with touch pad, pre installed Windows 7 professional, battery life not less than 6 hours etc. The portable data storage and analysis device should be of reputed make. The some of the minimum features are: 500 GB Hard disc(or higher), 3 GB DDR3 RAM (or higher), 12.1 TFT, Intel core i7 processor with corresponding motherboard, standard port and interfaces like RJ 11, RJ 45, Serial, 4 USB, port replicator interface, VGA out, Audio in out, Intel 3945 a/b/g, 10/100/1000 Gigabit NIC, Blue tooth, DVD writer, standard keyboard with touch pad, pre installed Windows 7 professional, Web camera, battery life not less than 4 hours etc.
(g) List of electronic control system deliverables: (i) Master controller (ii) System Software with their licenses (iii) Console with HMI, CPU (iv) Feedback Sensors
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 54
(v) Operator desk with SBC and operator dialog terminal and push buttons and levers (vi) Networking cable and associated hardware (vii) MCC Panel (viii) Slip rings (one of 8kVA rating other 250 kVA rating) (ix) Hybrid FORJ (2 no. one for the stow drum other for spare) (x) 3 Automatic voltage controller (8 kVA) (xi) Portable rugged data streaming device (xii) Portable data storage and analysis device (xiii) Back up supply (xiv) Communication system for maintenance crew and operator (xv) Engineering services (xvi) Commissioning services
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 55
4.6 Miscellaneous subsystem 4.6.1 Pedestal Drive and Slewing Bearing The entire mooring station is mounted on the pedestal using a slewing bearing. The slewing bearing allows the station to be rotated continuously about the vertical axis. The powered drive unit coupled to the slewing bearing allows the complete winch and mooring system to be oriented as required using a hydraulic motor. The operational controls for this are available at the operator control desk. It can be disengaged from the operator control desk to allow wind waning. The specification of this subsystem is given below: Specification Sheet - Aerostat Pedestal Drive 1. Application: Flange mounted Pedestal Drive with integral clutch for Mobile application 2. Dimensional Data: Mounting PCD Body diameter Total height
< 500 mm < 350 mm < 300 mm (from mounting flange to motor end face) 3 Input Interface: Hydraulic Motor 4. Output Torque: Dynamic: 1500 Nm 5. Output Speed: 5 rpm 6. Output Pinion Details: Module = 5 Number of teeth = 73 7. Output Interface:
Length of pinion shaft such that length from mounting face to pinion center = 48 mm 8. Clutch Details: Hydraulically engaged spring released clutch. Preferably non friction based positive engagement 9.
Sealing: Fully sealed against ingress of dust / water
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 56
10. Weight: Reduced component weight preferred 11. Life: 10 years (assuming operated (@ 2hrs per day) > 7200 hours (1.8 X 10 5 (No. of cycles @ 25 half cycles
Note : This specification sheet are for reference only.
Specification Sheet - Aerostat Slewing Bearing 1. Application: Slewing Bearing for Mobile application (Wind-vaning Station) 2. Bearing Type: Slewing bearing With Internal Gear 3. Make: Rothe Erde, Germany or Equivalent 4. Dimensional Data: Maximum External Diameter: Maximum Height :
2000 mm 300 mm 5. Accuracy Axial Run out on the mounting faces: Radial run out on locating spigots: Run out on gear PCD:
< 0.2mm < 0.2 mm < 0.12 mm 6. Starting Torque: < 1000 Nm 7. Bearing Loads: During Transportation: Operational load:
60 ton 30 ton 8. Gear: Maximum Operational Torque : Operating Speed :
6 kNm 1 rpm 9. Sealing: Fully sealed against ingress of dust / water 10. Weight: Reduced component weight preferred
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 57
11. Bearing Life: 10 years (assuming operated(@ 2hrs per day) > 7200 hours (1.8 X 10 5 (No. of cycles @ 25 half cycles per hr)) Suitable azimuth rotating mechanism or equivalent may be used which meets system requirement. Note : This specification sheet are for reference only.
4.6.2 Air Conditioning System Air conditioning system is used to maintain the temperature and humidity of the operator cabin as well as the winch enclosure. The air conditioner should be suitably chosen so that the temperature inside the operator cabin and the winch enclosure is comfortable even at the extreme operating condition. Air conditioner should have MIL grade type.
4.6.3 Pneumatic System and Air bags The Pneumatic System is solely for the purpose of inflating and maintaining the pressure in the Air Bags during operating conditions and to deflate Air Bags during transportation condition. Pneumatic system consists of compressor/ air cylinder, vacuum pump, air bags, pressure control valve and other accessories. Compressor/air cylinder and vacuum pump is used to inflate and deflate the air bags respectively. To control the pressure of air during the inflation or deflation of air bags, pressure control valves are used along with other accessories to ensure the proper distribution of air. The function of the airbags is to support balloon in docked condition. It is suitably located on the winch and mooring system. It has two frames which are welded to the main structural frame of the station. Each frame carries an inflatable Air bag, which provides cushioned support to Aerostat to keep it in horizontal position. 4.6.4 Lightning Protection: The tether is having lightning braids to cater 100 k Amps lightning. Adequate path should be available to earth the lightening.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 58
5.0 Scope of Work It includes development, fabrication, supply, integration of structural, hydraulic & control system, installation, commissioning of the system at ADRDE and conduct test trials as per ATP. This system requires a preliminary & critical design analysis, Material Selection, preparation of drawings, Fabrication & testing techniques. Finite Element Analysis of various structural members would be necessary to arrive at a rational mechanical design of the system. The scope of work mainly includes following: a) Design of whole system based on specification including FEM analysis of the system. b) Preparation of Configuration Document, Preliminary Design Report (PDR), Critical Design Report (CDR) etc. c) Review of the design by experts to be nominated by ADRDE. d) Preparation of manufacturing drawings of all the systems and components including assembly drawing in AUTOCAD and 3D modelling duly approved by ADRDE. (The firm should have in house CAD facilities and they are at least 5 years experience in fabrication and FEM analysis of structures and components). e) Review of acceptance Test Procedure (ATP) based on draft ATP provided by ADRDE and then preparation of final ATP. f) Preparation of QAP and WPS (Welding Procedure Specification) Document. g) Fabrication of the complete system. h) Testing of sub-assemblies of the system as per ATP at firms premises. i) Integration, installation and commissioning of whole system at ADRDE, Agra or place provided by ADRDE, Agra. j) Fabrication of test jigs and fixtures required in manufacturing and testing. k) Acceptance Testing as per final ATP. l) Preparation of Test Report (including stage inspection report).
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 59
6.0 Inspections and Acceptance Procedure: During complete execution of the job, inspection will be carried out by the Director ADRDE, Agra or his authorized representative. The inspection will be carried out in stages for raw materials, machined components, assembled components and bought out components. The contractor shall get the drawings approved for every component including structure, hydraulic circuit, various sensors and bought out components. All the material to be procured by the contractor shall be inspected by the inspecting authority i.e. Director ADRDE or his authorized representative. Stage inspection shall be carried out for subassemblies during fabrication. Contractor shall keep informed the inspecting authority on the progress of work and shall notify the inspecting authority well in advance. Inspection report format for each component has to be filled in separately for critical dimensions on each component using calibrated instruments only. All inspection, measuring and test equipment should have valid calibration as per ISO 9001 requirements. The system should be inspected and accepted as per final ATP which will be prepared after the review however the draft ATP is given in the Annexure I .
7.0 Painting: i) Cleaning: The surface to be painted shall be prepared to ensure complete removal of grease, rust scale corrosion, slag etc. Mechanical cleaning involving Scraping, wire brushing, rubbing with abrasion paper may be used. ii) Primer Coat: Primer coat shall consist of red oxide zinc chrome confirming to IS: 2074. Two coats of this shall be applied as per the procedure laid down in IS 1477 Part II. (painting process to be approved by ADRDE) iii) Finish Coat: Two coat of OG colour paint. iv) Adequate internal protection should be provided to the structure components used as hollow sections.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 60
8.0 Integration, Installation and commissioning: The integration, installation of the whole winch and mooring system will be carried out by the contractor initially at firms premises and then at ADRDE, Agra or the place provided by ADRDE Agra. After the installation the system will be commissioned by the firm at ADRDE, Agra or the place provided by ADRDE Agra.
9.0 Materials for Fabrication/Integration/installation: i) All the materials, tools, accessories, Welding set, crane required for integration and testing is to be arranged by the contractor at the work site (at firm premises or at ADRDE or place provided by ADRDE) at his own cost. ii) All the materials required for fabrication will be procured by the contractor along with their relevant test certificates. Material procured by the contractor for machining and fabrication work should confirm to relevant IS specification. Material, which is not confirming to the specification, will be rejected and will be replaced by the contractor at their (contractor) cost. The contractor shall furnish test certificates for all the material purchased by him confirming to relevant standards before commencement of work. Material shall be tested for its chemical composition, mechanical properties, ultrasonic test etc to detect any flaws before fabrication. The materials shall be stamped by the inspection agency before fabrication. iii) Firm should submit the QAP document, which will describe how raw material will fabricate into component.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 61
10.0 Quality control: As quality is integral part of the service process, so to enable the effective control of each service process the contractor should use calibrated instruments during manufacture of all the components. If such calibrated instruments are not available, the contractor should make necessary arrangements and provide calibrated instruments to the inspector as and when inspection is carried out. The contractor should strictly adhere to the tolerances specified in the approved drawings. Contractor should submit quality test plan along with technical bid.
10.1 Quality control for welding: i) Welding sequence shall be such that the distortions and residual stresses are minimized. All welds shall be deposited in proper sequence so as to balance the applied heat as far as possible. ii) All welding shall be carried out by qualified and approved welders. Quality of welds carried out by the welders shall be tested in accordance with IS:7318 before the welder is permitted to do the welding. iii) In case of fillet welds, test coupon shall be made and subjected to dye penetration test. The welding parameters of the accepted weld coupon be established and ensured in case of fillet welds. iv) Weld metal shall be solid except for the fine scattered porosity and small inclusions of oxides or slag may be overlooked. v) There shall be complete fusion and penetration between the weldment and the parent material during the successive runs. vi) Firm should submit the WPS (Welding Procedure Specification) document.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 62
11.0 Perfection of Work: i) All components and accessories shall be suitable for open field operating conditions including dust, sand, rain, salinity etc. For this, all components shall have anticorrosion treatment & should be dust proof. All mating components shall have proper lubricating arrangements. ii) The workmanship shall be of the highest in order. All components should be free from burrs, sharp edges and finished smooth. iii) All components and accessories having same part numbers shall be directly interchangeable with respect to installation and performance. The list of all spares should be supplied iv) The components that are used in fabrication of this system should be of reputed firm/company. The overall workmanship shall be of best quality to the satisfaction of inspection agency. All components/accessories should be of best trade quality and as far as possible should conform to IS specification. v) In the hydraulic drives, all the pipes should be bent neatly to the appropriate angle and be properly clamped and secured. Sharp bends should be avoided. No leakage what so ever in pipe joints and connections are allowed. vi) The electric motor along with the hydraulic pump, hydraulic motor and all other accessories shall be properly placed and mounted. vii) All the control valves shall be properly mounted on a panel in such a way that all the hydraulic components/fittings should be easily approachable and if needed be easily removable and re-fittable during repair/maintenance. viii) Hydraulic power pack shall be compact in design. ix) Fabricated components should be free from burs and sharp edges. x) The fabrication and welding of system shall be of highest quality.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 63
xi) All the components shall be manufactured as per the tolerances mentioned on the approved drawings. Unless otherwise specified, the tolerance for fabrication shall be as per IS: 2102 1993. xii) All supplied electronics subsystems should be of Industrial/MIL grade. All electrical subsystems should meet environmental condition as per JSS 55555. xiii) All sub-vendor (if any) should be approved by DIRECTOR, ADRDE.
12.0 Safety requirements: Safety has to be of prime importance to avoid any accident and injuries to the personnel working on the system. The following safety measures should be kept in mind during integration: i) All high pressure components/lines shall be properly covered to avoid damage due to falling of some objects or tools and prevent people to step on such components/lines during working. ii) Proper colour code shall be followed for marking of components/lines as per standard practice. iii) All hydraulic pipe lines shall be properly clamped as per standard practice to avoid loose connection and thereby leakage due to vibration during running of pump and motor. iv) Indian standard IS: 10481 Guide lines for application and installation of oil hydraulic system shall be followed for installation of hydraulic system. v) Items that will be used for the fabrication of the above system should be of flame proof quality.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 64
13.0 Tools for maintenance: i) Tools like Allen Key set inch and mm series, double ended spanner set, screw driver pipe wrench, adjustable wrench and any tools required for maintenance of hydraulic system or any component to be supplied by the contractor with the system. ii) Special maintenance tool required for specific hydraulic components as well as other components shall be supplied by the contractor.
14.0 Jigs and Fixtures All critical welding shall be carried out using welding fixtures. The welding fixtures shall be designed and fabricated by the firm. These shall be approved from the inspector. All the welding fixtures shall be robust for repetitive use. The welding fixtures shall not develop undesirable clamping stresses in the components being fabricated. The welding fixtures shall facilitate easy and proper welding of components from all sides.
15.0 Deliverables:
a) A complete set of detailed manufacturing drawings (in 3D and 2D) of every supplied component along with assembly drawing in both hard as well as soft form. b) Complete Design Report i.e. Configuration document, Preliminary Design Report (PDR), Critical Design Report (CDR) (including FEM Analysis report) in both hard as well as soft (in solid model) form. Document should be given in doc format. c) QAP and WPS Document in both hard as well as soft (in solid model) form. Document should be given in doc format. d) One set of fabricated Winch and Mooring System along with Trailer and spares. List of spares is attached as Annexure -II. e) Schedule of spare parts with proper part nos. and source of supply and portable rate of consumption.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 65
f) List of all brought out items with their test certificates. g) System description, Operational, maintenance and repair/trouble shooting manuals. h) Inspection and test reports of all components as well as the assembly. i) Compliance report of the Acceptance test of the winch and mooring system. j) Part list, part specification with literatures of all components. The catalogue and data sheet of all brought out item. k) Drawings of hydraulic circuit and plumbing and bill of materials. l) The winch and mooring should be suitable for inflation and deflation of the Aerostat when moored at the mooring structure. Fixtures for this, if any, are to be provided by the supplier. m) Recommended spares for two years maintenance shall be supplied. n) Spare kit as recommended by manufacturer for all hydraulic components/ control valves and accessories used in the system shall be supplied. o) Hydraulic hoses, tubes, end fittings connectors etc. required for two years of maintenance of the system are to be supplied. p) Access ladders q) Electronics deliverable as per point no. 4.5.1.(g) r) Warranty certificate of the complete winch and mooring system.
16.0 Time Schedule: The complete system is expected within 18 months from placement of SO. Total execution time shall be indicated with detailed activities like preparation of manufacturing drawings, procurement of materials, fabrication integration testing delivery etc shall be indicated in pert chart form at the time of tendering. The same shall be reviewed and up dated fortnightly till the delivery of the whole system. Firm should submit total plan and PERT chart along with technical bid.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 66
17.0 Guarantee/Warranty: The system shall be covered by a warranty for a period of two (02) years against malfunctioning, material and manufacturing defects.
18.0 Product Support: The contractor shall quote separately for comprehensive Annual Maintenance Contract (AMC) for a period of three (03) years after the completion of guarantee/warranty period, which shall include regular maintenance and fault repair including spares and consumable to be undertaken beyond the free warranty/guarantee period as well.
19.0 Presentation: The firm should give presentation before a committee, which include understanding of the complete system and how they complete the total task in given time frame with the PERT chart .
20.0 Compliance sheet: The contractor has to submit the completed compliance sheet (enclosed as Annexure III) and questionnaire (enclosed as Annexure IV) to ADRDE during submitting the tender Form.
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 67
1.0 SCOPE
This Acceptance test plan covers the test, inspection and acceptance procedure of winch & mooring system for Medium size aerostat.
2.0 GENERAL 2.1 All the raw material should conform to relevant specifications as mentioned in the drawings. 2.2 Manufacturer shall submit test reports of all raw material, only from govt. recognised labs. Along with a certificate that all material conform to relevant specification. 2.3 Rep ADRDE at his discretion, can draw samples from the material and carryout test at ADRDE or at the lab considered appropriate. 2.4 Vendor will undertake 100% inspection of all components/parts and Inspection reports will be submitted to ADRDE. 2.5 Variation if any, observed in critical dimension/parameters, the part/ component would be rejected. 2.6 Manufacture has to follow the process as, described in the drawing only. Variation from specified process should have prior approval of designer/ADRDE. Product will be rejected if process has not been followed as per specification/ as mentioned in the drawings. 2.7 All the test will be carried out in the ADRDE/Vendors Premises or any other place with the approval from ADRDE, Agra. 2.8 All the checks/Tests are to be performed in presence of ADRDE, Agra representative and a Vendor Representative. 2.9 Vendor will provide test certificates of the all the brought out items.
Acceptance Test Plan (Annexure - I)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 68
3.0 TEST CLASSIFICATION In this section we mention all the tests to be performed prior to acceptance of the systems.
3.1 Preliminary Checks i) Objectives: a) To check whether the dimensions of all components are within specified tolerances or not. b) To check whether material of requisite strength and chemical composition is used or not. c) To check whether finish and workmanship of the components are of good quality or not.
ii) Preliminary test consist of following type of tests
a) Dimensional checks: All the machined components should be checked for their dimensional accuracy within the tolerances specified in the drawings. These checks should be performed using suitable measuring instruments.
b) Material checks: All the materials used in the fabrication of various winch components should be test for their Chemical composition and Mechanical properties. The tested properties should have values in accordance with those specified in the relevant standards.
c) Welding test: Welding test is to be done during fabrication and after fabrication. Vender will submit all the test reports.
Acceptance Test Plan (Annexure - I)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 69
(d) Finish and workmanship test: All the machined components should be checked for Lay, Waviness, Surface flaws, Burrs by means of a Surface micrometer. All plated components should be tested for the plating thickness, which should be in accordance with thickness specified in the relevant IS. This test is essential to ensure that the peeling of plating does not occur.
e) Lubrication Check: The lubrication of the moving parts of the system should be checked by imparting motion to them under No load, Full load and Overload conditions. The motion in each of these cases should not be accompanied by any abnormal noise due to friction or misalignment.
f) Hydraulic checks: All brought items are checked for their test certificates. The fabricated components are checked for their intended use and functionality in standard hydraulic test bench or govt. approved laboratories in standard testing conditions.
3.2 Functional Test The functional test can be classified into two phases
3.2.1 Phase 1 (Winch assembly) All the tests performed on winch is to be done using suitable Test Winch which is to be fabricated by the vendor at their premises. The test winch should be duly approved by ADRDE, Agra. Following are the list of tests to be conducted:
Acceptance Test Plan (Annexure - I)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 70
(a) Capstan Brake load holding test: Capstan is tested for its braking capacity i.e. 90000 N. A load of specified value will be applied on the tether wrapped over the Capstan. Brake should not slip and no abnormal vibration and heating should be observed in any component. This load is gradually applied on the tether using a suitable actuator. At maximum load i.e. 90000 N load should be applied for at least 5 minutes.
(b) Stow drum test and spooler test: The objective of the test is to check the performance of the stow drum with speed varying from 0 75 m/min at a load of 6000 N. Minimum 4 complete layer on stow drum should be checked for proper winding and unwinding.
(c) Nose line/close haul Winch Test These winches are tested to winding and unwinding of the rope for specified load and speed (i.e. 1500 kg and 30 m/min).
3.2.2 Phase 2 (Integration trials) It consists of testing of the system after integration of each subsystem
a) Synchronization test The objective of the test is to test the synchronization between the capstan & stow drum assembly during operational loads. The winch is run at full load i.e. 34000 N and at specified speed i.e. 75 m/min for 5 cycles each in winding and unwinding mode with a pause of 5 min. and ensures smooth functioning of subsystems. (one cycle consist of winding & unwinding of min 350 m length of tether) b) Starting friction torque test The objective of the test is to verify the starting frictional torque (1200 Nm) of the Slewing bearing when complete is mounted over the slewing bearing. Acceptance Test Plan (Annexure - I)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 71
c) Structural test The objective of the test is to check the structural strength of the integrated system by simulating operational load conditions. The load will be applied on the winch and mooring system at the various points using crane etc. Based on the various load cases, critical load case(s) has (have) been identified and accordingly load has been applied to check the structural strength.
d) Cradle & latch Test The cradle of the system should be checked for tilting through actuator as well as the locking/unlocking of the nose probe in the latch assembly. The locking mechanism of the nose probe will be checked for 15000 N.
e) Mooring Tower actuator test The objective of this test is to check the actuation mechanism of the Mooring tower actuator & its load holding capacity for any angle from 0 110 0 .
f) Flying sheave Test: Flying sheave should rotate 360 degrees freely around the horizontal axis. It should also be able to tilt on both side (port side and starboard side) up to the stopper and return back to nutral position when tilting load has been removed. It should also be tested for 9000 kg load. This load test can be combine with the structural test.
g) Operational check and Leak test of Air Bags The Air Bags have been inflated to its maximum allowable pressure using pneumatic power pack and checked for any leakage by applying soap solution. Acceptance Test Plan (Annexure - I)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 72
h) Load test
This test is performed basically to check whether the structure can meet the loading requirements as stated in the specifications.
i) Operational check of Air Bags The Air Bags of the mooring system should be capable of supporting the aerostat without any leakage in the Air Bags.
j) Static Acceptance Test The static acceptance test is intended to check whether the structure is capable of carrying the design loads without undue distortion and without developing serious defects.
3.3 Environmental Test: All components/parts/subsystem supplied by the vender should environmentally tested as specified in the specification. A test certificate in this regard is provided by the vendor.
3.4 Integration Test (With balloon, tether etc.):
A complete trial integrating tether and Medium size aerostat will be flown tested up to height of 1000 m and carried out performance checks as specified in the specification. The system should meet all operational requirements.
Acceptance Test Plan (Annexure - I)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 73
List of Spare Parts for winch & mooring system for medium size Aerostat:
Sl. No. Item Qty Remark 1. Close haul/nose line winch assembly 1 no. 2. Stow drum and spooler assembly 1no. 3. Capstan assembly 1 no. 4. Cradle 1 no. 5. Pedestal 1 no. 6. Flying sheave 1 no. 7. Control console 1 no. 8. Tether guide assembly 1 no. 9. High tension sensor assembly 1 no. 10. Low tension sensor assembly 1 no. 11. Air bags 1 set 12. Pneumatic system 1 set 13. Pressure line filter 1 no. 14. Return line filter 1 no. 15. Hydraulic Power pack (same used in the winch and mooring system for medium size aerostat) with all its accessories, valves, proportional valves, Hydraulic Pump, Hydraulic motors, Hydraulic cylinder for mooring tower, Rotary actuator, oil cooler unit etc. 1 set 16. Hydraulic fittings 1 Set 17. Hydraulic Seals 1 Set 18. Hydraulic hose 1 set 19. Tyre with tube (besides 2 tyre-tube provided with trailer) 4 no. 20. Access ladder for access to the control cabin(It should have proper side and overhead protection) 1 no. 21. Access ladder for access the roof of the winch enclosure(it should have proper side and overhead protection) 1 no.
Note: All the items should be packed nicely in such a way that they should fulfil all the environmental as well as transportation condition mentioned in the specification LIST OF SPARES (Annexure II)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 74
Sl. No. Scope of work Vendor Compliance 1 Design of whole system based on specification including FEM analysis of the system.
2 Preparation of Configuration Document, Preliminary Design Report (PDR), Critical Design Report (CDR) etc.
3 Review of the design by experts to be nominated by ADRDE.
4 Preparation of manufacturing drawings of all the systems and components including assembly drawing in AUTOCAD and 3D modelling duly approved by ADRDE.
5 Review of acceptance Test Procedure (ATP) based on draft ATP provided by ADRDE.
6 Preparation of QAP and WPS(Welding Procedure Specification) Document.
7 Fabrication of the complete system
8 Testing of sub-assemblies of the system as per ATP at firms premises.
9 Integration, installation and commissioning of whole system at ADRDE, Agra or place provided by ADRDE, Agra.
10 Fabrication of test jigs and fixtures required in manufacturing and testing.
11 Acceptance Testing as per ATP.
12 Preparation of Test Report(including stage inspection report)
COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 75
Sl. No. Specification Vendor Compliance 1 The Winch and mooring system is required to hold the medium size Aerostat.
2 Mooring structure should be made in foldable modules to enhance the ease in transportation. The dimension of the winch and mooring system in the folded condition should not be more than 12 m (length) X 2.5 m (width) X 3.7m (height). The folding/unfolding operation should be mechanised (preferably hydraulically/electro-mechanical). The suitable locking arrangements should be provided during transportation and actual operational condition.
3 The winch is required to be capstan type with level winding arrangement (spooler) for uniform winding of tether, Single tether with hydraulic as well as electronic control.
4 Mooring system should be turn table type, hard nose with nose cradle and a latch assembly. Mooring system must have freedom of wind - vaning.
5 A pedestal hydraulic power drive is required to orient the winch and mooring system as per the requirement of the Aerostat.
6 The winch should be capable of hoisting and de hoisting the Aerostat at a tether tension of 34000 N at winding speed of 75 m/min.
7 The speed of the winch and mooring system should be varied from 0 to 75 m/min.
8 The Nose line winch and close haul winches should be designed to operate at 30 m/min at a load of 15000 N. However it should withstand a load of 30000 N.
COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 76
Sl. No.
Specification Vendor Compliance 9 Operating limits: The system should be capable of withstanding the following conditions in different orientations: (a) 70 Knots (36 m/s) wind speed when the balloon is moored on the structure and faces into the wind. (b) Side force corresponding to 20 knots (10.29 m/s) wind speed, which acts in case the bearing fails to rotate.
10 Winch and mooring system is capable of withstanding 90000 N acting at the flying sheave. The structure, flying sheave, Pulleys etc should be design to withstand that much of load.
11 The whole structure should able to rotate freely at a torque value 1200 Nm or less.
12 The break holding capacity of the winch system should be 90000 N. It means that when this much of load will come on the tether, the tether should not unwind itself from the winding drum.
13 All Aerostat program e.g. launching, recovery, mooring, controlling etc can be done should be done at single place i.e. at the operator cabin inside the winch enclosure. Provision should be made so that operator can communicate with other crew members.
14 A provision should be made in the cradle and latch assembly for automatic release of nose probe from the cradle. 15 Provision should be made to digital display and record the various parameters e.g. winding/unwinding speed of the main winch, tether tension value before and after the capstan, tension value of the nose line and close haul lines, Tether released out from the drum and tether storage length, Temperature of hydraulic oil, level of the hydraulic oil in the reservoir etc.
COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 77
Sl. No.
Specification Vendor Compliance 16 Data logging facility should be provided to record the data for minimum Fifteen (15) days. A rugged storage data device should be provided along with the system.
17 A portable data storage and analysis device and a online rugged data streaming device should also be provided for analysis of the store data. 18 All operation should be done by joystick provided at operator cabin. However provision should also be made to operate the system through hydraulic lever through PVG for redundancy. In case power failure the manual operation should also be provided.
19 The operator can also operate the system form the ground through remote/operator panel, instead of sitting in the operating cabin if the need arises. A Radio Frequency link in this regard should also be available.
20 Pneumatic Power Pack and airbag is controlled and operated from the controller cabin.
21 The winch should be automatically stop the operation when the seventh (7 th ) turn of the lowest layer of the tether remains on the stow drum.
22 Synchronization of two close haul winches, nose line winch, capstan and stow drum will be made. This means capstan, stow drum, two close haul winch and nose line winch should be operated simultaneously at same speed. The maximum winding/unwinding speed in this case will be 30 m/min
23 The winch and mooring should be suitable for inflation and deflation of the Aerostat when moored at the mooring structure.
COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 78
Sl. No.
Specification Vendor Compliance 24 All the items should be used for the fabrication of the winch and mooring system should be of flameproof & explosion proof quality.
25 All fasteners e.g. nuts and bolts, studs etc used in the assembly should be of suitable strength and protection with corrosion.
26 The system should be transportable by road in folded conditions.
27 Access ladder should be provided to access the operator cabin and the roof of the winch enclosure. Access ladder should have proper side and overhead protection.
28 The hydraulic oil shall be selected as per following temperature range. Storage temperature 20 0 C to +70 0 C, Operating temperature 10 0 C to +55 0 C
29 Cradle is able to tilt +125 0 and 45 0 from the horizontal
30 A slewing bearing of suitable capacity is to be provided which can withstand radial, axial and tilting moments.
31 Material to be used for fabrication of the structure is marine grade anti-corrosive steel.
32 One sets of Slip rigs integrated with FORJ are provided to supply the power to the prime mover as well as two way transfer the data from the airborne to the ground. Such slip ring and FORJ is to be provided at the stow drum to provide power and data to the tether. The Power slip ring with central hole is to be provided at the pedestal to transfer the power from the main supply to the rotating winch and mooring system.
COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 79
Sl. No.
Specification Vendor Compliance 33 The trailer should be suitably selected/designed to house the system as well as compatible with the prime mover TATA LPS 4018.
34 Provision should be made to grounding the lightening braid of the tether.
35 The winch enclosure should be properly covered so that the winch enclosure is protected from dust, rain etc. To reduce the heat load on the air conditioner the panels of the cover should be made of insulating material.
36 The critical components of the system should sustain the following environmental conditions:
a) Ambient temperature
Operating temperature range: 10 0 C to +55 0 C
Storage temperature range: 20 0 C to +70 0 C
b) Humidity: up to 95% at +40 o C, non-condensing conditions.
c) Altitude up to 3350 m from AMSL d) Rain intensity (IS: 9000 part 16, Static pressure 100 15 kpa, 4 shower used at an angle of 45 0 for 01 hour duration).
e) Salinity (IS: 8252 part 10 Clause 4.2.2) f) Dust as encountered in desert areas (IS: 9000 part 12, Temperature 40 3 0 C, relative humidity 40% steam of dust laden air, dust concentration less than 10 3 g for a duration one hour). g) Fungus growth as encountered in tropical climates (not encountered in mechanical components).
COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 80
Sl. No.
Specification Vendor Compliance 37 The system should also be designed to cater the various load cases given in the specification at point no 3.2(xxxvii).
38 Inspection will be carried out by the Director ADRDE, Agra or his authorized representative and will be carried out in stages for raw materials, machined components, assembled components and bought out components.
39 Painting as per point no.7.0 of the specification 40 Adequate internal protection should be provided for hollow structural component sections. 41 Integration, Installation and commissioning as per point no. 8.0 of specification 42 Materials for Fabrication/Integration/installation areas per point no.9.0 of specification 43 Quality control should be as per point no. 10.0 of specification. 44 Quality control for welding should be as per point no. 10.1 of specification. 45 Perfection of Work should be as per point no. 11.0 of specification. 46 Safety requirements should be as per point no. 12.0 of specification. 47 Warranty of the system for 2 years. 48 Delivery Period (18 months after placement of Supply order) 49 Product support (AMC)( 3 years after completion of warranty period). COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 81
Sl. No. Deliverable Vendor Compliance 1 A complete set of detailed manufacturing drawings (in 3D and 2D) of every supplied component along with assembly drawing in both hard as well as soft form.
2 Complete Design Report i.e. Configuration document, Preliminary Design Report (PDR), Critical Design Report (CDR) (including FEM Analysis report) in both hard as well as soft (in solid model) form. Document should be given in doc format.
3 QAP and WPS Document in both hard as well as soft (in solid model) form. Document should be given in doc format. 4 One set of fabricated Winch and Mooring System along with Trailer and spares. List of spares is attached as Annexure -II. 5 Schedule of spare parts with proper part nos. and source of supply and portable rate of consumption.
6 List of all brought out items with their test certificates.
7 System description, Operational, maintenance and repair/trouble shooting manuals.
8 Inspection and test reports of all components as well as the assembly.
9 Compliance report of the Acceptance test of the winch and mooring system.
10 Part list, part specification with literatures of all components. The catalogue and data sheet of all brought out item.
11 Drawings of hydraulic circuit and plumbing and bill of materials.
12 The winch and mooring should be suitable for inflation and deflation of the Aerostat when moored at the mooring structure. Fixtures for this, if any, are to be provided by the supplier.
13 Recommended spares for two years maintenance shall be supplied.
COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 82
Sl. No. Deliverable Vendor Compliance 14 Spare kit as recommended by manufacturer for all hydraulic components/ control valves and accessories used in the system shall be supplied.
15 Hydraulic hoses, tubes, end fittings connectors etc. required for two years of maintenance of the system are to be supplied.
16 Access ladders
17 Warranty certificate of the complete winch and mooring system.
18 Electronics deliverable as per following: (i) Master controller (ii) System Software with their licenses (iii) Console with HMI, CPU (iv) Feedback Sensors (v) Operator desk with SBC and operator dialog terminal and push buttons and levers (vi) Networking cable and associated hardware (vii) MCC Panel (viii) Slip rings (one of 8kVA rating other 250 kVA rating) (ix) Hybrid FORJ (2 no. one for the stow drum other for spare) (x) 3 Automatic voltage controller (8 kVA) (xi) Portable rugged data streaming device (xii) Portable data storage and analysis device (xiii) Back up supply (xiv) Communication system for maintenance crew and operator (xv) Engineering services (xvi) Commissioning services COMPLIANCE SHEET (ANNEXURE III)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 83
Sl. No. Task Questionnaires Vendor comment 1 Designing : Design of whole system based on specification including FEM analysis of the structure (i) Whether firm has designed trailer mounted system of about 30 Ton weight in the past. Please furnish details in brief.
(ii) Whether firm has independent design office and design team if yes, please specify the following.
(a) How many designers are working in their design team.
(b) What are different software design tools are available with the firm. The details of workstation/licenses of the computing/analysis software (IDEAS/ANSYS/UNIGRAPHICS/Pro-E/SOLIDWORKS) etc. Vender should have at least 6 licenses.
(c) Has FEM analysis has been carried out on 30 Ton or more weight class structure in the past. Please furnish details in brief.
(d) Has the firm have the experience in designing & fabricating the winch system in the past of about 3.5 Ton tension in the rope or more.
(e) Whether the firm has experience in designing & fabricating of Hydraulic system for circuits of 300 bar and 300 lpm or more.
QUESTIONNAIRES (ANNEXURE IV)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 84
(iii) Whether the firm has supplied electronic/ electrical system with PLC/SBC based in the past. Please provide details. (iv) Whether the firm has experience in integrating multidisciplinary system in the past.
S. No. Task Questionnaires Vendor comment 2
Fabrication: (i) Whether the firm has an overhead crane of 20 T capacity at 12 m height or more.
Fabrication of winch and mooring system
(ii) Whether the firm has 40 x 40 m area (approx) for fabricating and assembly of the mooring structure.
(iii) Whether the firm has TIG and MIG welding plants please specified the number. (iv) Please specified how many welder are approved for TIG &MIG welding procedures from competent authority.
(v) Please specify, whether firm have executed any work related to large structure in the past.
(vi) Please specify whether the firm carried out EMI/EMC and environmental testing on electrical/electronics equipment in the past. (vii) Please specify that the following machines are available with the firm:
General purpose m/c (Qty)
(a) Power hacksaw (b) Lathe (specify the capacity and quantity)
(c) Milling m/c (specify the capacity and quantity) QUESTIONNAIRES (ANNEXURE IV)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 85
(d) JIG boring m/c (specify the capacity and quantity)
(e) Surface grinder m/c (specify the capacity and quantity)
(f) Cylindrical grinder m/c (specify the capacity and quantity)
(g) Any other m/c (specify name, capacity and quantity) Special Machines
(a) CNC machine centre
(b) CNC lathe machine (c) CNC milling m/c
(d) Spline cutting machine (e) Tool room machine for making jigs and fixtures. (viii) Please specify that following material handling equipments are available with the firm.
(a) Fork lifter 3 Ton or more. (b) Crane 10 Ton capacity or more.
(c) Elevated platforms. (d) Hydraulic trolley for lifting materials.
3
Installation, Integration, testing, Operation & Inspection Facilities Whether the firm has the following: (i) Hard flooring on which the system can be assembled. Specify the Area.
(ii) Independent QA team & inspection lab. Knowledge of test procedures.
(iii) Measuring instruments like
QUESTIONNAIRES (ANNEXURE IV)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 86
(a) Vernior Calliper (For measuring of 1 m length)
(b) Micro meter 500 mm
(c) 3D Co-ordinate m/c
(d) Micro examination m/c for materials (e) Capable of measuring inspection jig for 18 m structure length.
(iv) Hydraulic circuit test facility like:
(a) Leakage test
(b) High pressure test (500 bar or more)
(c) Other Hydraulic test and maintenance facility. Please specify
(v) The sufficient power available for operating 150 kW motor and alternate power source like DG Set (250 KVA) (vi) Load test facility & its measurement capability through strain gauge method using software like lab view etc.
(vii) Material test lab facilities like:
(a) Spectrometer
(b) Chemical composition
(c) UTM (d) Hardeners tester etc
(e) Radiography test
QUESTIONNAIRES (ANNEXURE IV)
SPECIFICATION Integrated Aerostat Surveillance System-Medium Size (NAKSHATRA) Document No: ADRDE/QMS/MEG/MSD/TS/01 Dated: September 2011 Issue: 01. Revision: 00. WINCH AND MOORING SYSTEM FOR MEDIUM SIZE AEROSTAT 87
(f) Megnaflax testing etc.
(viii) Load test facility on mooring tower at different angle and its measurements
4
Execution of Govt. order in the past.
(i) Firm should specify the value of a single supply order received from the government, department of a system which they have successfully executed in the specified time in the past. Please furnish the details.
(ii) Firm should specify the financial strength and its turnover should be more than 75 crores in the last year.