Profit & Loss Report - Variation Order 3 - Approved Additional Precast Box Culvert Work
Profit & Loss Report - Variation Order 3 - Approved Additional Precast Box Culvert Work
EARTHWORKS
1 TEMPORARY WORK
1.2 Dewatering work 1 L/S - 100,000.00 - 100,000.00 100,000.00 - 100,000.00 - 100,000.00 100,000.00 -
2 EARTHWORKS
CONCRETE GRADE 25
3.2 in box culvert slab 223 m3 - 210.00 - 210.00 46,830.00 - 180.00 - 180.00 40,140.00 6,690.00
SAWN FORMWORK
3.3 to sides of box culvert slab 97 m2 - 38.00 - 38.00 3,686.00 - 32.00 - 32.00 3,104.00 582.00
STEEL REINFORCEMENT
3.5 12mm dia high tensile 116 kg - 2.75 - 2.75 319.00 - 2.50 - 2.50 290.00 29.00
3.6 8mm dia high tensile 116 kg - 2.75 - 2.75 319.00 - 2.50 - 2.50 290.00 29.00
3.7 One layer of BRC A10 in concrete slab as per drawing 445 m2 - 18.00 - 18.00 8,010.00 - 12.00 - 12.00 5,340.00 2,670.00
4 RC WING WALL
estimated 8m length, 4m height, 4 sides
CONCRETE GRADE 15
4.6 in 50mm thick as blinding 8 m3 - 180.00 - 180.00 1,440.00 - 130.00 - 130.00 1,040.00 400.00
CONCRETE GRADE 30
4.7 in wing wall 83 m3 - 225.00 - 225.00 18,675.00 - 210.00 - 210.00 17,430.00 1,245.00
SAWN FORMWORK
4.8 to sides of wing wall 182 m2 - 38.00 - 38.00 6,916.00 - 32.00 - 32.00 5,824.00 1,092.00
STEEL REINFORCEMENT
4.9 16mm dia high tensile 13376 kg - 2.75 - 2.75 36,784.00 - 2.50 - 2.50 33,440.00 3,344.00
SUNDRIES
5 APPROACH SLAB
CONCRETE GRADE 15
5.1 50mm thick to receive concrete slab 6 m3 - 180.00 - 180.00 1,080.00 - 130.00 - 130.00 780.00 300.00
CONCRETE GRADE 30
5.2 in concrete slab 16 m3 - 225.00 - 225.00 3,600.00 - 190.00 - 190.00 3,040.00 560.00
SAWN FORMWORK
5.3 to sides of concrete slab 32 m2 - 38.00 - 38.00 1,216.00 - 32.00 - 32.00 1,024.00 192.00
STEEL REINFORCEMENT
5.4 16mm dia high tensile 2457 kg - 2.75 - 2.75 6,756.75 - 2.50 - 2.50 6,142.50 614.25
5.5 16mm dia high tensile 1249 kg - 2.75 - 2.75 3,434.75 - 2.50 - 2.50 3,122.50 312.25
5.6 12mm dia mild steel as spacer bar 83 kg - 2.75 - 2.75 228.25 - 2.50 - 2.50 207.50 20.75
6 GABION WALL
CONCRETE GRADE 15
6.2 as blinding to receive gabion wall 26 m3 - 180.00 - 180.00 4,680.00 - 150.00 - 150.00 3,900.00 780.00
7 STONE MATTRESS
8 TURFING