Comparision Between PT and Conventional Slab

This document compares the costs of using a post-tensioned (PT) flat slab system versus a conventional reinforced concrete (RCC) flat slab system for a residential development project. For a typical floor, the PT system results in net savings of 29 Dhs/m2 due to reduced concrete and steel requirements compared to the RCC system. Assuming a typical floor area of 3000 m2, the net savings per floor is estimated to be 87,420 Dhs. For typical floors from first to roof level, the PT system results in net savings of 10.40 Dhs/m2 per floor and savings of 31,200 Dhs for a floor area of 3000 m2.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
1K views

Comparision Between PT and Conventional Slab

This document compares the costs of using a post-tensioned (PT) flat slab system versus a conventional reinforced concrete (RCC) flat slab system for a residential development project. For a typical floor, the PT system results in net savings of 29 Dhs/m2 due to reduced concrete and steel requirements compared to the RCC system. Assuming a typical floor area of 3000 m2, the net savings per floor is estimated to be 87,420 Dhs. For typical floors from first to roof level, the PT system results in net savings of 10.40 Dhs/m2 per floor and savings of 31,200 Dhs for a floor area of 3000 m2.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 5

Project: 2B+G+3+Duplex Residential Development / CENTRE COURT Prepared by Sheik Mohamed Date 18-08-09 Rev 0

Part: Cost comparison between conventional RCC Flat Slab System & Post Tensioned Flat Slab System
Floor: Typical Floor
Assumption
Manpower to support PT related activities = 6.25 Dhs / m
2
Purpose Residential Grouting Tendons = 2.25 Dhs / m
2
Imposed Load 9 kN/m
2
Pour strip concrete works = 1.5 Dhs / m
2
Span 7.8 m Edge shuttering & other miscell works
Total 10 Dhs / m
2
Slab Thickness
SAVINGS
PT Slab (Value Engineered Slab 210 mm
Thickness) Savings in Concrete = 0.05 m
3
/ m
2
RCC Flat Slab 260 mm
Concrete @ 350 Dhs / m
3
= 17.5 Dhs / m
2
Untensioned Reinforcement
PT Slab Savings in Steel = 24 kg/m
2
Basic Mesh at bottom 35 kg/m
3
Slab edge reinforcement 7 kg/m
3
Savings in Steel = 72 Dhs/m
2
Pour strip reinforcement 3 kg/m
3
(Steel Price including cut, bend & fix @ 3000 dhs /Tons)
Reinforcement over pier 14 kg/m
3
Reinforcement around anchorages 7 kg/m
3
Total Savings = 89 Dhs/m
2
Reinforcement for earth quake forces 6 kg/m
3
EXPENSES
Total 72 kg/m
3
For an average slab thickness of 210mm = 15.12 kg/m
2
PT Service charge = 50 Dhs/m
2
RCC Slab Expenses incurred at site due to = 10 Dhs/m
2
PT Works
Reinforcement 150 kg/m
3
(Steel in RCC slab varies between 140 - 160 kg /m
3
) Total PT Related Expenses = 60 Dhs/m
2
For an average slab thickness of 260mm = 39 kg/m
2
Net Savings = 29 Dhs/m
2
Assuming an average Floor area = 3000 m
2
Expenses incurred at Site due to PT
ASCON DESIGN DEPARTMENT
Comparision Based On Value Engineered Option
Net Savings per floor = 87,420.00 Dhs
Project: 2B+G+3+Duplex Residential Development / CENTRE COURT Prepared by Sheik Mohamed Date 18-08-09 Rev 0
Part: Cost comparison between conventional RCC Flat Slab System & Post Tensioned Flat Slab System
Floor: Typical Floors (First - Roof)
Assumption
Manpower to support PT related activities = 6.25 Dhs / m
2
Purpose Residential Grouting Tendons = 2.25 Dhs / m
2
Imposed Load 14 kN/m
2
Pour strip concrete works = 1.5 Dhs / m
2
Span 7.8 m Edge shuttering & other miscell works
Total 10.00 Dhs / m
2
Slab Thickness
SAVINGS
PT Slab (Thickness Proposed by 250 mm
Project Consultant) Savings in Concrete = 0.01 m
3
/ m
2
RCC Flat Slab 260 mm
Concrete @ 350 Dhs / m
3
= 3.5 Dhs / m
2
PT Slab
Untensioned Reinforcement Savings in Steel = 22 kg/m
2
Basic Mesh at bottom & Top (Incl temperature effects) 35 kg/m
3
Slab edge reinforcement 7 kg/m
3
Savings in Steel = 67 Dhs/m
2
Pour strip reinforcement 3 kg/m
3
(Steel Price including Material, cut, bend & fix @ 3000 dhs /Tons)
Reinforcement over pier 14 kg/m
3
Reinforcement around anchorages 7 kg/m
3
Total Savings = 70.40 Dhs/m
2
Reinforcement for earth quake forces 6 kg/m
3
EXPENSES
Total 72 kg/m
3
For The Slab thickness of 250mm = 18 kg/m
2
PT Service charge = 50 Dhs/m
2
RCC Slab Expenses incurred at site due to = 10 Dhs/m
2
PT Works
Reinforcement 155 kg/m
3
(Steel in RCC slab varies between 140 - 160 kg /m
3
) Total PT Related Expenses = 60 Dhs/m
2
For the slab thickness of 260mm = 40.3 kg/m
2
Net Savings = 10.40 Dhs/m
2
Assuming average Floor area = 3000 m
2
Net Savings per floor = 31,200.00 Dhs
ASCON DESIGN DEPARTMENT
Expenses incurred at Site due to PT Comparision Based on Existing Detail
Span To Depth Ratio For
PT Slab = 38
RCC Slab = 33
Project: Value Analysis Exercise Prepared by Sheik Mohamed Date 9/3/2009 Rev 0
Part: Cost comparision between conventional RCC Flat Slab system & Post Tensioned Flat Slab System
Floor: Mechanical Floor
Assumption
Manpower to support PT related activities = 6.25 Dhs / m
2
Purpose Mechanical Floor Grouting Tendons = 2.25 Dhs / m
2
Imposed Load 14 kN/m
2
Pour strip concrete works = 1.5 Dhs / m
2
Span 8.5 - 9 m Edge shuttering & other miscell works
Total 10 Dhs / m
2
Slab Thickness
SAVINGS
PT Slab 250 mm
Savings in Concrete = 0.05 m
3
/ m
2
RCC Flat Slab 300 mm (Assuming average PT slab thickness as 230mm against RCC slab of 310mm thick)
Concrete @ 350 Dhs / m
3
= 17.5 Dhs / m
2
Untensioned Reinforcement
PT Slab Savings in Steel = 29 kg/m
2
Basic Mesh at bottom & Top (Incl temperature effects) 35 kg/m
3
Slab edge reinforcement 7 kg/m
3
Savings in Steel = 71 Dhs/m
2
Pour strip reinforcement 3 kg/m
3
(Steel Price including cut, bend & fix @ 2500 dhs /Tons)
Reinforcement over pier 14 kg/m
3
Reinforcement around anchorages 7 kg/m
3
Total Savings = 89 Dhs/m
2
Reinforcement for earth quake forces 6 kg/m
3
EXPENSES
Total 72 kg/m
3
For an average slab thickness of 250mm = 18 kg/m
2
PT Service charge = 60 Dhs/m
2
RCC Slab Expenses incurred at site due to = 10 Dhs/m
2
PT Works
Reinforcement 155 kg/m
3
(Steel in RCC slab varies between 140 - 160 kg /m
3
) Total PT Related Expenses = 70 Dhs/m
2
For an average slab thickness of 300mm = 46.5 kg/m
2
Net Savings = 19 Dhs/m
2
Assuming average Floor area = 2500 m
2
Net Savings per floor = 46,875.00 Dhs
ASCON DESIGN DEPARTMENT
Expenses incurred at Site due to PT