This document is a prefunctional checklist for switchgear, panelboards, motor control centers, and transformers. It contains sections to verify the equipment identification and location, requested documentation, equipment details, installation checks, operational checks, sensor and actuator calibration, and final sign-off. The checklist is used to confirm the equipment is complete and ready for functional performance testing prior to the contractors signing off and the owner allowing the tests to proceed. Any outstanding items are noted on an attached deficiency form.
Download as DOCX, PDF, TXT or read online on Scribd
100%(1)100% found this document useful (1 vote)
926 views
Pre - Functional Checklist Documentation 9
This document is a prefunctional checklist for switchgear, panelboards, motor control centers, and transformers. It contains sections to verify the equipment identification and location, requested documentation, equipment details, installation checks, operational checks, sensor and actuator calibration, and final sign-off. The checklist is used to confirm the equipment is complete and ready for functional performance testing prior to the contractors signing off and the owner allowing the tests to proceed. Any outstanding items are noted on an attached deficiency form.
a. The above systems and components integral to this equipment are complete and ready for Functional Performance Tests. The Prefunctional Checklist items are complete and have been checked off only by parties having direct knowledge of the event, as indicted below, respective to each responsible contractor. This Prefunctional Checklist is submitted for approval and is subject to the attached list of outstanding items not completed successfully. Submit a Deficiency Form upon completion of any outstanding or deficient items. None of the outstanding items preclude safe and reliable functional tests being performed.
b. ___ Deficiency Form attached.
c. This Prefunctional Checklist does not take the place of the manufacturers recommended checkout and Start-up procedures or report.
d. Contractors assigned responsibility for sections of the Prefunctional Checklist shall be responsible to ensure that their subcontractors complete and check off their Checklist items.
e. Prefunctional Checklist items shall be completed as part of Start-up and initial checkout, preparatory to functional testing.
Contractor/Entity Company Abbreviation MD Anderson Staff MD ANDERSON Architect/Engineer A/E General Contractor / Construction Manager
GC Mechanical Contractor MC Electrical Contractor EC Building Automation System Provider
BAS Test, Adjust, and Balance Firm TAB Commissioning Consultant CA
2. Requested Documentation Submitted:
Specified Requirement Yes No Date to be Submitted a) Manufacturers Product Data including Performance Data and Shop Drawings, as approved by Architect/Engineer
b) Required Test Reports and/or Certifications c) Installation and Start-up Manual and Plan d) Wiring Diagrams, Control Schematics and Sequences e) Operating and Maintenance Manual Content for Applicable System
f) Equipment Matrix
3. Equipment Verification:
Item Specified Submitted Installed Manufacturer Model Number Serial Number Service Equipment Rating (amps) Voltage/Phase
4. Installation Checks:
a) Unit and General Installation Yes No Comments 1. Permanent labels affixed 2. Physical condition acceptable, no visible damage, cabinets in place
3. Properly mounted on equipment pad and anchored 4. Maintenance access acceptable 5. Interior clean and dry 6. Meter(s) installed per Contract Documents 7. Disconnects installed and labeled 8. Disconnects are pad lockable in open position 9. Circuit breakers installed and labeled 10. Fuses installed a) Unit and General Installation Yes No Comments 11. Conduits installed and connected 12. Cable/conduit routing does not obstruct access 13. Equipment room properly ventilated, air-conditioned, heated, fire/smoke wall separated, fire/smoke dampered, fire sprinklered, fire alarmed and illuminated (normal, emergency and battery backed-up fixtures)
14. As-built drawings updated
b) Switchgear (service entrance 1500kVA and above) and Switchboards (service entrance less than 1500 kVA) Yes No Comments 1. Free standing metal enclosure 2. Cobber buses 3. Penetration to utility service area and equipment per code
c) Distribution Panelboards and other Panelboards Yes No Comments 1. Tin plated copper buses 2. Each circuit identified and labeled 3. Space for additional circuits exist
d) Motor Control Centers Yes No Comments 1. Tin plated copper buses 2. Main breakers installed and labeled 3. Each circuit identified and labeled
e) Transformers Yes No Comments 1. Dry type installed 2. Unit properly labeled and identified
f) Electrical and Controls Yes No Comments 1. Panel devices labeled and wiring tagged per Contract Documents
2. I/O devices labeled and wiring tagged per Contract Documents
3. Digital inputs and outputs operational 4. All electrical connections tight 5. Proper grounding installed for the electrical system, equipment, components, and unit
6. Safeties in place and operable 7. Sensors, transmitters, gages, etc., installed 8. Sensors calibrated (see below) 9. Control system interlocks hooked up and functional 10. All control devices and wiring complete 11. Lightning protection installed f) Electrical and Controls Yes No Comments 12. Surge protection installed
g) Final Yes No Comments 1. Start-up report completed and attached with this Prefunctional Checklist
2. Safeties and safe operating ranges for this equipment have been reviewed and accepted
3. System is ready for Functional Performance Test
5. Operational Checks:
a. These checks supplement the manufacturers list. This is not the Functional Performance Test.
Operational Checks Yes No Comments 1. Associated Prefunctional Checklists are complete and accepted
2. Fuses are good 3. Resistance check(s) complete with results attached 4. Disconnect switch operates smoothly with full contact 5. Specified point-to-point checks have been completed and documentation record submitted for this system
6. Sensor and/or Actuator Calibration:
a. All field-installed temperature sensors, pressure sensors, meters, and gages, and all actuators and valves on this piece of equipment shall be calibrated. Sensors installed in the unit at the factory with calibration certification provided are not required to be field calibrated.
b. All test instruments have had a certified calibration within the last 12-months: Y / N
c. Sensor/Actuator Verification Table
Sensor or Actuator Correct Location (Y/N) (1) Thermometer or Gage Value BAS Value (2) Instrument Measured Value (3) Pass (Y/N)
1) Thermometer/Gage reading is the reading of the permanently mounted instrument on the equipment. 2) BAS is the Building Automation System. Instrument = testing instrument. 3) All sensors are calibrated within required tolerances ___ YES ___ NO
FINAL SIGN-OFF
Contractors attest that the above items have been verified and meet the requirements of the Contract Documents except as noted on the attached Deficiency form.
General Contractor: Print Name:
Signature:
Title:
Date:
Electrical Subcontractor Print Name:
Signature:
Title:
Date:
Other Subcontractor: Print Name:
Signature:
Title:
Date:
Prefunctional Checklist received and reviewed for completeness by MD ANDERSON representatives. Functional Performance Test can proceed.