OBSERVE SAFETY LIFESAVER DISTRIBUTION COMMISSIONING WORK INSTRUCTION HIGH VOLTAGE OVERHEAD LINE Note: This instruction covers the checking of all replacements or new installations of high voltage overhead power lines (three phase and single phase) to confirm the integrity of the overhead network.
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
100 views
Distribution Commissioning Work Instruction
OBSERVE SAFETY LIFESAVER DISTRIBUTION COMMISSIONING WORK INSTRUCTION HIGH VOLTAGE OVERHEAD LINE Note: This instruction covers the checking of all replacements or new installations of high voltage overhead power lines (three phase and single phase) to confirm the integrity of the overhead network.
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7
OBSERVE SAFETY LIFESAVER
DISTRIBUTION COMMISSIONING WORK INSTRUCTION
HIGH VOLTAGE OVERHEAD LINE
Note: This instruction covers the checking of all replacements or new installations of high voltage overhead power lines (three phase and single phase) to confirm the integrity of the overhead network.
Work Package No.:________________ DFIS PID/Pole Number (From): ________________
(To): ________________
1. CONDUCTOR TENSIONS CHECK Tension the conductors as per Conductor Tension Table and record. Date Tensioned / / Conductors at correct tension Conductor Size and Type Conductor Temperature 0 C Average bay Length metres Tension (dynamometer) kg Beat bay length metres Tension (beat method) Seconds/5 wave return
2. INSTALLATION AND CONSTRUCTION CHECKS Inspect the constructed and carry-out the following checks: Insure that the earth resistance test results at all earth points is acceptable Check that the construction complies with the Distribution Construction Standard Check the structures are numbered and/or labeled correctly Check the conductor arrangement and correct clearances from ground, buildings and trees Check the conductor for damage/s and are secured correctly Check that all line taps and earth connections are completed correctly and secured Check all the ground work is completed
3. ENERGISATION Energizing HV overhead line Ensure that all working earths and programmed earths are removed (if applicable) Check the HV fuses are correct (if applicable) Energize the line as per switching program # Check phasing at NOP (Normal Open Point) if applicable
4. HANDOVER OF RESPONSIBILITIES Commissioning Officer: ___________________________________________Pay No._____________
Signature: Date: Company:
X
OBSERVE SAFETY LIFESAVER DISTRIBUTION COMMISSIONING WORK INSTRUCTION LOW VOLTAGE AERIAL BUNDLED CONDUCTOR
Note: This instruction covers the checking of all replacements or new installations of high voltage overhead power lines (three phase and single phase) to confirm the integrity of the overhead network.
Work Package No.:________________ DFIS PID/Pole Number (From): ________________
(To): ________________
1. CONDUCTOR TENSIONS CHECK Tension the conductors as per Conductor Tension Table and record. Date Tensioned / / Conductors at correct tension Conductor Size 150mm 95mm Conductor Temperature 0 C Average bay Length metres Tension (dynamometer) kg
2. CONTINUITY TESTS Use a resistor box and 500 V insulation resistance tester to positively distinguish cable ends. Test Connections Test Results Resistor Values Red to neutral
White to neutral
Blue to neutral
3. INSULATION RESISTANCE TESTS Using a 500 V insulation resistance tester for a minimum duration of 1 minute. Test Connections Test Results Acceptable Values Red to White 100 M or higher for new cables
10 M or higher for aged cables White to Blue Blue to Red Red to Neutral White to Neutral Blue to Neutral
4. INSTALLATION AND CONSTRUCTION CHECKS
Check that the construction complies with the Distribution Construction Standard Check the structures are numbered and/or labeled correctly Check the conductor arrangement and correct clearances from ground, buildings and trees Check that all line taps and neutral connections are completed correctly and secured Check all the ground work is completed
X
X
X
OBSERVE SAFETY LIFESAVER
5. ENERGISATION Energizing the LV ABC conductor Ensure that all short circuiting equipment has been removed Check the LV fuses are correct (if applicable) Energize the circuit in accordance with the LV Switching Program. Record the Switching Program number:
Ensure that the LV network is only supplied from the supply transformer and not interconnected with any other transformer before proceeding to the next step.
Conduct a Metrel test at the furthermost part of the LV network from the supply transformer, preferably at the NOP (normally open point) and record results below
Red White Blue Test type (Acceptable results in brackets) / / / Voltages () Z Z Z Z line ( 1) / / / R-Earth10K () U1 n: V U1 n: V U1 n: V U1 n and U1 Pe (225-254 V) 216-264V are acceptable only during emergency condition Un-Pe (0 6V) U1 Pe: V U1 Pe: V U1 Pe: V Un Pe: V Un Pe: V Un Pe: V Phase out across NOP if applicable and record the results below. Red - Red V Acceptable results (0 10 V) White - White V Blue - Blue V
6. HANDOVER OF RESPONSIBILITIES Commissioning Officer: ___________________________________________Pay No._____________
Signature: Date: Company:
DISTRIBUTION COMMISSIONING WORK INSTRUCTION THREE PHASE POLE MOUNTED TRANSFORMER
Note: Following tests/checks must be carried out on all replacements or new installations and before putting into service. This is the minimum testing requirement for a 3 Phase Pole Mount Transformer before energisation.
Work Package No.:________________ DFIS PID________________________
1. INSULATION RESISTANCE TESTS a) Ensure that the earth resistance has been tested and is acceptable b) All electrical connections have been disconnected including MEN link c) Insulation resistance must be a minimum duration of 1 minute Transformer winding insulation resistance test Test Connection Test Voltage Resistance Expected results Primary/HV to Tank 2.5 Kv Greater than 1M Primary/HV to Secondary/LV 1 Kv Greater than 100M Secondary/LV to Tank 1 Kv Greater than 100M
2. INSTALLATION AND CONSTRUCTION CHECKS Inspect the following: Rating plate Tap setting Tank and bushings Oil level Wiring installation Neutral connection MEN link Transformer matches system voltage Transformer tap is at the position as per network planning Transformer bushings and tank in good condition (no oil leaks) Oil level satisfactory (if sight glass available) Transformer installed as per construction standard Neutral connected and earthed and MEN link reconnected All DFIS labels fitted and numbering correct as per DFIS sheet.
3. ENERGISATION Energising transformer without load Check HV fuses are correct Energize transformer as per switching program. (check for abnormal noise) Measured secondary voltages phase to neutral within acceptable range (225 254 V) R N _______ Volts, W N_________ Volts, B N ________ Volts
Measured secondary voltage between phases within acceptable range (389 440 V) R W _______ Volts, W B_________ Volts, B R ________ Volts
Energizing the transformer with load Ensure that all short circuiting equipment has been removed Check the LV fuses are correct (if applicable) Energize the circuit in accordance with the LV Switching Program. Record the Switching Program number:
Ensure that the LV network is only supplied from the supply transformer and not interconnected with any other transformer before proceeding to the next step.
Conduct a Metrel test at the furthermost part of the LV network from the supply transformer, preferably at the NOP (normally open point) and record results below
Red White Blue Test type (Acceptable results in brackets) / / / Voltages () Z Z Z Z line ( 1) / / / R-Earth10K () U1 n: V U1 n: V U1 n: V U1 n and U1 Pe (225-254 V) 216-264V are acceptable only during emergency condition Un-Pe (0 6V) U1 Pe: V U1 Pe: V U1 Pe: V Un Pe: V Un Pe: V Un Pe: V Phase out across NOP if applicable and record the results below. Red - Red V Acceptable results (0 10 V) White - White V Blue - Blue V
4. HANDOVER OF RESPONSIBILITIES Commissioning Officer: ________________________________________________ Pay No._____________
Signature: Date:
OBSERVE SAFETY LIFESAVER DISTRIBUTION COMMISSIONING WORK INSTRUCTION EARTHING SYSTEM RESISTANCE TESTING (ALL EQUIPMENT)
Note: This instruction covers testing of the earth resistance of electrodes or earth systems Good earthing systems are essential for the protection of personnel from electrical shock and the protection of electrical equipment from dangerous over voltages and excessive currents.
The following tests must be carried out on all replacements or new installations and before putting into service. If testing existing earth electrodes are connected to the network then refer to Work Practice Manual.
Work Package No.:________________ DFIS PID________________________
1. PRE TEST CHECK Visual Inspection Rated System Voltage Volts Equipment being protected (e.g. transformer, PTS) No. of earth electrodes per earthing point # Approximate depth of earth electrode Metres Size of earth cables mm Check that the earth conductors are correctly installed to the earth bar (if applicable) and that there are no signs of damage
Check if the earth electrodes are properly installed and are connected to the earth system by earth conductors
Check that the earth electrode is not within 15 m of an existing Telstra joint pit Check that the earth pits are properly installed, access to the earth electrode is possible and the earth pit lids are in good condition
Check that the compound earth grid is bonded to the fence and connected to MEN (if applicable)
2. EARTHING SYSTEM RESISTANCE TEST Fall of Potential Method Test Equipment: Earth Resistance Tester, (3 pole Fall of Potential test method) The earth electrode under test (Electrode # 1) must be disconnected from the earthing system. This test involves using two test instrument electrodes (Electrode # 2 and Electrode # 3) From the electrode under test (electrode # 1) install (electrode # 2), 50 metres away and electrode # 3, 31 metres (around 62% the distance between electrode # 1 and # 2) in a straight line. This test is repeated by moving electrode # 3, 3 metres forwards and backwards from its initial position.
The final test result is the average of the three test results. (See diagram below).
OBSERVE SAFETY LIFESAVER
Test results 1 st Test 2 nd Test 3 rd Test Initiate Test. Electrode # 2 @ 50 metres Electrode # 3 @ 31 metres
Record value Reposition electrode # 3 + 3.0 metres from initial position
Record value Reposition electrode # 3 - 3.0 metres from initial position
Record value
Average the value of the three test and record
Acceptable Values Description Maximum Allowable Resistance High Voltage System 30 Low Voltage System: Aggregate transformer rating up to 50 KVA 30 Low Voltage System: Aggregate transformer rating over 50 KVA but not greater than 500 KVA 15 Low Voltage System: Aggregate transformer rating over 500 KVA 10
3. HANDOVER FOR COMMISSIONING Commissioning Officer: ___________________________________________Pay No.______________