This document provides the basic approach and general conditions for preparing a standard data book for building works in Andhra Pradesh. It outlines that the description of items will be brief and link to relevant specifications. Concrete work can be mixed manually or with machinery, and concrete can be laid with winches or machinery. The inputs are analyzed based on average working conditions in the state. Overhead costs include site setup, equipment, labor costs, taxes, and contractor profits of 14%. Materials, labor rates, and machinery usage charges will be based on local rates. Testing of soil, materials and works are included.
Download as XLS, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
300 views
Revised Data (Buildings)
This document provides the basic approach and general conditions for preparing a standard data book for building works in Andhra Pradesh. It outlines that the description of items will be brief and link to relevant specifications. Concrete work can be mixed manually or with machinery, and concrete can be laid with winches or machinery. The inputs are analyzed based on average working conditions in the state. Overhead costs include site setup, equipment, labor costs, taxes, and contractor profits of 14%. Materials, labor rates, and machinery usage charges will be based on local rates. Testing of soil, materials and works are included.
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 95
A.P.
REVISED STANDARD DATA
PART-III
BUILDINGS
Basic approach and General conditions and assumptions for the preparation of Standard Data Book for Building Works.
The Basic approach for the preparation of Standard Data for Building works is indicated as under. Description of Items : The description of items is given briefly and linked with the relevant specifications in AP Standard Specifications. Use of Machinery : For concrete work mixing is proposed with machinery as well as manually. For laying concrete, lifting is proposed with either by winches or machinery. Manual means have been proposed for all other items. Working Conditions : The inputs for the Data have been analysed for the average working conditions prevailing in the state. Over Heads : This is assumed to include interalia the following elements: Site accommodation, setting up plant, access road, water supply, electricity and general site arrangements Office furniture, equipment and communications Provision towards expenditure on: Corporate office of contractor Site supervision Documentation and "as built" drawings Mobilisation / de-mobilisation of resources . Labour camps with minimum amenities required as per labour laws and transportation to work sites Light vehicles for site supervision including administrative and managerial requirements Setting up of Laboratories for quality control, field and laboratory testing for control of quality of various items of work and documentation of test results as per requirement of the Specifications. Minor T&P including vibrators for concrete work and survey instruments and setting outworks, including verification of line, dimensions, taking trial pits and bore holes, where required. Watch and ward Arraignment for Traffic and Traffic Management during construction. Provision towards safeguarding environment Sundries Financing expenditure of the Contractor Work Insurance / compensation. 4.1 Sales/Turnover Tax / VAT: Allow 4% and which should be exhibited separately. In agreements it should be mentioned that it will be reimbursed as per actuals. Contractors Profit : It is considered to allow 14% towards over head charges (Item 4) and Contractor Profits put together.
General : The AP Standard Specifications shall be followed with relevant BIS Specifications of various materials and construction work. The sources of all materials and samples of materials are required to be approved by the Engineer-in- Charge before starting of the work. For reinforced steel both HYSD and TMT bars continuing to IS 1786 and MS bars upto 36 mm dia as per IS 432 Part 1 have been considered. The Data includes inputs for testing of soil, materials and works. The contractor shall arrange and to provide and maintain an adequate equipped field laboratory. The Data includes inputs for testing of soil, materials and works. The contractor shall arrange and to provide and maintain an adequate equipped field laboratory. Quality Control of Works shall be governed by relevant AP Standard Specifications read with BIS Specifications. Sundries to cater for unforeseen contingency and miscellaneous items have been added in the overheads. The various activities of works shall also be documented in photographs and video cassettes. The Data for various Earth Work Excavation Items including classification of soils shall be as in Standard Data for Roads and Bridges. The course and fine aggregates shall conform to IS : 383 Basic Inputs : The Standard Data Book is based on the requirements of basic inputs of materials, labour and machineries for various items. The rates for labour, material and usage charges of machinery for the area where the project is located are to be ascertained from local authorities/enquiries to prepare Schedule of Rates for the area. The basic rates of materials, such as, stone boulders, stone for masonry, stone ballast, stone dust, moorum, gravel, lime, manure, sludge, quarry sweep, kankar, bricks, brick ballast, crushed slag, etc. at quarry / crusher sites shall be fixed by the Board of Chief Engineers yearly (effective from 1 st June to 31 st May). However, the basic rate of materials hand broken / machine broken, crushed aggregates shall be based on Analysis in Chapter 1 of Roads & Bridges. The cost of materials should include the cost at source and the cost of their carriage (as per Schedule of rates arrived in Chapter 1 of Roads & Bridges for conveyance, loading and unloading charges) upto the work site. Labour The labour wages should be as per rates fixed by the Board of Chief Engineers keeping the minimum wages fixed as per Minimum Wages Act. Skilled labour include mason, carpenter, blacksmith, mechanics and other trades.
Materials : Quantities of materials considered in the rate analysis are approximate for the purpose of estimation and include normal wastages. Actual consumption would depend on mix design. The rates of material should include basic cost at locations of stone crushers/factory/rail head and cost of its carriage to the site of work/plant including loading, unloading and stacking.
Credit for Dismantled Material: The dismantled materials should be examined and a realistic assessment made for credit for such materials, which can be utilized for works or auctioned. The basic rates should include all octroi charges, toll tax, sale tax, VAT, municipal taxes and other local taxes, etc. The Data for the following items of work shall be as per Data Items covered in AP Standard Data for Roads & Bridges Loading, Unloading, Carriage, Crushing of Materials Site Clearance Earth Work Items including classification of Excavated Material. Horticulture Concrete Items : For Concrete Work, the Grades of Concrete covered by Data Book is in accordance to IS 456 : 2000. The nominal mix of concrete shall be used upto M 20 Grade only. For RCC Work, M 20 Grade nominal mix may be used in exceptional cases of Remoteness. The design mix shall invariably used for M 20 and above Grades of Concrete as per IS 456 : 2000. The Data accounts for inputs of Material by Weight and use of ordinary mixture or ordinary mixer with weight batch arrangement. The Hire charges for vibrators are included in overhead charges. with weight batch arrangement. The Hire charges for vibrators are included in overhead charges. 10% extra cement may be provided for concreting under water, where ever required. Steel requirement of cement concrete work is required to be provided separately. Plants and Equipment : The usage charges for machines include ownership charges, cost of repair and maintenance including replacement of tyres and running and operating charges which includes crew, fuel and lubricants. The hire charges shall be worked out based on the Guidelines issued CWC for machinery covered in CWC Guidelines. Measurement and Rates Measurement of various items and their units shall be as defined in the respective Clauses of AP Standard Specifications. The rates for various items of work shall include all sub items defined in the respective Clauses of AP Standard Specifications. Privileged Document The Standard Data Book is for Department use only. It should not be produced in any court of law as reference/ authority and to that extent it is a privileged document.
BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-1 MORTARS BLD-CSTN-1-1 1 Cement Mortar (1 : 1) Unit : 1cum A. MATERIALS: Cement kg. 1440.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for sand cum 1.05 B. MACHINERY - Nil - - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Grand Total BLD-CSTN-1-2 2 Cement Mortar (1 : 1.5) Unit : 1cum A. MATERIALS: Cement kg. 960.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for sand cum 1.05 B. MACHINERY - Nil - - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Grand Total BLD-CSTN-1-3 3 Cement Mortar (1 : 2) Unit : 1cum A. MATERIALS: Cement kg. 720.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for sand cum B. MACHINERY - Nil - - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Grand Total BLD-CSTN-1-4 4 Cement Mortar (1 : 3) Unit : 1cum A. MATERIALS: Cement kg. 480.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for sand cum 1.05 B. MACHINERY - Nil - - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Grand Total BLD-CSTN-1-5 5 Cement Mortar (1 : 4) Unit : 1cum A. MATERIALS: Cement kg. 360.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for sand cum 1.05 B. MACHINERY - Nil - - - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Grand Total Andhra Pradesh Standard Data Buildings 659 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-1-6 6 Cement Mortar (1 : 5) Unit : 1cum A. MATERIALS: Cement kg. 288.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for sand cum 1.05 B. MACHINERY - Nil - - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Grand Total BLD-CSTN-1-7 7 Cement Mortar (1 : 6) Unit : 1cum A. MATERIALS: Cement kg. 240.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for sand cum 1.05 B. MACHINERY - Nil - - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Grand Total BLD-CSTN-1-8 8 Cement Mortar (1 : 8) Unit : 1cum A. MATERIALS: Cement kg. 180.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for sand cum 1.05 B. MACHINERY - Nil - - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Grand Total BLD-CSTN-2 CONCRETE, DAMP PROOF COURSE & REINFORCEMENT BLD-CSTN-2-1 9 Plain Cement concrete Grade M20 - Nominal Mix using 20mm metal with hand mixing Unit : 1cum A. MATERIALS: Cement Kg 400.00 Coarse aggregate 20mm cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 B. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 2.36 Water (including for curing) kl 1.20 Grand Total Note : For Nominal Mix : Considering table 9 IS 456 : 2000, the quantity of cement needed is 405 kgs / cum. Hence proposed 400 kgs of cement for cum of CC M20 660 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-2-2 10 Plain Cement concrete Grade M10 - Nominal Mix upto Plinth level using 40mm metal using concrete mixer Unit : 1cum A. MATERIALS: Cement Kg 220.00 Coarse aggregate 40mm cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Water (including for curing) kl 1.20 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 C. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 1.39 Grand Total BLD-CSTN-2-3 11 PCC Grade M15 - Nominal mix 1:2.5:5 (Hand mixing) Unit = 1cum A) Material Cement kg 275.00 Coarse sand cum 0.48 40 mm aggregate cum 0.54 20 mm aggregate cum 0.27 10 mm aggregate cum 0.09 Water (including for curing) kl 1.20 B) Labour Mason (1st Class) day 0.10 Mazdoor (Unskilled) day 2.36 Grand Total BLD-CSTN-2-4 12 Plain Cement concrete (1:4:8) using 40 mm metal with hand mixing upto Plinth level Unit = 1cum A. MATERIALS: Cement kg 162.00 Coarse aggregate 40 mm cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Water (including for curing) kl 1.20 B. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 2.36 Grand Total BLD-CSTN-2-5 13 Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture. All work upto plinth level. Unit = 1cum A. MATERIALS: Cement kg 162.00 Coarse aggregate 40 mm cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Water (including for curing) kl 1.20 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 661 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 C. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 1.39 Water Charges 1% - Grand Total BLD-CSTN-2-6 14 Plain Cement concrete (1:5:10) using 40 mm metal with hand mixing upto Plinth level Unit = 1cum A. MATERIALS: Cement kg 129.60 Coarse aggregate 40 mm cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Water (including for curing) kl 1.20 B. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 2.36 Grand Total BLD-CSTN-2-7 15 Plain Cement concrete (1:5:10) using 40 mm metal with Concrete mixture. All work upto plinth level. Unit = 1cum A. MATERIALS: Cement kg 129.60 Coarse aggregate 40 mm cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Water (including for curing) kl 1.20 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 C. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 1.39 Grand Total BLD-CSTN-2-8 16 Plain Cement concrete (1:6:10) using 40 mm metal with hand mixing upto Plinth level Unit = 1cum A. MATERIALS: Cement kg 129.60 Coarse aggregate 40 mm cum 0.90 Fine aggregate (Sand) cum 0.54 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.54 Water (including for curing) kl 1.20 B. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 2.36 Grand Total BLD-CSTN-2-9 17 Plain Cement concrete (1:6:10) using 40 mm metal with Concrete mixture upto Plinth level Unit = 1cum A. MATERIALS: Cement kg 129.60 Coarse aggregate 40 mm cum 0.90 Fine aggregate (Sand) cum 0.54 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.54 Water (including for curing) kl 1.20 662 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 C. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 1.39 Grand Total BLD-CSTN-2-10 18 Plain Cement concrete - Nominal Mix (1:3:6) using 40mm metal with hand mixing Unit : 1cum A. MATERIALS: Cement Kg 220.00 Coarse aggregate 40mm cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Water (including for curing) kl 1.20 B. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 2.36 Grand Total BLD-CSTN-2-11 19 Plain Cement concrete (M 20) Nominal Mix using 40mm metal using concrete mixer Unit : 1cum A. MATERIALS: Cement Kg 330.00 Coarse aggregate 40mm graded cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Water (including for curing) kl 1.20 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 C. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 1.39 Grand Total BLD-CSTN-2-12 20 Plain Cement concrete (M 15) Nominal Mix 1:2.5:5 using 40mm metal using concrete mixer Unit : 1cum A. MATERIALS: Cement Kg 275.000 Coarse aggregate 40mm cum 0.540 Coarse aggregate 20mm cum 0.270 Coarse aggregate 10mm cum 0.090 Fine aggregate (Sand) cum 0.480 Seigniorage charges for C.A cum 0.900 Seigniorage charges for F.A cum 0.480 Water (including for curing) kl 1.20 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 C. LABOUR: Mason 1 st class day 0.100 Mazdoor (unskilled) day 1.390 Grand Total 663 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-2-13 21 R.C.C. M-20 Nominal Mix NEW RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) corresponding to Table 9 of IS 456 using 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges such as machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work, but excluding centering, shuttering. A FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth) A. MATERIALS: 20mm HBG graded metal cum 0.900 Sand cum 0.450 Cement Kgs 400.000 B. LABOUR: 1st Class Mason day 0.133 2nd Class Mason day 0.267 Mazdoor (Both Men and Women) day 3.600 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 Cost of Diesel for Miller Liters 0.133 Cost of Petrol for Vibrator Liters 0.667 Water (including for curing) kl 1.200 BASIC COST per 1 cum B COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS A. MATERIALS: 20mm HBG graded metal cum 0.900 Sand cum 0.450 Cement Kgs 400.000 B. LABOUR: 1st Class Mason day 0.167 2nd Class Mason day 0.167 Mazdoor (Both Men and Women) day 4.700 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 Water (including for curing) kl 1.200 BASIC COST per 1 cum C RCC SLABS, BEAMS A. MATERIALS: 20mm HBG graded metal cum 0.900 Sand cum 0.450 Cement Kgs 400.000 B. LABOUR: 1st Class Mason day 0.067 2nd Class Mason day 0.133 Mazdoor (Both Men and Women) day 2.500 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 0.267 Water (including for curing) kl 1.200 BASIC COST per 1 cum 664 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 DESIGN MIX CONCRETE (WEIGH BATCH at SITE) BLD-CSTN-2-14 22 Supply and placing of the Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code from standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication charges for finished item of work. A FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth) ANY GRADE OF MIX 20mm HBG graded metal cum 0.80 Sand cum 0.40 1st Class Mason day 0.133 2nd Class Mason day 0.267 Mazdoor (Both Men & Women) day 4.600 Weigh Batcher Hire charges (Machine mixing) charges h 1.333 Water (including for curing) kl 1.200 BASIC COST per 1 cum B COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS ANY GRADE OF MIX 20mm HBG graded metal cum 0.80 Sand cum 0.40 1st Class Mason day 0.167 2nd Class Mason day 0.167 Mazdoor (Both Men & Women) day 5.600 Weigh Batcher Hire charges (Machine mixing) H 1.333 Water (including for curing) kl 1.200 BASIC COST per 1 cum C RCC SLABS, BEAMS ANY GRADE OF MIX 20mm HBG graded metal cum 0.80 Sand cum 0.40 1st Class Mason day 0.067 2nd Class Mason day 0.133 Mazdoor (Both Men & Women) day 3.077 Weigh Batcher Hire charges (Machine mixing) h 0.308 Water (including for curing) kl 1.200 BASIC COST per 1 cum For Design mix concrete, allow Cement as follows (for estimate purpose only) : Kgs 350 380 400 420 430 M 25 M 30 M 35 M 40 Note : Quantity of cement proposed for various design mixes is for estimating purpose only. Actual quantity of cement will be as per approved mix design. Similarly quantity for coarse and fine aggregates is for estimating purpose and the exact quantity shall be as per the mix design. Nominal mix of grades M20 is to be used with adequate supervision and quality control requirements. Excluding Cement cost Grade M 20 665 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-2-15 23 Supply and placing of the Ready Mix (RMC) Standard Design Mix Concrete grade as per IS 4926-2003 with minimum cement content as per IS code 456-2000 using 20 mm graded metal, from standard suppliers approved by the department including pumping, laying concrete, vibrating, curing etc. complete but excluding cots of steel and its fabrication charges, centering, shuttering for finished item of work. A FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth) Unit : 1cum A. MATERIALS: Coarse aggregate 20mm graded cum 0.80 Fine aggregate (Sand) cum 0.40 Seigniorage charges for C.A cum 0.80 Seigniorage charges for F.A cum 0.40 Water (including for curing) kl 1.20 B. MACHINERY Batching plant at 20 cum per hour hour 0.222 Transit mixer 4cum capacity for lead upto 1km hour 0.222 Concrete Pump day 0.222 C. LABOUR: Mason 1 st class day 0.056 Mason 2 nd class day 0.056 Mazdoor (unskilled) day 0.917 Grand Total Note : Wherever concrete is carried out using batching plant, transit mixer, concrete pump, then Admixtures @ 0.4% of weight of cement may be added for achieving desired slump of concrete. If concentrated Admixture is proposed, only 0.04% of weight of Cement shall be used. B COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS Unit : 1cum A. MATERIALS: Coarse aggregate 20mm graded cum 0.80 Fine aggregate (Sand) cum 0.40 Seigniorage charges for C.A cum 0.80 Seigniorage charges for F.A cum 0.40 Water (including for curing) kl 1.20 B. MACHINERY Batching plant at 20 cum per hour hour 0.444 Transit mixer 4cum capacity for lead upto 1km hour 0.444 Concrete Pump day 0.444 C. LABOUR: Mason 1 st class day 0.111 Mason 2 nd class day 0.222 Mazdoor (unskilled) day 1.556 Grand Total C RCC SLABS, BEAMS Unit : 1cum A. MATERIALS: Coarse aggregate 20mm graded cum 0.80 Fine aggregate (Sand) cum 0.40 Seigniorage charges for C.A cum 0.80 Seigniorage charges for F.A cum 0.40 Water (including for curing) kl 1.20 Excluding Cement any Grade. 666 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 B. MACHINERY Batching plant at 20 cum per hour hour 0.133 Transit mixer 4cum capacity for lead upto 1km hour 0.133 Concrete Pump day 0.133 C. LABOUR: Mason 1 st class day 0.033 Mason 2 nd class day 0.067 Mazdoor (unskilled) day 0.433 Grand Total Kgs 350 380 400 420 430 Description of Structure a. FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth) b. COLUMNS, LINTELS, WATER TANKS, RCC WALLS 1.333 Hrs c. RCC SLABS, BEAMS 0.267 Hrs BLD-CSTN-2-16 24 Damp proof course 40mm thick with cement concrete (1:2:4 Nominal mix), using 12mm hard broken stone aggregate including cost of all materials, seigniorage charges, excluding conveyance charges of materials, including the cost of machinery, labour charges, mixing, placing in position, leveling, vibrating, curing etc. complete for finished item of work. (Using concrete mixer) Unit = 25 sqm A. MATERIALS: Cement kgs 320.00 Coarse aggregate 12mm cum 0.90 Fine aggregate (sand) cum 0.45 Seigniorage charges of coarse aggregate cum 0.90 Seigniorage charges of sand cum 0.45 Form work L.S. B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 C. LABOUR: Mason 1 st class day 0.1 Mazdoor (unskilled) day 1.98 D. Grand Total for 25 sqm Rate per Sqm = D/25 Nil Nil 10% 10% M 40 Note: LIFT CHARGES - for all RCC Items 1. For Lift Charges of Labour, increase @ 10% on labour charges for each upper floor on Ground Floor Rate 2. For Lift Charges of Materials only, for lifting Concrete above 6.1 M (2nd floor onwards) Winch/ Lift hire charges may be allowed at following rates: Basic Rate for 2nd Floor (6.1 M) for each additional floor (3.05 M) over and above 2nd floor (6.1 M) M 20 M 25 M 30 M 35 For Design mix concrete, allow Cement as follows (for estimate purpose only) : Grade 667 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-2-17 25 Damp proof course 50mm thick with 1:2:4 cement concrete Nominal mix, using 12mm hard broken stone aggregate including cost of all materials, seigniorage charges, excluding conveyance charges of materials including the cost of machinery, labour charges, mixing, placing in position, leveling, vibrating, curing etc. complete for finished item of work. (Using concrete mixer) Unit = 20 sqm A. MATERIALS: Cement kgs 320.00 Coarse aggregate 12mm cum 0.90 Fine aggregate (sand) cum 0.45 Seigniorage charges of coarse aggregate cum 0.90 Seigniorage charges of sand cum 0.45 Form work L.S. B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 C. LABOUR: Mason 1 st class day 0.1 Mazdoor (unskilled) day 1.98 D. Grand Total for 20 sqm Rate per Sqm = D/20 BLD-CSTN-2-18 26 11.7 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specifications for Bars below 36 mm dia including over laps and wastage, where they are not welded Unit = t (a) Material HYSD bars including 5 per cent for overlaps and wastage t 1.05 Binding wire kg 6.00 (b) Labour for cutting, bending, shifting to site, tying and placing in position Blacksmith / Bar bender day 2.00 Mazdoor (Unskilled) day 6.40 Sundries on Material (c) Overheads on (a+b) (d) Contractors profit on (a+b+c) Rate per t = a+b+c+d A Supplying, fitting and placing HYSD bar reinforcement in foundation complete including wastage, as per drawings and technical specifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for Bars 36 mm dia and above, where welding required to be done compulsorily. Unit = t (a) Material HYSD bars including 2.5 per cent for wastage t 1.025 Welding Electrodes @ 5 per joint (14 joints / ton) each 70.000 Welding Charges (Hire charges of Welding Machine) Hr 10.00 Binding wire kg 6.00 1000 & 1200 1000 & 1200 668 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 (b) Labour for cutting, bending, shifting to site, tying and placing in position Welder day 2.50 Blacksmith day 2.00 Mazdoor (Unskilled) day 6.40 (c) Overheads on (a+b) (d) Contractors profit on (a+b+c) Rate per t = a+b+c+d BLD-CSTN-2-19 27 11.8 Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications for Bars below 36 mm dia including over laps and wastage, where they are not welded. Unit = t (a) Material TMT bars including 5 per cent for overlaps and wastage t 1.05 Binding wire kg 6.00 (b) Labour for cutting, bending, shifting to site, tying and placing in position Blacksmith / Bar bender day 2.00 Mazdoor (Unskilled) day 6.40 (c) Overheads on (a+b) (d) Contractors profit on (a+b+c) Rate per t = a+b+c+d A Supplying, fitting and placingTMT bar reinforcement in foundation complete including wastage, as per drawings and technical specifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for Bars 36 mm dia and above, where welding required to be done compulsorily. Unit = t (a) Material TMT bars including 2.5 per cent for wastage t 1.025 Welding Electrodes @ 5 per joint (14 joints / ton) each 70.000 Welding Charges (Hire charges of Welding Machine) Hr 10.00 Binding wire kg 6.00 (b) Labour for cutting, bending, shifting to site, tying and placing in position Welder day 2.50 Blacksmith day 2.00 Mazdoor (Unskilled) day 6.40 (c) Overheads on (a+b) (d) Contractors profit on (a+b+c) Rate per t = a+b+c+d BLD-CSTN-2-20 28 11.9 Supplying, fitting and placing MS bar reinforcement in foundation complete as per drawings and technical specifications for Bars below 36 mm dia including over laps and wastage, where they are not welded Unit = t (a) Material MS bars including 5 per cent for overlaps and wastage t 1.05 Binding wire kg 6.00 (b) Labour for cutting, bending, shifting to site, tying and placing in position Blacksmith / Bar bender day 2.00 Mazdoor (Unskilled) day 6.40 1000 & 1200 1000 & 1200 669 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 (c) Overheads on (a+b) (d) Contractors profit on (a+b+c) Rate per t = a+b+c+d BLD-CSTN-3 BRICK WORK, HONEY - COMBWORK BLD-CSTN-3-1 29 Brick Masonry in CM (1:3) with Bricks with traditional size 23 x 11 x 7 cms 2nd class a Unit = 1cum i A. MATERIALS: Cement kg 96.00 Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 Fine aggregate (Sand) cum 0.20 Seigniorage charges for F.A cum 0.20 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total Note : For Bricks 2.4 % wastage taken. ii Brick Masonry in CM (1:4) with Bricks traditional size 23 x 11 x 7 cms 2nd class Unit = 1cum A. MATERIALS: Cement kg 72.00 Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 Fine aggregate (Sand) cum 0.20 Seigniorage charges for F.A cum 0.20 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total iii Brick Masonry in CM (1:5) with Bricks traditional size 23 x 11 x 7 cms 2nd class Unit = 1cum A. MATERIALS: Cement kg 57.60 Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 Fine aggregate (Sand) cum 0.20 Seigniorage charges for F.A cum 0.20 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total 670 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 iv Brick Masonry in CM (1:6) with 2nd class Bricks traditional size 23 x 11 x 7 cms Unit = 1cum A. MATERIALS: Cement kg 48.00 Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 Fine aggregate (Sand) cum 0.20 Seigniorage charges for F.A cum 0.20 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total v Brick Masonry in CM (1:8) with Bricks traditional size 23 x 11 x 7 cms 2nd Class Unit = 1cum A. MATERIALS: Cement kg 36.00 Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 Fine aggregate (Sand) cum 0.20 Seigniorage charges for F.A cum 0.20 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total b Brick Masonry in CM (1:3) with Bricks traditional size 23 x 11 x 7 cms 1st Class Unit = 1cum A. MATERIALS: Cement kg 96.00 Bricks1st Class traditional size 23 x 11 x 7 cms Nos 512.00 Fine aggregate (Sand) cum 0.20 Seigniorage charges for F.A cum 0.20 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total Note : 1. When Mortar mix is changed as CM 1:4, 1:5, 1:6 and 1:8, proportionate quantity of cement has to be substituted. No change in other data. 2. When First class Modular Bricks are used provide 570 nos bricks of size 19 x 9 x 9 cms. 671 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-3-2 30 Brick Masonry in CM (1:3) with Modular Bricks 19 x 9 x 9 cms 2nd class i Unit = 1cum A. MATERIALS: Cement kg 100.60 Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 Fine aggregate (Sand) cum 0.21 Seigniorage charges for F.A cum 0.21 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total ii Brick Masonry in CM (1:4) with Modular Bricks 19 x 9 x 9 cms 2nd class Unit = 1cum A. MATERIALS: Cement kg 75.60 Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 Fine aggregate (Sand) cum 0.21 Seigniorage charges for F.A cum 0.21 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total iii Brick Masonry in CM (1:5) with Modular Bricks 19 x 9 x 9 cms 2nd class Unit = 1cum A. MATERIALS: Cement kg 60.48 Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 Fine aggregate (Sand) cum 0.21 Seigniorage charges for F.A cum 0.21 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total iv Brick Masonry in CM (1:6) with Modular Bricks 19 x 9 x 9 cms 2nd class Unit = 1cum A. MATERIALS: Cement kg 50.40 Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 Fine aggregate (Sand) cum 0.21 Seigniorage charges for F.A cum 0.21 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total iv Brick Masonry in CM (1:8) with Modular Bricks 19 x 9 x 9 cms 2nd class Unit = 1cum A. MATERIALS: Cement kg 37.80 Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00 Fine aggregate (Sand) cum 0.21 Seigniorage charges for F.A cum 0.21 B. LABOUR: 672 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Grand Total BLD-CSTN-3-3 31 11.5 cm wide Brick masonry for super-structure on ground floor in cm (1:3) using second class traditional size bricks including cost of all materials, seigniorage charges, labour and all operations for constructing half brick masonry, mixing cement mortar, curing etc., complete for finished item of work, but excluding conveyance charges of materials. unit:10sqm A. MATERIALS: Country bricks, second class traditional size 23x11x7cm nos 565.000 Cement kg. 106.000 Sand cum 0.220 Seigniorage charges for sand cum 0.220 B. LABOUR: Mason 1 st class day 0.600 Mason 2 nd class day 0.600 Mazdoor (unskilled) day 2.750 Add water charges 1% 1.00% Grand Total BLD-CSTN-3-4 32 Reinforced Brick Masonary walls of 11.5cm in CM(1:6) using FlyAsh bricks having a crushing strength of not less than 35.00kg/cm2 and using two mild steel bars of 6m dia in every third layer of brick masory, with free joints of the main block work including cost and seignorage charges and conveyance of all materials and water from approved sources to work site and all operational, incidental, labour charges such as scaffolding mixing mortor constructing masonary lift charges, curing etc. complete but excluding the cost of steel and its fabrication charges for finished item of work as per SS 509 Ground Floor : A. MATERIALS: II Class Bricks cum 512.000 C.M.(1:6) cum 0.200 B. LABOUR: Mason 1 st class day 0.600 Mason 2 nd class day 0.600 Mazdoor (unskilled) day 2.750 Grand Total BLD-CSTN-3-5 33 Exposed brick masonry for super structure on ground floor in cm (1:6) using wire cut bricks or moulded bricks including making horizontal and vertical grooves 10mm Wide 12mm deep, cost of all materials, seigniorage charges, labour and all operations, mixing cement mortar, curing etc., complete for finished item of work, but excluding conveyance charges of materials unit:1cum A. MATERIALS: Wire cut bricks or moulded bricks size 19x9x9cm nos 520.000 Cement kg. 48.00 673 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Sand cum 0.20 Seigniorage charges for sand cum 0.20 B. LABOUR: Mason 1 st class day 0.57 Mason 2 nd class day 0.57 Mazdoor (unskilled) day 2.54 Add water charges 1% 1.00% Grand Total Note : Compressive strength of individual Brick shall not be less than 70 kg / cm 2 BLD-CSTN-3-6 34 Brickwork in arches in cement mortar 1:4 complete including centering and shuttering excluding pointing and plastering as per drawing and technical specifications Clauses 606 and 1205.1 MORD Unit = cum a) Material Brick 1st class Nos. 525.00 Cement mortar (1:4) cum 0.24 b) Labour Mazdoor (Unskilled) day 1.88 Mason (1st Class) day 2.00 c) Add for centering and shuttering @ 110% of (a+b) Grand Total BLD-CSTN-3-7 35 Honey Comb work with Bricks of traditional Size and Plastered One Coat 10 mm. thick Cement Mortar 1:5 including White Washing 2 Coats Unit = cum a) Material Brick 2nd class 23 x 11 x 7 Nos. 750.00 Cement mortar (1:5) cum 0.67 b) Labour Mazdoor (Unskilled) day 6.60 Mason (1st Class) day 2.41 Mason (2nd Class) day 6.21 White Washing 2 Coats LS LS Grand Total BLD-CSTN-3-8 36 Honey Comb work with Bricks of Modular Size and Plastered One Coat 10 mm. thick Cement Mortar 1:5 including White Washing 2 Coats Unit = cum a) Material Brick 2nd class 19 x 9 x 9 Nos. 790.00 Cement mortar (1:5) cum 0.67 b) Labour Mazdoor (Unskilled) day 6.60 Mason (1st Class) day 2.41 Mason (2nd Class) day 6.21 White Washing 2 Coats LS LS Grand Total Note : 1 ) In case cement mortar 1:3 is used, proportionate rate is to be adopted. 2) Quantity of bricks for arches will be about 10 per cent more than that for ordinary brickwork . 3) In case special arch bricks are used, the quantity of bricks per cum shall be taken as 580 Nos. 4) Rates for spandrel walls shall be taken same as for brickwork in substructure. 5) Rate for spandrel filling will depend on the filling material adopted 6) Compressive strength of individual Brick shall not be less than 70 kg / cm2 674 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-4 STONE MASONRY, DAMP PROOF COURSE, DRY STONE PACKING, QUARRY RUBBISH & GRAVEL BACKING BLD-CSTN-4-1 37 Cut Stone Masonry in CM 1:2 Unit = 1cum A. MATERIALS: Cement kg 115.20 Cut Stone Roughly dressed to shape at quarry cum 0.89 Bond Stones cum 0.16 Fine aggregate (Sand) cum 0.16 Seigniorage charges for F.A cum 0.16 B. LABOUR: Mason 1 st class day 1.05 Mason 2 nd class day 2.45 Man mazdoor day 3.50 Woman mazdoor day 2.80 Grand Total BLD-CSTN-4-2 38 CRS Masonry in CM (1:2) 1st Sort i Unit = 1cum A. MATERIALS: Cement kg 201.60 Coursed Rubble Stone cum 0.94 Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 7Nos. 0.16 Fine aggregate (Sand) cum 0.28 Seigniorage charges for F.A cum 0.28 Seigniorage charges for Stone cum 1.10 B. LABOUR: Mason 1 st class day 2.50 Mazdoor (unskilled) day 2.32 Grand Total ii CRS Masonry in CM (1:3) 1st Sort Unit = 1cum A. MATERIALS: Cement kg 134.40 Coursed Rubble Stone cum 0.94 Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 7Nos. 0.16 Fine aggregate (Sand) cum 0.28 Seigniorage charges for F.A cum 0.28 Seigniorage charges for Stone cum 1.10 B. LABOUR: Mason 1 st class day 2.50 Mazdoor (unskilled) day 2.32 Grand Total iii CRS Masonry in CM (1:4) 1st Sort Unit = 1cum A. MATERIALS: Cement kg 100.80 Coursed Rubble Stone cum 0.94 Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 7Nos. 0.16 Fine aggregate (Sand) cum 0.28 Seigniorage charges for F.A cum 0.28 Seigniorage charges for Stone cum 1.10 B. LABOUR: Mason 1 st class day 2.50 Mazdoor (unskilled) day 2.32 Grand Total Note : When Mortar mix is changed as CM 1:3, 1:4, 1:5, 1:6 and 1:8, proportionate quantity of cement has to be substituted. No change in other data. 675 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 iv CRS Masonry in CM (1:6) 1st Sort Unit = 1cum A. MATERIALS: Cement kg 67.20 Coursed Rubble Stone cum 0.94 Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum 7Nos. 0.16 Fine aggregate (Sand) cum 0.28 Seigniorage charges for F.A cum 0.28 Seigniorage charges for Stone cum 1.10 B. LABOUR: Mason 1 st class day 2.50 Mazdoor (unskilled) day 2.32 Grand Total BLD-CSTN-4-3 39 CRS Masonry in CM (1:6) 2nd Sort Unit = 1cum A. MATERIALS: Cement kg 76.80 Coursed Rubble Stone cum 0.94 Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum cum 0.16 Fine aggregate (Sand) cum 0.32 Seigniorage charges for F.A cum 0.32 Seigniorage charges for Stone cum 1.10 B. LABOUR: Mason 1 st class day 1.50 Mazdoor (unskilled) day 2.32 Grand Total BLD-CSTN-4-4 40 Coursed rubble stone masonry arch (Ist sort) in cement mortar (1:4) complete including centering etc. complete as per drawing and technical specifications Clauses 706 and 1205.1 Unit = cum A. Material Stone for CR masonry 1st sort cum 0.94 Through and bond stone (7 Nos 0.24x0.24x0.39 = 0.16 cum) Nos. 0.16 Cement mortar (Rate as in item 11.5 II) cum 0.30 B. Labour Mason (1st Class) day 3.00 Mazdoor (Unskilled) day 2.43 C. Add for centering and shuttering @ 100 % of (a+b) Grand Total BLD-CSTN-4-5 41 Ashlar Arch Work in Cement Mortar (1:4) Unit = 1cum A. MATERIALS: Cement kg 57.60 Cut Stone Roughly dressed to shape at quarry cum 0.89 Bond Stones of Cutstone quality 0.16 Fine aggregate (Sand) cum 0.16 Seigniorage charges for F.A cum 0.16 Note : 1) In case cement mortar 1:3 is used, proportionate rate is to be adopted. Note : When Mortar mix is changed proportionate quantity of cement has to be substituted. No change in other data. 2) The addition for centering and sluttering at (c) above is for arch above 6 m span. For lesser span length the addition shall be 80 per cent for span above 4 m length and 50 per cent for spans less than 4 m. 676 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 B. LABOUR: Mason 1 st class day 5.05 Mason 2 nd class day 2.45 Mazdoor (unskilled) day 6.30 Centering Charges LS Grand Total BLD-CSTN-4-6 42 Rubble Arch Work in Cement Mortar (1:4) Unit = 1cum A. MATERIALS: Cement kg 100.80 Seleted Stone of sizes as per specification (including Bond Stones) cum 1.15 Fine aggregate (Sand) cum 0.28 Seigniorage charges for F.A cum 0.28 B. LABOUR: Mason 1 st class day 0.90 Mason 2 nd class day 2.10 Mazdoor (unskilled) day 2.43 Centering Charges LS Grand Total BLD-CSTN-4-7 43 Providing & Laying reinforced cement concrete arch complete including centering and shuttering excluding reinforcement as per drawings and technical specifications Clauses 800, 900 and 1205.1 Unit = cum I RCC grade M20 nominal mix a) Material Cement t 0.40 Coarse sand cum 0.45 20 mm aggregate cum 0.54 10 mm aggregate cum 0.36 b) Labour Mason (1st Class) day 0.20 Mazdoor (Unskilled) day 2.15 c) Machinery Concrete mixer 0.4/0.28 cum capacity hour 0.40 d) Add for cost of centering and shuttering @ 50 per cent of (a+b) per sqm of surface of arch soffit Grand Total II RCC Grade M 25 (Design mix) a) Material Cement t 0.38 Coarse sand cum 0.45 20 mm aggregate cum 0.54 10 mm aggregate cum 0.36 b) Labour Mason (1st Class) day 0.20 Mazdoor (Unskilled) day 2.15 c) Machinery Concrete mixer 0.4/0.28 cum capacity hour 0.40 d) Add for cost of centering and shuttering @ 50 per cent of (a+b) per sqm of surface of arch soffit Grand Total Note : The additional cost of centering and shuttering @ 50 per cent of cost of material and labour shall hold good for arch spans of 6 m and above. For lesser length of spans, the corresponding additional cost can be taken as 40 per cent for spans above 4 m length and 30 per cent for spans less than 4 m. 677 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-4-8 44 RR Masonry in CM (1:6) Unit = 1cum A. MATERIALS: Cement kg 79.20 CR Stone cum 0.44 Rough Stone cum 0.50 Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum cum 0.16 Fine aggregate (Sand) cum 0.33 Seigniorage charges for F.A cum 0.33 Seigniorage charges for Stone cum 1.10 B. LABOUR: Mason 1 st class day 1.20 Mazdoor (unskilled) day 2.00 Grand Total BLD-CSTN-4-9 45 RR Masonry in CM (1:8) Unit = 1cum A. MATERIALS: Cement kg 59.40 . CR Stone cum 0.44 Rough Stone cum 0.50 Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum cum 0.16 Fine aggregate (Sand) cum 0.33 Seigniorage charges for F.A cum 0.33 Seigniorage charges for Stone cum 1.10 B. LABOUR: Mason 1 st class day 1.20 Mazdoor (unskilled) day 2.00 Grand Total BLD-CSTN-4-10 46 Dry Stone Masonry for Retaining Walls Unit = 1cum A. MATERIALS: Rough Stone cum 1.04 Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum cum 0.16 Seigniorage charges for Stone cum 1.20 B. LABOUR: Mason 1 st class day 0.33 Mason 2 nd class day 0.77 Mazdoor (unskilled) day 1.10 Grand Total BLD-CSTN-4-11 47 Dry Stone Masonry for Well steining Unit = 1cum A. MATERIALS: Rough Stone cum 1.04 Bond Stones cum 0.16 Seigniorage charges for Stone cum 1.20 B. LABOUR: Mason 1 st class day 0.45 Mason 2 nd class day 1.05 Mazdoor (unskilled) day 1.10 Grand Total Note : When Mortar mix is changed proportionate quantity of cement has to be substituted. No change in other data 678 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-4-12 48 Damp Proof, Course Damp Proof (or anti Proof) Course with Cuddapah / Shabad slabs 50 mm. thick in CM (1:3) (Unit - 10 sqm) A. MATERIALS: Cuddapah / Shabad slabs 50 mm. thick sqm 10.50 Cement Mortar 1:3 cum 0.15 Seigniorage charges for Stone B. LABOUR: Mason 1 st class day 0.90 Mason 2 nd class day 2.10 Mazdoor (unskilled) day 2.00 Grand Total BLD-CSTN-5 POINTING BLD-CSTN-5-1 49 Flush Pointing with CM (1:3) to Brick / CRS Masonry Unit = 10 sqm A. MATERIALS: Cement kg 14.40 Fine aggregate (Sand) cum 0.03 Seigniorage charges for F.A cum 0.03 B. LABOUR: Mason 2 nd class day 0.50 Mazdoor (unskilled) day 0.74 Grand Total BLD-CSTN-5-2 50 Flush Pointing with CM (1:3) to RR Masonry Unit = 10 sqm A. MATERIALS: Cement kg 14.40 Fine aggregate (Sand) cum 0.03 Seigniorage charges for F.A cum 0.03 B. LABOUR: Mason 2 nd class day 0.50 Mazdoor (unskilled) day 0.74 Grand Total BLD-CSTN-5-3 51 Raised Pointing with CM (1:3) to RR Masonry Unit = 10 sqm A. MATERIALS: Cement kg 28.80 Fine aggregate (Sand) cum 0.06 Seigniorage charges for F.A cum 0.06 B. LABOUR: Mason 2 nd class day 0.50 Mazdoor (unskilled) day 0.74 Grand Total BLD-CSTN-5-4 52 Raised and cut pointing on coursed or Ashlar stone masonry or concrete block walling in white cement mortar 1 : 3 (1 white cement : 3 marble dust). Details of cost for 10 sq.m Materials :- Cement mortar 1 :4 cum 0.038 Labour : Mason llnd class day 1.460 Mazdoor (unskilled) day 2.260 Add for water charges @ 1 % Add for contractor's profit and overheads @ 10% Cost for 10 sq.m. Cost per sq.m Note : When Mortar mix is changed as CM 1:4 proportionate quantity of cement has to be substituted. No change in other data. 679 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-6 PLASTERING BLD-CSTN-6-1 53 Plastering with CM (1:3), 12 mm thick Unit = 10 sqm A. MATERIALS: Cement Mortar (1:3) cum 0.15 Seigniorage charges for F.A cum 0.15 B. LABOUR: Mason 1 st class day 0.60 Mazdoor (unskilled) day 0.96 Grand Total BLD-CSTN-6-2 54 Plastering with CM (1:4), 12 mm thick Unit = 10 sqm A. MATERIALS: Cement Mortar (1:4) cum 0.15 Seigniorage charges for F.A cum 0.15 B. LABOUR: Mason 1 st class day 0.60 Mazdoor (unskilled) day 0.96 Grand Total BLD-CSTN-6-3 55 Plastering with CM (1:5), 12 mm thick Unit = 10 sqm A. MATERIALS: Cement Mortor (1:5) cum 0.150 Seigniorage charges for F.A cum 0.150 B. LABOUR: Mason 1 st class day 0.60 Mazdoor (unskilled) day 0.96 Grand Total BLD-CSTN-6-4 56 Plastering with CM (1:6), 12 mm thick Unit = 10 sqm A. MATERIALS: Cement Mortor (1:6) cum 0.15 Seigniorage charges for F.A cum 0.15 B. LABOUR: Mason 1 st class day 0.60 Mazdoor (unskilled) day 0.96 Grand Total BLD-CSTN-6-5 57 Plastering with CM (1:8), 12 mm thick Unit = 10 sqm A. MATERIALS: Cement Mortor (1:5) cum 0.15 Seigniorage charges for F.A cum 0.15 B. LABOUR: Mason 1 st class day 0.60 Mazdoor (unskilled) day 0.96 Grand Total 680 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-6-6 58 Plastering with CM (1:4), 15 mm thick Unit = 10 sqm A. MATERIALS: Cement Mortar (1:4) cum 0.19 Seigniorage charges for F.A cum 0.19 B. LABOUR: Mason 2 nd class day 0.60 Mazdoor (unskilled) day 0.96 Grand Total BLD-CSTN-6-7 59 Plastering with CM (1:4), 20 mm thick Unit = 10 sqm A. MATERIALS: Cement Mortar (1:4) cum 0.210 Seigniorage charges for F.A cum 0.21 B. LABOUR: Mason 2 nd class day 0.94 Mazdoor (unskilled) day 1.60 Grand Total BLD-CSTN-6-8 60 Plastering with CM (1:3), 20 mm thick Unit = 10 sqm A. MATERIALS: Cement Mortar (1:3) cum 0.210 Seigniorage charges for F.A cum 0.21 B. LABOUR: Mason 2 nd class day 0.94 Mazdoor (unskilled) day 1.60 Grand Total BLD-CSTN-6-9 61 Plastering with CM 2 coats, 20 mm thick, base coat in CM (1:6), 16mm thick and top coat in CM (1:4), 4mm thick with Dubara sponze finishing. . Unit = 10 sqm A. MATERIALS: Base Coat in CM(1:6), 16 mm thick Cement kg 43.00 Fine aggregate (Sand) cum 0.18 Top Coat in CM(1:4), 4 mm thick Cement kg 14.50 Fine aggregate (Sand) cum 0.04 Seigniorage charges for F.A cum 0.22 B. LABOUR: Mason 1 st class day 0.63 Mason 2 nd class day 1.47 Mazdoor (unskilled) day 3.90 Grand Total BLD-CSTN-6-10 62 Plastering with CM 2 coats, 12 mm thick, base coat in CM (1:5), 8mm thick and top coat in CM (1:3), 4mm thick with sponze finishing. Unit = 10 sqm A. MATERIALS: Base Coat in CM(1:5), 8 mm thick Cement kg 31.70 Fine aggregate (Sand) cum 0.11 Top Coat in CM(1:3), 4 mm thick Cement kg 19.20 Fine aggregate (Sand) cum 0.04 Note : When Mortar mix is changed proportionate quantity of cement has to be substituted Note : When Mortar mix is changed proportionate quantity of cement has to be substituted 681 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Seigniorage charges for F.A cum 0.15 B. LABOUR: Mason 1 st class day 0.63 Mason 2 nd class day 1.47 Mazdoor (unskilled) day 3.90 Grand Total BLD-CSTN-6-11 63 Unit - 10 sqm A) MATERIALS Rabbit wire mesh (1.0 M panna for 0.6 M drop) sqm 13.30 Cement Mortar 1:3 for 25 mm thick cum 0.25 Dry Cement for making Lumps kg 50.00 12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides sqm 21.80 Excluding HYSD Steel/ Mild steel & Binding wire B) LABOUR CHARGES 1st Class Mason day 8.00 Miller Operator day 1.00 Mazdoor (unskilled) day 10.00 c) Machinery 32.00 Machine Mixing Mortar with Miller - Hire charges Hrs 2.00 BASIC COST per 10 sqm BLD-CSTN-6-12 64 20 mm thick rough cast exterior cement plaster on walls upto height of 10 metres above ground level consisting of 10 mm thick backing coat of 1 : 3 cement mortar (1 cement : 3 sand) and 10 mm thick finishing coat of 1 : 3 cement mortar (1 cement : 3 coarse aggregate of size 6 mm to 10 mm) including arrises, chamfers and/or rounded angles not exceeding 80 mm in girth. Details of cost for 10 sq.m Materials :- Cement mortar 1:3 (1 cement: 3 sand) cum 0.110 Cement mortar 1:3(1 cement: 3 coarse aggregate of size 6 mm to 10 mm) Cement kg 52.800 Coarse aggregate of size 6 mm -10 mm cum 0.110 Mazdoo (unskilled) for mixing mortar with coarse aggreagate 6 - 10 mm day 0.020 Labour for backing coat and finishing coat - Plaster work : Mason, llnd class day 1.710 Mazdoo (unskilled) day 3.270 Extra labour for scooping : Mason, llnd class day 0.250 Mazdoor (male) day 0.250 Add for water charges @ 1 % Cost for 10 sq.m. Cost per sq.m RCM facia 5cm thick in CM (1:3) for drop walls, fins with rabbit wire mesh & nominal reinforcement as directed by Engineer-in-charge with dubara sponge finishing, including cost & conveyance of all materials to site, seigniorage charges, sales & other taxes on all materials, operational & incidental, cost and conveyance of cement, wire mesh, water to work site, centering, scaffolding and form work, lift charges etc., complete for finished items of work but excluding cost of steel & its fabrication charges, for finished item of work. (APSS No.403 & 903) RCM FACIA WORKS Note : When Mortar mix is changed proportionate quantity of cement has to be substituted 682 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-6-13 65 Rough cast exterior cement plaster on walls upto a height of 10 metres above ground level with a mixture of sand and gravel or crushed stone graded from 6 mm to 10 mm nominal size dashed over and including fresh plaster in two coats, backing coat 10 mm cement plaster 1 : 3 (1 cemen" : 3 sand) and finishing coat 10 mm cement plaster with cement mortar 1:3 (1 cement: 3 sand) mixed with 10% finely grounded hydrated lime by volume of cement including arrises, chamfers and/or rounded angles not exceeding 80 mm in girth. (a) Natural cement finish using ordinary cement. Details of cost for 10 sq.m. Materials : Cement mortar 1:3 (1 cement: 3 sand) cum 0.224 Sand and gravel or crushed stone graded from 6 mm to 10 mm nominal size Coarse aggregate of size 6 mm -10 mm cum 0.100 Carriage Grounded hydrated lime kg 9.280 Carriage Labour for backing coat and finishing coat - Plaster work : Mason, llnd class day 1.710 Mazdoo (unskilled) day 3.270 Add labour for dashing crushed stone Mason 1st class day 0.500 Mazdoo (unskilled) day 1.000 Add for water charges @ 1 % Cost for 10 sq.m. Cost per sq.m (b) Dark coloured finish using ordinary cement and pigment Details of cost for 10 sq.m. Same rate as per (a) above item () Add cost of colour kg 6.000 Add for water charges @ 1 % Add for contractor's profit and overheads Cost for 10 sq.m. Cost per sq.m (c) Light coloured finish using white cement and pigment Details of cost for 10 sq.m. Same rate as per (a) above item () Add cost of light colour kg 6.000 Add for water charges on cost of colour @ 1 % Add for contractor's profit and overheads on cost of colour and water charges Cost for 10 sq.m. Cost per sq.m 683 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-6-14 66 Pebble dash exterior plaster on walls upto a height of 10 metres above ground level with a mixture of washed pebble or crushed stone graded from 6 mm to 12 mm nominal size dashed over and including fresh cement plaster in two coats, backing coat 10 mm cement plaster 1 : 3 (1 cement : 3 sand) and finishing coat 10 mm cement plaster 1 : 3 (1 cement : 3 sand) mixed with 10% finely grounded hydrated lime by volume of cement including arrises, chamfers and/or rounded angles not exceeding 80 mm in girth Details of cost for 10 sq.m Materials : Cement mortar 1:3 cum 0.224 Grounded hydrated lime kg 9.280 Pebbles or crushed stone graded from 6 mm to 12 mm nominal size Crushed stone / Pebble of size 6 mm -12 mm cum 0.100 Labour for backing coat and finishing coat :- Mason llnd class day 1.710 Mazdoor (unskilled) day 3.270 Labour for pebble dashing Mason llnd class day 0.500 Mazdoor (unskilled) day 0.610 Add for water charges @ 1 % Cost for 10 sq.m. Cost per sq.m Plain Cement Mortar Bands : BLD-CSTN-6-15 67 20 mm thick plain cement mortar bands in cement mortar 1 : 4 (1cement : 4 sand) upto 300 mm in width (a) Flush Band :- Details of cost for 10 metres long and 10 cm wide band Materials :- Cement mortar 1 :4 cum 0.023 Labour : Mason llnd class day 0.300 Mazdoor (unskilled) day 0.350 Add for water charges @ 1 % Cost for 10 metres long and 10 cm wide band Cost per cm width x metre long b) Sunk band :- Details of cost for 10 metres long and 10 cm wide band Materials :- Cement mortar 1 :4 cum 0.023 Labour : Mason llnd class day 0.300 Mazdoor (unskilled) day 0.350 Add for water charges @ 1 % Cost for 10 metres long and 10 cm wide band Cost per cm width x metre long C) Raised Band :- Materials :- Cement mortar 1 :4 cum 0.023 Labour : Mason llnd class day 0.380 Mazdoor (unskilled) day 0.430 Add for water charges @ 1 % Cost for 10 metres long and 10 cm wide band Cost per cm width x metre long 684 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-6-16 68 20 mm thick plain cement mortar bands in cement mortar 1:4(1 cement: 4 sand) above 300 mm in width (A) Flush Band :- Details of cost for 10 sq.m Materials :- Cement mortar 1 :4 cum 0.224 Labour : Mason llnd class day 2.200 Mazdoor (unskilled) day 2.700 Add for water charges @ 1 % Cost for 10 sq.m. Cost per sq.m (B) Sunk band :- Details of cost for 10 sq.m Materials :- Cement mortar 1 :4 cum 0.224 Labour : Mason llnd class day 2.500 Mazdoor (unskilled) day 3.000 Add for water charges @ 1 % Cost for 10 sq.m. Cost per sq.m (C) Raised band Details of cost for 10 sq.m Materials :- Cement mortar 1 :4 cum 0.224 Labour : Mason llnd class day 3.000 Mazdoor (unskilled) day 3.500 Add for water charges @ 1 % Cost for 10 sq.m. Cost per sq.m Moulded Cement Mortar Bands 15 mm BLD-CSTN-6-17 69 15 mm thick moulded cement mortar band in cement mortar 1 : 4 (1cement: 4 sand) Details of cost for 10 metres long and 10 cm wide band Materials :- Cement mortar 1 :4 cum 0.023 Labour : Mason llnd class day 0.870 Mazdoor (unskilled) day 0.920 Add for water charges @ 1 % Cost for 10 metres long and 10 cm wide band Cost per cm width x metre long BLD-CSTN-6-18 70 Masonry work in CM (1:8) prop with Flyash Cement solid blocks of size 290 x 225 x 140 mm for manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs. Gypsum of 5 kgs. and stone dust including cost and conveyance of all materials, labour charges, seiniorage charges, scaffolding and curing etc., cpomplete with a compresive streangth not lessthan 50 kg/sqm for walls for Superstructure Walls. Ground Floor Unit = 1 cum A. MATERIALS: No of blocks required for one cum of Masonry day 110.000 Cost of Cement Mortar (1:6) cum 0.100 B. LABOUR Mason 1st class day 0.420 685 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Mason 2nd class day 0.920 Man Mazdoor day 0.700 Woman Mazdoor day 2.100 Total BLD-CSTN-7 FLOORING BLD-CSTN-7-1 71 Flooring with 25mm thick polished shabad stones set over base coat of CM (1:8) over already laid CC bed / RCC Roof Slab, including neat cement slurry of honey like consistency spread @ 3.3 kgs per sqm. & Jointed with neat cement to full depth including cost of all materials like cement, sand, and water and flooring stones etc., complete, including seigniorage charges, labour charges for dressing of flooring stones etc., complete for finished item of work, but excluding the cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Polished Shabad Stone (White) (0.457 x 0.457m) SSR item No. (36) sqm 11.00 Cement for CM (1:8) proportion for base coat kg. 21.60 Cement for slurry kg. 33.00 Cement for jointing kg. 20.00 Sand for CM (1:8) proportion cum 0.12 Seigniorage charges of sand cum 0.12 B. LABOUR: Mason 1 st class day 3.10 Mason 2 nd class day 1.10 Mazdoor (unskilled) day 0.86 Add water charges 1% Grand Total BLD-CSTN-7-2 72 Flooring with 40 mm thick Rough Cuddapah/Shabad stones, set over base coat of cement mortar (1 : 8) 12 mm thick over CC bed already laid or RCC roof slab, including pointing with cement mortar 1:3 duly filling joints nearly, including cost of all materials like flooring stone, cement, sand, and water etc., complete, including seigniorage charges, labour charges for dressing of flooring stones etc., complete for finished item of work, but excluding the cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Rough Cuddapah/Shabad stones (40 mm thick) (0.457 x 0.457 m) sqm 10.50 Cement for CM (1:8) proportion for base coat kg. 21.60 Cement for CM 1:3 proportion for pointing kg. 9.60 Sand for CM (1:8) proportion cum 0.12 Sand for CM (1:3) proportion cum 0.02 Seigniorage charges of sand cum 0.14 B. LABOUR: Mason 1 st class day 0.960 Mason 2 nd class day 2.240 Mazdoor (unskilled) day 3.30 Add water charges 1% Grand Total 686 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-3 73 Flooring with polished marble slab 20 mm thick set over base coat of cement mortar (1:6) 20 mm thick (joints of stone must be flushed) over CC bed already laid or RCC roof slab, including near cement slurry of honey like consistency spread @3.30 kgs per sqm. Jointed with neat cement to full depth mixed with pigment of matching shade, including cost of all materials like flooring slab, cement, sand, and water etc., complete, including seigniorage charges, labour charges for dressing, rubbing and polishing of flooring stones etc., complete for finished item of work, but excluding the cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Marble slab of size 0.305 M x 0.305 M sqm 10.10 Cement for CM (1:6) proportion for base coat kg. 48.00 Cement for slurry for bedding kg. 33.00 White Cement for pointing kg. 5.00 Sand for CM (1:6) cum 0.20 Seigniorage charges of sand cum 0.20 B. Machinery Machine for rubbing of floor day 1.00 C. LABOUR: Mason 1 st class day 2.10 Mason 2 nd class day 3.00 Mazdoor (unskilled) day 5.00 Add water charges 1% Grand Total BLD-CSTN-7-4 74 Flooring with chequrred terrazzo tiles of 22 mm thick (medium shade) set over base coat of cement mortar (1:6) 12 mm thick over CC bed already laid or RCC roof slab, including near cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed with neat cement to full depth mixed with pigment of matching shade including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, complete for finished item of work, but excluding the cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Chequerred terrazzo tiles of 22 mm thick (medium shade) sqm 10.05 Cement for CM (1:6) proportion for base coat kg. 28.80 Cement for slurry kg. 33.00 Cement for jointing & pointing kg. 6.00 Pigment kg. Sand for CM (1:6) proportion cum 0.12 Seigniorage charges of sand cum 0.12 B. MACHINERY Nill C. LABOUR Mason 2 nd class day 0.960 Man mazdoor day 2.240 Mazdoor (unskiled) day 3.30 Add water charges 1% Grand Total 687 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-5 75 Flooring with vitrified tiles of 1 st quality, set over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Vitrified tiles of 1 st quality of size sqm 10.10 Cement for CM (1:8) for base coat kg. 21.60 Cement for slurry kg. 33.00 Cement for Pointing with CM (1:3) kg. 6.000 Sand for CM (1:8) cum 0.12 Sand for pointing cum 0.020 Seigniorage charges of sand cum 0.140 B. LABOUR Mason 1 st class day 0.96 Mason 2 nd class day 2.24 Mazdoor (unskiled) day 3.30 Add water charges 1% 1.00% Grand Total BLD-CSTN-7-6 76 Flooring with ceramic tiles, set over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Ceramic tiles sqm 10.10 Cement for CM (1:8) for base coat kg. 21.60 Cement for slurry kg. 33.00 White cement kg. 2.00 Sand for CM (1:8) cum 0.12 Seigniorage charges of sand cum 0.12 B. LABOUR Mason 1 st class day 0.96 Mason 2 nd class day 2.24 Mazdoor (unskiled) day 3.30 Add water charges 1% 1.00% Grand Total 688 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-7 77 Flooring with high polished granite 16 to 18 mm mm thick slabs other than black set over base coat of cement mortar (1:8), 20 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like cement, sand water and tilesetc., complete, including seigniorage charges, labour charges for dressing of tilesetc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: High polished granite 16 to 18 mm thick slab other than black sqm 10.10 Cement for CM (1:8) for base coat kg. 36.00 Cement for slurry kg. 33.00 White cement for jointing & pointing kg. 6.00 Cement for jointing kg. Sand for CM (1:8) cum 0.20 Seigniorage charges of sand cum 0.20 B. LABOUR Mason 1 st class day 3.00 Mason 2 nd class day 1.00 Mazdoor (unskiled) day 8.00 Add water charges 1% 1.00% Grand Total BLD-CSTN-7-8 78 Flooring with marble tiles polished 8 mm thick set over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Marble tiles polished 8 mm thick sqm 10.10 Cement for CM (1:8) for base coat kg. 36.00 Cement for slurry kg. 33.00 White cement for jointing & pointing kg. 5.00 Sand for CM (1:8) cum 0.20 Seigniorage charges of sand cum 0.20 B. LABOUR (including for polishing & rubbing) Mason 1 st class day 4.00 Mazdoor (unskiled) day 8.00 Add water charges 1% 1.00% Grand Total 689 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-9 79 Flooring with granite stone tiles 8 mm thick (mirror polished of all shades) set over base coat of cement mortar (1:6), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Granite stone tiles 8 mm thick (mirror polished of all shades) sqm 10.10 Cement for CM (1:6) for base coat kg. 48.00 Sand for CM (1:6) cum 0.20 Seigniorage charges of sand cum 0.20 B. LABOUR Mason 1 st class day 4.00 Mazdoor (unskiled) day 8.00 Add water charges 1% 1.00% Grand Total BLD-CSTN-7-10 80 Flooring with decorated white back ground glazed tiles, set over base coat of cement mortar (1:6), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Decorated white back ground glazed tiles sqm 10.10 Cement for CM (1:6) for base coat kg. 28.80 Cement for slurry kg. 33.00 White cement for jointing & pointing kg. 6.00 Sand for CM (1:6) cum 0.12 Seigniorage charges of sand cum 0.12 B. LABOUR Mason 1 st class day 0.96 Mason 2 nd class day 2.24 Mazdoor (unskiled) day 3.30 Add water charges 1% 1.00% Grand Total 690 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-11 81 Flooring with pressed clay flooring tiles, set over base coat of cement mortar (1:8) 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with cement mixed with pigment of matching shade to full depth, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: 20 X 20 cm pressed clay flooring tiles 1000 Nos 0.255 Cement for CM (1:8) for base coat kg. 21.600 Cement for jointing & pointing kg. 6.000 Pointing with CM (1:3) 10sqm 1.000 Deduct CM (1:3) cum 0.040 Sand for CM (1:8) cum 0.120 Seigniorage charges of sand cum 0.120 B. LABOUR Mason 1 st class day 0.960 Mason 2 nd class day 2.240 Mazdoor (unskiled) day 4.30 Add water charges 1% 1.00% Grand Total BLD-CSTN-7-12 82 Flooring with Plain Cement tiles, set over base coat of cement mortar (1:8) 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with cement paste mixed with pigment of matching shade to full depth, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Plain cement Tiles 20 x 20 cms 1000 Nos 0.255 Cement for CM (1:8) for base coat kg. 21.600 Cement for jointing & pointing kg. 6.000 Pointing with CM (1:3) 10sqm 1.000 Deduct CM (1:3) cum 0.040 Sand for CM (1:8) cum 0.120 Seigniorage charges of sand cum 0.120 B. LABOUR Mason 1 st class day 0.960 Mason 2 nd class day 2.240 Mazdoor (unskiled) day 3.30 Add water charges 1% 1.00% Grand Total 691 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-13 83 Gronolithie Concrete Flooring 20 mm thick with (1:1:2), using 6mm to 12 mm size hard granite machine crushed metal laid over CC bed already laid or RCC roof slab, in alternate panels of size not exceeding 1.50 m x 1.50 m and finishing the top surface to required smoothness and slopes and thread lining including cost of all materials like cement, metal, sand and water etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: 6mm to 12 mm H.G. Metal (Machine crushed) cum 0.17 Cement kg 120.00 Sand cum 0.085 Seigniorage charges of sand cum 0.085 B. LABOUR Mason 1 st class day 1.25 Mason 2 nd class day 0.06 Mazdoor (unskiled) day 3.00 Add water charges 1% 1.00% Grand Total BLD-CSTN-7-14 84 Flooring with 100mm thick Cement Concrete 1:6:10, using 40mm metal, 100mm thick and 20 mm Cement Concrete surface (Ellis Pattern, 1st Sort) Unit = 10 sqm A. MATERIALS: Cement Concrete 1:6:10 using concrete mixer cum 1.000 Stone Chippings 3.34 mm - 10 mm cum 0.250 Cement kg 120.000 B. LABOUR Mason 1 st class day 0.150 Mason 2 nd class day 0.350 Mazdoor (unskiled) day 5.40 Add water charges 1% 1.00% Grand Total BLD-CSTN-7-15 85 Flooring with Cement Concrete 1:6:10, using 40mm metal, 100mm thick and plastered over with 12 mm thick in CM(1:3) Unit = 10 sqm A. MATERIALS: Cement Concrete 1:6:10 using concrete mixer cum 1.00 Plastering with CM (1:3), 12 mm thick 10 sqm 1.00 Grand Total BLD-CSTN-7-16 86 Flooring with Cement Concrete 1:6:10, using 40mm metal, 100mm thick and plastered over with 12 mm thick in CM(1:3) using Red oxid, with polished surface Unit = 10 sqm A. MATERIALS: Cement Concrete 1:6:10 using concrete mixer cum 1.00 Plastering with CM (1:3), 12 mm thick 10 sqm 1.00 Red oxid kg 10.00 Note : When Mortar mix is changed proportionate quantity of cement has to be substituted for all above Flooring Items. The same data holds good for stones with all colours. Adopt same data for polished Kadapa Stones and Bethamcherla stones. 692 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 B. LABOUR Masons for polishing Nos 1.10 Grand Total BLD-CSTN-7-17 87 6 mm thick terrazzo flooring in situ with white, black, chocolate, gray, yellow or green superior marble chips, over 20 mm thick base coat of CM (1:3) laid over CC bed already laid or RCC roof slab, including cost of all materials like cement marble powder, marble chips, sand & water etc., complete including polishing to get high smooth finishing, seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Marble Powder kg 17.000 Marble Chips cum 0.060 Cement for top layer kg. 50.000 Cement for base coat in CM (1:3) kg. 96.000 Sand for base coat cum 0.200 Seigniorage charges of sand cum 0.200 B. MACHINERY Polishing Charges sqm 10.000 C. LABOUR Mason 1 st class day 0.960 Mason 2 nd class day 2.240 Mazdoor (unskiled) day 3.30 Grand Total BLD-CSTN-7-18 88 Providing skirting to internal walls to 15 cm height/risers of steps with ceramic tiles 7.30 mm thick length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., complete including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Ceramic tiles 7.30 mm thick sqm 10.00 Sand for cm 1:3 base coat cum 0.12 Cement for cm 1:3 base coat kgs 57.60 Cement for slurry kgs 33.00 White cement for jointing & pointing kgs 6.00 Seigniorage charges of sand cum 0.12 B. LABOUR Mason 1 st class day 0.77 Mazdoor (unskiled) day 0.80 Grand Total 693 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-19 89 Providing skirting to internal walls to 15 cm height/risers of steps with marble slab..mm thickness, length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like marble slab, cement, sand and water etc., complete including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Marble slabmm thickness sqm 10.10 Sand for base coat cum 0.12 Cement for base coat kg 57.60 Cement for slurry kg 33.00 White cement for jointing & pointing kg 5.00 Flate nosing charges RM 66.67 Machine cutting charges RM 67.67 Seigniorage charges of sand cum 0.12 B. LABOUR Mason Ist class day 2.10 Man mazdoor (Beldar) day 4.90 Man mazdoor (Beldar) for polishing & rubbing day 4.00 Woman mazdoor day 4.00 Grand Total BLD-CSTN-7-20 90 Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., complete including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Vitrified tiles polished 1st quality sqm 10.10 Sand for cm 1:5 base coat cum 0.12 Cement for cm 1:5 base coat kgs 34.56 Cement for slurry kgs 33.00 White cement for jointing & pointing kgs 2.00 Seigniorage charges of sand cum 0.12 B. LABOUR Mason Ist class day 0.96 Mason 2 nd class day 2.24 Mazdoor (unskilled) day 3.30 Add water charges 1% 1.00% Grand Total 694 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-21 91 Providing skirting to internal walls to 15 cm height/risers of steps with 8 mm thick mirror polished granite tiles length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., complete including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: 8 mm thick mirror polished granite tiles sqm 10.10 Sand for cm 1:3 base coat cum 0.12 Cement for cm 1:3 base coat kgs 57.60 Cement for slurry kgs 33.00 White cement for jointing & pointing kgs 5.00 Seigniorage charges of sand cum 0.12 B. LABOUR Mason Ist class day 2.10 Mazdoor (unskiled) day 0.80 Mason 2 nd class 4.90 Add water charges 1% 1.00% Grand Total BLD-CSTN-7-22 92 Providing skirting to internal walls to 15 cm height/risers of steps with 25 mm thick polished Cuddapah stone length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like Cuddapah stone, cement, sand and water etc., complete including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: 25 mm thick polished Cuddapah stone sqm 10.10 Sand for cm 1:3 base coat cum 0.12 Cement for cm 1:3 base coat kgs 57.60 Cement for slurry kgs 33.00 Seigniorage charges of sand cum 0.12 B. LABOUR Mason Ist class day 0.96 Mason 2nd class day 2.24 Mazdoor (unskiled) day 3.10 Add water charges 1% 1.00% Grand Total 695 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-23 93 Providing skirting to internal walls to 15 cm height/risers of steps with 25 mm thick polished Shahabad stone length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like Shahabad stone, cement, sand and water etc., complete including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: 25 mm thick polished Shahabad stone (White) sqm 10.10 Sand for cm 1:3 base coat cum 0.12 Cement for cm 1:3 base coat kgs 57.60 Cement for slurry kgs 33.00 Seigniorage charges of sand cum 0.12 B. LABOUR Mason Ist class day 0.96 Mason 2nd class 2.24 Mazdoor (unskiled) day 3.10 Add water charges 1% 1.00% Grand Total BLD-CSTN-7-24 94 Teak Wood Flooring 40mm. Thick Tongued and Grooved Planks, including cost of all materials, labour etc., complete Unit = 10 sqm A. MATERIALS: Teak Wood Planks 40mm thick cum 0.44 75 mm Long Screws 100 Nos 3.00 B. LABOUR Carpenters 1st Class day 1.95 Carpenters 2nd Class day 4.55 Man mazdoor day 5.40 Grand Total Note : Deduct 4.3 Nos Carpenters if plank rate is for tongued and grooved ready planned. Note : When Mortar mix is changed proportionate quantity of cement has to be substituted for all Skirting Items. 696 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-7-25 95 Flooring with Gravel 150 mm thick including cost of all materials, labour, watering etc., complete Unit = 10 sqm A. MATERIALS: Gravel (including 2% wastage) cum 1.53 B. LABOUR Man mazdoor day 1.10 Woman mazdoor day 0.50 Grand Total BLD-CSTN-8 ROOFING & CEILING BLD-CSTN-8-1 96 Roofing with corrugated G.I sheets 0.80mm thick fixed with G.I J bolts & nuts 8 mm dia with bitumen & G.I limpet washers filled with white lead & including a coat of approved steel primer and two coats of approved paint on over lapping of sheets complete (up to a pitch of 60 0 ) and seigniorage charges, etc., complete, excluding the cost of purlins, rafters, trusses & cost of conveyance of all materials Unit = 184.518 sqm A. MATERIALS: G.I corrugated 0.80 mm thick sheets kgs 103.09 G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884 nos 47.91 G.I bolts & nuts 20 x 6 nos G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos = 810 nos. with washers or srews, if wooden battens used. nos 43.90 Limpet washers (for scam & J bolts) 884 + 810 = 1694 nos 91.82 Bitumen washers nos 91.82 Zinc cromate yellow paint litre 0.14 Ready mixed paint litre 0.20 B. LABOUR For roofing Carpenter II class day 0.84 Man mazdoor (beldar) day 0.91 For premier painting one coat Painter day 0.06 Mazdoor (coolie) day 0.06 For two coats of painting to over laps Painter day 0.14 Mazdor (coolie) day 0.14 Sundries including 50 x 6 mm iron wind ties white lead etc. LS Add for Standard specification 1mm. Thick ridging and 1.25 mm thick sheet vallyes when such are required for a particular work. Average allowance for 10 sqm roofing. LS Grand Total Rate per 10 sqm = Grand Total/10 697 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-2 97 Roofing with corrugated G.I sheets 1.00mm thick fixed with G.I J bolts & nuts 8 mm dia with bitumen & G.I limpet washers filled with white lead & including a coat of approved steel primer and two coats of approved paint on over lapping of sheets complete (upto a pitch of 60 0 ) and seigniorage charges, turnover tax etc., complete, excluding the cost of purlins, rafters, trusses & cost of conveyance of all materials Unit = 184.518 sqm A. MATERIALS: G.I corrugated 1.00 mm thick sheets kgs 126.07 G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884 nos 47.91 G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos = 810 nos. nos 43.90 Limpet washers (for scam & J bolts) 884 + 810 = 1694 nos 91.82 Bitumen washers nos 91.82 Zinc cromate yellow paint litre 0.14 Ready mixed paint litre 0.20 B. LABOUR For roofing Carpenter II class day 0.84 Man mazdoor (beldar) day 0.91 For premier painting one coat Painter day 0.06 Mazdoor (coolie) day 0.06 For two coats of painting to over laps Painter day 0.14 Mazdor (coolie) day 0.14 Grand Total Rate per 10 sqm = Grand Total/10 BLD-CSTN-8-3 98 Roofing with corrugated G.I sheets 1.25mm thick fixed with G.I J bolts & nuts 8 mm dia with bitumen & G.I limpet washers filled with white lead & including a coat of approved steel primer and two coats of approved paint on over lapping of sheets complete (upto a pitch of 60 0 ) and seigniorage charges, turnover tax etc., complete, excluding the cost of purlins, rafters, trusses & cost of conveyance of all materials Unit = 184.518 sqm A. MATERIALS: G.I corrugated 1.25 mm thick sheets kgs 154.80 G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884 nos 47.91 G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos = 810 nos. nos 43.90 Limpet washers (for scam & J bolts) 884 + 810 = 1694 nos 91.82 Bitumen washers nos 91.82 Zinc cromate yellow paint litre 0.14 Ready mixed paint litre 0.20 B. LABOUR For roofing Carpenter II class day 0.84 Man mazdoor (beldar) day 0.91 For premier painting one coat Painter day 0.06 Mazdoor (coolie) day 0.06 698 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 For two coats of painting to over laps Painter day 0.14 Mazdor (coolie) day 0.14 Grand Total Rate per 10 sqm = Grand Total/10 BLD-CSTN-8-4 99 Roofing with 6 mm thick corrugated asbestos cement sheets, fixing with G.I J bolts & nuts 8 mm dia G.I plain washers complete including seigniorage charges etc., complete for finished item of work, but excluding the cost of purlins, rafters, trusses & cost of conveyance of all materials upto 60 0 pitch. Unit = 216.14 sqm A. MATERIALS: 6 mm thick corrugated AC sheets T /sqm 0.15 8 mm dia G.I J bolts & nuts nos 22.03 G.I washers nos 22.03 Bitumen washers nos 22.03 B. LABOUR Carpenter II class day 0.43 Man mazdoor day 0.54 Sundries including 50 x 6 mm iron wind ties white lead etc. LS Add for Standard specification 1mm. Thick ridging and 1.25 mm thick sheet vallyes when such are required for a particular work. Average allowance for 10 sqm roofing. LS Grand Total Rate per 10 sqm = Grand Total/10 BLD-CSTN-8-5 100 196 Best Tiled Roofing with Pan tiles over Flat Tiles and Lime mortar Borders including Teak Reapers. Unit = 10 sqm A. MATERIALS: Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 No 1560 Flat Tiles 150 x 150 x 15 mm 1000 No 470 Teak Reepers 50 x 12 mm 10RM 75.000 Wire Nails 40 mm long kgs 0.500 Lime cum 0.008 Lime Mortar cum 0.300 B. LABOUR Carpenter day 0.800 Bricklayers day 2.200 Man mazdoor day 1.100 Woman mazdoor day 5.400 Sundries including tarring reepers, extra labour / for pointing the underside of flat tiles and white washing the same. LS LS Grand Total Sub Analysis : Lime Moratar 1:2 lime cum 0.500 Sand cum 1.000 Grinding Lime Mortar cum 1.000 Total 699 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-6 101 197 Best Tiled Roofing with Pan tiles and Lime mortar Borders including Teak Reapers at 100 mm. centres Unit = 10 sqm A. MATERIALS: Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 No 1560 Teak Reepers 50 x 12 mm 10RM 107.000 Wire Nails 40 mm long kgs 0.700 Lime Moratar cum 0.120 B. LABOUR Carpenter day 1.100 Bricklayers day 1.400 Man mazdoor day 1.100 Woman mazdoor day 3.200 Grand Total BLD-CSTN-8-7 102 198 Best Tiled Roofing with Pan tiles laid on Bamboo Rafters, Bamboo Reepers and Bamboo Mats, including Lime mortar Borders Unit = 10 sqm A. MATERIALS: Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 No 1560 Bamboo rafters (450 mm apart) 75 to 100 mm dia RM 25 Bamboo reepers, Split 25 mm dia 100 No 150 Bamboo mats 10 sqm 10.500 Lime Moratar for Borders cum 0.120 B. LABOUR Carpenter day 1.100 Bricklayers day 1.400 Man mazdoor day 1.100 Woman mazdoor day 3.200 Sundries including nails Grand Total BLD-CSTN-8-8 103 199 Best Tiled Roofing with Mangalore tiles set in Lime mortar over Flat Tiles and including Teak Reepers Unit = 10 sqm A. MATERIALS: Mangalore tiles (vide Stadard Specification) 1000 No 160 Flat Tiles 150 x 150 x 15 mm 1000 No 470 Teak Reepers 50 x 12 mm 10RM 75.000 Wire Nails 40 mm long kgs 0.500 Lime cum 0.008 Lime Moratar cum 0.380 B. LABOUR Carpenter day 0.800 Bricklayers day 1.600 Man mazdoor day 1.100 Woman mazdoor day 4.300 Sundries including tarring reepers iron wind ties 30 x 3 mm, G.I. Screw, washers etc., and extra labour for pointing the underside of flat tiles and white washing the same. LS LS Grand Total 700 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-9 104 200 Best Tiled Roofing with Mangalore tiles including Teak Reepers Unit = 10 sqm A. MATERIALS: Mangalore tiles (vide Stadard Specification) 1000 No 160 Teak Reepers 50 x 12 mm 10RM 36.000 Wire Nails 50 mm long kgs 0.500 Lime Moratar cum 0.090 B. LABOUR Carpenter day 0.500 Bricklayers day 0.500 Man mazdoor day 1.100 Woman mazdoor day 2.200 Grand Total BLD-CSTN-8-10 105 201 Best Tiled Roofing with Mangalore tiles over Ceiling Tiles with Air Spaces and including Teak Reepers Unit = 10 sqm A. MATERIALS: Rate for "Best Mangalore tiled roofing with Mangalore tiles including teak reeper". 10 sqm 10.000 Add Terracing tiles 100 No 156 B. LABOUR Bricklayers day 0.500 Woman mazdoor day 1.100 Grand Total Common note Applicabable for Items 196 to 201 :- 1. The quantity proposed for Pan Tiles / Mangalore Tiles includes allowance for cost of special tiles for ridges and hips. 2. Reepers size is for rafter spacing 600 mm. including allowance for eves and valleys. 3. Labour including fixing galvanized iron sheeting-cost of sheeting to be paid separately. Sub Analysis : Lime Mortar (1: 1.5) : Unit = 1 cum Lime cum 0.670 Fine Sand cum 1.000 Grinding Mortar (Spl Grinding) cum 1.000 Sundries LS Total BLD-CSTN-8-11 106 Plastering with Lime Mortar 3 Coats, 25 mm thick (Sebara Rendering) Unit = 10 sqm Lime Mortar (1:2) cum 0.180 Lime Mortar (1:1.5) cum 0.080 Lime cum 0.023 LABOUR Bricklayers day 3.200 Mazdoor (unskilled) day 6.500 Sundries LS LS Total 701 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-12 107 204 Terrace Roofing with Brick on edge 75 mm. Concrete 2 Courses of Flat Tiles at Top and pointing Flat Tiles in Cement Mortar (1:3) and one coat of Cement Plaster (1:3) Unit = 10 sqm A. MATERIALS: Terracing Bricks 150 x 75 x 25mm 1000 No 2000 Flat Tiles 150 x 150 x 15 mm 100 No 900 Broken brick 20 mm cube cum 0.980 Lime cum 0.380 Lime Moratar cum 0.210 Pointing with cement mortar 1:3 (for rate - vide relevant schedule item) 10 sqm 1.000 Cement Mortar 1:3 cum 0.240 B. LABOUR Bricklayers day 4.300 Mazdoor (unskilled) day 6.500 Grand Total BLD-CSTN-8-13 108 205 Reinforced cement Concrete Roofing 125 mm thick with CC (M 20) using 20 mm graded metal and 2 courses of Flat Tiles at Top including pointing with Cement Mortar (1:3) Unit = 10 sqm A. MATERIALS: Reinforced Concrete Roofing slab 125 mm thick (for rate - vide relevant schedule item) 10 sqm 10.000 Flat Tiles 150 x 150 x 20 mm 100 No 900 Cement Mortar 1:3 cum 0.260 Pointing with cement mortar 1:3 (for rate - vide relevant schedule item) 10 sqm 1.000 B. LABOUR Bricklayers day 2.200 Woman mazdoor day 2.200 Sundries including crude oil LS Grand Total Sub Analysis : RCC (M 20) using 20 mm HG graded metal using Concrete mixturefor Roofing 125 mm thick CC (M 20) (Item No. cum 1.250 Centering Charges 10 sqm 1.000 Form Work Total BLD-CSTN-8-14 109 206 Reinforced cement Concrete Roofing 140 mm thick with CC (M 20) using 20 mm graded metal and 2 courses of Flat Tiles at Top including Pointing with Cement Mortar (1:3) Unit = 10 sqm A. MATERIALS: Rate of "Reinforced cement Concrete Roofing 125 mm thick and 2 courses of Flat Tiles at Top including pointing with Cement Mortar (1:3)" 10 sqm 1.000 Add : For extra thickness of roofing slab cum 0.150 Grand Total Note : The quantity proposed for broken brick allows for the brick powder formed, replacing sand for concrete layers. 702 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-15 110 207 Reinforced cement Concrete Roofing 150 mm thick with CC (M 20) using 20 mm graded metal and 2 courses of Flat Tiles at Top including Pointing with Cement Mortar (1:3) Rate of "Reinforced cement Concrete Roofing 125 mm thick and 2 courses of Flat Tiles at Top including pointing with Cement Mortar (1:3)" 10 sqm 1.000 Add : For extra thickness of roofing slab cum 0.250 Grand Total BLD-CSTN-8-16 111 207 Reinforced cement Concrete Roofing 100 mm thick with CC (M 20) using 20 mm graded metal and 2 courses of Flat Tiles at Top including Pointing with Cement Mortar (1:3) Rate of "Reinforced cement Concrete Roofing 125 mm thick and 2 courses of Flat Tiles at Top including pointing with Cement Mortar (1:3)" 10 sqm 1.000 Deduct : For Less thickness of roofing slab cum 0.250 Grand Total BLD-CSTN-8-17 112 207 Reinforced cement Concrete Roofing 100 mm thick with CC (M 20) using 20 mm graded metal with Imprevious Coat with 12 mm thick Plastering in CM (1:3) with 1 kg. of Impermo Compound or ACCO Proof per Bag of Cement and laid when slab is Green. Unit = 10 sqm Reinforced Concrete Roofing slab 100 mm thick (for rate - vide relevant schedule item) 10 sqm 1.000 Centering Charges 10 sqm 1.000 Plastering with CM (1:3), 12 mm thick 10 sqm 1.000 Impermo Compound kgs 1.500 Grand Total Note for Items 204 - 207 : 1. No extra rate will be paid for finishing the bottom surface of the roofing slab as described in SS No. "For estimating purpose the extra allowance for camber concrete, when such is required may be given under sundries." 703 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-18 113 208 Complete Surface Repairs to Leaky Terrace Roofs with Flat Tiles Unit = 10 sqm A. MATERIALS: Flat Tiles 150 x 150 x 15 mm 1000 No 450 Cement Mortar 1:3 cum 0.110 Pointing with cement mortar 1:3 (for rate - vide relevant schedule item) 10 sqm 1.000 B. LABOUR Bricklayers day 1.100 Man Mazdoor day 1.100 Clean removal of lime plaster from terraced roofs and raking out joints 12 mm deep (for rate - vide relevant schedule item) 10 sqm 1.000 Sub Analysis : Mazdoor (unskilled) Day Mate Day Sundries including crude oil LS Grand Total BLD-CSTN-8-19 114 209 Best Sloping Bengal Terrace with 3 courses of Flat Tiles at Top including Teak Wood Reepers Unit = 10 sqm A. MATERIALS: Flat Tiles 150 x 150 x 15 mm 1000 No 1350 Lime cum 0.008 Lime Moratar (1:1.5) cum 0.150 Teak Reepers 52 x 12 mm 10 RM 75.000 Wire Nails 40 mm long kgs 0.500 Plastering with lime mortar 3 coats (for rate - vide relevant schedule item) 10 sqm 1.000 B. LABOUR Carpenter day 0.800 Bricklayers day 2.200 Woman mazdoor day 2.200 Sundries including tarring reepers LS Grand Total Note : 1. Reepers size is for rafter spacing 600 mm. including allowance for eves and valleys. 2. No extra rate will bepaid for finishing the bottom surface of the roofing slab as described in SS No. 704 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-20 115 212 Removing Old Tiles and Retiling with New Pan Tiles over Old Teak Reepers including New White Washed Lime Mortar Borders 230 x 50 mm. at 2 Metres Intervals Unit = 10 sqm A. MATERIALS: Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 No 1560 Lime Moratar cum 0.120 B. LABOUR Bricklayers day 1.400 Man Mazdoor day 1.100 Woman mazdoor day 4.300 Sundries LS Grand Total BLD-CSTN-8-21 Shifting Pan Tiles (Labour Only) Unit = 10 sqm Bricklayers day 1.100 Man Mazdoor day 0.800 Grand Total BLD-CSTN-8-22 117 214 Shifting Pan Tilesand forming new White Washed Lime Mortar Boarders, 230 x 50 mm at 2 Metres Intervals Unit = 10 sqm Rate of "Shifting Pan Tiles" 10 sqm 1.000 Add : Lime Mortar Borders and White Washing LS Grand Total BLD-CSTN-8-23 118 222 12 mm. Teak Wood Plank Ceiling Tongued and Grooved Planking Unit = 10 sqm A. MATERIALS: Teak Wood Planks 150 x 12 mm cum 0.132 Screws 40mm long 100 No 300 B. LABOUR Carpenter day 6.500 Man Mazdoor day 5.400 Sundries LS Grand Total Note : Deduct 4.3 Nos Carpenters if plank rate is for tongued and grooved ready planned. BLD-CSTN-8-24 119 223 12 mm. Teak Wood Plank Ceiling with 40 x 12 mm Teak Wood Battens Unit = 10 sqm Rate for "12 mm. Teak Wood Plank Ceiling Tongued and Grooved Planking" 10 sqm 10.000 Teak Wood Battens 40 x 12 mm 10 RM 66.000 Brass screws 25 mm long 100 No 240 Deduct : Carpenter day 1.100 Sundries LS Grand Total 116 213 705 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-25 120 Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water proof compound per bag of cement laid over roof when it is green including cost of all materials, seigniorage charges, excluding conveyance charges of materials and including all operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of work Unit = 10 sqm A. MATERIALS: Cement Mortal 1:3 cum 0.210 Water proof compound kg 2.000 B. LABOUR Mason 1 st class day 0.660 Mason 2 nd class day 1.540 Mazdoor (unskiled) day 3.70 Grand Total BLD-CSTN-8-26 121 Providing & fixing insulating board ceiling of approved quality with nails etc., complete, excluding the cost of frame work for base and cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: 12 mm thick insulating board sqm 11.00 B. LABOUR Carpenter Ist class day 2.50 Man mazdoor day 2.00 Grand Total BLD-CSTN-8-27 122 Providing & fixing hard board sheet ceiling of approved quality with nails etc., complete, excluding the cost of frame work for base and cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: 3 mm thick standard quality of hard board sqm 11.00 B. LABOUR Carpenter Ist class day 2.50 Man mazdoor day 2.00 Grand Total BLD-CSTN-8-28 123 Providing & fixing flat pressed 3 layer medium density particle board sheet with necessary nails etc., complete, excluding the cost of frame work for base and cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Standard quality of flat pressed 3 layer medium density board sheet 4.50 mm thick sqm 11.00 B. LABOUR Carpenter Ist class day 2.50 Man mazdoor day 2.00 Grand Total 706 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-8-29 124 Providing & fixing plain AC sheet ceiling of approved quality with necessary nails etc., complete, excluding the cost of frame work for base and cost of conveyance of all materials Unit = 10 sqm A. MATERIALS: Plain AC sheet for ceiling sqm 11.00 B. LABOUR Carpenter Ist class day 2.50 Man mazdoor day 2.00 Grand Total BLD-CSTN-8-30 125 Providing 10 mm thick plaster of paris (Gypsum anhydrous) ceiling upto a height of 5 m above floor level over first class BT wood strips 25 x 6 mm with 10 mm gap in between and reinforced with rabbit wire mesh fixed to wooden frame excluding cost of wooden frame for base & cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Wooden strips 1 st class BT wood 25 x 6 mm size cum 0.05 Nails kg 0.75 Rabbit wire mesh sqm 10.20 Plaster of paris kg 219.76 B. LABOUR for Jointing the wooden strips including fixing the rabbit mesh Carpenter Ist class day 2.60 Man mazdoor (beldar) day 1.60 For doing plaster of paris over wooden strips Mason Ist class day 2.62 Mason IInd class day 1.62 Mazdoor (unskilled) day 377.00 Grand Total Gypboard Suspended false ceiling BLD-CSTN-8-31 126 Supplying and fixing Gyp Board Suspended regular single layer false ceiling (GS-MFSC-4.1 as per India Gypsum) using 12.5 mm thick Gyp Board conforming to IS 2095 - 1982 fixing to Gyp steel GI perimeter channels of size 20 mm x 27 mm x 30 mm(web) of 0.55 mm thick along the perimeter of ceiling screw fixed to brick work/ partition at 610 mm c/c and suspending the frame work using Intermediate channels (45 mm x 15mm x 15mm x 0.9 mm) from soffit at 1220 mm c/c with ceiling angle (25 mm x 10 mm x 0.55 mm) fixed with GI Cleat and steel expansion fasteners & connecting clip to the ceiling channels (with knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55 mm) fixed in direction perpendicular to the intermediate channel at 457 mm c/c and fixing the 12.5 mm tapered edge Gypboard with 25 mm drywall screws at 230 mm c/c & jointing and finishing using joint compound and paper tape to have a flush look including filling the tapered & square edges with jointing compound, two coats of drywall topcoat complete for finished item of work as per Idia Gypsum Ltd specification. UNIT -1 sqm A) Material requirement as per India Gypsum 12.5 mm Gypboard 1219 mm x 1829 mm size Boards sqm 1.03 707 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Ceiling Angle 25 mm x 10 mm x 0.55 mm RM 0.64 Connecting Clips Nos 1.84 Ceiling Section 51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick RM 2.30 Intermediate Channel 45 mmx 15 mm x 15 mm x 0.9 mm RM 0.84 Perimeter Channel 20 mm x 27 mm x 30 mm(web) of 0.55 mm thick RM 0.40 Rawl Plug Nos 0.64 Soffit Cleats Nos 0.64 Drywall Screws - 25 mm Nos 18.00 Jointing Compound Kgs 0.55 Jointing Paper Tape RM 1.46 Drywall Top Coat Lits 0.15 B) LABOUR CHARGES 1st Class Carpenter day 0.40 2nd Class Carpenter day 0.40 1st Class Painter day 0.08 2nd Class Painter day 0.08 Power Saw Cutter - Hand Operated - Operator day 0.04 Power Drill - Hand Operated - Operator day 0.08 Unskilled Mazdoor day 0.24 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32 Power Drill - Hand Operated - Hire Charges Hrs 0.64 Scaffolding charges 1% BASIC COST per 1 sqm Gyp Board Fine Line Grid false ceiling BLD-CSTN-8-32 127 Supplying and fixing Gyp Board Fine Line Grid false ceiling (GS-FLC-4.6 as per India Gypsum) in size 600 mm x 600 mm using 12.5 mm thick/ 9.5 mm thick Gyp Board sheet tiles of size 595 mm x 595 mm or 595 mm x 1195 mm conforming to IS 2095 - 1982 fixing to Gyp steel precoated GI wall angle of size 25 mm x 25 mm x of 0.70 mm thick along the perimeter of ceiling screw fixed to brick work/ partition at 610 mm c/c and suspending the frame work using precoated GI Tee section (24 mm x 38 mm x 0.7 mm) from soffit at 1220 mm c/c fixed with GI Soffit Cleat, rawl plugs and steel expansion fasteners & connecting clip to the GI T section with 4 mm dia GI Rod with galvanised spring steel level clip of PVC unversal holding clips system at 1200 mm c/c and fixing the 12.5 mm / 9.5 mm Gypboard Sheet tiles of size 595 mm x 595 mm or 595 mm x 1195 mm and finishing two coats of drywall topcoat complete for finished item of work as per Idia Gypsum Ltd specification. UNIT -1 sqm A) Material requirement as per India Gypsum 12.5 mm / 9.5 mm - Gypboard Tiles Either - 595 mm x 595 mm - sqm 1.00 Or - 595 mm x 1195 mm - GI Angle - Precoated 25 mm x 25 mm x 0.7 mm RM 0.40 GI - Precoated - T Section - 3600 mm long 24 mm x 38 mm x 0.7 mm thick RM 1.60 GI - Precoated - T Section - 600 mm long 24 mm x 38 mm x 0.7 mm thick RM 1.60 GI Rod - 4 mm Dia Connecting Rod RM 1.28 Rawl Plug Nos 1.28 Soffit Cleats Nos 1.28 Unversal Holding Clips Nos 5.36 708 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Drywall Top Coat Lits 0.15 B) LABOUR CHARGES 1st Class Carpenter day 0.40 2nd Class Carpenter day 0.40 1st Class Painter day 0.08 2nd Class Painter day 0.08 Power Saw Cutter - Hand Operated - Operator day 0.04 Power Drill - Hand Operated - Operator day 0.04 Unskilled Mazdoor day 0.24 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32 Power Drill - Hand Operated - Hire Charges Hrs 0.32 Scaffolding charges 1% BASIC COST per 1 sqm Armstrong False ceiling BLD-CSTN-8-33 128 Providing and fixing in true horizontal level 600 mm x 600 mm 15 mm thick Arm strong false ceiling system manufactured by M/s Arm strong world Industries using hot dipped Galvanised Steel section exposed surface with pre- coated capping, main Tee of size 24 x 32 mm at every 1200 mm c/c maximum and rotary stiched cross tee of size 24 x 27 mm at evry 600 mm c/c and sub-cross tee of size 24 mm x 25 mm at 1200 mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall and the above grid is suspended at every 1200 mm c/c in both directions using 2.0 mm thick pre-straightened GI Wire laying fine fissured butt edge ceiling tiles of 15 mm thick mineral fiber Board manufactured by M/s Arm Strong World Industries Ltd., having RH 99% and for finished of size 600 x 600 mm including Cost &conveyance of all materials and labour charges such as cutting , fixing of standing of frame work exposing roof making complete for finished item of work UNIT 1 sqm A) Material requirement 15 mm - Armstrong Mineral Fiber sheet 600 x 600 sqm 1.00 Hotdipped GI Angle - Precoated - Grid 19 mm x 19 mm RM 0.40 Polyster painted GI - T Section - 1200 mm (1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross Tee) RM 1.60 Polyster painted GI - T Section - 300 mm 24 mm x 27 mm RM 1.60 GI Rod - prestraightened - 2.0 mm dia Connecting Rod RM 1.28 6 mm Nylon Rawl Plug Nos 1.28 B) LABOUR CHARGES PER UNIT 1 sqm 1st Class Carpenter day 0.40 2nd Class Carpenter day 0.40 1st Class Painter day 0.08 2nd Class Painter day 0.08 Power Saw Cutter - Hand Operated - Operator day 0.04 Power Drill - Hand Operated - Operator day 0.04 Unskilled Mazdoor day 0.24 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 0.32 Power Drill - Hand Operated - Hire Charges Hrs 0.32 Scaffolding charges 1% BASIC COST per 1 sqm 709 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Thermocole False ceiling BLD-CSTN-8-34 129 Providing and fixing Thermocole False ceiling in true horizontal level 600 mm x 600 mm using 15 mm/ 19 mm thick Thermocole sheet anodised Aluminium Tee sections of size 24.50 mm x 24.0 mm x 2.4 mm in grid with cross tee of size 24 x 24.5 mm at every 600 mm c/c and anodised aluminium wall angle of size 24 x 24 mm fixed to periphery of the wall and the above grid is suspended at every 1200 mm c/c in both directions using 2.0 mm thick GI Wire for finished of size 600 x 600 mm including Cost &conveyance of all materials and labour charges such as cutting , fixing of standing of frame work exposing roof making complete for finished item of work UNIT 1 sqm A) Material requirement 15 mm/ 19 mm Thermocole sheet 600 x 600 sqm 1.00 Alumninium Angle 24 mm x 24 mm RM 0.40 Anodised Aluminium T Section (1) 24 x 24.5 x 2.4 mm mm RM 3.20 GI Rod - prestraightened - 2.0 mm dia Connecting Rod Nos 1.28 Rawl Plugs Nos 1.28 B) LABOUR CHARGES 1st Class Carpenter day 0.36 2nd Class Carpenter day 0.36 1st Class Painter day 0.00 2nd Class Painter day 0.00 Power Saw Cutter - Hand Operated - Operator day 0.02 Power Drill - Hand Operated - Operator day 0.04 Unskilled Mazdoor day 0.20 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 0.16 Power Drill - Hand Operated - Hire Charges Hrs 0.32 Scaffolding charges 1% BASIC COST per 1 sqm BLD-CSTN-9 WHITE WASHING, COLOUR WASHING & DISTEMPERING BLD-CSTN-9-1 130 White washing one coat with lime of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance charges of materials Unit: 10 sqm A. MATERIALS : Fine screened shell lime cum 0.005 Gum, conjee water, or prickly pear juice including necessary fire wood L.S B. LABOUR Brick Layers day 0.11 Mazdoor (unskilled) day 0.22 Sundries including brushes etc., LS Total cost for 10 sqm 710 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-9-2 131 White washing two coats with lime of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance charges of materials Unit: 10 sqm A. MATERIALS : Fine screened shell lime cum 0.007 Gum, conjee water, or prickly pear juice including necessary fire wood L.S B. LABOUR Brick Layers day 0.160 Mazdoor (unskilled) day 0.32 Sundries including brushes etc., LS Total cost for 10 sqm BLD-CSTN-9-3 132 White washing three coats with lime of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance charges of materials Unit: 10 sqm A. MATERIALS : Fine screened shell lime cum 0.009 Gum, conjee water, or prickly pear juice including necessary fire wood L.S B. LABOUR White washer day - Brick Layers day 0.220 Man Mazdoor day - Women mazdoor day - Mazdoor (unskilled) day 0.43 Sundries including brushes, ladders etc., LS Total cost for 10 sqm BLD-CSTN-9-4 133 White washing one coat with whiting of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance charges of materials Unit: 10 sqm A. MATERIALS : Whiting / White Cement cum / kg 1.20 Gum, conjee water, or prickly pear juice including necessary fire wood B. LABOUR Brick Layers / Painter day 0.11 Mazdoor (unskilled) day 0.22 Sundries including brushes, ladders, etc., 0.50% Total cost for 10 sqm with White Cement Grade II 711 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-9-5 134 White washing two coats with whiting of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance charges of materials Unit: 10 sqm A. MATERIALS : Whiting / White Cement cum / kg 2.00 Gum, conjee water, or prickly pear juice including necessary fire wood L.S B. LABOUR Brick Layers / Painter day 0.210 Mazdoor (unskilled) day 0.320 Sundries including brushes, ladders, etc., 1.00% Total cost for 10 sqm BLD-CSTN-9-6 135 White washing three coats with whiting of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance charges of materials Unit: 10 sqm A. MATERIALS : Whiting / White Cement cum / kg 2.800 Gum, conjee water, or prickly pear juice including necessary fire wood B. LABOUR Brick Layers / Painter day 0.300 Mazdoor (unskilled) day 0.430 Total cost for 10 sqm BLD-CSTN-9-7 Colour Washing, One Coat Unit: 10 sqm Rate for "White Washing" one coat 10 sqm 1.000 Add: For Colours, etc., (50 percent of above rate) Total BLD-CSTN-9-8 Colour Washing, Two Coats Unit: 10 sqm Rate for "White Washing" two coats 10 sqm 1.000 Add: For Colours, etc., (50 percent of above rate) Total BLD-CSTN-9-9 138 256 Distempering, 2 Coats with Water Bound Distemper Unit: 10 sqm A. MATERIALS : Distemper kg 1.340 B. LABOUR Painter day 0.500 Mazdoor (unskilled) day 1.300 Sundries including brushes, ladders, etc., 1.000% Total cost for 10 sqm 136 254 137 255 712 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-9-10 139 257 Distempering, 2 Coats with Oil Bound Distemper Unit: 10 sqm A. MATERIALS : Distemper kg 1.700 B. LABOUR Painter day 1.200 Sundries including brushes, ladders, etc., 1.000% Total cost for 10 sqm BLD-CSTN-10 PAINTING & VARNISHING BLD-CSTN-10-1 140 Painting to new walls with 2 coats of ready mixed oil bound wahsable distemper of approved brand and shade over a base coat of appropriate primer of approved brand, making 3 coats in all to give an even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges etc. complete for finished item of work as per SS 911 for internal walls PRIMARY COAT: Cost of Primer Lts 0.50 Painter I st class Nos 0.08 Pianter Iind class Nos 0.19 Cost of washable Oil Bound Distemper Lts 1.70 1st class painter Nos 0.36 II class painter Nos 0.84 Total cost BLD-CSTN-10-2 141 270 Painting, Priming Coat on New Plastered Surface Unit: 10 sqm A. MATERIALS : Cement Primer kg 1.00 B. LABOUR Painter day 0.700 Sundries including brushes, soaps, putty etc., 0.500% Total cost for 10 sqm BLD-CSTN-10-3 142 284 Painting Walls with Snowcem or other equal and approved Water Proof Cement Paint over Priming Coat, One Coat (All Colours) Unit: 10 sqm A. MATERIALS : Cement Paint at 5 sqm., per kg kg 2.000 B. LABOUR Painter day 0.300 Mazdoor (unskilled) day 1.500 Sundries including brushes, etc., 1.000% Total cost for 10 sqm BLD-CSTN-10-4 143 285 Painting Walls with Snowcem or other equal and approved Water Proof Cement Paint over Priming Coat, 2 Coats (All Colours) Unit: 10 sqm A. MATERIALS : Cement Paint at 3 sqm., per kg kg 3.500 B. LABOUR Painter day 0.500 Mazdoor (unskilled) day 1.500 Sundries including brushes, etc., 1.000% Total cost for 10 sqm 713 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-10-5 144 Painting to new walls with 2 coats of water proof cement paint of apporved brand and shade over a base coat of approved cement primer grade I making making 3 coats in all to give an even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges etc. complete for finished item of work as per SS 912 for internal walls Cost of Cement Primer kg 1.00 Ist class painter day 0.21 2nd class painter day 0.49 Cost of water proof cement Paint of approved quality kg 3.50 1st class painter day 0.15 2nd class painter day 0.35 Mazdoor (unskilled) day 1.50 Total cost BLD-CSTN-10-6 145 268 Painting, Priming Coat on New Wood Work Unit: 10 sqm A. MATERIALS : Wood Primer L 0.700 B. LABOUR Painter day 0.700 Sundries including brushes, soap, putty etc., 1.000% Total cost for 10 sqm BLD-CSTN-10-7 146 269 Painting, Priming Coat on New Iron Work Unit: 10 sqm A. MATERIALS : Red Oxide Primer L 0.70 B. LABOUR Painter day 0.70 Sundries including brushes, soap, putty etc., Total cost for 10 sqm BLD-CSTN-10-8 Varnishing to Wood Work, One Coat Unit: 10 sqm A. MATERIALS : Varnish L 0.800 Linseed Oil - boiled L 0.600 B. LABOUR Painter day 0.700 Man Mazdoor day 0.700 Sundries including brushes,fuel, size etc., Total cost for 10 sqm 147 281 714 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-10-9 Varnishing to Wood Work, Two Coats Unit: 10 sqm A. MATERIALS : Varnish L 1.200 Linseed Oil - boiled L 1.100 B. LABOUR Painter day 1.100 Man Mazdoor day 1.100 Sundries including brushes,fuel, size etc., Total cost for 10 sqm BLD-CSTN-10-10 Painting with Ready mixed oil paint (all colours) i. One Coat - New Wood Work : Unit: 10 sqm A. MATERIALS : Ready mixed paint kg 1.600 B. LABOUR Painter day 0.700 Sundries including brushes, soap, putty etc., LS Total cost for 10 sqm ii Two Coats - New Wood Work : Unit: 10 sqm A. MATERIALS : Ready mixed paint kg 2.800 B. LABOUR Painter day 1.200 Sundries including brushes, soap, putty etc., LS Total cost for 10 sqm iii One Coat - Old Wood Work & New Iron Work : Unit: 10 sqm A. MATERIALS : Ready mixed paint kg 1.500 B. LABOUR Painter day 0.700 Sundries including brushes, soap, putty etc., LS Total cost for 10 sqm iv Two Coats - Old Wood Work & New Iron Work: Unit: 10 sqm A. MATERIALS : Ready mixed paint kg 2.4. B. LABOUR Painter day 1.200 Sundries including brushes, soap, putty etc., LS Total cost for 10 sqm v One Coat - Old Iron Work : Unit: 10 sqm A. MATERIALS : Ready mixed paint kg 1.200 B. LABOUR Painter day 0.700 Sundries including brushes, soap, putty etc., LS Total cost for 10 sqm 149 256 to 265 148 282 715 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 vi Two Coats - Old Iron Work : Unit: 10 sqm A. MATERIALS : Ready mixed paint kg 2.100 B. LABOUR Painter day 1.100 Sundries including brushes, soap, putty etc., LS Total cost for 10 sqm vii Three Coats - Old Iron Work : Unit: 10 sqm A. MATERIALS : Ready mixed paint kg 3.400 B. LABOUR Painter day 1.500 Sundries including brushes, soap, putty etc., LS Total cost for 10 sqm viii Three Coats - New Wood Work : Unit: 10 sqm A. MATERIALS : Ready mixed paint kg 3.900 B. LABOUR Painter day 1.600 Sundries including brushes, soap, putty etc., LS Total cost for 10 sqm BLD-CSTN-10-11 Painting with : i. Plastic Emulsion paint Grade I - One Coat for New Wood Work, Old Wood Work & New Iron Work : A. MATERIALS : Plastic Emulsion paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.500 B. LABOUR Painter day 0.700 Sundries including brushes, soap, putty etc., Total cost for 10 sqm ii Plastic Emulsion paints - One Coat for Old Iron A. MATERIALS : Plastic Emulsion paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.400 B. LABOUR Painter day 0.700 Sundries including brushes, soap, putty etc., Total cost for 10 sqm iii Plastic Emulsion paints - Two Coats for New Wood Work : A. MATERIALS : Plastic Emulsion paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.900 B. LABOUR Painter day 1.200 Sundries including brushes, soap, putty etc., Total cost for 10 sqm 150 266 716 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 iv Plastic Emulsion paints - Two Coats for Old Wood Work & New Iron Work : A. MATERIALS : Plastic Emulsion paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.800 B. LABOUR Painter day 1.200 Sundries including brushes, soap, putty etc., Total cost for 10 sqm v Plastic Emulsion paints - Two Coats for New Iron Work : A. MATERIALS : Plastic Emulsion paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.800 B. LABOUR Painter day 1.100 Sundries including brushes, soap, putty etc., Total cost for 10 sqm vi Plastic Emulsion paints - Two Coats for Old Iron Work : A. MATERIALS : Plastic Emulsion paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.700 B. LABOUR Painter day 1.100 Sundries including brushes, soap, putty etc., Total cost for 10 sqm vii Plastic Emulsion paints - Three Coats for New Wood Work : A. MATERIALS : Plastic Emulsion paint (at 20 sqm / litre as per British Paints (I) Ltd. L 1.200 B. LABOUR Painter day 1.600 Sundries including brushes, soap, putty etc., Total cost for 10 sqm viii Plastic Emulsion paints - Three Coats for Old Iron Work : A. MATERIALS : Plastic Emulsion paint (at 20 sqm / litre as per British Paints (I) Ltd. L 1.100 B. LABOUR Painter day 1.500 Sundries including brushes, soap, putty etc., Total cost for 10 sqm BLD-CSTN-10-12 151 i Painting with Synthetic Enamel paints - One Coat - for New Wood Work, Old Wood Work & New Iron Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.700 B. LABOUR Painter day 0.700 Sundries including brushes, soap, putty etc., Total cost for 10 sqm 717 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 ii Painting with Synthetic Enamel paints - One Coat - For Old Iron Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.500 B. LABOUR Painter day 0.700 Sundries including brushes, soap, putty etc., Total cost for 10 sqm iii Painting with Synthetic Enamel paints - Two Coats - for New Wood Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. L 1.200 B. LABOUR Painter day 1.200 Sundries including brushes, soap, putty etc., Total cost for 10 sqm iv Painting with Synthetic Enamel paints - Two Coats - For Old Wood Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. L 1.100 B. LABOUR Painter day 1.200 Sundries including brushes, soap, putty etc., Total cost for 10 sqm v Painting with Synthetic Enamel paints - Two Coats - For New Iron Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. L 1.100 B. LABOUR Painter day 1.100 Sundries including brushes, soap, putty etc., Total cost for 10 sqm vi Painting with Synthetic Enamel paints - Two Coats - For Old Iron Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. L 0.900 B. LABOUR Painter day 1.100 Sundries including brushes, soap, putty etc., Total cost for 10 sqm vii Painting with Synthetic Enamel paints - Three Coats - for New Wood Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. L 1.700 B. LABOUR Painter day 1.600 Sundries including brushes, soap, putty etc., Total cost for 10 sqm 718 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 viii Painting with Synthetic Enamel paints - Three Coats - For Old Iron Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. L 1.600 B. LABOUR Painter day 1.500 Sundries including brushes, soap, putty etc., Total cost for 10 sqm BLD-CSTN-10-13 152 Polishing on wood work with readymade wax polish of approved brand and manufacture New Work : A. MATERIALS : Readymade wax polish kg 0.500 B. LABOUR Painter day 0.800 Healper day 0.800 Sundries including brushes, soap, cloth etc., LS Total cost for 10 sqm BLD-CSTN-10-14 153 Melamine polishing on wood work (one or more coat) New Work : A. MATERIALS : Melamine polish L 0.650 B. LABOUR Painter day 0.800 Healper day 0.800 Sundries for Spraying Machine etc., LS Total cost for 10 sqm BLD-CSTN-10-15 154 French Spirit polishing Two or more coats on new works including a coat of wood filler. A. MATERIALS : Shellac kg 0.228 Spirit L 1.630 B. LABOUR Painter day 3.200 Sundries such as pigment, terpentaine, sand paper, putty, wood filler, white woolen cloth, linseed oil, cotton etc., LS Total cost for 10 sqm BLD-CSTN-11 WOOD WORK, ALUMINUM DOORS, WINDOWS, VENTILATORS Etc., BLD-CSTN-11-1 155 Best Teak Wood wrought and put up to 2 meters (Schedule Item No 286) Unit = 1 cum Materials : Teak wood large scantlings upto 2 m cum 1.000 Labour : Carpenter day 17.700 Man Mazdoor day 8.800 Sundries including nails, screws etc., LS Cost per cum 719 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-11-2 156 Best Teak Wood wrought and put up over 2 metres and below 3 metres in length (Schedule Item No 287) Unit = 1 cum Materials : Teak wood large scantlings over 2 m and below 3 m in length cum 1.000 Labour : Carpenter day 17.700 Man Mazdoor day 8.800 Sundries including nails, screws etc., LS Cost per cum BLD-CSTN-11-3 157 Best Teak Wood wrought and put up in large scantling of over 3 metres in length (Schedule Item No 288) Unit = 1 cum Materials : Teak wood large scantlings over 2 m and below 3 m in length cum 1.000 Labour : Carpenter day 17.700 Man Mazdoor day 8.800 Sundries including nails, screws etc., LS Cost per cum BLD-CSTN-11-4 158 Best Teak Wood wrought and put up for trusses including straps and all iron work (Schedule Item No 289) Unit = 1 cum Materials : Teak wood large scantlings cum 1.000 Iron Work (average) kg 112.000 Labour : Carpenter day 26.500 Man Mazdoor day 8.800 Sundries including nails, screws etc., LS Cost per cum BLD-CSTN-11-5 159 Fully Panelled doors - External or Internal - Moulded panels (Schedule Item No 290) A Single Shutter i 800 x 2000 mm *Teak wood cum 0.083 Labour, wrought and putup in position frame & shutters sqm 1.600 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) LS Total for each door ii 900 x 2000 mm *Teak wood cum 0.088 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door 720 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 iii 1100 x 2000 mm *Teak wood cum 0.109 Labour, wrought and putup in position frame & shutters sqm 2.200 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) LS Total for each door iv 1200 x 2100 mm *Teak wood cum 0.123 Labour, wrought and putup in position frame & shutters sqm 2.520 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door v 900 x 2100 mm *Teak wood cum 0.094 Labour, wrought and putup in position frame & shutters sqm 1.890 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) LS Total for each door vi 1500 x 2400 mm *Teak wood cum 0.159 Labour, wrought and putup in position frame & shutters sqm 3.600 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) LS Total for each door B Double Shutter i 900 x 2000 mm *Teak wood cum 0.096 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door ii 1000 x 2000 mm *Teak wood cum 0.104 Labour, wrought and putup in position frame & shutters sqm 2.000 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door iii 1300 x 2200 mm *Teak wood cum 0.134 Labour, wrought and putup in position frame & shutters sqm 2.860 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door 721 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 iv 1400 x 2300 mm *Teak wood cum 0.147 Labour, wrought and putup in position frame & shutters sqm 3.220 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door * Note : Average rate for respective size scantlings and rough plank BLD-CSTN-11-6 160 Fully Panelled doors - Internal Five Ply - Ply- wood Panels (Schedule Item No 291) A Single Shutter i 800 x 2000 mm *Teak wood cum 0.068 Five - Ply - Ply - Wood brich sqm 0.720 Labour, wrought and putup in position frame & shutters sqm 1.600 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) LS Total for each door ii 900 x 2000 mm *Teak wood cum 0.071 Five - Ply - Ply - Wood brich sqm 0.870 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door iii 1200 x 2100 mm *Teak wood cum 0.100 Five - Ply - Ply - Wood brich sqm 1.160 Labour, wrought and putup in position frame & shutters sqm 2.520 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) LS Total for each door iv 1300 x 2200 mm *Teak wood cum 0.106 Five - Ply - Ply - Wood brich sqm 1.390 Labour, wrought and putup in position frame & shutters sqm 2.860 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door v 900 x 2100 mm *Teak wood cum 0.077 Five - Ply - Ply - Wood brich sqm 0.880 Labour, wrought and putup in position frame & shutters sqm 1.890 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) LS Total for each door 722 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 vi 1000 x 2100 mm *Teak wood cum 0.091 Five - Ply - Ply - Wood brich sqm 0.880 Labour, wrought and putup in position frame & shutters sqm 2.100 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door B Double Shutter i 900 x 2000 mm *Teak wood cum 0.082 Five - Ply - Ply - Wood brich sqm 0.710 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door ii 1000 x 2000 mm *Teak wood cum 0.088 Five - Ply - Ply - Wood brich sqm 0.820 Labour, wrought and putup in position frame & shutters sqm 2.000 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door iii 1100 x 2000 mm *Teak wood cum 0.090 Five - Ply - Ply - Wood brich sqm 0.940 Labour, wrought and putup in position frame & shutters sqm 2.200 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door iv 1400 x 2300 mm *Teak wood cum 0.123 Five - Ply - Ply - Wood brich sqm 1.900 Labour, wrought and putup in position frame & shutters sqm 3.600 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door v 1500 x 2400 mm *Teak wood cum 0.130 Five - Ply - Ply - Wood brich sqm 1.280 Labour, wrought and putup in position frame & shutters sqm 3.600 Sundries inclusive of holdfasts and all wind appliances (Vide relevant standard specification) Total for each door * Note : Average rate for respective size scantlings and rough plank 723 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-11-7 161 Furniture - Iron - for External doors (Schedule Item 292) Top Tower bolts (Ave : Size) Nos 2 Bottom Tower bolts 150mm long Nos 2 Parliament hings with screws Nos 6 Oxidised aldrop with bolts Nos 1 Wind cleats with hings Nos 2 (Same for all doors) BLD-CSTN-11-8 162 Furniture - Iron - Internal doors (Schedule Item 293) Top Tower bolts (Ave : Size) Nos 1 Bottom Tower bolts 150mm long Nos 2 Butt hings with screws Nos 6 Wind cleats with hings Nos 2 (Same for all doors) BLD-CSTN-11-9 163 Glazed and Panelled doors (Schedule Item No. 294) A Single Shutter i 800 x 2000 mm *Teak wood cum 0.072 Glass sqm 0.470 Labour, wrought and putup in position frame & shutters sqm 1.600 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door ii 900 x 2000 mm *Teak wood cum 0.076 Glass sqm 0.560 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door iii 1200 x 2100 mm *Teak wood cum 0.106 Glass sqm 0.760 Labour, wrought and putup in position frame & shutters sqm 2.520 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door iv 1300 x 2200 mm *Teak wood cum 0.115 Glass sqm 0.870 Labour, wrought and putup in position frame & shutters sqm 2.860 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door 724 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 B Double Shutter i 900 x 2000 mm *Teak wood cum 0.087 Glass sqm 0.420 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door ii 1000 x 2000 mm *Teak wood cum 0.092 Glass sqm 0.510 Labour, wrought and putup in position frame & shutters sqm 2.000 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door iii 1100 x 2000 mm *Teak wood cum 0.096 Glass sqm 0.600 Labour, wrought and putup in position frame & shutters sqm 2.200 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door iv 1400 x 2300 mm *Teak wood cum 0.123 Glass sqm 1.060 Labour, wrought and putup in position frame & shutters sqm 3.220 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door v 1500 x 2400 mm *Teak wood cum 0.130 Glass sqm 1.280 Labour, wrought and putup in position frame & shutters sqm 3.600 Sundries inclusive of putty, brads, hold fasts and all wind appliances (Vide relevant standard specification) LS Total for each door * Note : Average rate for respective size scantlings and rough planks. 725 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-11-10 164 Furniture - Same as for Fully Panelled Doors External (Schedule Item No. 295) Total for each door BLD-CSTN-11-11 165 Framed and Planked Doors (Schedule Item No. 296) i 1000 x 2000 mm *Teak wood cum 0.107 Labour, wrought and putup in position frame & shutters sqm 2.000 Sundries inclusive of putty, brads, hold fasts and wind appliances and screws for planks (Vide standard specification) LS Total for each door ii 1200 x 2100 mm *Teak wood cum 0.127 Labour, wrought and putup in position frame & shutters sqm 2.520 Sundries inclusive of putty, brads, hold fasts and wind appliances and screws for planks (Vide standard specification) LS Total for each door * Note : Average rate for respective size scantlings and rough planks. BLD-CSTN-11-12 166 Country wood Framed and Planked Doors (Schedule Item No. 297) Single Shutter : i 1000 x 2000 mm Country wood cum 0.107 Labour, wrought and putup in position frame & shutters sqm 2.000 Sundries inclusive of putty, brads, hold fasts and wind appliances and screws for planks (Vide standard specification) LS Total for each door ii 1200 x 2100 mm Country wood cum 0.127 Labour, wrought and putup in position frame & shutters sqm 2.520 Sundries inclusive of putty, brads, hold fasts and wind appliances and screws for planks (Vide standard specification) LS Total for each door BLD-CSTN-11-13 167 Furniture - 6 Butt Hings - 1 Top and 2 Bottom Tower Bolts and One Wrought steel safety Hasp L.S. (Schedule Item No. 298) Each Door BLD-CSTN-11-14 168 Ledged Braced and Planked Doors (Schedule Item No. 299) Single Shutter : i 800 x 2000 mm *Teak wood cum 0.083 Labour, wrought and putup in position frame & shutters sqm 1.600 Sundries inclusive of hold fasts and wind appliances and nails for planks (Vide standard specification) LS ** Furniture - 3 Nos T - hinges - Vide SS for size - 2 Nos Chain and slopes country make. LS Total for each door 726 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 ii 1000 x 2100 mm *Teak wood cum 0.100 Labour, wrought and putup in position frame & shutters sqm 2.100 Sundries inclusive of hold fasts and wind appliances and nails for planks (Vide standard specification) LS ** Furniture - 3 Nos T - hinges - Vide SS for size - 2 Nos Chain and slopes country make. LS Total for each door Note : * Average rate for respective size scantlings and rough planks. ** Note that for this type of door the furniture will be supplied and fixed by the contractor. BLD-CSTN-11-15 169 * Country wood Ledged Braced and Planked Doors (Schedule Item No. 300) i 800 x 2000 mm Country wood cum 0.083 Labour, wrought and putup in position frame & shutters sqm 1.600 Sundries inclusive of hold fasts and wind appliances and nails for planks (Vide standard specification) LS ** Furniture - 3 Nos T - hinges - Vide SS for size - 2 Nos Chain and slopes country make. LS Total for each door ii 1000 x 2100 mm Country wood cum 0.100 Labour, wrought and putup in position frame & shutters sqm 2.100 Sundries inclusive of hold fasts and wind appliances and nails for planks (Vide standard specification) LS ** Furniture - 3 Nos T - hinges - Vide SS for size - 2 Nos Chain and slopes country make. LS Total for each door ** Note that for this type of door the furniture will be supplied and fixed by the contractor. Note : * Class of Country wood to be defined in relevent schedule item. BLD-CSTN-11-16 170 Flush type Doors with 35mm Thick Flush Shutters with Bondwood solied Block Board Type Faced on Both the sides with Commercial Type Plywood (Schedule Item No. 301.) Single Shutter : i 900 x 2000 mm *Teak wood cum 0.035 Flush Shutter 35mm thick (Vide relevant standard specification) sqm 1.530 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of hold fasts and all wind appliances (Vide standard specification) Total for each door 727 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 ii 1000 x 2100 mm *Teak wood cum 0.037 Flush Shutter 35mm thick (Vide relevant standard specification) sqm 1.820 Labour, wrought and putup in position frame & shutters sqm 2.100 Sundries inclusive of hold fasts and all wind appliances (Vide standard specification) Total for each door *Note : Average rate for respective size scantlings. BLD-CSTN-11-17 171 Windows Glazed (Schedule Item No. 302) A Single Shutter : i 600 x 1200 mm *Teak wood cum 0.028 Glass sqm 0.390 Labour, wrought and putup in position frame & shutters sqm 0.720 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window ii 800 x 1200 mm *Teak wood cum 0.037 Glass sqm 0.500 Labour, wrought and putup in position frame & shutters sqm 0.960 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window B Double Shutter : i 1000 x 1200 mm *Teak wood cum 0.041 Glass sqm 0.700 Labour, wrought and putup in position frame & shutters sqm 1.200 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window ii 1200 x 1200 mm *Teak wood cum 0.061 Glass sqm 0.710 Labour, wrought and putup in position frame & shutters sqm 1.440 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window iii 1500 x 1200 mm (3 Pannels) *Teak wood cum 0.072 Glass sqm 0.920 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window iv 1000 x 1700 mm (2 Pannels) *Teak wood cum 0.059 Glass sqm 0.970 Labour, wrought and putup in position frame & shutters sqm 1.700 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window 728 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-11-18 172 Furniture for Double Leaf Windows Glazed With Top Lights (Schedule Item No. 303) Banel Bolts 100 mm long each 2 Top tower bolts 150 mm long each 2 Bottom bolts 150 mm long each 2 Parliament hinges each 4 BLD-CSTN-11-19 173 Furniture for Double Leaf Windows Glazed without Top Lights (Schedule Item No. 304) LS Top tower bolts 150 mm long each 2 Bottom bolts 150 mm long each 2 Parliament hinges each 4 Same for all such windows BLD-CSTN-11-20 174 Furniture for Single Leaf Windows Glazed without Top Lights (Schedule Item No. 305) LS Top tower bolts 150 mm long each 1 Bottom tower bolts 150 mm long each 1 Parliament hinges each 2 Same for all such windows BLD-CSTN-11-21 175 Windows Panelled (Schedule Item No. 306) A Single Shutter i 600 x 1200 mm *Teak wood cum 0.039 Labour, wrought and putup in position frame & shutters sqm 0.720 Sundries inclusive of hold fasts and wind appliances (Vide standard specification) Total for each window ii 700 x 1200 mm **Teak wood cum 0.043 Labour, wrought and putup in position frame & shutters sqm 0.840 Sundries inclusive of hold fasts and wind appliances (Vide standard specification) Total for each window B Double Shutter i 800 x 1200 mm *Teak wood cum 0.051 Labour, wrought and putup in position frame & shutters sqm 0.960 Sundries inclusive of hold fasts and wind appliances (Vide standard specification) Total for each window ii 1000 x 12000 mm *Teak wood cum 0.059 Labour, wrought and putup in position frame & shutters sqm 1.200 Sundries inclusive of hold fasts and wind appliances (Vide standard specification) Total for each window iii 1200 x 1200 mm *Teak wood cum 0.081 Labour, wrought and putup in position frame & shutters sqm 1.440 Sundries inclusive of hold fasts and wind appliances (Vide standard specification) Total for each window *Note : Average rate for respective size scantlings. *Note : Average rate for respective size scantlings. 729 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 iv 900 x 1200 mm **Teak wood cum 0.056 Labour, wrought and putup in position frame & shutters sqm 1.080 Sundries inclusive of hold fasts and wind appliances (Vide standard specification) Total for each window **Note : Average rate for respective size scantlings and rough planks. BLD-CSTN-11-22 176 Windows Panelled & Glazed (Schedule Item No. 307) A Single Shutter 600 x 1200 mm **Teak wood cum 0.036 Glass sqm 0.070 Labour, wrought and putup in position frame & shutters sqm 0.720 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window B Double Shutter i 900 x 1200 mm **Teak wood cum 0.052 Glass sqm 0.100 Labour, wrought and putup in position frame & shutters sqm 1.080 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window ii 1200 x 1200 mm **Teak wood cum 0.077 Glass sqm 0.120 Labour, wrought and putup in position frame & shutters sqm 1.440 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window C 1500 x 1200 mm (3 Pannels) **Teak wood cum 0.094 Glass sqm 0.150 Labour, wrought and putup in position frame & shutters sqm 1.800 Sundries inclusive of putty, brads, hold fasts and wind appliances (Vide standard specification) Total for each window **Note : Average rate for respective size scantlings and rough planks. 177 Furniture for Windows Panelled : Single Leaf with half Shutters (Schedule Item No. 308) Cabin hooks and eyes 200 mm long each 2 Butt hinges 75 mm size each 4 Top tower bolts 150 mm long each 1 Bottom bolts 150 mm long each 1 Same for all such windows BLD-CSTN-11-23 178 Furniture for Windows Panelled : Double Leaf with half Shutters (Schedule Item No. 309) Cabin hooks and eyes 200 mm long each 4 Butt hinges 75 mm size each 8 Top tower bolts 150 mm long each 2 Bottom bolts 150 mm long each 2 Same for all such windows BLD-CSTN-11-24 179 Teak Wood Windows - Ledged Braced and Planked (Schedule Item No. 310) 730 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 i 600 x 1200 mm (half Shutters) *Teak wood cum 0.034 Labour, wrought and putup in position frame & shutters sqm 0.720 Sundries inclusive of all furniture and fitting in accordance with relevant standard specification LS Total for each window ii 800 x 1200 mm (half Shutters) *Teak wood cum 0.048 Labour, wrought and putup in position frame & shutters sqm 0.960 Sundries inclusive of all furniture and fitting in accordance with relevant standard specification LS Total for each window iii 900 x 1200 mm (half Shutters) *Teak wood cum 0.052 Labour, wrought and putup in position frame & shutters sqm 1.080 Sundries inclusive of all furniture and fitting in accordance with relevant standard specification LS Total for each window iv 1000 x 1200 mm (half Shutters) *Teak wood cum 0.052 Labour, wrought and putup in position frame & shutters sqm 1.200 Sundries inclusive of all furniture and fitting in accordance with relevant standard specification LS Total for each window *Note : Average rate for respective size scantlings and rough planks. BLD-CSTN-11-25 180 Ventilators Glazed - Fixed Double Frame and with Wire Netting (Schedule Item No. 312) i 800 x 500 mm *Teak wood cum 0.012 Glass sqm 0.240 Wire netting sqm 0.190 Labour, wrought and putup in position sqm 0.400 Sundries inclusive of putty brads and iron hold fasts where such are necessary say in 30 cm wall. LS Total for each Ventilator ii 1000 x 500 mm *Teak wood cum 0.014 Glass sqm 0.310 Wire netting sqm 0.240 Labour, wrought and putup in position sqm 0.500 Sundries inclusive of putty brads and iron hold fasts where such are necessary say in 30 cm wall. LS Total for each Ventilator iii 1200 x 600 mm *Teak wood cum 0.018 Glass sqm 0.480 Wire netting sqm 0.290 Labour, wrought and putup in position sqm 0.720 Sundries inclusive of putty brads and iron hold fasts where such are necessary say in 30 cm wall. LS Total for each Ventilator *Note : Average rate for respective size scantlings 731 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-11-26 181 Swing Ventilators - Glazed (Schedule Item No. 313) i 800 x 500 mm *Teak wood cum 0.021 Glass sqm 0.190 Labour, wrought and putup in position frame & shutters sqm 0.400 Sundries inclusive of putty brads sash centres brass ring iron cleats and window card - vide relevant standard specifications. LS Total for each Ventilator ii 1000 x 500 mm *Teak wood cum 0.025 Glass sqm 0.024 Labour, wrought and putup in position frame & shutters sqm 0.500 Sundries inclusive of putty brads sash centres brass ring iron cleats and window card - vide relevant standard specifications. LS Total for each Ventilator iii 1200 x 600 mm *Teak wood cum 0.030 Glass sqm 0.390 Labour, wrought and putup in position frame & shutters sqm 0.720 Sundries inclusive of putty brads sash centres brass ring iron cleats and window card - vide relevant standard specifications. LS Total for each Ventilator *Note : Average rate for respective size scantlings and rough planks. Aluminium Fixed Glazing BLD-CSTN-11-27 182 Supply and fixing of aluminimum fixed glazing as per drawing using standard powder coated/ anodised aluminimum section of 101.4 x 44.45 x 3.18 mm thick fitted with 6.0mm thick / 4.0 mm thick plain glass glazing fitted with suitable Aluminimum glazing clips and aproved brand silicon sealant including cost and conveyance of all materials labour charges for manufacturing fixing in position using wooden blocks and sheet metal screw etc. to complete for finished item of work as approved by Engineer-in-charge Unit - 1 sqm A) MATERIAL REQUIREMENT ALUMINIUM SECTION GLAZING with GLASS SILICON SEALANT RUBBER BEADING B) LABOUR CHARGES 1st Class Carpenter day 0.947 2nd Class Carpenter day 1.158 Power Saw Cutter - Hand Operated - Operator day 0.105 Power Drill - Hand Operated - Operator day 0.211 Unskilled Mazdoor day 0.632 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 0.842 Power Drill - Hand Operated - Hire Charges Hrs 1.684 Supervision Charges Nos 0.211 Power charges for Motors 1% BASIC COST per 1 sqm Aluminimum Partition partly glazed 732 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-11-28 183 Supply and fixing of aluminimum Partition partly glazed as per drawing using standard powder coated/ anodised aluminimum section of 101.4 x 44.45 x 3.18 mm thick fitted with 12.0mm thick Particle Boards - prelaminated up to 2.1 M height and balance height provided with 5.0 mm thick plain glass glazing fitted with suitable Aluminimum glazing clips and aproved brand silicon sealant including cost and conveyance of all materials labour charges for manufacturing fixing in position using wooden blocks and sheet metal screw etc. to complete for finished item of work as approved by Engineer-in-charge Unit - 1 sqm A) MATERIAL REQUIREMENT ALUMINIUM SECTION PARTICLE BOARD - Prelaminated GLAZING with GLASS SILICON SEALANT RUBBER BEADING B) LABOUR CHARGES 1st Class Carpenter day 1.042 2nd Class Carpenter day 1.042 Power Saw Cutter - Hand Operated - Operator day 0.104 Power Drill - Hand Operated - Operator day 0.139 Unskilled Mazdoor day 0.347 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 0.833 Power Drill - Hand Operated - Hire Charges Hrs 1.111 Supervision Charges Nos 0.174 Power charges for Motors 1% BASIC COST per 1 sqm BLD-CSTN-11-29 184 Aluminium Anodised Casement windows Unit - 1 sqm Supply and fixing Aluminium Anodised Casement windows as per approved drawing with aluminium anodised sections of Series C Jindal Hollow sections and outer frame of 8804 of size 46 x 44 mm, Shutter frame of 8802 of size 44 mm x 46 mm and Mullion frame of 8803 of size 59 x 38 and glazing section of 4433 with plain clear float glass 6 mm thick fixed including supply and fixing aluminium powder coated 1 No.of casement friction stay hinges for each shutter, 1 Nos. aluminium handles of 150 mm for each shutter and all labour charges for fixing the fixtures with required no.of screws, bolts and nuts and including labour charges for fixing the frame in position, fixing shutter to frame etc. completed for finished item of work Unit - 1 sqm A) MATERIAL REQUIREMENT ALUMINIUM SECTION GLAZING with GLASS SILICON SEALANT RUBBER BEADING Alum.Anodised.PC Friction stay casement hinges Alum.Anodised.PC Handles B) LABOUR CHARGES 1st Class Carpenter day 0.360 2nd Class Carpenter day 1.081 as per design as per design as per design as per design as per design as per design as per design as per design as per design 733 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Power Saw Cutter - Hand Operated - Operator day 0.360 Power Drill - Hand Operated - Operator day 0.360 Unskilled Mazdoor day 1.081 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 2.883 Power Drill - Hand Operated - Hire Charges Hrs 2.883 Supervision Charges Nos 0.360 Power charges for Motors 1% BASIC COST per 1 sqm Aluminium Two/ Three Track Sliding Windows BLD-CSTN-11-30 185 Supply and fixing Aluminium Anodised Two/ Three Track Sliding Windows as per approved drawing with aluminium anodised sections of Series C Jindal sections and outer frame top horizontals & both verticals of 8774 of size 62 x 29.5 mm and bottom horizontal - two track frame of 8773 of size 62 x 29.5 mm, Shutter frame top, bottom and verticals of 8304 of size 50 mm x 20 mm and Weather interlocking frame of 8306 of size 50 x 20 with plain clear float glass 5 mm thick fixed including supply and fixing aluminium handles of 100 mm for each shutter, nylon rollers assembly and all labour charges for fixing the fixtures with required no.of screws, bolts and nuts and including labour charges for fixing the frame in position, fixing shutter to frame etc. completed for finished item of work UNIT 1 sqm A) MATERIAL REQUIREMENT ALUMINIUM SECTION GLAZING with GLASS SILICON SEALANT RUBBER BEADING Alum.Anodised.PC Handles B) LABOUR CHARGES 1st Class Carpenter day 0.347 2nd Class Carpenter day 1.042 Power Saw Cutter - Hand Operated - Operator day 0.347 Power Drill - Hand Operated - Operator day 0.347 Unskilled Mazdoor day 1.042 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 2.778 Power Drill - Hand Operated - Hire Charges Hrs 2.778 Supervision Charges Nos 0.347 Power charges for Motors 1% BASIC COST per 1 sqm as per design as per design as per design as per design as per design 734 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Aluminium Anodised Doors - Single Shutter BLD-CSTN-11-31 186 Supply and fixing Aluminium Anodised Doors - Single Shutter as per approved drawing with aluminium anodised sections of Jindal sections and outer frame top horizontals & both verticals of 2408 of size 101.6 x 44.75 x 3.18 mm Shutter frame top, bottom and verticals of 4504 of size 44.45 mm x 47.62 mm x 3.18 and Middle lock rail of 4621 of size 49.91 x 44.45 x 3 mm with plain clear float glass 5 mm thick fixed including supply and fixing aluminium handles of 100 mm for each shutter, floor springs/ hydraulic door closure assembly and all labour charges for fixing the fixtures with required no.of screws, bolts and nuts and including labour charges for fixing the frame in position, fixing shutter to frame etc. completed for finished item of work UNIT 1 sqm A) MATERIAL REQUIREMENT ALUMINIUM SECTION GLAZING with GLASS SILICON SEALANT RUBBER BEADING Alum.Anodised.PC Handles Hydraulic Floor Spring/ Door Closure B) LABOUR CHARGES 1st Class Carpenter day 0.417 2nd Class Carpenter day 0.833 Power Saw Cutter - Hand Operated - Operator day 0.417 Power Drill - Hand Operated - Operator day 0.417 Unskilled Mazdoor day 1.250 C) Machinery Power Saw Cutter - Hand Operated - Hire charges Hrs 3.333 Power Drill - Hand Operated - Hire Charges Hrs 3.333 Supervision Charges Nos 0.417 Power charges for Motors 1% BASIC COST per 1 sqm BLD-CSTN-11-32 187 Removing white wash or colour wash by steel wire brushing and/or scraping; sand papering and preparing the wall surface smooth including necessary repairs to scratches complete Details of cost for 10 sq.m Labour : White washer / Mason 2nd Class day 0.010 Mazdoor (unskilled) day 0.170 Sundries such as sand paper and scraper etc. Scaffolding Add for water charges @ 1 % Add for contractor's profit and overheads Cost for 10 sq.m. Cost per sq.m BLD-CSTN-11-33 188 Removing white wash or colour wash by steel wire brushing and/or scraping; sand papering and preparing the ceiling and/or sloping roofs surface smooth including necessary repairs to scratches complete Deatailed cost for 10 sqm Rate as per above item 10 sqm Add 10 % extra for ceiling / sloping roof Cost per 10 sq.m Cost per sq.m as per design as per design as per design as per design as per design as per design 735 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-11-34 189 Removing white wash or colour wash by steel wire brushing and/or scraping; sand papering and preparing the wall surface smooth including necessary repairs to scratches complete for the wall surface spoiled by smoke soot Rate as per Item No (203) 10 sqm For washing the wall surface spoiled by smoke soot with clear water before sand papering the surface smooth and including necessary repairs to the scratches complete Details of cost for 10 sq.m Labour : Mazdoor (unskilled) day 0.080 Sundries Add for water charges @ 1 % Add for contractor's profit and overheads Cost for 10 sq.m. Cost per sq.m BLD-CSTN-11-35 190 Removing white wash or colour wash by steel wire brushing and/or scraping; sand papering and preparing the ceiling and/or sloping roofs surface smooth including necessary repairs to scratches complete for the ceiling surface spoiled by smoke soot Rate as per Item No (205) 10 sqm Extra 10% for washing the surface with clean water on ceiling and/or sloping roofs Cost per 10 sq.m Cost per sq.m BLD-CSTN-11-36 191 Washing and cleaning of decorated wall surfaces with soap, soda and water Details of cost for 10 sq.m Labour : White washer / Mason 2nd Class day 0.010 Mazdoor (unskilled) day 0.170 Sundries such as soap, soda, sand paper and scaper etc Add for water charges @ 1 % Cost for 10 sq.m. Cost per sq.m BLD-CSTN-11-37 192 Washing and cleaning of the old plastered ceiling and/or sloping roofs with soap, soda and water Rate as per Item above Extra 10% over Cost per 10 sq.m Cost per sq.m BLD-CSTN-11-38 193 Washing and cleaning of oil and grease spots on decorated wall surface by suitable chemical Details of cost for 10 sq.m Labour : White washer / Mason 2nd Class day 0.010 Mazdoor (unskilled) day 0.170 Sundries, such as chemical etc. Add for water charges @ 1 % Cost for 10 sq.m. Cost per sq.m 736 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-12 DISMANTLING & DEMOLITION BLD-CSTN-12-1 194 Demolishing and disposal of unserviceable materials within 100 metres lead i Lime concrete. Details of cost for 1 cu.m. Labour :- Mazdoor (unskilled) day 1.220 Sundries Add for water charges @ 1 % Cost per cu m ii Unreinforced cement concrete upto 15 cm thicknes Details of cost for 1 cu.m. Labour :- Mazdoor (unskilled) day 2.440 Sundries Add for water charges @ 1 % Cost per cu m iii Unreinforced cement concrete more than 15 cm thickness Details of cost for 1 cu.m. Labour :- Mazdoor (unskilled) day 4.880 Sundries Add for water charges @ 1 % Cost per cu m BLD-CSTN-12-2 195 Demolition including stacking of serviceable materials and disposal of unserviceable materials within 100 metres lead i R.C.C. work Details of cost for 1 cu.m. Labour :- Mazdoor (unskilled) day 4.320 Sundries Add for water charges @ 1 % Cost per cu m ii Reinforced Brick work: Details of cost for 1 cu.m. Labour :- Mazdoor (unskilled) day 4.090 Sundries Add for water charges @ 1 % Cost per cu m BLD-CSTN-12-3 196 Extra over item 20.3 for cutting steel bars in R.C.C. of R.B. work (sectional area of R.C.C. or R.B. Work to be measured) Details of cost for one Sq.m. of sectional area Reinforced area considering 1% Labour for cuttings 0.01 Sq.m. reinforcement Blacksmith 2nd class day 0.500 Mazdoor (Male) day 0.500 Sundries Add for water charges @ 1 % Cost per sq m 737 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-12-4 197 Dismantling doors, windows and clear storey windows, ventilators etc.; (wood or steel) shutters including chowkhats, architraves, hold fasts and other attachments etc., complete and stacking them within 100 metre lead i Not exceeding 3 sq.m. in area: Details of cost per each Labour :- Mason, II class day 0.100 Mazdoor (male) day 0.200 Blacksmith II class day 0.050 Sundries Add for water charges @ 1 % Cost per each ii Exceeding 3 sq.m. in area Details of cost per each Labour :- Mason, II class day 0.130 Mazdoor (male) day 0.270 Blacksmith II class day 0.070 Sundries Add for water charges @ 1 % Cost per each BLD-CSTN-12-5 198 Taking out doors, windows and clearestorey window shutters (steel or wood) including stacking within 100 metres lead i Not exceeding 3 sq.m. in area: Details of cost per each Labour :- Carpenter II class day 0.060 Mazdoor (male) day 0.120 Sundries Add for water charges @ 1 % Cost per each ii Exceeding 3 sq.m. in area Details of cost per each Labour :- Carpenter II class day 0.080 Mazdoor (male) day 0.160 Sundries Add for water charges @ 1 % Cost per each BLD-CSTN-13 MISCELLANEOUS BUILDING ITEMS BLD-CSTN-13-1 199 Providing and fixing aluminium step edging 'L' shape of size 38 mm x 12 mm x 3 mm (thick) to stairs Details of cost for 3 metres length Materials: Aluminium step edging 'L' shape 38 x 12 x 3mm (thick) = 3.00 metres with 5% wasage m 3.150 Carriage of materials Sundries (Wooden plugs, screws and painting underneath of strips with bitumanistic paint, etc.,) Labour :- Carpenter II class day 0.090 Mason I class day 0.250 Mazdoor (male) day 0.250 Add for water charges @ 1 % Cost for 3 m Cost per m 738 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-13-2 200 Providing and fixing aluminium step edging 'L' shape of size 57 mm x16 mm x 3 mm (thick) to stairs Details of cost for 3 metres length Materials: Aluminium step edging 'L' shape 57 mm x16 mm x 3 mm (thick) with 5% wasage m 3.150 Carriage of materials Sundries (Wooden plugs, screws and painting underneath of strips with bitumanistic paint, etc.,) Labour :- Carpenter II class day 0.090 Mason I class day 0.250 Mazdoor (male) day 0.250 Add for water charges @ 1 % Cost for 3 m Cost per m BLD-CSTN-13-3 201 Cutting RCC steps for fixing of aluminium step edging and make good to match the surroundings Details of cost for 3 metres Cement Mortar Labour :- Mason, II Class day 1.000 Mazdoor (male) day 0.100 Add for water charges @ 1 % Cost for 3 m Cost per m BLD-CSTN-13-4 202 Providing and fixing 25 mm bore galvanised M.S. tube (light grade) outlet in cement mortar 1:3(1 cement: 3 fine sand) including cutting and making good the wall Details of cost for 10 pipes 12.5 cm long day i.e., 1.25 metres Materials: Galvanised mild steel tube (light grade) 25 mm nominal bore 10 x 12.5 cm = 1.25 metre with wastage of 5% m 1.310 Labour :- For cutting and fixing in position Assistant fitter day 0.100 Mason. day 0.400 Mazdoor (male). day 0.400 Sundries Add for water charges @ 1 % Cost for 1.25 m Cost per m BLD-CSTN-13-5 203 Providing and fixing 1.80 metre long RCC fencing posts with 6 mm bar nibs as per design in plate No. 22/2/2. (earth work & concrete to be paid for separately) Details of cost for 10 pipes 12.5 cm long day i.e., 1.25 metres Materials: Galvanised mild steel tube (light grade) 40 mm nominal bore 10 x 12.5 cm = 1.25 metre with wastage of 5% m 1.310 Labour :- For cutting and fixing in position Assistant fitter day 0.100 Mason. day 0.400 Mazdoor (male). day 0.400 Sundries 739 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Add for water charges @ 1 % Cost for 1.25 m Cost per m BLD-CSTN-13-6 204 Providing and fixing 1.80 metre long RCC fencing posts with 6 mm bar bibs as per design in plate No. 22/2/2. (earth work & concrete to be paid for separately) Details of cost for 10 posts, i.e., 0.336 Cu. m (Details as per Annexure ' X ' at the end of this item) Materials: Cement concrete 1:2:4 (1 cement : 2 coarse sand :4 graded stone aggregate 12.5 mm nominal size) cum 0.336 (Rate as per item No.5.42.d Section Concrete work) M.S. reinforcement 6 mm dia bars 10 x 4 x 1.88 = 75.20 metres 10 x 9 x 0.50 = 45.00 metres./ l20.00 m 120.20 m @ 0.22 Kg/m=26.44 Kg kg 26.440 (Rate as per item No.5.51 Section Concrete work) Centering and shuttering cum 0.336 (Details as per Annexure 'X') (Rate as per item No.9.1.8. of Section 9 Form work). 10 mm cement plaster with cement mortar 1:2 (1 cement: 2 sand) sqm 9.880 (Details as per Annexure 'X') Carriage of R.C.C. posts 6 mm bar bibs Sundries Labour for fixing posts in line Mason, 1st Class day 0.120 Mason, 2nd Class day 0.120 Mazdoor (Male) day 0.250 Add Water charges on A @ 1% Add Contractor's profit and overheads on 'A' + 'B' + 'C @ 10% Cost for 10 posts Cost per post Sub Analysis : Plastering with CM 1:3, 12 mm thick 10 sqm 1.000 Deduct - CM 1:3 cum 0.025 Add - Cement (720-480 x .125) cum 30.000 Rate for 10 sqm Rate per sqm Annexure - 'X' Details of quantities for RCC posts Concrete quantity Area of bottom A, =15+12.5/2 x 8.75+1/2 x 22/7 (6.25) = 120.31+61.38=181.69 Sq.m. Area of top A2= 10+7.5/1 x 6.25 + 1/2 x 22 x (3.75) 2 / 7= 54.69+22.10=76.79 Sq.Cm. A v A 2 = 118.12 Sq. Cm. Volume = h/3(A, + A2 + VA,A2) A2+A2+A, A2=0.V03766 Sq.m 740 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Volume = 1.05/3 * 0.03766 = 0.0131810 Cu.m. =0.0132 Cu.m. Volume of lower square portion =0.165x0.165x0.75 =0.0204 Cu.m Total volume = 0.0336 Cu. m Quantity for 10 posts = 0.336 Cu.m Quantity of centring & shuttering 0.2770* 1.05=0.2908 Sq.m. 3x0.165x0.75=0.3712 0.165x0.165=0.0272 0.10 x 0.10=0.0100/0.6992 Sq.m.. For ten posts=10 x 0.6992 = 6.992 Sq.m. Quantity of surface plaster area 12.50+7.60+7.60=27.70 Cm. xr=3.1416x5=15.71Cm./43.41Cm 0.434 x 1.05=0.4560 Sq.m. 4x0.165x0.75=0.4950 0.165x0.165=0.0272 0.10 x 0.10=0.0100/0.9882 Sq.m. For 10 posts = 10 x 0.9882=9.88 Sq.m. BLD-CSTN-13-7 205 Supplying and fixing galvanised steel barbed wire (IS : 278-1962 Type I) weighing 9.38 Kg per 100 metres (min.), Straining and fixing to any type of standard, rails, straining bolts, including securing with and provision of galvanised mild steel wire, stapples or steel pins, etc., as directed (Posts and struts of wood, concrete, steel, etc.) and straining bolts shall be paid for separately). Details of Cost per 100 metres (day line of wire) Materials: Galvanised steel barbed wire IS type I weighing 9.38 Kg/100 metre kg 9.380 Carriage of barbed wire. G.I. staples steel pins or binding wire LS Labour :- For fixing & stretching wire Blacksmith, 1st Class day 0.150 Blacksmith, 2nd Class day 0.150 Mazdoor (male). day 0.300 Sundries. Add water charges @ 1 % Cost for 100 metres day line of wire Rate per m BLD-CSTN-13-8 206 Broken glass coping as specified on top of walls In cement mortar 1:3 (1 cement: 3 sand) Details of cost per one Sq.m. Materials: Broken glass. kg 19.500 Cement mortar 1:3(1 cement: 3 sand) cum 0.040 Labour :- Mason (Skilled) day 0.080 Mazdoor (Male) day 0.160 Scaffolding etc Add water charges @ 1 % Cost per Sq.metre 741 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-14 ANTE-TERMITE TREATMENT BLD-CSTN-14-1 207 Providing Antitermite treatment as per IS 6315 (Part - 2) 2001 (Pre-constructional chemical treatment measures) along the internal & external vertical faces of the columns, plinth beams, basement and top surface of the basement filling below flooring bed as per the specified procedure conforming to IS 6315 (Part-2) 2001 and other relevant approved specification duly using Chlorpyriphos/ Lindane emulsifiable concentrate 20% with 1% concentration @ 7.5 Liters/ sqm of the vertical surface & @ 5.0 Liters/ sqm of the horizontal surface of the substructure to a depth of 500 mm around columns & 300 mm deep around plinth beams, basements & floor filling area including excavation channel along the wall & rodding etc & cost & conveyance of all materials to the site, cost of labour for spraying, rodding etc complete for finished item of work as per the approval of the Engineer-in-Charge Unit = 10 sqm A) Chlorpyriphos/ Lindane emulsifiable concentrate of 20% 1 liter : 19 Parts water Therefore: 868.55 L /20 Lit 4.100 Add 12%wastage Liters 0.41 Total Quantity 4.51 B) Add Water Charges @ 1% 1% C) Labour Charges Man Mazdoor day 3.0 Sprayer day 0.22 D) Hire charges Sprayer, drilling machine etc 10% sundries & contingencies 3% Water charges & electricity 1.50% Add OH & CP BASIC COST per 1 sqm Note: CPWD - Rate Analysis per 9 Sqm Vertical Chloropyriphos Lit Earthwork excavation cum Beldar Nos Horizontal Chloropyriphos Lit Vertical Nos Beldar Nos Hire charges Sprayer, drilling machine etc sundries & contingencies Water charges & electricity Add OH & CP BLD-CSTN-15 CENTERING, FORM WORK etc. BLD-CSTN-15-1 208 Providing traditional centering, shuttering and scaffolding using Cashewrina balli props and bracings supporting wooden brackets, wooden wall plates, wooden runners and steel plate form work as per the approved plan and other accessories as per the standard trade practice including hire charges for ballies, runners, wooden members and cost and conveyance of all other consumable accessories, taxes etc complete for finished item of work UNIT 1 sqm (I) Unsupported Roof Height up to - 3.66 M (12'0") A) MATERIAL REQUIREMENT Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 2.40 742 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Wall Plate Brackets / beam bottom supports Nos 1.44 Wedge Plate fixture Nos 1.44 Runner beams of approximately 4" x 4" size RM 16.00 Steel Plate - form work plates - sqm 1.86 B) LABOUR CHARGES 0.00 1st Class Carpenter day 0.16 2nd Class Carpenter day 0.28 Unskilled Mazdoor day 0.48 Supervision Charges day 0.04 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm (II) Unsupported Roof Height up to - 4.60 M (15'0") A) MATERIAL REQUIREMENT Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 4.32 Wall Plate Brackets / beam bottom supports Nos 1.44 Wedge Plate fixture Nos 1.44 Runner beams of approximately 4" x 4" size RM 16.00 Steel Plate - form work plates - sqm 1.86 B) LABOUR CHARGES 1st Class Carpenter Nos 0.20 2nd Class Carpenter Nos 0.36 Unskilled Mazdoor Nos 0.68 Supervision Charges Nos 0.06 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm (III) Unsupported Roof Height up to - 7.30 M (24'0") A) MATERIAL REQUIREMENT Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 5.76 Wall Plate Brackets / beam bottom supports Nos 1.44 Wedge Plate fixture Nos 1.44 Runner beams of approximately 4" x 4" size RM 16.00 Steel Plate - form work plates - sqm 1.86 B) LABOUR CHARGES 1st Class Carpenter Nos 0.28 2nd Class Carpenter Nos 0.52 Unskilled Mazdoor Nos 1.08 Supervision Charges Nos 0.08 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm BLD-CSTN-15-2 209 Providing rigid Steel centering, shuttering and scaffolding using steel pipes, adjustable Jack screw props, acro spans, couplers, tie rods, bracings members, supporting brackets, acro span beams and steel plate/ ply-wood form work as per the approved shuttering designs & plan and other accessories as per the IS Norms and stability calculations including hire charges for jack pipes, acro spans, runners, wooden members and cost and conveyance of all other consumable accessories, taxes etc complete for finished item of work UNIT 1 sqm (I) Unsupported Roof Height up to - 3.66 M (12'0") A) MATERIAL REQUIREMENT Jack Screw Adjsutable Props - 50 mm dia B Class Pipes for vertical props placed @ 3'0" c/c in bothways Approximately 33'-0" x 33'-0" roof area 743 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Span Beams - 2.4 M Long (Acro Spans) - Approximtely Wallers, Couplers, Foot Plates Steel Plate Beam Bottom - form work plates - 9" wide 230 mm wide plate x 80 RM Beam Sides - form work plates - 15" wide 400 mm wide plate x 80 RM - both sides Slab Bottom Plates - formwork plates 3'-0" x 4'-0" - 7 Nos 3'-0" x 2'-0" - 2 Nos 1'-0" x 4'-0" - 1 Nos Slab Sides - 0-6" Height - 40.0 RM Total Scaffolding Pipes & Centering Plates - Appx - Kgs 62.51 B) LABOUR CHARGES 1st Class Carpenter day 0.22 2nd Class Carpenter day 0.38 Unskilled Mazdoor day 0.72 Supervision Charges day 0.04 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm (II) Unsupported Roof Height up to - 7.32 M (24'0") A) MATERIAL REQUIREMENT Heavy Frames - 50 mm dia B Class Pipes (HD Span Beams - 2.4 M Long (Acro Spans) - Approximtely Wallers, Couplers, Foot Plates Steel Plate Beam Bottom - form work plates - 9" wide 230 mm wide plate x 80 RM Beam Sides - form work plates - 15" wide 400 mm wide plate x 80 RM - both sides Slab Bottom Plates - formwork plates 3'-0" x 4'-0" - 7 Nos 3'-0" x 2'-0" - 2 Nos 1'-0" x 4'-0" - 1 Nos Slab Sides - 0-6" Height - 40.0 RM Total Scaffolding Pipes & Centering Plates - Appx - Kgs 112.635 B) LABOUR CHARGES 1st Class Carpenter day 0.32 2nd Class Carpenter day 0.52 Unskilled Mazdoor day 1.28 Supervision Charges day 0.06 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm 744 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 TYPE OF STRUCTURE UNIT COST OF CENT ERIN RCC STRUCTU RE UNIT MEASUR EMENT B C A FOOTINGS 3.88 sqm per 1 cum B PEDESTALS 6.17 sqm per 1 cum C PLINTH BEAMS 9.35 sqm per 1 cum D LINTELS 7.94 sqm per 1 cum E CHAJJAS - SUNSHADES 1.22 sqm per 1 sqm F COLUMNS 11.15 sqm per 1 cum G BEAMS 9.35 sqm per 1 cum H SLABS - Up to 150 mm thick 1.05 sqm per 1 sqm I SLABS - above 150 mm - Up to 300 mm thick 1.09 sqm per 1 sqm J SLABS - above 300 mm thick 1.14 sqm per 1 sqm K WAFFLE - (GRID) SLABS (Rib Beams with Slabs) 3.85 sqm per 1 sqm L PERGOLA SLABS (Only Rib Beams) 2.70 sqm per 1 sqm M ARCHE BEAMS - up to 1.5 M Span 10.63 sqm per 1 cum N ARCHE BEAMS - above 1.5 M Span 10.78 sqm per 1 cum O DOME SLABS 17.19 sqm per 1 cum P HELICAL STAIRCASES 1.31 sqm per 1 sqm BLD-CSTN-15-3 210 Providing STAGE SCAFFOLD with staging using Cashewrina balli props and bracings supporting wooden brackets, wooden stage scaffold boards including hire charges for cashewrina ballies, wooden baords, scaffolds etc., and cost and conveyance of all other consumable accessories, taxes etc complete for finished item of work for PLAN AREA UNIT 1 sqm (I) Unsupported Roof Height up to - 3.66 M (12'0") A) MATERIAL REQUIREMENT Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 2.40 Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 2.70 B) LABOUR CHARGES 1st Class Carpenter day 0.04 2nd Class Carpenter day 0.30 Unskilled Mazdoor day 0.48 Supervision Charges day 0.04 Consumables like Rope, Nails, de-shuttering oil 1% Note : Cost of Centering charges with different centering & scaffolding materials for different structures may be calculated as per the guidelines given Below For calculating centering charges of RCC Structures, using either cashewrina balli scaffolding or steel pipe scaffolding, the respective cost may be arrived by taking the above values. CENTERING AREA A Therefore, Centering charges for any structure:C= A x B 745 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - PLAN AREA (II) Unsupported Roof Height up to - 4.60 M (15'0") A) MATERIAL REQUIREMENT Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 4.32 Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 2.70 B) LABOUR CHARGES 1st Class Carpenter day 0.08 2nd Class Carpenter day 0.38 Unskilled Mazdoor day 0.68 Supervision Charges day 0.06 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - PLAN AREA (III) Unsupported Roof Height up to - 7.30 M (24'0") A) MATERIAL REQUIREMENT Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 5.76 Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 2.70 B) LABOUR CHARGES 1st Class Carpenter day 0.12 2nd Class Carpenter day 0.54 Unskilled Mazdoor day 1.08 Supervision Charges day 0.08 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - PLAN AREA BLD-CSTN-15-4 211 Providing ACCESS SCAFFOLD using Cashewrina balli props and bracings supporting wooden brackets, wooden stage scaffold boards including hire charges for cashewrina ballies, wooden baords, scaffolds etc., and cost and conveyance of all other consumable accessories, taxes etc complete for finished item of work for ELEVATION AREA UNIT 1 sqm (I) Up to - 3.66 M (12'0") A) MATERIAL REQUIREMENT Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 1.74 Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 0.72 B) LABOUR CHARGES 1st Class Carpenter day 0.07 2nd Class Carpenter day 0.11 Unskilled Mazdoor day 0.2 Supervision Charges day 0.04 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - VERTICAL ELEVATION AREA (II) Up to - 7.32 M (24'0") A) MATERIAL REQUIREMENT 746 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height Nos 1.74 Scaffold Boards - Bamboo scaffolds - Bamboos - 8'0" long Nos 0.38 B) LABOUR CHARGES 1st Class Carpenter day 0.12 2nd Class Carpenter day 0.22 Unskilled Mazdoor day 0.36 Supervision Charges day 0.04 Consumables like Rope, Nails,de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - VERTICAL ELEVATION AREA BLD-CSTN-15-5 212 Providing STAGE SCAFFOLD using Steel Scaffolding Pipe Frames made of 40 mmd ia MS Pipes and bracings with scaffold boards including hire charges for MS Pipe Frames scaffolds boards etc., and cost and conveyance of all other consumable accessories, taxes etc complete for finished item of work for PLAN AREA UNIT 1 sqm (I) Unsupported Roof Height up to - 3.66 M (12'0") A) MATERIAL REQUIREMENT Jack Screw Adjsutable Props - 50 mm dia B Class Pipes for vertical props placed @ 3'0" c/c in bothways Lock Pins LD Foot Plates LD Couplers Total Scaffolding Pipes - Appx - Kgs 39.26 B) LABOUR CHARGES 1st Class Carpenter day 0.04 2nd Class Carpenter day 0.34 Unskilled Mazdoor day 0.60 Supervision Charges day 0.04 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - PLAN AREA (II) Unsupported Roof Height up to - 7.32 M (24'0") A) MATERIAL REQUIREMENT Heavy Frames - 50 mm dia B Class Pipes (HD Towers) Lock Pins LD Foot Plates LD Couplers Total Scaffolding Pipes - Appx - Kgs 112.635 B) LABOUR CHARGES 1st Class Carpenter day 0.12 2nd Class Carpenter day 0.58 Unskilled Mazdoor day 1.20 Supervision Charges day 0.08 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - PLAN AREA 747 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 BLD-CSTN-15-6 213 Providing ACCESS SCAFFOLD using Steel Scaffolding Pipe Frames made of 40 mmd ia MS Pipes and bracings with scaffold boards including hire charges for MS Pipe Frames scaffolds boards etc., and cost and conveyance of all other consumable accessories, taxes etc complete for finished item of work for ELEVATION AREA UNIT 1 sqm (I) Up to - 3.66 M (12'0") A) MATERIAL REQUIREMENT MS Pipe Scaffold Frames - 1.20 x 1.50 M Approximately 27.3 M Long x 3.66 M High MS Pipe Bracing structure - 1.5 x 2.25 M Scaffold Board Lock Pins LD Foot Plates LD Couplers Total Scaffolding Pipes - Appx - Kgs 19.7496 B) LABOUR CHARGES 1st Class Carpenter day 0.07 2nd Class Carpenter day 0.11 Unskilled Mazdoor day 0.24 Supervision Charges day 0.04 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - VERTICAL ELEVATION AREA (II) Up to - 7.32 M (24'0") A) MATERIAL REQUIREMENT MS Pipe Scaffold Frames - 1.20 x 1.50 M Approximately 27.3 M Long x 3.66 M High MS Pipe Bracing structure - 1.5 x 2.25 M Scaffold Board Lock Pins LD Foot Plates LD Couplers Total Scaffolding Pipes - Appx - Kgs 19.14 B) LABOUR CHARGES 1st Class Carpenter day 0.12 2nd Class Carpenter day 0.22 Unskilled Mazdoor day 0.44 Supervision Charges day 0.04 Consumables like Rope, Nails, de-shuttering oil 1% Tape, cover plates 1% Tools like Hammers etc., 1% BASIC COST per 1 sqm - VERTICAL ELEVATION AREA Description of Structure a b Cost of Scaffolding materials = Rs. A Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates,etc., Cashewrina Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., Let : Cost of Scaffolding materials = Rs. A Scrap value of Scaffolding materials = Rs. B Let : C (Usually B = A * 10%) Number of uses of Scaffolding materials = C Therefore, Hire Charges of scaffolding Materials: (Rs. A - Rs. B) 1. For Material Lift Charges & Labour rate for scaffolding above 7.32 M - increase @ 50% on labour component for each upper floor on First Floor Rate (7.32 M) 2. For Hire Charges of scaffolding Materials following ratesmay be allowed: Note: HIRE & LIFT CHARGES - for all Scaffolding Materials 748 BLD-CSTN Index-code S No Description Unit Quantity Rate Rs. Amount Rs. Remarks 1 2 3 4 5 6 7 Number of uses of Scaffolding materials (C ) Wooden Materials - No of Uses - 10 Times (C) Period of Requirement of Centering Material Slabs : 14 + 4 = 18 days Columns : 1.50 days Foundations : 2 days Scrap value of Scaffolding materials = Rs. B (Usually B = A * 10%) Period of Hire of Scaffolding materials, in years = C Life of Scaffolding materials, in years = D Therefore, Hire Charges of scaffolding Materials: Note: While calculating the Capital Cost of the materials, deprication shall be allowed based on the service life of the materials. Period of Hire of Steel Scaffolding materials, in years = 1.64 (200 days per Annum) D [(Rs. A - Rs. B)*C] Life of Steel Forms & Scafholding Material - 3 Years (D) 749