100% found this document useful (1 vote)
532 views

Leveling and Alignment of Pump Quality Control and Inspection Report Form

This document is a filed inspection report for leveling and alignment of a pump. It includes sections to record inspection details such as the inspection type and number, date, names of inspectors, level readings at points around the pump discharge flange and base plate, tolerances for shaft speed, soft foot measurements, and coupling alignment readings and tolerances.

Uploaded by

hasan_676489616
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
532 views

Leveling and Alignment of Pump Quality Control and Inspection Report Form

This document is a filed inspection report for leveling and alignment of a pump. It includes sections to record inspection details such as the inspection type and number, date, names of inspectors, level readings at points around the pump discharge flange and base plate, tolerances for shaft speed, soft foot measurements, and coupling alignment readings and tolerances.

Uploaded by

hasan_676489616
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

FILED INSPECTION REPORT

ITP No.: ___________________


Inspection GR.: ___________________
Report No.: ___________________
Date: ___________________

Inspection Type : WORK No. :
ITEM No. :
LOCATION :
SIGNATURE

LEVELING OF PUMP
COMPANY CONTRACTOR SUBCONTRACTOR
INSPECTION NOTICE No.:

COMPANYS INSPECTOR:
CONTRACTOR INSPECTOR:
SUBCONTRACTOR INSPECTOR:
























POINT


DIRECTION

DIFF.

REMARK
DISCHARGE FLANGE
0
180
90
270






















TOP OF BASE PLATE (SKID)

POINT

READING DIFF. REMARK
E
F
G
H







FILED INSPECTION REPORT
ITP No.: ___________________
Inspection GR.: ___________________
Report No.: ___________________
Date: ___________________

Inspection Type : WORK No. :
ITEM No. :
LOCATION :
SIGNATURE

PRE& FINAL ALIGNMENT OF PUMP
COMPANY CONTRACTOR SUBCONTRACTOR
INSPECTION NOTICE No.:

COMPANYS INSPECTOR:
CONTRACTOR INSPECTOR:
SUBCONTRACTOR INSPECTOR:




















ALLOWABLE :
SHAFT SPEED(rpm) SHAFT PARALLEL (A=A.A*) SHAFT ANGULAR (B=B.B*)


SOFT FOOT TOLERANCE: .0.05 mm 1 2
NO. 1 2 3 4
SOFT FOOT
ACTUAL

3 4

COUPLING ALIGNMENT:
0 90 180 270
TOLERANCE
A AXIAL
ACTUAL
TOLERANCE
B RADIAL
ACTUAL
TOLERANCE
C DBSE
ACTUAL