0% found this document useful (0 votes)
170 views2 pages

O o o o o o o o o o o o o o o O: Project Manager Checklist

This document is a project manager checklist that contains questions to consider before beginning construction work. It is divided into two sections. The first section requires action if the answer to questions about dust, chemicals, penetrations, demolition, and other construction activities is "yes" in order to ensure safety, prevent hazards, and comply with regulations. The second section requires action if the answers are "no" and addresses developing plans for spills, securing work areas, maintaining housekeeping and egress. The checklist aims to identify potential issues around asbestos, lead, hazardous materials, fire systems, traffic and more for construction project planning and compliance.

Uploaded by

sooner123456
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
170 views2 pages

O o o o o o o o o o o o o o o O: Project Manager Checklist

This document is a project manager checklist that contains questions to consider before beginning construction work. It is divided into two sections. The first section requires action if the answer to questions about dust, chemicals, penetrations, demolition, and other construction activities is "yes" in order to ensure safety, prevent hazards, and comply with regulations. The second section requires action if the answers are "no" and addresses developing plans for spills, securing work areas, maintaining housekeeping and egress. The checklist aims to identify potential issues around asbestos, lead, hazardous materials, fire systems, traffic and more for construction project planning and compliance.

Uploaded by

sooner123456
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT MANAGER CHECKLIST

Project Manager Name and Location of Project:


o
Is the work being done in a clinical
area? (Anywhere patients are seen)
Complete an Infection Control Construction Permit
Coordinate Interim Life Safety Measures with Campus Police
o
Will dust be generated during the
construction?
Dust is capable of activating smoke detectors. If smoke detectors are
covered during construction to avoid this, the covers must be removed
at the end of each work day. Covering these devices qualifies as an
impairment to the system. Notify Risk Manag
o
Will the contractor be using chemicals
such as, but not limited to,
paints/thinners, concrete curing
compounds, solvents, or cleaners?
The contractor must have Material Data Safety Sheets at the job site
for review of workers and University personnel.
o
Will there be any wall or floor
penetrations caused by drilling, cutting,
or coring operations?
Asbestos containing building materials may be affected by such
operations. Contact Safety and Health for an evaluation.
o
Will existing plumbing be demolished? Asbestos containing building materials may be affected by such
operations. Contact Safety and Health for an evaluation.
o
Will existing floor coverings be
removed?
Asbestos containing building materials may be affected by such
operations. Contact Safety and Health for an evaluation.
o
Will existing fire doors be removed or
replaced?
Some fire doors may be insulated with asbestos. Contact Safety and
Health for evaluation.
o
Does the project include replacing or
demolishing fluorescent lighting?
Fluorescent lamps and ballasts that contain PCBs must be handled
according to applicable environmental regulations.
o
Will there be any excavation involved? The contractor must be vigilant of potential environmental concerns
during excavation. Such concerns may include petroleum odors,
petroleum sheens on groundwater, free product on groundwater,
unusually colored soils, evidence of dumping (debris).
o
Will the excavation disturb an area of
ground greater than 1 acre?
A Storm Water Pollution Prevention Plan (SWP3) mandated by the
Ohio EPA must be developed and followed.
o
Will the contractor be using machinery
that requires periodic refueling.
The contractor must furnish Safety and Health with a Spill Prevention
and Spill Response Plan.
o
Will existing structural steel be stripped,
altered, cut, welded, or removed?
Existing steel may be coated with lead-based coatings that may create
a lead-inhalation hazard if torch-cut, ground, or welded to. Steel may
be covered with asbestos-containing spray-on fireproofing. Contact
Safety and Health for an evaluation.
o
Does the renovation require the
removal of fume hoods or related air
ducts?
Contact Safety and Health for evaluation of asbestos or chemical
hazards.
o
Are there any chemicals in the space to
be renovated?
Contact Safety and Health for disposal options.
o
Will the work being performed cause
impairment to the fire detection and/or
the fire suppression systems?
Risk Management must be notified in advance of the impairment of any
device (smoke detectors, heat detectors, pull stations, or alarm panels).
Long term impairment may require instituting a fire watch.
o
Will there be any hot work such as
welding, brazing, torch cutting, metabo
cutting or grinding?
The contractor must have a written hot work program for fire prevention
and fire watch if necessary. No hot work is permitted within one hour of
the end of a shift unless a fire watch is maintained.
Instructions: Review each of these questions prior beginning of work. The checklist is divided into two
sections. The first section requires action if the answer to each question is "Yes". The second section requires
action if the answer to the question is "No". Some questions may not be applicable to your project.
SECTION 1
Dust is capable of activating smoke detectors. If smoke detectors are
covered during construction to avoid this, the covers must be removed
at the end of each work day. Covering these devices qualifies as an
impairment to the system. Campus Police for Interim Life Safety
Measures
248763732.xlsx.ms_office
Printed: 10/24/2014
PROJECT MANAGER CHECKLIST
o
Will construction work be performed
adjacent to occupied offices or
classrooms?
The migration of construction dust or odors must be prevented from
impacting the occupied areas. This may include sealing all cracks, wall
penetrations, or other openings joining the construction and occupied
areas.
o
Is it possible to separate the
construction area from the other areas
of the building using existing doors and
walls?
Critical barriers must be erected if existing doors and walls are not
adequate to prevent the migration of fumes, dust, odors, or people to or
from the construction zone.
o
Will there be noise or vibration? Consideration should be given for the use off mufflers or other
attenuating devices or work should be scheduled for hours when the
least number of people will be affected.
o
Will oil based paint be used in finishing
operations?
Such painting must be performed outdoors or off-site.
o
Will there be open holes and trenches? The contractor is responsible for providing secure coverings to prevent
trip/fall hazards.
o
Will there be a possibility of falling
materials/debris from work area or
scaffolds?
The contractor must prevent falling objects by using catch platforms or
restrict access to the fall zone by erecting appropriate barriers.
o
Is there a need to control vehicular and
pedestrian traffic if the project is
outdoors?
The contractor must develop a plan if vehicular or pedestrian traffic is
affected.
o
Does the project inculde the installation
of a large air pollution source such as a
boiler?
A Permit To Install (PTI) may required on HSC. Then converted to a
Permit to Operate (PTO).
A Permit to Install and Operate may be required on MC.
Notify Safety and Health 6 months before construction begins.
o
Does the project include the installation
of a small air pollution source such as a
small boiler, gasoline tank or dispenser,
or paint booth?
Notify Safety and Health 6 months before construction begins in order
to determine permit requirements.
o
Does the project include the removal or
demolition of a large air pollution source
such as a boiler?
Notify Safety and Health so that the unit may be removed from our air
pollution inventory.
o
Does the project include the installation,
removal, or replacement of an
emergency generator?
Notify Safety and Health so that our air pollution inventory may be
updated.
o
Does the Project require draining of
HVAC fluids when modifying or
repairing an HVAC system?
The University is required to notify the City of Toledo before discharging
such fluids. Plan on the approval process to consume at least 2 weeks
o
Does the contractor have a plan in
place if a spill of hazardous materials
occurs?
The contractor must have a written plan for containing and cleaning the
spills of any hazardous, or nuisance chemicals that are used in their
work.
o
Does the contractor have a program to
identify hazards to the public?
The contractor must ensure the public's safety by defining and
securing the construction zone.
o
Is the work area locked when the
contractor is not there?
The contractor is responsible for securing the work area against
accidental or purposeful intrusion of the construction zone.
o
Does the contractor have a plan to
assure good housekeeping?
The contractor is responsible for maintaining public walkways and
roads adjacent to the construction zone.
o
Will safe egress through or adjacent to
the construction area be maintained?
Alternate routes shall be posted if egress is not maintained.
Section 2
248763732.xlsx.ms_office
Printed: 10/24/2014

You might also like