Sport Obermeyer Case Study
Sport Obermeyer Case Study
Sport Obermeyer,
Ltd.
Executive Summary
Sport Obermeyer, Inc. is a ski apparel company facing a dilemma in ordering production
of its products. The Company has high costs for both over-ordering and under-ordering in a
single season. The question currently facing management at Sport Obermeyer is to determine
the order quantity for its first phase of production. At this point in time, management has very
limited insight to the demand for particular styles for the upcoming ski season.
Page 2 of 15
Page 3 of 15
and is often a good indicator of the future American fashions. The Las Vegas show in March
also provides input into the design and design concepts are finalized by May.
Once the design concepts are finalized, Obersport begins production of sample garments.
These small quantities of sample garments are made with the actual materials used for final
production. Sales representatives then start to show the products to the retailers. Concurrent
with the sample production process, Obersport begins to determine material requirements to
place orders, as many of the materials take months to obtain. Initial production begins in
February of the current year. During the trade show in Las Vegas (March), most retailers place
their orders. Using the information from these orders, Obermeyer can then forecast the total
demand with the best possible accuracy. After completion of this forecast, Obermeyer places its
second and final production order.
In June and July, Obermeyers garments are shipped from Hong Kong to Seattle, and
then trucked to the Denver distribution center. In late August, Obermeyer ships orders to
retailers for sales to begin in September. Retailers may ask for replenishment of products if they
are able to sell all they have in stock. If Obermeyer has products available they will send the
retailer the replenishments.
Supply Chain Strategies
The supply chain in Sport Obermeyers world starts with its relationship with Obersport.
Sport Obermeyer contracts with Obersport who in turn purchases shell fabric and lining fabric
from its vendors. Shell fabric is typically purchased from many sources such as the United
States, Japan, Korea, Germany, Taiwan, Austria and Switzerland. The lining fabric is primarily
sourced from Korea or Taiwan. Obersport has the fabrics dyed as necessary and also works with
printing companies to develop screens which would be used as patterns on the outerwear. Other
components such as snaps, buttons and zippers, to name a few, are purchased from vendors and
Page
4
of
15
installed by Obersport. Many of these components are procured in Hong Kong, however, snaps
typically are procured from Germany and the zippers are purchased from a large Japanese zipper
manufacturer.
The product planning process is very critical to the overall success of this company; This
is due to the lead times of the materials and components, sensitivity of the timing of
Obermeyers sample production, raw material sourcing, and final production. Due to the lead
times of the materials and the sensitivity of the timing of Obermeyers sample production, then
raw material sourcing and final production, the product planning process is very critical to the
overall success of this company. They are dealing with suppliers from various countries, with
varying lead times depending on the material. Early decisions for colors and styles are a key to
starting the process and reducing the risk of late production. One tactic Obersport uses to limit
their risk is to carry excess stock of the miscellaneous components required.
Obermeyer to maximize the production of the cutting and sewing phase as their capacity was
only 30,000 parkas a month. With a maximum production order of 200,000 parkas, it would not
be feasible to produce all the parkas necessary if they were to wait on all of the pertinent
feedback from the retailers before
One disadvantage is that Obermeyer relies heavily on the retailers input for the
production of their products and get no input from the consumers. If the customers do not agree
with the retailers style choices, there will be a large variance in the quantity of garments sold.
Another disadvantage to the two-phase production strategy is the longer Obermeyer waits to ship
their products there is more of a likelihood that they could be shipped back to China because a
quota restriction is imposed on each product category. Shipping their initial production order in
June or July, Obermeyer would likely not have an issue with the quota restrictions. There second
and final production order shipping in August may run a larger risk. A final disadvantage is held
in the cutting and sewing phase. Due to the minimum order quantities per style, 1200 in China,
and 600 in Hong Kong, and the final forecasted demand quantities, it is not likely that the
remaining production necessary in the final run will match these quantities exactly. There will
likely be instances where remaining production to meet the forecasted demand will be lower than
the minimum order quantity. This will cause management to have to make a decision based on
the profitability of the style in question.
At first glance, based on the information provided in this case, the styles which are the
best candidates for initial production include the following: Entice, Assault, Seduced and Anita.
The common thread for these styles is they all have a relatively high average forecast with a
particularly low expected loss if unsold. The four styles chosen account for approximately 56%
of the expected forecast for the ten styles. It would be our recommendation to not order styles
which have both a high standard deviation and a high expected loss if unsold. We would also
Page
6
of
15
recommend that when ordering the initial phase, it would not be wise to order more than the
average expected sales less one standard deviation until we can be sure that the retailers look
upon our styles in initial production favorably.
There are also disadvantages to consider with these four styles. One disadvantage is that
these four styles are the least profitable styles per unit. This decision is perhaps made to lessen
the risk taken by manufacturing other styles and not being able to sell the entire stock. Another
disadvantage includes a large standard deviation for a couple of the chosen styles, specifically
Seduced and Anita. Though these are two of the higher forecasted sellers, there is a stronger
possibility that the average forecasted demand for these items will not be met. The greatest risk
taken would be by producing Anita in the initial phase as it has the highest standard deviation
across all styles within our line.
The next important aspect Wally needs to consider is the cost of overproduction for each
style. At this point, there is no under-order cost because this is only the initial production phase.
Other orders will be placed later, when more information is available to better predict demand.
So for now we focus our attention on the over-order costs.
For Sport Obermeyers parkas, the over-order cost is equal to the purchase price minus
the salvage value for each parka. The estimated average loss on a parka left unsold at the end of
the season is approximately 8% of the wholesale price. The styles with the highest over-order
cost are Electra and Daphne and the lowest are Seduced and Entice.
Considering both of these important factors, Wally can determine the optimal order
quantity. For purposes of this sample, we assume all first phase production will be ordered from
the Hong Kong factory. For the first phase of production at the Hong Kong factory, the
minimum order is 10,000 units and the minimum production quantity for a particular style is 600
units. Because this is the first order of the season and Obermeyer is trying to minimize overorder cost, Wally should try to order as close to the minimum total order as possible (10,000
units). When ignoring the 600 unit minimum per style, a variety of styles are ordered with only
the style, Stephanie, with zero units ordered. Even though at this point, it does not exclude the
style, Isis and Teri are below the 600-unit threshold. See Exhibit 1 for complete calculations.
When we include the limitation that the minimum order quantity for each style is 600
units, the order changes. Now we are ordering seven styles, with no order for styles: Isis, Teri,
and Stephanie. Seduced is still ordered the most, but an even higher quantity is ordered. See
Exhibit 1 for complete calculations.
Table 1: Order Quantities
Without
Min.
Production
Quantity
Page
8
of
15
Min.
Production
Quantity
=
600/style
Gail
Isis
Entice
Assault
Teri
Electra
Stephanie
Seduced
Anita
Daphne
594
382
922
1,873
218
1,055
0
3,112
1,241
617
626
0
968
1,933
0
1,114
0
3,219
1,424
722
TOTAL
10,014
10,006
It can be inferred that one of the most important factors in consideration of which style to
order right now is which styles had the highest average estimated demand. It is safer to order
these styles, as long as they are ordered at the lower end of the estimate (approximately one
standard deviation below the mean). And a higher quantity can be ordered of each of these
styles, adding up to the minimum production of 10,000 units.
Obermeyer will have a better idea of what the actual demand will be and can manufacture goods
accordingly. Therefore, in order for Sport Obermeyer to improve their supply chain network,
they must find ways to reduce their lead time, reduce the amount of uncertainty in their product
demand, or both.
Sport Obermeyer operates in a market with a high degree of demand uncertainty, which
consequently requires manufacturers to use a pull production process in order to be successful.
They also work within a framework of low supply uncertainty which allows for the use of JustIn-Time production. The result is a responsive supply chain that allows for increased production
of popular items. However, this system is greatly hindered by supplier lead times of up to 90
days, which makes being responsive to market demands very difficult. The system is also
hindered by the uncertain product line demand, which can only be predicted with any degree of
accuracy after 20% of the actual demand has been tallied. While Sport Obermeyers recalculated
sales projections become more accurate as more actual sales data becomes available, this
uncertainty, combined with long lead times, makes producing optimum amounts of each product
line very difficult.
The success of the Sport Obermeyer/Obersport/Alpine Factories supply chain relies on
the companies abilities to simultaneously deliver matching outfits and accessories to retailers
early in the selling season. The sales season lasts approximately 5 months, from September
through January with a peak in December and January. Skiwear fashion is considered to be a
one-year cycle. So Sport Obermeyer must reassess and redesign its product line each year,
resulting in a need for nearly a complete turnover in inventory each year. The current supply
chain system is functional because there is a great deal of interdependence and trust. This is
particularly true between Obermeyer and Raymond Tse who began Obersport, Ltd. as a joint
endeavor. Since Alpine Factories Inc. is ultimately responsible for the production of Sport
Page
10
of
15
Obermeyers product line and Sport Obermeyers production orders account for approximately
80% of all of Alpine Factories production, each company is heavily reliant on the other. As a
result, a natural profit and risk sharing system is already in place. In addition, their current
practices of pre-positioning with greige fabric to minimize 90-day lead times, keeping standing
inventories of snaps with long lead times and their use of the Hong Kong workers who are faster
and cross-trained are good steps towards maintaining an efficient supply chain. However, there is
a great deal of room for improvement to the overall supply chain system.
The companies in the Sport Obermeyer supply chain can take a number of measures in
order to improve existing inefficiencies. Zippers, finishing shell fabric and finished lining fabric
all have lead times between 45 and 90 days. Sport Obermeyer should work with the suppliers of
these items to find a way to reduce the lead times in order to increase their ability to be more
responsive to market demands.
From the manufacturing perspective, the production lines in China are long and
cumbersome because, unlike their counterparts in Hong Kong, the workers in China are not
cross-trained. Providing additional training to the line workers, particularly cross-training the
China workers, should reduce throughput times and ultimately reduce the lead time for
manufacturing the goods. Sport Obermeyer must also continue to improve and be innovative
with its production strategies in order to reduce production lead times. They can also provide
incentives to their suppliers for reduced lead times. For example, the manufacturing plants with
higher throughput rates can be given a higher portion of the production allocation in future years.
In this way, the more efficient workers will benefit from the increased work and Sport
Obermeyer benefits from reduced lead times.
From a sales perspective, Sport Obermeyer should develop a website through which they
can market their goods and make direct sales to consumers. Not only will this increase their
Page
11
of
15
sales, but it will provide them with a more accurate and earlier gauge of what the demands for
their product lines will be. Sport Obermeyer can also invite prior customers to participate in
surveys about prototype items to gauge their preferences for future fashion lines. This
information may help reduce uncertainty of demand.
Finally, and perhaps most perplexing, Sport Obermeyer loses one month of lead time
before the full scale production schedule due to the observance of the Chinese New Year at
manufacturing the plants. While it is understandable that the workers will want time off, it is still
worthwhile for Sport Obermeyer to investigate the option of providing workers with an increased
salary rate or a partial manufacturing schedule during January as an incentive to get the
employees to work during January as opposed to losing the entire month of lead time.
Page 12 of 15
them. If orders are late coming in to the country, compared to competitors, they may have entire
production loads turned away.
Hong Kong has only one major disadvantage and it is both a long and short term
problem. For many advantageous reasons, the labor is much more expensive in Hong Kong than
in China. These reasons are discussed below as advantages, but it cannot be ignored that the
labor rate, per hour, is twenty-four times greater than that of China.
Labor is more expensive in Hong Kong because of the several labor advantages. The
Hong Kong labor force is more skilled and works faster (50%) than its Chinese counterpart.
These are both long term advantages to using Hong Kong. They can produce nearly twice the
number of parkas per worker. The last two short term advantages that compliment one another
are the minimum order quantity is half that of Chinas and the labor force is capable of
performing more than one job function.
Overall, for making sure production levels are high, it appears that Wally should place his
initial order in China. Even though the labor force is slower and not as skilled, they can still
produce more garments overall for a lower price. The major drawback would be the U.S.
restrictions, but if items are turned back and/or have to be flown into the U.S. it would still be
cheaper per the estimated cost information provided. Wally should concentrate his efforts in
China. As time passes, if the capacity increases, the overflow can go to Hong Kong. This is
advantageous because the minimum order is lower in Hong Kong.
The recommendation would be to have as many items as possible produced in China,
particularly the largest volume items because the costs would be lowest, even if there were errors
in production that needed to be corrected. Production in China should start with Assault, Electra,
Seduced, Anita, and Daphne. If for any reason China cannot handle the full load, as may be
apparent in the disadvantages, Hong Kong could take the smaller additional production
Page
13
of
15
requirements as needed. Wally would need Hong Kong to produce the smaller forecasted items
because a number of them drop below the minimal order number for China if the average
forecast falls to the low end.
Page 14 of 15