Item Description: Architect S Instructions and Superintending Officer S Instructions
Item Description: Architect S Instructions and Superintending Officer S Instructions
Item
Description
Page
1.
2.
VARIATION ORDER
13
3.
22
4.
CONTRACTORS OBLIGATION
27
5.
CONTRACT DOCUMENT
33
6.
SITE AGENTS
46
7.
REFERENCES
49
Architect or S.O can only make an order for variation of works about affair that he
has the real power to do so. And here is some of the affair that can be issued by the
Architect or S.O: Differences of the documents, mistakes in bills of quantities
Move and replace materials and stuff that is not obey the contract
Change of works, quality, quantity and works conditions
Expenditure of the provisional and prime cost sum
Remove of works because of wars
Extension of works
Produce list of defect woks to be repaired by the contractor
Recovering works which is broke because of fire and so on.
Failure of the Contractor to obey and perform the Architect instruction or approve
S.O is count as breach of contract and give the right to employer to hired other person
to hand over and carry the works from the previous contractor by the deduction of the
contract sum that need to be paid to the contractor.
Effect of the Architect Instruction that is not approved, Contractor cannot be force
to obey and if he been force by the employer, the contract is break then. Still, if the
contractor wants to obey the instruction, there is no obligation for the client or employer
to pay the amount of the works that has been done.
Not all the Architect or S.O instruction cause changing the quantity and quality of
the original works, some of it was and instruction to the Contractor to repair and fixed
the workmanship to punctually follow the contract condition. However, architect and S.O
need to be care full while giving an opinion and advices to the contractor as for not to be
misunderstanding if all the A.I`s permitted the contractor to ask for the additional prices.
WHAT
IS
THE
PURPOSE
OF
SUPERITENDING
OFFICERS
(S.O)
AND
ARCHITECTS INSTRUCTION
Even though bills of quantities and drawing provided with details, there is need of
changing the quality and quantity of works which has been agreed in Document.
Variation order may be cause of this factor:
Design and Drawing is not fully complete when attending the contract
Other contingencies
For the standard form with Quantities, contract sum gains from the works
described in the bills of quantities. So, which ever works clearly described but differ from
the BQ, and have been perform by the Contractor, it is count as Variation Order and the
value of the works carry will be added to original contract sum. For the contract refers
with the drawing and specification, all the works is count as the contract sum when it is
stated in the drawing and specifications except otherwise stated.
PROCESS
FLOW
OF
ARCHITECHS
AND
SUPERINTENDING
OFFICERS
INSTRUCTION
START
WRTTING INSTRUCTION BY
S.Os
YES
INSTRUCTION IN S.Os
AUTHORITIES
YES
YES
NO
VALIDATE BY CONTRACTOR IN 7
DAYS
CONTRACTOR NEED
TO FOLLOW S.OS
INSTRUCTION
YES
NO
APPROVED BY S.OS
YES
NO
OBEY BY CONTRACTOR IN 7
DAYS
YES
FINISH
5.2 All instruction issued by the S.O. shall be in writing, The Contractor shall forthwith
with all instruction issued to him by the S.O. If such instruction given orally, the S.O
shall then issue a written instruction within seven (7) days from the date of such
instruction is given.
5.3 If within seven (7) days after receipt of a written notice from the S.O requiring
compliance of an instruction and the Contractor does not comply therewith, then the
S.O without prejudice to any other rights or remedies available to the Government
under this Contract, undertake the work whatsoever which may be necessary to
give effect to such instruction. All cost and expenses incurred in connection with
such employment (including On-Cost Charges), shall be deducted from any money
due or to become due to the Contractor under this Contract, and failing which such
deductions shall be recovered from the Performance Bond or as a debt due from
the Contractor.
5.4 The Contractor shall be responsible for all cost and expenses incurred by the
Government in carrying out the Works under clause 5.3 and On-Cost Charges
(calculated by applying the Percentage of On-Cost Charges stated in Appendix
hereto to the amount incurred). The Government shall be entitled due or to
overcome due to the Contractor under this Contract or to recover the same form the
Performance Bond or as a debt due from the Contractor.
10
2.4 If the time of compliance (which shall not less than seven (7) Days from receipt of
the AI) is stated by the Architect in the AI and the Contractor does not comply
therewith then the Employer may, without prejudice to any other rights and
remedies which he may possess under the Contract, employ and pay to other
person to execute the Works with may be necessary to give the effect to such
instruction. The cost of employing other Person and any additional cost in this
connection shall be set-off by the Employer under Clause 30.4.
11
PWD 203A(2007)
PAM (2006)
Clause 2.1
Contractor to
Superintending Officer (S.O) & S.O.
comply with
Architect
Representative
instruction
the works
Clause 2.4
Failure of Contractor
comply with
Instruction
12
13
That the works he has done is not paid in the contract sum
If the extra works is out of the work scope, and does not have related with original
contract, it might not count as a change and need other format of payment.
14
Extension of time for completion will affect the insurances, consultant fees,
rental, foremen, loss causes by the rental and so on.
15
16
Superintending Officers (S.O) and Architect also do not have a power to issue
the instruction about the safety of site. This is would be the responsible of contractor to
bear a safety on site. Had been a while, the architect have a responsible of giving an
attention to the contractor in certain situation that architect has the contractual
responsible to do thus thing or power to major the type of remedial measurement that
should take.
17
The S.O. may issue instructions requiring a Variation in a form a Variation Order.
No Variation required by the S.O shall vitiate this Contract. Upon the issuance of
such Variation Order, the Contractors shall forthwith comply with the Variation
Order issue by the S.O
24.2
24.3
Any variation made under this clause shall not relieve the Contractor form his
obligations under clause 22.1(c).
18
19
25.2
Where work cannot properly be measured or valued, the S.O may allow daywork
price as specified in Appendix. Unless otherwise provided in the Bills of
Quantities, the day work for the price for the purpose of this contract for the
labour concerned. The Contractor shall be paid the daywork prices, plus fifteen
percent (15%), which shall include for the cost of all ordinary plant, tools,
scaffolding, supervision and profit. PROVIDE ALWAYS that as a condition
precedent to any right to any payment the Contractor shall produce vouchers,
receipts and wage books specifying the for
materials used to the S.O not exceeding seven (7) days after the work shall have
been done.
25.3
The amount of variations shall be certified by the S.O and added to or deducted
from the Contract Sum as the case may be and the amount shall be adjusted
accordingly.
20
21
22
23
In respects of any and every Prime Cost or P.C Sum provided in the contract, the
amount due to any Contractor shall be determined by deducting the said Prime
Cost or P.C Sum and the relevant profit and/or attendance charges from the
Contract Sum and substituting for the same with the actual amount due to
relevant Nominated Sub-contractor or Nominated Supplier as valued in
accordance with the relevant sub-contract and the sum due to any contractor by
way of profit and/or attendance charges at the rates or prices stipulated in the
Contract Documents (if any)
34.2
The Provisional Sum may be expended at such times and in such amounts as
the S.O may direct. Such sum if not used either wholly or in part shall be
deducted from the Contract Sum. The value of works which are executed by the
Contractor in respect of Provisional Sum shall be ascertained in accordance with
clause 25 hereof. The said value of such work executed by the Contractor shall
be set off against all such Provisional Sums and the balance shall be added to or
deducted from the Contract Sum as the case may be.
34.3
24
34.4
Where the contractor in the ordinary course of his business directly carries out
works for which P.C Sums are provided in the Bills of Quantities and where such
works are set out in Appendix hereto and the S.O is prepared to accept tenders
from the contractor for such works the Contractor shall be permitted to tender for
the same or any of them without prejudice to Governments right to reject the
lowest or any tender. If the tender of the contractor for any work included in the
P.C Sums is accepted, such tender shall be held to include the profit and
attendance charges, and the contractor shall not be entitled to the profit and
attendance charges as contained in the Bills of Quantities notwithstanding any
provision to the contrary under clause 34.1.
25
The Architect shall issue AI in regard to the expenditure of P.C Sums and
Provisional Sums included in the Contract Bill and P.C Sums which arise as a
result of instructions issued in regard to the expenditure of Provisional Sums.
26
27
CONTRACTORS OBLIGATION
After the site possession is given, the main constraint, responsibility or obligation of the
Contractor is to start construction works and complete the works by or before the
completion date as stated in the Appendix to Conditions of Contract. The execution of
works shown by the Contractor must be continuous and following the stages and with
commitment or effort. These requirements are to ensure the contractor executes the
works according to the agreed schedule and the project completed in the promised
period. This importance is supported by other allowance whereas the service of the
contractor can be terminated on behalf of the failure of execution of the works by the
contractor with effort and continuous. (As referred to Clause 51 Form of Contract 203A)
Executing works according to stages and continuous is very crucial to ensure the
schedule of construction is followed and the project is completed in the reasonable
period. To achieve this target, the contractor must work systematically, continuous from
day to day with enough workers and labours, enough supply of materials without
interruption and suitable machinery planning with the associated works. Besides that,
the appointed contractor brings large impact to the progress of construction works. Even
though every source is enough and the material supply uninterrupted, without the effort
and willingness, the project cannot be completed within the period required. There for,
both responsibilities has to be incorporated by the Contractor in executing the
construction works to fulfill the objectives or purpose of the project.
28
(g) Provide and maintain throughout the contract period such number, categories of
qualified and competent personnel necessary to perform the works;
(h) Provide and maintain at its own cost and expense all equipment and materials
necessary for the proper and effective performance of the works;
(i) Instruct and supervise its stuff and sub-contractor in carrying out the works
repairs and other works in relation to the works;
(j) Make good any defect, imperfection, shrinkage or any other fault whatsoever
which may appear during the defects liability period; and
(k) Carry out any other obligations and responsibilities under this Contract.
30
1.2
1.3
Consultant of the Contractors design and alternative design shall not relive the
Contractor of the responsibilities under the contract.
1.4
32
33
CONTRACT DOCUMENT
The Contract Document is a document produced in result from the acceptance of the
client to the offer made by the Contractor. It is prepared by the consultants that have
prepared the Tender Document. Generally, the Contract Document includes items that
are similar to the Tender Document, but has been added with other documents. All
these documents need to be sorted neatly and chaptered before it is signed by both
parties. This document then will be the reference and guidance in the execution of a
project. Issues related to the Contract Document for the Contract Form PWD 203A is
mentioned in clause 4, 7 and 8.
Clause 4 explains about contract scope whereas items inside the Contract Document,
such as plans, specifications, items of agreement and conditions of contract is made
reference for the Contractor to execute the responsibilities to construct and complete
the project. Besides that, the clause also mentions that the contract scopes and
obligations of the contractor also includes making good defects and inside the defect
liability period.
Clause 7, contract form PWD 203A, states guidelines about the Contract Document.
Amongst them are:
a) The Contract Document shall always be under care of the Client. However the
Contractor is given the right to refer when required.
b) The Contractors qualification to obtain certain documents free of charge as soon
after the Contract is signed.
34
c) The S.Os responsibility to present the related plans or details to the Contractor
from time to time to explain or interpret the plans or specification for the purpose
of construction.
d) The responsibility of the Contractor to keep a copy of important documents such
as plans, specifications and Bill of Quantities at the site for the S.Os reference.
e) The responsibility of the Contractor to return (if asked) all documents given
before after the final payment is made.
f) Restrictions to the Contractor to use any Contract Documents for other purpose
except for items related to the Contract.
Clause 8 discusses two important aspects in the Contract Document. Clause 8(a)
explains that every content or part inside the Contract Document shall be taken into
account as reference to one another. For example, a simple explanation inside the Bill
of Quantities are explained in detail in the specifications and shown in diagrams. Next,
this clause stresses that every responsibility of the Contractor is to execute as the
purpose and true meanings of the Contract Document. Clause 8(b) explains the action
that needs to be done by the Contractor if there is any conflict between the Contract
Document, whereas the Contractor is responsible to inform the conflicts to the S.O.
From there, the S.O shall produce an Order as solution to the conflict.
The main contents of the Contract Document are as follows:
a) Tender Form
-
35
willingness of the Contractor to execute the works according to the price and
period of construction as in the Tender Document.
b) Letter of Acceptance
-
c) Articles of Agreement
-
This section includes general guides about the agreed deal by both parties. It
acknowledges about involved parties, the works that will be executed, rights
and responsibilities generally of both contract parties. Every details of each
article as well as rights and responsibility of the Contractor and the client is
referred to other parts that are the Conditions of Contract. At this section is
also a space for the Clients and the Contractors signature as well as the
witnesses for each party for the purpose of completing the Contract. For Form
of Contracts other than the PWD 203A, such as the PAM 98, name, address
and the main obligations of the consultants involved are also mentioned in the
this section.
36
d) Conditions of Contract
-
This section explains more clearly and detail about the agreement by both
parties mentioned generally. Basically, the contents of this section are divided
into 4 main functions. Firstly, it defines the meanings of certain abbreviations
and words used n the Form of Contract. Second, it explains more of the rights
and obligations of the Contractor. Generally, the rights of a certain party will
be a responsibility to other parties. Third, it explains the scope of works and
administration for certain issues and the fourth, it explains the methods or
solutions to small breaching of contract done by contractual parties.
e) Preliminary Works
-
37
of water, electric, telephone and others used completely for the project from
the beginning until the completion of construction.
f) Bill of Quantities
-
The Bill of Quantities is the part where in detail it explains the involved works
for a project with quantities and brief explanation. The Bill of Quantities is a
part of Contract for projects based on lump sum with lists of materials.
Basically it is sorted by elements of buildings. At tender stage, this part and
the preliminary works are priced by the Contractor to obtain the total cost of
the project.
g) Specifications
-
This part is purposed to explain the work requirements inside the drawings
with more details and cannot be explained in the drawings and Bill of
Quantities. For example the quality of material, brand or type of material,
method of works (if needed) and the quality of works required to for a project.
The Specifications are basically prepared according to trades and must
include all items needed for the project.
38
The drawings included inside the Contract Document are the whole drawings
used when preparing the Bill of Quantities for Bill of Quantities based on lump
sum or when all drawings given to the Contractor during tendering process for
lump sum based on drawings and specifications.
i) Appendix
-
The requirements and detailed needs of the Document Contract depend to the type of
contract used and conditions or requirements of the proposed project. Every part inside
the Contract Document has specific functions and purpose to achieve the main purpose
that is project execution. For this purpose, all contents of the Contract Document needs
to be taken into account as one whole Document and explainable to one another. This
39
item is explained in Clause 8(a). If there is a conflict between any contents of the
Contract Document, Clause 8(b) gives the right to the S.O to solve it after it has been
forwarded by the Contractor in written letter.
40
CONTRACT DOCUMENT
8.1
The contract shall be prepared in two (2) original copies. The original
copies of the contract shall remain in the custody of the S.O and the
Contractor
(b)
Immediately after the execution of this contract, the S.O shall furnish to
the Contractor without any charge (unless he shall have been previously
furnished) with:
(i)
(ii)
(c)
The S.O shall, as and when necessary and without charge to the
contractor, furnish him with two (2) copy of such further working drawings
or details as are reasonably necessary either to explain and amplify the
Contract Drawings or the specification(if any) or to enable the Contractor
to construct and complete the works in accordance with this contract.
PROVIDE THAT nothing contained in the said working drawings or details
shall impose any obligation beyond those imposed by the Contract
Documents.
41
(d)
The contractor shall keep one copy of the contract drawings, the
specification (if any), unpriced bills of quantities, priced Bills Of Quantities (if any)
and other like documents referred to in sub-clause (c) hereof the site and the S.O
shall at all reasonable times have access to the same.
(e)
Upon final payment being made pursuant to the issuance to the final
account and payment certificate under clause 31, the Contractor shall return to
the S.O all drawings, details, specifications, unpriced copy of bill of quantities and
priced Bill of Quantities, if any.
(f)
another. The Contractor shall provide everything necessary for the proper
execution of the works until its completion according to the true intent and
meaning of the Contract Documents taken together whether the true intent and
meaning may or may not be particularly shown or described PROVIDED THAT it
can be reasonably inferred there from.
(b)
42
43
CONTRACT DOCUMENTS
3.1
Contract Document
3.1
3.2
3.1(a)
3.1(b)
3.1(c)
3.1(d)
3.1(e)
3.1(f)
44
3.3
Copies of documents
Immediately after the execution of the Contract, the Architect or Quantity
Surveyor shall without charge to the Contractor provide him with:
3.3(a) one of the two signed original copies of the Contract Documents;
3.3(b) two (2) further copies of the Contract Drawings; and
3.3(c) two (2) copies of the unpriced Contract Bills.
45
46
SITE AGENTS
A site agent is personnel liable in managing one or more sites at the same time. The
main tasks of a site agent include:
On site health and safety including: Adherence to all applicable health and safety legislation.
Adherence to site rules.
Inspection of scaffolding.
Implementation of method statements.
Assisting in the carrying out of risk assessments.
Assisting in the setting up of tool/plant maintenance program.
Maintaining the confidentiality of both clients and the company at all times.
Carrying out any other duties, within reason, requested of them by the
management of the company.
47
Unless otherwise provided elsewhere in this contract, the Contractor shall keep
constantly on the site a competent, efficient, suitability qualified, experienced and good
character site agent and his assistants in each trade as may be necessary who must be
capable of receiving instructions in Bahasa Malaysia, and in default it shall be the
responsibility of the contractor to provide replacement for them and all wages and other
expenses in connection with the employment of such replacement site agent and
assistants. Any directions, explanations or instructions given to such site agent by the
S.O shall be deemed to have been given to the Contractor under this Contract.
48
REFERENCES
1. Modern Construction Management By Frank Harris, Ronald McCcaffew
2. Technique Planning & Controlling Construction Project, by H.N. Dhuja S.p. Rozzi
S.M. Abou Rizk
3. Form of Contract PWD 203A(Ref.2007)
4. Form on Contract PAM/ISM 2006
5. Pengenalan Kepada Kontrak Binaan PWD 203A, Mohamad Nazir Bin Ismail.
49