LNG Offshore Receiving Terminals
LNG Offshore Receiving Terminals
from
operating
considerations,
range
of
concerns
surround
The competitive,
market driven process for new LNG import terminals in the U.S. is intensely
competitive. Given the number of onshore import terminals that are planned
or proposed, it is unlikely that all of the potential offshore capacity will be
developed.
The Deepwater Port Act (DPA) authorized the U.S. Maritime Administration
(MARAD) to serve as the licensing authority responsible for permitting new
offshore LNG terminals in U.S. waters, in coordination with the USCG. 3. By
law, MARAD has only one year in which to issue a license to an offshore LNG
applicant and then it can only issue a license with approvals from the
Governors of all adjacent coastal states. Along with MARAD and the USCG,
other regulatory approvals must come from:
U.S. Environmental Protection Agency (EPA) under the Clean Air Act and
the Clean Water Act;
The USCG retained its non-administrative duties under DPA even though USCG was moved to
the U.S. Department of Homeland Security from the U.S. Department of Transportation, where
MARAD is based. USCG duties include staffing the determination of completeness, preparation
of the Environmental Impact Statement (EIS), and other duties. Information for this and the
following paragraphs on regulatory reviews and approvals was taken from Licensing of
Offshore Liquefied Natural Gas Terminal Facilities by Monica Schwebs, for the 12 th Section Fall
Meeting, Section on Environment, Energy, and Resources, American Bar Association, October
6-10, 2004, San Antonio, Texas.
3
National
Oceanic
and
Atmospheric
Administration
(NOAA)
approval
U.S. Fish and Wildlife Service (USFWS) or the National Marine Fisheries
Service (NMFS), depending upon the location of the species, for
consultation concerning the Endangered Species Act;
Under the DPA, and in addition to executive approval, the States have certain
rights and responsibilities.
offshore LNG facility with state coastal zone management plans made under
the Coastal Zone Management Act; issue leases for any use of state
submerged lands for natural gas pipeline purposes; approve any new
intrastate natural gas pipelines that must be developed; and be involved
through their State environmental agencies in the Endangered Species Act
consultation process.
would be almost ten times the volume of LNG imported in 2003. Growing
demand for natural gas as well as challenges in maintaining and replacing
4
See U.S. EIA annual long term outlook, December 2004, www.eia.doe.gov.
An onshore receiving
terminal will soon be under construction in New Brunswick and other onshore
projects are under regulatory review.5
The UH IELE has conducted a major review of natural gas supply demand balances and the
role of LNG. This report can be obtained at www.energy.uh.edu/lng.
5
Technology
Anticipated
startup
date
Estimated
Cost
$millions
Storage
Tanks
Capacity
Vaporizer
Type
# of tanks x
bcm of LNG
Gravity Base
Structure
Water Depth
83ft
2007
800
2x165000
m3
330000
m3
Comments
Sendout
Capacity
Avg/Peak
MMcfd
(Bcf of NG)
1. Port Pelican
Chevron
Baseload
Open Rack
Vaporizing
(ORV)
(7 Bcf)
Phase 1:
800/1000
Phase 2:
1600/2000
fabrication of the
Chevron Port Pelican
Gravity Based Structure
(GBS) is being prepared
by the USCG.
Updates from various industry trade publications including Natural Gas Intelligence (NGI), Status of Proposed and Existing Facilities.
http://intelligencepress.com/features/lng/terminals/lng_terminals.html, November 2004 why only mention this one??
6
Name /Location
Technology
Anticipated
startup
date
Estimated
Cost
$millions
Storage
Tanks
Capacity
Vaporizer
Type
# of tanks x
bcm of LNG
Submerged
Turret
Loading
(STL) Buoy
System
Jan. 2005
700
138,000
m3
(2.9 Bcf)
Comments
Sendout
Capacity
Avg/Peak
MMcfd
(Bcf of NG)
2. Louisiana Energy
Bridge Deepwater
Port
Baseload
Shell and
Tube
Vaporizers
(STV)
Water Depth
500
298ft
Technology
Anticipated
Startup
Date
Estimated
Cost
$millions
Storage
Tanks
Capacity
Vaporizer
Type
Baseload
Sendout
Capacity
Comments
Avg/Peak
# of tanks x
bcm of LNG
MMcfd
(Bcf of NG)
Salt caverns
2007
440
145000m3
Water Depth
(3.1 Bcf)
surface LNG
storage
210ft.
Open Rack
Vaporizing
(ORV)
1000/3000
and
Gulf of Mexico 16
miles southeast
Louisiana.9
4. Cabrillo
Deepwater Port,
BHP Billiton.
6x24660m3
28 Bcf salt
dome
natural gas
storage
facility
FSRU
(Floating
Storage and
2008
550
3x91000m3
273000 m3
Submerged
combustion
vaporizers
800/1500
Updates from various industry trade publications including Natural Gas Intelligence (NGI), Status of Proposed and Existing Facilities.
http://intelligencepress.com/features/lng/terminals/lng_terminals.html, November 2004.
7
California Energy Commission Staff report, West Coast LNG Projects, September 24, 2004.
Name /Location
Technology
Anticipated
Startup
Date
Estimated
Cost
Storage
Tanks
Capacity
$millions
Vaporizer
Type
MMcfd
(Bcf of NG)
Regasification
Unit)
(6 Bcf)
Comments
Avg/Peak
# of tanks x
bcm of LNG
21 miles offshore
Port Hueneme,
California10.
Baseload
Sendout
Capacity
(SCV)
Water Depth
DOT Docket # 16877
2900ft.
5. Pearl Crossing
ExxonMobil
Gulf of Mexico, 41
miles off of
Cameron
Gravity Base
Structure
2008
2x125000
m3
(5.3Bcf)
Open Rack
Vaporizing
(ORV)
2000/2800
Water Depth:
62ft
Parish, La.,
6. Gulf Landing
Shell Gas & Power
Gravity Base
Structure
38 miles offshore
Louisiana. West
Cameron Block 213.
Water Depth:
7. Crystal
Clearwater Port,
Crystal Energy
Platform
based
(Converting
10
2008
370
2x90000m3
180000m3
Open Rack
Vaporizing
(ORV)
1000/1200
(3.8Bcf)
54ft
2007
300
http://lngsolutions.bhpbilliton.com
800/1200
Name /Location
Technology
Anticipated
Startup
Date
Estimated
Cost
$millions
Storage
Tanks
Capacity
Vaporizer
Type
# of tanks x
bcm of LNG
(Bcf of NG)
LLC.
13 miles west of
Oxnard, California11.
Baseload
Sendout
Capacity
Avg/Peak
MMcfd
an existing
offshore,
Platform
Grace.)
Water Depth
318ft.
Proposed
8. Northeast
Gateway
Energy Bridge
Deepwater Port,
Excelerate Energy
Offshore Gloucester
MA.
Submerged
Turret
Loading
(STL) Buoy
System
2007
200
2010
700
Water Depth
300ft
9. Broadwater
Energy
TransCanada
Corporation/ Shell
US Gas & Power LLC
11
Comments
FSRU
(Floating
Storage and
Regasification
http://www.crystalenergyllc.com
400/800
Name /Location
Technology
Anticipated
Startup
Date
Estimated
Cost
$millions
Storage
Tanks
Capacity
Vaporizer
Type
# of tanks x
bcm of LNG
(Bcf of NG)
Baseload
Sendout
Capacity
Comments
Avg/Peak
MMcfd
Unit)
Water Depth
75 - 100ft
10. Port Penguin
LNG Chevron
Salt Cavern
HNG Storage
Bishops
Process
12. Offshore
California
750
Chevron
Technology
Anticipated
startup
date
Estimated
Cost
$millions
$millions
Gravity Base
Structure
2007
650
Storage
Tanks
Capacity
Vaporizer
Type
# of tanks x
bcm of LNG
Sendout
Capacity
MMcfd
Avg/Peak
(Bcf of NG)
MMcfd
250000m3
750/1400
(5.3 Bcf)
Water Depth
65ft.
Comments
Planned
Conversion Gas Imports
Bay of Campeche, Mexico
12
Bishops
Process.
Salt caverns
Studying feasibility
http://www.Chevron.com/gnlbaja/about/
# of Terminals
Mode of Operation
Continuous
Intermittent
Water Depth
Deepwater (>200ft)
0 20 miles
20 50 miles
Location
Gulf of Mexico
West Coast
Vaporization Method
would generally be used for intermittent operations. Five of the seven approved
or pending offshore terminals are continuous baseload operations as depicted in
Table 4. All the types of LNG terminals would include systems for docking and
unloading of LNG vessels and systems for vaporization of the LNG for delivery to
from offshore LNG import terminals, cryogenic storage tanks would be fitted on
floating vessels, as part of shipboard re-gasification units (FSRU), in gravity based
structures (GBS), or on platforms supported by pilings.
Intermittent Operations
At offshore LNG receiving facilities using intermittent operations, the LNG would not
be stored at the receiving terminals but immediately converted to natural gas for
delivery through a subsea pipeline (with likely storage in conventional underground
natural gas storage facilities).
stationary or floating. Stationary mooring and delivery methods would be much like
those required for continuously operating facilities, but without storage.
Floating
draft of 38 feet and require an additional two feet of depth to provide sufficient
clearance from the sea bottom for safe maneuvering.
minimum water depth for siting LNG offshore terminals will be determined by the
minimum depth of water required for the safe maneuvering of the LNG vessels,
which is about 40 feet. At present, there is no maximum depth of water that would
limit the location of an offshore LNG terminal, but ultimate water depths for safe,
economic operation are also determined by geometry of the sea floor, wave action,
distance from shore, and other factors.
GBS and platform-based offshore facilities would sit on the seabed and thus be
depth restricted. These facilities would be located closer to land and hence be more
visible from the beach. Deepwater locations would be farther offshore and would
require longer subsea pipelines at higher incremental cost, but would be
significantly less visible.13
Some of the advantages of offshore LNG terminals include the possibility of locating
the terminal in deeper water thereby eliminating the need for dredging inland
waterways and increased availability, safety and reduced voyage time as LNG
carriers need not enter and maneuver in congested waters.
In the U.S., the Deepwater Port Act (DWPA) of 1974 14, as amended, specifies the
regulations concerning offshore oil and gas terminals. The DWPA established a
licensing process for ownership, construction and operation of manmade structures
beyond the U.S. territorial waters. The limit of the US EEZ (Exclusive Economic
Zone) sets the maximum limit for siting LNG offshore terminals. In concept, this
Said, Mike and Joram Meijerink, Shell Global Solutions International B.V., LNG Import Terminals:
Offshore vs Onshore - A Site & Concept Screening Methodology, 14th International Conference on
Liquefied Natural Gas (LNG-14), Doha, Qatar. March, 2004.
13
14
Shell and tube vaporizer (STV) using either once-through heating seawater
(open-loop) or a steam heated (closed-loop) system.
panels,
Reference
as
source
shown
in
not
found.
Error:
The
would
flow through
intake
velocities
impingement
and
that
minimize
entrainment
of
structures and killed or injured. Entrainment can occur when eggs, larvae, young
juveniles, and smaller aquatic organisms are drawn into cooling systems and killed
or injured by thermal, chemical, or physical stresses. The cooled seawater would
be collected and discharged to the ocean after one pass through the system.
Depending on the send-out capacity the discharge line can be up to 5 7 feet in
diameter, Error: Reference source not found. The seawater is chlorinated to protect
the surface of the tube panel against biofouling and to prevent marine growth
bath is fresh water generated by collection of condensed water formed from the
natural gas fuel burned in the SCV. Moisture in the exhaust gas will condense on
cold LNG piping. Potable water for the terminal can be supplied from the
condensation of moisture out of the air at the SCV units. The water bath provides
stable heat transfer to the LNG and natural gas. The water bath is cooled as the
natural gas absorbs heat from it.
submerged combustion vaporization process. There are NO x and CO2 emissions due
the burning of natural gas to fire the burners.
the seafloor is relatively level or gently sloping, lacking in geologic hazards, and
with satisfactory sediments to support the foundation and weight of the
structure. If there is a significant thickness of soft clays, the most effective means
Source:
[Get a picture of showing GBS layout]
The GBS concept is particularly well suited to phased expansion, additional GBS
units may be constructed and installed adjacent to existing facilities and linked to
the existing GBS by a shallow water jackets and a bridge. Significant synergies can
arise due to the sharing of production utilities, storage and offloading facilities for
the phased expansion of the facility. The size of the GBS is defined by the storage
volume or topside area required for the support of facilities or a combination of both
requirements.
Raine, B., Kaplan, A.; Concrete-based offshore LNG production in Nigeria, LNG journal
September/October 2003.
17
18
See UH IELE FAQ Understanding LNG Cargo Tank Insulation www.energy.uh.edu/lng.. Dec. 2004
Gas Metering
The gas then would pass through a custody transfer meter system before entering
the pipeline. Metering capacity for the pipeline would match the peak discharge
capacity from the LNG sendout pumps.
Utility Services
All services not in direct contact with the delivered LNG are considered utility rather
than process services. Utility services take place on the Utility GBS. Utility services
include power generation, instrument and utility air, open drains and oily water
treatment, fuel gas, utility water, the hypochlorite system, potable water, wash
down, nitrogen generation and high pressure storage, wastewater treatment, diesel
fuel, aviation fuel, the emergency flare system, and fire and safety systems.
would
accommodate
about
50
personnel,
offices,
recreation,
Mooring System
Mooring of LNG ships at the GBS Terminal would be carried out through a
combination of both breasting and mooring dolphins. Breasting and mooring
dolphins are clusters of piles driven and bound together at the top (or a large
diameter pile) used to moor, anchor, breast or turn a vessel and also to protect
bridge piers and docks. Tugs would be required to assist in berthing and unberthing the LNG ships.
[insert picture of dolphins from Bluewater]
Fabrication
GBS fabrication and installation of the majority of the LNG tanks and regasification
equipment would be performed at a shore-based facility. The GBS needs to be
Decommissioning
GBS Terminals may be designed for up to 40 years of service. The decommissioning
involves removing all underwater structures and leaving facilities in place below
ground. The decommissioning procedure is a reverse of the installation procedure.
19
with LNG storage, process equipment, and ancillary facilities. The terminal would be
located approximately 36 statute miles (mi) south southwest of Freshwater City,
Louisiana in Vermilion Block 140 in the GOM. The proposed terminal site is to be
located in approximately 83 ft of water.
The facilities are to be designed, constructed, and operated in accordance with
applicable Federal, state, and local codes and standards. The Project would be
implemented in two phases. Phase I of the Project would include construction of a
terminal consisting of two GBSs. The terminal would initially have an average
sendout capacity of 800 million scfd and a peak sendout capacity of 1.0 billion scfd.
US Coast Guard: Maritime Administration: Final Environmental Impact Statement for the Port
Pelican Llc Deepwater Port License Application. August 2003.
19
from
the
fabrication
site
to
the
approved
location
offshore.
The
Topsides equipments would be placed on top of the GBSs, such as offices, crew quarters, electric
generators, regasification equipment and utilities.
20
Said ,Mike ; Meijerink, Joram Shell Global Solutions International B.V.: LNG Import Terminals:
Offshore vs Onshore A Site & Concept Screening Methodology, 14th International Conference on
Liquefied Natural Gas (LNG-14),Doha, Qatar. March, 2004
21
with
FSRU
operations,
including
electric
power
generation
and
LNG Storage
The LNG storage system is based on standard designs for ship cargo containment
systems; using spherical tanks, membrane or prismatic freestanding tanks 22.
22
See UH IELE briefing paper, LNG Safety and Security. www.energy.uh.edu/lng. Oct 2003
Fiscal Metering
The LNG storage tanks will be fitted with a radar type gauging system. This system
is used for custody transfer application and is fitted with a separate monitor in the
control room. For metering of send-out gas two ultrasonic in-line gas flow meters
will be used. One unit will handle the peak gas flow with the other unit as a standby. Flow, temperature and pressure signals will be transmitted to a flow computer
with display and printer located in the control room, which can transmit to shore if
desired. The system will be supplied with a certificate for fiscal accuracy and be
periodically re-evaluated for accuracy.
Utility Services
Similar to the GBS, the power generation for the ship services are normally
provided by gas turbines with dual fuel diesel engines as back up (sized according
to the requirements of the regasification equipment).
Mooring System
The vessel is a turret moored floating receiving unit designed for loading LNG from
a side-by-side moored LNG tanker in a relatively benign range of environmental
Cabrillo Port Application for Deepwater Port License, Submitted to Commandant, United States
Coast Guard Washington, D.C.; Submitted by BHP Billiton LNG International Inc. Houston, Texas.
23
24
California Energy Commission Staff Report: West Coast LNG Projects, Sept. 24, 2004
Source: BHP
The FSRU will be a ship-shaped double sided, double bottomed LNG storage and regasification facility. The FSRU will have a length of 286 m and breadth of 65 m,
with a displacement of approximately 190,000 dead weight tonnage (dwt). The
FSRU will store LNG in three Moss spherical tanks. Each tank will have a 91,000
m3 LNG storage capacity and the total FSRU LNG storage capacity will be 273,000
m3. The internal tank shell is aluminum, surrounded by insulating layers and clad in
an external steel shell. Each Moss spherical tank is supported on a steel skirt ring
that is braced inside the double hull of the vessel.
separate cargo hold with the tank skirt mounted directly on the foundation deck.
The spherical design reduces sloshing forces that can build up and cause damage in
non-symmetrical tanks. This allows the Moss tanks to be used without any filling
restrictions, allowing loading and unloading operations on the open seas.
The
entire internal and external shells of Moss type tanks can be inspected, and if
necessary readily repaired, as contrasted with membrane lined tank systems, where
access and repair requires significant downtime. Moss tanks have a normal fatigue
based life expectancy of 100-years.
capacity of 198 short tons per hour of LNG vaporized. The SCVs will superheat the
resultant natural gas to a temperature of about 41 oF at a pressure of about 1,500
psig. The project will have a capability of re-gasifying up to 1.5 billion cubic feet per
day (Bcf/d), with an anticipated average rate of 0.6 to 0.9 Bcf/d. The connection
from the FSRU to the send out pipeline will consist of a fixed turret style mooring
point, three flexible riser pipes, and a Pipeline Ending Manifold (PLEM) on the
seabed. The send out pipeline will run from the PLEM, through a shore crossing,
and on shore to the tie-in with the SoCalGas system. The only onshore component
of the project is a subsurface 0.65-mile segment of the send out pipeline, which
interconnects with the SoCalGas distribution system.
Three natural gas-fired generator sets, one dual fuel diesel/gas generating set and
one diesel emergency generator set will generate the onboard electric power. Each
of the three primary gas fired units will have power output of 7,400 kilowatts (kW)
at 6.6 kilovolts (kV), and the dual fuel unit an output of 5,700 kW, for a total power
plant generating capacity of approximately 28 megawatts. The diesel fuel unit used
for emergency duty will have a power output of 4,000 kW at 6.6 kV.
US Coast Guard:/ Maritime Administration Final Environmental Assessment of the El Faso Energy
Bridge Deepwater Port License Application, Nov. 2003
25
exploiting excess capacity in the existing infrastructure and has the flexibility to
easily adapt to shifting or volatile LNG supplies. Once delivered into the existing
natural gas transmission infrastructure, the gas would then be redelivered by
shippers into the national gas pipeline grid through connections with other major
interstate and intrastate pipelines.
A Submerged Turret Loading (STL) buoy receiving system to receive natural gas
from delivery vessels, with a mooring system of cables lines, chains and
permanent anchors.
A flexible riser pipe to carry the natural gas from the STL buoy to a sub sea
manifold.
Natural gas pipeline connecting the sub sea manifold to a metering platform.
A metering platform to direct and regulate the natural gas flows into
downstream pipelines.
two
EPEBVs
are
under
would
be
dedicated
to
EPEBV
would
transport
capacity
approximately
meters
have
138,000
(m3)
of
a
of
cubic
LNG
or
have
and
the
capability
unload
up
to
to
a
Source Excelerate
According to Conversion Gas Imports (CGI) 26, salt caverns can be solution mined in
far less time and at about one fifth of the cost of constructing cryogenic tanks
resulting in significantly lower investment and a shorter construction schedule. The
permitting schedule will also be significantly shorter. These advantages result in a
lower capital expenditure (CAPEX) and operating expenses (OPEX) than for
conventional terminals.
Salt cavern storage is a well-known technology and is well developed, acceptable to
the community and low cost. Salt caverns, thousands of feet below the Earths
surface, have been used to store hydrocarbons for more than 60 years. Salt
caverns provide about 5% of the natural gas storage capacity in the United States
McCall, Michael M., Conversion Gas Imports: Critical Components of Salt Cavern-Based Liquefied
Natural Gas Receiving Terminal Undergo Field Tests, GasTIPS. Summer 2004
26
Freeport-McMoRan Energy LLC: Deepwater Port License Application for the Main Pass Energy Hub
Project, Volume I, General (Public) February 2004 Submitted to USCG.
27
Two new platforms will be constructed to carry the LNG storage tanks and a
patent-pending Soft Berth System will be used to berth LNG carriers. Three
LNG storage tanks will be located on each platform, see Error: Reference source
not found and Error: Reference source not found. The LNG storage tanks will
each have a capacity of approximately 24,660 m3 with prismatic [SPB],
spherical [Moss] type, or any other acceptable containment system. The total
net capacity of the LNG storage tanks is approximately 145,000 m3. The two
LNG storage platforms will be connected to the processing facilities by a bridge.
tie -in location for two lateral transmission lines. These laterals will be 16 inches
(40.6 cm) in diameter and approximately 300 feet (91.4 meters) long
extending to proposed subsea tie -ins to existing natural gas transmission lines.
A 16-inch (40.6-cm) diameter natural gas pipeline will originate at the offshore
LNG terminal and extend east for 2.5 miles (4.0 km) to Main Pass 298 (MP
298), and tie into an existing natural gas transmission pipeline. A 20-inch (50.8cm)
diameter
natural
gas
pipeline
will
extend
south-southwest
for
high-efficiency,
water-warmed
heat
exchanger
have
been
28
The U.S. Department of Energy (DOE),s National Energy Technology Laboratory (NETL):
www.netl.doe.gov
29
McCall, Michael M., Conversion Gas Imports: Critical Components of Salt Cavern-Based Liquefied
Natural Gas Receiving Terminal Undergo Field Tests, GasTIPS. Summer 2004
30
Source:
31
Said ,Mike ; Meijerink, Joram Shell Global Solutions International B.V.: LNG Import Terminals:
Offshore vs Onshore A Site & Concept Screening Methodology, 14th International Conference on
32
Onshore
35 days/year.
(70 vessels @ 12hrs each to unload)
FSRU
130 days/year
(3 times a week @ 20hrs each to berth, unload and deberth)
Up to 280 days/year
(80 vessels @ 2.5- 3.5 days each to unload)
Source: Chan, A. et al: Evaluation Of Liquefied Natural Gas Receiving Terminals For
Southern California, 2003-2004 Group Project Thesis, University of California,
Santa Barbara. April 2004.
installing
an
LNG
transfer
six
reinstalling
LNG
and
vaporizers,
and
upgrading
the
installation
regasification
of
the
equipment
would
flexibility to the North American natural gas supply portfolio. One issue that has
been raised for Gulf of Mexico projects is potential marine impacts from ORV
systems.
Location
Expected
Flow Rate
(million
gal/day)
Water Area
Intake Intake
Depth filtered screen flow rate
(ft)
(km2/
Size
(ft/sec)
year)
(mm)
Gulf Landing
Shell
(Approved)
35 miles S of
Lake Charles,
LA
136
55
11.2
6.35
0.5
Compass Port
ConocoPhillips
11 miles S of
Mobile Bay
Inlet
156
72
12.6
6.35
0.5
36 miles S/SW
of Freshwater
City, LA
17 miles E of
Pass a Loutre,
LA
176
83
9.7
6.35
0.5
100
210
2.2
6.35
0.5
133
285
2.1
21
1.0
Main Pass
FreeportMcMoran
Energy
Source: Davy, Kay: NOAA Fisheries. Habitat Conservation Division Proposed LNG Facilities in
the Gulf of Mexico, Workshop on Liquefied Natural Gas (LNG) Facilities. April 28, 2004
The U.S. Clean Water Act (CWA) 33 requires that the location, design, construction,
and capacity of cooling water intake structures reflect the best technology available
for minimizing adverse environmental impact.
proposed offshore LNG projects will be built and put into service (see Figure 1 for
discussion on the competition among offshore LNG projects and LNG import
terminals in general).
suggests that the impact of LNG projects is such that proper and vigorous
mitigation measures could easily offset any reductions in fishery reproductivities.
The amount of water that would be affected via ORV operations is miniscule in the
overall Gulf of Mexico environment.
33
Environmental Protection Agency (EPA) Section 316(b) of the Clean Water Act www.epa.gov
34
Davy, Kay: NOAA Fisheries. Habitat Conservation Division, Proposed LNG Facilities in the Gulf of
Mexico, Workshop on Liquefied Natural Gas (LNG) Facilities. April 28, 2004
35
Foster Wheeler USA Corp: LNG Vaporizer Options Study for ConocoPhillips Compass Port GBS LNG
Receiving Terminal Pre-FEED. October 2003.
36
Allen, Ashley. EPA Office of Water: Quantifying Potential Environmental and Economic Impacts,
Workshop on Liquefied Natural Gas (LNG) Facilities. April 28, 2004
37
The center of the seawater intake array should be sited at 60 ft below mean sea
level
39