0% found this document useful (0 votes)
437 views20 pages

QCS 2010 Part 13 Traffic Signals

This document provides specifications for the supply and installation of traffic signal equipment for roadway junctions and pedestrian crossings. It outlines requirements for general project conditions, quality assurance, delivery and storage, and warranties. It also describes the supply of specific traffic signal components, including poles, signal heads, controllers, cabling, and detection loops. Installation requirements are established for poles, signal heads, controllers, cabling, electrical connections, and detection loops. The document concludes with specifications for testing, commissioning, and maintenance of the traffic signal equipment.

Uploaded by

RotsapNayrb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
437 views20 pages

QCS 2010 Part 13 Traffic Signals

This document provides specifications for the supply and installation of traffic signal equipment for roadway junctions and pedestrian crossings. It outlines requirements for general project conditions, quality assurance, delivery and storage, and warranties. It also describes the supply of specific traffic signal components, including poles, signal heads, controllers, cabling, and detection loops. Installation requirements are established for poles, signal heads, controllers, cabling, electrical connections, and detection loops. The document concludes with specifications for testing, commissioning, and maintenance of the traffic signal equipment.

Uploaded by

RotsapNayrb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

QCS 2010

Section 6

Part 13

Traffic Signals

Page 1

13.

TRAFIC SIGNALS ......................................................................................... 2

13.1

GENERAL...................................................................................................... 2

13.1.1
13.1.2
13.1.3
13.1.4
13.1.5
13.1.6
13.1.7

Summary
References
Submittals
Quality Assurance
Delivery, Storage and Handling
General Project/Site Conditions
Warranties

13.2

SUPPLY OF TRAFFIC SIGNAL EQUIPMENT .............................................. 4


4
4
4
5
6
6
7
8
9
9
9
10
10
10
10

13.3

INSTALLATION OF TRAFFIC SIGNAL EQUIPMENT ................................. 11

13.3.1
13.3.2
13.3.3
13.3.4
13.3.5
13.3.6
13.3.7

General
Poles, Gantries and Signal Heads
Installation of Traffic Signal Controller
Cabling
Circuit Protection and Earthing Requirements
Permanent Electrical Power Supply
Inductive Loops for Vehicle Detection

13.4

TESTING AND COMMISSIONING .............................................................. 17

13.5

GUARANTEED
MAINTENANCE
OF
TRAFFIC
SIGNAL
EQUIPMENT................................................................................................ 18

13.5.1
13.5.2
13.5.3
13.5.4
13.5.5

General
Operational Maintenance
Emergency Maintenance
Contractors Vehicles
Contractors Equipment

QCS 2010

11
11
11
12
12
13
14

18
18
19
20
20

BURHAN INTERNATIONAL

13.2.1 General
13.2.2 Identification of Equipment
13.2.3 Traffic Signal Posts
13.2.4 Traffic Signal Gantries
13.2.5 Three-Aspect Traffic Signal Heads
13.2.6 Two-Aspect Pedestrian Signal Heads
13.2.7 Traffic Signal Controllers
13.2.8 Pedestrian Operated Push-Buttons
13.2.9 Flexible Traffic Signal Cable
13.2.10Armoured Traffic Signal Cable
13.2.11Loop Cables
13.2.12Loop Feeder Cables
13.2.13Pulling Chamber Cover
13.2.14Unplasticised Polyvinyl Chloride (PVC-U) Ducts
13.2.15General Compatibility

2
2
2
3
3
3
3

QCS 2010

Section 6

Part 13

Traffic Signals

Page 2

13.

TRAFIC SIGNALS

13.1

GENERAL

13.1.1

Summary

This Part includes the provision of traffic signal equipment and related street furniture at
controlled roadway junctions and pedestrian crossings.

Related Sections
General
Concrete
Mechanical and Electrical Equipment
Instrumentation, Control and Automation
Electrical Works

13.1.2

References

The following standards are referred to on this Part:


BS 1361 ---------------Cartridge fuses for a..c circuits in domestic and similar premises
BS 381C ---------------Specifications for colours for identifications
BS 5493 ---------------Code of practice for protective coatings of iron and steel structures
against corrosion.
BS 7430 ---------------Code of practice and regulations for earthing
BS 7671 ---------------Requirements for electrical installations
BS 88-------------------Cartridge fuses for voltages up to and including 1000 Vac and 150 Vac
BS EN 1011 ----------Process of arc welding carbon and carbon manganese steels
BS EN 12368---------Road traffic signals
BS EN 13108---------Fine cold asphalt
BS EN 60529---------Degrees of protection provided by enclosures
BS EN ISO 146 ------Hot dip galvanised coatings on iron and steel articles
AASHTO Standard specification for supports for highway signs, luminaires, traffic signals
DIN 40050-------------Enclosures for electrical equipment
DIN 6163 Part 5 -----Diffusion lenses for traffic signals
QGEWC (E) Regulations for Electrical Installations
QGEWC (E) Regulations for Protective Multiple Earthing

13.1.3

Submittals

The Contractor shall submit to the engineer for approval shop drawings for each type of
signal pole, gantry and mounting frame for signal heads to be provided under the Contract
along with structural calculations. The drawings shall show materials specification and
finishes for each component proposed for use. All weld types and sizes shall be identified on
the shop drawings.

The Contractor shall submit to the engineer for approval design calculations for the
proposed signal poles and gantries. The design calculations shall be carried out in
accordance with the AASHTO Standard specification for supports for highway signs,
luminaires, and traffic signals

The Contractor shall propose a design for the foundations for each type of signal pole and
gantry and shall submit design calculations and drawings to the Engineer for approval.

QCS 2010

BURHAN INTERNATIONAL

Section 1
Section 5
Section 9
Section 10
Section 21

QCS 2010

Section 6

Part 13

Traffic Signals

Page 3

The Contractor shall submit to the engineer for approval a schematic wiring diagram for all
the installations. The Contractor shall also submit a wiring layout drawing for the cable loops
and the cross-sectional details of the cut in the road surface.

13.1.4

Quality Assurance

Contractors for the works shall be experienced specialists in the field of traffic control
systems with a minimum of 5 years experience of the installation, commissioning and
testing of such systems in a similar environment.

The Contractor shall submit a technical submission for the proposed subcontractor giving
details of previous installations date installed, client, technical data for proposed materials,
and experience record of proposed installation staff, supervisors and management.

Installation of traffic signal equipment shall only be conducted by approved specialist


subcontractors. The specialist subcontractors shall be approved by the PWA.

The performance and design requirements work shall be in compliance with QGEWC
Regulations for Electrical Installations.

All equipment supplied shall, in general, conform to the same style, colours and functions as
that already in place in Qatar. The supplier may be required to provide, at his own expense,
samples of his proposed equipment.

All equipment and installation shall be in accordance with the latest edition of the Qatar
Traffic Manual. For all signalled intersections and pedestrian signal control crossings the
timing sequence of signals displayed to drivers during phases shall be as per information
given by the PWA and/or Traffic Police.

13.1.5

Delivery, Storage and Handling

Before delivering a traffic signal controller to site, the Contractor shall arrange a factory
acceptance test in his workshop. The programmed and internally complete controller shall
be connected to a labelled light board capable of simulating all traffic signal aspects
controlled by that particular controller. The Contractor shall ensure that all equipment and
devices are available to show that the controller fully complies with
operational
requirements. The factory acceptance test shall consist of the following checks:
(a)
(b)
(c)
(d)
(e)
(f)
(g)

visual check of internal wiring and controller assembly


operation of green conflict monitor
intergreen times
group times
detector logic (where applicable)
stage to stage change logic
lamp switching.

The Contractor shall be responsible for the delivery of all items to the project site or to any
site as required by the Engineer.

13.1.6

General Project/Site Conditions

All equipment and associated components shall be designed and suitably rated to ensure
proper maintenance, continuous trouble free service under the prevailing climatic conditions.
All equipment and installation shall operate satisfactorily in a temperature range of 0 C to
+55 C and under humidity conditions ranging from 10 % to 100 %.

13.1.7

Warranties

All warranties and guarantees for traffic signal equipment shall commence from the day of
commissioning. The warranty period shall be that as designated by the manufacturer but
shall in any case not be less than 400 days

QCS 2010

BURHAN INTERNATIONAL

QCS 2010

Section 6

Part 13

Traffic Signals

Page 4

SUPPLY OF TRAFFIC SIGNAL EQUIPMENT

13.2.1

General

It shall be the Contractors responsibility to ensure that all equipment supplied is approved.
The Engineer will advise on approved suppliers.

It shall be the Contractors responsibility to honour the designated warranty periods..

The Contractor, shall make himself aware of any lead times required for delivery of
equipment and programme his works accordingly. It shall be the Contractors responsibility
to ensure that equipment is available as needed, any delays to works resulting from the
unavailability of equipment shall be deemed to be the responsibility of the Contractor.

The Contractor shall be responsible for the correct delivery, storage and handling and
storage of all equipment up to the time it is commissioned.

All equipment shall comprise of units of a type that have been used successfully in other
installations in a similar environment, from a minimum period of six months and shall be
subject to approval of the engineer. Particular attention shall be given in the selection and
design of equipment and components to the exclusion of water, moisture and dust.

Components and materials that may perish and deteriorate in the climatic conditions of
Qatar shall be avoided. All equipment shall be so constructed as similar units that shall be
readily available and completely interchangeable both mechanically and electrically.

The location layout of each installation and the number of phases and stages for each traffic
controller shall be as designated Controllers shall provide the signal sequences and phasing
designated for each installation.

The structural design and traffic signal posts and traffic signal gantries shall be in
accordance with provisions of AASHTO standard specification, Supports for Highway Signs,
Luminaires, Traffic Signals, or an approved alternative.

13.2.2

Identification of Equipment

The Contractor shall mark or clearly label all modules, units and main parts of a system with
a functional code or title, type number, serial number as approved by the Engineer.

Marking shall maintain legibility throughout the life of the equipment under the prevailing
environmental conditions.

The labelling system shall comply with the GIS system (as defined in the data dictionary)
used by the Government of Qatar and the PWA.

13.2.3

Traffic Signal Posts

Traffic signal poles shall be of the tubular steel type with a flanged base, having an internal
electrical termination point accessible through a lockable inspection window. The supply of
a traffic signal pole shall include; holding down bolts, nuts, washers and shims required for
erection; pole; terminal block; locking cover for inspection window complete with three sets
of keys; all grommets; glands and cable anchor points.

Traffic signal poles shall have dimensions conforming to those given in the contract
Drawings.

The traffic signal poles shall be of mild steel construction. Corrosion protection shall be
through the use of a hot dipped galvanised coating conforming to the requirements of British

QCS 2010

BURHAN INTERNATIONAL

13.2

QCS 2010

Section 6

Part 13

Traffic Signals

Page 5

Standard BS 5493 and BS EN ISO 1461, depth of galvanised coating shall be 85 microns.
All welded connections shall conform to British Standard BS EN 1011.
The termination point shall consist of a terminal block positioned internally within the traffic
signal pole. The terminal block shall be fully accessible through a lockable inspection
window. The terminal block shall be securely fixed to the traffic signal pole.

The terminal block shall be electrically isolated from the traffic signal pole and shall have a
minimum capacity of 2 x 20 No. connectors. Each connector shall have a minimum rated
capacity of 100 watts at 240 volts.

The connectors on the terminal block shall be in compliance with the requirements of the
QGEWC.

The traffic signal pole shall have the facility to secure incoming cables at a point prior to
them being connected to the terminal block

The traffic signal pole shall be fitted with an electrical earthing stud, such that at least four
earth connections can be made to it.

13.2.4

Traffic Signal Gantries

Traffic signal gantries shall be of the tubular steel type with a flanged base, having an
internal electrical termination point accessible through a lockable inspection window. The
supply of a traffic signal gantry shall include: holding down bolts, nuts, washers and shims
required for erection; pole caps; terminal block; locking cover for inspection window
complete with three set of keys; all grommets, glands and cable anchor points. Traffic signal
gantry shall be styled in accordance with Contract Drawings.

The traffic signal gantries shall have minimum dimension conforming to those given in the
Drawings. The design of the gantries is open to submission by the supplier.

The supplier shall provide full details of the materials used and the method of construction
employed when quoting for this item, this shall include workshop fabrication drawings,
material specifications and calculations pertaining to the structural design of the gantry. The
gantry shall be capable of supporting three aspect traffic signal heads, each having a total
weight of 25 kg, inclusive of mountings. The number and position of heads are to be as
designated.

With regard to termination points, cable anchor points and earthing points, these shall be as
specified in Section 6 Part12 of this Specification

The supplier shall furnish full details of the foundation requirements for his proposed gantry,
this shall include details of dimensions, reinforcement, quality of concrete and fixings.
Anchor bolts shall be Grade 8.8 and shall be hot-dip galvanized to BS EN ISO 1461.

The gantry and foundation design shall be such that the gantry is completely detachable
from the foundation, should this be required.

The gantry shall have a system such that it can be adjusted subsequent to installation, to
allow for leveling and turning.

The supplier shall furnish full details of the proposed foundation for his proposed gantry, this
shall include details of dimensions, reinforcement, quality of concrete and fixings. The
gantry and foundation design shall be such that the gantry is completely detachable from the
foundation, should this be required. Anchor bolts shall be Grade 8.8 and shall be hot-dip
galvanised to BS EN ISO 1461. The gantry shall have a system such that it can be adjusted
subsequent to installation, to allow for levelling and truing.

QCS 2010

BURHAN INTERNATIONAL

QCS 2010

Section 6

Part 13

Traffic Signals

Page 6

The electrical termination point shall consist of a terminal block positioned internally within
the gantry. The terminal block shall be fully accessible through a lockable inspection
window. The terminal block shall be securely fixed to the gantry.

13.2.5

Three-Aspect Traffic Signal Heads

Three-aspect traffic signal head dimensions shall be as designated. The Contractor shall
submit drawings of the proposed units.

Signal heads shall comprise of a polycarbonate body containing three traffic signal aspects,
coloured red, amber and green and shall include:
lamps
reflectors
lenses
transformers
visors
anti-phantom devices (if designated)
brackets, frames and all fixtures and fittings required for mounting
backing board.

Signal heads shall be constructed, in as far as is possible, out of high quality polycarbonate
plastic. Any metal fittings shall be suitably protected against corrosion.

The design and construction of signal heads shall allow for all of the following features:
(a)
(b)
(c)
(d)

hinged lens panels to allow quick access to the lamps


flexible, detachable visors
easily adjustable mounting system
capability of internally fitting optical arrow mask.

The signal heads shall use, for each aspect, a 10 volt halogen lamp of type SIG 64015/1 50W or SIG 64015 - 50W. The lamp holder and connectors shall be compatible with the type
of lamp used. The lamps shall conform to BS EN 12368. The supply voltage to the signal
head shall be 240 volts ( 5 %) and shall be converted to the lamp voltage by the use of a
standard design transformer (El Type). Each aspect shall have an individual transformer,
these transformers shall be fitted with noise suppression equipment. The transformers will
be required to operate in ambient temperatures up to 60 C. The transformers shall have a
minimum operational life of five years with an effective switch-on ratio of 3300: 4380.

Signal heads shall be capable of being mounted on the traffic signal pole or gantry as
designated or, in the case of traffic signal gantry, as may be proposed by the Contractor.
The mounting system used shall be such that no predrilling or permanent attachment of
brackets to the signal pole or gantry is required. The mounting system shall be such that the
signal head shall be capable of being adjusted through an arc of 30 degrees about its
vertical axis. It shall be possible to mount two three-aspect traffic signal heads side by side
on a single pole such that the vertical faces being presented to oncoming traffic of each
head remain in the same plane. It shall be possible to mount the signal heads asymmetrical
from the centreline of the pole. The signal head shall be rendered splash proof by means of
an lP54 enclosure. The item description covering signal heads shall include, where
necessary, extra mounting brackets to enable the above facilities.

The optical reflector shall be made of a high grade aluminium, mirror finished. Diffusion
lenses shall be constructed with an internal cobweb pattern and shall be coloured red,
amber or green as defined by the colour limits laid down in the DIN Standard DIN 6163 Part
5.

13.2.6

Two-Aspect Pedestrian Signal Heads

Two-aspect pedestrian signal heads shall have the designated dimensions. The Contractor
shall submit drawings of the proposed units.

QCS 2010

BURHAN INTERNATIONAL

(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)

QCS 2010
2

Section 6

Part 13

Traffic Signals

Page 7

Signal heads shall comprise of a polycarbonate body containing two pedestrian signal
aspects, coloured red and green and shall include:
(a)
(b)
(c)
(d)
(e)
(f)
(g)

lamps
reflectors
lenses
transformers
visors
anti-phantom devices (if designated)
brackets, frames and all fixtures and fittings required to mount the signal head.

The material, electrical and mounting requirements for the signal head shall be the same as
the requirements for the three aspect traffic signal head.

The optical requirements for the signal head shall be the same as the requirements for the
three aspect traffic signal head with the additional requirement that each aspect of each two
aspect pedestrian signal head be supplied with a 'Walking Man' and 'Stopping Man' optical
mask.

13.2.7

Traffic Signal Controllers

Traffic signal controllers shall be microprocessor based and capable of meeting all the
designated requirements. The Contractor shall submit drawings of the proposed units.

Supply shall include:


(a)
(b)
(c)
(d)
(e)

basic control hardware including relays housings and cabinets


all required additional modules and circuits
all internal wiring
all detector modules and control circuits
plates, fixings and fastenings, glands, seals and clips.

The controller shall be provided with the following operational modes:


(a)
(b)
(c)
(d)
(e)
(f)

computer control
standby co-ordinated
local mode with multi-plan operation
flashing
manual mode
signal on/off mode.

Means will be provided within the controller housing to select and to test each of these
modes of operation.

For pedestrian crossings the controller shall be capable of showing a green flashing man
before the end of each pedestrian phase.

All controllers shall include a dimming feature.

Controllers shall be of a manufacturers type approved by the PWA and/or Traffic Police.

All equipment supplied shall be compatible with the existing traffic signal controllers in use in
the state of Qatar.

Where the supplier cannot provide evidence of his equipment having been previously
successfully used with the above traffic signal controllers, he shall be required to
demonstrate, at his own expense, the compatibility of his equipment.

10

Traffic signal controllers shall be programmed as designated and as agreed with the
Engineer. It shall be the Contractors responsibility to provide competent personnel to
programme the controller.

11

Each controller shall be supplied with full documentation which shall include :

QCS 2010

BURHAN INTERNATIONAL

QCS 2010
(a)
(b)
(c)
(d)
(e)

Section 6

Part 13

Traffic Signals

Page 8

wiring diagrams
timing charts
intergreen tables
stage diagrams
any other relevant information relating to the operation.

Three copies of the documentation shall be supplied with each controller.


The controller shall be housed in the cabinet of sufficient size to accommodate the controller
and all other associated equipment and shall provide easy access for maintenance and test
purposes. The controller and associated equipment shall be arranged within the cabinet so
that they will not interfere with the entry and exit cables. The cabinet to house signal
controllers shall be constructed of aluminium sheet of thickness 3 mm in accordance with
BS EN 12368 or with non-metallic materials where the properties for abrasion resistance,
exposure to the elements are equal or better than aluminium cabinet. Cabinets shall be
painted to a colour and specification agreed by the Engineer. The cabinet shall be
weatherproof, rain proof and dust proof and be able to maintain proper operation of
equipment. The Contractor shall construct a suitable foundation for the cabinet. and it shall
allow for the entry and exit of all cables. The cabinet shall be secured to the foundation by
anchor bolts.

13

The traffic signal controller shall be micro-processor based and capable of meeting all the
requirements of the operational Specification and any further requirements as specified by
the Engineer. The supply of a traffic signal controller shall include for: the basic control
hardware including relays housings and cabinets, all additional modules and circuits
required to meet the operational Specification, all internal wiring, all detector modules and
control circuits, plates fixings and fastenings glands, seals and clips.

14

Traffic signal controllers shall be of an approved type and supplied by an approved


manufacturer taken from the most recent list prepared by the Public Works Authority.

15

Traffic signal controllers shall be programmed according to the operational Specification and
as agreed with the Engineer. It shall be the Contractors responsibility to provide competent
personnel to programme the controller.

16

The traffic signal controller shall also have the following capabilities:
(a)
(b)
(c)

(d)
(e)
(f)
(g)

To give a flashing red pedestrian man before switching to a red man at the end of
pedestrian cycle.
The controller shall include a timing feature.
The controller shall support two power supply inputs coming from two different
substations. The purpose is to continuously operate the controller in case of power
failure on one substation by automatically transferring to the other power supply input.
The controller shall be made to ensure that the dual power supply input is stabilized at
240 volts.
The controller can be operated manually.
The controller shall be capable of providing flashing green before switching to
yellow/amber at the end of vehicle green phase
The controller shall be capable of providing continuous flashing yellow/amber in the
channelized island.

17

Each traffic signal controller shall be fully documented, this shall include: wiring diagrams,
timing charts, intergreen tables, stage, diagram and any other relevant information relating to
the operation. Three (3) No. copies of the documentation shall be supplied with each
controller.

13.2.8

Pedestrian Operated Push-Buttons

Pedestrian operated push-buttons shall comply with the requirements and regulations of the
QGEWC.

QCS 2010

BURHAN INTERNATIONAL

12

QCS 2010

Section 6

Part 13

Traffic Signals

Page 9

The push-button shall include traffic signs as per the Qatar Traffic Control Manual either as
an integral part, or be mounted separately on the traffic signal pole or gantry.

Push-buttons shall comprise of a metal or plastic body containing a push-button switch and
an illuminated text panel in Arabic and English.

The unit shall have a light that provides confirmation after a pedestrian has pushed the
button.

The dimensions and position of the push-buttons shall be proposed by the supplier and
approved by the Engineer.

Push-buttons shall be constructed of metal or high grade plastics.

13.2.9

Flexible Traffic Signal Cable

Flexible traffic signal cable shall comprise of four cored, PVC coated, internal core PVC
coated, cable. The cable shall be PVC sheathed wiring, catalogue description being NYM-J,
page 2/3 or equivalent.

The cable shall be of a rated voltage and current carrying capacity suitable for the proposed
cable runs. The Contractor shall submit calculations showing the voltage drop for the cable.

Cable shall be supplied in 500 metre lengths and wound onto a suitable cable drum.

Cable shall have a minimum cross-section area of the conductor in each core of 1.5 mm2
and the overall diameter of the cable shall be 11 mm. The individual core may be either
solid or stranded. Each core shall be uniquely identifiable by coloured PVC sheathing.

13.2.10 Armoured Traffic Signal Cable


1

Armoured traffic signal cable shall comprise of a multi-cored (number of cores as specified),
PVC coated, copper wire armoured, internal core PVC coated, cable. Catalogue description
being, PVC-CWA-PVC or equivalent.

Cable shall be supplied in 500 m lengths, wound onto a suitable cable drum.

Cable may be supplied in three sizes, 7 core, 12 core or 19 core. The minimum area of the
conductor in each core shall be 1.5 mm2. The individual cores may be either solid or
stranded. Each individual core shall be uniquely identifiably by either having a uniquely
coloured PVC sheathing or by its PVC sheathing having a unique, repetitive marking.

13.2.11 Loop Cables


1

Loop cables shall consist of a heat resistant coated core cable. Loop feeder cables shall
comprise of a communication type cable, PVC coated having six pair of individually coated
cores. The Loop shall be manufactured by Never Fail Loop Systems, USA (local
representative Traffic Tech (Gulf), P.O. Box 9377, Telephone Number 4621814) or similar
approved.

Loops shall be constructed from polypropylene conduit with 9.5mm inside diameter and
16mm outside diameter. Conduit shall be filled with hot rubberised asphalt which allows the
loop to remain flexible once cooled to prevent incursion of moisture and set the turns of wire
firmly in place. Loops shall have 127mm expansion/contraction joints at intervals along the
loop to allow for movement. Each expansion/contraction joint shall have a 229mm long
schedule 80 polypropylene cover slide to be placed over the joint.

Lead-in wires shall be encased in a non-conductive 2250 psi flex hose constructed with a
seamless extruded polyester fiber braid reinforcement and a non-conductive, seamless

QCS 2010

BURHAN INTERNATIONAL

QCS 2010

Section 6

Part 13

Traffic Signals

Page 10

extruded urethane non-perforated jacket. Fill lead-in hose completely with hot rubberised
asphalt. Twist wires in all lead-ins with a minimum of three turns per 305 mm for the entire
length of the lead-in. Attach lead-ins to loop heads with a sch. 80 CVPC tee.
4

Loop cable shall have one individual core, the conductor of which shall have a crosssectional area of 1.5 mm2. The loop cable such that the coating is able to withstand direct
application of temperatures up to 175 C.

13.2.12 Loop Feeder Cables


Loop feeder cable shall have six pairs of individual cores, each of which having a conductor
of cross-sectional area of 0.6mm2. Each individual core shall be uniquely identifiable by
either, having a uniquely coloured PVC-U sheathing or by its PVC-U sheathing having
unique, repetitive marking.

The use of alternative types of cable may be permitted with the express written permission of
the Engineer.

Each individual core shall be uniquely identifiable by either having a uniquely coloured PVC
sheathing or by its PVC sheathing having a unique, repetitive marking.

13.2.13 Pulling Chamber Cover


1

Pulling chamber covers shall be of ductile iron.

The pulling chamber covers shall have a square opening of the dimensions shown on the
project drawings.

The pulling chamber covers shall be inscribed with wording to identify the type of service and
the system reference. The exact wording shall be to the approval of the Engineer.

13.2.14 Unplasticised Polyvinyl Chloride (PVC-U) Ducts


1

Unplasticised Polyvinyl Chloride shall be supplied in two different sizes, 2 inches diameter or
4 inches diameter (50mm or 100mm). The colour shall be dark gray. The PVC-U shall be
either encased burial type or direct burial type. Catalogue description being, PVC-U
Electrical Conduit & Tubing and Utility Duct, NEMA TC-6 or NEMA TC-8 or equivalent.

Unplasticised polyvinyl chloride ducts shall be supplied in 6 metre lengths with solvent weld
socket on one end. The minimum wall thickness shall be 1.52 mm for 2 inches diameter
and 2.08 mm for 4 inches diameter.

13.2.15 General Compatibility


1

All equipment supplied shall, in general, conform to the same style, colours and functions as
that already in place in Qatar. The supplier may be required to provide at his own expense,
samples of his proposed equipment. These samples shall become the property of the PWA,
whether or not an order is placed.

All equipment supplied shall be compatible with the approved traffic signal controllers and
supplied by an approved manufacturer according to the most recent approved list of the
PWA.

Where the supplier cannot provide evidence of his equipment have been previously used
successfully with the above mentioned traffic signal controller, he shall be required to
demonstrate, at his own expense, the compatibility of his equipment.

QCS 2010

BURHAN INTERNATIONAL

QCS 2010

Section 6

Part 13

Traffic Signals

Page 11

INSTALLATION OF TRAFFIC SIGNAL EQUIPMENT

13.3.1

General

It shall be the Contractors responsibility to ensure that all traffic signal installation work is
conducted by skilled, competent personnel.

The Engineers approval of any subcontractor or individual personnel in no way relieves the
Contractor of his responsibility to ensure that traffic signal equipment is correctly installed.

The Engineer shall reserve the right to inspect and approve all installation practices.

Installation of traffic signal equipment shall only be conducted by approved companies taken
from the most recent list prepared by the PWA.

13.3.2

Poles, Gantries and Signal Heads

Signal posts and gantries shall be installed onto their prepared foundations, using two
levelling nuts or an appropriate fixing method approved by the Engineer. The pole or gantry
shall be plumbed square, irrespective of the orientation of surrounding features.

The Contractor shall take every precaution to prevent damage to the pole or gantry's
protective coating, during installation. Where the protection is damaged or breached the
Contractor shall take immediate action to make repairs.

Where designated, posts and gantries where necessary shall be painted with an approved
paint, colour grey (BS 381C) before installation of signal heads and push-buttons..

Signal heads and push-buttons shall be installed as shown on the contract drawings. Final
positioning and fixing shall not be undertaken without the Engineers approval.

Signal heads, once fixed, shall be covered with an opaque protective material such that it is
clear to motorists that the signals are not in operation.

13.3.3

Installation of Traffic Signal Controller

The Contractor shall install the controller housing in the position defined by the Engineer.
The Contractor shall ensure that the housing is positioned so that when the access doors
are opened to their fullest extent they will not obstruct the sidewalk or cause a danger in any
way to members of the public. The housing shall not be positioned adjacent to the kerb as to
render it liable to damage by vehicles or so that the safety of persons working on the
controller is not endangered.

The Contractor shall organise the connection of the electricity supply to the controller
housing and any other peripheral equipment requiring an electricity supply by direct liaison
with the QGEWC (E) Consumer Section. The Contractor shall ensure that the power supply
is contained within its own separate duct, up to the point at which it enters the controller
housing. The electrical supply shall at no point share the same ducts or chambers as the
traffic signal cabling. The Contractor, where necessary, shall be responsible for providing
any housings required for QGEWC apparatus. Where a separate housing is required it shall
be positioned directly adjacent to the controller housing.

The Contractor shall endeavour to complete as much of the internal wiring of the controller
as possible inside his workshop, such that on-site work within the controller housing are kept
to a minimum. All external cables terminating within the controller shall be clearly labelled
as to their function, destination and nominal voltage. These cables shall, on entering the
controller housing, be clamped and supported such that any stress or strain on the cables
themselves shall not be transmitted to the controllers internal components. Spare or
redundant cables entering the controller housing are to be terminated in such a fashion that

QCS 2010

BURHAN INTERNATIONAL

13.3

QCS 2010

Section 6

Part 13

Traffic Signals

Page 12

they do not interfere in any way with access to the controllers internal components. The
conductors of these cables are to be electrically isolated and sealed against the ingress of
moisture.
It shall be the Contractors responsibility to provide all competent personnel and specialist
equipment to enable the controller to be programmed.

13.3.4

Cabling

The Contractor shall install all cables in the ducts as designated. He shall take all
reasonable care to ensure that no undue stress or strain is placed on the cable during
installation and shall adhere to the cable manufacturers published data with regard to
allowable minimum radius of curvature. The Contractor shall ensure that duct drawstrings
remain in place subsequent to cable installation.

A single dedicated cable shall service each individual traffic signal pole. This cable shall be
of the designated size and shall have a minimum of 10 % spare capacity. On entering the
signal pole the cable shall be firmly anchored to the pole. At least 3 m of spare cable shall be
allowed for within the signal pole, over and above that length which is required to reach the
termination block.

Spare or redundant cores within the cable shall be terminated at the termination block and
labelled 'Spare'. The core acting as earth protection shall be connected directly to the body
of the signal pole by means of the poles earthing stud. The cable armouring shall not be
used as the protective earth conductor.

With the exception of loop cable to loop feeder cable connections, the jointing of cables shall
not be permitted. Where jointing of the cables is permitted, this shall be undertaken using a
suitable jointing kit of an approved type which allows the integrity of the protective earth
conductors to be maintained. Loop cable to loop feeder cable joints shall only be located
within an access chamber.

13.3.5

Circuit Protection and Earthing Requirements

The Contractor shall provide protection against dangerous earth-leakage currents by the use
of fuses or excess-current circuit breakers compliant with the QGEWC (E) Regulations for
Electrical Installations. The Contractor shall ensure that all installations shall be such as to
allow for the operation of the protective devices to operate upon the occurrence of a fault
within the time period specified for fixed equipment installations and that all non-current
carrying metallic parts shall be connected to the earth terminal in such a manner as to
ensure that a hazardous voltage cannot exist on exposed conductive metalwork.
All
cabinets, posts and other metal hardware comprised by the traffic signalling equipment shall
be bonded via protective conductors to the main earth terminal with an earthing conductor to
the main terminal by a protective conductor.

The main earthing terminal or bar shall comply with QGEWC (E) Regulations for Electrical
installation and shall be connected to the earthing point provided by the QGEWC (E) with a
copper earthing conductor in accordance with the Regulations. It shall have a minimum
cross-sectional area of 6.00 mm2 and shall be green/yellow stripe coded. The earthing
conductor is defined as a protected conductor connecting a main earthing terminal or bar of
an installation to an earth electrode of other means of earthing. Where a residual current
circuit breaker is used, the cross sectional area of the earthing conductor shall comply with
the requirements of QGEWC (E) Regulations.

The connection to metalwork shall be made internally to a secure terminal on a part of the
enclosure which is a permanent fixture. The terminal shall be constructed of a material which
will minimise chemical corrosion resulting from contact with the protective conductor or other
metal part. Conductor terminations shall be by the use of soldered or crimped connectors or
screwed terminations, or other approved methods.

QCS 2010

BURHAN INTERNATIONAL

QCS 2010

Section 6

Part 13

Traffic Signals

Page 13

Earth and other protective conductors shall be selected and installed so that they comply
with the QGEWC (E) Regulations for Electrical Installations, the BS 7430, BS 7671 and the
Regulations for Protective Multiple Earthing where appropriate. All protective conductors
shall be colour coded green/yellow stripe. Where protective conductor is part of a multicore
cable and a green/yellow stripe colour coded core is not available, the Contractor shall
ensure that the protective conductor is adequately identified. Each cable shall enter the
controller housing via a stuffing gland in the gas plinth gland plate. The stuffing gland shall
be so designed as to prevent the diffusion of gas and support the cable. The earth stud of
the cable terminator shall be correctly bonded to the earth bar in accordance with the
QGEWC (E) Regulations, using a 6.00 mm2 conductor (2.50 mm2 for loop feeder cables).

The earthing requirements at the head of each traffic signal pole shall be as follows:

(b)

(c)

(d)

(e)

the earth terminal of the gland, shall be connected to the earth terminal of the pole
with a protective earth conductor correctly terminated with crimp connectors and
having a minimum cross-sectional area of 6.00 mm2
the protective conductors from each signal head, pedestrian head, push-button unit or
other equipment shall be connected together at the head of each pole and connected
to the earth terminal in the controller housing by means of one dedicated core of the
armoured signal cable servicing that pole
the earth connection at the head of the pole specified in (b) above, shall be connected
to the earth stud of the pole with a bonding conductor having a minimum area of
6.0 mm2 and by means of a crimped connector, or similar
push-button units fixed to a signal pole shall be earthed to the earth stud of the pole
with a separate protective conductor terminated with crimp connectors and having a
minimum cross-sectional area of 6.00 mm2
There shall be electrical connections by means of conductors having a copper
equipment cross-sectional area of not less than 6.00 mm2 between the earthing
terminal and all metal structures, metal pipes and other metalwork (not being
metalwork forming part of a telegraphic, telephone or signalling circuit) which
(i)
are, or may reasonably be expected to become, in electrical contact with the
general mass of earth
(ii)
are so situated that simultaneous contact may reasonably be expected to be
made by any person with such structures, pipes or other metalwork (or any
metalwork in electrical contact therewith).
These connections shall be made as near as practicable to locations where users or
maintenance staff approach the facility.

13.3.6

Permanent Electrical Power Supply

The Contractor shall be responsible for liaison with QGEWC (E) to provide a power supply to
the traffic signal controller and shall be responsible for all works required to provide this
supply.

The electricity supply shall be 240 V AC 50 Hz single phase.

The Contractor shall organise, with the approval of QGEWC (E), one of the following
earthing systems:
(a)

(b)

(c)

TN-S System. Where QGEWC (E) will provide an earthing point which affords a
continuous metallic return path to the earth of the supply system. The Contractors
earthing conductor shall be connected to this point
TN-C-S System (PME). Where QGEWC (E) will provide a combined neutral earth
supply. The earthing Contractors earthing terminal and a lead from the earth terminal
shall be left available for the QGEWC (E) to connect to the incoming supply. A similar
neutral conductor lead shall also be left available for the same purpose
TT System. Where a means of earthing will not be provided by the QGEWC (E) the
earthing terminal will be connected to an effective earth electrode compliant with the
QGEWC (E) Regulations for Electrical installations. Where the TT System is provided
by the QGEWC (E) the Contractor shall install an earth leakage circuit breaker to
comply with the QGEWC (E) Regulations.

QCS 2010

BURHAN INTERNATIONAL

(a)

QCS 2010

Section 6

Part 13

Traffic Signals

Page 14

The Contractor shall ensure that the equipment complies in all respects with the regulations
and requirements of the QGEWC (E).

The Contractor shall be responsible for all cable laying and jointing.

It shall be the responsibility of the Contractor to inform the Engineer of the earliest date when
he will be ready for the QGEWC (E) to make the service connections.

The Contractor shall supply the equipment to be terminated to the QGEWC (E) service with
phase and neutral conductors of not less than 4 mm2 and earthing conductor of not less than
6 mm2. The QGEWC (E), shall connect the controller conductors and earth conductor to the
terminal provided by the QGEWC (E).

The QGEWC (E) cut-out shall incorporate a high breaking capacity fuse carrier and fuse to
BS 88 or BS 1361 of the correct rating. The rating shall be specified by the Contractor to
comply with the type requirements of the QGEWC (E) Regulations. The maximum
permissible earth fault loop impedance shall be those stated in the QGEWC (E) Regulations.

13.3.7

Inductive Loops for Vehicle Detection

Slot cutting shall be carried out by a specialist subcontractor. The Contractor shall be
responsible for marking out all slot configurations and shall supervise the work of the
subcontractor. The slot cutting subcontractor shall make arrangements to provide an
adequate water supply to enable him to carry out the necessary works. The approximate
position of inductive loops and route of feeder cables will be as designated. The Contractor
shall specify the loop configurations at each site, the detailed layout of individual loops and
the number of turns per loop. This information shall be supplied to the Engineer. When loop
configurations are specified by the Engineer, such information as required will be supplied to
the Contractor. In order to obtain a high standard of installation, the Contractor's staff and
subcontractors shall be fully briefed by the Contractor and given written instructions
describing the technical requirements of this specification and method of installation. This
shall cover depth and preparation of slots, backfilling, jointing, ducting under kerbs, earthing
and commissioning of equipment.

Subsurface detector housings for loop detection equipment are not acceptable to the
Engineer. Detector housings shall be positioned so as to reduce the possibility of damage in
the event of a road traffic accident and shall not present an obstruction or visual intrusion. In
cases of doubt, the advice of the Engineer shall be sought. Positions of detector housings
shall be to the approval of the Engineer. Where a remote detector housing is used, each
one shall be connected to the controller by 'Twinflex' cable. The cable will be ducted to the
controller unless the Engineer's agreement is obtained to cutting a slot in the carriageway.
Voltages on this cable shall not exceed 50 V AC or 120 V DC whether between
conductors or to earth. The Contractor shall provide two sets of keys to all equipment
housing supplied as initial issue. The Contractor shall be responsible for removing all surplus
materials from site at the completion of the works.

The cable specified may in exceptional circumstances be replace with an armoured


multicore cable (i.e.. triple vehicle extensions with speed discrimination) double vehicle
extensions with speed assessment. The cable specified shall be terminated at the controller
with a cable gland or castellated bar approved by the Engineer. The gland shall be bonded
to the earth point using a 4 mm2 flexible earthing cable terminated with crimp connection
tags. The remote end of the cable shall be connected to the plate and 4 mm2 flexible
earthing cable terminated with crimp connection tags or by other means approved by the
Engineer. In addition one core of the armoured cable shall be used as an earth continuity
conductor and shall be bonded to the earth point on the controller and to both the equipment
earth and the metalwork of the housing at the remote end of the cable. The cable specified
shall be provided with a minimum of 25 percent spare conductor capacity (armoured and
non-armoured multicore cables only).

QCS 2010

BURHAN INTERNATIONAL

QCS 2010
4

Section 6

Part 13

Traffic Signals

Page 15

The detector shall operate satisfactorily with a feeder up to 100 metres in length. The feeder
is defined as the cable between the loop tails and the detector housing. Where adjustments
are required to sensitivity and presence time, these shall be made during initial setting-up
and no further adjustments shall be necessary. The equipment, including loop and feeder,
shall operate correctly within all carriageways of reasonable condition without any reduction
in performance as follows:
air temperature (-10C to 60C)
relative humidity up to 100 % (non-condensing)
carriageway flooded under 1 cm water, or dry
carriageway subjected to continued heavy use by buses and heavy goods vehicles
sidewalk and kerbs subjected to misuse by vehicles
feeder assumed to be buried in soil or sand which may be dry or wet
the detector shall not operate from electrical noise pick-up on the loop or feeders.

Slot-cutting operations shall not be conducted in wet weather. Wet weather to be defined as
such conditions where the Engineer considers it would be unsafe to carry out slot cutting
operations. Slots shall be cut using a motorised machine fitted with a diamond saw blade.
The layout of the loop configuration shall avoid areas of poor reinstatement in the road
surface caused by other roadworks or works. Slots shall be cut at least one metre from any
such disturbance. Slots shall be cut at least one metre from any ferrous objects such as
manhole covers. In concrete road surface, the Contractor shall not cut slots less than 1.5
metres from transverse joints between adjacent concrete sections. The depth of loop slots
shall be (50 + 7.0 n) mm with a tolerance of + 10.0 mm / - 0.0 mm. In concrete surfaces the
depth shall be (25 + 7.0 n) mm with a tolerance of + 5.0 mm / - 0.0 mm where 'n' is the
number of cables and the first figure is the minimum depth of cover. The depth of each slot
shall be checked with a depth gauge along the whole length of the slot. The Contractor shall
ensure that there are no irregularities in the base of the slot. Where an angle more acute
than 13 degrees in formed at the junction of two adjacent loop slots, then the slot junction
shall be truncated with a saw cut at the apex of the junction; i.e., one blade thickness from
the inside edge of the slot corner, and this cut shall be to the same depth as the adjoining
slots. The junction shall not be truncated with a cold chisel. Slots cut for feeder cables shall
be 20 mm wide (core cables 25 mm) with a tolerance of 3 mm, to give a cover of 65 mm in
bituminous surfaces (45 mm in concrete surfaces) with a tolerance of + 10.0 mm / -0.0 mm.
Only one feeder cable shall occupy each slot.

The loop feeder cables shall take the most direct route to the indicated cable chamber. This
slot is specified as being 20 mm wide, therefore care shall taken not to obliterate any road
markings in whole or part. In the first instance the most direct route from the loop position to
the kerb line shall be taken. The loop feeder cables shall be joined in the carriageway only
with the approval of the Engineer. The joint slot shall be 10 mm wider and 10 mm longer
than the overall dimensions of the completed joint. The depth of the slot shall be sufficient to
give a minimum 40 mm cover above the joint. The joint slot shall be positioned either at a
traffic lane boundary or at crown of the road so that it is not subjected to the maximum
stresses exerted by road vehicles. Each loop shall be separated from adjacent loops by a
minimum of 100 mm. The Contractor's supervisory staff shall check the quality of
workmanship before laying cable and backfilling. All debris and slit shall be cleared from the
base of the slot and the slot blown dry with compressed air before cable laying.

For laying loop cables the cable shall be dry before installation. The Contractor shall ensure
that the cable lies evenly in the bottom of the slot, and shall secure the cable in such a
position if necessary. Sharp implements shall not be used to seat the cable in the slot. Loop
tails shall not extend more than 20 metres from the loop before being joined to the feeder
cable. Loop tails shall be twisted. Each twisted tail shall have a dedicated slot to the joint
with feeder cable. Loop tails shall normally be joined to the feeder cable within cable
inspection chambers. Cables shall not be bent to a radius of less than 12 times their
diameter or less than a radius recommended by the manufacturer whichever is the greater.
Where cables enter the sidewalk a small area of carriageway is to be excavated and a uPVC
duct laid through the kerbs for each feeder cable. The duct shall be level with the base of the
slot from which the feeder cable emerges. The excavated area shall be backfilled with fine
aggregate concrete to the duct invert level. The cables shall then be backfilled with

QCS 2010

BURHAN INTERNATIONAL

(a)
(b)
(c)
(d)
(e)
(f)
(g)

QCS 2010

Section 6

Part 13

Traffic Signals

Page 16

compacted fine cold asphalt and hot oxidised bitumen R85/40. The kerb stone shall be
reinstated. Feeder cables in soft verge or beneath sidewalks are to be laid in ducts at a
minimum depth of 500 mm below ground level unless otherwise specified by the Engineer.
Feeder cables laid unducted in trenches shall be laid on a 75 mm bed of sand free from
stones and other sharp materials with a further 75 mm of similar sand placed over the cable.
Where feeder cables are laid unducted in soft verges, the cable position shall be indicated
with a plastic warning tape laid at a depth of 150 mm to 200 mm from ground level and
vertically above the cable. The tape shall be printed with suitable warning message repeated
at one metre intervals. Where feeder cables are required to cross French drains or other
coarse bed materials in central reservations, the cable shall be looped and protected with
flexible plastic ducting. Ducting is to be provided by the installation Contractor.
Cable joints shall be approved by the Engineer. Feeder cables shall be electrically
connected to the loop tails with insulated crimp connector using a ratchet type of crimping
tool. The Contractor shall ensure that the cable conductor has been correctly crimped by
visually checking the cable and also by applying a vigorous pull test to the cable on either
side of the joint. The electrical connectors shall be encased in a joint approved by the
Engineer and the Contractor shall ensure that the connectors are staggered to avoid the
possibility of any short circuits. The Contractor shall ensure that any instructions issued by
the cable joint manufacturer are provided in writing to his installation and supervisory staff.
These instructions shall form part of this specification. The Contractor shall ensure that the
joint is waterproof before backfilling. With the exception of cable joints between loop and
feeder cables, no other joint shall be permitted in the loop/feeder configuration. Cables shall
be terminated in the controller or detector housing using terminal connection blocks which
are adequate in size for the diameter of conductors used. Screws shall not bear directly onto
conductors, either a protective leaf in the terminal or a crimped pin on the end of the
conductor shall be used.

Immediately before backfilling, the Contractor shall ensure that all slots are clean and dry
and that all silt and debris has been removed from the base of the slot. Loop slots shall be
backfilled with a low viscosity epoxy resin, approved by the Engineer, to give a minimum of
10 mm cover above the uppermost cable. The resin specified shall be poured at a viscosity
of between 500 and 1000 pascal seconds. The Contractor shall provide the Engineer
documentary evidence from the resin manufacturer of the temperature necessary to achieve
this viscosity.
The Contractor shall satisfy the Engineer, before epoxy resin operations
commence, that the specialist subcontractors on-site equipment is able to raise the epoxy
resin and maintain it at the temperature necessary to achieve the viscosity specified. The
remaining volume of loop slot shall be backfilled with blown grade hot oxidised bitumen to
the level of the road surface. Feeder cable slots shall be backfilled with fine cold asphalt
compacted around the cable. The upper 20 mm of the slot shall be filled with hot oxidised
bitumen. Joint slot shall be backfilled with epoxy resin to a level 10 mm above the
completed joint. The remaining volume shall be filled with hot oxidised bitumen. The hot
oxidised bitumen specified shall be heated to a pouring temperature of 185 C and shall be
poured from an enclosed container which shall be preheated before use. The fine cold
asphalt specified shall comply with the requirements of BS EN 13108. The asphalt shall be
soft and easily worked when applied, and shall be hand compacted to the satisfaction of the
Engineer. Alternative compounds proposed by the Contractor shall be approved by the
Engineer.

10

The contractor shall be responsible in determining the exact location of the loops and shall
supervise the work of the sub-contractor. The sub-contractor shall mark the locations of the
performed inductive loops. Each shall be separated from adjacent loops by a minimum of
100mm and shall be laid on top of the road base or 230mm form the road surface.

11

The cable shall be dry before installation. The sub-contractor shall lay the performed
inductive loops and stretch it as per the marked locations. The T-joint of the loops shall be
positioned to the nearest chamber/pull box/detector hand hole. The loops shall be fixed by
using a clamps and nails to achieve the desired shape

QCS 2010

BURHAN INTERNATIONAL

QCS 2010

Section 6

Part 13

Traffic Signals

Page 17

The loop wires from the preformed loop to the adjacent chamber/pull box/detector hand hole
shall be twisted together into a pair with minimum of three turns per 305mm and encased in
polypropylene conduit and/or 2250 psi hydraulic hose between the performed loop and the
adjacent chamber/pull box/detector hand hole. Lead-in conduit shall be 100% injected with
hot asphalt sealant to prevent the entrance of water at the chamber/pull box/detector hand
hole.

13

Asphalt shall be manually laid around the loops to protect it from the pavement
machine/equipment.

14

Upon completion of the installation works, the Contractor shall lay the asphalt on the entire
carriageways by using the approved pavement machine.

15

Each loop shall be tested sequentially by three methods: by megger (measured by mega
ohms), by resistance (in ohms), by inductance (measured in micro henries).

16

In case of existing pavement, a groove shall be cut by using a slot cutting machine. The
frames and home-runs shall be placed into the cuts. The cuts shall be filled with hot melted
asphalt-rubber sealant conforming to the manufacturers recommendations.

17

All the installation works shall conform to the manufacturers specifications.

13.4

TESTING AND COMMISSIONING

Before delivering a traffic signal controller to site, the Contractor shall arrange a factory
acceptance test in his workshop. The programmed and internally complete controller shall
be connected to a labelled light board capable of simulating all traffic signal aspects
controlled by that particular controller. The Contractor shall ensure that all equipment and
devices are available to show that the controller fully complies with operational requirements.
The factory acceptance test shall consist of the following checks:
(a)
(b)
(c)
(d)
(e)
(f)
(g)

visual check of internal wiring and controller assembly


operation of green conflict monitor
intergreen times
group times
detector logic (where applicable)
stage to stage change logic
lamp switching.

All traffic signal equipment shall be commissioned to the satisfaction of the Engineer.

It shall be the responsibility of the Contractor to supply all equipment and personnel required
to commission the traffic signal equipment.

On completion of installation, and before commissioning, the Contractor shall undertake the
following tests to the satisfaction of the Engineer and in accordance with the QGEWC (E)
Regulations.
(a)
(b)
(c)
(d)
(e)

visual inspection
continuity test of all protective conductors
insulation resistance test; insulation resistance shall not be less than 100 megaohms
polarity check
earth loop impedance test.

Where a residual current circuit breaker is installed, tests in accordance with the QGEWC
(E) Regulations shall be complied with. The Contractor shall provide the equipment
necessary to complete the tests and shall provide all other test equipment to demonstrate
that the installation is compliant.

QCS 2010

BURHAN INTERNATIONAL

12

QCS 2010

Section 6

Part 13

Traffic Signals

Page 18

After the traffic signal and controller equipment is installed on site and after it is connected to
all its associated equipment, the Contractor shall arrange for a site acceptance test. The site
acceptance test will recheck all the points covered in the factory acceptance tests and in
addition shall include visual and electrical tests on all posts, gantries, heads, push-buttons
and cabling. The Contractor shall ensure that the area of site covered by the installation
being tested is cleared of all debris, plant and machinery. The Contractor shall be
responsible for the supply of any personnel required to conduct the site acceptance test. The
Contractor shall provide any vehicles required to conduct the site acceptance test. The
Contractor shall ensure that all equipment and devices are available to show that the
controller fully complies with the operational requirements.

Each loop and feeder configuration of the vehicle detection system shall be tested as follows
and the results given in a test certificate for the loop installation. This certificate shall include
all pertinent information for the testing. The Contractor shall submit a pro-forma certificate to
the engineer before carrying out the commissioning.
(a)

(b)

(c)

(d)
(e)

(f)

(g)

With the loop circuit disconnected from the detector, the impedance to earth of the
two loop and feeder conductors shall be measured at a test voltage of 500V DC
applied for at least one minute. This shall not be less than 10 megaohms. The two
ends of the loop circuit shall be connected together for this test
With the armouring of the feeder cable disconnected from the earth point, the
impedance to earth of the armouring shall be measured at a test voltage of 500V DC
applied for one minute. This shall not be less than 10 megaohms
With the armouring of the feeder connected to the earth point of the equipment
housing, the impedance to earth of the armouring shall be measured. This impedance
shall not be greater than 0.5 ohms
The inductance of the loop and feeder circuit shall be measured. This shall be
comparable with the theoretical value previously supplied to the Engineer
The frequency of operation of each configuration shall be measured. Where two loop
circuits share a common feeder cable their frequency of operation shall be separated
by at least 5 kHz
The Contractor shall adjust the sensitivity and presence time of each detector to the
requirements specified by the Engineer. The Contractor shall demonstrate correct
operation of the detector at the sensitivity specified
The Contractor shall ensure that an inductance change caused by vehicles in one
loop shall not induce spurious observations in any adjacent loop system.

Any loop or feeder which fails these tests shall be replaced by the Contractor at his expense.

Upon satisfactory completion of the factory acceptance and site acceptance tests, and when
the Engineer is fully satisfied that correct installation and adherence to the operational
requirements has been attained. The PWA will issue a final commissioning certificate. The
installation, or any part thereof shall not be opened to general traffic until this certificate is
received.

13.5

GUARANTEED MAINTENANCE OF TRAFFIC SIGNAL EQUIPMENT

13.5.1

General

During the initial maintenance period complete record of component failures shall be kept by
the Contractor in order to provide information on the reliability of various components.

13.5.2

Operational Maintenance

The Contractor shall provide full operational maintenance coverage for a period of 400 days
subsequent to the issuance of the final commissioning certificate.

The Contractor shall use only maintenance contractors approved for this work by the PWA.

During the maintenance period, the Contractor shall be responsible for providing coverage
for the following:

QCS 2010

BURHAN INTERNATIONAL

QCS 2010
(a)
(b)
(c)

(e)

Part 13

Traffic Signals

Page 19

Replacement or repair and installation of any failed equipment


Daily corrective maintenance
Quarterly maintenance
(i)
Check the cycle length, green time, intergreen time and all other signal timing
parameters as given in the timing chart.
(ii)
Check the timings of the different signal programmes and test the switch over
them manually and by time clock.
(iii) Test loop detectors for activation and re-tune if necessary.
(iv) Test ELCB and any other circuit breakers.
(v)
Replace any items that show significant wear and/or are operating outside of
the manufacturers tolerances.
(vi) Test operations of pedestrian push buttons
(vii) Check timing of Flashing Units
(viii) Service controller in accordance with manufacturers specifications
(ix) All signal heads, reflectors, optical lenses and backing boards shall be cleaned
(both internally and externally) in accordance with the manufacturers
specifications
Bi-annual maintenance - The following works are to be carried out in addition to those
described in section (c)
(i)
All protective earth conductors shall be inspected and tested.
(ii)
All lamp fittings and connectors shall be dismantled and cleaned.
(iii) Signal heads shall be checked for correct alignment and all brackets and
clamps tightened.
(iv) All electrical connectors are to be checked and cleaned where necessary.
Annual maintenance - The following works shall be carried out in addition to those
described in sections (c) and (d)
(i)

(ii)
(iii)
(iv)

All signal poles and gantries shall be painted and renumbered. The signal
poles and gantries shall be coated with primer, red-oxide, and two coats of
colour grey paint. The paint specification/colour shall be approved by the
Engineer.
All inspection chambers shall be cleaned properly.
Timings for all signals shall be altered as directed by the Engineer at the
beginning and end of the month of Ramadan.
Minor changes to the controllers operational configuration (Changing of
phasing /staging, green times and intergreen times) as deemed necessary by
the PWAs traffic signal engineer.

The Contractor shall ensure that personnel are available to maintain equipment such that
failed equipment shall be replaced or repaired within four hours of notification of the fault.
Where controller configuration changes are required, the Engineer shall allow a reasonable
period for the Contractor to respond.

Failed equipment shall be replaced/repaired within 4 hours of notification of the fault.

Where controller configuration changes are required, the Engineer shall allow a reasonable
period for the Contractor to respond.

13.5.3

Emergency Maintenance

In the case of accidental damage or 'knock downs' or any other equipment failure deemed to
be outside of the Contractors control, shall not be required to take responsibility for repair or
replacement. However it shall be the Contractors responsibility to provide the immediate
on-site response to a police or the PWA request.

Upon the PWA having effected a remedy to any emergency maintenance requirement, it
shall be the Contractors responsibility to ensure that all repairs or replacements have been
conducted to a standard such that no warranties become invalid.

QCS 2010

BURHAN INTERNATIONAL

(d)

Section 6

QCS 2010

Section 6

Part 13

Traffic Signals

Page 20

If the Contractor feels that any repair or replacement is not of sufficient standard to maintain
his warranty he shall notify the PWA with 14 days of any such repair or replacement having
been conducted.

13.5.4

Contractors Vehicles

The Contractor shall arrange a vehicle mounted hydraulic platform with boom and any
additional vehicle for the use of his staff whenever required throughout the maintenance
period.

The vehicles shall be provided with a flashing amber roof light array.

The contractor shall be responsible for any cost associated with the vehicles.

The hydraulic platform shall be capable of performing the required vertical and horizontal
manoeuvres safely and satisfactorily, including adequate platform capacity and boom
articulation.

The contractor shall gain approval from the Engineer as to the vehicle acceptability prior to
supplying the said vehicle.

13.5.5

Contractors Equipment

The Contractor shall be responsible for supplying any regular or special equipment or tools
required for the satisfactory undertaking of the works. In particular this shall include, but not
limited to:
(a)

(b)
(c)

Specialised commission/testing equipment for all the current traffic signal (Siemens,
Futurit, Peek and Tyco) controllers to allow Factory Acceptance Tests (FAT) and Site
Acceptance Tests (SAT).
Portable keyboard interfaces to allow interrogation and on-site programming of microprocessor signal controllers for all the traffic signal systems.
Workshop based aspect simulators to allow for Factory Acceptance Tests.

END OF PART

QCS 2010

BURHAN INTERNATIONAL

You might also like