TS
TS
TECHNICAL REQUIREMENTS
A-01 :
1.00.00.
2.00.00
PARAMETERS
2.01.00
Conveyor System
i.
ii.
2.01.01
(a)
1600 TPH
(b)
1200 TPH
(a)
2000 TPH
(b)
1760 TPH
(c)
Conveyor 9A/B
1440 TPH
Design capacity
iii.
Belt width
Minimum 1400 mm
iv.
3.2
M/sec.
Minimum number of plies for belting shall be four (4). Other details of belting
shall be as specified else where in the specification.
(c)
16 mm (Min.)
24 mm(Min.)
5 Minutes
(4.) Diameter :
(i) All drive pulleys
KODERMA TPP (2 x 500 MW)
COAL HANDLING PLANT
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 1 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(ii) All balance pulleys
Paddle Feeders
(a)
Nos. required
Four (4)
(b)
900 MTPH
(c.)
20% to 100% of
guaranteed capacity
(d)
400 mm
250 m
(e)
2.01.03
2.01.04
2.01.05
Nos. required
(b)
900 MTPH
(c.)
(d)
Nos. required
Four (4)
(b)
Type
Two (2)
No. required
(b)
Stacking
1600 TPH
(ii)
Reclaiming
1600 TPH
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 2 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(c)
(i)
Stacking
1760 TPH
(ii)
Reclaiming (Peak)
2000 TPH
(d)
10 meters
(e)
50 meters
(f)
41 meters
(-) 20 mm
One (1)
(g)
2.01.06
2.01.07
2.01.08
Wagon tippler
(a)
No. required
(b)
20 tips/hr
No. required
One (1)
(b)
58 wagons
(2)
Nozzle spacing.
500 mm
(3)
(4)
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 3 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(II)
(2)
Nozzles spacing
500mm
(3)
No of zones
One no (1)
(4)
All
(b)
(1)
Operation
(2)
Location of spray
(3)
Capacity / Pressure at
inlet of spray head
(c)
(1)
Maximum number
of nozzles operating simultaneously
Capacity & Pressure of each
spray nozzle
(2)
(d)
2.01.09
2.01.10
: 5 cub.m/hr
: 2 kg/sq.cm
(c.)
No of pumps
: 2 nos.
(d)
: 6 nos.
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 4 of 25
CLAUSE NO.
2.01.11
2.01.12
TECHNICAL REQUIREMENTS
Ventilation System
A
i.
Underground Areas
Minimum 20 supply air changes and minimum 10 exhaust air changes per hour.
ii.
Other Areas
B.
C.
Chutes
Minimum clear cross section of chute shall be 1000 mm x 1400 mm (inside both
ways).
2.01.13
Hoists
Suitable hoists as specified elsewhere shall be provided for erection & servicing of all
major equipment. The equipment to be covered shall include (but not be limited to) all
conveyor drive units, all pulleys, crushers along with drive units, in line magnetic
separators, sampling units, sump pumps, various DS/service water/potable water
pumps, gravity take up units, removal of equipment from tunnels, lifting of belt drum
at all transfer houses/crusher house/bunker floors etc.
2.01.14
All other equipment under the scope shall be suitable to the system capacities
parameters as specified above.
3.00.00
3.01.00
3.02.00
General Requirements
The instruments and controls to be furnished and erected under this specification are
as required for safe and satisfactory operation of the Coal Handling System, as
outlined under mechanical section and as specified elsewhere in the specification.
For the equipment and materials procured by the Contractor from his sub-vendors,
the Contractor shall study the specification, safety requirements, interface drawings
for such equipment and material in detail and shall coordinate his work with his sub
vendors and supply instrumentation and control to suit the actual Coal Handling
equipment.
3.02.01
Standards / Codes
All construction, installation, workmanship, design & equipment shall conform to acts,
rules & regulations of the jurisdiction within which the project is to be located, and to
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 5 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
the current edition of the following or equivalent standards or codes, in so far as they
apply :
American Iron & Steel Institute (AISI)
American Society for Mech. Engineers (ASME)
American Society for Testing & Materials (ASTM)
American Wire Gauge (AWG)
Institute of Electrical & Electronic Engrs. (IEEE)
Instrument society of America (ISA)
National Electrical Code (NEC)
National Electrical Manufacturers Association (NEMA)
United States of America standards (USAS)
Bureau of Indian Standards (BIS)
Conveyor Equipment Manufacturers Association (CEMA)
3.02.02
3.03.00
3.03.01
General Construction
Control desks/panels and annunciation system shall be as per the requirement of
electrical Section. Annunciations, indications, electrical meters and instrumentation
shall be provided as specified.
3.03.02
Design
The complete coal handling plant except for stacker-reclaimer and wagon tippler
shall be controlled from contractors PLC system as detailed elsewhere.
The Contractor shall provide a comprehensive control indication and annunciation
scheme. Contractor shall furnish block diagram and write-up on the scheme
proposed. The final scheme will be approved by the Employer. In general,
interlocking shall be achieved through feed-back signals from field equipment.
Comprehensive Annunciation and Indication scheme shall be provided such that, it
will be possible for the operator to locate and identify the fault from the face of
PLC/LVS/Control-Panel/ HMI itself. The scheme shall include the basic remote
control instrumentation, indication and annunciation requirements as per various
technical specification requirements.
However, the Contractor may offer any alternative proposal which he considers to be
equal, superior to the scheme as described in subsequent clauses below for
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 6 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
achieving reliable and trouble free operation of the plant, for consideration of the
employer.
4.00.00
4.01.00
4.02.00
(i.)
(j.)
(b)
(c)
Belt Weighers
(d)
Metal detectors
(e)
Electric hoist - wall mounted control box with pendent push button controls.
(f)
(g)
Suspended Magnet
(h)
Sump Pump
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 7 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(i)
(j)
(k)
All the above local control panels shall be accessible and located near their
respective equipment and shall be complete with all the required controls, interlocks,
annunciations etc. Further, necessary controls, indications and annunciations for all
the above equipment shall also be provided at main CHP Control Room as described
under relevant clause.
4.02.01
4.02.02
4.03.00
In addition to the remote control of various equipment, local stop push button stations
shall be provided for all equipment.
4.04.00
System Operation
4.04.01
Coal flow path selection shall be done from LCD screen/Keyboard to select
any one of the following conveying paths.
(1.)
(2.)
(3.)
(4)
(5)
(6)
Combination of above
The coal handling system operator will select any one of the above paths from OWS
located on the main control desk. The flow stream path is then selected by
positioning different flap gates/ movable discharge pulley at desired positions by
means of keyboard available at the central control desk. Once the system is in the
operation, the gates/ movable discharge pulley can not be moved from their positions
and path. Flap gates which do not come in the stream in which coal flow is taking
place, can be operated at any time. However, for the flap gates in bunker area
conveyors, it shall be possible to change flap gate position while the conveyor is in
KODERMA TPP (2 x 500 MW)
COAL HANDLING PLANT
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 8 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
operation and feeding coal using interlock bypass facility, provided that sequential
permissive are available.
The Control system will be designed for Auto & Manual operation of the conveyors
in the selected path. Auto/Manual Selection shall be done from keyboard.
Auto Mode : In the Auto mode, the conveyors and related equipment will start
sequentially when the System Start is activated. During stopping, when the System
Stop is activated, all conveyors will also stop sequentially (in the reverse sequence)
allowing time delays for clearing the belts.
Manual Mode : In Manual Mode, the operator will start the conveyor system, in the
same sequence as in Auto mode from keyboard. The operator will also stop the
conveyor system, by pressing "System stop" or individual Stop push
buttons/command from keyboard in the reverse sequence.
During Sequence Start in both Auto and Manual modes, first the required number of
hooters (3 phase induction motor type) will be energized simultaneously for a preset
time of 1 minute or so (adjustable at site) as per the program. After the preset time,
the hooters will stop and a preset time of two minutes (adjustable at site) as per
program will be allowed for the movement of the personnel and for the permissive of
the conveyor system operation. This condition will be indicated on the panel by
glowing of lamp Coal Handling Sequence Start. The starting permissive will be
available for a period of 5 minutes (Pre-programmed and adjustable in the field). In
the event the last conveyor / equipment is not started within this preset time of 5
minutes, the start command for equipment not started will be withdrawn. The system
cannot be started again unless the Sequence Start push button is again pressed
and the hooters sound again, as described before. Those conveyors and equipment,
which have already started, will continue to run.
The status indication in the graphic display against all conveyors and equipment in
the selected path/stream will start slow flickering. However, all status indications
against all flap gates / movable discharge pulley in the selected path will glow
steadily. Therefore, from the selected flow stream path of the flap gates / movable
discharge pulley, the operator will come to know the conveyors and equipment to be
started for the selected path/stream. After a conveyor/equipment is started, the
status indications against that conveyor / equipment will change to steady glow
indicating that it is running.
Graphic display status indicators associated with a particular motor/equipment shall
flicker fast in case of fault / trip.
In addition, emergency stop push button on the control desk for immediate shut down
of complete plant shall be provided.
For changeover of feed from one row of Bunkers to another row of Bunkers without
stopping of the CHP, provision shall be made for interlock bypass on the control desk
for flap gates of all conveyors in Boiler area for a preset period. If the changeover, in
above specified time, is not completed then the entire CHP shall stop.
(i)
Lamp test facility will be provided for the annunciation and mimic lamps.
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 9 of 25
CLAUSE NO.
4.05.00
TECHNICAL REQUIREMENTS
Conveyor System
(a)
Normally the movement of the paddle feeders feeding coal from the track
hopper to the reclaim conveyor shall be controlled from the paddle feeder
itself based on instructions from main control room.
(b)
The paddle feeder carriages shall move continuously to and fro along their
tracks. Suitable limit switches and anti-collision devices (both mechanical
limit switch operated and infra red type) shall be provided to enable them to
change direction of movement as soon as they come within a specified
distance of each other and at the end of travel in one direction.
(c)
The operation and stoppage of the paddle feeders shall be signaled in the
main control room of the coal handling plant. It shall be possible to stop the
paddle feeder from main control room. It shall be possible to stop the track
hopper conveyor from respective paddle feeder.
(d)
Approach of a Railway wagon rake to the plant shall be signaled (visual and
audible) in the main coal handling plant control room, as soon as the rake
come within 100 meters distances from the track hopper.
(e)
Each conveyor shall be protected against damage to the edge of the belt due
to excessive sideways movement by providing an adequate number of belt
sway switches. In addition, each conveyor shall be provided with one (1) No.
speed detection device (zero speed switch). The zero speed switches shall
be designed to sense belt speed. In case of speed of belt goes below 85% of
rated speed, it shall trip the conveyor.
(f)
All the conveyors shall be protected from reverse running due to power failure
by providing mechanical or electrical locking system.
(g)
(2.)
In case of stacking of coal in stock yard, start from yard conveyor and
end up with reclaim conveyors below track hopper/wagon tippler
hopper. However, for yard conveyor to start, the stacker-cumreclaimer shall be in operation.
(3.)
(4.)
(5.)
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 10 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(h)
(i)
Any individual equipment (belt conveyor etc.) should not be allowed to start
unless the equipment immediately following the same in the direction of flow of
material is already in operation.
(j)
Stop/tripping of any equipment from running condition shall trip all preceding
equipment in the system, except crushers but shall not effect succeeding ones
which shall continue to operate.
(k)
(l)
(m)
(n)
Suitable indication for paddle wheel rpm shall be provided on the local panels.
Manual facility to control the cutting rate of paddle feeder shall also be
provided.
(o)
Motors shall start only when the brake/rail clamp if-provided, is in not applied
condition. This signal shall be obtained from limit switch provided for that
purpose.
(p)
(q)
Once a conveyor trips, flap gate directing coal from this conveyor shall change
over its position with a time delay and shall come back to the original position
again. This is to prevent jamming of gate.
(r)
(s)
It shall be possible to trip track hopper conveyor, bunker conveyor and yard
conveyor from paddle feeder, mobile tripper and stacker / reclaimers
respectively.
(t)
Where ever scoop type coupling provided for HT motors, the coasting time of
respective conveyor, thrustor brake, actuator selection and the chute size shall
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 11 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
be so selected such that there is no spillage of coal from any down stream
conveyors during next start. If required necessary fly wheel may also be
provided in the down stream Conveyor to restrict the speed.
4.06.00
(u)
(v)
Control system shall envisage blending of coal. For this blending can be
considered by suitably mixing coal from reclaim path and direct path are
mixing of coal from two reclaimers.
(w)
Coal flow rate and coal integrator readings of belt scales on track hopper
conveyors shall be repeated at stacker reclaimers & wagon tippler control
room for auto blending of coal.
Interlocking
(a.)
(1.)
All conveyors
(2.)
(3)
(4)
(5)
Metal detectors
(6)
(7)
Crushers
(8)
Paddle Feeders
(9)
Belt scale
(10)
Mobile Trippers
(11)
Stacker/Reclaimer
(12)
Wagon tipplers
(b.)
The following equipment will not come under interlock of the conveyor
scheme.
(1.)
(2.)
Ventilation systems
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 12 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(c.)
All conveyors and equipment will have local push button stations each
consisting of :
(1.)
Pos - I, Pos - II & stop button for flap gate and R & P gate
(2.)
(d.)
(e.)
(f.)
(g.)
(h.)
The following are the various safety interlocks for the conveyors and other
equipment. This list is indicative only and the Contractor shall develop a
comprehensive interlocking scheme.
Conveyors
a).
b).
c).
d).
e).
f).
g).
h).
i).
Paddle Feeders
a).
b).
c).
d).
e).
Travelling Tripper:
a).
b).
c).
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 13 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
Magnetic Separators / Metal Detectors / Suspended Magnets
a).
b).
c).
d).
b).
c).
Ring Granulator
a).
b).
c).
d).
e).
4.06.01
4.06.02
(d.) Belt sway switch operated for each conveyor (individual switch indication on
CRT).
(e.) Pull cord switch operated for each conveyor (Individual switches indication on
CRT).
(f.)
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 14 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(h.) Travelling tripper position.
(i.)
Crusher ON
(j.)
(k.)
(l.)
Annunciation System:
PLC/Control desk shall be provided with adequate number of facia type annunciation
windows operating through PLC for the following audio-visual fault annunciation
purposes. Wherever group annunciation is provided, alarm status of individual
equipment shall be provided on OWS.
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
(j)
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 15 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(k)
HT motor bearing/ winding temp. high alarm (group) and trip (group)
(l)
(o)
(p)
(q)
(r)
(s)
(t)
(u)
(v)
(w)
(x)
(i)
(ii)
(y)
(z)
(ab) Dust suppression/service water system faults and trips (system wise)
(ac) Water level low in tanks (group)
(ad) Oil temperature of fluid coupling high
(ae) Crusher low speed & crusher bearing temperature high.
(af)
(ag)
For identification of the fault for a particular conveyor or equipment, status indication
against that conveyor / equipment in the mimic will start fast flickering and the
annunciation window will be blinking against that particular fault. In addition, a buzzer
(alarm) will start sounding. After acknowledgement of the fault, the buzzer will stop,
but the fast flickering on the mimic and the steady glow on the annunciation window
will continue until the fault is cleared and the Reset push button is pressed. When the
fault is cleared and the Reset push button is pressed, the status indication of that
KODERMA TPP (2 x 500 MW)
COAL HANDLING PLANT
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 16 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
conveyor / equipment on the mimic will start slow blinking if it is on selected path
otherwise it will go off and the steady glow in the annunciation window will go off.
However, pressing of the Reset push button before clearance of the fault, will have
no effect on the lamps.
At the time of a fault, the faulty conveyor / equipment, as well as the preceding
conveyors / equipment in the interlock sequence, will stop except H.T. motors for
which only scoop coupling will be disengaged and motor will continue to run for
process fault. In case of motor fault, H.T. motor will trip but the succeeding conveyors
/ equipment will continue to run. The status indication against the preceding
conveyors / equipment will start slow blinking while the faulty conveyor / equipment
will be fast blinking.
Start command shall not be initiated unless reset button in pressed after clearance of
fault.
The sequence of operation of the annunciation system shall be as follows :Condition
Normal :
Fault
Press
Accept. PB.
Press Reset
PB (When
fault is
cleared):
Status
Ann. Window
Off.
Status indication
Steady glow
Buzzer
Off.
Ann. Window
Blinking.
Status indication
Fast blinking
Buzzer
Sounding.
Ann. Window
Steady glow.
Status indication
Fast blinking
Buzzer
Off.
Ann. Window
Off.
Status indication
i)
Steady
blinking
selected path)
ii)
Buzzer
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
(if
on
Off
Sub-Section - IIIA-01
CHP
Page 17 of 25
CLAUSE NO.
4.08.00
TECHNICAL REQUIREMENTS
Dust Suppression System
(a.) Conveyors / Equipment
(1.) It shall be possible to spray the water on to coal stream only when
corresponding conveyors/equipment are running with material at spray
application points.
(2.) If a running pump trips stand-by pump shall start automatically. It shall be
possible to select any of the pumps as auto standby from main CHP
control room.
(3.) Pump/pumps shall trip with a time delay, if discharge valves fail to open.
Suitable pressure/flow switch shall be provided to sense this condition.
(4.) Pumps shall trip in case of low level of water in tank.
(5.) All feeding pumps to tank shall trip in case of high pressure & no flow by
pressure switch.
(6.) Motorized inlet valve to D.S. tanks shall close in case of High-High level &
open in case of low level.
(7.) All the controls shall be through PLC.
(b.) Wagon unloading (At Track Hopper and wagon tippler)
(1.) System shall be operated from local control panel. However, the controls
shall be through PLC.
(2.) Dust suppression system shall be provided to cover the Track Hopper in
minimum one & maximum twenty sections. Push button for each section
shall be located on each side of track hopper at convenient location.
(3.) Pumps shall be started manually or from PLC. If any of the pump/pumps
trips, stand-by pump/pumps shall start automatically. It shall be possible
to select any of the pumps as auto stand - by.
(4.) Pumps shall trip in case of low level of water in tank.
(5.) Following annunciations shall be provided at local control panel.
(i) Motor electrical protection operated (Group)
(ii) Discharge water pressure low (Group)
(iii) Water level low in tank (Individual)
(6.) Following individual indications shall be provided at local control panel.
Motor ON/OFF/TRIP
Discharge pressure healthy
Water level high in tank.
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 18 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(c.)
(d)
(e)
4.09.00
Following individual inputs shall be provided to P system from all the above
dust suppression systems (except trolley mounted system for paddle feeders)
for alarms/indications.
(i.)
Motor ON/OFF/TRIP
(ii.)
(iii.)
(iv.)
Metal detectors
(a)
It shall be possible to start the conveyors only after energizing the metal
detector and Metal detector reset condition. Once the metal is detected, the
corresponding conveyor shall trip.
It shall be possible to restart the conveyors, after local resetting of metal
detector and putting back the marker bag in position. Metal detector ON/OFF
push buttons shall be provided in main control room also.
(b)
(c)
Metal detector ON
(2)
Metal detected
(3)
(4)
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 19 of 25
CLAUSE NO.
4.10.00
TECHNICAL REQUIREMENTS
Sump Pumps
(a)
Sump Pumps shall start and stop by the level switches in the sump
automatically. Further manual override start / stop push button shall be
provided locally on ground level.
(b)
(c)
If the sump level continues to be high even after the first pump is under
operation second pump shall start automatically.
(d)
The following indications for sump pumps shall be provided on local Control
Panel.
(1.) Water level high
(2.) Motor ON/OFF/TRIP.
4.11.00
Coal Sampling Unit shall be controlled through main coal handling plant PLC.
Controls and interlocks for proper material flow shall be provided similar to
conveyor system. Mimic shall be provided in the Operator Work Station (OWS)
at main CHP control room.
(b)
Only one start/stop push button along with selector switches for various modes
of operation of coal sampling system shall be provided for automatic operation
of complete coal sampling system. This control facility shall be provided at main
CHP control desk as well as locally. In any case, local push button stations
shall be provided for all individual equipment of coal sampling system near the
equipment.
(c)
All necessary automatic controls shall be provided for meeting the requirements
of ASTM-D-2234.
(d)
(e)
(f)
There shall be protection in the primary coal sampler to trip the conveyor belt in
case primary sampler falls on running conveyor due to coupling failure etc.
Individual motor ON/OFF/TRIP indications shall be provided at main CHP
control room.
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 20 of 25
CLAUSE NO.
4.12.00
TECHNICAL REQUIREMENTS
Paddle Feeders
Paddle feeders shall be controlled from the local control panel suitably mounted on
the unit. Requirement of operation as described else where in the specification shall
be complied with. Following indications shall also be provided on the local control
panel:
(a.) Motor ON/OFF
(b.) Motor O/L protection operated
(c.)
Mobile Trippers
(a)
Mobile tripper unit shall be locally controlled from the operating platform suitably
located with the unit as per instructions given from main CHP control room.
(b)
(c)
Travel drive motor shall start only when brake and rail clamps are in
disengaged condition.
(d)
(e)
When the last bunker is full, it shall not be possible to change over the tripper
flap gate from bunker feeding position to last bunker feeding position.
(f)
As soon as the bunker conveyor trips, tripper flap gate shall change over its
position after a time lag.
(g)
Two nos. emergency stop button one on each side shall be provided on tripper
to stop the machine at any position. The control unit on tripper shall be provided
with start / stop push button and indication lamp for travel / gate. The tripper
brakes and rail clamps shall be energised (and released) when the tripper
motors are ON and the brakes will be applied when the travel motors are OFF.
Two travel limit switches shall be provided at either end of tripper carriage for
limiting the travel drive between two ends of the track. The first one shall be
normal limit and the second one for over travel limit. In addition to above,
position indication for bunker position of tripper will be provided in Main control
room. Necessary position encoders/ limit switches shall be provided. Over
speed protection for protection against dragging shall be provided.
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 21 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(h)
4.14.00
(i)
Indication of tripper flap gate positions shall be given in the main CHP control
room.
(j)
It shall be possible for operator to manually trip the coal feeding eqpt. viz.
paddle feeders or stacker / reclaimers from the tripper.
(k)
Chute blockage switch shall be provided at each leg of chute and shall trip the
tripper conveyor in case of blockage.
4.15.00
Belt Weighers
Each belt scale shall give output to PLC for display of flow rate indicator and totalizer
on CRT and print out at main CHP control room. 4 Nos. flow rate indicators, one for
each paddle feeder shall also be furnished to display the instantaneous TPH on
respective paddle feeder using the output of belt scale on Conveyors. Each belt scale
shall also have rate flow indicator and totaliser mounted near the unit. Belt weighers
shall also be provided on Stacker-Reclaimer as described elsewhere in the
specification.
4.16.00
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 22 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(e.) Oil temperature high
4.17.00
(b)
(c)
4.18.00
Stacker/ Reclaimer
(a)
The Stacker cum reclaimer shall be controlled from the operators cabin in the
machine through PLC system of stacker cum reclaimer.
(b)
(c)
(d)
At the end of Slew Pass Stacker - Cum - reclaimer drive shall advance
automatically to required depth of cut. Depth of cut shall be controlled through
the setting of power transducer on Bucket wheel. It shall also be possible to set
the depth of cut through a separate setting knob in operator cabin.
(e)
All controls shall be based on feed back signals from field equipment.
(f)
(g)
(h)
For all drives, zero speed shall be ensured before affecting reversal, by
providing suitable speed sensing device.
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 23 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(i)
Motors shall start on when the Brake and/or rail clamp, is in Not Applied
condition. This signal shall be obtained from limit switch provided for that
purpose.
(j)
If wind velocity is high, it shall cut off power supply to stacker - cum-reclaimer
with a time delay, after giving sufficient time to operator to bring the Boom in
minimum wind pressure direction/ position.
(k)
(l)
Manual Remote
Manual controls facility shall also be provided in control desk and keyboard
(operators cabin) as below :
(1.) Individual controls shall be provided for each equipment.
(2.) Manual slew speed variation and depth of cut setting facilities shall be
provided.
(o)
(2.)
(3.)
(4.)
(5.)
Chute plugged
(6.)
(7.)
(8.)
(9.)
(10.)
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 24 of 25
CLAUSE NO.
TECHNICAL REQUIREMENTS
(p)
(11.)
(12.)
LT breaker tripped
(13.)
HT switch tripped
(14.)
(15.)
(2.)
(3.)
(q)
Ammeters shall be provided in control desk for all the motors rated 30 kW and
above.
(r)
(s)
(t)
(u)
It shall be possible to trip stacker/ reclaimer from main CHP control room also.
(v)
A push button shall be provided in operators cabin to trip the yard conveyor.
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID. DOC. NO.:CS-9451-156-2
Sub-Section - IIIA-01
CHP
Page 25 of 25