Piling WorksTender
Piling WorksTender
TENDER
INDEX
SL.
NO.
CONTENT
SECTION -1
1.1
1-4
1.2
1-2
1.3
BG FOR EMD
1-2
SECTION -2
2.1
1-55
2.2
1-2
2.3
1-3
3.0
TECHNICAL SPECIFICATIONS
1-14
4.0
1-5
PAGE NO
1.0
Item rate bids are invited by C.O.O.., IIT Madras Research Park from contractors who
satisfy the criteria mentioned in the RFQ documents for the work of Piling Works for
Proposed New Buildings of IIT Madras Research Park at, Kanagam Road,
Taramani, Chennai.
2.0
Agreement shall be drawn with the successful bidder on the prescribed form.
3.0
The time allowed for carrying out the work is 155 Days which will be reckoned from
the 7th day after the date of written orders to commence the work or from the first day of
handing over of the site, whichever is later, in accordance with the milestones, if any,
indicated in the Bid Documents
4.0
5.0
If the bidder withdraws his bid during the period of Bid Validity;
5.4.2 Makes any modification in the terms and conditions of the Bid which is
not acceptable to the Employer.
Page 1 of 4
Section-1.1
5.4.3 In case of successful bidder :5.4.3.1 Fails to submit Performance Security as per the Clause 22 of
General Conditions of Contract.
5.4.3.2 Fails to mobilise for the execution of the Work within stipulated
period mentioned in Contract Data.
5.4.3.3 Fails to sign formal Agreement within 30 days from the date of
issue of Letter of Acceptance.
6.0
1) [email protected]
2) [email protected]
The minutes of the Pre bid meeting will be circulated to all who have attended the
meeting. It will also be published in the web site of IITMRP. Not attending the pre bid
meeting will not be a disqualification for processing the tender.
7.0
Page 2 of 4
Section-1.1
8.0
All the three envelopes shall be placed in another envelope and sealed. The name of the
work and date of opening may be super scribed on the envelope and submitted to
Mr. Rajendra Mootha,
C. O.O.,
IIT Madras Research Park
No. 1FA, 1st Floor, Kanagam Road
Taramani, Chennai 600 113
up to 4.00 P.M. on 15 May 2013.
9.0
Bidders are advised to inspect and examine the site and its surroundings and satisfy
themselves before submitting their bids as to the nature of the ground and sub-soil, the
form and nature of the site, the means of access to the site, the accommodation they
may require and in general shall themselves obtain all necessary information as to risks,
contingencies and other circumstances which may influence or affect their bid. A bidder
shall be deemed to have full knowledge of the site whether he inspects it or not and no
claims / extra charges consequent on any misunderstanding or otherwise shall be
allowed.
10.0
Submission of a bid by a bidder implies that he has read this notice and all other contract
documents and has made himself aware of the scope and specifications of the work to
be carried out and of conditions and rates at which stores, tools and plant, etc. will be
issued to him by the Client and local conditions and other factors having a bearing on
the execution of the work.
11.0
The employer does not bind itself to accept the lowest or any other bid and reserves to
itself the right to reject any or all the bids received without the assignment of any reason.
The bidders shall bear all the cost of preparation of the bid and all expenses in
connection thereof and shall not be entitled for any compensation in the event of non
acceptance of the bid including the employer not proceeding with the Project.
11.0
All bids in which any of the prescribed condition(s) is not fulfilled or any condition
including that of conditional rebate is put forth by the bidder, shall be liable to be
summarily rejected.
12.0
Canvassing whether directly or indirectly, in connection with bids is strictly prohibited and
the bids submitted by the contractors who resort to canvassing will be liable to rejection.
13.0
The employer reserves to himself the right of accepting the whole or any part of the bid
and the bidder shall be bound to perform the same at the rates quoted.
14.0
The bid for the works shall remain open for acceptance for a period of 60 (Sixty) days
from the date of submission of the bid. If so requested by the employer the validity of the
Page 3 of 4
Section-1.1
bid shall be extended for a further period of 30 (Thirty) days at the same and conditions
of original submission.
15.0
15.1.0 If the bidder is an individual , he/she should sign above his / her type written
name and the current address.
15.1.1 If the bidder is a proprietary firm, the Proprietor should sign above his type
written name and full name of his firm with current address.
15.1.2 If the bidder is a firm in partnership , the document should be signed by all the
partners of the firm above their full type written name and current addresses.
Alternatively the document should be signed a Partner holding Power of Attorney
for the firm and in this case a certified copy of the Power of Attorney should
accompany the Documents. In both cases a certified copy of the Partnership
Deed and current address of all the partners of the firms should be furnished.
15.1.3 If the bidder is a limited Company or a Corporation, the Document shall be
signed by a duly authorized person holding Power of Attorney for signing the
Documents accompanied by a copy of the Power of Attorney.
16.0
The bidder shall fill in rates and prices for all items of work indicated in the Bill of
Quantities. Corrections, if any, shall be made by crossing out, initialing and rewriting.
17.0
Any error in description , quantity or any omission here from shall not vitiate the contract
or release the contractor from the execution of the whole or any part of the work
comprised herein according to drawings and specifications or from any of his obligation
under the contract.
18.0
Correction of Errors
18.1.0 This being an item rate tender, only the rates quoted shall be considered.
18.1.1 Any tender containing percentage below / above the rates quoted is liable to be
rejected.
18.1.2. Rates quoted by the bidder shall be accurately filled in so that there is no
discrepancy in the rate written in figures and words. However if a discrepancy is
Page 4 of 4
Section-1.1
found, the rates which correspond with the amount worked out by the bidder shall
unless otherwise proved, be taken as correct.
18.1.3 If the amount on an item is not worked out by the bidder or it does not
correspond with the rates written either in figures or in words, then the rates
quoted in words shall be taken as correct.
18.1.4 Where the rates quoted by the bidder in figures and in words tally but the amount
is not worked out correctly the rates quoted by the bidder unless otherwise
proved, be taken as correct and not the amount.
19.0
Bidders shall submit the documents mentioned below along with the tender :19.1
19.2
Program for execution of the work in the form of PERT chart listing all the
activities with definable milestones taking into account the overall time schedule/
milestones and the scope of the work.
19.3
19.4
19.5
20.0
Bidder shall treat the bid documents, drawings and other records connected with the
work as confidential documents and shall not communicate information derived therefrom to any person other than a person to whom bidder is authorized to communicate
the same.
21.0
This Notice Inviting Bid (NIB) shall form a part of the Contract document
In case of any query please contact Mr. Rajendra Mootha at the telephone /email
mentioned in this document
Page 5 of 4
Section-1.1
Subject:
Dear Sir,
1. Being duly authorized to represent and act on behalf of
_______________________________________________(hereinafter called the bidder )
and having reviewed and fully understood all information provided in this bid document, the
undersigned hereby submit our proposal as a contractor for the execution of the work for
which the bid proposal is invited.
2. Attached to this letter is the bid proposal comprising the following; (Bidder to indicate the
content of Bid proposal)
The Employer and/ or their PMC may contact the following person(s) in connection with
the bid.
Name:
Address:
Phone No.:
E-mail:
3. This bid proposal is made in full understanding that bidder may be subjected to verification
of all information by the Employer.
We understand and acknowledge that the Employer reserves the right to:
Bid Proposal Form
Page 1 of 2
Section 1.2
a.
Reject any or all bid proposals without assigning any reason there for, and the
Employer shall not be liable for any compensation / claims from any of bidder
whatsoever for such action.
The undersigned declare that to the best of their knowledge and belief the statements made
and the information provided in the Bid Proposal are complete, true and correct in every detail.
Yours faithfully,
Authorised Signatory:
Name and Title of Signatory:
Name of bidder: ..
Address: ..
Contact No.: .. Mobile No.:.
Date:
Page 2 of 2
Section 1.2
AND WHEREAS it has been stipulated in the said Bid documents that the Bidder shall furnish
IIT Madras Research Park Earnest Money amounting to Rs 5,00,000. (Rupees Five Lakhs
only) and this Earnest Money may be furnished in the form of Bank Guarantee issued by a
Nationalized / Scheduled bank for the sum specified therein.
1.
2.
3.
We, the said bank further undertake to pay IIT Madras Research Park the money so
demanded notwithstanding any dispute or disputes raised by the contractor(s) in any suit
or proceeding pending before any court or Tribunal relating thereto, our liability under this
present being absolute and unequivocal.
4.
The Payment so made by us under this bond shall be a valid discharge of our liability for
payment there under and the Contractor(s) shall have no claim against us for making such
payment.
5.
We, . (indicate the name of the Bank) further agree that the
guarantee herein contained shall remain in full force and effect till the COO on behalf of
IIT Madras Research Park certify that the terms and conditions of the said tender have
been fully and properly carried out by the said Contractor(s) and accordingly discharges
this guarantee.
BG for EMD
Page 1 of 2
Section 1.3
6. This guarantee will not be discharged due to the change in the constitution of the Bank or
of the Contractor(s).
7.
We, . (indicate the name of the Bank) undertake not to revoke this
guarantee except with the previous consent of IIT Madras Research Park in writing.
9. Notwithstanding anything mentioned above, our liability against this guarantee is restricted
to Rs.5,00,000 ( Rupees Five Lakhs only) and unless a claim in writing is lodged with us
within six months of the date of expiry or the extended date of expiry of this guarantee all
our liabilities under this guarantee shall stand discharged.
BG for EMD
Page 2 of 2
Section 1.3
SECTION 2
Section 2
GCC
INDEX
Sl. No.
Description
1.0
DEFINITIONS
2.0
3.0
4.0
5.0
REPRESENTATION ON WORKS
6.0
7.0
8.0
9.0
DISCLOSURE OF RELATIONSHIP
10.0
11.0
ILLEGAL GRATIFICATION
12.0
13.0
14.0
15.0
CONTRACTORS UNDERSTANDING
16.0
ADVANCES
17.0
18.0
INDEMNITY BY EMPLOYER
19.0
20.0
INDEMNITY BY CONTRACTOR
21.0
SECURITY DEPOSIT
22.0
PERFORMANCE SECURITY
23.0
INSURANCE
24.0
EXCEPTED RISKS
25.0
26.0
POSSESSION OF SITE
27.0
28.0
29.0
COMMENCEMENT OF WORK
30.0
31.0
Page 1 of 2
Section- 2.2
32.0
SETTING OUT
33.0
TEMPORARY WORKS
34.0
35.0
EXCAVATED MATERIALS
36.0
37.0
LABOUR CAMP
38.0
39.0
ENGAGEMENT OF LABOUR
40.0
41.0
CARE OF WORKS
42.0
EXTRAORDINARY TRAFFIC
43.0
44.0
SAFETY PROVISIONS
45.0
46.0
47.0
48.0
49.0
50.0
51.0
52.0
53.0
54.0
COVERING UP OF WORK
55.0
MODIFICATIONS TO WORK
56.0
57.0
58.0
PRICE VARIATION
59.0
60.0
ON ACCOUNT PAYMENT
61.0
ROUNDING OFF
62.0
PRODUCTION OF VOUCHERS
63.0
64.0
FORCE MAJEURE
65.0
Page 2 of 2
Section- 2.2
66.0
SUSPENSION OF WORKS
67.0
68.0
69.0
70.0
71.0
72.0
73.0
URGENT REPAIRS
74.0
75.0
76.0
CLAIMS
77.0
78.0
79.0
Page 3 of 2
Section- 2.2
DEFINITIONS
In the Contract, as hereinafter defined, the following words and expressions shall
have the meanings hereby assigned to them, except where the context requires
otherwise.
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
Page 4 of 2
Section- 2.2
m.
n.
o.
p.
q.
r.
s.
t.
u.
v.
w.
x.
2.0
Page 5 of 2
Section- 2.2
be part thereof and shall not be taken into consideration in the interpretation
or construction thereof or of the Contract.
2.2
Interpretation
Words importing persons or parties shall include firms, corporations and any
organization having legal capacity.
3.0
4.0
4.2
ii.
The PMC may, from time to time, in writing delegate to the PMCs
Representative, any of the powers and authorities vested in the PMC,
and shall furnish to the Contractor and to the Employer, a copy of all
such written delegations of powers and authorities. Any written
instruction, decision or approval given by the PMCs Representative to
the Contractor within the terms of such delegation, but not otherwise,
shall bind the Contractor and the Employer, as though it had been given
by the PMC, provided always as follows:
a.
Page 6 of 2
Section- 2.2
4.3
4.4
Instructions in Writing
Instructions given by the PMC shall be in writing, provided that if for any
reason the PMC considers it necessary to give any such instruction orally, the
Contractor shall comply with such instructions. Confirmation in writing of such
oral instruction given by the PMC, whether before or after carrying out of the
instruction shall be deemed to be an instruction within the meaning of this
sub-clause.
5.0
REPRESENTATION ON WORKS
The Contractor, shall, when he is not in a position to be present at the site of work
place, keep responsible agent(s)/representatives there, during all working hours, who
shall, on receiving reasonable notice, present himself/ themselves to the PMC,
PMCs Representative or their Assistants. The instructions and orders given by them
to the Contractors Agent(s) shall be deemed to have the same force, as if they had
been given to the Contractor. Before absenting himself, the Contractor should furnish
the name and address of his agent(s), for the purpose of this clause. Failure on part
of the Contractor to comply with these provisions shall constitute a breach of Contract
leading to action under Clause 73.0.
6.0
Communications to be in writing
All notices, communications, references and complaints by either party to the
Contract shall be in writing and no notice, communication, reference or
complaint not in writing, shall be recognized or be binding.
6.2
Language of Contract
The Contract document shall be drawn up in English. Supporting documents
or literature may be in any other language, but an appropriate English
Page 7 of 2
Section- 2.2
7.0
7.2
Co-relation of documents
The Contract documents are complementary and what is called for by any
one of them shall be as binding as if called for by all them.
7.3
Ambiguities or discrepancies
In case of ambiguities or discrepancies, the same shall be clarified and
adjusted by the PMC who shall thereupon issue to the Contractor instructions
thereon and in such event, the priority of the documents forming the Contract
shall be as follows: a.The Agreement
b.The Letter of Acceptance
c. The Letter of Negotiations
d.The Bill of Quantities
e.The Specifications.
f. The Special Conditions of Contract.
g.The Tender Drawings.
h.The General Conditions of Contract.
8.0
9.0
DISCLOSURE OF RELATIONSHIP
If the Contractor or any partner of the Contractor or Director of the Contractors
company, is closely related to any of the officers of the Employer or the PMC, or
alternatively, if any close relative of an officer of the Employer or the PMC has
Page 8 of 2
Section- 2.2
financial interest/ stake in the Contactors firm, the same shall be disclosed by the
Contractor at the time of filling his bid. Any failure to disclose the interest involved,
shall entitle the Employer to rescind the Contract, without payment of any
compensation to the Contractor.
10.0
b.
a.
The Contractor shall have no claim to compensation for any loss sustained by
him by reason of his having purchased or procured any materials or entered
into any commitment or made any advance on account of the Contract and
the Contractor shall not be entitled to recover or be paid any sum for any
work thereto or actually performed under the Contract, unless and until the
PMC shall have certified the performance of such work and the value payable
in respect thereof and the Contractor shall only be entitled to be paid the
value so certified.
b.
Page 9 of 2
Section- 2.2
11.0
ILLEGAL GRATIFICATION
11.1
11.2
11.3
11.4
12.0
The Contractor shall comply with the provisions of the Contract, with due care
and diligence, and execute and maintain the works and provide all labour
therefore, and be responsible for supervision of all works, structural plans and
other things whether of temporary or permanent nature required for such
execution and maintenance in so far as necessary for providing these, as is
specified or as is reasonably inferred from the Contract. The Contractor shall
take full responsibility for the adequacy, stability and safety at site of all
works, materials and methods of construction, provided, however, that the
Contractor shall not be responsible except as may be expressly provided for
Page 10 of 2
Section- 2.2
13.0
The Contractor shall be liable for the consequences that may arise due to a
mistake in design carried out and drawing issued by the Contractor
/Contractor's sub-contractor. Checking and approval by the Employer of the
design/drawing prepared by the Contractor/ Contractor's sub-contractor shall
not compromise or reduce the liability of the Contractor.
Reasonable opportunity
The Contractor shall, in accordance with the requirements of the PMC,
cooperate with and afford all reasonable opportunities for carrying out their
work to any other contractors employed by the Employer and their workmen
and to the workmen of the Employer and the workmen of any other duly
constituted authority, who may be employed in the execution on or near the
Site, of any work not included in the Contract or of any contract which the
Employer may enter into in connection with or ancillary to the Works.
The Contractor shall, on the written request of the PMC or the PMCs
Representative, make available to any such other contractor or to the
Employer or any such authority, any roads or ways for the maintenance of
which the Contractor is responsible, for which no additional payment shall be
made by the Employer. The Contractor shall also permit the use by any such
of the Contractors scaffolding or other plant on the Site, or provide any other
service of whatsoever nature at the request of the Employer. The Employer
shall pay to the Contractor in respect of such use or service such sum or
sums as shall, in the opinion of the PMC, be reasonable. The decision of the
PMC as to the sum payable shall be final and binding.
13.2
14.0
Assignment of Contract
The Contractor shall not assign the Contract or any part thereof, or any
benefit or interest therein or there under.
14.2
Subcontracting
i.
The Contractor shall not subcontract the whole of the Works. Except
where otherwise provided in the Contract, the Contractor shall not
subcontract any part of the works without the prior consent of the PMC.
Any such consent shall not relieve the Contractor from any liability or
Page 11 of 2
Section- 2.2
obligation under the Contract and he shall be responsible for the acts,
defaults and neglects of any Sub-Contractor, his agents, servants or
workmen as fully as if they were the acts, defaults or neglects of the
Contractor, his agents, servants or workmen.
ii. Provided that the Contractor shall not be required to obtain such consent
for :
a. the provision of labour, or
b. the purchase of materials which are in accordance with the standards
specified in the Contract, or
c. the subcontracting of any part of the Works for which the SubContractor is named in the Contract.
14.3
14.4
14.5
Explanation on Sub-contracting
Provided always that execution of the details of the works by petty
contractors, or on piece work basis, under the personal supervision of the
Contractor or his agent, shall not be deemed to be sub-contracting under this
clause.
14.6
15.0
CONTRACTORS UNDERSTANDING
15.1
The Contractor shall be deemed to have inspected and examined the Site
and its surroundings and information available in connection therewith and to
have satisfied himself, so far as is practicable, before submitting his Bid, as to
the form and nature thereof, including the sub-surface conditions, the
hydrological and climatic conditions, the extent and nature of work and
materials necessary for the completion of the Works, the means of access to
the Site and the accommodation he may require and, in general, shall be
deemed to have obtained all necessary information, subject as above
Page 12 of 2
Section- 2.2
16.0
ADVANCES
16.1
Types of advances
Subject to any conditions given herein, the Contractor may avail of the
following advances for the execution of the Works:
a.
b.
16.2
Mobilization advance
Advance against materials at site.
Mobilisation Advance
16.2.1 For completing preliminaries such as construction of site offices,
hiring of accommodation, , arranging electricity and water supply and
movement of staff, labour plant and machinery, an advance specified
in the Contract Data and as required by the Contractor shall be
payable against a Bank Guarantee of a Scheduled Bank approved by
the Employer for an equivalent amount of advance in the proforma
acceptable to the Employer.
16.2.2 Such advance shall be given only after the Contractor has submitted
the Performance Security and signed the Contract Agreement. .
16.4
16.5
Page 13 of 2
Section- 2.2
17.0
17.2
18.0
INDEMNITY BY EMPLOYER
The Employer shall indemnify the Contractor against all claims, proceedings,
damages, costs, charges and expenses in respect of the use or occupation of the
land by the works or part thereof.
19.0
20.0
INDEMNITY BY CONTRACTOR
Page 14 of 2
Section- 2.2
20.1
20.2
21.0
SECURITY DEPOSIT
21.1
The Contractor shall permit Employer at the time of making any payment to
him for work done under the Contract to deduct a sum at the rate of 5 % of
the gross amount of each running bill till the sum along with the sum already
deposited as Earnest Money, will amount to Security Deposit of 5% of the
Contract value of the work. Such deductions will be made and held by the
Employer by way of Security Deposit unless he/they has/have deposited the
amount of Security at the rate mentioned above in cash or in the form of Bank
Guarantee/Government Securities or fixed deposit receipts. In case a fixed
deposit receipt of any Bank is furnished by the Contractor to the Employer as
part of the Security Deposit and the Bank is unable to make payment against
the said fixed deposit, the loss caused thereby shall fall on the Contractor and
the Contractor shall forthwith on demand furnish additional security to the
Employer to make good the deficit. Earnest money shall be adjusted first in
the security deposit and further recovery of security deposit shall be
commence only when the up to date amount of security deposit starts
exceeding the earnest money.
21.2
Page 15 of 2
Section- 2.2
22.0
PERFORMANCE SECURITY
22.1
INSURANCE
23.1
Requirements
Page 16 of 2
Section- 2.2
23.3
Currency of Policy
The policies shall remain in force throughout the period of execution of the
Works and till the satisfactory completion of the Defects Liability Period. The
Contractor shall, submit to the Employer copies of the Policies within 10 days
from the date of issue of the Letter of Acceptance and whenever called upon,
produce to the PMC or his representative the various insurance policies
obtained by him as also the receipts of premium paid by him to ensure that
the policies indeed continue to be in force. If the Contractor fails to effect or
keep in force or provide adequate cover in the Insurance policies mentioned
in Sub-clause 23.1 or any other insurance he might be required to effect
under the Contract, then in such cases, the Employer may effect and keep in
force any such insurance or further insurance and the cost and expenses
incurred by him in this regard shall be deductible from payments due to the
Contractor or from the Contractors Performance Security.
24.0
EXCEPTED RISKS
The Excepted Risks are war, hostilities (whether war be declared or not), invasion,
act of foreign enemies, rebellion, revolution, insurrection or military or usurped power,
civil war, unless solely restricted to employees of the Contractor or of his subcontractors and arising from the conduct of the Works, riot, commotion or disorder,
loss or damage due to use or occupation by the Employer of any part of the
Permanent Works, loss or damage caused solely due to the PMC design of the
Page 17 of 2
Section- 2.2
Works, radiations or contaminations by radio activity from any nuclear fuel or from
any nuclear waste from the combustion of nuclear fuel, radioactive toxic explosive, or
other hazardous properties of any explosive, nuclear assembly or nuclear component
thereof, pressure waves caused by aircraft or other aerial devices traveling at sonic
or supersonic speeds, or any such operations of the forces of nature as an
experienced contractor could not foresee, or reasonably make provision for or insure
against all of which are herein collectively referred to as the Excepted Risks.
25.0
26.0
POSSESSION OF SITE
Save insofar as the Contract may prescribe, the extent of portion of the Site of which
the Contractor is to be given possession from time to time, and the order in which
such portions shall be made available to him and, subject to any requirement in the
Contract as to the order in which the Works shall be executed, the Employer will, on
the PMCs written order to commence the Works, give to the Contractor, possession
of so much of the Site, as may be required to enable the Contractor to commence
and proceed with the execution of the Works in accordance with the programme
referred to in Clause 25.0 hereof, if any, and otherwise in accordance with such
reasonable proposals of the Contractor as he shall, by written notice to the PMC,
make. The Employer will, from time to time as the Works proceed, give to the
Contractor possession of such further portions of the Site as may be required to
enable the Contractor to proceed with the Execution of the Works with due dispatch
in accordance with the said programme or proposals as the case may be. If the
Contractor suffers delay or incurs extra cost as a result of failure on the part of the
Employer to give possession of site in accordance with the terms of this Clause, the
PMC may on Contractors request, grant extension of time for the completion of the
Works and/or certify such sum, as in his opinion, shall be fair to cover the extra cost
incurred, which sum shall be paid by the Employer to the Contractor. Provided further
Page 18 of 2
Section- 2.2
that if the Employer is unable to give possession of the site for a small portion of the
Works, the Employer, or the PMC on his behalf, may delete the work at that site from
the scope of the Contract and ask the Contractor to complete the rest of the work.
The Contractor shall complete the same within the time frame stipulated in the
contract without any extra payment. The decision of the PMC as to extra cost as
referred to above in this clause shall be final.
27.0
27.2
Access Road
The Contract shall provide necessary access roads to the site of work, from
the nearest public through fare/right of way, at his cost, unless otherwise
provided for in the Contract.
28.0
29.0
Where the works are to be executed by the Contractor as per his own
designs, it will be the responsibility of the Contractor to make bore holes or to
carry out exploratory excavation at his cost. If at any time during the
execution of the works, the PMC shall require the Contractor to make out
additional bore holes or to carryout additional exploratory excavation, the
Contractor shall comply with the same and no extra amount will be payable
on this account.
28.2
Where the works are to be executed by the Contractor as per the Designs of
the PMC, the Contractor shall be guided by the site investigation details
furnished in the Bid Documents. In such cases, if the PMC shall require the
Contractor to make bore holes or to carry out exploratory excavation, such
requirement shall be ordered in writing and shall be paid for extra.
COMMENCEMENT OF WORK
The Contractor shall commence the Works as soon as is reasonably possible after
the receipt by him of a notice to this effect from the PMC, within the time limit as
specified in the Contract Data. Thereafter, the Contractor shall proceed with the
works with due expedition and without delay.
30.0
Ownership
Page 19 of 2
Section- 2.2
The Contractor shall keep at site in good order one copy of latest approved
Specifications and Drawings and also such other Contract documents as may
be necessary and make them available to the PMC or his Representative. All
Specifications and Drawings shall remain the property of the Employer and
shall not be used on other works and shall be returned by the Contractor to
the Employer on completion of the works or on termination of the Contract.
30.2
30.3
30.4
The Contractor shall give written notice to the PMC whenever progress of
the works is likely to be delayed or disrupted unless any further drawing,
or order, including a direction, instruction or approval is issued by the
PMC within a reasonable time. The notice shall include details required
and of why and by when it is required and of any delay or disruption likely
to be suffered if this issue is delayed.
ii. The PMC shall furnish with reasonable promptness after receipt by him of
any request from the Contractor for review of drawing for defect noticed
by the Contractor, additional instructions by means of drawings or
otherwise necessary for the proper execution of the works or any part
thereof. All such drawings and instructions shall be consistent with the
Contract documents and reasonably inferable there from. The PMC may
ask the Contractor for alternative proposals or clarifications or additional
data or any other detail in respect of the request of the Contractor, if any.
iii. If, by any reason of any failure or inability of the PMC to issue within a
reasonable time any drawing or order requested by the Contractor as
stated above, the Contractor suffers delay and / or incurs additional costs,
the PMC shall take such delay into account while determining extension
of time to which the Contractor would be entitled.
31.0
Page 20 of 2
Section- 2.2
32.0
31.1
The rates entered in the accepted Bill of Quantities of the Contract, shall be
all inclusive and provide for Works duly and properly completed in
accordance with these conditions of the Contract, Special Conditions of
Contract and the Specifications and Drawings, together with such
enlargement, extension, diminution, reduction, alteration or addition, as may
be ordered in terms of conditions of the Contract, and without prejudice to the
generality thereof, shall inter-alia be deemed to include and cover all charges
relating to labour and superintendence thereof, supply including all cost and
freight of materials, stores, equipments, profiles, moulds, cuttings, centering,
scaffoldings, shuttering, machinery, derricks, tackles, ropes, pegs, posts,
tools, all apparatus, required at/for the work, and contingencies, except such
items as may be specified in the Contract Document to be supplied to the
Contractor by the Employer.
31.2
Nothing extra shall be payable over the quoted rates, notwithstanding any
provision to the contrary in any law for the time being in force, save except
what is specifically provided in the Contract Document.
SETTING OUT
The Contractor shall be responsible for the true and proper setting out of the Works,
in relation to the original points, lines and levels of reference given by the PMC in
writing and for the correctness, subject as above mentioned, of the positions, levels,
dimensions and alignment of all parts of the works, and for the provision of all
necessary instruments, appliances and labour, in connection therewith. If at any time
during the progress of Works, any error appears or arises in any part of the work, the
Contractor, on being required so to do by the PMC shall at once rectify such error, to
the satisfaction of the PMC or his representatives. The checking of any setting out, or
of any line or level by the PMC or his representative, shall not in any way relieve the
Contractor of his responsibility for the correctness thereof, and the Contractor shall
carefully protect and preserve all bench marks, sight rails, pegs and other things
used in setting out the works.
33.0
TEMPORARY WORKS
All temporary works necessary for the proper execution of the works shall be
provided and maintained by the Contractor at his cost and subject to the consent of
the PMC shall be removed by him at his expense when they are no longer required
and in such manner as the PMC shall direct. In the event of failure on the part of the
Contractor to remove the temporary works, the PMC may cause them to be removed
and cost as incurred for removal, supervision, and other incidental charges shall be
recovered from the Contractor. Such temporary work shall also include providing
suitable barricading around the site up to height of at least 6.0 meters and removal of
the same. The barricading shall be provided using steel pipes/ rolled steel sections
and steel sheets
34.0
Page 21 of 2
Section- 2.2
35.0
EXCAVATED MATERIALS
The Contractor shall not sell or otherwise dispose off, or remove, except for the
purpose of this Contract, sand, stone, clay, ballast, earth, rock or any other
substance or materials, which may be obtained from any excavation made for the
purpose of the works, or any building or produce existing at the site at the time of
delivery of possession thereof. All such substances, materials, belong to the
Employer; provided that the Contractor may, with the permission of the PMC, use the
same for the purpose of the Works either free of cost or on payment of cost, as per
mutually accepted terms and conditions.
36.0
37.0
LABOUR CAMP
37.1
37.2
37.3
Preservation of Peace
The Contractor shall take requisite precautions, and use his best endeavors
to prevent any riotous or unlawful behavior by or amongst his workmen, and
others, employed on works directly or through petty contractors or assignees
or sub-contractors and for preservation of peace and protection of the
inhabitants and security of property in the neighborhood of works. In the
event of the Employer requiring the maintenance of a special Police Force at
or in the vicinity of the Site, during the tenure or Works, the expenses thereof
shall be borne by the Contractor and if paid by the Employer, shall be
recoverable from the Contractor.
37.4
Sanitary Arrangements
The Contractor shall provide the facilities meeting the requirement of all the
sanitary rules and regulations, and carry out at his cost all sanitary measures
Page 22 of 2
Section- 2.2
that may from time to time be prescribed by the Local Medical Authority, and
permit inspection of all sanitary arrangements at all times by the PMC, the
PMCs Representative or the Medical staff of the Employer and the staff of
the local municipal or other authorities concerned.
37.5
37.6
37.7
Use of Intoxicants
The sale of ardent spirits or other intoxicating drugs or beverages upon the
Works, or in any of the buildings, encampments or tenements owned or
occupied by or within the control of the Contractor or any of his employees
employed on the Works directly or through petty contractors or sub
contractors shall be forbidden, and the Contractor shall exercise his influence
and authority to secure strict compliance with this condition. The contractor
shall also ensure that no labour or employee is permitted to work at the Site
in an intoxicated state or under the influence of drugs.
38.0
Page 23 of 2
Section- 2.2
39.0
ENGAGEMENT OF LABOUR
39.1
39.2
39.3
40.0
Page 24 of 2
Section- 2.2
40.2
40.3
41.0
CARE OF WORKS
From the commencement of the Works until the date stated in the Certificate of
Completion for the whole of the Works, the Contractor shall take full responsibility for
the care thereof. Provided that if the PMC shall issue a Certificate of Completion in
respect of any part of the Permanent Works for which a separate date of completion
is stipulated the Contractor shall cease to be liable for the care of that part of the
Permanent Works from the date stated in the Certificate of Completion in respect of
that part and responsibility for the care of that part shall pass to the Employer.
Provided further that the Contractor shall take full responsibility for the care of any
outstanding work which he shall have undertaken to finish during the Defect Liability
Period. In case any damage, loss or injury shall happen to the Works, or to any part
thereof, from any cause whatsoever, save and except the Excepted risks as defined
in Clause 24.0 hereof, while the Contractor shall be responsible for the care thereof,
the Contractor shall, at his own cost, repair and make good the same, so that on
completion, the Permanent Works shall be in good order and condition and in
conformity in every respect with the requirements of the Contract and the PMCs
instructions. In the event of any such damage, loss or injury happening from any of
the Excepted risks the Contractor shall if and to the extent required by the PMC,
repair and make good the same as aforesaid at the cost of the Employer. The
Contractor shall also be liable for any damage to the Works occasioned by him in the
course of any operations carried out by him for the purpose of implementation of
this Contract.
Page 25 of 2
Section- 2.2
42.0
EXTRAORDINARY TRAFFIC
42.1
42.2
Special Loads
Save insofar as the Contract otherwise provides, the Contractor shall be
responsible for and shall pay the cost of strengthening any bridges or altering
or improving any road communicating with or on the routes to the Site to
facilitate the movement of Contractors plant or materials or execution of
Temporary Works and the Contractor shall indemnify and keep indemnified
the Employer against all claims for damage to any such road or bridge
caused by such movement, including such claims as may be made directly
against the Employer, and shall negotiate and pay all claims arising solely out
of such damage.
42.3
Page 26 of 2
Section- 2.2
43.0
44.0
SAFETY PROVISIONS
44.1
Safety of Labour
The Contractor shall, at his own expense, arrange for the safety provisions as
required by any law for time being in force, in respect of labour employed
directly or indirectly for performance of the Works, and shall provide all
facilities in connection therewith.
Safety precautions shall be as warranted by the particular type of work. Also,
mere observance of these precautions shall not absolve the Contractor of his
liability in case of loss or damage to property, or injury to or death of any
person, including Contractors labour, employers officers, agents or servants
or any member of the public.
44.2
45.0
Existing road or water courses shall not be blocked, cut through, altered,
diverted or obstructed in any way by the Contractor, except with the
permission of the PMC. All compensation claimed for any unauthorized
closure, cutting through, alteration, diversion or obstruction to such roads or
water courses by the Contractor or his agent or his staff shall be recoverable
from the Contractor by deduction from any sums which may become payable
to him in terms of the Contract, or otherwise according to law.
45.2
Page 27 of 2
Section- 2.2
45.3
46.0
The Contractor shall be responsible for taking all precautions to ensure safety
of the public, whether on public or Employers property and shall post such
look out men as may be required in the opinion of the PMC, is necessary to
comply with the regulations pertaining to the Work and to ensure safety.
47.0
48.0
49.0
Page 28 of 2
Section- 2.2
All construction plant and materials provided by the Contractor shall, when
brought on to the Site, be deemed to be exclusively intended for the
execution of the Works and the Contractor shall not remove the same or any
part thereof, except for the purpose of moving it from one part of the Site to
another, without the consent, in writing, of the PMC, which shall not be
unreasonably withheld or delayed.
49.2
49.3
49.4
49.5
49.6
50.0
51.0
Page 29 of 2
Section- 2.2
works in a safe and proper manner. The Contractor shall employ only such
supervisors and workmen as are capable, careful, and skilled in their trade and
calling. The PMC shall be at liberty to object to and require the Contractor to remove
forthwith from the works, any person employed by the Contractor in or about the
execution of works or maintenance of works, who, in the opinion of the PMC,
misconducts himself or is incompetent or negligent in the proper performance of his
duties or whose employment is otherwise considered by the PMC to be undesirable
and such person shall not be employed again in the works without the written
permission of the PMC. Any person so removed from the works shall be replaced as
soon as possible by a competent substitute.
52.0
ii. Source of materials being supplied shall be intimated to the PMC and are
subject to his approval. Materials that are not specified in the Contract
document shall conform to the relevant Indian Standards. If Indian
Standards are not available, they shall conform to any International
standard approved by the PMC.
52.2
Supply of sample
All samples shall be supplied by the Contractor at his own cost.
52.3
54.3
Page 30 of 2
Section- 2.2
the Contract or the PMCs instructions, then the cost of such test will be
borne by the Contractor.
If the normal test indicate that the work is below the specifications and the
PMC decides to conduct special tests, all the cost and expenses incurred
in connection with such tests shall be borne by the Contractor.
53.0
The PMC shall have the authority to order in writing from time to time:
a. the removal from site within such time, as the PMC may specify, any
material, which in his opinion, is not in accordance with the specifications
and conditions of the Contract,
b. The substitution of defective material by proper and suitable material, and
c. The removal and proper re-execution, notwithstanding any previous
decision or interim payment thereof, of any work which in respect of
materials or workmanship is not, in the opinion of the PMC, in accordance
with the Contract.
53.2
54.0
In case of default on the part of the Contractor in carrying out such order, the
Employer shall be entitled to employ and pay other parties, to carry out the
same, and all expenses consequent thereof or incidental thereto, shall be
recoverable from the Contractor or may be deducted by the Employer from
any money which may be due to the Contractor.
COVERING UP OF WORK
54.1
54.2
55.0
MODIFICATIONS TO WORK
Page 31 of 2
Section- 2.2
55.1
55.2
55.3
56.0
57.0
The quantities of items shown in the Bill of Quantities are approximate, and
liable to vary during the actual execution of the Work. The Contractor shall be
bound to carry out and complete the stipulated work/group of works,
irrespective of the variations in individual items or group of items, specified in
the Bill of Quantities.
56.2
Page 32 of 2
Section- 2.2
bound to carry out such works at the rates to be decided as per Sub-clause
60.2
57.2
57.3
Notice by Contractor
i.
In all cases where extra items of work are involved, for which there are no
rates in the accepted Bill of Quantities, the Contractor shall give a notice
to the PMC at the earliest opportunity but at least 7 days before the need
for their execution arises.
ii. Such a notice shall not however be necessary if the PMC has already
instructed in writing to take up such an item of work. To decide the rate,
the PMC may ask the Contractor to furnish detailed analysis of the new
rates on the lines mentioned in Sub-clause 60.2 above and/or attend a
meeting with him to settle the rate. The Contractor shall be bound to
furnish the requisite details and / or attend the meeting.
57.4
57.5
Page 33 of 2
Section- 2.2
58.0
PRICE VARIATION
58.1
59.2
59.3
60.0
ON ACCOUNT PAYMENT
60.1
Page 34 of 2
Section- 2.2
60.3
61.0
ROUNDING OFF
In calculating the amount of each item due to the Contractor, in every certificate
prepared for payment, sums of less than fifty paisa shall be omitted and sums of fifty
paisa and more up to one rupee shall be reckoned as one rupee.
62.0
63.0
PRODUCTION OF VOUCHERS
62.1
62.2
Page 35 of 2
Section- 2.2
Every receipt of payment which may become payable, or for any Performance
Security amount which may become returnable to the Contractor, under this Contract,
shall, if signed in the partnership name by anyone of the partners of a Contractor
firm, or by a person holding a power of attorney, if the Contractor is a limited (private /
public) company, be a good and sufficient discharge to the Employer in respect of
moneys or security amount purported to be acknowledged thereby. In the event of
death of any of the Contractors partners during the currency of the Contract, it is
hereby expressly agreed that every receipt by any one of the surviving Contractors
partners, shall , if so signed as aforesaid, be a good and sufficient discharge as
aforesaid, provided that nothing in this Clause shall be deemed to prejudice or affect
any claim, which the Employer may hereafter have against the legal representatives
of any Contractors partner so dying, for or in respect of breach of any of the
conditions of the Contract. Provided also that nothing contained in this clause shall
be deemed to prejudice or affect the respective rights and obligations of the
Contractors partners, or of the legal heirs / representatives of any deceased
Contractor / partner inters.
64.0
FORCE MAJEURE
If, at any time during the currency of the Contract, the performance in whole or in part
by either party of any obligation under this Contract shall be prevented or delayed by
reason of any war, hostilities, invasion, acts of public or foreign enemies, rebellion,
revolution, insurrection, civil commotion, sabotage, large scale arson, floods,
earthquake, large scale epidemics, nuclear accidents, any other catastrophic
unforeseeable circumstances, quarantine restrictions, any statutory rules,
regulations, orders or requisitions issued by a Government Department or competent
authority or acts of God ( hereinafter referred to as event) then, provided notice of
the happening of such an event is given by either party to the other within 21 days of
the occurrence thereof.
a.
b.
c.
d.
e.
f.
Page 36 of 2
Section- 2.2
65.0
The time allowed for execution and completion of the Works or part of the
Works (Interim Milestones as specified in the Contract Data) as specified
in the Contract, in accordance with these conditions, shall be the essence
of the Contract on the part of the Contractor. Subject to any requirement
in the Contract as to completion of any portion or portions of the works
before completion of the whole, the contractor shall fully and finally
complete the whole of the Works comprised in the Contract (with such
modifications as may be decided by the PMC in terms of Clause 58.0) by
the date stipulated in the Contract or extended date in accordance with
the Contract. In case of delay on the part of the Contractor, the Contractor
shall pay as compensation an amount as provided herein. This is without
prejudice to the right of the Employer to rescind the Contract in terms of
Clause 73.0
ii. As soon as it becomes apparent to the Contractor, that the Works and/or
portions thereof (required to be completed earlier), cannot be completed
within the periods(s) stipulated in the Contract (Interim Milestones as
specified in the Contract Data), or the extended periods granted, he shall
forthwith inform the PMC and advise him of the reason(s) for the delay, as
also the extra time required to complete the works and/or portions of
work, together with justification therefore. In all such cases, whether the
delay is attributable to the Contractor or not, the Contractor shall be
bound to apply for extension in the period of completion of the whole
works and /or portions thereof. This application shall reach the PMC, at
least 30 days before the stipulated or extended date of completion of the
whole works or the stage completion date of any portion of the work. In
case the Contractor fails to apply for the extension of Contract or fails to
apply in time, the PMC, shall, in the case of any subsequent delay in the
completion of the whole and /or portion of works, be justified to hold that
such delay is due only to Contractors failure or fault and shall take further
action accordingly in terms of the Contract. Any reasons or circumstances
leading to delay in the completion of the work(s) even if they are not the
result of the Contractors failure or fault shall not invalidate or vitiate the
Contract.
65.2
65.3
Page 37 of 2
Section- 2.2
65.5
65.6
65.7
Page 38 of 2
Section- 2.2
SUSPENSION OF WORKS
66.1
66.2
66.3
67.0
Page 39 of 2
Section- 2.2
any materials or items of work are not available in the Contract, these
shall be fixed by the PMC. If any materials supplied by the Employer to
the Contractor at the cost of the Contractor are rendered surplus, the
same shall be returned by the Contractor to the Employers depot at
Contractors cost and full credit at rates initially charged to the Contractor,
shall be allowed for such materials. Similarly, any plant, equipment or tool
issued by the Employer to the Contractor free of cost or on lease terms
shall be returned by the Contractor to Employers depot at his own cost.
The Employer shall be entitled to recover the cost of unreturned material,
plant, equipment and tools from the Contractor where such materials
have been supplied free of cost or on lease basis to the Contractor as
stipulated in the Contract Data. In case of such unreturned materials,
recovery shall be effected from the Contractor as indicated in Sub-clause
50.6. In case of such unreturned plant, equipment and tools, the amount
to be recovered from the Contractor shall be decided by the PMC and this
shall be final and binding as indicated in Clause 51.0. The Contractor
shall have to pay back un-recovered portion of advances made to him,
together with interest accrued thereon in terms of the conditions
governing the payment of the advance. In case the Contractor defaults,
the Employer shall be entitled to recover the amounts from any payment
due to the Contractor, or from the Performance Security amount or by
enchasing the Bank Guarantees given by the Contractor for securing the
advances. This is without prejudice to other remedies available to the
Employer.
ii. Provided further, that any diminution of quantities against individual items
of the Contract, merely as a variation when the work is completed, shall
not constitute foreclosure of Contract in terms of this clause, and no
compensation or payment whatsoever as per this clause will be due or
payable to the contractor on that account.
67.2
Default of Employer
i.
Page 40 of 2
Section- 2.2
period of 30 days, the PMC notifies the Contractor with a copy to the
Employer, that the reason stated in the notice of the Contractor are
not valid or that the alleged reasons of default of the Employer have
been remedied and no longer exist, then the Contractor shall not be
entitled to terminate the Contract.
ii. Subject to the PMC not raising any objection to the notice of termination
of the contract by the Contractor, upon expiry of 30 days notice as per
Para (i) of this Sub-clause, the Contract shall stand terminated and the
Contractor shall remove from site all balance material and construction
plant and equipment brought by him thereon, with all reasonable
dispatch.
68.0
69.0
The Employer shall have lien over all or any moneys that may become due
and payable to the Contractor under these presents, and / or over the deposit
of Performance Security or other amount or amounts made under the
Contract and which may become payable to the Contractor, under the
condition in that behalf herein contained, in respect of any debt or sum that
may become due and payable to the Employer by the Contractor, either alone
or jointly with others, either under this or under any other Contract or
transaction of any nature whatsoever between the Employer and the
Contractor.
68.2
And further, unless the Contractor pays and clears immediately on demand
any claim of the Employer, the Employer shall at all times be entitled to
deduct the amount of the said claim from the moneys, securities and / or
deposits which may have become or will become payable to the Contractor
under these presents, or under any other Contract or transaction whatsoever
between the Employer and the Contractor even if the matter stands referred
to Arbitration. Provided further that if the Contractor does not accept any such
claim, the amount deducted shall be treated as having been withheld only till
the claim is mutually settled or determined by the Arbitrator or by the
competent court of law. The Contractor shall have no claim for any interest or
damages whatsoever in respect of any amounts withheld or treated as
withheld under the lien referred to above and duly notified as such to the
Contractor.
Page 41 of 2
Section- 2.2
further that the legal representatives of the deceased Contractor or the surviving
partners shall also not be liable to pay any damages, alleged or actually suffered by
the Employer, in respect of incomplete part of the Contract. Any liability incurred by
the deceased contractor, or by the deceased partner of the contracting firm, before
his death, shall be recovered from the legal representatives of the deceased
Contractor or from the surviving partners of the said contracting firm as the case may
be.
70.0
If the Contractor,
Page 42 of 2
Section- 2.2
Entitlement of Employer
In both cases described in sub-clause 73.1 (ii) above, the Employer shall be
entitled to:
a) Forfeit the whole or such portion of the Performance Security amount, as
he may consider fit, and
b) Recover from the Contractor the cost of carrying out the balance work in
excess of the sum which he would have been paid, according to the
certificate of the PMC, if the works had been carried out and completed
by the Contractor under the terms of the Contract. Such certificate shall
be final and binding upon the Contractor. The amount to be recovered
may be deducted by the Employer from any monies then due or which, at
any time thereafter, may become due to the Contractor alone or jointly
under this or any other Contract or otherwise.
70.3
71.0
Completion Certificate
Within ten days of the completion of the work, the Contractor shall give notice
of such completion to the PMC and within thirty days of the receipt of such
notice the PMC shall inspect the work and if there is no defect in the work,
shall furnish the Contractor with a final certificate of completion, otherwise a
provisional certificate of physical completion indicating defects (a) to be
rectified by the Contractor and/or (b) for which payment will be made at
reduced rates, shall be issued. But no final certificate of completion shall be
issued, nor shall the work be considered to be complete until the Contractor
Page 43 of 2
Section- 2.2
shall have removed from the premises on which the work shall be executed
all scaffolding, surplus materials, rubbish and all huts and sanitary
arrangements required for his/their work people on the site in connection with
the execution of the works as shall have been erected or constructed by the
Contractor(s) and cleaned off the dirt from all wood work, doors, windows,
wall, floor or other parts of the building, in, upon, or about which the work is to
be executed or of which he may have had possession, for the purpose of the
execution thereof, and not until the work shall have been measured by the
PMC. If the Contractor shall fail to comply with the requirements of this
clause, as to removal of scaffolding, surplus materials and rubbish and all
huts and sanitary arrangements as aforesaid and cleaning off dirt on or
before the date fixed for the completion of work, the PMC may at the expense
of the Contractor remove such scaffolding, surplus materials and rubbish etc.,
and dispose of the same as he thinks fit and clean off such dirt as aforesaid,
and the Contractor shall have no claim whatsoever in this regard except for
any sum actually realised by the sale thereof.
71.2
71.3
Completion plans
The Contractor shall within one month of the date of completion of the work
submit:
(i) Completion Plans of all the internal and external works including, but not
limited to the Civil, Electrical, Sanitary, Water Supply and Drainage
installations by marking on a set of drawings all the details including the
route, position and details of the pipes, fixtures, fittings in the manner
specified by the PMC.
(ii) The Contractor shall also arrange statutory inspection and certification of
the installations by local authorities in conformity with the bylaws, if any.
If the Contractor fails to submit the Completion Plans and obtain necessary
statutory certificates from the Local Authority as aforesaid the PMC shall get
the Completion Plans prepared and arrange necessary statutory certificates
as aforesaid. The expenses that may be incurred by the PMC shall be
payable by the Contractor and the PMC shall have the authority to recover
the said expenses from the dues of the Contractor.
72.0
Page 44 of 2
Section- 2.2
satisfaction of the PMC. No final payment in settlement of the accounts for works
shall be made or held to be due to the Contractor, till, in addition to any other
condition necessary for such final payment, site clearance shall have been affected
by him. Such clearance may be made by the PMC through any other agency at the
expense of the Contractor in the event of the Contractors failure to comply with this
provision within 7 days after receiving notice to that effect from the PMC. Should it
become necessary for the PMC to have the site cleared at the expense of the
Contractor, the Employer and / or the PMC shall not be held liable, for any loss or
damage to Contractors property on the site due to such removal there from. Removal
may be effected by means of public sale of such plant, materials and property or in
such a manner as may be deemed fit and proper by the PMC. All expenses on such
removal/ clearance shall be debited to the Contractor as loans due from the
Contractor to the Employer, and the Employer shall be competent to recover the
same from Contractors on account or final bills, or from Performance Security
amount or from any other amount payable to the Contractor.
73.0
URGENT REPAIRS
If, by reason of any accident, or failure, or other event occurring to or in connection
with the Works, or any part thereof or proximity thereof, either during the execution of
the Works, or during the Period of Maintenance, any remedial or other work or repair
shall, in the opinion of the PMC or the PMCs Representative, be urgently necessary
for the safety of the Works, adjoining property, traffic, utility or public, and the
Contractor is unable or unwilling to do such work or repair at once, the Employer may
employ and pay other persons to carry out such work or repair, as the PMC or the
PMCs Representative, may consider necessary. If the work or repair so got done by
the Employer is work which, in the opinion of the PMC, the Contractor was liable to
do at his own expense under the Contract all expenses properly incurred by the
Employer in so doing, shall be recoverable from the Contractor by the Employer, or
may be deducted by the Employer from any monies due or which the PMC or the
PMCs Representative, as the case may be, shall, as soon after the occurrence or
any such emergency as may be reasonably practicable, notify the Contractor thereof
in writing.
74.0
Soon after the issue of the Completion Certificate the PMC shall have the
final measurements taken, recorded and signed, as in the case of interim
measurements. A joint account of any plant, equipment and materials issued
by the Employer to the Contractor, shall also be prepared and signed jointly.
Based on the final measurements and joint materials and plant, equipment
account statements, the Contractor shall submit a draft Final Bill with
supporting documentation, in the proforma prescribed by the PMC. Within
one month of receipt of the draft Final Bill and of all information reasonably
required for its verification, the PMC shall determine the value of all matters to
which the Contractor is entitled under the Contract, and issue his draft Final
Bill account to the Employer and the Contractor. The Contractor shall sign the
PMCs copy of the draft Final bill Account in token of acknowledgement of the
full and final value of the Works performed under the Contract, and based on
that, submit promptly the Final Bill duly signed by him in the format desired by
the PMC, together with a No Claim certificate or a list of any unsettled
claims in accordance with clause 81.0. On receipt of the Final Bill, the PMC
shall promptly prepare and issue to the Employer the Certificate of Final
Payment, confirming the amount due to the Contractor under the Contract.
Page 45 of 2
Section- 2.2
75.0
75.2
Maintenance Certificate :
The Contract shall not be considered as completed, until a Maintenance
certificate shall have been signed by the PMC stating that the works have
been completed and maintained to his satisfaction. Maintenance Certificate
shall be issued by the PMC, upon expiration of the Defects Liability Period or
as soon thereafter as any repair works ordered during such period shall have
been completed to the satisfaction of the PMC and full effect shall be given to
this Clause, notwithstanding the taking possession of or using the works or
any part thereof by the Employer.
75.2.1 Final Approval by Maintenance certificate
No certificate other than Maintenance Certificate shall be deemed to
constitute final approval of any work or be deemed to constitute final
approval of any other matter, in respect of which it is issued, or shall
be taken as an admission of due performance of the Contract or any
Page 46 of 2
Section- 2.2
CLAIMS
The Contractor shall send to the PMCs Representative once every month an
account giving particulars, along with full details and justification, of all claims for any
additional payment to which the Contractor may consider himself entitled and of all
extra or additional work ordered by the PMC which he has executed during the
preceding three months. No final or interim claim for payment for any such work or
expenses will be considered which has not been included in such particulars.
Provided always that the PMC shall be entitled to authorize payment to be made for
any such work or expenses, notwithstanding the Contractors failure to comply with
this condition, if the Contractor has, at the earliest practicable opportunity, notified the
PMC in writing that he intends to make a claim for such work.
77.0
Should any dispute or difference of any kind whatsoever arise between the
Employer and the Contractor, touching, in connection with, or arising out of
the Contract, or subject matter thereof, or the execution of Works, whether,
during the progress of Works or after their completion and whether before or
after termination, abandonment or breach of Contract, it shall, in the first
place, be referred to the Chairman Engineering Unit of IIT Madras , who shall,
within a period of sixty days after being requested in writing by either party to
do so, give written notice of his decision to the Employer and the Contractor.
The Chairman , Engineering Unit, IIT Madras, while considering the matters
of dispute referred to him, shall be competent to call for any records,
vouchers, information and enforce the attendance of the parties either in
person or through authorized representatives, to sort out or clarify any issue,
resolve the differences and to assist him to decide the matters referred to
him. Subject to arbitration, as hereinafter provided, such decision in respect
of every matter so referred shall be final and binding upon the Employer and
Page 47 of 2
Section- 2.2
the Contractor and shall forthwith be given effect to by the Employer and by
the Contractor, who shall proceed with the execution of works with all due
diligence irrespective of whether any of the parties goes in or desires to go in
for arbitration. If the Chairman Engineering Unit, IIT Madras, has given written
notice of his decision to the Employer and the Contractor and no intimation of
reference of any claim to arbitration has been sent to him by either the
Employer or the Contractor within a period of sixty days from receipt of such
notice, the said decision shall remain final and binding upon the Employer
and the Contractor and the same shall be deemed to have been accepted by
them. The Employer or the Contractor shall not seek any arbitration
thereafter.
77.2
77.3
77.4
Settlement of disputes
Except where otherwise provided in the Contract, all disputes or differences,
whatsoever arising between the parties, arising out or touching or relating to
construction, measuring, operation or effect of the Contract or the breach
thereof, shall be settled by arbitration, subject to provisions of Sub- Clauses
77.3 and 77.5
77.5
77.6
No suspension of work.
The reference to arbitration shall proceed notwithstanding that the Works
shall not then be or be alleged to be complete, provided always that the
obligations of the Employer and the Contractor shall not be altered by
Page 48 of 2
Section- 2.2
77.7
77.8
77.9
Limitation of time.
No dispute or difference shall be referred to Arbitration after expiry of 90 days
from the date of decision by the Chairman, Engineering Unit, IIT Madras, if
notified, or from the date when the Chairman, Engineering Unit, IIT Madras
ought to have given his decision in terms of provisions under Sub clause 77.1
in case of failure on the part of the Chairman, Engineering Unit, IIT Madras to
give notice of decision.
78.0
79.0
Any money due to the contractor either alone or jointly with others, including the
Performance Security amount refundable to him, may be withheld or retained by
exercise of lien by the Employer, against any claim of Employer or of any other
branch, office, department or subsidiary of the Employer in respect of payment of a
sum of money arising out of or under any Contract other than the present Contract
made by the Contractor, alone or jointly, with the employer or any other branch,
office, departments or subsidiary of the Employer. It is an agreed term of the Contract
that the sum of the money so withheld or retained under this clause by the Employer,
shall be kept withheld or retained till the claims arising out of or under the other
Contract, are either mutually settled or determined by the Arbitrator, or by the
competent court, as the case may be and that the Contractor shall have no claim for
interest or damages whatsoever on this account, or any other account, in respect of
any sums of money withheld or retained, under this clause and duly notified to the
Contractor.
Page 49 of 2
Section- 2.2
Clause
Ref. No.
(GCC)
1.
1 a.
Employer
2.
1 b.
Project Management
Consultant (PMC)
3.
16.2.3
Mobilization Advance
4.
16.2.3
Rate of Recovery of
Mobilization Advance
5.
16.3
Advance against
material at site
No Advance
6.
21.1
Security Deposit
7.
22.1.i
8.
23.1
Performance
Guarantee
CAR Policy & Third
party insurance policy
9.
23.1b
10.
23. 3
11.
25.0
st
12.
25.0
13.
29.0
14.
50.0
15.
51.0
16.
53.0
17.
63.1
Workmens
Compensation Policy
Submission of
Insurance Policy
Time period for
submission of
construction program
Stipulated period of
completion
Commencement of
work
Employers material.
Employers tools,
plants and machinery.
Supply of Water &
Electrical Power
Time schedule for
interim bill certification
& payment.
Page 50 of 2
Section- 2.2
Sl.
No
Clause
Ref. No.
(GCC)
Description
18.
68.5
Rate of liquidated
damage
19.
78.1
Defects Liability
period
Page 51 of 2
Section- 2.2
SCC
CL.
No.
Special Conditions
Supplement to
GCC Clause
No
Sub-Contracting of works
14.0
Assignment &
Subcontracting
15.0
Contractors
Understanding
37.0 Labour
Camp
Temporary Structures
38.0 Sheds,
Stores & Yards
SCC
Page 1 of 3
Section- 2.3
SCC
Page 2 of 3
Section- 2.3
1.
Non use of hard hat Rs. 100 per head / day
2.
Non use of safety shoes Rs. 100 per head / day
3.
Non use of safety belt work working over 3 m height Rs. 200 per head per day
4.
Collection of debris/waste at places other than designated Rs. 5000 per default
per day
Concrete may be procured from plants approved by the PMC. Concreting using batch
mixers at site is not permitted.
In case of any ambiguity in the specifications given in the tender or any missing
specification, relevant CPWD specifications supported with relevant IS Codes to be
referred
All reinforcement steel shall be of TMT type. Wastage in steel to be considered in the
quoted rates and will not be paid separately.
SCC
Page 3 of 3
Section- 2.3
TECHNICAL SPECIFICATIONS
FOR
PILING WORKS
Technical Specifications
Page 1 of 14
Section-3.0
1.0
INDIAN STANDARDS
Indian Standards used for this section are:
1.
IS 456 -2000
MATERIAL
2.1
Bentonite
Bentonite powder to be used by mixing with water in suspension shall be such as to
maintain the stability of excavation in trench/bore. Each consignment of bentonite
powder received by the Contractor shall be accompanied by a Test Certificate from
the manufacturer stating its properties as determined by the supplier/manufacturer.
The Certificate shall be submitted to the PMC for his record.
In general properties of bentonite and its slurry shall be as stated in Appendix A of IS
2911 (Part 1 / Sec 2)
2.2
Cement
Cement should be OPC 53 grade and never should be SRC. Other cement viz.PPC
or PSC can be used with the permission of PMC / Employer
2.3
Aggregates
2.3.1
Coarse aggregate shall have flakiness & elongation index not more than 30%.
2.3.2
2.4
Concrete
2.4.1
Grade of Concrete shall be M30 Total cementatious material content shall not be less
than 400Kg/m3, Water Cementatious material ratio not to exceed 0.35., Slump at
pouring point shall be 150 to 180mm.
2.4.2
2.4.2.1
2.4.2.2
Technical Specifications
Page 2 of 14
Section-3.0
2.4.3
Volume of concrete shall be paid on theoretical volume of pile from pile tip to 300mm
above cut-off level.
2.4.4
Concrete not meeting the slump at the pouring point will be rejected.
2.5
Reinforcement
Reinforcement shall be TMT bars of specified grade from primary manufacturer viz.
TISCO, SAIL, RINL, etc. or secondary manufacturers like SRMB, Ramswarup,
Shyam, or any other suppliers from local market, subject to the approval of the PMC
Steel who use billets from SAIL, RINL or TISCO and have ISO 9000 certification.
3.0
4.0
SCOPE OF WORK
4.1
This section covers for providing bored cast-in-situ reinforced concrete pile
foundations including boring work, steel reinforcement, concreting, finishing of pile
heads and all other related work as required.
The work included consists of all necessary services and furnishing of all labour,
material, tools, equipment and related items for full performance of the contract items
as shown on the drawings, or as specified or reasonably implied.
In brief, items of work will be as follows:
Boring for piles including chiselling/cutting hard strata like boulder/weathered and
hard rock, disposal of excavated material, keeping the site clean, etc.
Bored muck excess/removed concrete shall be disposed off outside the premises
and the Contractor shall indemnify the Employer against any claims that may
arise in this regards. No separate payment shall be made for this activitiyAll other
miscellaneous concrete and related work shown in the drawings and/or called for
in the BOQ.
Technical Specifications
Page 3 of 14
Section-3.0
4.2
The Contractor shall be responsible for the safety of each pile and/or group of piles
and shall guarantee his workmanship and materials against any damage resulting
there-from to the building superstructure erected on the pile foundation.
4.3
The Contractor shall, taking into account the site investigation information available
and his own local knowledge, submit, with his tender, the full details of his proposals
for the piles.
4.4
The Contractor shall include in his tender provision for a qualified site engineer and
staff experienced in piling construction to execute the work and who shall be
approved by the PMC, who will work full time at the site. The Contractor shall indicate
his organization chart with his bid.
5.0
FOUNDING STRATA
5.1
Piles shall be founded in weathered rock/ hard rock with 6D socketing (D=Diameter
of pile).Weathered rock is deemed to have commenced at chisel energy level of
50T/sq.m/cm. Also minimum socket length shall be 2D in energy zone of
125T/sq.m/cm. Both conditions for socketing in rock shall be satisfied.
Adequacy or otherwise of socketing criteria is as per soil investigations report. Any
change in socket length shall be indicated before the award of work.
Detailed geo-technical investigation has been carried out at site and relevant
borelogs and profiles are enclosed. Contractors are free to refer detailed geotechnical investigation reports available in Employers office.
The Contractor are also free to carry out one or two boreholes within or nearby the
piling area (as permitted by Employer) at his own cost, to ascertain the penetration
resistance/boring time etc. These boreholes shall be backfilled with granular soil
(sand/stone chips etc.) at the end of boring at Contractors own cost.
In case of sudden variation of strata, PMC / Employer may order the Contractor to
conduct SPT in pile bore to ascertain compactness of strata and/or order alteration of
founding depth, SPT test only shall be paid separately.
5.2
The Contractor shall provide and maintain, during the progress of his work, a suitable
firm working surface at the site and as the work proceeds shall remove from the site
all excavated material and rubbish arising thus to the satisfaction of the PMC.
5.3
The Contractor shall, during the progress of the works, maintain full records of each
pile constructed including the soil profile as bored, the length and diameter of the pile
and the quantity of concrete placed in the pile in the proforma as detailed hereunder
or as directed by the PMC.
5.4
The Contractor shall take every precaution to avoid damage to the existing structures
in the vicinity as a result of piling operation. All claims arising on account of any
damage caused to the existing structures in the vicinity as a result of construction of
pile foundation shall be borne by the Contractor.
6.0
CO-ORDINATION OF DRAWINGS
The Contractor shall co-relate all relevant Architectural, Structural and Services
drawings and satisfy himself that the information available therein is complete and
unambiguous. Any discrepancy in drawing shall be brought to the notice of the PMC
Technical Specifications
Page 4 of 14
Section-3.0
prior to execution of the work. The Contractor at his cost shall correct any aspect
overlooked by him.
7.0
SETTING OUT
A benchmark shall be established by constructing a masonry pillar or marking on a
suitable structure at the site. Based on the drawing the Contractor shall prepare a
layout drawing indicating pegs setting in both directions for approval of the PMC. The
approved setting out shall be carried out at site with the use of Theodolite, steel
tapes, etc. For proper execution it is recommended that a well-built masonry pillar be
provided with top surfaces that are smooth-finished to predetermined levels and
marked sharply with axis for cross-reference. The Contractor shall ensure that all
benchmarks, pillars and other marks used in setting out are protected and preserved
till the completion of operation. The Contractor shall be fully responsible for the
accuracy and sufficiency of layout, and to achieve the standard of work required.
8.0
BORING
8.1
Boring shall be done by direct mud circulation method. Stabilisation of the sides of
the borehole shall be done by the use of drilling mud fluid (bentonite slurry).
Temporary casing shall be provided up to 150cm into self supporting stiff clay below
backfilled soil.
8.2
The drilling fluid, wherever required, shall be used at least from the level of subsoil
water and the hole shall then be always kept almost full with the fluid preferably kept
in motion. The density and composition of the fluid shall be such as to suit the
requirements of the ground conditions and to maintain the fine materials from the
borings in suspension. A 5% bentonite suspension would be generally suitable.
8.3
Construction sequence from the centre onwards from a group of piles shall be
prepared and submitted for approval of the PMC.
9.0
CLEANING
The bottom of the bore holes shall be cleaned by direct / reverse mud circulation or
by compressed air of all the spoils and sediments before placing the concrete and
after placing of cage reinforcement so that the bases of piles shall be free from loose
material. When direct/reverse mud circulation is adopted, density of mud in borehole
shall be close to fresh mud slurry. In case of hydraulic /rotary rigs, cleaning of
boreholes shall also be done by cleaning bucket, before lowering the reinforcement
cage.
11.0
REINFORCEMENT
Only TMT bars of specified grade shall be used. Reinforcement cage shall be made
up to into cages sufficiently well wired by binding wire to withstand handling without
damage.
18gauge M.S. Wire shall be used for binding. Only necessary lengths of binding wire
pieces shall be used and any extra lengths projecting shall be bent inwards.
For pile length up to and including 11m from cut-off, no laps will be paid. Beyond
11m, one lap will be paid when required to be used.
Technical Specifications
Page 5 of 14
Section-3.0
Only cement concrete cover blocks shall be used to maintain specified cover.
12.0
CONCRETING
11.1
After lowering the reinforcement cage and tremie pipe, the boreholes shall be
thoroughly cleaned by continuous circulation of fresh bentonite slurry to remove all
the debris from shaft bottom. The concreting shall be immediately carried out after
the cleaning
11.2
Concreting shall start as soon as possible after the completion of boring and borehole
cleaning. If boreholes are not concreted within two hours of cleaning, they shall be
cleaned once again thoroughly prior to placing the concrete.
11.2
Concreting shall be done so as not have any voids formed due to faulty consolidation
of entrapped air. The volume of concrete placed shall be observed and checked to
monitor any deviation in the volume of the concrete placed.
11.3
Concreting shall be placed by means of a water tight tremie pipe. Minimum diameter
of tremie pipe shall be 200mm with maximum size of aggregate as 20mm and it
should be 250mm with maximum size of the aggregate as 40mm.
11.4
It shall be ensured that the concrete entering the tremie pipe does not get mixed up
with slurry. The tremie pipe shall extend up to the bottom of the bore hole at the start
and shall be withdrawn in sections as the level of concrete rises in the bore holes, but
its discharge end shall at all times be embedded in the concrete to a minimum depth
of one meter or a sufficient head to prevent the inflow of soil and water.
11.5
The borehole should be maintained full with the drilling fluid, where used, throughout
the concreting operation. Mud displaced from the borehole by the concrete shall be
channeled away or pumped into suitable receptacles for disposal to waste or reuse.
11.6
Design mix
11.6.1
Design mix concrete is that concrete in which the design of mix i.e. the determination
of proportions of cement, aggregate and water is arrived as to have target mean
strength for specified grade of concrete.
BOQ shall specify various types of concrete aimed to be used in works. It shall be
the responsibility of the Contractor to carry out design mixes and approval of the
same shall be obtained from the PMC at least 35 days in advance from the actual
pouring of concrete at site in the permanent works.
1.
Technical Specifications
Mix design of concrete shall be done as per IS 10262 & SP 23, 24. Following
basic points shall be finalized.
Page 6 of 14
Section-3.0
Aggregates being used are tested to IS383. Include for Alkali reactivity,
chloride and sulphate contents independently and combination of cement
and water.
Further the Contractor shall ensure that designed mix meet minimum cement
contents as specified in BOQ/drawings and proposed revision to IS 456 along with
maximum water cement ratio, to different exposure condition from durability point of
view. In addition Contractor shall ensure
a)
Alkali - reactivity
Aggregates containing material susceptible to attack by alkali's (Na2O and
K2O) originating from cement or other sources and producing expansive
reaction shall not be used.
The aggregates source shall be initially tested for alkali reactivity prior to
being used in design mix.
b)
11.6.2
- 0.15 %
-4%
Compressive strength
For expected strength of cubes tested on the 28th day, the design mix at preliminary
test and work site shall be as per IS 456-2000.
11.6.3
11.6.4
Trial mixes
11.6.4.1
The Contractor shall submit, at least 5 weeks in advance, to the PMC the mix design
that he proposes to use at site. The mix design in addition to points in 11.6.2 shall
also give basic details (when tested according to IS 1199 and IS 2386-Part III 1963),
as per followings
a)
Slump/Workability
b)
Bleeding
c)
Compacting factor
d)
Vee-Bee time
Technical Specifications
Page 7 of 14
Section-3.0
11.6.4.2
e)
f)
g)
On receipt of this, the PMC may immediately order to carry out work site test before
the final approval. This shall be done with mixer and materials actually being used at
site.
This shall give the Contractor additional chance to check for himself actual
workability and make sure that the mix proposed by him will be fully satisfactory with
regards to slump, segregation, bleeding, water-cement ratio and workability.
6 cubes shall be taken from each of the 3 batches to test the mix. Cubes shall be
cast, stored, cured, transported and tested to IS 516. The test may be carried out at
site or laboratory as approved by the PMC.
Trial mixes shall be approved provided that average strength of 3 consecutive
cubes is not less than that specified and that one out of three may give a value
less than specified but limited to a maximum of 90% of the specified strength.
11.6.4.3
In case the trial mix falls below the above criterion, the PMC shall order fresh trial
mixes to be made as before, until the desired strength is arrived at.
11.6.4.4
This design mix and trial mix hold good so long as the materials continue to be of the
same quality and from the same sources. For any change, the PMC may order fresh
design mix and trial mixes to be carried out before the same is used at site.
11.6.5
Mixing of concrete
11.6.5.1
Batching
Batching shall be done by weigh batchers conforming to IS 2722. A platform
scale of capacity 300kg with fraction up to 100gms shall be at site.
For water supply to mixture through metering system shall be organized.
Design mix converted to volumetric may be permitted by PMC. Accordingly
suitable size of boxes equivalent to 1 bag of 50kg cement shall be prepared
by the Contractor.
b)
Mixer
Mixers used shall conform to IS. Type Capacity shall be as per size, extent
and nature of work.
c)
Transportation
Wheel borrows, cranes, mini dumpers, truck, agitators, belt conveyors,
pumps with piping etc. as per requirement depending upon location, size
extent and nature of work shall be deployed by the Contractor with prior
approval of the PMC.
d)
Vibrators
Internal and external vibrators working on electricity, Pneumatic or petrol
shall be approved by the PMC. Vibrators shall conform to IS.
Technical Specifications
Page 8 of 14
Section-3.0
e)
11.6.5.2
At the start of mixing mixer shall be rinsed /coated by loading with cement, sand,
water of the same proportion of batch to be used. Loading the mixer/charging the
mixer shall be done mechanically and care to be taken that all material is fully loaded.
The mixer shall be run for a minimum period of 2 minutes after all materials are
loaded in full quantity. The concrete produced shall be uniform in color and
consistency. Unless agreed by PMC the first batch of concrete from mixer shall
contain two-third of normal quantity of coarse aggregate.
11.6.5.3
Transportation
Concrete shall be transported to place of pour as far as possible in most efficiently,
conveniently and without loss of concrete characteristic. Method of transportation
shall depend upon the location, size and nature of work. Concrete should be placed
within hour of production i.e. prior to initial set.
Use of admixtures such as air entraining agent, retarders etc. shall be adopted and
incorporated into design mix stage.
Concrete shall be kept in agitating state when ambient temperatures are high. This
shall increase placing time to 1 hrs after water is added.
Points to be taken care are
11.6.5.4
Placing
The placing temperature of concrete shall not be more than 34o C. If it is more, the
PMC may order addition of ice or chilled water to the concrete. Also the Contractor
shall take the following precautions:
11.6.5.5
a)
b)
c)
d)
Use chilled water for mixing or add flake ice as a proportion of the mixing
water.
e)
Concrete
Ready mix concrete as approved only shall be used. It shall comply all
requirements of concrete. Batching plant, mixture, truck mixture, pump etc
Technical Specifications
Page 9 of 14
Section-3.0
Pumping of concrete
Stationery or mobile pumps as per requirements shall be deployed. Concrete
shall be continuous to avoid any blockage within pump. Concrete mix shall
be with slump as desired by pump manufacturer and most desirable at site to
pump operator / supervisor.
Required piping, bends, clamps, chutes etc. shall be well organized and
placed in position prior to start so continuous concrete with minor changes
will keep concrete flowing at predetermined location in approved manner.
Mix design adopted shall be approved by PMC and shall conform all test as
detailed in specification.
Pump concrete shall flow quite fast and is placed with larger impact on
formwork. Hence special precautions at design stage of formwork shall be
taken and staging/scaffolds should be well restrained in all directions to
withstand thrust.
Pumping shall be done with due care and safety. Recommendation of pump
suppliers shall be followed strictly.
c)
Field control
Sampling at both truck discharge and point of final placement shall be
employed to determine if any changes in the slump and other
significant mix characteristics occur. However, for determining strength
of concrete, cubes shall be taken from the placement end of line.
d)
Planning
Proper planning of concrete supply, pump locations, line layout, placing
sequence, and the entire pumping operation shall be made and got
approved. The pump should be as near the placing area as
practicable, and the entire surrounding area shall have adequate
bearing strength to support concrete delivery pipes. Lines from pump
to the placing area should be laid out with a minimum of bends. For
large placing areas , alternate lines should be installed for rapid
connection when required. Standby power and pumping equipment
should be provided to replace initial equipment, should breakdown
occur.
The placing rate should be estimated so that concrete can be ordered
at an appropriate delivery rate.
e)
Technical Specifications
Page 10 of 14
Section-3.0
pressure
distance
not spill
the line
12.0
12.1
All piles shall be cast minimum 300mm above cut-off to permit all laitance and
unsound concrete to be removed.
12.2
13.0
TOLERANCES
13.1
The Contractor shall exercise every care to ensure that all the piles are located at the
correct assigned positions as indicated in the drawings. The piles shall be, as
accurately as possible, true to the vertical.
13.2
Permissible positional deviation for bored piles shall not be greater than 7.5 cm at the
level of the bottom of the pile cap. The deviation from the vertical shall not be more
than 1 in 100.
14.0
RECORDS
A competent supervisor shall be present to record the necessary information when
the pile is being installed. The data record shall be kept in the form as prescribed in
IS 2911(Part I-Section2) Appendix D or as directed by the PMC or as per enclosed
formats herein. However the formats will be frozen before start of piling work.
15.0
DEFECTIVE PILES
15.1
PMC reserves the right to reject any pile which, has not been constructed according
to specifications. The Contractor shall leave the rejected piles in place or pull them
out as judged and directed by the PMC. No extra payment will be made on this
account.
15.2
The cost of extra piles if any at new locations and any other additional work such as
extra pile cap required as a result of rejection of defective piles shall be borne by the
Contractor.
16.0
LOAD TEST
Two types of test will be carried out on piles.
1)
Integrity test
2)
Integrity test shall be carried out on all piles whereas the dynamic test shall be
carried out subsequently on selected few piles.
Both the tests shall be carried out through a specialized agency approved by PMC.
Technical Specifications
Page 11 of 14
Section-3.0
Tests shall be carried out in accordance with the requirements of IS 2911 (Part IV).
16.1
Testing Procedure
Procedure recommended by the specialized agency shall be submitted along with
tender bid for scrutiny and approval.
16.2
Number of Test
Test shall be carried out in phased manner. After completion of about 50% of piles,
integrity test shall be carried out. At least one pile of 1200mm diameter and one pile
of 1000mm diameter shall be selected for carrying out dynamic test. On completion of
entire work the remaining piles shall be tested for integrity test and at least one more
pile of 1200mm diameter will be selected for dynamic testing. Additional test may be
carried out if required. The final decision in this regard will be made by PMC.
16.3
Failure of Test
If the result of any test is found to be unsatisfactory the Contractor shall carry out
remedial measures after obtaining due approvals from PMC and cost of repeating
test on such pile will be borne by Contractor.
17.0
MEASUREMENTS
17.1
17.2
Boring shall be measured separately in running meters and length shall be from
bottom level of the pile cap to the bottom of level of pile.
17.3
Concrete shall be measured separately in running meters from the founding level to
300 mm above the theoretical cut-off level of the pile. Volume of Concrete shall be
paid on theoretical volume of pile.
17.4
17.5
18.0
Technical Specifications
GENERAL
1.
STRUCTURE NO.__________
2.
3.
GROUND LVL(RL)__________
4.
5.
6.
7.
G.W.T.
8.
(RL)___________
Page 12 of 14
Section-3.0
(II)
(II)
(II)
(III)
A.
B1
B2.
BORING
1.
2.
3.
4.
(UPTO
HARD
STRATA)
CHISEL WEIGHT______MT.
2.
3.
4.
5.
6.
7.
TYPE OF MACHINE.
2.
3.
4.
TIME REQUIRED TO
WEATHERED ROCK.
5.
6.
CUT
SOCKET
LENGTH
IN
FLUSHING/CLEANING
(A)
2.
(IV)
3.
FLUSHING TIME___________________
4.
AT START
(b)
AT END
CONCRETE
Concrete Supplied by :
GRADE M-
Technical Specifications
1.
DATE __________
2.
3.
Section-3.0
(V)
4.
SLUMP _____________mm
5.
6.
REINFORCEMENT
1.
(VI)
BORELOG REMARKS:
Ground Water
PMC'S REPRESENTATIVE
Time
Strata
CONTRACTORS REPRESENTATIVE
*****
Technical Specifications
Page 14 of 14
Section-3.0
1.0
2.
Quantities given are tentative and any changes will not allow the contractor to claim extra
on the rates quoted.
Quantities stated in the item are not to be used for ordering of any material. Contractor
shall verify quantities himself and order with suppliers shall be placed with required
wastages. Copies of orders shall be forwarded to EIC to verify date of order, supplier and
materials ordered.
3.
All materials to be used at the site shall be tested as per specifications or as per the IS.
Testing shall be done at site and / or at approved laboratories as specified or as directed
by the EIC at the cost of contractor. Any defective or unapproved materials will be
removed from site immediately at Contractors cost.
4.
The contractor shall be responsible for protection of his own work and the work of other
trades during the progress and till handover to the Employer.
6.
Contractor shall provide, required rigid double-legged steel scaffolding accessible at all
locations with safety rails.
8.
Contractor to organize himself for safe storage, handling, site offices, labour
accommodation if any at his cost. No extra cost payable on this account.
9.
Price of each item inserted shall be considered as self-supporting and do not have any
bearing on other items of the project.
10.
Contractor shall engage sufficient number of labour and Supervisors / Mukadam at site
full-time while the work is carried out, to ensure proper execution of the work. Authorized
representative should be available as and when required by the Employer.
11.
Contractor shall not employ at work site any persons working with Employer or persons
dismissed/suspended/retired from the services of the Employer, unless specific prior
permission in writing is given by the Employer for such employment.
12.
Contractor shall also not employ any person who is or may be working with other
contractor, and also those against whom the Employer may take exception.
13.
Contractor and all of his workers, servants, agents and officers employed by contractor
shall observe the rules and regulations of the Employer particularly in regard to entry and
exit and search by the Employers authorised personnel.
14.
Contractor shall not employ any female employees between 6-00 P.M. and 6-00 A.M.
15.
Contractor shall ensure that all workmen refrain from smoking or carrying matches, fire
or naked light or other means of producing naked lights or sparks or flames or fire, and
any damage, loss, injury, harm or action to or against the Employer due to breach these
provisions on the part of Contractor / Sub - Contractor will be fully made good by
Contractor. Smoking is prohibited all over the premises.
16.
Contractors workers drinking alcohol inside the premises and workers come in the
premises after consuming intoxicants/liquor are strictly prohibited.
17.
If any worker shall meet with accident, contractor must provide adequate financial help
immediately for treatment at the hospital or outside facilities, including transport etc.
18.
Contractor shall show all Challans of materials to be shifted including debris at security
gate while bringing in vehicle and all materials/tools taking outside the premises shall be
verified by the Security of the Employer.
19.
Contractor shall ascertain where to stock materials like tools / plants, machinery, etc.,
wherever applicable, prior to bringing them on site and depute his representative to take
delivery of such materials and to ensure that the materials are unloaded and are stocked
in specified area only. In case of wrong unloading he shall be immediately shift to proper
places as the case may be and as directed by the EIC of the Employer at Contractors
risk and cost. The Employer shall not be responsible for loading, unloading or checking
of contractors materials or detention of contractors trucks due to the absence of his
representative.
20.
The movement of workers or vehicles within the premises shall be restricted only to the
place of work assigned to contractor.
21.
Contractors shall also be liable to the Employer for any act of commission or omission on
the part of contractors employees thereby causing loss, damage inconvenience to the
Employer.
22.
23.
The Employer may after issuing the order, require the Contractor to alter, to omit, add to
or otherwise vary the works due to any change in their plan, after mutual discussions.
24.
Contractor shall be responsible and liable to ensure that in course of carrying out /
performing the Contract, no provisions of any laws, Bye Laws, Rules or Regulations
are violated or contravened. Contractor shall be responsible if any loss, damage or harm
is caused to the Employer as a result of or arising out of or directly or indirectly due to
any breach, violation or contravention of any Laws / Rules of regulation on the
Contractor / Sub Contractor part, or on the part of any contractors officers, servants,
workers, or agents even if such breach, violation or contravention occurs not in course of
carrying out / performing the Contract.
2.0
PILING WORK
Work and rate shall include
a)
b)
c)
d)
e)
Casting of piles including cleaning, maintaining necessary cover, providing casing and
removing as specified
f)
g)
h)
Demobilisation on completion
i)
Cleaning and disposing off bored, slushy earth outside the site at approved location by
statutory bodies.
j)
Testing of materials
k)
*****
BILL OF QUANTITES
Sl No
1
1.1
1.1.1
a.
b.
1.1.2
a.
b.
1.2
a.
b.
1.3
a.
b.
1.4
Item Description
Unit
Rate
- Rs
Quantity
Amount
Rs
PILING WORK
Installing Rotary drill bored cast-in-situ reinforced cement concrete
end bearing piles (Concrete & reinforcement paid separately); driving
temporary steel casing pipe of 8 MM thickness with stiffener band
and with sharp cutting edge up to bottom to non-collapsible strata,
boring in over-burden and through all type of strata encountered up
to the founding level as described in the specification; socketing in
approved strata, using bentonite slurry, including disposal of all bored
materials at the disposal point earmarked etc. complete as per
drawings and specifications.
Boring in all types of soil strata like clay, murrum, slushy soils, sandy
soils, soil mixed with stones, boulders. .
600mm dia
1000mm dia
Boring and chiseling through boulders, weathered rock, hard rock etc.
600mm dia
1000mm dia
Providing and concreting of bored cast in situ end bearing piles
conforming to IS 2911,Part I, with M30 Concrete (minimum cement
content as per IS 456 or specified by Structural Consultant whichever
is more) through tremie pipe; including use of super plasticisers and
other additives as approved, to correct level, providing and
withdrawing required steel casing up to the depth of non-collapsible
strata or as directed etc.; including finishing of pile heads as per
specifications, and completing as per drawings and specifications, all
complete to the satisfaction of the PMC. (Concreting of piles to be
carried out for 600mm above the cutoff level which will not be paid,
being contaminated concrete.)
600mm dia, capacity 180 Tonne
1000mm dia, capacity 500 Tonne
Empty Boring measured from the existing ground level to the cut-off
levels of the piles. Further it shall be filled with approved dry sand.
600mm dia
1000mm dia
Providing and fixing steel reinforcement for RCC, including
transporting, de-coiling, straightening, cutting, bending, and placing in
position at all levels and depths and binding with approved quality
G.I. annealed binding wire of 18 gauge for end bearing cast-in-situ
piles conforming to IS 2911,Part I with correct size PVC cover blocks
or approved concrete cover blocks of same grade as of concrete. The
rate shall include cost of binding wire, chairs, spacers, pins, which
will not be measured separately for payment. Quantity of steel as per
bar bending schedule as approved by the PMC and with authorized
overlaps only shall be measured and paid for. Further include where
required carryout dewatering, provide required labour and machines /
equipments / tools / tackles for handling, shifting, bending, binding,
etc. all complete to the satisfaction of the PMC at all depths & leads.
a. High yield strength deformed TMT bars conforming to IS 1786 - Fe
500 grade
Rmt
Rmt
2643
6836
Rmt
Rmt
294
1368
Rmt
Rmt
2936
8203
Rmt
Rmt
294
1231
MT
846
1.5
Vertical load testing of piles in accordance with IS 2911 (Part IV) with
conventional method including installation of loading platform and
preparation of pile head or construction of test cap and dismantling of
test cap after test etc. complete as per specification and as per the
directions of PMC
Nos.
Nos.
1.6
a.
Nos.
b.
Nos.
13
1.7
Nos.
233
Nos.
651
a.
b.
GRAND TOTAL