0% found this document useful (0 votes)
142 views

ACC103 Assignment-Q1

Roman Ltd's Finishing Department report summarizes production costs for March 2013. It began the month with 50,000 units in work-in-process that were 25% complete. During the month, it completed and transferred out 140,000 units, and ended with 40,000 units that were 30% complete. The report provides a breakdown of material, labor, and overhead costs for work-in-process units at the start and end of the month, as well as costs incurred during March production.

Uploaded by

mingren93
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
142 views

ACC103 Assignment-Q1

Roman Ltd's Finishing Department report summarizes production costs for March 2013. It began the month with 50,000 units in work-in-process that were 25% complete. During the month, it completed and transferred out 140,000 units, and ended with 40,000 units that were 30% complete. The report provides a breakdown of material, labor, and overhead costs for work-in-process units at the start and end of the month, as well as costs incurred during March production.

Uploaded by

mingren93
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Roman Ltd.

The following data have been compiled for Roman Ltd's Finishing Department for the month of Mar 2013.
Work in process, 1 Mar - 50,000 units :
Direct Material: 100% complete, cost of
Mixing department
Finishing department direct material
Conversion: 30% complete, cost of
Finishing department direct labour
Finishing department overheads
Units completed during Mar and transferred out:

$1,100,000
$850,000
$150,000
?
140,000 units

Work in process, 31 Mar - 40,000 units:


Direct material: 100% complete
Conversion : 30% complete
Cost incurred during Mar :
Material added
Direct labour
Overheads

$3,055,000
$3,900,000
?

Information:
(i)
Additional materials are added when processing is 20% complete in Finishing department.
(ii)
Conversion activity occurs uniformly throughout the production process.
(iii)
Overhead is allocated on the basis of 110% of direct labour cost.
(iv)
Units transferred in from Mixing were charged at $28.00 per unit.

the month of Mar 2013.

A
29
30

Roman Ltd.
Production Cost Report for Mar 2013 : Finishing Department

31
32
33 Work in process, 1 Mar
34 Unit transferred-in during Mar
35 Total units to account for

Physical
Units

Percentage of
Completion with
Respect to Conversion

Equivalent Units
Transferred-in Direct Material

50,000
130,000
180,000

25%

140,000
40,000
180,000

100%
30%

Conversion

36
37
38
39
40

Units completed &


transferred out
Work in process, 31 Mar
Total units accounted for
Total equivalent units

140,000
40,000

140,000
40,000

140,000
12,000

180,000

180,000

152,000

41
42
43 Work in process, 1 Mar
44 Current period
45 Total costs to account for
46
47
48
49
50
51
52
53
54
55
56
57

Equivalent units
Costs per equivalent unit ($)

Transferred-In
($)
Direct Material ($) Conversion ($)
1,100,000.00
850,000.00
315,000.00
3,640,000.00
3,055,000.00
8,190,000.00
4,740,000.00
3,905,000.00
8,505,000.00

Total ($)
2,265,000.00
14,885,000.00
17,150,000.00

180,000
26.33

103.98

Assignment of cost :
Cost of goods completed and transferred-out
Cost remaining in Mar 31 work in process inventory
Transferred-in:
$ 1,053,333.33
$ 867,777.78
Direct Material:
$ 671,447.37
Conversion:
Total cost accounted for

14,557,441.52

$
$

2,592,558.48
17,150,000.00

180,000
21.69

152,000
55.95

A
58
59
60
61
62
63
64

Q1. (b)(i)
Assumed that conversion costs of Finishing Department in Mar increased by 20%.
New conversion cost per equivalent unit
New total cost per equivalent unit
New cost of units completed and transferred-out

66.73

16,066,125.73

114.76

A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

Q1. (a)(ii)
PROCESS COSTING SPREADSHEET 2 : FIFO Method
PROCESS DETAILS
% Completion Material added
conversion costs assumed incurred uniformly

20%

PRODUCTION DETAILS
Work in process, 1 March
Units completed & transferred out during March
Work in process, 31 March
% Completion of O/WIP
% Completion of C/WIP

50,000 units
140,000 units
40,000 units
25%
30%

Overhead is allocated on the basis of 110% of direct labour cost.


Work in process, 1 March, cost includes :
Department- Mixing costs
Department- Finishing direct materials
Department- Finishing direct labour
Department- Finishing overheads

$
$
$
$

1,100,000.00
850,000.00
150,000.00
165,000.00

During the month of March, costs were :


Materials added
Direct labour
Overheads

$
$
$

3,055,000.00
3,900,000.00
4,290,000.00

Units transferred in from Mixing in March were charged at $28.00 per unit.

You might also like