PMP Formulas List
PMP Formulas List
If you think a formula is missing here but required in PMP exam. Post a comment and we will
add to this table.
1. PERT
2. Standard Deviation
3. Variance
4. Float or Slack
5. Cost Variance
6. Schedule Variance
7. Cost Perf. Index
8. Sched. Perf. Index
9. Est. At Completion (EAC)
18. BCWS
19. BCWP
20. ACWP
21. Order of Magnitude Estimate
22. Budget Estimate
23. Definitive Estimate
24. Comm. Channels
25. Expected Monetary Value
26. Point of Total Assumption
(PTA)
Sigma
Or PV or Revenue / PV of Cost
Less is better
Net Investment / Avg. Annual cash flow.
PV
EV
AC
-25% - +75% (-50 to +100% PMBOK)
-10% - +25%
-5% - +10%
N(N -1)/2
Probability * Impact
((Ceiling Price - Target Price)/buyer's Share Ratio)
+ Target Cost
1 = 68.27%
2 = 95.45%
3 = 99.73%
6 = 99.99985%
Net Income Before Taxes (NEBT) / Total Sales OR
Net Income After Taxes ( NEAT ) / Total Sales
NEBT / Total Assets OR
NEAT / Total Assets
NEBT / Total Investment OR
EF = (ES + Duration - 1)
EVA = Net Operating Profit After Tax - Cost of Capital (Revenue - Op. Exp - Taxes) (Investment Capital X % Cost of Capital) EVA - Economic Value Add Benefit Measurement
- Bigger is better
Comprehensive notes by PMZilla Members. up Memorizing Inputs Tools and Outputs updated for PMBoK 4th Editon
i date asia
You're what
You're what blogging needs, an open minded superhero who isn't afraid to tell it like it is. This
idateaisa scam
Sigma
Submitted by ram6s9 on Fri, 06/06/2008 - 21:28.
For the sake of completeness, I guess it would be better to include the Six Sigma value too.
6 Sigma = 99.99985
(P + 4M + O ) / 6 is
Submitted by o3dr0p0ut1o on Thu, 02/17/2011 - 14:48.
(P + 4M + O ) / 6
Franchise
Submitted by MichelSteve on Fri, 10/21/2011 - 11:38.
I just checked the MDAS rule and after this i got know that it is true.Any how tahnks for
recommending.
Franchises
PMBOK 4 Formula's
Submitted by miansahib on Tue, 09/15/2009 - 22:08.
Hi Gurus,
May I know some one maintaining these formula's and updating for PMBOK4.
also I want to know How many Formula's are in Total in PMBOK4 and can someone please
share if already got it.
Regards,
Thanks
Chandra
operand
EV
operand
---------------
PV
--------------
CV=
SV
CPI=
SPI
Helpful
Submitted by twenty20 on Mon, 03/26/2012 - 08:44.
This is really helpful ! Thanks for compiling !!
Cheers, Naveen
ROM RANGE
Submitted by sspawar on Thu, 08/23/2012 - 15:20.
PMBOK 4 IS +/- 50%,
AND IN ABOVE LIST IT IS -50/+100 %, I THINK IT WAS IN PMBOK 3.