Commissioning Test Procedure Overhead Lines
Commissioning Test Procedure Overhead Lines
December 2011
TABLE OF CONTENTS
PURPOSE
The purpose of this document is to identify generic requirements applicable to the testing &
commissioning of new Subtransmission Overhead Power Line systems associated with Essential
Energys network infrastructure.
This procedure applies to all new overhead line installations that are to be connected to Essential
Energys network. The use of this procedure is for Accredited Service Providers, Essential Energy
staff and accredited sub-contractors.
The purpose of undertaking overhead line testing is to prove system integrity after installation work
is completed and before connection to the Essential Energy Network.
The tests specified within this procedure are minimum requirements. Additional tests or
amendments to testing requirements may vary depending upon project/site conditions.
Testing requirements will be negotiated between Essential Energy & the Accredited Service provider
after submission, to EE by the ASP, a project specific commissioning program.
All electricity works shall be designed to be safe for the electrical conditions likely to be experienced
during service and the physical environment in which they will operate. EE needs to ensure that
appropriate tests have been completed before an installation is commissioned into service for
compliance with the design & specifications. This will require close cooperation between the ASP1s
construction AR and EE.
EE will appoint a commissioning manager or QCC auditor as EEs representative for coordination
purposes.
3a
Tests
Before any tests are performed, EE and the AR must agree on the procedures to be used for the
tests and any modification to or deletion from this procedure.
EEs QCC auditor shall be notified a minimum of 10 working days prior to the commencement of line
installation or any tests to be undertaken.
The AR will be responsible for ensuring that the completed work is QA checked and tested and all
records and reports are forwarded to the QCC promptly.
EEs QCC auditor may be present to witness the testing procedures, and only with EE approval shall
proceed to test.
Tests must be carried out in the presence of representatives nominated by the AR and EE. The AR
must provide the results of tests to EE as requested by EE, within a maximum time period of 10
working days.
All test results shall be documented and submitted to EE including the following detail:
Testing organisation details.
Date, time and location of test.
Description of line tested.
Description of test equipment used including calibration dates.
Test procedure.
Test results.
If tests indicate that corrective works are required to ensure line integrity the AR must then:
Undertake, at their cost, all rehabilitation, modification or remediation work required to the
reasonable satisfaction of EE.
Report back to EE in writing when all corrective work has been completed and renegotiate a
suitable program to recommence tests.
3b
Test Equipment.
All test equipment and instrumentation used for testing shall have been calibrated by a NATA
Accredited organisation and have a current test sticker affixed. The AR is responsible for ensuring
that test equipment and instrumentation is traceable.
COMMISSIONING
4a
4c
As Installed Detail
On completion of construction and prior to final commissioning of the overhead line installation the
ASP is to provide the following As Installed detail to EE :
As Installed detail shall be provided to EE in electronic form as well as hard copy. Electronic
documentation is required in the following formats :
PRE COMMISSIONING
5a
QA Checks
During the installation a system of records shall be maintained which provides objective evidence
that requirements have been met, including construction in accordance with applicable standards,
construction drawings/plans and specifications.
All records shall be available for audit and review by EE during the installation. The records should
provide full traceability of all quality characteristics and activities.
During construction activities QA mechanisms such as check sheets, checklists, inspection & test
plans (ITPs) shall be utilised for an EE representative to witness and sign off.
EEs QCC auditor may be present to witness the installation at hold points, as required by EE, and
work shall not proceed past a hold point without EE consent.
5b
Notice of Completion
On completion of construction works and prior to final commissioning the AR is to submit a notice of
completion to EEs QCC auditor.
The completion notice is to include
T&C Plan.
CEPG 2047 written notification.
As Installed Plans and documentation.
A final inspection/audit will be carried out by EEs QCC auditor along with the ASP1s AR.
5c
Final Inspection/Audit
The purpose of the final inspection/audit is to ensure the new asset is acceptable to EE for
connection to EEs transmission network.
A review will be undertaken of the following
Vegetation & Environmental Management.
Access.
Construction Quality Assurance including visual inspection of works and sign off of non-conformance
issues.
The purpose of pre commissioning tests are to confirm line integrity & compliance with the earthing,
EPR & protection studies carried out and approved for the project.
The required pre commissioning tests for subtransmission overhead lines are :
Structure Earth Resistance Test.
Phase Continuity Test
Insulation Resistance Test.
Earth Current Injection Test.
OPGW Tests.
6a
After completion of structure installation but prior to the installation of any OHEW/OPGW, the
electrical resistance of structure earthing shall be measured by the ASP1. EEs QCC auditor or
nominated representative may be present to witness tests. The results shall be supplied to EEs QCC
auditor without delay for review.
The ASP1 may be directed by EE to install supplementary earthing where readings exceed the
required value. The installation of supplementary earthing shall be in accordance with EE standards
and shall be completed prior to the installation of OHEW/OPGW. The supplementary earthing shall
be installed so as to comply with the specified electrical resistance of each structure to earth.
6b
A phasing check shall be completed prior to commissioning to ensure that the phases are correctly
aligned to synchronise with the network to which the line is to be connected.
6c
An insulation resistance check ie megger test, shall be completed prior to commissioning to ensure
no inadvertent short circuits.
6d
For shielded lines, earth current injection tests shall be undertaken and the following measurements
taken at each support structure
Line Earth Impedance.
Step & Touch Potential.
Earth Potential rise.
Zero Sequence Impedance.
Recorded test measurements are to confirm compliance with the requirements of AS/NZS 7000.
Tests shall be performed after the substation earth mats at all ands of the line are fully installed and
connected.
6e
OPGW Tests
The testing of system components to identify the apparent performance of the optical fibres before
and after the responsibility of the component has been transferred between independent parties is
essential.
EE advocates that the stringing and splicing activities to be carried out by specialised accredited
service providers. It is mandatory that the following testing procedures are implemented between
each interface and progressively throughout the works to ensure the separate activities are
adequately controlled.
6e.1
Either mini or Full Featured Optical Time Domain Reflectometer (OTDR) instruments, immune to
polarisation noise and conforming to the Telcordia/Bellcore Standard GR-196-CORE Generic
Requirements for Optical Time Domain Reflectometer Type Equipment, are to be used for all
OTDR measurements.
The OTDR must be capable of storing the traces on an electronic medium (eg floppy disk or USB
stick) for transportation/submission, allow retrieval and reading of traces. All traces are to be stored
and submitted in a format compatible OTDR 3.0 emulation software, the preferred trace formats
are : Telcordia standard SR4731 Rev 2.0 (SOR extension files) or GR 196 compatible file format.
The OTDR testing is to be carried out at either 1310nm, 1550nm and/or 1625nm wavelengths. The
1625nm OTDR trace is primarily used to identify pressure points, macro bends and imperfections in
cable installations.
The OTDR operator must be experienced in the use of high performance OTDRs and shall, have
attended an approved TITAB OTDR training course.
6e.2
The AR shall provide fusion splices with an average attenuation below 0.1dB when measured at
1550nm. Any fusion splice with attenuation above 0.1dB shall be re-spliced and re-tested.
The approved methodology comprises measuring in both directions, using an OTDR, the attenuation
of each splice for all fibres. The average of the two readings for each fibre will be accepted as the
splice attenuation for each fibre. In addition the end to end attenuation of each fibre in each
direction shall be measured using a calibrated light source and light meter.
All measurements shall be made with an accuracy of 0.01dB and shall not be made over sections
greater than the capability of the OTDR in use.
Testing of unterminated fibres shall be performed by splicing temporary pigtails to the fibres or by
using a Bare Fibre Adapter. A terminated fibre refers to fibres terminated with connectors on patch
panels at an ODF and/or at equipment.
6e.3
Drum Test
Upon receipt, by the AR, of the OPGW from either the ARs supplier or EE the AR shall check the
cable attenuation and continuity of each drum. The AR shall conduct a one way OTDR test for all
optical fibres for all drums from the inside end. The inside end of the cable is accessible for one way
Testing & Commissioning Proceedure Generic V2
December 2011
Prepared by: Dennis Darke
Page 8 of 10
OTDR testing at the nominated wave lengths (1310, 1550 and/or1625nm), without removing the
laggings.
Following testing the cable ends shall be resealed with a suitable heat shrink end cap to ensure
against moisture or dirt ingress.
The AR shall give EE a minimum of 48hours notice before conducting these tests. If the OPGW is
supplied by EE the Drum Test is to be carried out at EE store prior to transport to site.
Any problems or discrepancies encountered shall be immediately reported to EE. The AR shall
provide EE with a report of test results within 10 working days of product issue.
6e.4
Span Test
The span test is a two way OTDR test at the nominated wave lengths (1310, 1550 and/or 1625nm).
The span test shall be conducted, by the AR, progressively as each drum is strung and clamped off.
Any problems are required to be identified and rectified prior to splicing.
The same test equipment shall be used as for the Drum Test.
The AR shall test the strung OPGW only after all clipping in is complete and in the presence of an EE
nominated representative at a time to be mutually agreed upon. The AR shall notify EE at least
48hours in advance of the tests proceeding.
6e.5
Splice Test
The AR shall measure the attenuation, of each splice, in both directions at both 1310nm and
1550nm.
The AR shall submit to EE a Splice Testing Strategy. This strategy is to demonstrate how the AR
intends to measure each splice in order to guarantee the average loss per splice was achieved
throughout all the splices on the link.
The same test equipment shall be used as for the previous tests undertaken.
6e.5
The AR shall measure the end to end attenuation of each optical fibre. The same test equipment
shall be used as for the previous tests undertaken.
The AR shall submit to EE a Fibre Testing Strategy to guarantee the average loss per splice was
achieved throughout the fibre link.
The AR shall
Are placing the transmission line into service the following commissioning tests may be required :
Radio Frequency Radiation Test.
Thermal Scan under load.
These tests may be requested by EE to be carried out by the ASP1 at full cost to the ASP1. If
required these tests will be requested prior to the end of the construction warrenty period.
7a
Radio frequency radiation measurements are carried out to ensure that any interference is less than
the values specified in AS 2344 Limits of electromagnetic interference from overhead a.c. power
lines and high voltage equipment installations in the frequency range 0.15to 1000MHz.
Where interference exceeds these values, the sources of interference must be identified and
corrective action taken before re-testing.