EEP - Preparing To Synchronize A Generator To The Grid
EEP - Preparing To Synchronize A Generator To The Grid
http://us.mg1.mail.yahoo.com/dc/launch?.gx=1&.rand=88mniifk1e4hg&re...
Subject:
From:
To:
Date:
Published on Mar 27, 2013 01:20 am by Edvard | Subscribe to Monthly Download Updates
Preparing to synchronize a generator to the grid (on photo: General Electric steam turbine generator)
1 of 5
4/1/2013 12:42 AM
http://us.mg1.mail.yahoo.com/dc/launch?.gx=1&.rand=88mniifk1e4hg&re...
Conditions
In order to synchronize a generator to the grid, four conditions must be met:
1.
2.
3.
4.
Phase Sequence
Voltage Magnitude
Frequency
Phase Angle
1. Phase Sequence
The phase sequence (or phase rotation) of the three phases of the generator must be the same as the
phase sequence of the three phases of the electrical system (Grid).
The only time that the phase sequence could be wrong is at initial installation or after maintenance. There
are two possible problem sources.
The generator or transformer power leads could actually be interchanged during maintenance orthe potential
transformer leads could be interchanged during maintenance.
2. Voltage Magnitude
The magnitude of the sinusoidal voltage produced by the generator must be equal to the magnitude of the
sinusoidal voltage of the grid.
If all other conditions are met but the two voltages are not the same, that is there is a voltage differential,
closing of the AC generator output breaker will cause a potentially large MVAR flow.
Recall that before a generator is synchronized to the grid, there is no current flow, no armature reaction and
therefore the internal voltage of the generator is the same as the terminal voltage of the generator.
If the generator voltage is higher than the grid voltage, this means that the internal voltage of the
generator is higher than the grid voltage. When it is connected to the grid the generator will be overexcited
and it will put out MVAR.
If the generator voltage is less than the grid voltage, this means that the internal voltage of the
generator is lower than the grid voltage. When it is connected to the grid the generator will be under-excited
and it will absorb MVAR.
2 of 5
4/1/2013 12:42 AM
http://us.mg1.mail.yahoo.com/dc/launch?.gx=1&.rand=88mniifk1e4hg&re...
3. Frequency
The frequency of the sinusoidal voltage produced by the generator must be equal to the frequency of the
sinusoidal voltage produced by the grid.
Figure 3 shows the condition where the generator and grid have matching speed. The high points and
zero crossings of the sinusoidal voltages occur at the same rate of speed.
However, if you notice in 2 with the grid and a phase angle exists between them. This would appear as a
3 of 5
4/1/2013 12:42 AM
http://us.mg1.mail.yahoo.com/dc/launch?.gx=1&.rand=88mniifk1e4hg&re...
non-rotating synchroscope (both generator and grid at same frequency), where the pointer would appear
stuck at about 9:00 oclock (generator lagging grid).
If the generator breaker were to be closed at this time, the grid would pull the generator into step.
However, this again would cause a large current in-rush to the generator and high stresses on the
rotor/stator with subsequent damage to the generator. If the generator were leading the grid, it would try
to immediately push power into the grid with the same destructive forces as mentioned.
Hence the generator must be brought to a point where the grid voltage waveform exactly matches what it is
producing.
4. Phase Angle
As previously mentioned, the phase angle between the voltage produced by the generator and the voltage
produced by the grid must be zero.
The phase angle (0 to 360) can be readily observed by comparing the simultaneous occurrence of the
peaks or zero crossings of the sinusoidal waveforms.
If the generator breaker is closed when they match exactly, the connection will appear smooth and
seamless.
At that instance (Figure 4 below), the pointer on the synchroscope would indicate 12:00 oclock.
The worst case occurs if the generator is exactly out-of phase, with a phase angle of 180 and the
synchroscope pointing at 6:00 oclock.
Resource: Science and Reactor Fundamentals Electrical CNSC Technical Training Group
Jump to original technical article at EEP - Preparing to synchronize a generator to the grid
Category & Tags: Energy and Power, frequency, generator, grid, phase angle, phase sequence,
4 of 5
4/1/2013 12:42 AM
5 of 5
http://us.mg1.mail.yahoo.com/dc/launch?.gx=1&.rand=88mniifk1e4hg&re...
4/1/2013 12:42 AM