15 Estimates 11
15 Estimates 11
COMMITTEE ON ESTIMATES
(2010-2011)
ELEVENTH REPORT
ELEVENTH REPORT
COMMITTEE ON ESTIMATES
(2010-2011)
(FIFTEENTH LOK SABHA)
CONTENTS
Page No.
COMPOSITION OF THE COMMITTEE ON ESTIMATES (2010-11)
COMPOSITION OF THE COMMITTEE ON ESTIMATES (2009-10)
INTRODUCTION
CHAPTER I
INTRODUCTORY
CHAPTER II
CHAPTER III
CHAPTER IV
(i)
Budgetary allocation
(ii)
Resource mobilization
(iii)
Public-Private Partnership
13
18
35
(NHDP)
(ii)
(iii)
Toll Policy
(iv)
(v)
Delayed projects
(vi)
Non-performing contractors
(vii)
Maintenance
41
45
52
66
76
80
88
93
(ix)
Sub-contractoring of projects
(x)
Environmental clearance
(xi)
Port-connectivity projects
(xii)
projects
97
101
in
North-Eastern
103
108
OBSERVATIONS/RECOMMENDATIONS
110
ANNEXURES
(i)
153
155
157
159
(Under implementation)
(v)
184
192
194
Projects (Completed)
(viii) List of Terminated Contracts
197
199
200
203
APPENDICES
(i)
206
on 22.09.2009
(ii)
208
on 30.03.2010
(iii) Minutes of the Sitting of the Committee held
210
on 07.04.2010
(iv) Minutes of the Sitting of the Committee held
212
on 24.09.2010
(v)
214
on 10.03.2011
(vi) Minutes of the Sitting of the Committee held
on 26.04.2011
216
3.
4.
5.
6.
7.
8.
9.
Shri P. Karunakaran
10.
11.
Shri M. Krishnaswamy
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
Shri S. Semmalai
23.
24.
25.
26.
27.
28.
29.
30.
SECRETARIAT
1.
Shri P. K. Grover
Joint Secretary
2.
Additional Director
3.
Deputy Secretary
4.
Executive Assistant
(iv)
3.
4.
5.
6.
7.
8.
9.
Shri P. Karunakaran
10.
11.
Shri M. Krishnaswamy
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
Shri C. Rajendran
22.
Shri S. Semmalai
23.
24.
25.
26.
27.
28.
29.
30.
(v)
INTRODUCTION
2.
Estimates (2009-2010), taking into account the urgent need to develop a functional,
efficient and well knit network of National Highways, not only to meet infrastructural
requirements but also to provide a boost to the economic development. The subject
National
Highways
Development
Project
including
implementation
of
Golden
Quadrilateral was carried forward for examination & report during the year 2010-2011.
3.
The Committee held five sittings on the subject. The representatives of the
Ministry of Road Transport & Highways briefed the Committee on 22.09.2009 on the
subject. The Committee took their oral evidence on 30.03.2010, 7.04.2010, 24.09.2010
and again on 10.03.2011.
4.
The Report was considered & adopted by the Committee at the sitting held on
26.04.2011.
5.
The Committee would like to express their deep appreciation of the valuable
6.
The Committee wish to express their thanks to the representatives of the Ministry
of Road Transport & Highways and National Highways Authority of India (NHAI), who
appeared before them and placed their considered views on the subject. The
Committee also wish to thank them for furnishing the information required in connection
with examination of the subject during the briefing and oral evidences.
7.
The Committee would also like to place on record their deep sense of
appreciation for the invaluable assistance rendered to them by the officials of the Lok
Sabha Secretariat attached to the Committee.
8.
For
facility
of
reference
and
convenience,
the
observations
and
recommendations of the Committee have been printed in bold letters at the end of the
Report.
NEW DELHI;
26 April, 2011
Vaisakha 6,1933(S)
FRANCISCO SARDINHA,
CHAIRMAN,
COMMITTEE ON ESTIMATES
CHAPTER I
INTRODUCTORY
1.2
India has one of the largest road networks of 3.62 million kms, consisting of
National Highways, Expressways, State Highways, major District Roads, other District
Roads and village Roads. These road networks cater to 60 percent of the freight traffic
and 87.4 percent of passenger traffic.
about 2 percent of the road network, it carries 40 percent of total road traffic. National
Highways have witnessed large expansion in recent years, still, to cater to the
unprecedented growth of road traffic, to provide for the future traffic needs and to
improve accessibility to the hinterland in order to bring them into economic mainstream,
it is imperative that development of wellknit network of National Highways are accorded
highest priority.
1.3
National Highways Development Project (NHDP) the largest highways project ever
undertaken by the country, has been initiated in a phased manner.
The National
Highways Authority of India (NHAI) an autonomous body under the Ministry of Road
Transport and Highways has been entrusted with the implementation of this project.
The NHDP programme began in the late 90s with the Phase I & Phase II, which
envisaged 4/6 lanning of about 14,000 Km of National Highways, at an estimated cost
of about `65,000 Cr. at 2004 prices. These two phases comprise ambitious projects of
Golden Quadrilateral (GQ) that consists of 5,846 Km and connects four metro cities
viz. Delhi, Mumbai, Chennai and Kolkata and NorthSouth & EastWest corridors
(NSEW) which consists of 7,142 Km and connects Srinagar in North to KanyaKumari in
the South including a spur from Salem to Kochi and Silchar in the East to Porbandar in
1
the West. The NHDP also includes Port Connectivity Project comprising a length of
380 Km for improvement of roads connecting 12 major ports in the country. NHDP
programme, at present is being implemented in 7 phases viz. Phase I, II, III, IV, V, VI &
VII throughout the country.
1.4
It is, however, being observed for the last few years that certain critical issues
have plagued the NHDP and created impediments in establishing the envisaged
transport infrastructure. The Economic Survey (2010-11), presented in the Parliament
recently, has categorically stated that achievement has been lower than the target in
NHDP during 2007-2008 to 2009-10. In fact, a negative growth of -32.2% for 2010-11
(April - November) has been observed for NHAI projects. Delay in completion of
projects is foremost among the problems confronting National Highways Development
Project (NHDP). Absence of a Comprehensive Toll Policy, inordinate delays in land
acquisitions
and
Environmental
Clearances,
non-performing
contractors
and
Maintenance of existing Highways are other critical issues which need immediate
attention. Alongwith these, issues such as balanced regional development of National
Highways and Road Safety measures (engineering and technical aspect of Road
Safety) also need to be addressed, if a functional and efficient network of National
Highways is to be created. All this necessitates a concerted, coordinated and coherent
effort made through all channels possible.
1.5
In this backdrop, the Committee took up the subject for detailed examination and
report.
CHAPTER II
ORGANIZATIONAL SET UP AND FUNCTIONS
2.1
The Ministry of Road Transport & Highways, an apex organisation under the
informed that the Ministry has three wings: Roads Wing, Transport Wing and Highways
Wing each entrusted with the following specific functions and responsibilities.
2.3
Roads wing of the Ministry of Road Transport and Highways deals with
2.4
Transport Wing of the Ministry deals with matters relating to Road Transport.
Collects, compiles and analyses road accident statistics and takes steps for
developing a Road Safety Culture in the country by involving the members of
public and organizing various awareness campaigns.
Provides grants-in-aid to Non-Governmental Organisations in accordance
with the laid down guidelines.
2.5
matters
&
programme
management
for
National
Highways
2.6
National Highways Authority of India (NHAI) an autonomous body under the Ministry
of Road Transport & Highways and constituted by an Act of Parliament to develop,
maintain and manage the National Highways vested in or entrusted to, it by the Central
Government.
2.7
The Annual Report (2009-2010) of the Ministry provides the administrative set up
of NHAI. According to it, NHAI, which became operational in February, 1995 is headed
by a Chairman under whom there are five full time Members namely Member
(Administration), Member (Finance), two Members (Projects) and Member (Technical).
There are four part time (ex-officio) Members of the Authority namely Secretaries of the
Ministry of Road Transport and Highways, Department of Expenditure, Planning
Commission and the Director General (Road Development) from the Ministry of Road
Transport & Highways. The Members are assisted by officers at the level of Chief
General Managers, General Managers, Deputy General Managers and Managers. The
Authority has its field offices in the form of Project Implementation Units (PIUs) and
Corridor Management Units (CMU) spread all over the country. These units are headed
by Project Directors who are responsible for the implementation of various NHDP
projects and Operation & Maintenance of completed stretches. All procurements related
4
to civil contractors, supervision of consultants etc. are done by the Head Office. Project
Directors are responsible for pre-construction activities including land acquisition, utility
shifting and liaison with State Governments/Central Government organizations for
successful implementation of the projects.
2.8
Minister
Minister of State
Minister of State
Secretary
Additional
Secretary and
Financial
Advisor
Chief
Controller of
Accounts
Joint
Secretary
(T&G, CVO &
IT Manager)
Joint
Secretary
(Highways)
General
Administratio
n, Motor
Administrativ
Vehicle
e matters of
Legislation,
NHAI, Policy
Road
and
Transport &
Programme of
Safety, O&M
National
Official
Highways,
Language,
Public Private
Vigilance,
Partnership
Grievances,
matters
E-Governance
and EDP Cell
Joint
Secretary
(LA&C)
International
Cooperation,
Coordination,
Land
Acquisition
for National
Highway
projects, all
Toll issues,
Environment
and Forest
Clearances,
Expressway
Authority of
India and
National
Highway
Tribunal
Joint
Secretary
(Estt.)
Director
General (RD)
& Special
Secretary
Advisor
(Transport
Research)
Collection,
Compilation
and
Development
dissemination
&
of statistics of
All
Maintenance
transport,
Establishment
of National
economic/
matters
Highways
Statistical
including CES
other than
analysis of
Central Sector
(Roads)
date for policy
Roads and
planning,
Central Funds
transport
coordination,
etc
1. Regional
Offices at
Bangalore,
Guwahati,
Lucknow,
Jaipur,
Kolkata,
Mumbai,
Bhopal,
Bhubaneswar,
Hyderabad,
Thiruvananthapuram,
Chandigarh
Accounts,
Budget &
Work Study
2. ELOs at
Raipur, and
Dehradun
2.9.
Highways Development Project has been entrusted to Highways Wing of the Ministry.
When asked about the merit of allotting work related to National Highways to two
different wings and the level of coordination between those, the Ministry of Road
Transport and Highways, in a written reply stated:
The allocation of work between the two wings has been done in such a manner
that there is no conflict or duplication. Roads wing is responsible for monitoring
the ongoing NHDP projects while the Highways wing is responsible for policy
matter, appraisal by Public Private Partnership Appraisal Committee (PPPAC)
and approval by Governments.
CHAPTER III
FINANCIAL ASPECTS IN DEVELOPMENT OF PROJECTS
(i)
BUDGETARY ALLOCATION
3.1
According to the Ministry of Road Transport and Highways, the details of Budget
Numeric
Code
Description
REVENUE SECTION (Non-Plan)
3054
BE
2009-2010
` in crs
340.00
340.00
01.00.54
Investment (Cess)
1.03
01.03.53
Major Works
7075
02.00.55
68.00
Total
8918.45
8578.45
272.00
As stated by the Ministry, the following Budget Heads for Estimates are not specifically
mentioned in the prescribed format-
200.00
5000.00
5200.00
3.2
statements for Budget Estimates (2010-2011) and Expenditure (upto 28th February
2011) under Plan and Non-Plan Head:
PLAN HEAD
Allocation and expenditure of important schemes (included in the Annual Plan) of
the Ministry of Road Transport & Highways during the financial year 2010-11
Sl No
Budget
Estimates
Revised
Estimates
(` in crores)
Expenditure
upto
28/02/11
EAP NHAI
a) Externally Aided (NHAI)
b) Loan to NHAI
c) EAP under Road Wing
Sub-total EAP NHAI
a) National Highways (Original)
Works) (Rs. 200 crore for NE
states from MH 4552)
320.00
80.00
100.00
500.00
3958.10
320.00
80.00
1.00
401.00
4656.10
240.00
60.00
0.00
300.00
3120.46
2.00
2.00
0.91
15.00
5.00
0.01
3975.10
1000.00
4663.10
750.00
3121.38
578.21
Rail-cum-Road
bridge,
Munger, Bihar
Development of VijayawadaRanchi Road
100.00
100.00
0.00
100.00
20.00
0.00
700.00
760.00
523.13
7
8
Other charges
Development of information
technology
(i)* BRDB - Strategic Roads
(ii) Strategic Roads under
Roads Wing
0.50
3.50
0.50
3.50
0.01
1.10
100.00
5.00
95.00
1.00
48.07
0.00
3
4
5
10
11
12
13
14
15
16
(*)
6.00
1.50
6.00
1.50
0.57
0.00
6.00
7848.98
195.75
20.00
14.67
230.42
433.00
1057.00
6.00
8440.94
208.27
20.00
15.61
243.88
433.00
1057.00
0.21
5886.25
101.42
0.00
0.00
101.42
231.77
320.96
10.00
10.00
0.63
1500.00
1623.00
1500.00
1623.00
553.36
969.64
17700.00
18615.42
12083.35
NON-PLAN
Allocation and expenditure of important schemes (not included in the Annual
Plan) of the Ministry of Road Transport & Highways during the year 2010-11
Sl No
4
5
Budget
Estimates
other
10
Revised
Estimates
(Rs in crores)
Expenditure
upto
28/02/11
1819.17
54.89
8.60
3.70
3.98
1.86
1.41
0.14
1893.75
1022.86
2635.52
58.40
9.15
3.94
4.23
1.98
1.50
0.15
2714.87
1989.46
1862.36
54.89
3.14
1.09
0.00
0.00
0.00
0.00
1921.48
659.99
34.00
65.00
21.19
1.77
2.00
1.75
1.00
0.28
charges
Equipment & Machinery (NonPlan)
Permanent
International
Association
of
Road
Congress, Paris (PIARC)
Works
financed
from
Permanent Bridge Fee Fund
6
7
8
9
Cost of collection
payable to States
of
fee
Total
* Expenditure upto 31/01/11
(*)
Central Road Fund
3.3
0.50
3.00
0.00
0.06
0.06
0.00
120.00
120.00
92.30
0.50
0.50
0.02
3075.44
4895.64
2695.26
estimates are based, the Ministry of Road Transport and Highways submitted the
following in its written reply:Head
Maintenance
Repairs (M&R)
Investment (Cess)
External
Assistance
Additional
Budgetary Support
(ABS)
IEBR
by NHAI)
11
3.4
The Committee had sought the original estimates, revised estimates and actual
expenditure under each sub-head during each of preceding three years together with
reasons for variations. In this regard, the Ministry of Road Transport and Highways, in a
written reply, furnished detailed statements to the Committee, which are enclosed at
Annexure I, II & III.
3.5
The Secretary, Ministry of Road Transport and Highways also added during
briefing:
.our expenditure under other heads is extremely high. In fact, last year, for the
national highways development, which is done under a planned scheme NH(O)
by the Department through the State Governments, our expenditure has been far
more than what was provided in the Budget Estimates for 2008-2009. This year
also, progress is extremely satisfactory. In fact, under that particular scheme,
which is the major scheme, we have already released about 50 per cent. Overall
our expenditure is about 40 per cent as of now. So, this reflects that the sector
has the potential of absorbing more funds and we have constraint of resources
particularly with regard to maintenance of National Highways. We are receiving
only `1000 crore, that too with the additional allocation of about `200 to `250
crore after the supplementaries....
12
(ii)
3.6
RESOURCE MOBILIZATION
A part of the fuel cess is allocated to the NHAI to fund the implementation of the
NHDP. The fund allocated from the cess is leveraged to borrow additional funds from
the domestic market. The Government of India has also taken loans for financing
various projects under the NHDP from the World Bank (US$ 1,965 million), Asian
Development Bank(ADB) (US$ 1,605 million) and Japan Bank for International
Cooperation (32,060 million yen), which are passed on to the NHAI partly in the form of
grant and partly as loan. The NHAI has also availed a direct loan of US $149.78 million
from the ADB for the Surat-Manor Expressway Project.
Cess fund
External
grant
Assista
nce
loan
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11 (BE)
3269.70
6407.50
6541.50
6972.50
7404.70
7848.98
(8440.94) RE
2400.00
1582.50
1788.80
1515.00
272.00
320.00
500.00
395.50
447.20
379.00
68.00
80.00
Amounts in ` Crore
Borrowings Ploughing back of
Funds deposited
by NHAI in CFI
against toll
collection,
Negative Grant &
Revenue Sharing
1289.00
1500.00
305.20
1096.30
1148.05
7455.00
1623.00
3.7
Total cost of NHDP has been estimated to be `54,000 Crore or US$ 13.2 billions
whose components are as below:Total Cost
`54,000 Crores
Likely sources
20,000
4.90
External assistance
20,000
4.90
Market borrowings
10,000
2.40
4,000
1.00
13
3.8
From the website of the Ministry, the Committee gathered that the National
(i) Through budgetary allocations from the Government of India i.e. Cess:
In a historic decision, the Government of India introduced a Cess on both
Petrol and Diesel. This amount at that time (at 1999 prices) came to a total of
approximately `2,000 crores per annum. Further, Parliament decreed that the
fund so collected were to be put aside in a Central Road Fund (CRF) for
exclusive utilization for the development of a modern road network. The
developmental work that it could be tapped to fund, and the agencies to whom it
was available were clearly defined as :
1.Construction and Maintenance of State Highways by State Governments.
2.Development of Rural Roads by State Governments
3.Construction of Rail over- bridges by Indian Railways
4.Construction and Maintenance of National Highways by NHDP and Ministry of
Road Transport & Highways
At present, the Cess contributes between ` 5 to 6 Thousand crore per annum
towards NHDP.
(ii) Loan assistance from international funding agencies:
Loan assistance is available from multilateral development agencies like
Asian Development Bank and World Bank or Other overseas lending agencies
like Japanese Bank of International Co - Operation.
(iii) Market borrowing:
NHAI proposes to tap the market by securities cess receipts.
(iv) Private sector participation:
Major policy initiatives have been taken by the Government to attract
foreign as well as domestic private investments. To promote involvement of the
private sector in construction and maintenance of National Highways, some
Projects are offered on Build Operate and Transfer (BOT) basis to private
agencies. After the concession period ,which can range up to 30 years, this road
is to be transferred back to NHAI by the Concessionaries. NHAI funds are also
leveraged by the setting up of Special Purpose Vehicles (SPVs).The SPVs will
be borrowing funds and repaying these through toll revenues in the future. This
model will also be tried in some other projects. Some more models may emerge
14
in the near future for better leveraging of funds available with NHAI such as
Annuity, which is a variant of BOT model.
3.9
Highway projects are characterized by back-ended cash flows and require term
loans of longer period (10 to 20 years) with back-ended repayment structure. However,
there is dearth of long-term structured sources of funds. When asked about the steps
taken by the Ministry to assist private investors in taking long-term structured loans, the
Ministry of Road Transport and Highways has stated in a written reply as under:
It is true that highway projects awarded on PPP mode have back ended cash
flows which require term loans of longer maturity. Highway concessions have
tenures extending up to 30 years and they need loan facilities extending for up to
75-80% of such tenure. Unfortunately both capital market as well as institutional
mechanisms appear to have constraints in providing such credit to infrastructure.
Availability of pure project finance for funding the debt requirement has remained
an issue for road SPVs, which are formed to execute these projects. In the
absence of project finance, SPVs have to look at commercial banks for debt.
More than 80% of the road sector projects are funded by commercial banks. In
view of the Assets Liability Mismatch (ALM) of Banks, they are not able to
provide long-term debt (generally taken as average maturity of more than or
equal 10 years). Further, due to the structure of the concession agreement, debt
provided by the lenders is classified as unsecured debt, which comes along with
its own set of issues like maturity profile and exposure norms.
NHAI had made the following suggestions before the B.K. Chaturvedi
Committee in the context of availability of long-term finance for highway projects:
(i)
(ii)
(iii)
(iv)
Long term infrastructure bonds issued by SPVs (with maturity more than 5
years) held by banks and insurance companies should be allowed to be
classified under Held-to-Maturity (HTM) category; and
(v)
Ministry of Finance may ask RBI about the validity of the Escrow and
Substitution agreement as a valid security for secured loan.
15
3.10
Asked to state whether any advice has been sought from the Ministry of Finance/
Planning Commission on this matter, the Ministry submitted in the affirmative and their
response was as under:
a)
long term debt, have already been raised before MoF in other fora. High Level
Committees such as the Deepak Parekh Committee, Patil Committee, Percy S.
Mistry Committee and Raghuram Rajan Committee have also made several
recommendations on the subject. These are structural issues which cannot be
tackled with institution specific solutions. These recommendations are already
being pursued by MoF and several of them are at various stages of
implementation.
b)
It has been the general view of MoF that issues involving financial
would not necessarily augment the availability of finance. Moreover, there are
already several existing financial institutions for this purpose;
(ii)
(iv)
17
(iii)
3.11
PUBLIC-PRIVATE PARTNERSHIP
Traditionally, the road projects were fully financed and controlled/ supervised by
the Government. The implementation of road projects was purely dependent on the
availability/ allocation of funds out of the budget of the Government. It was assessed, at
the time of the preparation of the Tenth Plan that for National Highways alone,
`1,65,000 crore was required for removal of the deficiencies. It is in this context that
alternative innovative means of financing have gained importance for providing an
adequate and sustained support for financing the road projects.
3.12
The galloping resource requirements and the concern for efficiency coupled with
3.13
During briefing, the Committee inquired about the rationale behind the shift
3.14
estimated that even if we did 20 kms stretches, tolling would not be so important;
it would be there, but it was not a primary source of funding. NHAI would be fully
funded by the cess collected on diesel. However, in view of the growing
expectations of the people, on which the hon. MPs are themselves responding, it
was felt that the Golden Quadrilateral would not be enough East West,
North-South and other important Corridors were taken up, and NHDP phase III
was taken up, to connect places of economic importance. And, there was a
switch in methodology in two ways. One was, it was realized that Government
would not be able to deploy the massive budgetary resources necessary for
doing these EPC projects. Therefore, if our target is 20 kms a day and if we have
to cover more roads, which is something which we would also like to do, why not
possible get good high speed roads. The cost in todays prices would be
something between `9 to `10 crore per km. varying according to terrain,
number of bridges, structures. In a dry State like Rajasthan we have fewer
bridges and the cost would be lower, and in a State like Bengal or Kerala,
Orissa, the cost would be much higher. So, it would vary. But it would be the
rough cost, Sir.
The expenditure would be like ` 200 crore per day and for
3.15
The Committee were further informed through a written note from the Ministry
that the Government has chalked out a massive investment plan in the road sector,
under the National Highways Development Programme (NHDP). During the period
2009-2015 an investment of around `3,31,000/- crore has been planned for extensive
upgradation of National Highways network, predominantly in the PPP mode. PPP in
highway development seeks to tap the resources, expertise and professionalism of
private sector for public development under a framework attractive to both parties. The
framework enables a private entrepreneur to secure reasonable returns at manageable
risk and assures the user adequate service quality at an affordable cost and facilitates
the Government in procuring value for public money. Characteristics of infrastructure
projects such as long gestation periods vest it with higher than normal risks. In a PPP
framework the project risks are allocated to the party that is best equipped to manage
them.
19
3.16
3.17
20
(c)
(d)
(e)
(f)
(g)
3.18
(h)
(i)
(ii)
(iii)
Shifting of utilities
(iv)
(ii)
The private sector has more flexible procurement and decision making
procedures and therefore, it can speed up implementation efforts
(iii)
21
(iv)
3.19
(v)
(vi)
While there are a number of forms of Public Private Partnership, the common
forms that are popular in India and have been used for development of National
Highways are - Build Operate and Transfer (BOT) Toll basis.
- Build Operate and Transfer (BOT) Annuity basis.
- Special Purpose Vehicle (SPV) basis
3.20
In a BOT (Toll) Model, the concessionaire (private sector) is required to meet the
upfront/construction
cost
and
the
expenditure
on
annual maintenance.
The
Concessionaire recovers the entire upfront/construction cost along with the interest and
a return on investment out of the future toll collection. The viability of the project greatly
depends on the traffic (i.e., toll). However, with a view to bridge the gap between the
investment required and the gains arising out of it, i.e., to increase the viability of the
projects, capital grant is also provided (up to a maximum of 40% of the project cost has
been provided under NHDP).
3.21
meet the entire upfront/construction cost (no grant is paid by the client) and the
expenditure on annual maintenance. The Concessionaire recovers the entire
investment and a pre-determined cost of return out of the annuities payable by the
client every year. The selection is made based on the least annuity quoted by the
bidders (the concession period being fixed). The client (Government/NHAI) retains the
risk with respect to traffic (toll), since the client collects the toll.
3.22
The NHAI has also formed Special Purpose Vehicle (SPV) for funding road
projects. SPVs are separate legal entities formed under the Companies Act, 1956. It
involves very less cash support from the NHAI in the form of equity/debt; rest of the
funds comes from Ports/Financial Institutions/beneficiary organisations in the form of
22
3.23
On this issue, the Secretary, Ministry of Road Transport and Highways added
3.24
3.25
implementation of NHDP, the outlay for project under NHDP Phase III to Phase VII
during the period 2005-2015 revealing a radical shift in the financing pattern was
submitted to the Committee as shown below:
23
Length in
Phase
Kms
BOT (Toll)
Total Cost (`
in crores)
BOT
(Annuity)
NHDP III
12,109
76,546
76,546
NHDP IV
20,000
6,950
20,850
27,800
NHDP V
6,500
41,210
41,210
NHDP VI
1,000
16,680
16,680
NHDP VII
2,594
9,638
4,448
16,680
3.26
The Ministry of Road Transport and Highways was asked to furnish the status of
BOT projects undertaken so far. The following tabulated statement has accordingly
been furnished:SUMMARY OF BOT TOLL PROJECTS
Status as on 31st January, 2011
Category
Awarded
No. of
Length in
Contracts
km
Total Project
Cost
(Rs Crs)
Completed
No. of
Length in
Contracts
km
NHDP Phase I
454.1
3598
454.1
GQ
373.4
2679.35
373.4
Others
80.7
918.65
80.7
NHDP Phase II
19
992.66
8109.77
14
713.83
NS - EW
16
787.44
6849.77
11
508.63
Others
205.217
1260
205.217
78
6625.17
54009.14
12
666.48
NHDP Phase IV
589
1639.01
NHDP Phase V
19
2300.35
21390.28
152.7
41
2335
Total
131
11002.40
91081.20
38
1987.11
DoRTH
83.4
30
24
NHDP Phase I
Awarded
No. of
Length in
Contracts
km
8
475.57
Total Project
Cost
(Rs Crs)
2353.57
Completed
No. of
Length in
Contracts
km
8
476
GQ
382.57
1979
383
Others
93
375
93
NHDP Phase II
20
1029.65
13912.37
436
11
740.9
4559.88
36
NHDP Phase IV
176.3
2498.76
SARDP-NE
111.80
762.00
Total
42
2534.22
24086.58
16
948
NS-EW
As stated by the Ministry, the BOT projects undertaken so far are too few to
make any impact assessment of these projects.
experienced that BOT projects report more satisfactory progress than traditional EPC
Projects.
3.27
During the meetings, the Committee had expressed their concern over the slow
Upto year 2005 when majority of NHDP Phase I and Phase II were
awarded NHAI Board was empowered to approve individual project for award.
Pursuant to a decision of the Cabinet Committee on Economic Affairs in its
meeting on 27th October 2005, a Public Private Partnership Appraisal Committee
(PPPAC) was set up and system of project wise approval through PPPAC for
25
NHDP projects was brought in. Ultimately this process only delayed the award of
NHDP projects.
b)
such
as Model Concession
Agreement (MCA), Request for Qualification (RFQ) and Request for Proposal
(RFP) caused severe disruption of the award process.
c)
From May06 the water fall mechanism was introduced for award of
issues and obtaining clearances for tree cutting, shifting of utilities etc.
These issues are now being addressed and some recommendations have
been proposed in the B K Chaturvedi Committee report regarding changes in
MCA, RFQ/RFP clauses. Regarding land acquisition, NHAI is setting up special
land acquisition units and Regional Offices have been set up by NHAI to closely
monitor land acquisition issues.
3.28
The Secretary, Ministry of Road Transport and Highways further clarified during
the briefing:There are also changes in the standard documents which are being used for
awarding these projects to the potential bidders. Model Construction Agreement
(MCA) which is the basic document was revised and the whole new provisions
were introduced. Rather I would say the new MCA itself was introduced in place
of the old MCA, which was being followed by NHAI. With this new MCA projects
are being awarded after February, 2008. Besides, the MCA, the bidding process
was made completely transparent and the bidding documents RFQ and RFP
were standardized. The Planning Commission and the Finance Ministry are
primarily responsible for these documents. They have done it very carefully after
taking into consideration the best practices in the relevant areas all over the
world. Therefore, this process took little time because it was a complete switch
over from the old system to the new. Therefore, the progress in awarding
projects in 2007, may be 2006 was bit slow but in 2008 we had awarded the
26
projects very smoothly. However, I would like to mention that in the second part
of 2008 there was a credit crisis.
3.29
Agreement (MCA) and its comparative advantage with the old MCA, the Ministry of
Road Transport and Highways stated the following in a written communication:
Salient features of New MCA:
Sl.
No.
1.
MCA
Clause
Article
2.
Grant
of
Conce
ssion.
2.
26.2
Conce
ssion
Fee/P
remiu
m
The
Concessionaire
is
required to spell upfront
negative grant/premium in
place of Revenue Sharing as
in old MCA.
29.2.3
Effect
of
Traffic
Variati
on
project
highway,
the
Authority would prepare a
DPR for augmentation and
assess
the
cost.
The
Concession period would be
extended to such period
which would yield a return of
16% on the augmentation
cost. Such extension of
Concession period shall be
however limited to 5 (five)
years. In the event of refusal
of the Concessionaire to
underake the augmentation,
an indirect political event will
be deemed to occur and the
Authority may terminate the
Concession
making
a
termination
payment
in
accordance with cl. 34.9.2.
4.
48
& Chan Change in ownership is now
7.1(k)
ge in allowed after 2 years of
owner COD.
ship
5.
40.2(b)
When asked to comment on the reports that bidding process failed to attract
investors due to severe cash crunch, high cost of borrowing, lack of realistic data in
detailed project reports (DPR) and faulty traffic estimates prepared by NHAI, the
Ministry of Road Transport and Highways stated the following in a written reply:-
28
a)
The phenomena of severe cash crunch, high cost of borrowing and falling
traffic growth was the immediate fall out of the financial market meltdown which
occurred during mid 2009. The world then had to brave one of the harshest
recessions of our times, which has slowed down the global economy. The crisis
has hit India too, though the effect has not been as severe as in many developed
countries. India faced the crisis better because our growth is driven by domestic
demand both consumption and investment. Consumption and saving are well
balanced. In India, the share of private final consumption expenditure in GDP is
around 55 per cent. The Government announced a slew of measures which
moderated the impact of this recession. Currently no trace of such difficulties
remains and there are a large number of entrants eager to enter the road sector.
In fact, NHAI had to put certain measures in place to ensure that non-serious
entrants do not enter the field.
b)
3.31
The Ministry, in their latest reply, has further stated the following:
..With the experience gained over the last few years and following the
acceptance of B. K. Chaturvedi Committee report, The Government has
introduced structural changes in policy, removed irritants in the model
agreements and other documents which has had the affect of revamping the
entire award process of NHDP. Consequently, the award of projects has been
accelerated over 2009-10 and 2010-11 and bids received were highly
competitive and about 77% of the awards have been on BOT (Toll) basis.
During the last nearly 2 years the bidders have submitted positive and
aggressive bids for both BOT (Toll) and BOT (Annuity)..
29
3.32
of Government policy with many formats with varying degree of success. Since, the
Committee argued that the private investment flow into any sector purely depends on
the consistent, long term policy adopted by the Government, the Ministry of Road
Transport and Highways was asked to furnish its response on this issue, and steps
initiated to address the same. The following reply was accordingly furnished by the
Ministry of Road Transport and Highways :Consistency in policy is desirable and infrastructure policy guidelines have been
subjected to many experiments, often seriously disrupting the award process. A
few can be cited for ready reference;
a)
projects, including those in balance for award in Phase II of NHDP, shall in future
be awarded on BOT Toll basis was a paradigm shift in the award process.
Prioritisation in execution of projects thus became dependent on their
attractiveness as commercial ventures. This was conceptually a sea change
since till then construction of road network were primarily driven by the intention
to connect the whole country through a chain of roads, primarily to the network of
GQ and the Corridors. Admittedly the Planning Commissions objective in
revising the design template was perhaps with the intent of bridging the gap
between actual and potential resources. But the fact remains that world over
PPP mode road infrastructure development is only a fraction of the whole, as
against the Indian experiment which places the same as the predominant mode.
Public acceptance of toll payment would be a critical issue, given that the public
already pays a fuel cess and while some stretches are toll free, the rest are
subjected to toll.
b)
Initially, the Governments direction was that all projects are first to be bid
out as BOT(Toll) and upon failure to attract an acceptable bid to be then bid out
as BOT (Annuity) and failing that to taken up on EPC mode with specific
approval of CCEA. For the market this posed a huge challenge, since estimating
the cost of a project involves considerable expense and each such stage needed
that at least part of these expenses be repeated. Perhaps as a reaction to this,
the market reacted by non-participation to NHAI bids. During 2008 end, bid
30
c)
Some critical
observations were also given by the World Bank. These were not agreed to by
Planning Commission. Similarly model RFQ/ RFP were issued by Ministry of
Finance. Many of the provisions were severely restrictive and after substantial
dislocation was seen to have been caused, at NHAIs instance, policy changes
were once again sought and were brought out under BKC Committee
recommendations which brought the required order to these processes.
3.33
When asked to state the steps taken to attract private investors in the bidding
process, the Ministry of Road Transport and Highways informed the Committee as
follows:
India today is a leading destination for infrastructure spend and, underscored by
the aspirations laid out in the Eleventh Five Year Plan, this sector offers
tremendous growth potential. Highways have a large shelf of projects which can
be readily offered to the market including those which had a serious setback last
year due to the global financial meltdown. Given our historical underinvestment
in highway infrastructure and the role this sector can play in stimulating
economic growth, we believe it imperative that adequate investment flows are
attracted to this segment. It is also felt that, in this discontinuous time, players
looking to finance highway infrastructure spend would benefit from a fresh
assessment of the opportunity. They have to be convinced that notwithstanding
the structural challenges, the profit pool remains large and attractive, with
potential for players to enlarge exposures. For the investment levels the highway
sector requires, domestic sources would need to be supplemented with
31
The Secretary, Ministry of Road Transport and Highways further added the
3.35
The Economic Survey (2010-11) document provided the following latest facts
approved additional budgetary support for the SARDP-NE and J&K projects. The
EGoM has also approved the Work Plan for 2010-11 onwards with the stipulation
that of the total NH length to be developed, broadly 60 per cent would be taken
up on build, operate, and transfer (BOT) (Toll) basis, 25 per cent on BOT
(Annuity)
basis,
and
theremaining
15
per
cent
on
engineering
3.36
3.37
disputes between the developers and various funding agencies. This experiment
has been very successful in the case of Power and should be replicated in other
key Ministries.
34
CHAPTER IV
ISSUES IN IMPLEMENTATION OF NATIONAL HIGHWAYS DEVELOPMENT
PROJECT
(i)
4.1
The National Highways have a total length of 70,934 km to serve as the arterial
network of the country. As per the Economic Survey (2010-11) document, about 25
percent of the total length of National Highways is single lane/intermediate lane, about
52 percent is two lane standard and the balance 23 per cent is four lane standard or
more. The development of National Highways is the responsibility of the Government of
India, which in turn, has launched major initiatives to upgrade and strengthen National
Highways through various phases of National Highways Development Project (NHDP),
which are briefly as under:
4.3
4.4
`34,339 crore (2002 prices) comprises mostly NS-EW Corridor (6,161 km) and other
National Highways of 486 km length, the total length being 6,647 km.
35
NHDP Phase-III:
4.5
Build, Operate and Transfer (BOT) basis at an estimated cost of `80,626 crore under
NHDP Phase III. The phase has been approved in two parts i.e. Phase III - A consisting
total length of 4,815 km at an approved cost of `33,069 crore and Phase III - B,
consisting total length of 7,294 km at an approved cost of `47,557 crore. The scheduled
date of completion of NHDP Phase III is December, 2013. Under this phase, the
stretches have been identified as per the following criteria:
(i)High density traffic corridors not included in Phase I & II
(ii)Providing connectivity of State capitals with NHDP (Phase I & II)
(iii)Connectivity of centres of tourism and places of economic importance.
Against 12,109 km, a length of 1190 km has already been four laned up to 31.12.2009
and a length of 3170 km is under implementation.
NHDP Phase - IV
4.6
2-lane with paved shoulders under NHDP. This phase was approved by the
Government in July, 2008. Out of approved length of 20,000 kms which is to be
implemented in a phased manner in stretches of 5000 kms each, the Ministry of Road
Transport and Highways is implementing the first Phase i.e. NHDP Phase IV A,
upgradtion/strengthening of 5,000 km of single/intermediate/two lane National
Highways to two lane with paved shoulders on BOT (Toll) and BOT (Annuity) basis.
NHDP Phase - V
4.7
Six laning of 6,500 km of existing 4 lane National Highways under NHDP Phase
V (on Design Build Finance Operate (DBFO) basis was approved in October, 2006. Six
laning of 6,500 km includes 5,700 km of GQ and 800 km of other stretches. Against
6500 km, a length of 148 km has already been six laned up to 31 st December, 2009
and a length of 886 km is under implementation.
NHDP Phase - VI
4.8
expressways under Public Private Partnership (PPP) model following DBFO approach.
Phase VI of NHDP was approved at an estimated cost of `16,680 crore in November,
2006. NHAI has appointed a consultant for carrying out feasibility study for Vadodara
36
Separators, Flyovers, elevated roads, tunnels, road over bridges, underpasses, service
roads etc on BOT (Toll) mode under NHDP Phase VII in December, 2007 at an
estimated cost of `16,680 crore. 36 stretches in different States have been proposed to
be taken up. Proposal for 4 lane elevated road from Chennai port to Maduravoyal in
Tamil Nadu costing `1485 crore approved by PPPAC in August, 2008. RFQ proposals
received in October, 2008. Project was awarded in January, 2009. Proposal for
upgradation of NH-7 between Hebbal flyover to New Airport (22 km.) in Bangalore
costing `680 crore was awarded on 8.2.2010.
4.10
Total Length
in km
Date of
Approval
I
GQ,EW-NS corridors,
Port connectivity &
others
II
4/6-laning North
South- East West
Corridor, Others
Total phase III (phase
III A + III B)
7,522*
12.12.2000
30,300
(37739.71)
7398
124
6,647
18.12.2003
34,339
(45722.63)
4983
1220
444
12,109
05.03.2005,
27.10.2006 &
12.4.2007
80,626
(21938.01)
2048
5293
4699
37
Approved Cost
Length
Length To be
(Expenditure till Completed under awarded
31.12.10) in Rs
in km
Imp.
Crore
IV
20,000 July -2008 for
2 - laning with paved
5000 km
shoulders
V
6,500
05.10.2006
6-laning of GQ and
High density corridor
VI
1000
02.11.2006
Expressways
VII
700 km of 06.12.2007
Ring Roads, Bypasses ring roads/
and flyovers and other bypass +
structures
flyovers
4.11
27,800
41,210
(7485.53)
16,680
(3.49)
16,680
(0.18)
765
19235
467
1833
4200
NIL
NIL
1000
41
659
phases. The present phases under Phase I, II & III envisages improving more than
25,255 km of arterial routes of NH network to international standards. The project wise
details of NHDP phase I, II, III & V are as follows: (status 28th February, 2011)
NHDP
GQ
Total
Length
(Km.)
25
Contracts
Under
Implement
ation (No.)
96
Balance
length for
award
(Km.)
421
4.12
490
80
17
14799 48,254
Port
Total by
Conne Others
NHAI
ctivity
380
1383 50,017
14,006
306 932
15,244
41
112
765
9,695
74
431
10,220
210
220
20 23,803
38
4.13
The East West & North South corridor project (NHDP Phase II) was earlier
7142 km
Completed length
5258 km (74 %)
Under Implementation
1457 km
427 km
4.14
The Ministry of Road Transport and Highways was asked to furnish details of
4.15
The Committee also observed that in respect of NHDP phase III B (upgradation,
4/6 laning), which was approved in 12.4.2007 out of total length of 7,294 km, only 10
km has been completed as on 31.8.2010, yet December, 2013 has been kept as the
likely date of project completion.
4.16
The length of Highways awarded by NHAI during the year 2010-11 (up to
January 2011) is 4345 Kms. Briefing the Committee on the targets of NHDP fixed for
the years 2011 and 2012 as well as the progress on the same, the Secretary, Ministry
of Road Transport and Highways stated the following in March, 2011:
39
.... I would say that during the current year, 2010-11, as against the targets
which had been put for NHAI for completion in NHDP, there was a slow down. I
must concede that there were a couple of CBI cases and raids and that did bring
in a slow down for four to five months, but after that, the organisation is again
geared up and in the last few months, again momentum is there.
4.17
40
(ii)
GOLDEN QUADRILATERAL
4.18
Highways Development project Phase-I connecting four metro cities of Delhi, Mumbai,
Chennai, Kolkata (Figure 1).
Figure: 1
4.19
The Committee were informed by the Ministry of Road Transport and Highways
that as per original mandate of task force, the Golden Quadrilateral Project was to be
completed by March 04. However, the CCEA approved the project on 18.12.2000 in
which the date of completion of GQ was mentioned as December03. The date of
completion was further extended to December05 in view of compelling circumstances
41
like delay on account of pre construction activities which includes delay in land
acquisition due to procedural formalities, litigation and court cases, forest clearance,
environment clearance, clearance/ approval from railways. This delay was justified as
the programme of this magnitude was unprecedented and also the construction
industry in road sector was not developed enough to take up the works of such
magnitude.
4.20
The Secretary, Ministry of Road Transport and Highways also added during the
briefing:
So far as the Golden Quadrilateral is concerned, it is going on smoothly in
respect of projects in other phases.
decided to pay attention to the Golden Quadrilateral, I would like to mention that
it is almost complete out of 5,846 km., only 115 km. is incomplete. These
stretches were incomplete primarily because of contractual problems.
The
contracts which were awarded originally have become sour. As a result they
had to be terminated. I am sorry to report that they had to be terminated. I am
happy to report that in all the cases, the new contracts have already been
awarded and so, the work is going on smoothly.
4.21
The Committee are further informed that to complete GQ a total number of 128
contracts were awarded, out of which all are completed except 15 projects. The total
length of GQ was 5846 km., out of which 5799 km. length has already been completed.
Targeted date of completion for balance length has been extended to December 2010
due to non-performance by some of the contractors. Their performance during the
currency of original contract was poor and therefore NHAI was compelled to terminate
the contracts. Their contracts were terminated and balance work has been re- awarded.
These contracts are scheduled to be completed from May, 2010 to December, 2010.
4.22
42
4.23
YEAR
LENGTH COMPLETED
PERCENTAGE
DEC-2000
648
11.08%
MAR-2004
3100
53.03%
DEC-2007
5501
94.10%
MAR-2009
5721
97.86%
AUG-2010
5799
99.20%
4.24
When enquired about the steps taken to expedite the project completion, the
Ministry of Road Transport and Highways stated, in a written reply that NHAI has
taken several steps to expedite project completion. To strengthen monitoring of the
projects, NHAI has formulated a revised strategy for implementation of projects. As
per this strategy, 10 Regional Offices headed by Chief General Manager (CGM) have
been opened. The Chief General Managers have been delegated financial as well as
administrative powers for execution of works. Further co-ordination between various
state level agencies has also been assigned to the Regional Office. For land
acquisition, special land acquisition cell has been created in HQ and special land
acquisition units involving the State level Officers, who are well-conversant with land
acquisition process, have been engaged for expeditious completion of land
acquisition. Special training is also being imparted to these officers.
4.25 As per the material furnished to the Committee during September, 2010, 6 km
road under Golden Quadrilateral was yet to be given on contract, whereas this project
was scheduled to be completed in September itself. When asked to state the position in
this regard, the Ministry of Road Transport and Highways submitted the following in its
written reply:
All stretches under Golden Quadrilateral were awarded. The 6 km stretch yet to
be awarded is the Ennore Expressway project which is part of port connectivity
projects under NHDP Phase I. This stretch could not be awarded so far due to
delay in Land Acquisition and R&R of Project Affected Families (PAFs). The latest
status is as below:
43
4.26
of the projects completed under Golden Quadrilateral, the Ministry responded in the
written reply that Quality Assurance is an integral part of each project and Supervision
Consultants are being engaged through international bidding process to supervise
quality of work on day to day basis. Regular and mandatory testing of material used in
construction as well as quality of construction is closely monitored. Besides, inspections
are also carried out by NHAI officers, both from field and HQ, from time to time.
4.27
commensurate with the hubs and spokes pattern of transport system considered
essential for the balanced regional development. In this regard, Ministry of Road
Transport and Highways responded that work Plan is under consideration to cover
about top 300 towns in terms of population around hub cities.
44
(iii)
TOLL POLICY
4.28
As informed by the Ministry of Road Transport & Highways, Section 7(1) of NHAI
Act 1956 as amended in 1993 (Act 1 of 1993) empowers the Government to levy fees
for use of sections of National Highways at such rates as laid down in rule made in this
behalf. In 1997 the rules were framed for public funded projects. Section 11 of the rules
provided for collection of fees in perpetuity. The rates provided in the rules for
conversion of projects from 2 lane to 4 lane sections of National Highways were
decided considering the following principles:
4.29
a)
b)
c)
The Secretary, Ministry of Road Transport and Highways also added the
4.30
45
raised, but this is the users fee and since the amount is inadequate because the
cess goes even for the rural roads, which are not tolled, this is in addition to the
cess but both are independent of each other. Every road is not subjected to toll;
only those roads that are through-traffic and that carry commercial traffic, they
are tolled; most of the roads still remain untolled.
4.31
The Committee wanted to know about the changes, which have taken place in
Toll Policy in recent times. In this regard, Ministry submitted the following in a written
reply:-
i) In the year 2008, when the new fee rules of 2008 were published in
supersession of fee rules of 1997, the base rate of 1997 was considered after
indexation. Further, two separate category of vehicles i.e. Multi Axle Vehicles
(3 to 6 axles) and oversized vehicles (more than 6 axles) were introduced.
ii) The fee is to be collected in Perpetuity, as per rules. (Refer rule 6 (6) of new
fee rules, 2008)
iii) As per new fee rules, 2008, the distance between two fee plazas should be 60
Kms. Other conditions for setting up the fee plazas are provided in rule 8 of the
new fee rules, 2008.
iv) In the new fee rules of 2008, it is provided that fee shall be revised every year
effective from 1st April based on, a) 3% fixed increase and b) 40% of the
change in Whole Sale Price Index (WPI).
v) Before publication of fee rules of 2008, in case of Public Funded projects, fee
shall be revised after every five years based on change in WPI and in case of
BOT projects as per the provisions of the concession agreement.
vi) On the basis of the feedback received from the stakeholders as well as the
experience gained during implementation, some proposals are under
consideration of the Government.
4.32
In respect of New fee rules, 2008, the Secretary, Ministry of Road Transport and
46
within less than 5 KMs; then, between two toll plaza, there will be no toll at all;
one can move freely so that the local people are not put to any inconvenience.
Generally the distance between one toll plaza and another will be 80-100 KM.
This is what the new toll policy says. In fact the new toll policy tries to rationalize
many problems which were existing, in the old policy. That is one of the reasons.
In the earlier policy, the toll gates were there between 15-20 KMs, unfortunately
what happens whatever has been done under the old toll policy, we are
governed by the agreement; it is very difficult for us to do anything because it
was an agreement with the private party and the Government; and that has to be
honoured.
4.33
(b)
(c)
47
ii)
iii)
iv)
removed /
debarred by NHAI based on their performance in toll collection or any other assignment
are not eligible for bidding.
4.34
The Ministry has further stated that steps taken to address problems associated
It is understood that once the successful bidders are handed over the toll
under the
Chairmanship of
Shri Nandan
Nilekani, Chairman,
Unique
Identification (RFID) technology complying to ISO 18000 6-C for use in all toll
plazas of National Highways in India. The system should meet the following
requirement with high degree of reliability:
a)
b)
c)
d)
e)
4.35
The Ministry, in their latest reply, has now stated the following:
..based on the Report submitted by the expert committee headed by Shri.
Nandan Nilekani, Chairman, UIDAI, MoRTH/NHAI is in the process of
implementing Electronic Toll Collection (ETC) at toll plazas on NHs.
In
The Apex
4.36
The Committee have also been apprised by the Ministry about the review of Toll
Policy. The Ministry has stated that The National Highways Fee (Determination of
Rates and Collection) Rules, 2008 were notified on 5th December, 2008. After the
notification and coming into effect of the Highways Fee rules, Ministry has received
49
4.37
The Secretary, Ministry of Road Transport and Highways added during the
4.38
per km for levy of user fee on Two lane NHs. (earlier it was Rs 1.00 crore
per km)
50
b)
Bridge/ Tunnel with user fee of Bypass section to be at the rate 1.5 times
of the prescribed rates for the section.
d)
Highways fee rules, 1997 to New Fee Rules, 2008 in respect of public
funded project is approved so the effect of change may not be more than
25% in a year including the normal increase for the year.
51
(iv)
4.39
operation of National Highways is done under Section 3 of the National Highways Act,
1956.
conduct survey in the land so notified. Any person interested in the land may file
objection within 21 days of the Notification to the Competent Authority for the
land acquisition. The Competent Authority after hearing all such objections may
either allow or disallow the objections.
Competent
Authority
submits
report
to
the
Central
Government and on receipt of the report the Central Govt. publishes the 3(D)
Notification. On Notification under 3(D)all land mentioned therein shall vest with
the Central Govt. absolutely free from encumbrances.
4.40
The NH Act further provide that where land is acquired under the Act ibid, the
Government for publication. NHAI, HQs is responsible for legal vetting of all the
Notifications of 3(a), 3A and 3D, and for submission for approval of the Honble
Minister. After approval by the Central Government, Notifications are published
in the Gazette of India and later on in the local newspapers. The process of
completion of LA activities is taking on and average about 18 months starting
from publication of 3(a) notification.
4.41
The Secretary, Ministry of Road Transport and Highways also added the
Governments are not involved will really be called into question because the
Deputy Collector or the Additional Collector, who is the competent authority,
prepares the notification. Consultants may have given the report but he sends
the draft notification which we approve. That determines the alignment, where
the road will pass, that kind of land will be acquired. It is he who scrutinizes
every aspect and then sends it to us.
compensation. We do not put any limit. It says any value which he fixes as the
market value. In the Act the word used is compensation.
4.42
When the Committee enquired about any limit given for compensation, the
Secretary stated the following during briefing:We have not imposed any limit. It is for the local officer to fix the ward and send
it.
If someone is
53
4.43
4.44
These nodal officers are PWD Principal Secretaries who deal with the
Highways.
Directors and see what is happening on ground. Therefore, from the Ministry
side we are very keen that the State Governments or the local officers are fully
involved.
publicity to the local people so that they know that this type of a road is coming.
All these provision are there. NHAI does not approve the feasibility report or the
DPR unless it has been passed through the nodal officers appointed by the State
Government. In fact our present Minister has issued instructions that the nodal
officer should be the Chief Secretary so that he can coordinate between land,
PWD, law and order. So, some States have appointed Chief Secretaries as the
nodal officers. This is about the land acquisition.
54
4.45
The Committee wanted to know the difficulties being encountered in the extant
procedure of Land acquisition. In this regard, the Ministry submitted that delay in
acquisition of land has been one of the major problems in the execution of projects. The
main reasons for delay in the acquisition of land are as follows:
(i)
under the National Highways Act 1956, the NHAI requests the district
administration to nominate a Revenue Officer to be appointed as the Competent
Authority under the Act. There is generally delay in the appointment of
competent authority by the State Government. Delay in nomination of the
competent authority by the State Governments invariably leads to delay in the
land acquisition process.
(ii)
frequent transfers of CALA, and CALAs assign low priority to land acquisition for
NHAI (which is their secondary task).
(iii)
(iv)
Valuation of the structures and other assets like trees on land requires
(v)
records and unclear titles of the land being acquired results in preparation of
poor land acquisition plans; this also excludes at times the legitimate rights of the
affected persons for compensation and increases litigation. The settlement of
claims during land acquisition and duplication of procedures and processes to
acquire land under the revised land acquisition plans delays the process. The
revenue records are not updated and in some cases joint verification is not done
in time, which causes delay in the process of acquisition.
55
(vi)
Time lost in arbitration: The NH Act does not provide for any time-limit
NHAIs
approaches the arbitrator even after 2-3 years from the date of determination of
the award and these cases remain unsettled till that time. As a result there is
considerable loss of time in arbitration.
(vii)
provide for payment of an interest amount calculated at the rate of twelve per
cent, over and above the market value of the land for the period commencing on
and from the date of publication of the notification under sub-section (1) of
section 4 in respect of such land to the date of award of the competent authority
or the date of taking possession of the land, whichever is earlier, subject
however to the condition that in computing such period, any period or periods
during which the proceedings for the acquisition of the land were held up on
account of any stay or injunction by the order of any court shall be excluded. In
addition, a provision also exists for awarding a sum of 30% as solatium amount
over and above the market value of the land in consideration of the compulsory
nature of the acquisition. The land owner/person interested in the land whose
land is acquired under the NH Act expects to be compensated at similar rates as
provided for in the LA Act.
(viii)
(ix)
56
to be acquired are omitted from the Notification. Consequently, the omitted plots
have to be purchased because initiation of processes for issue of Notifications
afresh causes loss of time, and also loss of money because compensation for
land is to be computed as per market-rates prevalent on date of issue of 3A
Notification.
(x)
4.46
When asked to state the initiatives taken by the Ministry to remove the
bottlenecks in Land acquisition, the Ministry submitted the following in a written reply:
Several
(i) Utilization of State Govt. machinery for land acquisition: Under the current
system of land acquisition State Govt. Revenue Department officers are
appointed as CALAs. Appointment of State Govt. Revenue Department officers
are as CALAs is advantageous to NHAI due to their familiarity with local
conditions/land-rates/land-use patterns, and because they/their Departments are
custodians of local Revenue Records on basis of which Notifications under NH
Act are issued for acquisition of land.
57
respectively.
Further,
provision
was
also
made
for
(iv) Interaction with the State Govts. : As brought out above, NHAI is entirely
dependent on State Govts. for obtaining possession over encumbrance free
land. Accordingly, instead of being assigned responsibilities over individual
stretches of Highway (e.g. arms of GQ, halves of NS or EW Corridors, or BOT
projects), CGMs have been assigned responsibilities for implementation of
projects in individual States. The level at which NHAI coordinates/interacts with
State Govts for problem-solving is at the level of NHAIs State CGM-State
Govts Nodal Officer for NHDP. Recently, in order to further streamline
interaction with State Govts for smooth implementation NHDP, CGMs in charge
of individual States have been posted to the respective State Capitals.
(v) Chief Secretaries as Nodal Officers: State Govts. have been requested to
nominate their Chief Secretaries as Nodal Officers for monitoring NHAI projects.
The Govts. of J&K, Punjab and Andhra Pradesh have constituted committees
under the Chief Secretaries for monitoring NHAI projects.
58
(vi) Meetings with State Chief Ministers/Chief Secretaries: Meetings have been
held with State Chief Ministers/Chief Secretaries for resolving land acquisition
and related problems/issues.
(ix) Constitution of Special Land Acquisition Units (SLAUs): In order to tide over
the problem of land acquisition getting delayed due to delay in appointment of
CALA, frequent transfers of CALA, and because CALAs assign low priority to
land acquisition for NHAI (which is their secondary task), Chairman has recently
requested Chief Secretaries of all State Govts. wherein NHDP projects are
being implemented, to constitutes dedicated Special Land Acquisition Units
(SLAUs), for acquisition of land for NHAI.
The composition proposed for Special Land Acquisition Units are as follows;
(i)
ADM/SDM
01
(ii)
Tehsildar
02
(iii)
02
(iv) Patwari
02
(v)
06
(vi) Chainman
06
06
Surveyor/Amin
25
All the administrative and establishment charges of these units will be borne by
NHAI. The infrastructure like hiring of accommodation, vehicles, telephone
59
services etc. will be provided by NHAI. The activities of the Special Land
Acquisition Units will include the following;
(i)
State Govts. have also been requested to consider a senior Revenue Officer
(ADM level) for deputation to NHAI to coordinate with Special Land Acquisition
Units in the State. Till date 90 SLAUs have been constituted.
As mentioned above, in order to tide over the problem of land acquisition getting
delayed due to delay in appointment of CALA, frequent transfers of CALA, and
because CALAs assign low priority to land acquisition for NHAI (which is their
secondary task), Chairman has recently requested Chief Secretaries of all State
Govts wherein NHDP projects are being implemented, to constitutes dedicated
Special Land Acquisition Units (SLAUs), for acquisition of land for NHAI
A proposal has been submitted by NHAI for making amendments to the NH Act for
provision of timeframes for initiation/completion of Arbitration.
4.47
themselves appreciate the progress in the Western and Southern parts of the
country. Progress in UP, Bihar, Assam and West Bengal is poor. We do not
hesitate to accept it and the main reason is land acquisition. I have gone to
Assam four or five times.
interest but six packages are in North-Cachar district. Right up to the Cabinet
Secretary, everybody is making attempt but still condition on the ground have not
improved and the contractors have run away. They do not want to do the work
unless there is basic assurance about the law and order. So, the position is,
unless the State Government cooperate with regard to land acquisition, providing
protection to the contractors and with regard to collection toll, things cannot
move. For example, State like Orissa, Goa are not cooperating in toll collection.
The result will be the NHAI will be left with no alternative but either to abandon
the programme or to continue in a slow manner
4.48
The Secretary, Ministry of Road Transport & Highways further added the
4.49
The Committee are also informed by the Ministry about the proposals to amend
current Land acquisition policy. The Ministry of Road Transport and Highways, in a
written reply, has submitted that measures to compress the timeline of completion of
land acquisition have been conceptualized/proposed, which are as follows:
61
(i)
(ii)
(iii)
4.50
During evidence, the Committee, express concern over the land acquisition
status in States like Kerala and Goa, where the highways projects have been severely
affected because of the problems associated with land acquisition. It was pointed out
that in these States, several stretches of NH are hemmed in by dense population of
homes and commercial structures. The huge numbers of residential and commercial
structures along these highways are under fear of demolition in view of Highways
projects.
62
4.51
In respect of Goa, where NH-17 & NH-4A were facing the Land acquisition
problems and people were asking for 45 metre Road instead of 60 metre standard four
lane Road, the representative of Ministry of Road Transport and Highways/NHAI stated:
About the NH-17 Project, I would submit that we have already decided to restrict
the land acquisition to 45 metres. About NH-4A, we have received some
representations from the State and the local people. We are in the process of
taking a decision in that matter also.
4.52
When inquired about the land acquisition problems in Kerala, where vast
stretches of National Highways are dotted with houses and shops that are the only
source of livelihood of people, Secretary, Ministry of Road Transport & Highways
responded by saying:
Unfortunately, in Kerala, Sir, but the problems are very very complex.
As
hon. Member is saying, all along the National Highways people are living
the
and
the National Highways are narrow. If you want to widen them we have to uproot
those people. It is a big problem. That has to be solved by all of us with a human
angle in mind. If the road has to be built, land has to be given. This is precisely
the reason why in Kerala award has been very slow. In fact, we were about to
drop this North-South corridor. In 2007 there was a stalemate. The Kerala
Cabinet agreed to give 45 metres. We wanted 60 metres. They were first not
prepared to give anything beyond 30 metres. The
We said we would suspend the project and we did. Then the Kerala Cabinet
decided to give 45 metres and the work moved. Even if this 45 metres is not
given, there is no alternative for the NHAI but to terminate the project
irrespective of the consequences. This is the view of the Ministry and the
Minister has made it abundantly clear.
4.53
63
has decided to with hold the land acquisition action till the assembly elections to
be held in April 2011. During the meeting with the State Government officials it
has also been agreed in principle to consider minor changes in the alignments,
wherever possible, to ensure minimum demolition of residential and commercial
structures.
In the State of Goa all the demands raised by public, institutions and State
Government have been taken into consideration and only bare minimum
demolition is involved.
4.54
4.55
When asked to explain reasons as to why for the four-lanning of road, land has
been acquired from only one side, the representative of Ministry of Road Transport &
Highways commented the following during evidence:
Sir, there are two ways that a four-lane road can be constructed. One way is the
two-lane road is already existing; you make another by the side of it leaving
some gap for the median which is 4.5 metres. This is one way which is called
eccentric widening. From the centreline it is eccentric. The second way is
concentric widening. There is a seven metre road and then add on both sides.
These are the two ways. If we do the concentric widening what happens is this.
Then, four-and-a-half metres of the existing road will be rendered useless
because at that portion the median will come. The divider will come at four-anda-half metres. Even if we put the dividers last, the road is already existing and
that will be rendered useless because that will come within the median. It is
preferred to have a new road so that we can utilise the existing one. The other
advantage is that if we are concentric widening, at least there is one road on
which the traffic moves during construction. If you start doing this and then you
64
also construct the median then there is some problem of traffic diversion. Even
that can be managed. But then it is a cleaner arrangement to have a new one.
4.56
4.57
Secretary, Ministry of Road Transport & Highways stated during the evidence:
........If the State Government authority and the land owner or the shop owner or
house owner, they amicably settle and come out with a package, we are
approving it. In some cases if the land acquisition officer is not doing, it is entirely
the job of the arbitrator who is provided in the Act. Who is the arbitrator? It is the
Collector. If the Collector says that this is an amicable settlement, it is okay. Let
me give an example. In Baghpat district, Ghaziabad, NOIDA etc. the Collectors
fixed some price. It was around end of 2008. But the landlords did not agree.
Then the Commissioners intervened and finally they have fixed an amount which
is very high. We said okay, whatever you say we will accept. As far as the
Central Government is concerned and the National Highway Act is concerned,
there is no impediment. It is entirely for the State Government to fix the price and
come out with a package.
65
(V)
DELAYED PROJECTS
4.58
The Ministry of Road Transport & Highways furnished detailed list of awarded
NHDP Projects (Underimplementation), Golden Quadrilateral Projects and North SouthEast West Corridor Projects (Fully completed as well as Underimplementation). These
lists are given at Annexure IV, V, VI & VII. These lists/statement shows that almost all
works of highway projects had been delayed or were likely to be delayed.
The
Committee also noted that in several cases, duration of these delays as well as
corresponding cost escalations are substantial.
4.59
strip of 10 m for plantation of all along the highway. Such a condition is very
difficult to meet and creates problems in the implementation of works. The Net
Present Value (NPV) of the diverted forest land is demanded even for the road
side lands belonging to PWD/NHAI (notified as protected forest for management
purposes).
`1100 crores for the North-South and East-West Corridor taking the lowest NPV
rate of `5.80 lakhs per ha. In a few projects widening involves diversion of small
strip of land in the wildlife areas (National Part/sanctuary). The application for
forest clearance in such cases is to be first submitted to the National Board of
Wildlife. Approval of the Board is required at various states, including the very
first step of undertaking survey and investigation for preparation of Detailed
Project Report. The process of approval at each stage takes a long time as the
Board meets only once in three months. Moreover, there remains an uncertainty
with regard to whether the projects on such alignments would receive final
approval. Environmental clearance is required even for a highway widening
projects involving land acquisition of more than 20 m put together on either side;
and for a new alignments exceeding `100 crore in cost, even though the
alignment may not be falling in an eco-sensitive area. As a result, projects are
delayed and progress of the works is affected.
involves coordination with various State forest department, MOEF, and State
Pollution Control Boards.
Clearance of Railways for ROB designs
Under NHDP Phases-I&II and other projects about 229 (84 on GQ alone) Rail
Over Bridges (ROB)/ Rail Under Bridges (RUB) have to be constructed.
Approvals have
Obtaining
the
above
clearances/approval
from
the
Railways
involves
coordination with several departments within Railways and it takes a long time
to get the
constructed by
the
Railways
themselves,
progress
has
not
been
4.60
When the Committee enquired about the procedural delays and asked the
Ministry to comment on the reports that there was a time lag of three years between a
project being sanctioned and the work starting on it, the Ministry, in a written reply,
stated the following:
Once the projects are approved by the Government, NHAI is required to
complete Detailed Project Report/Feasibility Report of the project by appointing
a Consultant. The process of appointment of Consultants usually takes four to
six months time and the Detailed Project Report requires another 1 to 1 1/2
year time depending upon the project length and number of structures
involved. After finalization of cost through DPR, the project is awarded for
68
4.61
Secretary, Ministry of Road Transport & Highways also, during the evidence held
69
4.62
The Committee wanted to know about the status of NHDP Phase III A, which
was earlier scheduled to be completed by December 2009. In this regard, the Ministry
of Road Transport & Highways informed the Committee as follows:
Government of India approved 4/6 laning of 4000 km of NH under NHDP
Phase-IIIA on BOT basis at an estimated cost of `22,000.00 crores (at 2004
prices) on 05.03.2005. Against the 4000 km, Ministry identified 80 projects of
total length of 6139 km scheduled for completion by December 2009. So far 41
projects of length 2755 km have been, awarded under NHDP Phase-IIIA. Bids
for another 3 projects have been received and are under process. During 200708 NHAI initiated bidding for 44 projects under NHDP-III. The economic slow
down in 2008 affected the bidding of these projects which resulted in little or no
response to the bidding. Most of the projects remaining to be awarded are
commercially non-viable on BOT (Toll) for 4-laning. The projects are being restructured to reduce the cost consistent with road safety to make them viable.
These projects are proposed for bidding during the current year. Upto
September 2009 the total length completed under NHDP-IIIA is 982 km.
The Committee was subsequently informed by the Ministry that likely date
of completion of project has been revised to December, 2013.
4.63
In the background material furnished to the Committee, Ministry had stated that
Phase-IV, VI and VII have been approved in the month of July 2008, November 2006 &
December 2007 respectively. In spite of that NIL progress (as Length completed) has
been indicated in their status as on 31 August 2009. When asked about the reason for
the same, the Ministry responded the following in a written communication:
NHDP Phase IV, VI and VII are targeted for completion by December, 2015,
December, 2015 and December, 2014 respectively. Presently feasibility studies
are being prepared for most of the projects under above mentioned NHDP
Phases. After completion of feasibility studies process of land acquisition will be
initiated followed by bidding process for award of concession and financial
closer. Generally, highway projects have a gestation period of 4-5 years
(including the DPR phase). Hence, if physical progress be achieved in the initial
phase of construction, the completion of actual length will be achieved towards
the end of the target date of completion of project.
70
4.64
Responding to a query from the Committee about the steps taken by the Ministry
of Road Transport & Highways to expedite the projects, the Ministry stated the
following:
(a)
simplified. Earlier all the notification under NH Act were vetted by the Ministry of
Law. Recently, an amendment has been made in the Allocation of Business
Rules by which these notifications are not required to be sent to the Ministry of
Law. The Ministry of Law has approved the standard formats of various
notifications keeping in view the similar nature of the notifications of Land
Acquisition.
(e)
posted to NHAI to coordinate the Ministry of Railways. MOU has also been
signed with M/s. IRCON for construction of some of the ROBs.
(f)
Action has been taken against non performing contractors and they are
not allowed to bid for future projects unless they improve the performance in
existing contracts.
(g)
4.65
A new direction has been given to expedite the implementation of the National
Highways Development Project (NHDP) with the objective to achieve construction of 20
km road per day. The issues of critical concern to various stakeholders in regard to
policy framework and planning and implementation have been addressed. The Ministry
has targeted the procedural issues, acting as roadblocks and major bottlenecks in
achieving the desired progress of the Infrastructure. A Committee under Shri B.K.
Chaturvedi, Member, Planning Commission was constituted to recommend framework
and strategy to resolve procedural impediments to the programme objective as well as
to take a holistic look at the financing need and arrive at a financing plan that balances
the needs of the road sector and other priority areas of the Government. The
recommendations of the Committee for expeditious implementation of the NHDP have
1
2
As per Economic Survey (2010-11), 14 Regional Offices have been set up as on date.
192 Special Land Acquisition Units have been set up in various States.
72
been approved by the Government. The main features of the revised policy framework
are:
(i)
(ii)
delivery viz. BOT (Toll), BOT (Annuity) and EPC (Item Rate Contract)
concurrently rather than sequentially. Roads below a certain threshold in terms
of traffic do not merit testing on BOT (Toll) as the process only leads to delays in
implementation and award. Hence, a road not found prima facie suitable for BOT
(Toll) can be implemented directly on BOT (Annuity) subject to the overall cap as
envisaged in the Work Plan. The decision of shifting a project from BOT (Toll) to
BOT (Annuity) would be taken by the IMG chaired by Secretary, MORTH and
approved by Minister, Road Transport & Highways.
(iii)
tested for BOT (Annuity) and only if unacceptable bids are received then only the
project will be awarded on EPC basis. Normally, an Annuity bid working out to an
Equity IRR of up to 18% will be acceptable as per these norms. However, in the
event of bids exceeding the Equity IRR of 18 %, the same will be bid out on
EPC. In case of difficult areas having law & order problems, security,
inhospitable terrain etc, a bid working out to an Equity IRR of up to 21% will be
acceptable considering the risk premium of 3 %, on case to case basis. PPPAC
will be empowered to give approval for projects to be moved from Annuity to
EPC where acceptable bids have not been received.
73
(iv)
(v)
Qualification (RFQ), Request for Proposal (RFP) and the Model Concession
Agreements (MCA) have been carried out in accordance with the approved
recommendations of the B.K. Chaturvedi Committee for bids being invited for
various projects.
(vi)
Kashmir with Additional Budgetary Support (ABS) over and above the cess that
the Government provides to NHAI on a yearly basis.
Apart from it, a Joint Task Force of Confederation of Indian Industry (CII) and
the Ministry of Road Transport and Highways has also been constituted to serve as an
institutionalized framework for a constant Industry Government dialogue and
interaction on the issues related to the development of National Highways under the
Chairmanship of the Secretary (RT&H). The support of State Governments has been
institutionalized with the signing of State Support Agreement (SSA) by 19 States so far.
Other States have also been requested to expedite the signing of the Agreement. Chief
Ministers of all the States have been requested to set up High Level Coordination
Committees under Chief Secretaries to sort out issues involving coordination with
various Departments.
4.67
When asked about any professional study conducted by the Ministry of Road
Transport & Highways on the delayed projects, the Ministry responded that projects
implemented by NHAI are regularly reviewed in the ministry at highest level and NHAI
is advised to take actions as per provisions of contract where the projects are delayed.
4.68
supervision available with the Ministry of Road Transport & Highways; more so, since
presently most of the highways projects are carried out on BOT model, the Committee
74
asked the Ministry to state the steps (other than the opening of 10 regional offices)
being taken by them. The Ministry responded:
NHAI appoints independent/supervision consultants who monitor the progress
of projects. Further, the projects are also monitored on daily basis by the project
directors posted in the field offices. Measures have been initiated to provide
adequate staff to the Regional Offices which will enhance the capacity of
regional offices to closely monitor the implementation of projects. Apart from
these measures projects are also monitored regularly at the Head Quarter with
routine/regular reviews of targets/milestones fixed.
75
(vi)
NON-PERFORMING CONTRACTORS
4.69
Non-performing contractors are one of the major reasons for the inordinate
4.70
communication as follows:
The performance of contractor is constantly reviewed while reviewing the
progress of projects and if consistent poor performance is observed the
contractor is placed in the list of non performing contractors. In some cases due
to lack of progress the contracts have been terminated. Contractors placed in the
list of non-performing contractors are barred from bidding for NHAI projects. In
order to expedite the process of award certain changes have been made in the
documentation and process of award consequent to the acceptance of Shri B. K.
Chaturvedi Committee Report by the Government.
4.71
that project irregularities in the highways project are expected to cost the Government
76
revenue about ` 384 crore from projects. In this regard, Ministry of Road Transport &
Highways stated that regarding project irregularities in the Highways Projects, the
C&AG in its Audit Report No. PA 16 of 2008 UG (Commercial) have pointed out
revenue loss of ` 384 crores in following projects:
Para No. Name of the Project Observations
of
the
Report
2.3
DelhiGurgaon The concession period
Project
should have been fixed as
14 years instead of 20
years
2.3
Jaipur-Kishangarh
The concession period
Project
should have been fixed as
12 years instead of 20
years
4.2.1
Satara-Kagal project Penalty for delay in
completion of project
Amount
` Crores
121.63
187.77
2.11
4.2.1
4.2.2
Panagarh-Palsit
- DO 8.75
Satara-Kagal project Penalty
for
non 1.89
completion of punch list
4.2.3
Jaipur-Kishangarh
Project
4.2.3
Satara-Kagal
Project
TambaramTindivanam,
Tuni
Anakapalli,
Palsit
dankuni, Panagarh
Palsit
TambaramTindivanam,
Tuni
Anakapalli,
Palsit
Dankuni
-DO-
4.5.1
4.5.2
12.05
384.59
Actions taken Note of the C&AG report have already been submitted to Ministry
on 20.05.2009 which has been forwarded by Ministry to C&AG for their vetting.
77
4.72
When asked to state whether any punitive measure had been taken against
4.73
The Ministry further elaborated that in all cases of terminated contracts, the
Bank Guarantee for performance security is en-cashed and materials on the project site
are confiscated and utilized by new contractors.
4.74
When the Committee enquired whether there is any provision for financial
4.75
developers have been barred from bidding for new projects if they did not achieve
financial closure for three or more projects they were working on, the Ministry submitted
the following in a written reply:
78
The Authority has felt that many new entrants in the road sector do not have
the necessary resources to successfully manage execution of road projects and
hence would be exposing itself to project risk if suitable remedial measures are
not provided for. One of the most effective methods to assess the developers
level of comfort would be the lenders response to project financing. Hence a
criteria linked to this has been recently approved by the Authority as per which
for projects of total project cost (TPC) less than `3000 crore, a developer
should not have more than 3 outstanding projects pending for financial close and
for projects of TPC more than `3000 crores not more than 2 outstanding
financial close, and, both put together not more than 3 outstanding financial
close. With the same intent, certain restrictions have been placed with regard to
selection of EPC contractors by the developers, minimum net worth requirement
linked to project size, restrictions on non-performers from seeking prequalifications etc.
4.76
Providing an overview of the steps taken to expedite the progress of NHDP, the
79
(vii) MAINTENANCE
4.77
4.78
The Secretary, Ministry of Road Transport & Highways further added the
But the roads which are constructed under the EPC or under the
4.79
On a query from the Committee about official mechanism available with the
Ministry or NHAI for the maintenance of national highways in different parts of the
country, particularly in the wake of complaints regarding the dilapidated condition of
80
several stretches of national highway, the Ministry of Road Transport and Highways, in
a written statement, submitted as under:
Wherever 4/6 laning works under NHDP are under implementation, to keep the
existing roads in traffic worthy condition, the maintenance of existing roads are
carried out by the Contractor/Concessionaire as part of their obligations under
contract/concession agreement. In case of sections entrusted to NHAI where
4/6 laning have not yet started, the maintenance of existing roads are being
carried out by NHAI directly or through State PWDs with funds provided by
NHAI. After completion of 4/6 laning works, comprehensive maintenance are
regularly carried out. For projects constructed by NHAI on EPC basis i.e. through
budgetary sources, the maintenance of completed highways is carried out by
engaging Operation and Maintenance contractors selected through competitive
bidding. Under this, apart from routine and periodic operation and maintenance
of highways, engineering improvement as required for better road safety are also
taken up as and when necessary.
4.80
Routine Maintenance
Pothole treatment-timely repair to prevent further damage
Crack sealing - to prevent pothole occurrence
Median plantation - to improve the highway ambience
Shoulder/slope maintenance-to protect the highway from weather
effects
Cleaning of drains etc-to ensure efficient drainage
81
Engineering improvement
Service-road- to segregate slow traffic from fast traffic for safe and fast
movement
on the highway
Incident Management
Route patrolling-to watch and ward highway assets and help road user
Tow away crane to tow away broken down vehicle from the carriage way
Ambulance service- to briskly provide first aid to accident victim and carry
him to nearest hospital, if required.
4.81
82
4.82
4.83
The Committee referred to some reports that when some of the roads were
handed over to NHAI from State Highways for four-laning, immediately after handing
over, the State Government stopped taking care of those roads and even NHAI was not
maintaining them. The representative of Ministry of Road Transport & Highways
responded as follows:
It was happening earlier. But now we have decided that we do not hand over
the highways to the NHAI until the work is awarded. So, prior to the awarding of
the work, we are continuing the maintenance through the State Public Works
Department. We handover the highways only when they award the work to the
concessionaire. So, the problem which was there earlier now is no longer there.
4.84
83
In these contracts, maintenance is not part of the contract, however, one year
defects liability period is there wherein we retain his performance guarantee and
within one year if there is any defect noticed that he has to repair or rectify.
4.85
The Committee further referred to the successful PMGSY (Pradhan Mantri Gram
Sadak Yojana), which has an inbuilt maintenance clause of 5 or 7 years. In this regard,
the Ministry of Road Transport and Highways submitted that
a policy decision
4.86
The Secretary, Ministry of Road Transport and Highways further updated during
4.87
When the Committee enquired about the instrument of supervision available with
the Ministry of Road Transport and Highways to supervise/monitor the quality of roads
and maintenance undertaken, the Ministry, in a written statement, stated the following:
As far as the National Highways implemented by state Governments on behalf
of Ministry is concerned, the programme of periodic maintenance is finalized on
the advice of Ministrys regional officers (ROs) in charge of the respective
states. The works once awarded are directly monitored by ROs. Similar
procedure is followed for a flood damage repairs (FDR) and Special Repairs
(SR). As regards to routine maintenance, funds are subjected to availability and
paced at the disposal of State Governments who carry out their operations. In
the case of projects funded by NHAI where maintenance is being undertaken by
NHAI through O&M contractor, the maintenance of national highways is carried
out under the direct supervision of NHAI. Stretches under NHDP are maintained
under traffic worthy condition. In the case of BOT projects, NHAI has appointed
independent engineers to administer the contract. These independent engineers
supervise the quality of roads and maintenance undertaken.
84
4.88
Maintenance
Manual
Part No. I
Maintenance
Manual
analysis,
Part No. II
specifications,
drawings,
performance
Manual
analysis,
specifications,
drawings,
performance
M/s. Consulting Engineering Services (India) Pvt. Ltd. submitted a draft for all the
above mentioned 3 parts of the maintenance manual which is under examination.
The document on finalization is expected to not only ensure cost optimization but
also generate satisfaction among the road users due to timely and visible
maintenance operations.
4.89
The Ministry of Road Transport and Highways further added that the manual
85
4.90
Highways, the Committee were informed by the Ministry of Road Transport and
Highways that the financial resources made available to the Ministry under
Maintenance & Repairs Head (Non-Plan) had been only about 40% of the requirement
based on approved norms and projected by this Ministry, as evident from the following
table:
Year
Requirement
as per
norms
(` Crore)
Amount
provided
(` Crore)
Shortfall
(` Crore)
2002 2003
2,200.00
800.00
1,400.00
63.64
629.54
2003 2004
2,200.00
731.74
1,468.26
66.74
731.62
2004 2005
2,480.00
745.56
1,734.44
69.94
679.03
2005 2006
2,480.00
868.10
1,611.90
65.00
838.31
2006 2007
2,480.00
814.38
1,665.62
67.16
784.30
2007 2008
2,280.00
1,001.70
1,278.30
56.07
981.35
2008 2009
2,500.00
973.97
1,526.03
61.04
969.45
2009 2010
2,500.00
1,059.10
1,439.56
57.58
981.49$
2010 2011
2,500.00
1,056.86
1,443.14
57.73
330.83
Provisional
%
Expenditure
Shortfall
(` Crore)
As on August10
The issue of inadequate allocation for Maintenance & Repair of NHs needs to be
urgently addressed to prevent premature failure of sections of NHs developed at large
capital investments on account of self-accumulation of deficiencies due to thin
spreading of available resources for M&R on large NH network.
4.91
The representative of the Ministry of Road Transport & Highways further added
There is no
86
4.92
When asked whether the matter of inadequate allocation for maintenance has
been taken up with the Ministry of Finance, the Ministry stated in a written reply that
against the demand of `2121.20 crore for Maintenance and Repair of National
Highways (M&R) for the year 2009-10, fund of `1036.44 crore were allocated at BE
stage. At RE stage, it was again requested to enhance the provision to `2000.00 crore
from `1036.44 crore for the purpose but no additional fund was provided by Ministry of
Finance for the year 2009-10. For the year 2010-11, fund amounting to `1032.86 crore
has been provided for M&R against the demand of ` 2000 crore at BE level. Ministry of
Finance has now been requested to provide additional fund of `1000 crore under M&R
raising the total allocation for the year to as `2032.86 crore.
4.93
Emphasising the fact that tolling is required for meeting maintenance costs, the
Secretary, Ministry of Road Transport and Highways added during the evidence held on
30th March, 2010:
What we would emphasize for the hon. Members benefit is that in road
construction, only 20% of the life cycle cost is initial construction. 80% is meant
for the maintenance over the life of the road. That is why this issue which was
raised about tolling, that you collect the initial cost and then, do not do any
tolling. We would be very happy to do that, provided the EC can recommend that
sufficient funds are placed at the disposal of the Ministry for Maintenance. At the
moment the budgetary provision is so tight that we do not feel that roads could
be adequately maintained without tolling.
87
4.94
4.95
As per the Ministrys Annual Report, road safety is a multi-sectoral and multi-
4.96
The Ministry of Road Transport and Highways has been mandated to formulate
policies for road safety so as to minimize road accidents. The important schemes
formulated and managed by the Road Safety Cell include publicity programmes,
National Highways Accident Relief Service Scheme (NHARSS), refresher training to
heavy vehicle drivers in unorganized sector etc. The Committee on Road Safety &
Traffic Management set up under the chairmanship of Shri S. Sunder, former Secretary,
MoST also formulated and recommended a National Road Safety Policy for
consideration of the Government. The National Road Safety Policy envisages greater
emphasis on awareness on road safety issues, establishment of road safety information
database, strengthening of driving licence system and training, better enforcement of
road safety laws etc. The policy also envisages setting up of a dedicated agency
namely National Road Safety & Traffic Management Board to oversee the road safety
activities in the country.
4.97
The Secretary, Ministry of Road Transport and Highways also added the
the Road Safety Organisation and the measures to be taken for improving the
road safety. We are now in the process of finalizing the Bill. It is expected that
the Bill will be introduced in the Session which will start after the recess. That Bill
comprehensively deal with all the aspects of road safety management.
4.98
The Committee are further informed that Road Safety Bill has been introduced in
the Lok Sabha in May, 2010, which proposes the creation of a Board for Road Safety
and Traffic Management. When the Committee enquired about the rationale behind the
creation of a separate body, keeping in mind that multiplicity of bodies will only lead to
procedural delays, the Ministry of Road Transport and Highways elaborated in a written
statement as under:
Road safety is a multi-dimensional issue. In the existing scenario, various road
safety aspects are handled in a fragmented manner. There is no mechanism to
look into all these issues in a comprehensive manner. The agencies such as the
automotive
testing
institutions,
the
State
Governments,
the
Highway
89
the question of overlapping of functions would not arise. Moreover, the Board will
consult all these agencies before framing up its recommendations and would
thus carry considerable weightage for implementation by the Government. An
expert committee constituted by the Ministry under the Chairmanship of Shri S.
Sundar, Former Secretary (MoST) and Distinguished Fellow, TERI has
deliberated all the aspects in detail and has recommended creation of the Board
as an effective mechanism to take care of road safety issues in the country. It is
further stated that the Ministry has examined the recommendations of the
Department related Parliamentary Standing Committee on the Bill introduced in
Lok Sabha on 04.05.2010. The Ministry is examining various options to make the
Bill more comprehensive and objective oriented.
4.99
When asked to comment on the issue of service roads and safety, the Secretary,
4.100 On the issue of Trauma Centres for road accidents, the Secretary added:
I must say that the Cabinet has approved setting up of 140 such centres by the
Health Ministry and not by us. We are required to provide 140 ambulances
which we are doing. Cabinet has approved the scheme at the cost of `600
crore. We are very keen that these road safety issues are properly handled.
4.101 The Secretary, Ministry of Road Transport and Highways further added following
technical requirements ensuring road safety during evidence:
on the four-lane roads, we insisted that there has to be certain width of
median in the four-laning. This is to ensure that if there are any accidents,
vehicles from one carriageway does not come to the other and cause blockage
90
of the road and cause stopping of the carriageway. In certain States like Kerala,
we do have acute problem of land acquisition; we tried to do four-lane; we are
trying to do in 45 metres width, where normally we require 60 metres width. The
result of doing it in less width is that service lanes which we would provide on the
sides for local traffic, in 30 metre width or 45 metre width, we simply cannot
provide that, which means that between the habitation and the highway, we do
not get a shoulder, that is, if somebody goes off the road, there is nothing to
sustain him. The roads are not just blacktopped portion; on both sides, we have
shoulder; if you go off the road at high speed, you do not immediately overturn.
You should be able to go on for some time. In areas where we do not get
sufficient width because of land acquisition problem, shoulder provision is not
possible, service lane provision is not possible. Also, the median provision on the
middle of the road becomes a problem. So, the two are interrelated getting
sufficient width is a technical requirement and it is there to ensure safety; it is
there to ensure safe movement of slow moving traffic; it is essential that if we
have to provide foot over-bridge, or some underpass, we have some sufficient
width so that the slope is not very steep whether you are going over or under
the road. So, these are technical requirements and we cannot waive them easily.
These are some of the issues which we would like to place before you.
4.102 Engineering/technical aspects of Road Safety are being taken care of at the
design stage of the National Highway (NH) itself.
sections of National Highways in different parts of the country, where there are
recurrence of fatal accidents. One such section referred to by the Committee is near
Kooteripattu on NH-45 (140 kilometers from Chennai). 260 people have already died
within three years since the opening of this section of highway. When the Committee
enquired whether the Ministry was aware about such incidents and actions initiated by
the Ministry of Road Transport and Highways, to address problems of this kind, in a
written reply responded that Kooteripattu is grade intersection with vehicular traffic
towards Chennai on North, Trichy on South, Pondicherry on East and Gingee on West.
This junction is part of project for four laning of Tindivanam-Ulundurpet Section of NH45 on BOT basis which has already been widened to four lane and the junction
improvement as envisaged in the project has been completed. To prevent accidents at
this junction, the concessionaire has provided service roads on both sides of the main
carriageway and rumble strips on the cross roads. In addition to the above, blinkers,
91
speed limit boards, pedestrian crossing boards, median opening boards, etc have been
provided by the concessionaire. Studs have also been placed across the road to
indicate the pedestrian crossing and lighting arrangements have also been provided
along the road. As frequent accidents are occurring at this junction, the district
administration has placed temporary barricades across the road to reduce the speed of
the vehicles.
4.103 The Committee again raised the issue of Kooteripattu during the evidence held
on 24th September, 2010, stating that in 2009 also, 44 people died at the same place.
The Committee asked as to why a foot-over-bridge or a similar structure has not been
constructed there, the Chairman, NHAI stated:
We have no problem doing a pedestrian over-bridge... But the State
Government has asked for a complete grade interchange with a flyover, which is
quite expensive. We are preparing a report on it. A pedestrian over-bridge at
Kooteripattu is no problem, and we can sanction it.
92
(ix)
SUB-CONTRACTING OF PROJECTS
Further, it is also now mandated that in RFP the bidders have to specifically
name the EPC contractors whom they intend to appoint for carrying out the
works.
The above steps have been taken to ensure that work does not suffer due to
appointment of substandard EPC contractors.
the subcontractor has got certain quality and he has got certain records. The
need to have people with higher degree of capital equipment is very clear.
4.106 The
Committee
wanted
to
know about
the
comparative
advantages-
disadvantages of small contractors over large contractors. The Committee also wanted
the Ministry of Road Transport and Highways to comment on the reports/allegations
that policies followed by the Ministry of Road Transport and Highways tend to favour
large contractors, who eventually sub-contracts the project. On this issue, the
Chairman, NHAI stated the following during evidence:
Our experience with small contractors was, somewhere a question has been put
in Parliament, in Lok Sabha also, we have pointed out that we have had two
experiences. One is EPC contract, they have typically undergone time and cost
overrun; there have been relatively very few small contractors who have shown
the ability to finish the projects.
4.107 The Ministry of Road Transport and Highways further submitted a written
statement, as follows:
a)
Name of Stretch
Rohtak-Jind
51
94
b)
Seekur-Reengus
49
Jorhat -Shillong
14
Jorhat -Demow
Trichy -Karaikudi
36
Karaikudi - Ramanathapuram
35
Tindivanam- Krishnagiri
34
Dindigul - Theni
34
Palwal- Indapur
52
Bhopal- Sanchi
54
Jhansi-Khajuraho
43
Jabalpur-Rajmarg crossing
47
0-100
100-250
250-1000
1000-3000
No of applicants
20
18
35
10
Hence, it was apparent that many applicants did not have the required means to
successfully execute road projects. It was also learnt that many such applicants
were forming synthetic associations with consortium partners who were merely
indulging in name lending, without actively participating in execution of projects.
c)
stage, there is a high probability of sub optimal bids being tendered. Market
conditions are dynamic and it is felt that these need to be responded to in an
appropriate manner, to ensure optimal bids. When relaxation to various
provisions in MCA/ RFQ/ RFP were sought in 2009 under the aegis of B.K.
Chaturvedi Committee, the situation was drastically different, when RFQ
response was very minimal and such a situation had to be responded to. Since
then, a need was felt to tighten certain norms. Hence it is incorrect to allege that
these were made to favor large contractors. On the contrary these changes
95
96
(x)
ENVIRONMENTAL CLEARANCE
4.108 A negative eventuality associated with the development of roads and national
highways is the destruction of trees and diversion of forest areas. A clearance is,
therefore, to be obtained from the Ministry of Environment and Forests, wherever such
a situation arises. However, many a times, this has led to inordinate delays in highways
projects.
4.109 The Committee were informed by the Ministry of Road Transport & Highways
that the Highway projects require the following clearances from Ministry of Environment
& Forests (MoEF):
1.
2.
3.
Environment Clearance:
As far as environment clearance is concerned, no project is held up on account of
this. The projects submitted to MoEF for environment clearance are getting cleared
by the MoEF during its regular monthly meetings. One of the pre-requisites of
environment clearance is to have public hearing which is conducted by the State
Pollution Control Board (SPCB). It has been observed that there are delays by the
SPCB in convening such public hearings, which results in delay in submission of
final proposal to the MoEF.
Forest Clearance:
The forest clearance is a time consuming process as it is granted in two stages. In
the first stage in-principle approval is granted with certain conditions. After fulfilment
of the conditions, final clearance is granted by MoEF.
97
in delays in getting final clearance. In order to speed up the forest clearance NHAI is
holding regular meetings with the MoEF and the state forest departments.
At
present only 6 proposals are pending with MOEF. For resolving these issues,
meetings have been held at the highest level.
4.110 The Ministry further stated in a written reply that NHAI is to take permission
under Forest Conservation Act, 1980 and local laws for cutting of trees and diversion of
forest areas. In order to compensate the loss of trees, NHAI has to deposit the amount
for Compensatory Afforestation with the Forest Department. As per policy, the forest
department is to plant the trees in place of trees felled for which they are charging
NHAI. These charges are levied for twice the number of trees planted or more,
depending on the density and level status of the forest land along the national highway
98
where the trees are felled. The compensatory afforestation in lieu of cutting of old trees
or newly planted trees within 60m ROW for widening of 4-lane to 6-lane is carried out
along the highways (single row or double row as per the availability of land) and also on
the degraded forest. In this regard, sometimes revenue area is also taken for plantation
as per special conditions imposed by the State Government.
problems. These shady roads are intended really for bullock carts and for
traditional modes of travel. ........In general, when we are widening the four lanes,
we are designing them for a speed of 80 kilometre. Now, with 80 kilometre of
speed, we do not want to plant any tree within 14 to 15 metres of the highway
because if there is any accident, if any vehicle leaves the highway running at 80
kilometre speed, it would go and hit the tree if the tree is next to the
highway......... When you are travelling with 80 kilometre speed, trees planted too
close to the highways are a traffic hazard. So, we have got our own norms for
doing that. Because we do not have sufficient land to plant three trees for every
tree cut, we are depositing funds with the Forest Department of the State. They
are planting three trees in other areas, which are there. The Ministry of
Environment and Forests is well aware of this. The statements may be made in
the press; they may not be reliable. But all the figures stating as to how many
trees we have planted, where they have been planted, are available with the
State Forest Department. We have only limited space. We cannot create forest
just next to the road. They are a big traffic hazard. They are not permitted.
99
4.113 While explaining the massive delays of highway projects due to lack of
environmental clearances, the representative of the Ministry of Road Transport and
Highways informed the Committee about a particular project of NH-24 i.e. Hapur to
Garmukteshwar, having total length of 35 kilometes. The representative stated as
under:
Only the four-lane of 15 kilometres has been completed. The work relating to
the majority portion of the length is going on. It is delayed due to primarily two
reasons. One is that the clearance is to be made by the Ministry of Environment
and Forests.
The Ministry of
Environment and Forests is not able to give clearance because they are looking
forward for the recommendations of the State Wildlife Board. But as there is no
State Wildlife Board constituted, there is no question of any recommendations of
the State Wildlife Board. Whenever we are approaching the Central Ministry that
the project had come up for clearance, they say, it should come with the
recommendations of the State Wildlife Board. In the State, where there is a
statutory requirement to constitute the State Wildlife Board, they have not
constituted it.
Ministry. But it is now for them to find a solution to this because in this process,
we do not get any clearance and our project will not be able to proceed further.
100
(xi)
PORT-CONNECTIVITY PROJECTS
4.114 Port Connectivity projects are the integral component of phase-I of National
Highways Development Project (NHDP), comprising a length of 380 Kms for
improvement of roads connecting 12 major Ports of the country to National Highways.
These projects envisage better connectivity and integration of ports with hinterland.
4.116 During their interactions with the Ministry as well as in their study visit
discussions, the Committee had expressed concern over the Mormugao Port
connectivity project and Chennai-Ennore Port connectivity project, which have hit
severe roadblocks and are yet to be completed.
4.117 In respect of Mormugao Port connectivity project under NHDP Phase I, out of
18.3 km length, 13.1 km was completed way back in 2004, but the balance work was
awarded in June 2009 only. When the Committee enquired for the reason of this delay
and asked for the likely date of completion of this project, the Ministry of Road
Transport and Highways, in a written reply stated.
The work beyond 13.10 km. could not be taken up because of non-completion
of rehabilitation and land acquisition work by the State Government. As per the
direction of Honble High Court, the State Government was ordered to hand over
the balance stretch of 5.2 km. by 30 Sept. 2009. So far 4.18 km. stretch has
been handed over. Keeping in view the Court order, the balance work has
already been awarded and agreement signed on 23 rd Sept. 2009 with a
completion period of 2 years from date of start. The work is likely to commence
shortly.
4.118 On this issue, the Ministry subsequently informed the Committee about the
following:
As per the directives of the Honble High Court of Bombay at Goa, PWD, Govt.
of Goa has handed over 4.02 km to NHAI out of the balance 5.20 km. The
remaining 1.18 km which is still occupied by encroachers and the same was to
101
4.119 Regarding Port-Connectivity project between Chennai port and Ennore port - two
extremely busy ports that cater very high volume of work, the Ministry of Road
Transport and Highways in a written reply, stated the following:
Chennai and Ennore Port Connectivity includes 9 km Tiruvottiyur Ponneri
Panchetti Road (TPP Road) and 15 km - (Manali Oil Refinery Road(MORR) +
Inner Ring Road (IRR) + 1.6 km EE + 3 groynes) road. In TPP road of 9 km, LA
process was delayed by Govt. of Tamil Nadu and due to this Contract was
terminated with mutual consent on 24.06.2008. In the second road of 15 km (MoRR + IRR + 1.6 km EE + 3 groynes), the contractor did not mobilize the work
and the contract was terminated due to this. After combining the above two road
works and adding a service road in TPP Road, bids was invited & received on
10.11.08 for the combined project and proposal was submitted to NHAI Board
on 17.11.08 in this regard. As the project cost increased from `309 crore to
`600 crore, NHAI Board directed to obtain confirmation of enhanced equity/debt
contribution from SPV partners.
stakeholders (SPV partners) was made available. Due to this, the Bid for the
above work received on 10.11.2008 has been cancelled in December, 2009.
Invitation of fresh bid for the project will be taken up after receiving clear
commitment from all stakeholders for equity/debt contribution as per direction of
NHAI Board and shifting of 1800 project affected families from Ennore
Expressway.
102
(xii)
4.120 The transport sector has been marred by the imbalanced development of roads
& highways in certain regions of country, particularly the North-East region. The
condition of road transport and highways are dismal in these regions, nevertheless, no
substantial progress has been achieved in respect of awarded NHDP.
4.121 The Committee are informed that the Ministry of Road Transport and Highways
has been paying special attention to the development of the National Highways in the
North-Eastern region. A Special Accelerated Road Development Programme for North
Eastern region (SARDP-NE) has been envisaged, which aims at improving road
connectivity of State capitals with District headquarters and remote places of NE region.
Valecha-TBL (JV) (AS-25) have refused to take up the projects due to reasons of
adverse Law & Order and non availability of land. An effort is being made for the
foreclosure of 5 projects of NC3 Hills amicably. Two projects have already been
foreclosed on 15.12.2009. A stretch Balachera to Herangajo of 31Km length
103
4.123 When the Committee further asked the Ministry to expain the reasons for slow
progress and steps taken to address this issue, the Ministry in a written statement
stated that some of the reasons for slow progress and action taken in this regard are as
follows:
Board (ASEB). In this regard ASEB has been requested to expedite the balance
work.
The Contractors in NC Hills District have stopped the works in March 2008 and
the works have not been resumed till date. The contractors have stated that their
employees are not willing to work in that area and have requested for amicable
settlement of the five civil contracts. NHAI has agreed to foreclose these contracts and
further action is being taken accordingly. Two projects have been already foreclosed on
15.12.2009.
4.124 The Ministry of Road Transport and Highways also added the following:
Keeping in view the adverse Law & Order situation in NC Hills District, NHAI
has agreed for foreclosure of five Civil Packages No AS-21, AS-22, AS-24, AS25 & AS-26 under East West Corridor in Assam. Out of above, foreclosure of 2
civil packages AS-21 & AS-22 has been accomplished and process for
remaining 3 packages (AS-24, AS-25 & AS-26) is underway.
However, the
general Law & Order situation in the State appears to have improved and all out
efforts are being made in consultation with State Government to expedite the
progress of works. As regards delay in land acquisition, after due cooperation
from State Government, the progress of land acquisition has improved.
Regional office/ Project Directors of NHAI are making concentrated efforts to
105
issues which were pending since last 4-5 years have been obtained from MoEF
recently. This will definitely expedite the progress of projects under East West
Corridor in Assam.
4.125 The Secretary, Ministry of Road Transport and Highways also added the
following during the evidence:
.............law and order is a State subject. NHAI, of course, learnt it in the
process through interactions with the State Governments. For example, the
State Government of Assam came forward and said that we need to provide for
payment of some of the forces which are provided as security for contractors.
Now, this was not envisaged earlier. But then, as we went along, NHAI learnt it
and it had agreed to pay for some of the extra security services which have been
provided.
106
4.127 When the Ministry of Road Transport and Highways was asked to comment on
the report that NHAI has decided to pursue project implementation by bypassing the
States where land acquisition is slow and leave those States out of the road building
loop, the Secretary, responded the following during evidence:
I think, we did not say by-pass. I think, it has appeared in the Press, though I
must share with you that there is no formal decision as of now. Perhaps I saw it
in the Press, and the hon. Member has referred to it, that the Minister told this.
The idea is like this. I do not want to name the State. Suppose a State does not
want to cooperate in land acquisition, what is the solution? You have to either
drop the project or even close the ongoing project because we do not have any
alternative. This is what it means.
107
4.129 In order to improve the road connectivity in the Left Wing Extremism (LWE)
affected areas, the Government has come up with a scheme for development of
National Highways and State roads in the area of 33 districts in eight States at an
estimate cost of `7300 cr. Under the scheme, development of identified stretches of
NHs (1202 kms) and State roads (4362 kms) to two lane standards are planned to be
taken up in a phased manner in the next three years, subject to adequate security
arrangements being provided by the respective State Governments / Central Agencies.
An allocation of `500 cr. was made for the year 2009-10 (BE). This has been modified
to `125 cr. at a RE stage for 2009-10. For the year 2010-11, the budgetary outlay for
LWE areas is `1000 cr.
4.130 When the Committee enquired why the funds utilization for current year is very
low, the Secretary, during the evidence, held on 24 th September, 2010, stated the
following:
.of course, the utilization has been less because the awards have been
only recent. Current year, it is `1,057 crore, but award has been there significant
in the last about six months. But I take your point on record. We will try and see
how best we can try and coordinate, even though the award of projects is by
State Governments.
4.131 Left Wing Extremism in the country is to a large extent, funded out of the
extortion/concession, which the naxals get from every Government contractors. All this
make the entire development strategy counter-productive & self-defeating. When the
Committee asked whether any physical vetting of contractors is carried out, before
awarding the contracts in naxalism/LWE affected areas, the Secretary during
evidence stated:
For the construction, we leave it entirely to the State Governments. So, it is the
State PWD which does the contracting or the construction. So, the straight
answer to your question is, no; we do not get the contractors verified with the
Home Ministry or we ourselves verify so, the answer is, no
108
4.132 When the Committee emphasized upon the need to get verification of
contractors in LWE areas, the Secretary said as under:
The point made by the hon. Members is a very valid point. I would agree with
you. we will try to address this issue.
4.133 The Ministry of Road Transport and Highways in a written reply further added
that the matter regarding checking credentials of contractors of LWE roads to avoid
diversion of funds to LWE groups would be examined in consultation with State
Governments and Union Ministry of Legal Affairs.
109
OBSERVATIONS/RECOMMENDATIONS
1.
110
111
2.
The Committee, while reviewing the financial plan of NHDP, note that the
observe
that
Ministry
of
Finance
is
already
pursuing
the
112
In this regard, the Committee are of the firm opinion that the Government
intervention is not only desired but also indispensable to enable faster capital
inflows and resource mobilization in this infrastructure sector. The Committee,
therefore, suggest that in the current environment, when the economy is coming
out of recession, it is none but imperative that the issue of availability of long
term debt with back-ended repayment structure is pursued at the highest level in
order to provide an institutional mechanism for specialized infrastructure
financing. The Committee further desire that the creation of this institutional
mechanism should be done within a stipulated time frame to avoid any project
delay due to financial crunch. The Committee also agree with the suggestions
made in the World Bank Report on Financing Infrastructure, which stress upon
the need for specialized infrastructure institutions such as Infrastructure Leasing
and Financial Services (IL & FS) and Infrastructure Development Finance
Corporation (IDFC) to participate at the design stage/ DPR stage of a project in
order to make it easier for project developers to obtain finances as well as to
provide the developer with the opportunity to use the expertise of such
institutions in project designing & financial structuring. The Committee also note
that the Ministry of Power have reportedly set up an Inter-Institutional Group
(IIG), consisting of infrastructure developers and senior representatives from
banks and financial institutions, which has proved to be of substantive help in
resolving any outstanding issues or disputes between the developers and
various funding agencies. The Committee suggest that the Ministry of Road
Transport and Highways should emulate such models with a view to removing
113
114
3.
The initial phases of NHDP were public funded. However, later the Public-
115
project will be awarded on EPC basis. The Committee are of the view that there is
urgent need to streamline the system to cut delays caused by lengthy
procedures. They would like to be apprised of the status of projects post the
waterfall mechanism and hope that at least now the long delays in completion
of NH projects would be avoided.
116
4.
The Committee observe that Highway sector has a large shelf of projects,
which can be readily offered to private players, including those which had a
serious setback in the year 2009-2010 due to global financial meltdown. Since the
financial crisis is now over, the Committee suggest the Ministry to take concerted
efforts to attract private players in this sector. Apart from an enabling fiscal
environment, development of mutual trust is the fundamental pre-requisite to
encourage entry of private investors. Organization of Business conclaves
periodically with active cooperation of FICCI, CII and other corporate bodies may
also lead to a positive response. In respect of pending Highway projects due to
non-response/low response of private investors, the Committee urge the Ministry
to explore various possibilities to attract bidders by way of revising the project
cost, providing funds on concessional interest rates and providing updated &
authentic traffic data flexibility in the Concessional Agreement too.
From the deposition of the Ministry made before them, the Committee also
note that one of the fundamental problems faced by the private investor is
experiments of Government policy with many formats with varying degrees of
success. Changes in the policy guidelines as well as project documents such as
MCA (Model Concession Agreement), RFQ (Request for Qualification) and RFP
(Request for proposal) have caused severe disruption of the award process in the
past. The Committee feel that private investment flow into the Highway sector will
purely depend on the consistent, adoption of long term policies and their
adherence by the Government and therefore, there is an urgent need to
standardize project documents and streamline policy guidelines vis--vis Public-
117
118
5.
and
balanced
regional
development.
The
Committee,
therefore,
recommend that those projects, which have not been able to attract private
investors so far, should not be left to be doomed and that the Ministry should
evolve alternate strategies for such projects on priority basis. Resorting to EPC
mode of delivery could be one of them.
119
6.
project ever undertaken by the country, was initiated in the late 90s to create,
develop and improve network of 70,934 km of National Highways throughout the
country. However, the Committee are pained to note that the progress of most of
the projects has not been satisfactory due to procedural delays, land acquisition
issues, contractual problems and other factors. Even the Secretary, Ministry of
Road Transport & Highways has conceded slow down in NHDP projects. The
Committee would like to cite a few examples of the delays like phases 3A & 3B
involving 12,109 kms, in which only 2048 kms has been completed and the noncompletion of Golden Quadrilateral connecting the four metro cities, even on the
revised date of December, 2010. The Ministry have now assured the Committee
that by 31st March, 2011, around 5,500-5,800 kms of roads under NHDP would be
awarded, which would be the highest ever award. The Ministry also appears to be
confident about the next years target of 7,300 kms. The Committee would like to
be apprised of the actual length awarded out of the present years target.
However, in view of the poor performance so far, they fail to understand the
rationale behind expanding NHDP, without even completing Phases I & II and the
Golden Quadrilateral. As regards certain impediments in the Highways projects,
with the setting up of an Empowered Group of Ministries, those bottlenecks are
expected to be tackled effectively. The Committee are of the opinion that absence
of coordination among different Ministries/agencies and State Governments is
the root cause of delay at every stage. The Committee, therefore, recommend that
Ministry must utilize the revised mechanism effectively and strive hard to develop
120
121
7.
The Committee are distressed to note that flagship project of NHDP i.e.
122
8.
123
124
9.
125
126
10.
Toll collection work of EPC projects is being carried out through DGR
(Directorate
General
Resettlement,
Ministry
of
Defence)
sponsored
Ex-
servicemen. However, Ministry of Road Transport and Highways has been candid
before the Committee to acknowledge that several complaints regarding pilferage
of revenue and non-compliance of contract conditions have been received, some
of which have been proved too. In this connection, the Committee have been
informed that the Ministry has come up with New Policy for engagement of Fee
collecting Agencies to address these issues. While the impact of the new policy
remains to be seen, the Committee are of the view that the instrument of
supervision needs to be further strengthened and streamlined. They, therefore,
recommend that Ministry of Road Transport and Highways should develop an
effective mechanism in coordination with NHAI to monitor toll collection not only
in EPC projects but also in PPP projects (BOT Toll & Annuity) with a view to
obviate unnecessary harassment of the highway users by way of an illegal and
unscrupulous method of toll collection.
127
11.
Land
acquisition
for
development,
maintenance,
management
and
128
determination of award and these cases remain unsettled for long, leading to
inordinate delay in complete procedure.
Although Ministry has submitted a proposal for the necessary amendments
to NH Act, the Committee fail to understand as to why the Ministry took so long to
propose amendments to NH Act 1956 despite more than 15 years of experiencing
hurdles under NHDP. Besides, such a proposal is not being pursued vigorously
in order to facilitate smoother acquisition of land for future projects under
various phases of NHDP. The Committee feel that there is an urgent need to
streamline the Land Acquisition process and, therefore, recommend that Ministry
should take necessary steps to amend the existing NH Act, 1956 in order to
incorporate firstly, provision of compensation as per provisions of Land
Acquisition Act, 1894 and second, provision of timeframes for declaration of
awards by Competent Authority for Land Acquisition (CALA), disbursement of
compensation and initiation/completion of arbitration. The Committee desire to
be apprised of the status of the proposal submitted for making amendment in the
NH Act.
129
12.
The Committee observe that the issue of land acquisition in general and
Before
130
Committee desire the Ministry to pursue this with other State Governments,
vigorously.
The Committee further observe that the State Governments/District
Collectors have been extremely conservative in awarding compensation and it is
the sole reason for landowners to keep litigating for decades in the hope of better
compensation and therefore, suggest that there is an urgent need to sensitize
State Governments/CALAs/Arbitrators to take into account future development
potential of the land for its owner, while awarding the compensation. The
Committee are of the firm view that the Ministry of Road Transport and Highways,
being the nodal Ministry for Highway construction, development & maintenance,
can play a pivotal role in this regard.
The Committee further observe that in respect of Kerala and Goa, the
Ministry/NHAI and respective State Governments have been stuck with the issue
of 35 metres/ 45 metres/ 60 metres of highway width and unprecedented delay
encountered in the completion of projects are likely to make those redundant in
the light of ever increasing vehicular traffic. The Committee note the Ministrys
suggestion that in these cases, expressways with completely new alignment
and avoiding all human habitation, can provide the ideal solution. The Committee
do understand that the quantum of investment required for these green-field
projects would be very high, but considering the benefits, not only at present but
in future as well, the Government should give a serious thought to it without
further delay. The Committee also recommend that the Expressway Authority of
India., as envisaged and prioritized in the Eleventh Five Year Plan document
131
should be constituted as early as possible. The Committee are also of the view
that in cases similar to Kerala & Goa, where widening of Highways can lead to
displacement of local people or have an adverse effect on their livelihoods, the
construction of expressways should be considered from the initial stage itself.
They hope that these suggestions would be suitably incorporated in the XII Five
Year Plan, otherwise certain crucial National Highway Projects may not see the
light of the day at all.
132
13.
The Committee are extremely concerned to note that almost all works of
highway projects had been delayed or were likely to be delayed. In several cases,
period of these delays as well as corresponding cost escalations are substantial.
While agreeing that certain complex issues and impediments may come up in the
implementation of Highway projects, the Committee wish to emphasise that
issues such as Land acquisition, Railway clearance for Rail Over Bridge (ROB)
design, environmental clearance, shifting of utilities and poor performance of
contractors are of routine nature in a Highway construction and can be
addressed
with
effective
coordination,
supervision
and
pursuance
with
concerned organization/agencies.
Although few corrective measures have been taken by the Ministry, for
instance, posting of a Railways officer in NHAI to expedite clearances of ROBs,
changes in the process of awarding contracts, increase in the number of State
Level Land Acquisition Units etc, the Committee are of view that the Ministry and
NHAI have a major responsibility in this regard. The Committee are anguished to
note NIL progress (as length completed) in respect of NHDP, Phase IV, VI and VII
project, which were approved way back in the month of July, 2008, November,
2006 and December, 2007 respectively. The submission of the Ministry that
presently feasibility studies are being prepared for most of these projects, is
not convincing. The Committee desire that timelines should be set realistically
while announcing a new project, after taking into consideration the time required
on account of land acquisition, environment & forest clearance etc.
The
Committee also note that though in respect of BOT projects, delay does not have
133
134
14.
major reasons for long delays in completion of Highway projects. Also, the
possibility of a nexus between middlemen, non-performing contractors and
corrupt officials siphoning off project funds cannot be ruled out. The Committee
have been given to understand that the contracts of such contractors, who do not
perform even after periodical review, are terminated and the bank guarantee for
performance security are encashed. As per stipulations, these contractors are
also not being pre-qualified for award of any future project in NHAI until their
performance improves. The Committee feel that in an atmosphere, where delays
have become a regular affair, blacklisting alone may not be effective and thus
there should be a provision to impose substantial cash penalty on the nonperforming contractors. The Committee, therefore, recommend that Ministry
should either incorporate a provision of financial penalty or raise the amount of
bank guarantee in the contract agreement. It will serve two purposes, firstly it will
be an effective instrument of penalty and will act as a deterrent for nonperforming contractors and secondly, it will keep away non-serious contractors
or the contractors, who do not have the requisite capabilities to undertake major
National Highway Project.
Further, the
Committee would like to emphasize upon the fact that construction of Highways
through contracting and bidding requires a sharp and effective evaluation and
supervision of contractors.
135
jeopardize the projects. Thus, the Committee recommend that senior managers
in NHAI should be made to adopt an effective approach to hire capable
contractors and supervise them sincerely and efficiently. Equally important is the
need to be aware of the pitfalls of making inappropriate decisions in this direction
for which responsibility should be fixed and the erring officials penalized.
136
15.
paramount importance in view of the overload they bear. Poor maintenance and
potholes on most of the Highways have turned them into an increased safety
hazard to the users. For instance, NH6, NH13 and NH34 are in bad condition.
Other glaring examples of the same are Mahatma Gandhi Bridge and Rajendra
Bridge in Bihar and Roopnarayan Bridge in West Bengal.
The Panvel-Goa
Highway and the Shivpuri by-pass are some other examples of certain spots
being severely accident-prone on National Highways. The Committee are
constrained to note that financial resources made available to the Ministry under
Maintenance and Repairs Head (Non-Plan) have been only about 40% of the
requirement during the last four years. The Committee are of the firm opinion that
if due maintenance cannot be provided to existing network of highways, all
efforts to expand its reach are meaningless and hence, recommend that
maintenance should be accorded highest priority and the issue of inadequate
allocation for maintenance and repairs of National Highways should be taken up
with Ministry of Finance and Planning Commission at the highest level. The
Committee also suggest that controlled entry of trucks, conducting of awareness
programs among road users and night patrolling on the Highways should be
undertaken for enhancing safety. Specific observations on the maintenance and
safety aspects have been covered in the next two recommendations.
137
16.
138
an integrated mechanism, the proposal of the Ministry is, in fact, creating yet
another institution adding to the existing ones. Furthermore, the Committee learn
that the proposed Board is merely advisory in nature and it has not been
provided with any explicit statutory role of effecting coordination amongst the
different agencies. The Committee, therefore, emphasize that what is required
first is a National Road Safety Policy to bring about synergy and better
coordination among the already existing Government agencies/ research
organizations and making the system effective, rather than creating another one.
The Committee therefore feel that the Government needs to assess the present
situation in a holistic manner.
As regards road safety, the Committee also observe that availability of
suitable width of land is required to make a highway safe for commuters and that
some States Governments are not cooperating on the issue. In the opinion of the
Committee, holistic perspective that addresses the entire gamut of road safety is
the need of the hour. In their view, convening of regular meetings between the
Chairman, NHAI and the Chief Ministers/Chief Secretaries of the States
concerned, on the significance of requisite land for highways to avoid loss of
lives, could remove bottlenecks and hurdles in the implementation of NHDP.
139
17.
Road Safety are being taken care of at the design stage of the National Highway
itself. However, the Committee are pained to note that there are certain sections
of National Highways in different parts of the country, from where recurrence of
fatal accidents has been regularly reported due to their faulty design or such
shortcomings. One such section is near Kooteripattu on NH-45. Since the
inception of this section of highway in 2005, about 700 accidents have already
taken place, killing more than 132 people. The Committee have been raising his
issue for the last one year. Though some tentative action has been reportedly
taken on the matter, yet the Committee are shocked to know that the Ministry of
Road Transport and Highways is still preparing a report on the same. This state
of affairs raises serious doubts about how the sufferings of a common man are
dealt with in the existing set up. The Committee express their profound anguish
over the scant regard that has been shown towards the lives of the people and
strongly deprecate the callous approach of concerned agencies. They also
recommend that road safety issue of Kooteripattu alongwith the complaints of
similar nature from any other section in the entire NH network should be
addressed with utmost urgency. The Committee also recommend that the
Ministry should compulsorily carry out road safety audit for all future projects
either at the planning stage or at the Detailed Project Reports stage. The needs of
the local population living on both sides of such Highways should also be given
due attention in the form of subways, foot overbridges, pedestrian crossings,
service road, underpasses or even realignment of the road, if needed, because no
140
141
18.
Committee observed that in several cases, once a stretch of road was being taken
up for development, there was a sufficient time gap between the handing over of
the road and the actual commencement of the project, and thus, the road
remained neglected in the interregnum. They feel that the issue requires serious
attention. Further, the Committee note that prior to entrustment of National
Highway stretches, Ministry of Road Transport and Highways is solely
responsible for the maintenance and repair of these stretches. Same is being
carried out through State PWDs and Ministry releases the funds for this purpose.
On similar lines, prior to award of civil works for development, NHAI is carrying
out the maintenance & repair work through State PWDs from the funds
allocated/released by Ministry of Road Transport and Highways. However, the
financial position of State PWDs is weak in several States and shortage of funds
leaves no room for road maintenance, hence incessant complaints have been
received about the poor condition of National Highways. The Committee,
therefore, feel that the situation warrants a direct role and intervention on the part
of Ministry. The Committee note that NHAI has now decided to formulate a
Standard Maintenance Manual for improving the maintenance & repair of
highways, which is currently under examination. The Committee feel that such a
manual should have been in place much earlier. They would emphasize that
earnest effort should be made for preventive maintenance rather than
conventional reactive maintenance of roads and highways.
142
The Committee further feel that the Ministry should tighten its supervisory/
monitoring mechanism vis--vis not only PPP projects but also EPC projects. The
Committee are also of the view that provision of the Damages for breach of
maintenance obligation, as recommended by B.K. Chaturvedi Committee,
wherein the authority shall be entitled to recover damages, until the breach is
repaired, should be adhered to religiously. The Committee are of the view that
in respect of EPC contracts, DLP(Defect Liability Period), which was just one
year till recent times, was utterly insufficient. Though, the Ministry has amended
it to three years, still the Committee feel that incorporation of 5 years inbuilt
maintenance clause in all construction contracts, on the lines of Pradhan Mantri
Gram Sadak Yojna (PMGSY), is essential for the efficiency of Highway projects.
The Committee, therefore, recommend that the Ministry should now initiate
efforts in this regard at the earliest after consulting the Ministry of Finance, for
the projects due to be undertaken in the 12th Plan period. The Committee are also
of the opinion that since the responsibility of maintenance under PPP is that of
the concessionaire and the period can vary from 12 to 30 years, more projects
under PPP should be encouraged as this will not only reduce the financial burden
on the Government but will also be in public interest.
143
19.
144
145
20.
several Highway projects is the delay in obtaining necessary clearance under the
Forest Conservation Act, 1980 and local laws for cutting of trees and diversion of
forest areas as well as the wildlife clearance all being time consuming
processes. The Committee have been informed by Ministry that as regards
environmental clearance, they are depositing the compensatory afforestation
amount for trees being cut for a highway with the Ministry of Environment. The
Committee also take note of the argument put forth by the Ministry that planting
trees close to the road is no longer relevant in the absence of bullock carts now
and thus is only a major traffic hazard and that on this point there is a difference
in viewpoints of both the Ministries. The Committee are of the view that central
nodal institutions like Ministry of Road Transport and Highways and NHAI, being
mandated to construct, develop and maintain the National Highways throughout
the country can certainly play a more proactive role and therefore, strongly
recommend that the Ministry, in coordination with Ministry of Environment and
Forest, should devise a mutually agreed formula for time-bound clearances of the
highway projects. The Committee also desire that Ministry should pursue with the
Ministry of Environment and Forest vigorously to get preferential treatment for
the National highways, similar to certain coal-mining projects, keeping in mind
their significance for the progress of the nation. The Committee further counsel
the Ministry that the process of obtaining environmental clearances should be
initiated at the earliest possible stage and clearances should be obtained before
finalizing the cost or awarding the project and not vice-versa.
146
The Committee also came across a peculiar case concerning the highway
project of NH-24 i.e. Hapur to Garmukteshwar (total length 35 km), where the
Ministry of Environment and Forest has not been able to give environmental
clearances because they are looking forward for the recommendation of State
Wildlife Board. And since, State Wildlife Board has not yet been constituted, the
project is lying in doldrums. Similarly, a project in Gwalior is being held-up for the
last eight years due to non-cooperation of the Army to hand-over one acre of
land.
bureaucratic cow-web are not going to help the issue and therefore, recommend
that all concerned parties should follow a pragmatic approach towards solving
issues of these nature. They suggest that the Ministry should take up the matter
with the Ministry of Defence, the concerned State Governments as well as the
Ministry of Environment & Forest urgently to ensure clearance and timely
completion of this highway project.
147
21.
some of the Port Connectivity Projects are not getting due attention. Mormugao
Port Connectivity project, Chennai-Ennore Port Connectivity project as well as
Haldia Port Connectivity project have been getting delayed on one account or the
other. In respect of Mormugao Port Connectivity project, the Committee are
constrained to note that due to certain issues such as acquisition of Government
land (presently 1.18 km stretch of road is still to be acquired) and due to
encroachment problems, Mormugao Port Trust (MPT) and Government of Goa are
at loggerheads and project is suffering. The Committee, during their visit to Goa,
were pained to note that several areas of disagreement existed between MPT and
Government of Goa. The matter is sub-judice currently. The Committee hope that
the matter would be resolved soon. With regard to connectivity project involving
the Chennai & Ennore Ports, the Committee are disturbed to note that bidding for
the same is being held up due to lack of clear commitment from all stakeholders
for equity/debt-contribution as well as shifting of 1800 PAPs (Project Affected
Parties) from Ennore Expressway. The Committee, therefore, suggest that
Ministry should make concerted efforts through all channels possible and ensure
cooperation among all stakeholders in order to expedite implementation of these
Port Connectivity Projects.
148
22.
The Committee note that the development of roads and highways in the
North-Eastern region is not at par with the rest of the country, because progress
achieved in respect of awarded NHDP projects in the region is rather dismal. For
instance, in respect of the projects in Assam under East-West corridor (NHDP
phase-II), zero progress has been shown in 8 projects as on 31.08.2010. The
Committee find that the situation is more alarming because most of these
projects have already crossed the date of completion as per original contracts.
Even the
inception of new
programme
viz.
Special
Accelerated Road
149
connectivity to these regions in the absence of proper rail and air connectivity
and act as the lifeline of the people. The Committee also suggest that Ministry
and NHAI should undertake a coherent and coordinated effort with active and
effective cooperation of the Ministry of Home Affairs and the State Governments
of NE region to remove bottlenecks in their Highway projects.
150
23.
the road connectivity in the Left Wing Extremism (LWE) affected areas covering
33 districts in eight States. However, the Committee are dismayed to find that
funds allocated for this purpose are grossly underutilized. During the year 20092010, out of Budget Estimates of ` 500 cr and Revised Estimates for ` 125 cr, only
` 5 cr could be utilized. Even for the year 2010-11, out of Budget Estimates of `
1000 cr; only ` 578.21 cr have been utilized upto 28th February, 2011, which is
quite unsatisfactory.
of
LWE
affected
areas,
reducing
economic
isolation
and
strengthening political cohesion, the Committee desire that a high level group
comprising of representatives of Ministries of Home, Urban Development,
Development of North Eastern Region (DONER) and the Ministry of Road
Transport & Highways (MORTH) and National Highways Authority of India (NHAI)
should be formed, who should be entrusted with the responsibility to
supervise/monitor the programme on a regular basis to ensure that funds are
utilized prudently and required infrastructure is created for the common good.
The Committee would particularly emphasize upon the fact that the Ministry
needs to coordinate effectively with the Ministry of Home Affairs and concerned
State Governments to tackle the disruption of works by extremists and for
successful implementation of this project.
The Committee further note that Left Wing Extremism is, to a large extent,
funded out of the extortion/concession, which the extremists get from many
151
Government contractors. All this make the entire development strategy counterproductive and self-defeating. The Committee, therefore, recommend that
credentials of contractors of LWE affected areas should be verified with help from
Ministry of Home Affairs and concerned State Governments in order to stop the
diversion of funds in the hands of unscrupulous elements.
NEW DELHI;
26 April, 2011
Vaisakha 6 ,1933(S)
FRANCISCO SARDINHA,
CHAIRMAN,
COMMITTEE ON ESTIMATES
152
Annexure I
Allocation and expenditure under of important schemes
of the Department of Road Transport & Highways during the year 2007-08
Sl No
Budget (Original)
Estimates
Revised
Estimates
1
1
2
EAP NHAI
a) Externally Aided (NHAI)
b) Loan to NHAI
Sub-total EAP NHAI
a) National Highways (original) - including Rs 200.24 crore
re-appropriated from MH 4552 for
NE States
b) Travel Expenses (Rs. 1.39 crore) c) Machinery &
equipment (Rs. 38.25 crores) (including Rs 5.00 crore for
NE States)
a) Works under BRDB - Other than NER
b) Works under BRDB - NER
Sub-total - BRDB
Other charges
Development of information technology
a) Strategic roads under BRDB NER
b) Strategic roads Other than NER
Sub-total Strategic roads
R&D Planning studies
Professional Organisation (Rs. 1.00 crore)/ Training (Rs.
0.50 crore)
Charged expenditure
NHAI (investment)
E&I for States from CRF (including Rs.41.00 crore for
POSCO, Orissa and Mughal Road in J&K.
E&I for UTs from CRF
a) SARDP-NE - BRDB
b) SARDP-NE - - RPAO, Guwahati
c) SARDP-NE NHAI
Sub-total SARDP
Total
4
5
6
7
8
9
10
11
12
13
Variations
Variations
Actual
Reasons for
Expenditure as between Col. 3 & between Col. 4 variations
4 Excess (+)
& 5 Excess (+) under Col. 6
on 31.03.09
Savings (-)
Savings (-)
6
1788.8
447.2
2236
2079.25
1776
444
2220
2028.64
1776
444
2220
2011.07
349.76
150
499.76
0.5
9.5
7
67
74
8.5
1.5
449.76
200
649.76
0.5
2.75
7
67
74
1.86
1.5
423.93
200
623.93
0.5
0.32
6.35
61.45
67.8
0.2
0.35
6
6541.06
264.93
6
6541.06
205.93
5.93
6541.06
169.7
9
250
150
0
710
12440
9
270
146
294
710
12451
1.6
270
134.02
294
698.02
12339.92
*NOTE : Does not include Rs.60.00 crore (RE Rs.49.00 crore) for Road Transport & Rs.2090.00 crore as IEBR.
7
-12.8
-3.2
-16
8
0 As per actual
0 As per actual
0
-50.61
100
50
150
0
-6.75
0
0
0
-6.64
-17.57
-25.83
0
-25.83
0
-2.43
-0.65
-5.55
-6.2
-1.66
0
0
0
-1.15
-0.07
0
-59
0
20
-4
294
0
11
-36.23
-7.4
0
-11.98
0
-11.98
-111.08
(Rs in crores)
Reasons for
variations
under Col. 7
9
-
As allocated
As allocated
As allocated
As per actual
As per actual
-
As per actual
-
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
-
As allocated
As per actual
As per actual
As per demand
As allocated
As per actual
As per demand
-
Allocation and expenditure of important schemes (not included in the Annual Plan) of the Department of Road Transport & Highways (Roads Wing) during the
year 2007-08
Sl No
Budget (Original)
Estimates
Revised
Estimates
1
1
2
CRF for States
CRF for Delhi
CRF for Pondicherry
CRF for A&N Islands
CRF for Chandigarh
CRF for Dadra & Nagar Haveli
CRF for Daman & Diu
CRF for Lakshadweep
Sub-total - CRF
Maintenance and repairs of National Highways - Roads
Wing
Maintenance and repairs of National Highways entrusted to
Border Roads Wing
NH Tribunals
NH Administration - other charges
Equipment & Machinery (Non-Plan)
Permanent International Association of Road Congress,
Paris (PIARC)
Works financed from Permanent Bridge Fee Fund
Cost of collection of fee payable to States
Grants for development of State roads from GBS
Total
2
3
4
5
6
7
8
9
10
Variations
Variations
Actual
Reasons for
Expenditure as between Col. 3 & between Col. 4 variations
4 Excess (+)
& 5 Excess (+) under Col. 6
on 31.03.09
Savings (-)
Savings (-)
1511.45
44.69
3.67
1.9
2.28
1.1
0.79
0.12
1566
794.32
1511.45
44.69
3.67
1.9
2.28
1.1
0.79
0.12
1566
971.62
5
1312.19
9.5
0
0.5
0
0
0
0
1322.19
952.64
20.06
30.06
28.71
1.9
1
1.54
0.05
1.9
1
1.54
0.05
0.2
0.07
0.2
0.04
90
0.5
0.68
2476.05
90
0.5
0.68
2663.35
61.57
0
0.52
2366.14
6
0
0
0
0
0
0
0
0
0
177.3
10
0
0
0
0
0
0
0
187.3
7
-199.26
-35.19
-3.67
-1.4
-2.28
-1.1
-0.79
-0.12
-243.81
8
-
(Rs in crores)
Reasons for
variations
under Col. 7
9
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
Annexure II
Allocation and expenditure under of important schemes
of the Department of Road Transport & Highways during the year 2008-09
Sl No
Budget (Original)
Estimates
Revised
Estimates
Variations
Variations
Actual
Reasons for
Expenditure as between Col. 3 & between Col. 4 variations
4 Excess (+)
& 5 Excess (+) under Col. 6
on 31.03.09
Savings (-)
Savings (-)
5
(Rs in crores)
Reasons for
variations
under Col. 7
EAP NHAI
a) Externally Aided (NHAI)
1515.00
1515.00
b) Loan to NHAI
379.00
379.00
Sub-total EAP NHAI
1894.00
1894.00
2
2142.79
2853.74
a) National Highways (original) including
2.00
2.00
b) Travel Expenses (Rs. 2.00 crore)
10.00
4.05
c) Machinery & equipment (Rs.10.00 crore)
Sub-total - NH(O)
2154.79
2859.79
3
Rail-cum-Road bridge, Munger, Bihar
40.00
40.00
4
650.00
650.00
Works under BRDB
5
Other charges
0.50
0.50
6
Development of information technology
3.50
3.50
7
78.00
78.00
BRDB - Strategic Roads
8
R&D Planning studies
8.50
3.50
9
Professional Organisation (Rs. 1.00 crore)/
1.50
1.50
Training (Rs. 0.50 crore)
10
Charged expenditure
6.00
6.00
11
NHAI (investment)
6972.47
6972.47
12
a) E&I for States from CRF
175.74
175.74
b) E&I - POSCO
40.00
40.00
c) E&I - Mughal Road
30.00
30.00
d) E&I - Sansari Nulla Killer
5.00
5.00
13
e) E&I for UTs from CRF
10.00
10.00
Sub-total - E&I
260.74
260.74
14
700.00
500.00
a) SARDP-NE - BRDB
b) SARDP-NE - RPAO, Guwahati
400.00
400.00
c) SARDP-NE Not allocated
100.00
100.00
SARDP-NE
1200.00
1000.00
Grand Total
13270.00
13770.00
*Rs.500.00 crore additional fund provided under NH(O) through 2nd Batch of supplementary.
1515.00
379.00
1894.00
2852.70
1.24
3.07
2857.01
40.00
645.80
0.13
0.71
76.96
0.71
0.16
2.07
6972.47
175.65
40.00
0.00
0.00
0.00
215.65
398.11
245.61
0.00
643.72
13349.39
0.00
0.00
0.00
710.95
0.00
-5.95
705.00
0.00
0.00
0.00
0.00
0.00
-5.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
-200.00
0.00
0.00
-200.00
500.00
0.00
0.00
0.00
-1.04
-0.76
-0.98
-2.78
0.00
-4.20
-0.37
-2.79
-1.04
-2.79
As per actual
As per actual
As per actual
As per actual
As per actual
-1.34
-3.93
0.00
-0.09
0.00
-30.00
-5.00
-10.00
-45.09
-101.89 As allocated
-154.39
-100.00
-356.28
-420.61
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
Allocation and expenditure under of important schemes (not included in the Annual Plan) of the Department of Road Transport & Highways during the year 200809
Sl No
1
1
Budget (Original)
Estimates
2
3
CRF for States*
1605.82
CRF for Delhi
48.45
CRF for Pondicherry
7.59
CRF for A&N Islands
3.27
CRF for Chandigarh
3.51
CRF for Dadra & Nagar Haveli
1.64
CRF for Daman & Diu
1.24
CRF for Lakshadweep
0.12
Sub-total - CRF
1671.64
2
Maintenance and repairs of National Highways
792.03
- Roads Wing** &
3
Maintenance and repairs of National Highways
26.35
entrusted to Border Roads Wing
4
NH Tribunals
2.40
5
NH Administration - other charges
2.50
6
Equipment & Machinery (Non-Plan)
2.00
7
Permanent International Association of Road
0.05
Congress, Paris (PIARC)
8
Works financed from Permanent Bridge Fee
90.00
Fund
9
Cost of collection of fee payable to States
0.50
Total=
2587.47
* Rs.500.00 crore provided under CRF for States under 2nd Batch of supplementary
**Rs.155.94 crore provided under M&R for Road Wing through at RE stage.
& Expenditure provisional subject to final adjusment with States
Revised
Estimates
Variations
Variations
Actual
Reasons for
Expenditure as between Col. 3 & between Col. 4 variations
4 Excess (+)
& 5 Excess (+) under Col. 6
on 31.03.09
Savings (-)
Savings (-)
2105.82
48.45
7.59
3.27
3.51
1.64
1.24
0.12
2171.64
947.97
5
2072.98
41.29
6.56
0.00
1.17
0.00
0.00
0.00
2122.00
947.77
26.00
21.68
2.40
2.50
2.00
0.05
0.44
0.02
0.14
0.05
90.00
68.71
0.50
3243.06
0.00
3160.81
7
500.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
500.00
155.94
-0.35
0.00
0.00
0.00
8
-32.84 As per demand
-7.16
-1.03
-3.27
-2.34
-1.64
-1.24
-0.12
-49.64
Reasons for
variations
under Col. 7
9
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
0.00
0.00
0.00
0.00
655.59
-21.29
-0.50
-82.25
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
Annexure III
Allocation and expenditure of important schemes (included in the Annual Plan) of the Ministry of Road Transport & Highways during the financial year 2009-10
(Rs in crores)
Sl No
Name of the scheme
Budget
Revised
Variations Variations Reasons for
Actual
Reasons for
(Original)
Estimates
between variations
Expenditure between Col.
variations under
Estimates
3 & 4 Excess Col. 4 & 5 under Col. 6
as on
Col. 7
(+) Savings (- Excess (+)
31.03.10
)
Savings (-)
1
1
3
4
5
6
7
8
9
10
11
12
13
14
15
2
EAP NHAI
a) Externally Aided (NHAI)
b) Loan to NHAI
Sub-total EAP NHAI
a) National Highways (original) Works (Rs.4029.55 + Rs.313.00
from MH 4552) (52.00 crore as additional from MH-4552 , 103
crore supplementary grant and 845 crore by re-appropriation =
Rs.1000 crore)
b) Travel Expenses (Rs. 2.00 crore)
c) Machinery & equipment (Rs.15.00 crore)
Sub-total - Other Schemes
Funds for National Highways in Naxalite affected area
Rail-cum-Road bridge, Munger, Bihar
Development of Vijayawada-Ranchi Road
Works under BRDB (Rs.706.00+Rs.50.00 from MH 4552)
Other charges
Development of information technology
BRDB - Strategic Roads
R&D Planning studies
Professional Organisation (Rs. 1.00 crore)/ Training (Rs. 0.50
crore)
Charged expenditure
NHAI (investment)
a) E&I for States from CRF
b) E&I - POSCO
c) E&I - Mughal Road
d) E&I - Sansari Nulla Killer
e) E&I for UTs from CRF
Sub-total - E&I
a) SARDP-NE to BRDB
a) SARDP-NE to RPAO, Guwhati
b) SARDP - Other Admn. Expenses
c) SARDP- Not allocated
SARDP-NE
272.00
68.00
340.00
3342.55
272.00
68.00
340.00
4342.55
272.00
68.00
340.00
4298.12
2.00
15.00
3359.55
500.00
60.00
200.00
600.00
2.00
15.00
4359.55
125.00
60.00
20.00
756.00
1.20
0.53
4299.85
5.00
60.00
0.00
723.49
0.50
3.50
60.00
5.50
1.50
0.50
3.50
100.00
4.50
1.50
0.00
3.05
82.17
3.84
0.39
6.00
8578.45
213.97
30.00
20.00
3.00
16.03
283.00
700.00
490.00
10.00
0.00
1200.00
6.00
7404.70
184.67
30.00
20.00
3.00
13.83
251.50
700.00
490.00
10.00
0.00
1200.00
5.32
7404.70
104.35
0.00
0.00
0.00
0.00
104.35
380.91
277.60
0.04
0.00
658.55
7
0.00
0.00
0.00
0.00
0.00
0.00
1000.00
0.00
0.00
1000.00
-375.00
0.00
-180.00
As per actual
As per actual
As per actual
156.00
0.00
0.00
40.00
-1.00
As per actual
As per actual
As per actual
As per actual
As per actual
0.00
0.00
-1173.75
-29.30
0.00
0.00
0.00
-2.20
-31.50
0.00
0.00
0.00
0.00
0.00
-1.11
-0.68
0.00 As allocated
-80.32 As allocated
-30.00
-20.00
-3.00
-13.83 As allocated
-147.15
-319.09
-212.40
-9.96
0.00
-541.45
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
-
Sl No
Budget
(Original)
Estimates
Revised
Estimates
Variations
Actual
Expenditure between Col.
3 & 4 Excess
as on
(+) Savings (31.03.10
)
Reasons for
variations under
Col. 7
-565.25
-942.04
Grand Total
15198.00
14632.75
13690.71
Allocation and expenditure of important schemes (not included in the Annual Plan) of the Ministry of Road Transport & Highways during the year 2009-10
Sl No
Budget
(Original)
Estimates
Revised
Estimates
2
3
4
5
6
7
8
9
Variations
Actual
Expenditure between Col.
3 & 4 Excess
as on
(+) Savings (31.03.10
)
-272.34
-8.22
-1.29
-0.55
-0.59
-0.28
-0.21
-0.02
-283.50
-1.34
-375.95
-51.78
-8.11
-2.29
-0.56
-1.43
-1.33
-0.13
-441.58
-77.61
1988.55
60.00
9.40
4.05
4.34
2.03
1.54
0.15
2070.06
1036.44
24.00
1716.21
51.78
8.11
3.50
3.75
1.75
1.33
0.13
1786.56
1035.10
24.00
1340.26
0.00
0.00
1.21
3.19
0.32
0.00
0.00
1344.98
957.49
23.73
2.40
2.50
2.00
0.06
0.91
0.83
0.50
0.06
0.03
0.02
0.00
0.00
90.00
0.50
3227.96
90.00
0.50
2938.46
89.95
0.01
2416.21
0.00
-1.49
-1.67
-1.50
0.00
0.00
0.00
-289.50
Reasons for
variations under
Col. 7
As allocated
As allocated
As allocated
As allocated
As allocated
As allocated
As allocated
As allocated
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As per actual
As allocated
As per actual
-0.27
-0.88 As allocated
-0.81 As allocated
-0.50 As allocated
As per actual
As per actual
As per actual
As per actual
-0.06
-0.05
-0.49
-522.25
As per actual
As per actual
As per actual
Annexure IV
List of Under Implementation Projects
S.No.
stretch
NH No
Total
Length
(In Km)
Completed
Length
(In Km)
Funded
By
TPC
(Rs.Cr.)
Date of
Start
Date of
completion as
per contract
Date of
Completion
anticipated
59
11.9
BOT
390.56
Feb2010
Feb-2012
Feb-2012
Gundla Pochampalli to
Bowenpalli Shivarampalli to
Thondapalli (NS-23/AP)
23.1
16.2
NHAI
71.57
Dec2005
Dec-2006
Mar-2011
Hyderabad-Vijayawada
181.63
BOT
1740
Apr2010
Oct-2012
Oct-2012
Cuddapah-Mydukur-Kurnool
18
188.752
BOT
1585
Aug2010
Feb-2013
Feb-2013
183.52
BOT
1535
Hyderabad-Yadgiri (Approved
Length 30)
202
35.65
13.05
BOT
388
Aug2010
May-2012
May-2012
82.5
11
BOT
572.3
May2009
Oct-2011
Oct-2011
54
28
NHAI
385.13
Oct2006
Apr-2009
Dec-2013
54
23
NHAI
167.64
May2006
Nov-2008
Dec-2013
10
54
24
24
NHAI
225
Dec2005
Jun-2008
Mar-2011
11
54
16
6.75
NHAI
280
Aug2006
Feb-2009
Dec-2011
12
31
30
26.65
NHAI
200
Dec2005
Jun-2008
Mar-2011
13
54
15
NHAI
280.13
May2006
Nov-2008
Dec-2013
14
31
25
13
NHAI
225
Nov2005
Jun-2009
Dec-2011
15
54
21
NHAI
200
Oct2006
Apr-2009
Dec-2011
16
31
28
NHAI
175.96
Dec2005
Apr-2008
Mar-2012
17
31
27.3
NHAI
208
Oct2005
Apr-2008
Dec-2011
18
31
NHAI
217.61
Oct2006
Apr-2010
Mar-2012
19
31C
30
0.5
NHAI
195
Nov2005
Jun-2008
Dec-2011
20
31
21.5
19.105
NHAI
142
Dec2005
Jun-2008
Dec-2011
21
54
18.5
10.7
NHAI
130
Feb2008
Aug-2010
Dec-2011
22
31C
30
16.62
NHAI
230
Nov2005
Jun-2008
Dec-2011
23
31C
33
10.1
NHAI
237.8
Nov2005
Jun-2008
Dec-2011
24
54
24
NHAI
196
Jan2007
Jul-2009
Dec-2013
25
Silchar-Udarband (AS-1)
54
32
12.5
NHAI
154.57
Sep2004
Sep-2007
Mar-2011
26
37
25
12
NHAI
264.72
Dec2005
Jun-2008
Dec-2011
27
31
28
11.5
NHAI
198.16
Oct2005
Apr-2008
Mar-2012
28
37
23
22.185
NHAI
230
Dec2005
Jun-2008
Apr-2011
29
37
19
14
NHAI
245
Sep2005
Jun-2009
Dec-2011
30
37
22
NHAI
160
Nov2005
May-2008
Dec-2011
31
37
25
14.602
NHAI
200
Dec2005
Jun-2008
Dec-2011
32
36
30.5
23.415
NHAI
225
Dec2005
Jun-2008
Oct-2011
33
54
26
NHAI
212
Jan2007
Jul-2009
Dec-2013
34
28
38
33
WB
240
Nov2005
Nov-2008
Mar-2011
35
28
41.085
WB
300
Nov2005
Oct-2008
Jun-2012
36
57
15.15
13.36
NHAI
100.5
Apr2006
Apr-2008
Jun-2011
37
80
69.27
Annuity
351.54
38
57A
9.258
Annuity
73.55
39
Patna - Bakhtiarpur
30
50.6
BOT
574
40
57
10.63
Annuity
418.04
Apr2007
Apr-2010
Jun-2011
41
57
38.55
35.6
NHAI
340
Jan2006
Jun-2008
Mar-2011
42
57
37.59
22
NHAI
340
Apr2006
Sep-2008
Dec-2011
43
57
37.75
37.75
NHAI
291.8
Jan2006
Jun-2008
Feb-2011
44
28
40
37
WB
275
Sep2005
Sep-2008
Mar-2011
45
28
40
37
WB
239
Sep2005
Sep-2008
Mar-2011
46
Forbesganj-Simrahi (BR-3)
57
34.87
13.5
NHAI
332.94
Apr2006
Sep-2008
Jun-2011
47
77
86
Annuity
511.54
48
57
32.05
31.75
NHAI
305
49
Motihari-Raxaul (Approved
Length 67 Km)
28A
68.79
BOT
375.09
50
Patna- Muzzaffarpur
19 &
77
63
Annuity
671.3
May
2010
Nov 2012
Nov 2012
51
31
28
26.41
NHAI
205.73
Sep2001
Sep-2004
Mar-2011
52
19
65
Annuity
575
Jan2006
Jun-2008
Nov-2011
53
Varanasi-Aurangabad
192.4
BOT
2848
54
82.685
77.3
BOT
464
Jan2008
Jan-2011
Apr-2011
55
Aurang - Raipur
43.485
40.7
BOT
190
Apr2006
Jan-2009
Mar-2011
56
12.9
12.9
NHAI
87.89
Jun2009
Sep-2010
Mar-2011
57
Panji-Goa/Karnatka Border
4A
69
BOT
471
58
17
139
BOT
1872
59
4 Laning of Ahmedabad to
Godhara (Approved Length 210
Km)
59
117.6
BOT
1008.5
60
59
87.285
BOT
785.5
61
Samaikhiali-Gandhidham
8A
56.16
BOT
805.39
Sep-10
Mar-13
Mar-13
62
8A
71.4
BOT
953.88
63
4 laning of Jetpur-Somnath
section of NH-8D (approved
length 127.6)
8D
123.45
BOT
828
64
132.9
4.93
BOT
1509.1
Mar2010
Sep-2012
Oct-2012
65
Gagodhar to Garamore
(Package-IV)
15, 8A
90.3
87.5
ADB
479.54
Feb2005
Nov-2007
Mar-2011
66
239
134.455
BOT
1693.75
Feb2009
Aug-2011
Aug-2011
67
Rohtak - Bawal(Approved
Length 97 Km)
71
82.553
BOT
650
68
Delhi/Haryana Border to
Rohtak
10
63.49
40.66
BOT
486
69
Panipat - Rohtak(Approved
Length 73 Km)
71A
80.858
BOT
807
70
291
103.5
BOT
2288
May2008
May-2010
May-2011
May2009
May-2011
Nov-2011
71
Zirakpur - Parwanoo
22
28.69
16.5
BOT
295
Feb2008
Aug-2010
May-2011
72
225.6
65
BOT
1673.7
Apr2009
Oct-2011
Jun-2012
73
179.5
BOT
1928.22
74
Chenani-Nashri
1A
12
Annuity
2159
Jun2010
Jun-2015
Jul-2015
75
1A
30
25.85
NHAI
193.1
Sep2005
Feb-2008
Jun-2011
76
1A
33.65
27.95
NHAI
166.3
Sep2005
Feb-2008
Jun-2011
77
Jammu - Udhampur
1A
65
Annuity
1813.76
Jul2010
Jul-2013
Jul-2013
78
1A
15
14.7
NHAI
85.34
Nov2005
May-2008
Mar-2011
79
1A
17.2
17
NHAI
110
Jan2002
Dec-2004
Mar-2011
80
1A
1.23
NHAI
62.96
Jun2006
Dec-2008
Dec-2011
81
Quazigund-Banihal
1A
15.25
Annuity
1987
Jul2010
Jul-2015
Jul-2015
82
Srinagar to Banihal
1A
67.76
Annuity
1100.7
83
Hazaribagh-Ranchi
33
75
Annuity
625.07
84
33
41.314
BOT
398
85
Chitradurga -Tumkur
Bypass(Approved Length 145
Km)
114
BOT
839
Mar2011
Aug-2013
Aug-2013
86
Neelamangala Junction on NH
4 with NH 48 to Devihalli
48
81
77.5
BOT
441
Jan2008
Jul-2010
Mar-2011
87
Belgaum-Dharwad(Approved
Length 111 Km)
80
BOT
480
Dec2010
Jun-2013
Jun-2013
88
Banglore-Hoskote-Mudbagal
Section
79.724
79.6
BOT
565
Jan2008
Jul-2010
Mar-2011
Aug2010
Jan-2013
Jan-2013
89
Hungund-Hospet (Approved
Length 194 Km)
13
97.89
BOT
946
Sep2010
Mar-2013
Mar-2013
90
Haveri - Harihar
56
56
NHAI
196.65
Nov2008
Jul-2010
Mar-2011
91
22.12
BOT
680
Nov2010
Nov-2012
Nov-2012
92
Devihalli-Hassan(Approved
Length 73 Km)
48
77.23
BOT
453
Dec2010
May-2013
May-2013
93
Harihar - Chitradurga
77
77
NHAI
207.56
Oct2008
Jun-2010
Mar-2011
94
13
97.22
BOT
748
Sep2010
Sep-2010
Mar-2013
95
Kundapur-Surathkal &
Mangalore-KNT/Kerala Border
17
90
BOT
671
Sep2010
Mar-2013
Mar-2013
96
13, 17
& 48
37
35.31
SPV
196.5
Jun2005
Dec-2007
Mar-2011
4A
81.89
BOT
359
Mar2011
Sep-2013
Sep-2013
97
4 Laning of Belgaum-Khanpur
Section(Km 0.00 to Km 30.00)
and 2 Laning with paved
sholuders of khanpur-Knt/Goa
border.(Km 30.00 to Km 84.120)
Sep2006
98
47
40
40
BOT
312.5
Mar-2009
Mar-2011
99
17
83.2
BOT
1366
100
NH Connectivity to ICTT
Vallarpadam
47C
17.2
15.1
NHAI
557
101
Charthalai-ochira
47
83.6
BOT
1535
102
17
126.6
BOT
1157.16
103
47
30
BOT
617
104
17
81.5
BOT
1312
105
Indore-Dewas(Approved Length
55 Km)
45.05
BOT
325
Nov2010
May-2013
May-2013
106
Indore-Jhabua-Gujrat/MP
(Approved Length 168)
59
155.15
BOT
1175
Oct2010
Apr-2013
Apr-2013
Aug2007
Feb2010
Feb-2010
Aug-2012
May-2012
Aug-2012
107
26
54
34.1
ADB
251.03
Apr2006
Oct-2008
Jun-2011
108
Khalghat - MP/Maharashtra
Border
82.8
78
BOT
549
Nov2008
May-2011
May-2011
109
75, 3
42
36.29
Annuity
300.93
Apr2007
Oct-2009
Mar-2011
110
26
44
28.5
ADB
203.43
Apr2006
Oct-2008
Dec-2011
111
26
54.7
48.82
ADB
229.91
Apr2006
Oct-2008
Jun-2011
112
56.475
27.73
Annuity
407.6
Dec2007
Jun-2010
Oct-2012
113
49.35
40.11
Annuity
263.17
Mar2007
Sep-2009
Oct-2012
114
Bhopal-Sanchi(Approved
Length 40 Km)
86Ex
53.78
Annuity
209
115
26
55
50.28
ADB
225
Apr2006
Oct-2008
Mar-2011
116
26
26
23.3
ADB
151.3
Apr2006
Oct-2008
Nov-2011
117
10
2.5
NHAI
232.45
Sep2007
Sep-2010
Jun-2012
118
69
176.3
Annuity
2498.76
Feb2011
Aug-2014
Aug-2014
69A &
26B
418
NHAI
1565
75
80
31.17
Annuity
604
Jun2007
Dec-2009
Jun-2011
Jun2005
Dec-2007
Apr-2011
120
Multai-Chhindwara-Seoni
section & NarsinghpurAmarwara-Umranala-Saoner
section ( 2-laning with 4 paved
shoulders)
Gwalior - Jhansi
121
Borkhedi-Jam (NS-22/MH)
27.4
27
NHAI
110
122
Panvel-Indapur
17
84
BOT
942.69
123
MP/Maharashtra Border-Dhule
98
32
BOT
835
Dec2009
Jun-2012
Jun-2012
124
Talegaon-Amravat(Approved
Length 58Km)
67.8
BOT
567
Nov2009
Nov-2013
Nov-2013
119
125
Nagpur - kondhali
40
37.8
BOT
168
Jun2006
Dec-2008
Aug-2011
126
Gonde-Vadape (Thane)
100
98
BOT
579
Apr2006
Apr-2009
Mar-2011
127
Pune-Sholapur Pkg-I(Approved
Length Pkg I & II 170 Km)
110.05
29.5
BOT
1110
Nov2009
Mar-2012
May-2012
128
95
22.015
BOT
1170.52
Apr2010
Jun-2012
Oct-2012
129
Wadner-Devdhari (NS-60/MH)
29
NHAI
145
T E
R
M I N A
T E D
130
Kelapur-Pimpalkhatti (NS-62)
22
8.5
NHAI
117.4
T E
R
M I N A
T E D
131
Jam-Wadner (NS-59/MH)
30
28.605
NHAI
145
Oct2005
Apr-2008
Apr-2011
132
140.35
BOT
1724.55
133
Pune-Sholapur Pkg-II(Approved
Length I & II 170 Km)
105
BOT
835
134
Butibori ROB(NS-29/MH)
1.8
0.5
NHAI
26
Jun2005
Dec-2006
Apr-2011
135
60
13
BOT
940
Jan2010
Jul-2012
Jul-2012
136
Shilong-Bypass
40 &
44
50
Annuity
226
137
Jorbat-Barapani
40
61.8
Annuity
536
138
62.64
57.5
NHAI
228.7
139
67
BOT
1047
140
Sambalpur-BaragarhChattisgarh/Orrisa Border
88
BOT
909
141
50.8
47.81
NHAI
263.27
Jul2006
Nov-2008
Apr-2011
142
55.713
33.78
NHAI
241.53
Oct2009
Oct-2011
Oct-2011
Dec2008
Dec-2010
Mar-2011
Jan2001
143
27.15
27.15
NHAI
140.85
144
Bhubneshwar-Puri(Approved
Length 59 Km)
203
67
BOT
500.29
145
215
96
BOT
586
146
1A
44
14
NHAI
359
147
95
78
BOT
479
148
Kurali - Kiratpur
21
42.9
40
BOT
309
Dec2007
Jun-2010
Mar-2011
149
15
106
BOT
705
May2010
Nov-2012
Nov-2012
150
1A
19.65
13.375
NHAI
97.73
Nov2005
May-2008
Jun-2011
151
1A
40
37.83
NHAI
284
Nov2005
May-2008
Jun-2011
Feb2010
Jan-2004
Aug-2012
Mar-2011
Aug-2012
152
Jaipur-Tonk - Deoli(Approved
Length 148.77 Km )
12
150
BOT
792.06
Jun2010
153
Deoli - Kota
12
83
BOT
593
154
Kishangarh-Ajmer-Beawar
82
13
BOT
795
Nov2009
May-2012
May-2012
155
76
1.4
NHAI
281.31
Nov2006
Feb-2010
Mar-2012
156
76
26.42
26.35
NHAI
250.39
May2006
Nov-2008
Feb-2011
157
Jaipur-Reengus(Approved
Length 52.65 Km )
11
54
BOT
267.81
Aug-10
Feb 2013
Feb 2013
158
46
148.3
BOT
1250
159
Madurai-Kanniakumari
Section(NS-41/TN)
39.23
39.23
NHAI
323.36
Sep2005
Apr-2008
Mar-2011
160
67,
KC2
55.2
54.35
MORTH
Aug2006
Aug-2008
Mar-2011
Dec-2012
Dec-2012
161
Trichy - Dindigul
45
88.273
82
BOT
576
Jan2008
162
2 Laning of Dindigul-PerigulamTheni-Kumili
220
134
Annuity
485
163
Tuticorin Port
7A
47.2
SPV
182.25
164
210 &
67
110.372
Annuity
374
165
Madurai-Arupukottai-Tuticorin
45B
128.16
127
BOT
629
Jan2007
Jan-2010
Feb-2011
166
Salem-Ulundrupet (BOT-1/TN06)
68
136.357
97
BOT
941
Jan2008
Jan-2011
Jun-2011
167
Chengapalli to Coimbatore
Bypass and End of Coimbatore
Bypass to TN/Kerala Border
47
54.83
BOT
852
168
Thanjarur - Trichy
67
56
54.16
BOT
280
Dec2006
Jun-2009
Feb-2011
169
43.4
BOT
353.37
Apr2009
Oct-2011
Oct-2011
Apr2010
Jul-2010
Apr-2012
Mar-2011
Apr-2012
170
Sep2010
19
BOT
1655
Sep-2013
Sep-2013
171
SR
30.2
SPV
600
172
59.87
BOT
535
173
Trichy - Karur
67
79.7
58
BOT
516
Jan2008
Jul-2010
Jun-2011
174
Kanniyakumari-Panagudi(NS32)
31.7
30.83
NHAI
120
Apr2008
Apr-2010
May-2011
175
Improvement of Access of GQ
within Chennai City including
Construction of 4 grade
Seperators
205 , 4
& 45
MORTH
210
Apr2005
Apr-2007
Mar-11
176
Pondicherry - Tindivanam
66
38.61
35.7
BOT
285
Jan2008
Jul-2010
Apr-2011
177
205
124.7
BOT
571
178
Garhmukteshwar - Muradabad
24
56.25
55.85
NHAI
275
Mar2005
Sep-2007
Mar-2011
Dec2005
179
28
40
33.5
WB
242
Dec-2008
May-2011
180
Kanpur - Kabrai
86
123
BOT
373.47
181
26
38
30
ADB
198
May2006
Nov-2008
Mar-2011
182
Meerut-Muzaffarnagar
58
79
75
BOT
359
Mar2006
Mar-2009
Mar-2011
183
Gorakhpur Bypass
28
32.6
18.5
Annuity
600.24
Apr2007
Oct-2009
Jun-2011
184
Ayodhya-Lucknow (LMNHP-3)
28
46
45.5
WB
212
Nov2005
Nov-2008
Mar-2011
185
Hapur - Garhmukteshwar
24
35
23
NHAI
220
Mar2005
Sep-2007
Jun-2011
186
Gorakhpur-Ayodhya (LMNHP-4)
28
29
27.25
WB
205
Nov2005
Nov-2008
Mar-2011
187
Gorakhpur-Ayodhya (LMNHP-5)
28
44
33
WB
227
Oct2005
Oct-2008
Jun-2011
Oct2005
188
Gorakhpur-Ayodhya (LMNHP-6)
28
44.86
44.77
WB
239
Oct-2008
Feb-2011
189
Agra - Aligarh
93
79
BOT
250.5
190
Aligarh - Kanpur
91
268
BOT
723.68
191
Raibariely to Allahabad
24B
119
BOT
291.36
192
25, 26
49.7
38.7
Annuity
355.06
Mar2007
Sep-2009
Mar-2011
193
25
16
15.3
NHAI
54
Feb2010
Aug-2011
Aug-2011
194
Bara to Orai
2, 25
62.8
59
Annuity
465
Oct2006
Apr-2009
Mar-2011
195
Agra-Shikohabad (GTRIP/I-A)
50.83
50.76
WB
367.49
Mar2002
Mar-2005
Mar-2011
196
56A &
B
22.85
18
NHAI
111.78
Mar2009
Aug-2010
Mar-2011
197
Muradabad-Bareily (Approved
Length 112)
24
121
BOT
1267
198
25
5.6
0.7
NHAI
201.66
Dec2005
Sep-2008
Jun-2011
199
Sitapur - Lucknow
24
75
64.5
BOT
322
Jun2006
Jun-2009
Mar-2011
200
2,3
32.8
NHAI
348.16
Oct2007
Oct-2010
Jun-2013
201
Bareily - Sitapur(Approved
Length 134 Km)
24
151.2
BOT
1046
202
28
41.115
35
WB
227
203
Ghaziabad-Aligarh (Approved
Length 106 )
91
126
BOT
1141
204
25
15
14.83
ADB
158.06
Nov2005
May-2008
Mar-2011
205
25
68.2
68.2
ADB
451.97
Oct2005
Apr-2008
Mar-2011
Dec2005
Dec-2008
Jun-2011
206
Ayodhya-Lucknow (LMNHP-2)
28
47
45.5
WB
217
Oct2005
Oct-2008
Mar-2011
207
25
50
48.1
ADB
340.68
Sep2005
Mar-2008
Mar-2011
208
Ayodhya-Lucknow (LMNHP-1)
28
36.75
34
WB
193
Oct2005
Oct-2008
Mar-2011
209
26
49.3
48
Annuity
276.09
Mar2007
Sep-2009
Mar-2011
210
Muzaffarnagar - Haridwar
(Approved Length 77 )
58, 72
80
BOT
754
211
72
39
Annuity
478
212
31C
32
17.33
NHAI
221.82
Jun2006
Nov-2008
Sep-2011
213
Dalkola Bypass
34
5.5
NHAI
67
Sep2006
Aug-2008
Jun-2011
214
Haldia Port
41
53
48.242
SPV
522
Sep2008
Sep-2010
Jun-2011
215
4 Laning of Brahampore-Faraka
34
103
BOT
998.79
216
4 Laning of Faraka-Raiganj
34
103
BOT
1078.84
217
4 Laning of Raiganj-Dalkola
34
50
BOT
580.43
218
1.732
0.48
NHAI
81
T E R
M I N A
T E D
219
31
26
17.84
NHAI
225
Jan2006
Jul-2008
Dec-2012
Annexure V
List of Under Implementation (NS-EW Corridor) Projects :
S.No
Stretch
NH No
Total
Length
(Km)
Complete
Completio
UI Length
Anticipated
d length
Start Date n as per
(km)
Completion
(Km)
contract
State Name
Category
37
25
12
13
Dec-2005 Jun-2008
Dec-2011
Assam
EW
31
Oct-2006 Apr-2010
Mar-2012
Assam
EW
31C
33
10.1
22.9
Nov-2005 Jun-2008
Dec-2011
Assam
EW
37
19
14
Sep-2005 Jun-2009
Dec-2011
Assam
EW
37
22
15
Nov-2005 May-2008
Dec-2011
Assam
EW
37
25
14.602
10.398
Dec-2005 Jun-2008
Dec-2011
Assam
EW
37
23
22.185
0.815
Dec-2005 Jun-2008
Apr-2011
Assam
EW
36
30.5
23.415
7.085
Dec-2005 Jun-2008
Oct-2011
Assam
EW
54
18.5
10.7
7.8
Feb-2008 Aug-2010
Dec-2011
Assam
EW
10
54
15
15
Feb-2011 Aug-2013
Aug-2013
Assam
EW
11
54
28
28
Mar-2011 Sep-2013
Sep-2013
Assam
EW
12
54
23
23
May-2006 Nov-2008
Dec-2013
Assam
EW
13
54
24
24
Dec-2005 Jun-2008
Mar-2011
Assam
EW
14
54
16
6.75
9.25
Aug-2006 Feb-2009
Dec-2011
Assam
EW
15
31
21.5
19.105
2.395
Dec-2005 Jun-2008
Dec-2011
Assam
EW
16
31
30
26.65
3.35
Dec-2005 Jun-2008
Mar-2011
Assam
EW
17
31
27.3
20.3
Oct-2005 Apr-2008
Dec-2011
Assam
EW
18
31
25
13
12
Nov-2005 Jun-2009
Dec-2011
Assam
EW
19
54
21
21
Oct-2006 Apr-2009
Dec-2011
Assam
EW
20
31C
30
16.62
13.38
Nov-2005 Jun-2008
Dec-2011
Assam
EW
21
54
26
26
Jan-2007
Jul-2009
Dec-2013
Assam
EW
22
Silchar-Udarband (AS-1)
54
32
12.5
19.5
Sep-2004 Sep-2007
Mar-2011
Assam
EW
23
31C
30
0.5
29.5
Nov-2005 Jun-2008
Dec-2011
Assam
EW
24
31
28
11.5
16.5
Oct-2005 Apr-2008
Mar-2012
Assam
EW
25
31
28
20
Dec-2005 Apr-2008
Mar-2012
Assam
EW
26
54
24
24
Jan-2007
Jul-2009
Dec-2013
Assam
EW
27
57
38.55
35.6
2.95
Jan-2006 Jun-2008
Mar-2011
Bihar
EW
28
28
40
37
Sep-2005 Sep-2008
Mar-2011
Bihar
EW
29
28
40
37
Sep-2005 Sep-2008
Mar-2011
Bihar
EW
30
57
37.75
37.75
Jan-2006 Jun-2008
Feb-2011
Bihar
EW
31
57
37.59
22
15.59
Apr-2006 Sep-2008
Dec-2011
Bihar
EW
32
28
41.085
34.085
Nov-2005 Oct-2008
Jun-2012
Bihar
EW
33
57
10.63
10.63
Apr-2007 Apr-2010
Jun-2011
Bihar
EW
34
57
15.15
13.36
1.79
Apr-2006 Apr-2008
Jun-2011
Bihar
EW
35
28
38
33
Nov-2005 Nov-2008
Mar-2011
Bihar
EW
36
31
28
26.41
1.59
Sep-2001 Sep-2004
Mar-2011
Bihar
EW
37
57
32.05
31.75
0.3
Jan-2006 Jun-2008
Nov-2011
Bihar
EW
38
Forbesganj-Simrahi (BR-3)
57
34.87
13.5
21.37
Apr-2006 Sep-2008
Jun-2011
Bihar
EW
39
15, 8A
90.3
87.5
2.8
Feb-2005 Nov-2007
Mar-2011
Gujarat
EW
40
76
1.4
1.4
Nov-2006 Feb-2010
Mar-2012
Rajasthan
EW
41
76
26.42
26.35
0.07
May-2006 Nov-2008
Feb-2011
Rajasthan
EW
42
Ayodhya-Lucknow (LMNHP-2)
28
47
45.5
1.5
Oct-2005 Oct-2008
Mar-2011
Uttar
Pradesh
EW
43
28
40
33.5
6.5
Dec-2005 Dec-2008
May-2011
Uttar
Pradesh
EW
44
25
15
14.83
0.17
Nov-2005 May-2008
Mar-2011
Uttar
Pradesh
EW
45
28
41.115
35
6.115
Dec-2005 Dec-2008
Jun-2011
Uttar
Pradesh
EW
46
Ayodhya-Lucknow (LMNHP-3)
28
46
45.5
0.5
Nov-2005 Nov-2008
Mar-2011
Uttar
Pradesh
EW
47
Gorakhpur-Ayodhya (LMNHP-4)
28
29
27.25
1.75
Nov-2005 Nov-2008
Mar-2011
Uttar
Pradesh
EW
48
25
50
48.1
1.9
Sep-2005 Mar-2008
Mar-2011
Uttar
Pradesh
EW
49
Gorakhpur-Ayodhya (LMNHP-5)
28
44
33
11
Oct-2005 Oct-2008
Jun-2011
Uttar
Pradesh
EW
50
Bara to Orai
2, 25
62.8
59
3.8
Oct-2006 Apr-2009
Mar-2011
Uttar
Pradesh
EW
51
25
16
15.3
0.7
Feb-2010 Aug-2011
Aug-2011
Uttar
Pradesh
EW
52
25
5.6
0.7
4.9
Dec-2005 Sep-2008
Jun-2011
Uttar
Pradesh
EW
53
Ayodhya-Lucknow (LMNHP-1)
28
36.75
34
2.75
Oct-2005 Oct-2008
Mar-2011
Uttar
Pradesh
EW
54
Gorakhpur Bypass
28
32.6
18.5
14.1
Apr-2007 Oct-2009
Jun-2011
Uttar
Pradesh
EW
55
56A & B
22.85
18
4.85
Mar-2009 Aug-2010
Mar-2011
Uttar
Pradesh
EW
56
Gorakhpur-Ayodhya (LMNHP-6)
28
44.86
44.77
0.09
Oct-2005 Oct-2008
Feb-2011
Uttar
Pradesh
EW
57
25
68.2
68.2
Oct-2005 Apr-2008
Mar-2011
Uttar
Pradesh
EW
58
31C
32
17.33
14.67
Jun-2006 Nov-2008
Sep-2011
West Bengal
EW
59
31
26
17.84
8.16
Jan-2006
Jul-2008
Dec-2012
West Bengal
EW
60
23.1
16.2
6.9
Dec-2005 Dec-2006
Mar-2011
Andhra
Pradesh
NS
61
59
11.9
47.1
Feb-2010 Feb-2012
Feb-2012
Andhra
Pradesh
NS
62
12.9
12.9
63
Quazigund-Banihal
1A
15.25
15.25
64
1A
17.2
17
65
Chenani-Nashri
1A
12
66
1A
67
68
Jun-2009 Sep-2010
Mar-2011
Delhi
NS
Jul-2015
Jul-2015
Jammu
Kashmir
NS
0.2
Jan-2002 Dec-2004
Mar-2011
Jammu
Kashmir
NS
12
Jun-2010 Jun-2015
Jul-2015
Jammu
Kashmir
NS
1.23
1.23
Jun-2006 Dec-2008
Dec-2011
Jammu
Kashmir
NS
1A
15
14.7
0.3
Nov-2005 May-2008
Mar-2011
Jammu
Kashmir
NS
1A
33.65
27.95
5.7
Sep-2005 Feb-2008
Jun-2011
Jammu
Kashmir
NS
69
Jammu - Udhampur
1A
65
65
Jul-2010
Jul-2013
Jul-2013
Jammu
Kashmir
NS
70
1A
30
25.85
4.15
Sep-2005 Feb-2008
Jun-2011
Jammu
Kashmir
NS
71
Srinagar to Banihal
1A
67.76
67.76
Jammu
Kashmir
NS
72
47
30
30
Feb-2010 Aug-2012
Aug-2012
Kerala
NS
73
47
40
40
Sep-2006 Mar-2009
Mar-2011
Kerala
NS
74
26
44
28.5
15.5
Apr-2006 Oct-2008
Dec-2011
Madhya
Pradesh
NS
75
26
26
23.3
2.7
Apr-2006 Oct-2008
Nov-2011
Madhya
Pradesh
NS
76
56.475
27.73
28.745
Dec-2007 Jun-2010
Oct-2012
Madhya
Pradesh
NS
77
26
54
34.1
19.9
Apr-2006 Oct-2008
Jun-2011
Madhya
Pradesh
NS
78
75, 3
42
36.29
5.71
Apr-2007 Oct-2009
Mar-2011
Madhya
Pradesh
NS
79
26
54.7
48.82
5.88
Apr-2006 Oct-2008
Jun-2011
Madhya
Pradesh
NS
80
49.35
40.11
9.24
Mar-2007 Sep-2009
Oct-2012
Madhya
Pradesh
NS
81
26
55
50.28
4.72
Apr-2006 Oct-2008
Mar-2011
Madhya
Pradesh
NS
82
10
2.5
7.5
Sep-2007 Sep-2010
Jun-2012
Madhya
Pradesh
[1]/Rajasthan
[9]
NS
Jul-2010
83
Gwalior - Jhansi
75
80
31.17
48.83
Jun-2007 Dec-2009
Jun-2011
Madhya
Pradesh[68.5
]/Uttar
Pradesh[11.5
NS
84
95
22.015
72.985
Apr-2010 Jun-2012
Oct-2012
Maharashtra
NS
85
Wadner-Devdhari (NS-60/MH)
29
29
T E D
Maharashtra
NS
86
Borkhedi-Jam (NS-22/MH)
27.4
27
0.4
Jun-2005 Dec-2007
Apr-2011
Maharashtra
NS
87
Jam-Wadner (NS-59/MH)
30
28.605
1.395
Oct-2005 Apr-2008
Apr-2011
Maharashtra
NS
88
Kelapur-Pimpalkhatti (NS-62)
22
8.5
13.5
T E D
Maharashtra
NS
89
Butibori ROB(NS-29/MH)
1.8
0.5
1.3
Jun-2005 Dec-2006
Apr-2011
Maharashtra
NS
90
1A
19.65
13.375
6.275
Nov-2005 May-2008
Jun-2011
Punjab
NS
91
1A
44
14
30
Feb-2010 Aug-2012
Aug-2012
Punjab
NS
92
1A
40
37.83
2.17
Nov-2005 May-2008
Jun-2011
Punjab[29]/H
imanchal
Pradesh[11]
NS
93
47
54.83
54.83
Tamil Nadu
NS
94
Kanniyakumari-Panagudi(NS-32)
31.7
30.83
0.87
Apr-2008 Apr-2010
May-2011
Tamil Nadu
NS
95
Madurai-Kanniakumari Section(NS41/TN)
39.23
39.23
Sep-2005 Apr-2008
Mar-2011
Tamil Nadu
NS
96
25, 26
49.7
38.7
11
Mar-2007 Sep-2009
Mar-2011
Uttar
Pradesh
NS
97
26
38
30
May-2006 Nov-2008
Mar-2011
Uttar
Pradesh
NS
98
26
49.3
48
1.3
Mar-2007 Sep-2009
Mar-2011
Uttar
Pradesh
NS
99
2,3
32.8
32.8
Oct-2007 Oct-2010
Jun-2013
Uttar
Pradesh
NS
T E R
T E R
M I N A
M I N A
S.No
Stretch
NH No
Total
Length
(Km)
Complete
Completio
UI Length
Anticipated
d length
Start Date n as per
(km)
Completion
(Km)
contract
State Name
Category
37
10.5
10.5
Sep-2001 Sep-2003
Jun-2004
Assam
EW
37
Jun-2000 Jun-2002
Dec-2003
Assam
EW
Purnea-Forbesganj (BR-2)
57
36.7
36.7
Nov-2005 Apr-2008
Jul-2010
Bihar
EW
Purnea-Forbesganj (BR-1)
57
42.5
42.5
Nov-2005 Apr-2008
Apr-2010
Bihar
EW
31
15.15
15.15
Dec-1999 Mar-2002
May-2008
Bihar
EW
14
85.4
85.4
Feb-2005 Nov-2007
Sep-2008
Gujarat
EW
8B
17
17
Sep-2001 Apr-2003
Oct-2002
Gujarat
EW
14
22.7
22.7
Aug-2001 Aug-2003
Feb-2003
Gujarat
EW
8B
64.5
64.5
Feb-2005 Nov-2007
Jan-2009
Gujarat
EW
10
11
Rajkot - Ribda
Bamnaborr - Rajkot
Abu Road Deesa Section near
Palanpur (EW/1)
8B
8B
15
31
15
31
0
0
Gujarat
Gujarat
EW
EW
14
10
10
Dec-1999 Apr-2001
Apr-2001
Gujarat
EW
13
15
106.2
106.2
Feb-2005 Nov-2007
May-2008
Gujarat
EW
14
8A
71.4
71.4
Feb-2005 Nov-2007
Jul-2009
Gujarat
EW
15
8B
50.5
50.5
Feb-2005 Nov-2007
May-2007
Gujarat
EW
8B
36
36
Sep-2005 Mar-2008
Mar-2008
Gujarat
EW
12
16
17
By MoRT&H
By MoRT&H
25, 76
53
53
Aug-2005 Feb-2008
Oct-2008
Madhya
Pradesh
Madhya
Pradesh
EW
18
25
35
35
Aug-2005 Feb-2008
Nov-2008
19
76
40
40
Oct-2005 Apr-2008
Dec-2008
Rajasthan
EW
20
76
31
31
Jan-2006
Jul-2008
Dec-2009
Rajasthan
EW
21
76
63
63
Oct-2005 Apr-2008
Dec-2008
Rajasthan
EW
22
76
44
44
Nov-2005 May-2008
Mar-2009
Rajasthan
EW
23
24
25
26
27
76
76
76
76
76, 14
43.15
70
65
59.85
43
43.15
70
65
59.85
43
0
0
0
0
0
Oct-2005
Sep-2005
Oct-2005
Oct-2005
Dec-2005
Apr-2008
Mar-2008
Apr-2008
Apr-2008
Jun-2008
Jun-2009
Oct-2008
Dec-2008
Jun-2009
May-2009
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
EW
EW
EW
EW
EW
28
14
76
76
Sep-2006 Mar-2009
May-2009
Rajasthan[42]
/Gujarat[34]
EW
29
25
15.5
15.5
Sep-2001 Apr-2003
Mar-2005
30
25
10.42
10.42
Apr-2000 Oct-2001
Aug-2002
31
25
22.2
22.2
Sep-2001 Nov-2003
Feb-2006
32
25
41
41
Oct-2005 Apr-2008
May-2009
33
31
25
25
Apr-2006 Oct-2008
Oct-2008
West Bengal
EW
34
31
23
23
Dec-1999 Mar-2002
Mar-2004
West Bengal
EW
31
23.85
23.85
Apr-2000
Nov-2005
West Bengal
EW
35
36
37
38
39
Jul-2002
55.74
55.74
Aug-2006 Feb-2009
Mar-2009
12.5
12.5
Dec-1999 Jun-2001
Jan-2003
17
17
Dec-1999 Dec-2001
Apr-2002
41.35
41.35
Mar-2007 Aug-2009
Jan-2011
Uttar
Pradesh
Uttar
Pradesh
Uttar
Pradesh
Uttar
Pradesh[11]/
Madhya
Pradesh[30]
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
EW
EW
EW
EW
EW
NS
NS
NS
NS
40
41
42
43
40.35
40.35
Mar-2007 Aug-2009
Jan-2011
74.65
74.65
Sep-2006 Mar-2009
Nov-2009
9.2
9.2
53.01
53.01
Mar-2007 Mar-2010
Aug-2010
By MoRT&H
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
NS
NS
NS
44
46.162
46.162
Aug-2006 Feb-2009
Feb-2009
45
31
31
May-2007 Nov-2009
Nov-2009
46
54.6
54.6
May-2007 Nov-2009
Aug-2010
47
45.05
45.05
Mar-2007 Aug-2009
Nov-2010
42
42
Mar-2007 Aug-2009
Nov-2010
40
40
Mar-2007 Sep-2009
Dec-2010
42.88
42.88
Mar-2007 Sep-2009
Jan-2011
85.74
85.74
Sep-2006 Mar-2009
Mar-2009
1
1
10
116
10
116
0
0
Jan-2006
1A
17.8
17.8
Oct-2003 Sep-2008
Nov-2010
Jan-2000 Oct-2001
Jul-2001
Karnataka
NS
61.38
61.38
Mar-2007 Mar-2009
Dec-2009
Karnataka
NS
25
25
Sep-2001 Mar-2004
Aug-2008
Karnataka
NS
47
47
17
16.6
17
16.6
0
0
By MoRT&H
Sep-2001 Aug-2003 Jun-2004
Kerala
Kerala
Madhya
Pradesh
Madhya
Pradesh
Madhya
Pradesh
Madhya
Pradesh
NS
NS
Maharashtra
NS
Maharashtra
NS
Mar-2002
Maharashtra
NS
58
59
60
15
15
Sep-2001 Jun-2003
Aug-2004
61
26
43.16
43.16
Apr-2006 Oct-2008
Dec-2010
18
18
Aug-2001 May-2003
Dec-2005
Jul-2000
Dec-2001
Jan-2003
Oct-2005 Apr-2008
Oct-2010
48
49
50
51
52
53
54
55
56
57
62
63
64
Devdhari-Kelapur (NS-61/MH)
30
30
65
Nagpur- Chinchbhuvan
9.2
9.2
25.6
25.6
Jan-2009
Jun-2008
By MoRT&H
By MoRT&H
Andhra
Pradesh
NS
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
Andhra
Pradesh
Haryana
Haryana
Jammu
Kashmir
NS
NS
NS
NS
NS
NS
NS
NS
NS
NS
NS
NS
NS
NS
NS
67
Chinchbguvan-Butibori - Borkhedi
(NS-7)
Phagwara Junction on NH-1
Dec-2005 Dec-2006
Jan-2008
Punjab
NS
68
1A
21.77
21.77
Aug-2001 Aug-2003
Oct-2004
Punjab
NS
69
14.4
14.4
Nov-1999 Feb-2002
Jun-2004
Punjab
NS
70
71
Jalandhar-Ambala
Mania - Dholpur (NS/5)
1
3
160.7
10
160.7
10
0
0
By MoRT&H
Dec-1999 Mar-2001 Mar-2001
Punjab
Rajasthan
NS
NS
72
19.2
19.2
Sep-2001 Aug-2003
Mar-2010
Tamil Nadu
NS
73
33.48
33.48
Jul-2006
Jan-2009
Aug-2009
Tamil Nadu
NS
74
68.125
68.125
Oct-2006 Apr-2009
Nov-2009
Tamil Nadu
NS
75
16.6
16.6
May-2005 Nov-2007
Jan-2010
Tamil Nadu
NS
76
62.5
62.5
Jul-2006
Dec-2008
Jan-2009
Tamil Nadu
NS
77
7.4
7.4
Dec-1999 Sep-2001
Apr-2002
Tamil Nadu
NS
78
0.84
0.84
Jul-1999 Mar-2001
Sep-2002
Tamil Nadu
NS
79
53.025
53.023
Jul-2006
Sep-2009
Tamil Nadu
NS
66
Sep-1999 Mar-2002
Jan-2009
80
81
82
83
84
85
86
87
88
89
41.55
41.55
Aug-2006 Feb-2009
Aug-2009
Tamil Nadu
NS
8.4
8.4
8.4
8.4
Sep-2001 Nov-2002
Apr-2004
Tamil Nadu
NS
Dec-1999 Sep-2001
Jan-2003
Tamil Nadu
NS
9.36
9.36
Aug-1999 Aug-2001
Sep-2002
Tamil Nadu
NS
47
48.51
48.51
Jul-2006
Jan-2009
Aug-2009
Tamil Nadu
NS
43
43
Oct-2005 May-2008
Aug-2009
Tamil Nadu
NS
42.7
42.7
Sep-2005 Mar-2008
Aug-2010
Tamil Nadu
NS
47
53.525
53.525
Jul-2006
Jan-2009
Apr-2010
Tamil Nadu
NS
38.86
38.86
Sep-2005 Apr-2008
Sep-2009
Tamil Nadu
NS
42
42
Sep-2005 Apr-2008
Sep-2009
Tamil Nadu
NS
90
16
16
Dec-1999 Sep-2001
Nov-2001
Uttar
Pradesh
NS
91
17
17
Aug-2001 Aug-2003
Jan-2005
Uttar
Pradesh[7]/R
ajasthan[10]
NS
20
20
Oct-2006 Oct-2008
Dec-2010
Haryana
NS
15
15
Dec-1999 Jun-2001
Nov-2001
Haryana
NS
21.7
21.7
Jan-2006
Jul-2007
Dec-2010
Haryana
NS
8.5
8.5
Nov-2001 Nov-2003
Jan-2007
Delhi
NS
92
93
94
95
Annexure VI
Details of projects of Golden Quadrilateral under implementation
S.No. Stretch
Total
NH No. Length (In
km )
Completed
length (In
Km)
Funded
By
Date of
Start
Date of
completion as
per contract
Date of
anticipated
completion
Total
Project
cost (Rs
Cr.)
33.78
NHAI
Oct-09
Oct-11
Oct-11
241.53
Under Implementation
55.71
50.8
62.64
47.81
57.5
NHAI
NHAI
Jul-06
Dec-08
Nov-08
Dec-10
Apr-11
Mar-11
263.27
Due to persistent non-performance of the contractor, the contract with M/s PCL
STICC was terminated in April 2008. The balance work has since been awarded
the work is in process. 4- laning of 21.20 km is already completed. The balance
work is scheduled for completion October, 2011
Due to non-performance of the original contractor M/s Bhumi Hiways DDBL, the
contract was terminated in January, 2004. Balance work, after settlement of court
cases filed by the terminated contractor, could be awarded only in July, 2006.
The work was targeted for completion in November, 2008. Due to various reasons
including delay in permission by the State Government, for blasting license, Stay
order by the Honble High Court, for quarrying stone aggregate, seizure of crushing
unit of the contractor, as per direction of Honble Orissa High Court, has also
delayed the project. The project is likely to be completed by April, 2011.
228.7
Due to persistent non-performance of the contractor, the contract with M/s ElsamexTWS-SNC was terminated in December 2007. Balance work was awarded to M/s
BBEL- MIPL (JV) in November, 2008. There has been initial procedural delay in the
allotment of quarry by State Government. The contractor initially applied for the
quarry on 28.08.2008 and he has got the permission on 28.07.2009. The work is
scheduled for completion by March, 2011.
Agra-Shikohabad (GTRIP/I-A)
50.83
50.76
WB
Mar-02
Mar-05
Mar-11
367.49
Delay in approval for traffic cum power block and dismantling scheme of existing
two lane Tundla ROB. Due to revised GAD for ROB.
Due to poor performance of Contractor (GIL), the case of declaring nonperformance has been processed.
Haveri - Harihar
56
56
NHAI
Nov-08
Jul-10
Mar-11
196.65
The work due to poor performance of contractor was terminated Jan 2007 and
balance work reawarded in Sept. 2008, the balance work is in progress.
Harihar - Chitradurga
77
77
NHAI
Oct-08
Jun-10
Mar-11
207.56
The work due to poor performance of contractor was terminated Jan 2007 and
balance work reawarded in Sept. 2008, the balance work is in progress
S.No. Stretch
Total
NH No. Length (In
km )
27.15
1.73
Completed
length (In
Km)
Funded
By
Date of
Start
Date of
completion as
per contract
Date of
anticipated
completion
Total
Project
cost (Rs
Cr.)
27.15
NHAI
Jan-01
Jan-04
Mar-11
140.85
0.48
NHAI
TERMINATED
81
The work was awarded to M/s Bhagirtha Engineering Ltd. in January, 2001. Out of 9
bridges, the contractor had completed 8 bridges, but did not completed bridge
(Rupnarayan Bridge). The work on the Roopnarayan Bridge was practically
standstill for more than one year, due to the acute cash flow problems of the
contractor in spite having been given financial assistance by NHAI several times.
Since the work was not progressing and contractor has failed in completing the work
despite financial assistance given to him, the Contract was terminated on
21.8.2008.
Bids for completion of balance work, were invited in December, 08 but no bids were
received. Second time bids were invited from selected Contractors/Organization in
February, 2009. But again no response came from any selected
Contractors/Organization. Third time bid has been invited in May, 2009 but no firms
have turned up for submission of bid. Accordingly, the balance work was included in
6- laning of Dankuni Kharagpur section of NH-6.
Annexure VII
Details of completed projects under Golden Quadrilateral
S.No. Stretch
Total
Funded
NH No. Length (In
By
km )
Date of
Date of Start completion as
per contract
Date of
completion
Total
Project
cost (Rs
Cr.)
83
Completed Projects
78.75
4
4
2
2
2
77
NHAI
NHAI
WB
WB
WB
38.99
7
8
Shikohabad-Etawah (GTRIP/I-B)
10
11
12
Tumkur Bypass
Chitradurga Bypass
13
Jun-09
Sep-10
Dec-10
Apr-07
Sep-08
Dec-10
104
Sep-01
Mar-05
Sep-10
399.745
Mar-02
Mar-05
Sep-10
467.93
Mar-01
Oct-04
Sep-10
372.4
WB
Jun-04
Dec-06
Dec-09
440.93
44.71
WB
Nov-04
May-07
Dec-09
534.39
1.02
WB
Sep-03
Mar-06
Oct-08
91.36
59.02
WB
Sep-05
Sep-07
Sep-08
261.22
30
WB
Mar-02
Mar-05
Jul-08
221.87
72.83
WB
Mar-02
Mar-05
May-08
348.44
Kanpur-Fatehpur (GTRIP/II-B)
51.5
WB
Mar-02
Mar-05
May-08
495.35
13
Etawah Bypass
13.6
NHAI
Feb-06
Feb-08
May-08
132.18
14
Chitradurga - Sira
66.7
ADB
Mar-02
Aug-04
May-08
304
15
72
WB
Mar-01
Jul-04
Apr-08
286
16
11.59
NHAI
Aug-01
May-04
Apr-08
155
17
Hubli - Haveri
64.5
NHAI
Jun-01
Dec-03
Mar-08
260.93
18
60
WB
Sep-01
Mar-05
Jul-07
320.42
19
80
WB
Mar-02
Mar-05
Jul-07
452.71
20
BOT
Sep-02
Apr-06
Jun-07
641
21
Belgaum - Dharwad
62
NHAI
Apr-02
Nov-04
Jun-07
279
22
48
NHAI
Dec-05
Dec-06
May-07
171.97
23
Sikandara-Bhaunti (TNHP/II-A)
62
WB
Feb-01
Aug-04
May-07
323.62
24
60
53.41
NHAI
Mar-01
Dec-03
May-07
272
25
Kanchipuram - Poonamalee
56.4
NHAI
Jul-01
Dec-03
May-07
211
26
54.4
NHAI
May-01
Mar-04
Mar-07
393
27
28.5
NHAI
Nov-01
May-04
Mar-07
97.9
28
60
NHAI
Sep-01
Jun-04
Aug-06
80
29
Belgaum Bypass
18
NHAI
Jun-01
Dec-03
Jun-06
115.9
30
60
65.86
NHAI
Jun-01
Mar-04
Jun-06
332
31
NHAI
Nov-02
Feb-05
Jun-06
146.25
32
52.06
NHAI
May-01
Dec-03
Mar-06
189.68
33
45
WB
Feb-01
Feb-04
Mar-06
230.55
34
66
NHAI
Jun-01
Dec-03
Mar-06
319.21
35
Satara - Kagal
133
BOT
Feb-02
May-04
Mar-06
600
36
46
51
NHAI
Nov-01
May-04
Feb-06
223
37
46
45
NHAI
Oct-01
Apr-04
Jan-06
211
38
52
NHAI
Jun-03
Dec-05
Dec-05
175
39
33
NHAI
Sep-01
Jan-04
Dec-05
143.05
40
41.8
NHAI
Jun-01
Dec-03
Dec-05
233
41
40
WB
Feb-01
Feb-04
Nov-05
242.61
42
72
NHAI
Aug-01
Apr-04
Sep-05
321.41
43
47
Annuity
May-02
Nov-04
Aug-05
231.9
44
29
NHAI
Sep-01
Jan-04
Aug-05
135.11
45
Palsit - Dankuni
65
Annuity
Oct-02
Feb-05
Jul-05
432.4
46
NHAI
Sep-01
Mar-04
Jul-05
79.14
47
Panagarh - Palsit
64.46
Annuity
Jun-02
Dec-04
Jun-05
350
48
74
NHAI
Jun-01
Jan-04
Jun-05
324
49
79.6
ADB
Nov-00
Oct-03
Jun-05
504.6
50
NHAI
Aug-01
Feb-04
May-05
131.33
51
75.5
NHAI
Dec-00
Dec-03
May-05
305.3
52
43.8
NHAI
May-01
Feb-04
May-05
181
18
76
53
60.45
NHAI
Dec-00
Dec-03
Mar-05
Total
Project
cost (Rs
Cr.)
375
54
48.4
NHAI
Oct-01
Apr-04
Mar-05
226.05
55
90.38
BOT
Apr-03
Sep-05
Mar-05
644
56
76
58.18
NHAI
Nov-01
May-04
Mar-05
170
57
46
49
NHAI
Nov-01
May-04
Mar-05
195
58
53
Annuity
May-02
Nov-04
Mar-05
206
59
34.95
NHAI
Jun-01
Dec-03
Mar-05
130.8
60
34.7
NHAI
Dec-01
Jun-04
Mar-05
210
61
2.45
NHAI
Aug-01
Feb-04
Mar-05
136.45
62
Champawati-Vishakhapatnam (AP-3)
46.2
NHAI
Jun-01
Feb-04
Feb-05
200
63
Ankapalli - Tuni
58.95
Annuity
May-02
Nov-04
Jan-05
283.2
64
43
WB
Feb-01
Jun-04
Jan-05
151.7
65
Sira - Tumkur
41.4
ADB
Mar-02
Aug-04
Jan-05
184
66
Maharastra Border-Belgaum
77
Annuity
Jun-02
Dec-04
Oct-04
332
67
Nellore Bypass
17.17
Annuity
Oct-02
Oct-04
Sep-04
143.2
68
164.25
69
70
S.No. Stretch
Total
Funded
NH No. Length (In
By
km )
Date of
Date of Start completion as
per contract
Date of
completion
79
50
NHAI
Nov-01
May-04
Sep-04
NE1
50
SPV
Jun-01
Dec-03
May-04
365
79
66
NHAI
Nov-01
May-04
May-04
202.88
71
81.08
NHAI
Aug-01
Feb-04
Feb-04
323.35
72
Valelapet - Kanchipuram
36.2
NHAI
Sep-01
Mar-04
Jan-04
130
73
62
NHAI
Oct-01
Apr-04
Jan-04
245.91
74
Hosur - Krishnagiri
45.4
NHAI
Jun-01
Jun-04
Jan-04
213
75
76
48
NHAI
Nov-01
May-04
Jan-04
161.2
76
Atul - Kajali
38.6
ADB
Nov-00
Apr-03
Jan-04
174.59
77
79
55.87
NHAI
Nov-01
May-04
Jan-04
182.09
78
79A
36.23
NHAI
Nov-01
May-04
Jan-04
113.5
79
110.52
BOT
Aug-01
Dec-03
Dec-03
621.35
80
54.6
NHAI
Nov-01
May-04
Dec-03
182.29
81
29
NHAI
Nov-01
Apr-04
Dec-03
118.93
82
Tumkur - Neelmangala
32.5
BOT
Jun-02
Nov-03
Dec-03
155
83
35
NHAI
Jul-01
Dec-03
Dec-03
139
84
Kajali - Manor
57.4
ADB
Nov-00
Oct-03
Nov-03
192.71
85
Westerly Diversion
34.25
NHAI
Jun-00
Aug-02
Oct-03
109.38
86
NHAI
Aug-01
Feb-04
Sep-03
71
87
23.78
JBIC
Mar-99
Mar-02
Jan-03
68
88
25
JBIC
Mar-99
Mar-02
Jan-03
60
89
32
JBIC
Mar-99
Mar-02
Jan-03
80
90
Chandikhole - Jagatpur
27.8
JBIC
Feb-00
Feb-03
Jan-03
103.35
91
43.4
SPV
Aug-00
Dec-02
Dec-02
165
92
Hathipali - Hosur
16
NHAI
Dec-99
Aug-02
47
93
10
MSRDC
Dec-01
By MoRT&H
94
2.88
JBIC
May-99
May-02
May-02
58
95
Sira Bypass
5.8
NHAI
Jul-00
Apr-02
Apr-02
19.32
96
NHAI
Jun-00
Mar-02
Mar-02
19
97
Eluru-Vijayawada Package V
72
ADB
Dec-97
Jan-02
Jan-02
134
98
43
ADB
Mar-99
Dec-01
Dec-01
120
99
Raniganj - Panagarh
42
ADB
Mar-99
Nov-01
137
100
80
MSRDC
Nov-01
By MoRT&H
101
Dharwad - Hubli
29
MORTH
By MoRT&H
102
58
MORTH
By MoRT&H
103
Khambakti Ghat
MORTH
By MoRT&H
104
Barakar - Raniganj
33
WB
105
Gurgaon - Kotputli
126
ADB
Mar-99
Mar-01
Mar-01
251
106
14
NHAI
Sep-98
Jan-01
75
107
Jagatpur - Bhubneshwar
28
WB
Jan-01
By MoRT&H
By MoRT&H
S.No. Stretch
Total
Funded
NH No. Length (In
By
km )
Date of
Date of Start completion as
per contract
Date of
completion
Total
Project
cost (Rs
Cr.)
Feb-00
18
By MoRT&H
108
MORTH
109
ROB at Kishangarh
BOT
110
Mathura - Agra
54
JBIC
Feb-00
By MoRT&H
111
MORTH
By MoRT&H
112
Vishakhapatanam - Ankapalli
38
MORTH
By MoRT&H
113
Delhi-Mathura
145
ADB
By MoRT&H
114
Bangalore - Hathipali
33
MORTH
By MoRT&H
115
Vadodara - Surat
152
MORTH
By MoRT&H
116
Delhi-Gurgaon
36
MORTH
By MoRT&H
117
Kotputli - Amer
86
ADB
By MoRT&H
118
Dhaishar - Mumbai
MORTH
By MoRT&H
119
Ahmedabad bypass
15
MORTH
By MoRT&H
120
Neelmangala - Bangalore
30
MORTH
By MoRT&H
Total :
5466.5
Mar-98
21739.2
S.no
1
2
3
4
5
Stretch
NH No
Length
Category
Terminated
Date
18
GQ
Apr-06
BUMI-HIWAY-DDBL
50.8
GQ
Jan-04
59.02
GQ
Jun-04
Completed
YOU ONE-MAHARIA
Bhageeratha Engg. Ltd.& Ashwini
Construction Co.(JV)
48
GQ
Dec-04
Completed
13.6
GQ
Apr-05
UEM-ESSAR(JV)
56
GQ
Jan-07
77
GQ
Jan-07
62.64
GQ
Dec-07
Completed
Balance work reawarded on
Sep-2008
Balance work reawarded in
Sep-2008
Balance work reawarded in
Nov-2008
Contractor
Chitradurga Bypass
Ganjam - Icchapuram (OR-VIII)
(Balance work)
Shikohabad-Etawah
(GTRIP/I-B)
Srikakulam to Champawati
(AP-1)
Etawah Bypass
Haveri - Harihar
Annexure VIII
Harihar - Chitradurga
UEM-ESSAR(JV)
Elsamex - TWS - Shanker
Narayan Shetty (JV)
55.713
GQ
Apr-08
10
11
4
6
13
1.732
GQ
GQ
May-08
Aug-08
21.7
NS
Dec-04
12.9
NS
Dec-04
14
Tumkur Bypass
Bridges Section (WB-III)
Six laning of Panchi Gujran to Kamaspur
(Sonepat) (NS-17/HR)
Eight laning of Haryana/ Delhi Border to
Mukaraba Chowk (NS-18/DL)
Eight laning of Haryana/ Delhi Border to
Mukaraba Chowk (NS-18/DL)
BJCL Brite(JV)
12.9
NS
Jan-09
15
Gundla
Pochampalli
to
Shivarampalli to Thondapalli
Balance Work
23.1
NS
Dec-04
16
Kanniyakumari-Panagudi(NS/32)
30.6
NS
Jan-07
17
1A
40
NS
Sep-08
18
Prakash-Atlanta(JV)
56 A&B
22.85
EW
Mar-03
19
25
16
EW
Oct-11
12
13
Bowenpalli
(NS-23/AP)-
Present Status
S.no
Stretch
Contractor
HSCL-SIPL(JV)
Progressive Construction Ltd.
NH No
Length
Category
Terminated
Date
29
EW
Mar-09
28
41.085
NS-EW
Feb-09
20
Wadner-Devdhari(NS-60/MH)
21
22
Haldia Port
CWHEC-HCIL(JV)
41
53
PC
Apr-07
23
24
Cochin Port
Tuticorin Port
47
7A
10
47.2
PC
PC
May-07
Nov-09
25
SR
PC
Jun-08
26
27
Engineering Projects(I)Ltd.
Devi Enterprises Ltd
SR
7
15
22
PC
NS
Sep-08
May-10
Present Status
Terminated
Terminated. Termination revoked in
Sep, 2010
Balance work awarded on
29/04/2008
Balance work awarded on
28/08/2008
Balance Work reawarded on Feb 10
Terminated Projects merged with one
project under Phase I. The total project
length increased by 6 km ( 30.2 km).
Balance work re-awarded on Jan 2011.
Terminated
Annexure XI
Sl.
No.
Contract Stretch
Districts
Pkg
No.
NH
No.
Length
(km)
{AS-12}
Length
completed
(km)
Awarded
cost
( Rs in
Crore)
Physical
Progress
Achieved
Commencement
(as per contract)
Anticipated
date of
Completion
10
11
12
31C
30.00
18.10.05
31.12.11
18.90
218.38
49.06
{AS-11}
31C
30.00
06.10.05
31.12.11
3.30
199.41
36.37
STATE-ASSAM
Bijni - WB Border
( Km 30.0 -0.00)
Kokrajhar
(BTC)
2
Bongaigaon
& Chirang
(BTC)
{AS-10}
31C
33.00
06.10.05
31.12.11
11.30
248.69
41.43
Nalbari - Bijni
(Km. 983.00 961.50)
Bongaigaon
{AS-9}
31
21.50
03.11.05
31.07.11
18.17
131.23
84.22
Nalbari - Bijni
( Km. 1013.00 983.00)
Bongaigaon
&
Baska(BTC)
{AS-8}
31
30.00
03.11.05
30.11.11
26.65
187.08
84.03
Nalbari - Bijni
(Km. 1040.30 1013.00 )
Barpeta
(AS-7)
31
27.30
Oct-05
Dec-11
7.50
207.165
49.75
Nalbari -Bijni
(Km 1065.00 1040.30 )
Nalbari &
Baska (BTC)
(AS-6)
31
25.00
Nov-05
Dec-11
13.00
182.48
58.25
Guwahati -Nalbari
(km1093 -1065)
Kamrup
(Rural)
(AS-5)
31
28.00
Oct-05
Dec-11
11.50
192.87
60.42
Date of
Sl.
No.
Contract Stretch
Guwahati - Nalbari
(km1121- 1093)
Districts
Pkg
No.
NH
No.
Length
(km)
Kamrup
(Rural)
(AS-4)
Bridge over
10 Brahamputra river
(km 1121-1126)
11
Sonapur Guwahati
( Km 183.00 163.90)
Kamrup
(Metrol)
Length
completed
(km)
Awarded
cost
( Rs in
Crore)
Physical
Progress
Achieved
Commencement
(as per contract)
Anticipated
date of
Completion
10
11
12
31
28.00
Dec-05
Dec-12
6.00
173.63
26.88
(AS-28)
31
5.00
Oct-06
Dec-12
0.00
238.4
38.08
{AS-3)
37
19.00
Sep-05
Dec-11
14.00
166.72
50.40
(AS-20)
37
22.00
Nov-05
March,12
7.50
137.75
43.56
13
Dharamtul Sonapurkm
( Km230.50-205.00
)
Morigaon
{AS-19}
37
25.500
25 Dec 05
(25 Nov 05)
Dec, 11
15.20
173.14
65.1
14
Nagaon- Dharamtul
i/c Nagaon Bypass
(km 262.725 255.00 )
Morigaon &
Nagaon
{AS-02}
37
24.500
26 Dec 05
(25 Nov 05)
Dec, 11
15.10
273.8
67.36
15
Daboka -Nagaon
( km 36.0 - 5.5 )
{AS-18}
37
23.663
16 Dec 05
(16 Nov 05)
April, 11
22.41
238.72
87.08
{AS-17}
36
30.362
26 Dec 05
(25 Nov 05)
Oct 11
24.60
202.18
81.5
{AS-16}
54
24.032
26 Dec 05
(25 Nov 05)
April, 11
24.03
198.65
96.78
{AS-15}
18.00
14.03.08
March,12
11.85
143.97
54.40
20.50
15.10.06
Dec,12
0.00
198.68
15.34
22.90
10.05.06
Dec-13
0.00
179.25
Foreclosed
bids under
evaluation
17
Nagaon
Lumding -Daboka
i/c 4.2km Daboka
Bypass
( km 22.0 - 2.40 )
Lanka - Lumding
18 I/c Lanka Bypass
(km 40.0 -22.00)
Nagaon
19
Maibang -Lumding
(Km 60.5 - 40)
{AS-27}
20
Maibang - Lumding
(Km 83.40 -60.50)
{AS-26}
54E
N.C. Hills
Date of
Sl.
No.
Contract Stretch
Districts
Pkg
No.
NH
No.
Length
(km)
Length
completed
(km)
Awarded
cost
( Rs in
Crore)
Physical
Progress
Achieved
12
Commencement
(as per contract)
Anticipated
date of
Completion
10
11
{AS-25}
27.60
05.11.06
Dec-13
0.00
226.16
{AS-24}
16.00
10.05.06
Dec-13
0.00
171.62
15.57
05.08.06
Oct, 12
8.50
317.11
54E
21
Maibang - Lumding
( Km 111 -83.40 )
N.C. Hills
22
Maibang - Lumding
(Km 127- 111 )
Narimbanglo 23 Maibang
(Km 140.70 - 127)
{AS-23}
{AS-22}
Harangajo -Jatinga
25 ( Km 190.587 165.4 )
27
Silchar -Balachera
(Km275.0-306.54)
(Foreclosed
and reawarded in
Dec, 2010)
(Foreclosed
and reawarded in
Dec, 2010)
N.C. Hills
Balachera to
26 Harangajo section
(Km 244 to 190.58)
54
54
23.38
{AS-21}
54
25.19
Cachar
(21.987 Km)
&
NC
Hills (3.20
Km)
AS-14
54
25.19
Cachar
(AS-1)
54
25.88
30.12.06
30.12.06
Dec, 13
Dec, 13
0.00
0.00
241.53
253.09
47.06
Foreclosed
under process
of re-award
bids to be
received on
14.3.2011
Foreclosed
under process
of re-award
bids to be
received on
14.3.2011
17.09.04
June, 11
13.00
115.86
60.50
Annexure X
SUMMARY STATUS OF PROJECTS UNDERTAKEN BY NHAI FOR MAJOR PORTS CONNECTIVITY
Sl.
No.
Name of Work
Length
(km)
1.
West Bengal
Haldia
Port
Connectivity
(NH41) from Kolaghat to
Haldia
in
West
Bengal
52.2
(NH41)
6.125
HPL Link
Rd
Orissa
Paradip
Port
Connectivity
(NH5A)
from
Chandikhole
to
Paradip in Orissa
Andhra Pradesh
Visakhapatnam
Port
Connectivity
(Port
Road)
in
Andhra Pradesh
Tamil Nadu
Chennai-Ennore
Port Connectivity in
Tamil Nadu
Phase-II
: 9 km
(TPP Road)
77
2.
3.
4.
Phase-III-15 km
(MoRR + IRR + 1.6
km EE + 3 groynes
Phase-IV : 6 km
Balance EE
Project
Cost (Rs.
in Crore)
273
(revised Rs.
522 crore)
Contractor/
Supervision
Consultant
M/s
Dineshchandra /
Date of
Commen
cement
Sept, 08
Scheduled
/Likely
Completion
Sept,
2010/May
2011
Cum. %
Progress till
Feb.11
66.62
Feb., 04
Feb 07/
May2010
Completed
June, 02
Dec., 04
M/s CES
500
Revised
M/s HCC /
M/s LASA
12.5
116
M/s M. Venkata
Rao /
M/s LASA
Phase-I :
Sea
Protection
Work
9 km
Phase-I
24.6
39.2
15 km
Phase-III :
76.76
6 km
Balance for
award
Present status
June, 03
June, 05
M/s ECCI /
TNRDC
May, 06
Contract
terminated
11
M/s EPIL /
TNRDC
Sept., 07
Contract
terminated
Nil
Sl.
No.
Name of Work
5.
6.
7.
Length
(km)
Project
Cost (Rs.
in Crore)
Contractor/
Supervision
Consultant
19
1655
(1345+310)
M/s
ChennaiElevated
Tollway Co.Ltd.
Ennore-Thatchur
New Four Lane
Road from Northern
gate of Ennore Port
to Thachur (NH-5)
Under NHDP Phase
VII Through PPP on
DBFOT Toll Basis
21.5
278.54
Tuticorin
Port
Connectivity Project
on NH 7A
in
Tamilnadu
Kerala
Cochin
Port
Connectivity to ICTT,
Vallarpadam, Cochin
47.2
231.2
17.2
571
4-laning of NH-47
from km 348.4 to km
358.75 Cochin.
10.40
193
Karnataka
New Mangalore Port
Connectivity Project
on NH 17, 13 & 48 in
Karnataka
37.5
196.5
Date
of
Commenc
ement
Scheduled
/Likely
Completion
Cum. %
Progress till
Feb.11
April, 2010
April, 2012
16
Suncom-Soma
(JV) / LASA
Sept 2007
Feb., 2010 /
Dec 2012
100
RDS-CVCC (JV)
/Dalal MottMac
Donald
Nov 2008
IRCON /
SNC-SAI (JV)
June 2005
Apr/Dec,
2010
Dec2007/
Mar 2011
100
83
Present status
Sl.
No
.
Name of Work
Length
(km)
Project
Cost (Rs.
in Crore)
Contractor/
Supervision
Consultant
Date of
Commen
cement
Scheduled
/Likely
Completion
10
11
Goa
Mormugao
Port
Connectivity on NH
17 B in Goa
18.3
145
KMC/ Aarvee
Oct 2009
Oct 2011
Maharashtra
JNPT
Package-I:
Four laning of NH 4B
& NH 4
30
159
Feb 2002
July, 2004
JNPT
Package-II:
Four laning of SH 54
&
Aamra
Marg
including
Panvel
Creek Bridge)
14.4
143
Jog-Shirke
STUP
Nov 2004
May, 2007
279
Implementation of the interchange through SPV at a cost of Rs. 279 crore was approved by NHAI Board in its
meeting held on 25.03.2008. DPR has been prepared by M/S Aarvee Associates / GAD approval of ROB from
Railway is awaited.
JNPT Package-III:
Construction of two
interchanges
at
Aamra Marg with
NH- 4B near Gavan
Phata and NH- 4B
with SH-54 Near
JNPT
(JV)/
Cum. %
Progress till
Feb.11
Present status
Substantially
Completed
in Dec 2008
As decided in Mar 2010 SPV Board meeting, a Feasibility Study and Detailed Project Report for 6/8 laning of
NH-4B, NH-4, SH-54 and Amra Marg on boundaries of proposed Navi Mumbai International Airport in the State of
Maharashtra to be executed as BOT (Toll) on DBFOT Pattern. M/s STUP Consultant who are the feasibility cum
DPR Consultant to give the Draft DPR by 15 Mar 2011.
Chairman
MEMBERS
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
1.
2.
3.
Joint Secretary
Director
Deputy Secretary
WITNESSES
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
1.
2.
3.
4.
5.
6.
Secretary (RT&H)
DG(RD) & SS
AS&FA
ADG
Joint Secretary
Joint Secretary
2/-
-2-
7.
8.
9.
10.
Chief Engineer
Chief Engineer
CCA
Director
Chairman, NHAI
Member (A)
Member (F)
Member (P)
Member (P)
CGM
CGM
2.
At the outset, the Chairman welcomed the Members of the Committee and
representatives of Ministry of Road Transport and Highways to the sitting of the Committee.
3.
Thereafter, the Secretary, Ministry of Road Transport and Highways briefed the
4.
The Committee sat on Tuesday, the 30th March, 2010 from 1500 hrs. to 1800 hrs.
PRESENT
Shri Francisco Sardinha Chairman
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
MEMBERS
Shri Sanjay Singh Chauhan
Shri T.K.S. Elangovan
Dr. Sanjay Jaiswal
Shri Ramesh Jigajinagi
Shri P. Karunakaran
Shri Mohinder Singh Kaypee
Shri M. Krishnaswamy
Shri Prabodh Panda
Shri M. Sreenivasulu Reddy
Shri Madan Lal Sharma
Shri Brij Bhushan Sharan Singh
Dr. Raghuvansh Prasad Sigh
Shri Sushil Kumar Singh
Shri Lalji Tandon
Shri Manish Tewari
Shri K.C. Venugopal
SECRETARIAT
1
2
Joint Secretary
Director
WITNESSES
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
1.
2.
3.
4.
5.
Secretary (RT&H)
DG (RD) & SS
Addl. Secy. & FA
ADG
Joint Secretary
Chairman
Member (A)
8.
9.
10.
11.
12.
13.
14.
Member (T)
Member (P)
Member (T)
Member (F)
CGM (Coord)
CGM (Coord)
CGM
2.
***
***
***
***
***
3.
***
***
***
***
***
4.
Thereafter, the representatives of Ministry of Road Transport & Highways were called in.
5.
The representatives of the Ministry gave oral evidence before the Committee on the
6.
The Committee sat on Wednesday, the 7th April, 2010 from 1500 hrs. to 1800 hrs.
PRESENT
Shri Francisco Sardinha Chairman
2
3
4
5
6
7
8
9
10
11
12
13
14
15
MEMBERS
Shri Sanjay Singh Chauhan
Shri T.K.S. Elangovan
Shri Mohinder Singh Kaypee
Shri M. Krishnaswamy
Smt. Ranee Narah
Shri Prabodh Panda
Shri C. Rajendran
Shri Jagdish Singh Rana
Shri M. Sreenivasulu Reddy
Shri S. Semmalai
Shri Brij Bhushan Sharan Singh
Shri Sushil Kumar Singh
Shri Lalji Tandon
Shri K.C. Venugopal
SECRETARIAT
1
2
3.
Joint Secretary
Director
Under Secretary
WITNESSES
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
1.
2.
3.
4.
5.
6.
Secretary (RT&H)
DG (RD) & SS
Addl. Secy. & FA
ADG
Pr. CCA
Joint Secretary
Chairman
Member (T)
Member (P)
Member (T)
Member (F)
CGM (Coord)
CGM
GM (P&IS)
Manager (P&IS)
At the outset, the Chairman welcomed the Members of the Committee and
representatives of Ministry of Road Transport and Highways to the sitting of the Committee.
3.
Thereafter, the
4.
Shri M. Krishnaswamy
10
11
Shri S. Semmalai
12
13
14
15
16
SECRETARIAT
1.
Additional Director
2.
Deputy Secretary
WITNESSES
Ministry of Road Transport & Highways
1. Shri R.S. Gujral
Secretary
AS&FA
Pr. CCA
ADG
5. Shri S.K.Dash
Joint Secretary
Page 1 of 2
Joint Secretary
Joint Secretary
Director (RT)
2.
1.
Chairman, NHAI
2.
Member (Admn.)
3.
Dr. J.N.Singh
Member (Finance)
4.
Member (Project)
5.
Member (Tech.)
6.
CGM (Tech)
7.
CGM (Tech)
8.
Shri V. K. Sharma
CGM (LA)
At the outset, the Chairman welcomed the Members of the Committee and representatives
of the Ministry of Road Transport and Highways to the sitting of the Committee.
3.
Thereafter, the Committee took oral evidence of the representatives of the Ministry. The
Members of the Committee sought clarification on various issues relating to the subject to which
the representatives of the Ministry responded. The Honble Chairman requested the Secretary,
Ministry of Road Transport and Highways to furnish replies in writing to the questions for which
answers were not readily available during the course of evidence.
4.
The Committee decided to hold the next sitting on 1st October, 2010.
5.
Page 2 of 2
2.
3.
4.
5.
6.
7.
8.
Shri M. Krishnaswamy
9.
10.
11.
12.
13.
14.
15.
16.
1.
Shri P. K. Grover
Joint Secretary
2.
Deputy Secretary
WITNESSES
Ministry of Road Transport & Highways
1.
Secretary &
Chairman, NHAI
2.
AS & FA
3.
DG (RD)
4.
JS (T&G)
Page 1 of 2
5.
JS (Highways)
6.
JS (LA&C)
7.
CE(PIC)
8.
CE (P-1)
9.
CE (P-7)
10.
SE (PIC)
11.
SE (Plg.)
12.
Shri P. Srinivas
SE (Mon)
2.
1.
Member (Admn.)
2.
Dr. J.N.Singh
Member (Finance)
3.
Member (Project)
4.
Member (Tech.)
At the outset, the Honble Chairman welcomed the Members of the Committee to the sitting
of the Committee.
3.
4.
***
***
***
***
ushered in.
5.
After formal welcome by the Honble Chairman, the Committee took oral evidence of the
representatives of the Ministry on the subject National Highways Development Project including
implementation of Golden Quadrilateral. The Members of the Committee sought clarification on
various issues relating to the subject to which the representatives of the Ministry responded. The
Honble Chairman requested the Secretary, Ministry of Road Transport and Highways to furnish
replies in writing to the questions for which answers were not readily available during the course of
evidence.
6.
Page 2 of 2
1.
Shri P. K. Grover
2.
Additional Director
3.
Deputy Secretary
Joint Secretary
WITNESSES
***
***
***
***
2.
At the outset, the Chairman welcomed the Members to the sitting of the Committee.
3.
Thereafter the Committee took up for consideration the draft Report on the subject National
4.
The Committee adopted the draft Report with minor modifications suggested by the
5.
The Committee then authorized the Chairman to finalize the Report in the light of
modifications suggested and present the same to the Honble Speaker under Direction 71A of the
Direction by the Speaker, Lok Sabha. The Committee also decided to present the Report to
Parliament in the coming Monsoon session.
6.
***
***
***
***
7.
***
***
***
***
8.
***
***
***
***